US20220163602A1 - System and method for electric meter outage time detection - Google Patents

System and method for electric meter outage time detection Download PDF

Info

Publication number
US20220163602A1
US20220163602A1 US17/667,262 US202217667262A US2022163602A1 US 20220163602 A1 US20220163602 A1 US 20220163602A1 US 202217667262 A US202217667262 A US 202217667262A US 2022163602 A1 US2022163602 A1 US 2022163602A1
Authority
US
United States
Prior art keywords
power
electric meter
power interruption
duration
control device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US17/667,262
Inventor
David Stenberg
Robert Monroe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Landis and Gyr LLC
Original Assignee
Landis and Gyr LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Landis and Gyr LLC filed Critical Landis and Gyr LLC
Priority to US17/667,262 priority Critical patent/US20220163602A1/en
Assigned to LANDIS+GYR LLC reassignment LANDIS+GYR LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: MONROE, ROBERT, STENBERG, DAVID
Publication of US20220163602A1 publication Critical patent/US20220163602A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/40Testing power supplies
    • G01R31/42AC power supplies
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters
    • G01R22/06Arrangements for measuring time integral of electric power or current, e.g. electricity meters by electronic methods
    • G01R22/061Details of electronic electricity meters
    • G01R22/063Details of electronic electricity meters related to remote communication
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters
    • G01R22/06Arrangements for measuring time integral of electric power or current, e.g. electricity meters by electronic methods
    • G01R22/061Details of electronic electricity meters
    • G01R22/068Arrangements for indicating or signaling faults
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/12Measuring rate of change
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/175Indicating the instants of passage of current or voltage through a given value, e.g. passage through zero
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • G01R31/54Testing for continuity

Definitions

  • This disclosure relates to electric meters generally and, more particularly, to electric meters that can measure the length of time of electrical power interruptions in power lines that the electric meter monitors.
  • Electricity meters are devices that measure and/or meter aspects of energy provided to a load.
  • the load may be a residence, business, or even part of a larger electricity distribution system.
  • Commonly available meters include electromechanical meters and electronic meters.
  • Electromechanical meters employ a rotating disk that rotates in response to electric and magnetic fields induced by the electricity passing to the load. As is known in the art, the disk rotation speed is a function of the amount of electricity delivered to the load. Mechanical counters accumulate the number of disk rotations, which is indicative of energy consumed by the load.
  • an electromechanical meter can employ processing circuitry to perform additional operations with the consumption information provided by the rotating disk.
  • Electronic meters typically employ processing circuitry instead of the rotating disk and mechanical counters.
  • sensors within the meter detect the voltage and current that is delivered to the load.
  • Circuitry within the meter converts the sensed voltage and current into digital values.
  • Processing circuitry then employs digital signal processing to calculate consumed energy, among other things, from the digital values.
  • Electronic meters provide greater flexibility in the types of energy consumption information that they may calculate, track, and store.
  • the electric lines that an electric meter monitors may experience interruptions in providing power due to power outages that occur in a power grid.
  • electrical utilities are required to provide aggregate information about an average amount of time that different portions of a power grid experience an interruption to electrical power. This measurement can refer to an average amount of time that the power grid experiences a power loss during a predetermined time span, such as a monthly or annual time span, where of course in many instances only a portion of the power grid experiences an interruption at any one time.
  • SAIDI System Average Interruption Duration Index
  • N i refers to a total number of customers at a particular location i
  • U i is the total duration of power interruptions at the location i
  • N T is the total number of customer locations.
  • the SAIDI measurement is generally calculated over a one year period to provide an average duration of power interruptions for a power grid that provides power to multiple locations and customers.
  • interruptions to electrical power delivery are monitored from a centralized system, but while such monitoring can identify large-scale power outages effectively, the monitoring process may not identify smaller-scale power outages that have shorter durations accurately. Consequently, improvements to systems that monitor the consumption of electrical power to increase the accuracy of measuring periods of power interruption would be beneficial.
  • a method of identifying power interruptions includes receiving, with an external monitoring system, a load profile from an electric meter that includes at least one of an accumulated frequency measurement and an accumulated number of zero crossing events that the electric meter records in an AC power signal during a predetermined monitoring period, and identifying, with a processor in the external monitoring system, a total duration of at least one power interruption during the predetermined monitoring period based on at least one of a deviation of the accumulated frequency measurement in the load profile from a predetermined accumulated frequency value or a deviation of the accumulated number of zero crossing events in the load profile from a predetermined number of zero crossing events during the predetermined monitoring period.
  • a method of operating an electric meter to identify power interruptions includes operating, with a battery in the electric meter, at least one component in the electric meter in response to a first power interruption in a power line connected to the electric meter, identifying, with a control device in the electric meter, a duration of the first power interruption based on a duration of a time on battery while operating with the battery in the electric meter after the first power interruption, and transmitting, with an output device in the electric meter, a message including a total duration of power interruptions including the duration of the first power interruption to an external monitoring system.
  • a system for monitoring power interruptions includes an electric meter.
  • the electric meter includes a voltage sensor, an output device, and a control device operatively connected to the voltage sensor and the output device.
  • the control device is configured to monitor an AC power signal in a power line that is connected to the electric meter using the voltage sensor, identify at least one of an accumulated frequency measurement of the AC power signal during a predetermined monitoring period or an accumulated number of zero crossing events in the AC power signal during the predetermined monitoring period, and transmit a load profile that includes at least one of the accumulated frequency measurement and the accumulated number of zero crossing events with the output device to an external monitoring system to enable the external monitoring system to identify a total duration of at least one power interruption in the AC power signal that occurs during the predetermined monitoring period.
  • FIG. 1 is a schematic diagram of an electric meter that is configured to measure power interruptions.
  • FIG. 2 is a block diagram of a process that the electric meter 100 performs to measure the duration of power interruptions.
  • FIG. 3 is a block diagram of another process that the electric meter 100 performs to measure the duration of power interruptions.
  • FIG. 4 is a diagram depicting a voltage waveform of an alternating current (AC) power signal that the electric meter of FIG. 1 monitors during a power interruption.
  • AC alternating current
  • the term “metrology circuit” refers to any suitable circuit that detects, measures, and determines one or more electricity and/or electrical energy consumption values based on energy flowing between terminals of an electric meter that are connected in-line with a power line between an electric power source and the load that receives the electric power.
  • a power grid or other generation source is connected to one set of terminals and the load that receives the electrical power is connected to the other set of terminals.
  • the electric power in the power line flows through the electric meter and the metrology circuit measures various aspects of the electrical signal including, but not necessarily limited to, voltage and current.
  • power outage and “power interruption” are used interchangeably and refer to an event in which the normal supply of electric power through one or more power lines that are connected to an electric meter temporarily ceases. Power outage and interruption events are also referred to as “blackouts” in which all electrical power ceases to flow through the power lines or the level of electrical power drops to a level that prevents normal operation of a load and the electric meter.
  • FIG. 1 depicts an electric meter 100 that is configured to measure the duration of power interruptions in the supply of electricity through one or more power lines that are connected to the electric meter 100 and to transmit load profile data to an external monitoring system 1000 via a network 175 .
  • the electric meter 100 includes a meter base 120 and a metrology circuit 150 that are supported by and at least partially contained within a housing of the electric meter.
  • the meter base 120 includes two pairs of terminals 124 A/ 128 A and 124 B/ 128 B that are electrically connected together by conductors 126 A and 126 B, respectively.
  • each of the terminals 124 A, 124 B, 128 A, and 128 B is formed from an electrically conductive member, often referred to as a “blade” or a “stab”, which extends from the housing of the electric meter to engage a socket that is connected to a power line (socket and power line not shown).
  • Each of the terminal pairs 124 A/ 128 A and 124 B/ 128 B is configured to connect in-line with a conductor in a powerline where all of the power that passes through the power line from an energy source to a load passes through the terminal pairs 124 A/ 128 A and 124 B/ 128 B to a load.
  • the terminal pairs 124 A/ 128 A and 124 B/ 128 B and the electrical conductors 126 A and 126 B effectively become part of the power line connected between the generation source and the load when the electric meter 100 is connected to the socket. While FIG.
  • FIG. 1 depicts two pairs of terminals with two conductors that are configured to be connected in-line with a power line that includes two conductors (and that often includes a neutral conductor not shown in the drawings), alternative embodiments optionally include only one pair of terminals for a single conductor or additional pairs of terminals with additional conductors to enable monitoring of power lines that include more than two conducting lines, such as three-phase power lines.
  • the meter base 120 includes inductive coils 132 A and 132 B that are inductively coupled to the electrical conductors 126 A and 126 B, respectively. As described in further detail below, the inductive coils 132 A and 132 B are electrically connected to electrical current sensors 154 A and 154 B in the metrology circuit 150 .
  • the alternating current (AC) power signals in the electrical conductors 126 A and 126 B induce a current in the inductive coils 132 A and 132 B, respectively, that the metrology circuit 150 uses to monitor electrical current levels in the power line.
  • AC alternating current
  • the inductive coils 132 A and 132 B are also referred to as “coil transformers” since in some embodiments the inductive coils 132 A and 132 B form one set of coils in a current transformer in which a second set of coils produce a current measurement signal. While FIG. 1 depicts the coils 132 A/ 132 B and current sensors 154 A/ 154 B for illustrative purposes, other embodiments may employ different current sensing devices that are otherwise known to the art.
  • the metrology circuit 150 include current sensors 154 A/ 154 B, and voltage sensors 158 .
  • the metrology circuit 150 further includes an analog-to-digital converter 168 , a digital control device 180 , network communication device 184 , and in-meter control interface 188 .
  • the metrology circuit 150 receives electrical power for operation from the power line via the terminal pairs 124 A/ 128 A and 124 B/ 128 B that are connected to a power supply 196 (connections omitted for clarity).
  • the power supply 196 is, for example, a switched capacitor power supply or other suitable conversion circuit that produces direct current (DC) electrical output power from the AC power received at the terminals to provide electrical the components in the electric meter 100 .
  • the power supply 196 provides electrical power to the components in the metrology circuit 150 and the meter base 120 that require electrical power during operation of the electric meter 100 .
  • the power supply 196 further includes a battery 198 that provides electrical power to operate the control device 180 during a power interruption to the normal AC voltage and current flow through the power lines that are connected to the electric meter 100 .
  • a capacitor or other energy storage device in the electric meter 100 supplies electrical power to the control device 180 and optionally other components in the electric meter 100 during a power interruption.
  • the current sensors 154 A/ 154 B are each connected to one of the inductive coils 132 A and 132 B, respectively, to enable the current sensors to monitor the levels of electrical current in the electrical conductors 126 A and 126 B, respectively.
  • the current sensors 154 A and 154 B each includes a second set of coils that are coupled to the corresponding inductive coils 132 A or 132 B in a coil transformer arrangement.
  • the coils in the current sensors 154 A and 154 B generate electrical currents that correspond to the current levels in the electrical conductors 126 A and 126 B, although at greatly reduced amplitudes to enable measurement of the current in an efficient manner and with the current sensors having galvanic isolation from the much higher current levels of the electrical conductors 126 A and 126 B.
  • the current sensors 154 A and 154 B generate analog current measurement signals that are supplied to the ADC 168 to be provided as digital current level signals to the control device 180 , although in an analog electrical meter an analog control circuit may receive the analog current measurement signals directly.
  • the voltage sensor 158 is connected to both of the electrical conductors 126 A and 126 B.
  • the voltage sensor 158 is configured to generate an analog voltage measurement signal having a waveform representative of the voltage provided to the load through the power line.
  • the outputs of the voltage sensor 158 is connected to the ADC 168 to enable the control device 180 to receive digitized representations of the measured voltage levels from the voltage sensors 158 .
  • the voltage sensor 158 includes a voltage divider circuit to bring the measured voltage waveform to a magnitude that is suitable for the ADC 168 .
  • the voltage sensor 158 may alternatively take other known forms.
  • the control device 180 is a digital logic device that includes, for example, one or more microprocessors, microcontrollers, field programmable gate arrays (FPGAs), digital signal processors (DSPs), programmable logic controllers (PLCs), application specific integrated circuits (ASICs), and the like.
  • the control device 180 also includes or is operatively connected to a real time clock (RTC) 190 and a memory 192 .
  • the RTC 190 tracks the time at which the meter 100 records samples of input sensor data from the current sensors 154 A/ 154 B and voltage sensor 158 .
  • the control device 180 also uses the RTC 190 to measure the duration of “time on battery” events that correspond to the duration of power interruptions in some embodiments.
  • the memory 192 includes one or more memory devices that store programmed software or firmware instructions that the control device 180 executes to operate the electric meter 100 in conjunction with the other components of the electric meter.
  • the memory 192 also stores “load profile” records that the electric meter generates during a predetermined monitoring period, which is typically on the order of one minute to one hour in duration although other embodiments may use longer or shorter monitoring periods.
  • the load profile typically includes multiple data fields in the load profile that are referred to as “channels” that include, for example, measurements of the accumulated energy consumption of loads that are attached to the power line, an accumulation of frequency measurements in the voltage of the AC power signal, an accumulation of zero crossing events in the voltage of the AC power signal, and other information that the electric meter 100 records and reports to a centralized monitoring system.
  • channels include, for example, measurements of the accumulated energy consumption of loads that are attached to the power line, an accumulation of frequency measurements in the voltage of the AC power signal, an accumulation of zero crossing events in the voltage of the AC power signal, and other information that the electric meter 100 records and reports to a centralized monitoring system.
  • the electric meter 100 if the electric meter 100 experiences a power interruption during a monitoring period then the electric meter 100 sets a value in the load profile indicating that monitoring only occurred for a partial monitoring period instead of for the full predetermined monitoring period.
  • the memory 192 is implemented using at least one non-volatile memory device such as a NAND or NOR memory device or other suitable solid-state memory, and in some embodiment the memory 192 includes a volatile memory device such as random access memory (RAM).
  • the control circuit 180 also performs metrology routines, display routines, communication routines, that are commonly associated with the operation of electric meters. As depicted in FIG. 1 , the control device 180 receives input data from the current sensors 154 A and 154 B and the voltage sensor 158 , either directly or indirectly via the ADC 168 .
  • the control device 180 is operatively connected to network communication device 184 and the in-meter interface 188 in addition to being connected to receive input data from the current sensors 154 A/ 154 B and the voltage sensors 158 .
  • the network communication device 184 and the in-meter interface are both examples of output devices.
  • the network communication device 184 is, for example, an analog modem or digital subscriber line (DSL) device that couples to a telephone network, an Ethernet transceiver that transmits data over a wired network, a local serial bus output such as RS-232 or Universal Serial Bus (USB), or either or both of a wireless local area network (WLAN) or wide area network (WWAN) transceiver that transmits metrology data to the external monitoring system 1000 .
  • DSL digital subscriber line
  • USB Universal Serial Bus
  • the in-meter interface 188 provides a visual and in some instances audible output device that enables manual meter reading and manual inspection of the electric meter to retrieve power consumption and power interruption data.
  • in-meter interfaces include mechanical gauges, indicator lights, LCD or LED display screens, alarm bells or speakers and the like.
  • the in-meter interface optionally includes control inputs that enable an operator to send commands to the control device 180 while physically present at the electric meter. While the metrology circuit 150 includes both the network communication device 184 and the in-meter interface 188 , some embodiments of electric meters that measure the durations of power interruptions only include a network communication device 184 or an in-meter interface 188 , but not both elements.
  • some electric meters have no need to communicate with a remote system via a data network and only include the in-meter interface 188 , while other electric meters rely exclusively on the network communication device 184 to transmit the meter data and do not include the in-meter interface 188 .
  • the external monitoring system 1000 includes a processor 1004 that is operatively connected to a memory 1008 and a network communication device 1012 .
  • the processor 1004 is a central processing unit (CPU) or other suitable digital logic device that is configured to process load profile information that the external monitoring system 1000 receives using the network communication device 1012 to communicate with the corresponding network communication device 184 in the electric meter 100 via the network 175 .
  • the memory 1008 stores programmed instructions for the processor 1004 , load profile data that are received from the electric meter 100 , and stores records of the accumulate duration of power interruptions that may occur in the electric meter 100 over a series of predetermined monitoring periods. While not depicted in further detail in FIG. 1 , in some configurations the external monitoring system 1000 receives and processes load profile data from a plurality of electric meters with the same or similar configuration as the electric meter 100 .
  • the external monitoring system 1000 includes, for example, a head end unit that monitors the electric meter 100 and in some embodiments other electric meters that are not expressly shown in FIG. 1 .
  • Electric utilities, site owners, or other entities operate the external monitoring system 1000 to monitor power interruptions in the electric meter 100 to calculate SAIDI and monitor power interruptions.
  • the external monitoring system 1000 periodically receives a load profile from the electric meter 100 that includes channels for either or both of the accumulated frequency measurement and accumulated zero crossing measurement.
  • the external monitoring system 1000 determines the duration of one or more power interruptions that may occur during a predetermined monitoring period based on the accumulated frequency measurement and accumulated zero crossing channels.
  • the external monitoring system 1000 transmits command messages to the control device 180 in the electric meter 100 via the network communication device 184 .
  • the electric meter 100 transmits load profile data including the channels that identify either or both of the accumulated frequency counts and accumulated zero crossing counts to the external monitoring system 1000 via the network 175 .
  • the external monitoring system 1000 identifies the duration of power interruptions that the electric meter 100 experiences during one or more predetermined monitoring periods to enable fine-grained tracking of the duration of power interruptions to measure SAIDI and to perform other monitoring operations in an electric power distribution system.
  • the control device 180 in the electric meter optionally measures the durations of power interruptions and stores records of the total duration of any power interruptions that occur during a predetermined monitoring period (e.g. a 15 minute period).
  • the control device 180 also generates transmits reports of the total duration of power interruptions that occur over one or more monitoring periods, such as a total duration of power interruptions over the course of an hour, day, week, month, or year, to a monitoring service using the network communication device 184 .
  • the operation of the electric meter 100 to track the duration of power interruptions is described in further detail below.
  • FIG. 2 depicts a process 200 for operation of an electric meter to measure, record, and report the durations of power interruptions.
  • a reference to the process 200 performing a function or action refers to the operation of a digital processing device, such as a control device in a meter, a processor in an external monitoring system, or a combination thereof, to execute stored program instructions to perform the function or action in association with other components in an electric meter.
  • the process 200 is described in more detail below in conjunction with the electric meter 100 of FIG. 1 and the graph of FIG. 4 .
  • the control device 180 monitors the voltage of the AC power signal that is supplied from a power line using the voltage sensors 158 to record measurements of the accumulated value of frequency measurements, the accumulated value of a total number of zero crossing events, or both, during the predetermined monitoring period (block 204 ).
  • the voltage of the AC power signal is supplied from a power line and passes between the terminal pairs 124 A/ 128 A and 124 B/ 128 B in the electric meter 100 during the predetermined monitoring period.
  • the ADC 168 generates digital samples of the voltage values from the voltage sensors 158 at a sampling frequency that exceeds the expected frequency (e.g.
  • the ADC 168 generates digital voltage samples at rate in a range of, for example, 1 KHz to 20 KHz to collect multiple samples in each cycle of the sinusoidal AC power signal.
  • the predetermined monitoring period is any suitable length of time, such as a 15 minute period used in the illustrative embodiment of FIG. 2 , which enables the electric meter 100 to produce an average value of the measured AC signal frequency or total number of zero crossings in the AC power signal.
  • the control device 180 identifies the time difference T between successive positive peaks or negative peaks in the voltage waveform of the AC power signal to measure the frequency of the AC power signal.
  • Each peak occurs when a series of samples of data from the ADC for the voltage of the AC power signal reach a maximum absolute value (positive or negative) and begin to return to zero, and the control device 180 optionally interpolates between data samples to identify the time of each peak with greater accuracy.
  • the control device 180 identifies the frequency of each cycle as T ⁇ 1 and the measured frequency of the signal is an averaged value for multiple cycles that are measured over the predetermined monitoring period.
  • the electric meter 100 generates records of the accumulated frequency measurements of the AC power signal as part of a load profile during a predetermined monitoring period and reports the frequency measurement information to an external monitoring system at regular intervals as one channel in the load profile that also includes additional data collected by the electric meter 100 .
  • FIG. 4 depicts a graph 400 of the electrical voltage levels of an example AC power signal over time with time periods 432 , 436 , and 452 that correspond to the expected frequency of the sinusoidal AC power signal at a predetermined frequency, such as 50 Hz or 60 Hz.
  • the meter 100 measures the same periods based on the time between troughs (negative peaks) in each cycle of the AC power signal.
  • the frequency of an AC power signal in a large power grid is generally stable and experiences far smaller variations during normal operation than the voltage levels of the AC signal.
  • the control device 180 measures the frequency of the AC power signal at a predetermined rate (e.g.
  • FIG. 4 also depicts a power interruption 444 in the AC power signal in which there are no additional peaks.
  • the control device 180 does not record any frequency measurements during the power interruption 444 and in most embodiments is not activated during the power interruption 444 .
  • the electric meter 100 restarts after the power interruption and the controller 180 continues to record additional frequency measurements, although the total accumulated value of all the frequency measurements during the predetermined monitoring period is lower than expected due to the power interruption. While FIG. 4 depicts a single interruption 444 , in some situations the electric meter 100 experiences multiple power interruptions during a single monitoring period, and the embodiments described herein can identify the accumulated duration of one or more power interruptions.
  • the control device 180 records a count of the accumulated number of zero crossing events that occur in the AC power signal. As depicted in FIG. 4 , the zero crossing events occur when the voltage in the AC power signal transitions from a positive to negative or negative to positive voltage, and the control device 180 optionally interpolates between data samples to identify the time of each zero crossing with greater accuracy.
  • the electric meter 100 generates records of the measured zero crossing events of the AC power signal as part of a load profile during a predetermined monitoring period and reports the accumulated zero crossing event measurement information to the external monitoring system at regular intervals as one channel the load profile that also includes additional data collected by the electric meter 100 .
  • FIG. 4 depicts the zero crossings 404 A/ 404 B, 408 A/ 408 B, 412 A/ 412 B, and 416 A/ 416 B that occur during different cycles of the AC power signal, where each cycle of the AC power signal includes two zero crossings.
  • the control device 180 identifies each zero crossing event based on a transition of the measured voltage values from a positive value to a negative value or from a negative value to a positive value in the digital sensor data samples that the control device 180 receives from the ADC 168 .
  • the control device 180 records an accumulated value of the total number of measured zero crossing events that occur during each predetermined monitoring period. As depicted in FIG.
  • the control device 180 records a reduced number of zero crossings compared to a predetermined expected value based on the predetermined frequency of the AC power signal when power interruptions occur.
  • the process 200 continues as the electric meter 100 transmits the recorded load profile that includes either or both of the accumulated frequency and zero crossing count channels to an external monitoring system that identifies the duration of power interruptions, if any, during one or more of the predetermined monitoring periods (block 208 ).
  • the electric meter 100 continues monitoring during a subsequent monitoring period as described above with reference to the processing of block 204 .
  • the external monitoring system 1000 identifies the duration of any power interruptions that the meter 100 experiences based on one or both of the accumulated frequency channel and the accumulated zero crossing count channel in the load profile (block 210 ).
  • the total duration of power interruptions ID is based on a ratio of the accumulated frequency measurement divided by the predetermined accumulated frequency value, as well as the length of the predetermined monitoring period.
  • the processor 1004 in the external monitoring system 1000 only calculates the duration of a power interruption if the electric meter 100 sets the partial monitoring period flag in the load profile, which indicates that the electric meter 100 detected at least one power loss event during a predetermined monitoring period. In this configuration, the external monitoring system ignores small deviations in the accumulated frequency count that might occur during normal operation of the electric meter 100 .
  • the external monitoring system 1000 identifies the duration of a power interruption that occurs during at least one of the predetermined monitoring periods based on the accumulated zero crossing count in the load profile data that are received from the electric meter 100 .
  • the zero crossing channel includes a data parameter for the accumulated number of zero crossing events that the meter 100 detects during the predetermined monitoring period.
  • the processor 1004 in the external monitoring system 1000 identifies the total duration of one or more power interruptions that occur during a monitoring period based on a deviation between the total number of recorded zero crossing events in the load profile from a predetermined nominal number of expected zero crossing events that are expected to occur during the predetermined monitoring period.
  • the total duration of power interruptions ID is based on the ratio of the counted zero crossing events divided by the predetermined number of zero crossing events, as well as the length of the predetermined monitoring period.
  • the duration of the power interruption increases as the number of measured zero crossing events in the zero crossing channel of the load profile experiences larger deviations from the predetermined nominal number of zero crossing events that are expected to occur during the predetermined monitoring period.
  • the processor 1004 in the external monitoring system 1000 only calculates the duration of a power interruption if the electric meter 100 sets the partial monitoring period flag in the load profile, which indicates that the electric meter 100 detected at least one power loss event during a predetermined monitoring period. In this configuration, the external monitoring system ignores small deviations in the accumulated zero crossing count that might occur during normal operation of the electric meter 100 .
  • the control device 180 in the electric meter 100 identifies the total duration of power interruptions during each predetermined monitoring period based on either or both of the accumulated frequency count channel and the zero crossing channel in the load profile (block 212 ). In this embodiment, the control device 180 identifies the total duration of the power interruptions in the same manner that is described above for the external monitoring system 1000 , and the control device 180 stores the total duration of power interruptions in the memory 192 . In some embodiments, the control device 180 generates the load profile data including a separate channel that indicates the total duration of power interruptions that occur during each predetermined monitoring period and transmits the power interruption data to the external monitoring system 1000 as part of the load profile.
  • control device 180 can store a sum of a total value for all power interruptions that occur over a series of monitoring periods, such as a sum of the total duration of power interruptions that occur during a predetermined monitoring period added to a sum stored in the memory 192 for one or more earlier monitoring periods.
  • the external monitoring system 1000 can request the total duration of power interruptions from the electric meter 100 as part of the process for calculating SAIDI or other power interruption monitoring calculations that cover longer periods of time such as hours, days, months, weeks, years, etc., and the control device 180 optionally resets the sum of the total duration of power interruptions after reporting the data to the external monitoring system 1000 .
  • both the external monitoring system 1000 and the electric meter 100 identify the total duration of power interruptions as described above.
  • FIG. 3 depicts a process 300 for operation of an electric meter to measure, record, and report the durations of power interruptions.
  • a reference to the process 300 performing a function or action refers to the operation of a control device to execute stored program instructions to perform the function or action in association with other components in an electric meter.
  • the process 300 is described in more detail below in conjunction with the electric meter 100 of FIG. 1 .
  • the processor 1004 in the external monitoring system 1000 or the control device 180 in the electric meter 100 measures the duration of a power interruption based on a duration of a “time on battery” event (block 304 ).
  • time on battery refers to a time period of operation in the electric meter 100 in which the power supply 196 uses the battery 198 to provide electrical power to components in the electric meter 100 .
  • the time on battery occurs when the power supply 196 receives no electrical power or an insufficient level of electrical power for normal operation from the external power line during a power interruption. While FIG.
  • FIG. 1 depicts the battery 198 as being integrated with the power supply 196 for illustrative purposes, in some embodiments the battery 198 is incorporated into the metrology circuit 150 , including in embodiments where the battery 198 only supplies electrical power to the RTC 190 during power interruptions.
  • the battery 198 in the power supply 196 provides electrical power to maintain operation of at least the control device 180 in the electric meter 100 and the power supply 196 sends a first signal to the control device 180 to indicate that the electric meter 100 is operating on battery power at the start of the power interruption.
  • the power supply 196 sends a second signal to the control device 180 to indicate that the electric meter 100 is again receiving external electricity from the power line and is not operating from electrical power supplied by the battery 198 at the end of the power interruption.
  • the control device 180 identifies the “time on battery” and the duration of the power interruption based on the difference in time between receiving the first on-battery signal from the power supply 196 and the second off-battery signal from the power supply 196 .
  • the battery 198 in the power supply 196 does not provide power for full operation of the control device 180 , which shuts down during a power interruption. Instead, the battery 198 supplies enough power to maintain operation of the RTC 190 while the other components in the electric meter 100 are not operational. In many practical embodiments the battery 198 can supply power to operate the RTC 190 for prolonged power interruptions that may last for hours, days, or weeks.
  • the control device 180 After the end of the power interruption, the control device 180 returns to operation and identifies the time on battery as the time difference between a timestamp associated with a shutdown event that is stored in an event log in a non-volatile portion of the memory 192 at the beginning of the power interruption and the present time of the RTC 190 that the control device 180 reads at the end of the power interruption.
  • the control device 180 identifies the duration of the power interruption based on the time on battery even though the control device 180 was not fully operational during the power interruption.
  • the process 300 continues as the control device 180 records the duration of the power interruption to the memory 192 after the electric meter 100 returns to normal operation (block 308 ).
  • the control device 180 stores the duration of each power interruption in the memory 192 in association with a timestamp identifying the start or end of the power interruption.
  • the control device 180 stores a single record of a total duration of one or more power interruptions in the memory 192 and adds the duration of the most recent power interruption to a value stored in the memory 192 that corresponds to a total sum of durations for previously recorded power interruptions.
  • the process 300 continues as described above with reference to the processing of blocks 304 - 308 until the electric meter 100 transmits the load profile data including a channel that indicates the total duration of one or more recorded power interruptions to the external monitoring system 1000 based on the measured time on battery (block 312 ).
  • the control device 180 uses the network communication device 184 to transmit the power interruption duration data stored in the memory 192 to the external monitoring system 1000 via a data network.
  • the control device 180 operates the in-meter interface 188 to report the power interruption duration data via a display screen or a peripheral connection to a computerized meter reader device.
  • the electric meter 100 transmits the power interruption duration data as part of the load profile at regular intervals (e.g.
  • the electric meter 100 transmits the power interruption duration data in response to a request from the external monitoring system 1000 or meter reader. After reporting the total duration of the power interruptions, the electric meter 100 can reset internal power interruption counters in the memory 192 , if any, and continue the operations of the process 200 as described above to record the durations of additional power interruptions during operation of the electric meter 100 .
  • the embodiments described herein improve the accuracy of monitoring the duration of power interruption events in large power systems because individual electric meters, such as the meter 100 , can monitor the duration of even short power interruptions with a high level of accuracy and report the total duration of the power interruptions to a centralized monitoring system.
  • the centralized monitoring system uses the power interruption data from multiple electric meters to monitor the reliability of a power grid and to identify SAIDI for a power grid with greater accuracy than in prior art systems.

Abstract

A method identifies a duration of power interruptions in an electrical monitoring system. The method includes receiving, with an external monitoring system, a load profile from an electric meter that includes at least one of an accumulated frequency measurement and an accumulated number of zero crossing events that the electric meter records in an AC power signal during a predetermined monitoring period, and identifying a total duration of at least one power interruption during the predetermined monitoring period based on at least one of a deviation of the accumulated frequency measurement in the load profile from a predetermined accumulated frequency value or a deviation of the accumulated number of zero crossing events in the load profile from a predetermined number of zero crossing events during the predetermined monitoring period.

Description

    CLAIM OF PRIORITY
  • This application is a divisional application of U.S. application Ser. No. 16/104,805, entitled “System and Method for Electric Meter Outage Time Detection”, filed on Aug. 17, 2018, which claims the benefit of U.S. Provisional Application No. 62/685,563, entitled “System and Method For Electric Meter Outage Time Detection”, filed on Jun. 15, 2018, the entire contents of which are expressly incorporated herein by reference.
  • TECHNICAL FIELD
  • This disclosure relates to electric meters generally and, more particularly, to electric meters that can measure the length of time of electrical power interruptions in power lines that the electric meter monitors.
  • BACKGROUND
  • Electricity meters are devices that measure and/or meter aspects of energy provided to a load. The load may be a residence, business, or even part of a larger electricity distribution system. Commonly available meters include electromechanical meters and electronic meters. Electromechanical meters employ a rotating disk that rotates in response to electric and magnetic fields induced by the electricity passing to the load. As is known in the art, the disk rotation speed is a function of the amount of electricity delivered to the load. Mechanical counters accumulate the number of disk rotations, which is indicative of energy consumed by the load. In some cases, an electromechanical meter can employ processing circuitry to perform additional operations with the consumption information provided by the rotating disk.
  • Electronic meters typically employ processing circuitry instead of the rotating disk and mechanical counters. In such meters, sensors within the meter detect the voltage and current that is delivered to the load. Circuitry within the meter converts the sensed voltage and current into digital values. Processing circuitry then employs digital signal processing to calculate consumed energy, among other things, from the digital values. Electronic meters provide greater flexibility in the types of energy consumption information that they may calculate, track, and store.
  • During operation, the electric lines that an electric meter monitors may experience interruptions in providing power due to power outages that occur in a power grid. In many instances, electrical utilities are required to provide aggregate information about an average amount of time that different portions of a power grid experience an interruption to electrical power. This measurement can refer to an average amount of time that the power grid experiences a power loss during a predetermined time span, such as a monthly or annual time span, where of course in many instances only a portion of the power grid experiences an interruption at any one time. One example of such a measurement is the System Average Interruption Duration Index (SAIDI), which is expressed mathematically as: SAIDI=ΣUiNi/NT where Ni refers to a total number of customers at a particular location i, Ui is the total duration of power interruptions at the location i, and NT is the total number of customer locations. The SAIDI measurement is generally calculated over a one year period to provide an average duration of power interruptions for a power grid that provides power to multiple locations and customers.
  • In some existing electrical systems, interruptions to electrical power delivery are monitored from a centralized system, but while such monitoring can identify large-scale power outages effectively, the monitoring process may not identify smaller-scale power outages that have shorter durations accurately. Consequently, improvements to systems that monitor the consumption of electrical power to increase the accuracy of measuring periods of power interruption would be beneficial.
  • SUMMARY
  • In one embodiment, a method of identifying power interruptions has been developed. The method includes receiving, with an external monitoring system, a load profile from an electric meter that includes at least one of an accumulated frequency measurement and an accumulated number of zero crossing events that the electric meter records in an AC power signal during a predetermined monitoring period, and identifying, with a processor in the external monitoring system, a total duration of at least one power interruption during the predetermined monitoring period based on at least one of a deviation of the accumulated frequency measurement in the load profile from a predetermined accumulated frequency value or a deviation of the accumulated number of zero crossing events in the load profile from a predetermined number of zero crossing events during the predetermined monitoring period.
  • In another embodiment, a method of operating an electric meter to identify power interruptions has been developed. The method includes operating, with a battery in the electric meter, at least one component in the electric meter in response to a first power interruption in a power line connected to the electric meter, identifying, with a control device in the electric meter, a duration of the first power interruption based on a duration of a time on battery while operating with the battery in the electric meter after the first power interruption, and transmitting, with an output device in the electric meter, a message including a total duration of power interruptions including the duration of the first power interruption to an external monitoring system.
  • In another embodiment, a system for monitoring power interruptions has been developed. The system includes an electric meter. The electric meter includes a voltage sensor, an output device, and a control device operatively connected to the voltage sensor and the output device. The control device is configured to monitor an AC power signal in a power line that is connected to the electric meter using the voltage sensor, identify at least one of an accumulated frequency measurement of the AC power signal during a predetermined monitoring period or an accumulated number of zero crossing events in the AC power signal during the predetermined monitoring period, and transmit a load profile that includes at least one of the accumulated frequency measurement and the accumulated number of zero crossing events with the output device to an external monitoring system to enable the external monitoring system to identify a total duration of at least one power interruption in the AC power signal that occurs during the predetermined monitoring period.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • The foregoing aspects and other features of system and methods for the measurement of the duration of electrical power interruptions are explained in the following description, taken in connection with the accompanying drawings.
  • FIG. 1 is a schematic diagram of an electric meter that is configured to measure power interruptions.
  • FIG. 2 is a block diagram of a process that the electric meter 100 performs to measure the duration of power interruptions.
  • FIG. 3 is a block diagram of another process that the electric meter 100 performs to measure the duration of power interruptions.
  • FIG. 4 is a diagram depicting a voltage waveform of an alternating current (AC) power signal that the electric meter of FIG. 1 monitors during a power interruption.
  • DETAILED DESCRIPTION
  • For a general understanding of the environment for the device disclosed herein as well as the details for the device, reference is made to the drawings. In the drawings, like reference numerals designate like elements.
  • As used herein, the term “metrology circuit” refers to any suitable circuit that detects, measures, and determines one or more electricity and/or electrical energy consumption values based on energy flowing between terminals of an electric meter that are connected in-line with a power line between an electric power source and the load that receives the electric power. In one common configuration, a power grid or other generation source is connected to one set of terminals and the load that receives the electrical power is connected to the other set of terminals. The electric power in the power line flows through the electric meter and the metrology circuit measures various aspects of the electrical signal including, but not necessarily limited to, voltage and current.
  • As used herein, the terms “power outage” and “power interruption” are used interchangeably and refer to an event in which the normal supply of electric power through one or more power lines that are connected to an electric meter temporarily ceases. Power outage and interruption events are also referred to as “blackouts” in which all electrical power ceases to flow through the power lines or the level of electrical power drops to a level that prevents normal operation of a load and the electric meter.
  • FIG. 1 depicts an electric meter 100 that is configured to measure the duration of power interruptions in the supply of electricity through one or more power lines that are connected to the electric meter 100 and to transmit load profile data to an external monitoring system 1000 via a network 175. The electric meter 100 includes a meter base 120 and a metrology circuit 150 that are supported by and at least partially contained within a housing of the electric meter.
  • The meter base 120 includes two pairs of terminals 124A/128A and 124B/128B that are electrically connected together by conductors 126A and 126B, respectively. In the meter base 120, each of the terminals 124A, 124B, 128A, and 128B is formed from an electrically conductive member, often referred to as a “blade” or a “stab”, which extends from the housing of the electric meter to engage a socket that is connected to a power line (socket and power line not shown). Each of the terminal pairs 124A/128A and 124B/128B is configured to connect in-line with a conductor in a powerline where all of the power that passes through the power line from an energy source to a load passes through the terminal pairs 124A/128A and 124B/128B to a load. The terminal pairs 124A/128A and 124B/128B and the electrical conductors 126A and 126B effectively become part of the power line connected between the generation source and the load when the electric meter 100 is connected to the socket. While FIG. 1 depicts two pairs of terminals with two conductors that are configured to be connected in-line with a power line that includes two conductors (and that often includes a neutral conductor not shown in the drawings), alternative embodiments optionally include only one pair of terminals for a single conductor or additional pairs of terminals with additional conductors to enable monitoring of power lines that include more than two conducting lines, such as three-phase power lines.
  • The meter base 120 includes inductive coils 132A and 132B that are inductively coupled to the electrical conductors 126A and 126B, respectively. As described in further detail below, the inductive coils 132A and 132B are electrically connected to electrical current sensors 154A and 154B in the metrology circuit 150. The alternating current (AC) power signals in the electrical conductors 126A and 126B induce a current in the inductive coils 132A and 132B, respectively, that the metrology circuit 150 uses to monitor electrical current levels in the power line. The inductive coils 132A and 132B are also referred to as “coil transformers” since in some embodiments the inductive coils 132A and 132B form one set of coils in a current transformer in which a second set of coils produce a current measurement signal. While FIG. 1 depicts the coils 132A/132B and current sensors 154A/154B for illustrative purposes, other embodiments may employ different current sensing devices that are otherwise known to the art.
  • Referring to the metrology circuit 150 include current sensors 154A/154B, and voltage sensors 158. The metrology circuit 150 further includes an analog-to-digital converter 168, a digital control device 180, network communication device 184, and in-meter control interface 188. The metrology circuit 150 receives electrical power for operation from the power line via the terminal pairs 124A/128A and 124B/128B that are connected to a power supply 196 (connections omitted for clarity). The power supply 196 is, for example, a switched capacitor power supply or other suitable conversion circuit that produces direct current (DC) electrical output power from the AC power received at the terminals to provide electrical the components in the electric meter 100. The power supply 196 provides electrical power to the components in the metrology circuit 150 and the meter base 120 that require electrical power during operation of the electric meter 100. The power supply 196 further includes a battery 198 that provides electrical power to operate the control device 180 during a power interruption to the normal AC voltage and current flow through the power lines that are connected to the electric meter 100. In other embodiments a capacitor or other energy storage device in the electric meter 100 supplies electrical power to the control device 180 and optionally other components in the electric meter 100 during a power interruption.
  • In the metrology circuit 150, the current sensors 154A/154B are each connected to one of the inductive coils 132A and 132B, respectively, to enable the current sensors to monitor the levels of electrical current in the electrical conductors 126A and 126B, respectively. In one embodiment, the current sensors 154A and 154B each includes a second set of coils that are coupled to the corresponding inductive coils 132A or 132B in a coil transformer arrangement. The coils in the current sensors 154A and 154B generate electrical currents that correspond to the current levels in the electrical conductors 126A and 126B, although at greatly reduced amplitudes to enable measurement of the current in an efficient manner and with the current sensors having galvanic isolation from the much higher current levels of the electrical conductors 126A and 126B. The current sensors 154A and 154B generate analog current measurement signals that are supplied to the ADC 168 to be provided as digital current level signals to the control device 180, although in an analog electrical meter an analog control circuit may receive the analog current measurement signals directly.
  • In the metrology circuit 150, the voltage sensor 158 is connected to both of the electrical conductors 126A and 126B. The voltage sensor 158 is configured to generate an analog voltage measurement signal having a waveform representative of the voltage provided to the load through the power line. The outputs of the voltage sensor 158 is connected to the ADC 168 to enable the control device 180 to receive digitized representations of the measured voltage levels from the voltage sensors 158. In one embodiment, the voltage sensor 158 includes a voltage divider circuit to bring the measured voltage waveform to a magnitude that is suitable for the ADC 168. The voltage sensor 158 may alternatively take other known forms.
  • In the electric meter 100, the control device 180 is a digital logic device that includes, for example, one or more microprocessors, microcontrollers, field programmable gate arrays (FPGAs), digital signal processors (DSPs), programmable logic controllers (PLCs), application specific integrated circuits (ASICs), and the like. In the embodiment of FIG. 1, the control device 180 also includes or is operatively connected to a real time clock (RTC) 190 and a memory 192. The RTC 190 tracks the time at which the meter 100 records samples of input sensor data from the current sensors 154A/154B and voltage sensor 158. As described below, the control device 180 also uses the RTC 190 to measure the duration of “time on battery” events that correspond to the duration of power interruptions in some embodiments. The memory 192 includes one or more memory devices that store programmed software or firmware instructions that the control device 180 executes to operate the electric meter 100 in conjunction with the other components of the electric meter. The memory 192 also stores “load profile” records that the electric meter generates during a predetermined monitoring period, which is typically on the order of one minute to one hour in duration although other embodiments may use longer or shorter monitoring periods. The load profile typically includes multiple data fields in the load profile that are referred to as “channels” that include, for example, measurements of the accumulated energy consumption of loads that are attached to the power line, an accumulation of frequency measurements in the voltage of the AC power signal, an accumulation of zero crossing events in the voltage of the AC power signal, and other information that the electric meter 100 records and reports to a centralized monitoring system. In some embodiments, if the electric meter 100 experiences a power interruption during a monitoring period then the electric meter 100 sets a value in the load profile indicating that monitoring only occurred for a partial monitoring period instead of for the full predetermined monitoring period. The memory 192 is implemented using at least one non-volatile memory device such as a NAND or NOR memory device or other suitable solid-state memory, and in some embodiment the memory 192 includes a volatile memory device such as random access memory (RAM). In addition to the specific functions described herein, the control circuit 180 also performs metrology routines, display routines, communication routines, that are commonly associated with the operation of electric meters. As depicted in FIG. 1, the control device 180 receives input data from the current sensors 154A and 154B and the voltage sensor 158, either directly or indirectly via the ADC 168.
  • In the metrology circuit 150, the control device 180 is operatively connected to network communication device 184 and the in-meter interface 188 in addition to being connected to receive input data from the current sensors 154A/154B and the voltage sensors 158. The network communication device 184 and the in-meter interface are both examples of output devices. The network communication device 184 is, for example, an analog modem or digital subscriber line (DSL) device that couples to a telephone network, an Ethernet transceiver that transmits data over a wired network, a local serial bus output such as RS-232 or Universal Serial Bus (USB), or either or both of a wireless local area network (WLAN) or wide area network (WWAN) transceiver that transmits metrology data to the external monitoring system 1000. In the metrology circuit 150, the in-meter interface 188 provides a visual and in some instances audible output device that enables manual meter reading and manual inspection of the electric meter to retrieve power consumption and power interruption data. Examples of in-meter interfaces include mechanical gauges, indicator lights, LCD or LED display screens, alarm bells or speakers and the like. The in-meter interface optionally includes control inputs that enable an operator to send commands to the control device 180 while physically present at the electric meter. While the metrology circuit 150 includes both the network communication device 184 and the in-meter interface 188, some embodiments of electric meters that measure the durations of power interruptions only include a network communication device 184 or an in-meter interface 188, but not both elements. For example, some electric meters have no need to communicate with a remote system via a data network and only include the in-meter interface 188, while other electric meters rely exclusively on the network communication device 184 to transmit the meter data and do not include the in-meter interface 188.
  • In FIG. 1, the external monitoring system 1000 includes a processor 1004 that is operatively connected to a memory 1008 and a network communication device 1012. In the external monitoring system 1000, the processor 1004 is a central processing unit (CPU) or other suitable digital logic device that is configured to process load profile information that the external monitoring system 1000 receives using the network communication device 1012 to communicate with the corresponding network communication device 184 in the electric meter 100 via the network 175. The memory 1008 stores programmed instructions for the processor 1004, load profile data that are received from the electric meter 100, and stores records of the accumulate duration of power interruptions that may occur in the electric meter 100 over a series of predetermined monitoring periods. While not depicted in further detail in FIG. 1, in some configurations the external monitoring system 1000 receives and processes load profile data from a plurality of electric meters with the same or similar configuration as the electric meter 100.
  • In various configurations the external monitoring system 1000 includes, for example, a head end unit that monitors the electric meter 100 and in some embodiments other electric meters that are not expressly shown in FIG. 1. Electric utilities, site owners, or other entities operate the external monitoring system 1000 to monitor power interruptions in the electric meter 100 to calculate SAIDI and monitor power interruptions. In particular, the external monitoring system 1000 periodically receives a load profile from the electric meter 100 that includes channels for either or both of the accumulated frequency measurement and accumulated zero crossing measurement. The external monitoring system 1000 determines the duration of one or more power interruptions that may occur during a predetermined monitoring period based on the accumulated frequency measurement and accumulated zero crossing channels. Additionally, in some configurations the external monitoring system 1000 transmits command messages to the control device 180 in the electric meter 100 via the network communication device 184.
  • During operation, the electric meter 100 transmits load profile data including the channels that identify either or both of the accumulated frequency counts and accumulated zero crossing counts to the external monitoring system 1000 via the network 175. As described in more detail below, the external monitoring system 1000 identifies the duration of power interruptions that the electric meter 100 experiences during one or more predetermined monitoring periods to enable fine-grained tracking of the duration of power interruptions to measure SAIDI and to perform other monitoring operations in an electric power distribution system. The control device 180 in the electric meter optionally measures the durations of power interruptions and stores records of the total duration of any power interruptions that occur during a predetermined monitoring period (e.g. a 15 minute period). The control device 180 also generates transmits reports of the total duration of power interruptions that occur over one or more monitoring periods, such as a total duration of power interruptions over the course of an hour, day, week, month, or year, to a monitoring service using the network communication device 184. The operation of the electric meter 100 to track the duration of power interruptions is described in further detail below.
  • FIG. 2 depicts a process 200 for operation of an electric meter to measure, record, and report the durations of power interruptions. In the description below, a reference to the process 200 performing a function or action refers to the operation of a digital processing device, such as a control device in a meter, a processor in an external monitoring system, or a combination thereof, to execute stored program instructions to perform the function or action in association with other components in an electric meter. The process 200 is described in more detail below in conjunction with the electric meter 100 of FIG. 1 and the graph of FIG. 4.
  • During the process 200, the control device 180 monitors the voltage of the AC power signal that is supplied from a power line using the voltage sensors 158 to record measurements of the accumulated value of frequency measurements, the accumulated value of a total number of zero crossing events, or both, during the predetermined monitoring period (block 204). In the electric meter 100, the voltage of the AC power signal is supplied from a power line and passes between the terminal pairs 124A/128A and 124B/128B in the electric meter 100 during the predetermined monitoring period. In one embodiment, the ADC 168 generates digital samples of the voltage values from the voltage sensors 158 at a sampling frequency that exceeds the expected frequency (e.g. 50 Hz or 60 Hz) of the AC sinusoidal signal to enable the control device 180 to identify features such as positive and negative peaks and zero crossing events in the voltage waveform of each cycle of the AC sinusoidal signal. In one specific example, the ADC 168 generates digital voltage samples at rate in a range of, for example, 1 KHz to 20 KHz to collect multiple samples in each cycle of the sinusoidal AC power signal. As described above, the predetermined monitoring period is any suitable length of time, such as a 15 minute period used in the illustrative embodiment of FIG. 2, which enables the electric meter 100 to produce an average value of the measured AC signal frequency or total number of zero crossings in the AC power signal.
  • In one configuration, the control device 180 identifies the time difference T between successive positive peaks or negative peaks in the voltage waveform of the AC power signal to measure the frequency of the AC power signal. Each peak occurs when a series of samples of data from the ADC for the voltage of the AC power signal reach a maximum absolute value (positive or negative) and begin to return to zero, and the control device 180 optionally interpolates between data samples to identify the time of each peak with greater accuracy. The control device 180 identifies the frequency of each cycle as T−1 and the measured frequency of the signal is an averaged value for multiple cycles that are measured over the predetermined monitoring period. The electric meter 100 generates records of the accumulated frequency measurements of the AC power signal as part of a load profile during a predetermined monitoring period and reports the frequency measurement information to an external monitoring system at regular intervals as one channel in the load profile that also includes additional data collected by the electric meter 100.
  • FIG. 4 depicts a graph 400 of the electrical voltage levels of an example AC power signal over time with time periods 432, 436, and 452 that correspond to the expected frequency of the sinusoidal AC power signal at a predetermined frequency, such as 50 Hz or 60 Hz. In another configuration, the meter 100 measures the same periods based on the time between troughs (negative peaks) in each cycle of the AC power signal. The frequency of an AC power signal in a large power grid is generally stable and experiences far smaller variations during normal operation than the voltage levels of the AC signal. During operation, the control device 180 measures the frequency of the AC power signal at a predetermined rate (e.g. four measurements per second in one embodiment) and stores an accumulation of all the frequency measurements in the frequency channel of the load profile that is stored in the memory 192 during each predetermined monitoring period. FIG. 4 also depicts a power interruption 444 in the AC power signal in which there are no additional peaks. The control device 180 does not record any frequency measurements during the power interruption 444 and in most embodiments is not activated during the power interruption 444. The electric meter 100 restarts after the power interruption and the controller 180 continues to record additional frequency measurements, although the total accumulated value of all the frequency measurements during the predetermined monitoring period is lower than expected due to the power interruption. While FIG. 4 depicts a single interruption 444, in some situations the electric meter 100 experiences multiple power interruptions during a single monitoring period, and the embodiments described herein can identify the accumulated duration of one or more power interruptions.
  • In another configuration, the control device 180 records a count of the accumulated number of zero crossing events that occur in the AC power signal. As depicted in FIG. 4, the zero crossing events occur when the voltage in the AC power signal transitions from a positive to negative or negative to positive voltage, and the control device 180 optionally interpolates between data samples to identify the time of each zero crossing with greater accuracy. In this configuration, the electric meter 100 generates records of the measured zero crossing events of the AC power signal as part of a load profile during a predetermined monitoring period and reports the accumulated zero crossing event measurement information to the external monitoring system at regular intervals as one channel the load profile that also includes additional data collected by the electric meter 100.
  • FIG. 4 depicts the zero crossings 404A/404B, 408A/408B, 412A/412B, and 416A/416B that occur during different cycles of the AC power signal, where each cycle of the AC power signal includes two zero crossings. The control device 180 identifies each zero crossing event based on a transition of the measured voltage values from a positive value to a negative value or from a negative value to a positive value in the digital sensor data samples that the control device 180 receives from the ADC 168. The control device 180 records an accumulated value of the total number of measured zero crossing events that occur during each predetermined monitoring period. As depicted in FIG. 4, during the power interruption period 444 the AC signal does not produce any zero crossings and the control device 180, which is typically deactivated during the power interruption 444, does not record zero crossing events during the power interruption. During the predetermined monitoring period, the control device 180 records a reduced number of zero crossings compared to a predetermined expected value based on the predetermined frequency of the AC power signal when power interruptions occur.
  • Referring again to FIG. 2, the process 200 continues as the electric meter 100 transmits the recorded load profile that includes either or both of the accumulated frequency and zero crossing count channels to an external monitoring system that identifies the duration of power interruptions, if any, during one or more of the predetermined monitoring periods (block 208). The electric meter 100 continues monitoring during a subsequent monitoring period as described above with reference to the processing of block 204. In some embodiments of the process 200, the external monitoring system 1000 identifies the duration of any power interruptions that the meter 100 experiences based on one or both of the accumulated frequency channel and the accumulated zero crossing count channel in the load profile (block 210).
  • In one configuration, the external monitoring system 1000 identifies the duration of a power interruption that occurs during at least one of the predetermined monitoring periods based on the accumulated frequency channel in the load profile data that are received from the electric meter 100. For example, if the nominal frequency of an AC power signal is 60 Hz and the electric meter 100 is configured to record a measurement of the frequency four times per second over a predetermined monitoring period of 15 minutes (900 second), then the accumulated frequency channel in the load profile data has an expected predetermined accumulated frequency value of 216,000 ((4)(60 Hz)(900 sec)=216,000). If the recorded accumulated frequency measurement deviates from the predetermined accumulated frequency value, then the processor 1004 in the external system 1000 calculates the duration of the power interruption based on the magnitude of the deviation. For example, if the frequency channel in the load profile that is generated in the electric meter 100 produces a value of 213,120, then the external system identifies that the electric meter 100 recorded one or more power interruptions with a total duration ID of 12 seconds
  • ID = ( 9 0 0 sec - ( 213120 216000 ) ( 900 sec ) = 12 sec ) .
  • Once again, the total duration of power interruptions ID is based on a ratio of the accumulated frequency measurement divided by the predetermined accumulated frequency value, as well as the length of the predetermined monitoring period. In some configurations, the processor 1004 in the external monitoring system 1000 only calculates the duration of a power interruption if the electric meter 100 sets the partial monitoring period flag in the load profile, which indicates that the electric meter 100 detected at least one power loss event during a predetermined monitoring period. In this configuration, the external monitoring system ignores small deviations in the accumulated frequency count that might occur during normal operation of the electric meter 100.
  • In another configuration, the external monitoring system 1000 identifies the duration of a power interruption that occurs during at least one of the predetermined monitoring periods based on the accumulated zero crossing count in the load profile data that are received from the electric meter 100. As described above, the zero crossing channel includes a data parameter for the accumulated number of zero crossing events that the meter 100 detects during the predetermined monitoring period. The processor 1004 in the external monitoring system 1000 identifies the total duration of one or more power interruptions that occur during a monitoring period based on a deviation between the total number of recorded zero crossing events in the load profile from a predetermined nominal number of expected zero crossing events that are expected to occur during the predetermined monitoring period. For example, given a 60 Hz frequency AC power signal and a monitoring period with a duration of 900 seconds, the nominal value of the predetermined number of zero crossing events Znom that is expected occur during the predetermined monitoring period is Znom=2(60 Hz)(900 sec)=10,800 zc where zc represents “zero crossings”. If the processor 1004 measures Zcounted=10,656 during a predetermined monitoring period for the zero crossing channel, then the processor 1004 in the external monitoring system 1000 identifies that the measured accumulated value of zero crossings corresponds one or more power interruptions with a total duration ID of:
  • ID = 900 sec - ( 10 , 656 zc 10 , 800 zc ) ( 900 sec ) = 12 sec .
  • Once again, the total duration of power interruptions ID is based on the ratio of the counted zero crossing events divided by the predetermined number of zero crossing events, as well as the length of the predetermined monitoring period. The duration of the power interruption increases as the number of measured zero crossing events in the zero crossing channel of the load profile experiences larger deviations from the predetermined nominal number of zero crossing events that are expected to occur during the predetermined monitoring period. In some configurations, the processor 1004 in the external monitoring system 1000 only calculates the duration of a power interruption if the electric meter 100 sets the partial monitoring period flag in the load profile, which indicates that the electric meter 100 detected at least one power loss event during a predetermined monitoring period. In this configuration, the external monitoring system ignores small deviations in the accumulated zero crossing count that might occur during normal operation of the electric meter 100.
  • In an alternative configuration, the control device 180 in the electric meter 100 identifies the total duration of power interruptions during each predetermined monitoring period based on either or both of the accumulated frequency count channel and the zero crossing channel in the load profile (block 212). In this embodiment, the control device 180 identifies the total duration of the power interruptions in the same manner that is described above for the external monitoring system 1000, and the control device 180 stores the total duration of power interruptions in the memory 192. In some embodiments, the control device 180 generates the load profile data including a separate channel that indicates the total duration of power interruptions that occur during each predetermined monitoring period and transmits the power interruption data to the external monitoring system 1000 as part of the load profile. Additionally, the control device 180 can store a sum of a total value for all power interruptions that occur over a series of monitoring periods, such as a sum of the total duration of power interruptions that occur during a predetermined monitoring period added to a sum stored in the memory 192 for one or more earlier monitoring periods. The external monitoring system 1000 can request the total duration of power interruptions from the electric meter 100 as part of the process for calculating SAIDI or other power interruption monitoring calculations that cover longer periods of time such as hours, days, months, weeks, years, etc., and the control device 180 optionally resets the sum of the total duration of power interruptions after reporting the data to the external monitoring system 1000. In some configurations, both the external monitoring system 1000 and the electric meter 100 identify the total duration of power interruptions as described above.
  • FIG. 3 depicts a process 300 for operation of an electric meter to measure, record, and report the durations of power interruptions. In the description below, a reference to the process 300 performing a function or action refers to the operation of a control device to execute stored program instructions to perform the function or action in association with other components in an electric meter. The process 300 is described in more detail below in conjunction with the electric meter 100 of FIG. 1.
  • During the process 300, the processor 1004 in the external monitoring system 1000 or the control device 180 in the electric meter 100 measures the duration of a power interruption based on a duration of a “time on battery” event (block 304). The term “time on battery” refers to a time period of operation in the electric meter 100 in which the power supply 196 uses the battery 198 to provide electrical power to components in the electric meter 100. The time on battery occurs when the power supply 196 receives no electrical power or an insufficient level of electrical power for normal operation from the external power line during a power interruption. While FIG. 1 depicts the battery 198 as being integrated with the power supply 196 for illustrative purposes, in some embodiments the battery 198 is incorporated into the metrology circuit 150, including in embodiments where the battery 198 only supplies electrical power to the RTC 190 during power interruptions.
  • In one configuration, the battery 198 in the power supply 196 provides electrical power to maintain operation of at least the control device 180 in the electric meter 100 and the power supply 196 sends a first signal to the control device 180 to indicate that the electric meter 100 is operating on battery power at the start of the power interruption. After external electrical power is restored, the power supply 196 sends a second signal to the control device 180 to indicate that the electric meter 100 is again receiving external electricity from the power line and is not operating from electrical power supplied by the battery 198 at the end of the power interruption. The control device 180 identifies the “time on battery” and the duration of the power interruption based on the difference in time between receiving the first on-battery signal from the power supply 196 and the second off-battery signal from the power supply 196.
  • In another configuration, the battery 198 in the power supply 196 does not provide power for full operation of the control device 180, which shuts down during a power interruption. Instead, the battery 198 supplies enough power to maintain operation of the RTC 190 while the other components in the electric meter 100 are not operational. In many practical embodiments the battery 198 can supply power to operate the RTC 190 for prolonged power interruptions that may last for hours, days, or weeks. After the end of the power interruption, the control device 180 returns to operation and identifies the time on battery as the time difference between a timestamp associated with a shutdown event that is stored in an event log in a non-volatile portion of the memory 192 at the beginning of the power interruption and the present time of the RTC 190 that the control device 180 reads at the end of the power interruption. The control device 180 identifies the duration of the power interruption based on the time on battery even though the control device 180 was not fully operational during the power interruption.
  • The process 300 continues as the control device 180 records the duration of the power interruption to the memory 192 after the electric meter 100 returns to normal operation (block 308). In one configuration the control device 180 stores the duration of each power interruption in the memory 192 in association with a timestamp identifying the start or end of the power interruption. In another configuration, the control device 180 stores a single record of a total duration of one or more power interruptions in the memory 192 and adds the duration of the most recent power interruption to a value stored in the memory 192 that corresponds to a total sum of durations for previously recorded power interruptions.
  • The process 300 continues as described above with reference to the processing of blocks 304-308 until the electric meter 100 transmits the load profile data including a channel that indicates the total duration of one or more recorded power interruptions to the external monitoring system 1000 based on the measured time on battery (block 312). In one configuration, the control device 180 uses the network communication device 184 to transmit the power interruption duration data stored in the memory 192 to the external monitoring system 1000 via a data network. In another configuration, the control device 180 operates the in-meter interface 188 to report the power interruption duration data via a display screen or a peripheral connection to a computerized meter reader device. In some embodiments, the electric meter 100 transmits the power interruption duration data as part of the load profile at regular intervals (e.g. after each monitoring period, hourly, daily, weekly, monthly, annually), while in other embodiments the electric meter 100 transmits the power interruption duration data in response to a request from the external monitoring system 1000 or meter reader. After reporting the total duration of the power interruptions, the electric meter 100 can reset internal power interruption counters in the memory 192, if any, and continue the operations of the process 200 as described above to record the durations of additional power interruptions during operation of the electric meter 100.
  • The embodiments described herein improve the accuracy of monitoring the duration of power interruption events in large power systems because individual electric meters, such as the meter 100, can monitor the duration of even short power interruptions with a high level of accuracy and report the total duration of the power interruptions to a centralized monitoring system. The centralized monitoring system uses the power interruption data from multiple electric meters to monitor the reliability of a power grid and to identify SAIDI for a power grid with greater accuracy than in prior art systems.
  • It will be appreciated that variants of the above-disclosed and other features and functions, or alternatives thereof, may be desirably combined into many other different systems, applications or methods. Various presently unforeseen or unanticipated alternatives, modifications, variations or improvements may be subsequently made by those skilled in the art that are also intended to be encompassed by the following claims.

Claims (20)

1. An electric meter comprising:
a control device;
a battery; and
a power supply operatively connected to at least one terminal pair and to the battery and configured to provide power to components of the electric meter, including the control device,
wherein the power supply is configured for:
determining that the power supply is operating using power supplied by the battery;
in response to determining that the power supply is operating using power supplied by the battery, sending a first signal to the control device indicating that the power supply is operating using power supplied by the battery;
determining that the power supply is operating using power supplied by an external power line via the at least one terminal pair; and
in response to determining that the power supply is operating using power supplied by the external power line, sending a second signal to the control device indicating that the power supply is operating using power supplied by the external power line;
wherein the control device is configured for:
receiving the first signal from the power supply;
determining that the first signal from the power supply corresponds to a start of a power interruption;
receiving the second signal from the power supply;
determining that the second signal from the power supply corresponds to an end of the power interruption;
determining a duration of the power interruption based on a time difference between receiving the first signal and the second signal from the power supply; and
transmitting a communication that indicates the duration of the power interruption to an external monitoring system.
2. The electric meter of claim 1, wherein the control device comprises memory, and wherein the control device is further configured for storing the duration of the power interruption in the memory along with a timestamp.
3. The electric meter of claim 2, wherein the timestamp corresponds to the start of the power interruption or the end of the power interruption.
4. The electric meter of claim 1, wherein the control device comprises memory, and wherein the control device is further configured for:
storing the duration of the power interruption in the memory;
receiving a third signal from the power supply;
determining that the third signal from the power supply corresponds to a start of a second power interruption;
receiving a fourth signal from the power supply;
determining that the fourth signal from the power supply corresponds to an end of the second power interruption;
determining a duration of the second power interruption based on a time difference between receiving the third signal and the fourth signal from the power supply; and
adding the duration of the second power interruption to the duration of the power interruption to obtain a total duration and storing the total duration in the memory.
5. The electric meter of claim 4, wherein transmitting a communication that indicates the duration of the power interruption to an external monitoring system comprises transmitting a communication that indicates the total duration.
6. The electric meter of claim 1, wherein transmitting a communication that indicates the duration of the power interruption to an external monitoring system comprises:
responding to a request received from the external monitoring system for power interruption data, or
transmitting load profile data at an end of a next load profile interval.
7. The electric meter of claim 1, wherein the control device comprises memory and wherein the control device is further configured for:
storing a value in memory for the duration of the power interruption; and
after transmitting the communication that indicates the duration of the power interruption, resetting the value.
8. An electric meter for monitoring power interruptions comprising:
a control device;
a memory comprising non-volatile memory;
a real time clock (RTC);
a battery operatively connected to the RTC and configured to power the RTC; and
a power supply operatively connected to at least one terminal pair and configured to provide power to components of the electric meter, including the control device, when power is available from an external power line on the at least one terminal pair;
wherein the control device is configured for:
operating using power received from the power supply;
detecting a power interruption;
in response to detecting the power interruption, storing a timestamp that corresponds to a beginning of the power interruption in an event log stored in the non-volatile memory;
shutting down;
detecting an end of the power interruption and resuming operation using power received from the power supply;
determining a current time of the RTC;
determining a duration of the power interruption based on a time difference between the timestamp that corresponds to the beginning of the power interruption and the current time of the RTC; and
transmitting a communication that indicates the duration of the power interruption to an external monitoring system.
9. The electric meter of claim 8, wherein the control device is further configured for storing the duration of the power interruption in the memory along with a timestamp.
10. The electric meter of claim 9, wherein the timestamp corresponds to the beginning of the power interruption or the end of the power interruption.
11. The electric meter of claim 8, wherein the control device is further configured for:
detecting a second power interruption;
in response to detecting the second power interruption, storing a timestamp that corresponds to a beginning of the second power interruption in the event log stored in the non-volatile memory;
shutting down;
detecting an end of the second power interruption and resuming operation using power received from the power supply;
determining a second current time of the RTC;
determining a duration of the second power interruption based on a time difference between the timestamp that corresponds to the beginning of the second power interruption and the second current time of the RTC; and
adding the duration of the second power interruption to the duration of the power interruption to obtain a total duration and storing the total duration in the memory.
12. The electric meter of claim 11, wherein transmitting a communication that indicates the duration of the power interruption to an external monitoring system comprises transmitting a communication that indicates the total duration.
13. The electric meter of claim 8, wherein transmitting a communication that indicates the duration of the power interruption to an external monitoring system comprises:
responding to a request received from the external monitoring system for power interruption data, or
transmitting load profile data at an end of a next load profile interval.
14. The electric meter of claim 8, wherein the control device comprises memory and wherein the control device is further configured for:
storing a value in memory for the duration of the power interruption; and
after transmitting the communication that indicates the duration of the power interruption, resetting the value.
15. The electric meter of claim 8, further comprising a capacitor operatively connected to the control device and configured to provide power to the control device during the power interruption.
16. The electric meter of claim 8, further comprising a display device, wherein the control device is further configured for displaying the duration of the power interruption on the display device.
17. A method of operating an electric meter to identify power interruptions comprising: operating, with a battery in the electric meter, at least one component in the electric meter in response to a first power interruption in a power line connected to the electric meter; identifying, with a control device in the electric meter, a duration of the first power interruption based on a duration of a time on battery while operating with the battery in the electric meter after the first power interruption; and transmitting, with an output device in the electric meter, a message including a total duration of power interruptions including the duration of the first power interruption to an external monitoring system.
18. The method of claim 17 further comprising: operating, with the battery in the electric meter, the control device in the electric meter in response to the first power interruption; receiving, with the control device, a first signal from a power supply in the electric meter indicating a start of the time on battery at a start of the first power interruption; receiving, with the control device, a second signal from a power supply in the electric meter indicating an end of the time on battery at an end of the first power interruption; and identifying, with the control device, the duration of the time on battery based on a difference in time between receiving the first signal and receiving the second signal.
19. The method of claim 17 further comprising: operating, with the battery in the electric meter, a real time clock (RTC) in the electric meter in response to the first power interruption; operating, with a power supply in the electric meter, the control device at an end of the first power interruption; and identifying, with the control device, the duration of the time on battery based on a difference in time between a timestamp of a shutdown event stored in an event log in a memory in the electric meter and a time of the RTC at the end of the first power interruption.
20. The method of claim 17 further comprising: identifying, with the control device, the total duration of power interruptions by adding the duration of the first power interruption to a value stored in a memory of the electric meter corresponding to a sum of durations of power interruptions that occurred prior to the first power interruption.
US17/667,262 2018-06-15 2022-02-08 System and method for electric meter outage time detection Abandoned US20220163602A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US17/667,262 US20220163602A1 (en) 2018-06-15 2022-02-08 System and method for electric meter outage time detection

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US201862685563P 2018-06-15 2018-06-15
US16/104,805 US11275123B2 (en) 2018-06-15 2018-08-17 System and method for electric meter outage time detection
US17/667,262 US20220163602A1 (en) 2018-06-15 2022-02-08 System and method for electric meter outage time detection

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US16/104,805 Division US11275123B2 (en) 2018-06-15 2018-08-17 System and method for electric meter outage time detection

Publications (1)

Publication Number Publication Date
US20220163602A1 true US20220163602A1 (en) 2022-05-26

Family

ID=68839879

Family Applications (2)

Application Number Title Priority Date Filing Date
US16/104,805 Active 2040-06-09 US11275123B2 (en) 2018-06-15 2018-08-17 System and method for electric meter outage time detection
US17/667,262 Abandoned US20220163602A1 (en) 2018-06-15 2022-02-08 System and method for electric meter outage time detection

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US16/104,805 Active 2040-06-09 US11275123B2 (en) 2018-06-15 2018-08-17 System and method for electric meter outage time detection

Country Status (6)

Country Link
US (2) US11275123B2 (en)
EP (1) EP3807663A1 (en)
JP (2) JP7146958B2 (en)
CN (1) CN112534286B (en)
CA (1) CA3103873A1 (en)
WO (1) WO2019241618A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11899516B1 (en) 2023-07-13 2024-02-13 T-Mobile Usa, Inc. Creation of a digital twin for auto-discovery of hierarchy in power monitoring

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11921532B2 (en) * 2021-10-20 2024-03-05 Landis+Gyr Technology, Inc. Controlling pulsed operation of a power supply during a power outage
CN115835055B (en) * 2022-11-22 2023-10-27 宁夏隆基宁光仪表股份有限公司 Dynamic regulation method for concentrator communication process

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4197582A (en) * 1978-03-31 1980-04-08 Westinghouse Electric Corp. Auxiliary power supply and timer arrangement for time registering multifunctional electric energy meters
US5216357A (en) * 1987-04-10 1993-06-01 Schlumberger Industries, Inc. Real time solid state register having battery backup
US6115676A (en) * 1996-04-09 2000-09-05 General Electric Company Methods and apparatus for performing load profile and load control
US20010010032A1 (en) * 1998-10-27 2001-07-26 Ehlers Gregory A. Energy management and building automation system
JP2006184218A (en) * 2004-12-28 2006-07-13 Toshiba Corp Watt-hour meter
US7457991B1 (en) * 2002-12-03 2008-11-25 Unisys Corporation Method for scanning windows event logs on a cellular multi-processor (CMP) server
US20130119974A1 (en) * 2011-11-14 2013-05-16 General Electric Company System and method for tamper detection in a utility meter
US20160154040A1 (en) * 2014-12-02 2016-06-02 Itron, Inc. Electrical Network Topology Determination
US20170271915A1 (en) * 2016-03-16 2017-09-21 Why Energy, LLC Energy Demand Monitoring System and Smart micro-Grid Controller
US20190029074A1 (en) * 2016-03-07 2019-01-24 Seiko Epson Corporation Gateway device and communication system

Family Cites Families (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4467434A (en) 1981-09-18 1984-08-21 Mcgraw-Edison Co. Solid state watt-hour meter
JPH07333266A (en) 1994-06-06 1995-12-22 Canon Inc Malfunction prevent device
US5924051A (en) 1994-12-16 1999-07-13 General Electric Company Demand meter having load profile recording capabilities
US5525898A (en) * 1994-12-16 1996-06-11 General Electric Company Programmable multi-channel load profile recorder and method of recording electrical energy metering quantities therein
US5918380A (en) * 1997-09-17 1999-07-06 Itron, Inc. Time-of-use and demand metering in conditions of power outage
JP4693729B2 (en) 2006-09-15 2011-06-01 パナソニック株式会社 VOLTAGE DETECTION CIRCUIT, POWER SUPPLY DEVICE EQUIPPED WITH THE SAME, SWITCHING REGULATOR DEVICE, AND ELECTRONIC DEVICE
US8081726B2 (en) * 2007-05-10 2011-12-20 Schneider Electric USA, Inc. Method and apparatus for synchronizing data in utility system
JP2009041918A (en) 2007-08-06 2009-02-26 Toto Ltd Electronic instrument and toilet apparatus
JP5219251B2 (en) * 2008-03-13 2013-06-26 東光東芝メーターシステムズ株式会社 Electricity meter
US8193787B2 (en) * 2010-07-06 2012-06-05 V Square/R, LLC System and method for regulating RMS voltage delivered to a load
US8547109B2 (en) * 2010-07-19 2013-10-01 The Southern Company Capacitor monitoring systems and methods of metering and monitoring capacitor bank
JP5460838B2 (en) * 2012-12-10 2014-04-02 三菱電機株式会社 Power converter
JP2014176206A (en) 2013-03-08 2014-09-22 Ricoh Co Ltd Uninterruptible power supply device, image formation device, and uninterruptible power supply system
US10466285B2 (en) 2013-04-12 2019-11-05 Landis+Gyr Llc Utility meter having data logging with power loss recovery
US20150309103A1 (en) 2014-04-25 2015-10-29 Leviton Manufacturing Company Ground Fault Detector With Self-Test
JP6169055B2 (en) 2014-08-22 2017-07-26 京セラドキュメントソリューションズ株式会社 Power supply device, image processing device
US10250032B2 (en) 2015-04-24 2019-04-02 Vertiv Corporation Intelligent power strip with management of bistable relays to reduce current in-rush
JP2017116480A (en) * 2015-12-25 2017-06-29 パナソニック デバイスSunx竜野株式会社 Watthour meter
IT201700022263A1 (en) * 2017-02-28 2018-08-28 St Microelectronics Srl TESTING CIRCUIT, POWER SUPPLY, EQUIPMENT AND CORRESPONDENT PROCEDURE

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4197582A (en) * 1978-03-31 1980-04-08 Westinghouse Electric Corp. Auxiliary power supply and timer arrangement for time registering multifunctional electric energy meters
US5216357A (en) * 1987-04-10 1993-06-01 Schlumberger Industries, Inc. Real time solid state register having battery backup
US6115676A (en) * 1996-04-09 2000-09-05 General Electric Company Methods and apparatus for performing load profile and load control
US20010010032A1 (en) * 1998-10-27 2001-07-26 Ehlers Gregory A. Energy management and building automation system
US7457991B1 (en) * 2002-12-03 2008-11-25 Unisys Corporation Method for scanning windows event logs on a cellular multi-processor (CMP) server
JP2006184218A (en) * 2004-12-28 2006-07-13 Toshiba Corp Watt-hour meter
US20130119974A1 (en) * 2011-11-14 2013-05-16 General Electric Company System and method for tamper detection in a utility meter
US20160154040A1 (en) * 2014-12-02 2016-06-02 Itron, Inc. Electrical Network Topology Determination
US20190029074A1 (en) * 2016-03-07 2019-01-24 Seiko Epson Corporation Gateway device and communication system
US20170271915A1 (en) * 2016-03-16 2017-09-21 Why Energy, LLC Energy Demand Monitoring System and Smart micro-Grid Controller

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
English Translation of JP-2006184218-A (Year: 2006) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11899516B1 (en) 2023-07-13 2024-02-13 T-Mobile Usa, Inc. Creation of a digital twin for auto-discovery of hierarchy in power monitoring

Also Published As

Publication number Publication date
JP2021528637A (en) 2021-10-21
JP7146958B2 (en) 2022-10-04
JP2022174285A (en) 2022-11-22
US20190383866A1 (en) 2019-12-19
CA3103873A1 (en) 2019-12-19
US11275123B2 (en) 2022-03-15
WO2019241618A1 (en) 2019-12-19
EP3807663A1 (en) 2021-04-21
CN112534286B (en) 2023-06-20
CN112534286A (en) 2021-03-19

Similar Documents

Publication Publication Date Title
US20220163602A1 (en) System and method for electric meter outage time detection
US6611773B2 (en) Apparatus and method for measuring and reporting the reliability of a power distribution system with improved accuracy
US6671654B1 (en) Apparatus and method for measuring and reporting the reliability of a power distribution system
US8450995B2 (en) Method and apparatus for monitoring power consumption
JP5842120B2 (en) Power usage monitoring device, power usage monitoring system
US4697182A (en) Method of and system for accumulating verifiable energy demand data from remote electricity meters
AU605468B2 (en) Method of and system for accumulating verifiable energy demand data from remote electricity meters
CN106291030B (en) A kind of distribution network metering guard system
US20150212138A1 (en) Method for detecting open-circuit faults in electric power distribution system, and power distribution facilities management system
US11156641B2 (en) Power distribution network monitoring system for detecting abnormalities
WO2021176459A1 (en) A system and method of energy disaggregation using nonintrusive load monitoring
US7058523B2 (en) Electricity meter having gas consumption correction processing
WO2009058955A1 (en) Faulted circuit indicator apparatus with transmission line state display and method of use thereof
CN110018437B (en) Gateway electric energy metering device online monitoring method and system for shunt inspection
CN115685050A (en) Electric energy meter fault detection method and system
US20100305887A1 (en) Voltage monitoring in an advanced metering infrastructure
EP0248137B1 (en) System for accumulating verifiable energy demand data from remote electricity meters
KR101022288B1 (en) Apparatus for automatic greenhouse gas calculation using separated electric field sensor installation without power interruption
JP2012215391A (en) Check scheduling apparatus
CN218383263U (en) Electric energy metering management terminal with state online monitoring function
KR102120053B1 (en) AC and DC combination Watt hour meter
KR100637627B1 (en) Both transformer power load monitoring and watt meter reading remote control system
CN107422175B (en) Method and system for judging clock abnormity of power consumption information acquisition system
JP2006184218A (en) Watt-hour meter
JP5633069B2 (en) Health maintenance state estimation device and estimation method based on power consumption

Legal Events

Date Code Title Description
AS Assignment

Owner name: LANDIS+GYR LLC, INDIANA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:STENBERG, DAVID;MONROE, ROBERT;SIGNING DATES FROM 20190612 TO 20190614;REEL/FRAME:058930/0953

STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION