US20220021234A1 - Smart switching panel for secondary power supply - Google Patents

Smart switching panel for secondary power supply Download PDF

Info

Publication number
US20220021234A1
US20220021234A1 US17/490,782 US202117490782A US2022021234A1 US 20220021234 A1 US20220021234 A1 US 20220021234A1 US 202117490782 A US202117490782 A US 202117490782A US 2022021234 A1 US2022021234 A1 US 2022021234A1
Authority
US
United States
Prior art keywords
power supply
switching
condition
panel
switching elements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
US17/490,782
Inventor
Brian Northway
Michael Miller
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Briggs and Stratton LLC
Original Assignee
Briggs and Stratton LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Briggs and Stratton LLC filed Critical Briggs and Stratton LLC
Priority to US17/490,782 priority Critical patent/US20220021234A1/en
Assigned to BRIGGS & STRATTON, LLC reassignment BRIGGS & STRATTON, LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BRIGGS & STRATTON CORPORATION
Assigned to BRIGGS & STRATTON CORPORATION reassignment BRIGGS & STRATTON CORPORATION ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: MILLER, MICHAEL A., NORTHWAY, BRIAN
Publication of US20220021234A1 publication Critical patent/US20220021234A1/en
Assigned to WELLS FARGO BANK, NATIONAL ASSOCIATION, AS COLLATERAL AGENT reassignment WELLS FARGO BANK, NATIONAL ASSOCIATION, AS COLLATERAL AGENT SECURITY INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BRIGGS & STRATTON, LLC
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00002Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by monitoring
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00004Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the power network being locally controlled
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00032Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for
    • H02J13/00036Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for the elements or equipment being or involving switches, relays or circuit breakers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/061Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems for DC powered loads
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • H02J2310/12The local stationary network supplying a household or a building
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/068Electronic means for switching from one power supply to another power supply, e.g. to avoid parallel connection
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/30Wind power
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/12Energy storage units, uninterruptible power supply [UPS] systems or standby or emergency generators, e.g. in the last power distribution stages
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Definitions

  • the present disclosure generally relates to a switching panel for use with a primary power supply and a secondary power supply. More specifically, the present disclosure relates to a smart switching panel that allows each of a plurality of electric loads to be selectively and separately switched between a primary power supply and a secondary power supply.
  • Secondary power supplies can come in many different forms.
  • the secondary power supply could be a backup generator that runs on a gas supply, a grid of solar panels, a wind turbine or a bank of rechargeable electric storage batteries.
  • the rechargeable electric storage batteries are typically charged by the utility power supply but could be charged by a wind turbine or a grid of solar panels.
  • some type of switching panel or transfer switch panel is used to transfer the source of power feeding multiple electric loads from the primary, utility power supply to the secondary power supply.
  • the transfer switching panel typically transfers power from the primary power supply to the secondary power supply for a plurality of electric loads that are designated as essential loads.
  • Such a transfer switch allows for the continuous supply of power to the essential loads upon an interruption to the primary power supply.
  • this type of system functions well to provide continuous power to the essential loads, the currently available transfer switch panels underutilize the available power from the secondary power supply.
  • the present disclosure recognizes the under utilization of the secondary power supply and provides a system and method that is able to utilize the power available from one or more secondary power supplies both during power interruption from the primary power supply and when the primary power supply is available.
  • the present disclosure relates to a smart switching panel for use with a plurality of electric loads.
  • the smart switching panel includes a plurality of individual switching elements that each are connected to a primary power supply and a secondary power supply. Each of the switching elements is connected to at least one electric load and can be transitioned between first and second conditions. In the first condition, electric power from the primary power supply is supplied to the electric load. In the second condition, electric power from the secondary power supply is supplied to the electric load.
  • a current sensor is positioned between the switching element and the electric load to monitor the amount of current drawn through the switching element by the loads connected to the switching element.
  • a controller is configured to receive information as to the amount of current draw by each load from the current sensor.
  • the controller is connected to each of the switching elements through a control line to control the operative position of the switching element between the first position, the second position and an open position. In this manner, the controller can selectively connect either the primary power supply or the secondary power supply to each of the loads or disconnect the load from both power supplies to isolate the load. In an over current condition, the controller can transition the switching element to the open condition.
  • a user can monitor the operation of the smart switching system through the controller.
  • the user can select the condition of each of the switching elements to selectively control whether the primary power supply or the secondary power supply is used to drive the individual electric loads.
  • the controller can be accessed either directly or through a wireless network.
  • the controller can also be operated in an automatic mode to select which of the primary and secondary power supplies is connected to each of the loads. This determination can be based on many different variables, including the cost of electricity and the state of the secondary power supply.
  • FIG. 1 is a schematic illustration of a prior art switching system
  • FIG. 2 is a schematic illustration of the smart switching system and smart switching panel of the present disclosure for switching between the primary and secondary power supplies;
  • FIG. 3 is a second schematic illustration showing the connections between the secondary power supplies and the individual loads in a home
  • FIG. 1 illustrates a prior art configuration for switching between a primary power supply 10 and a secondary power supply 12 .
  • the primary power supply 10 is a utility that provides a source of electric power through a conventional electric grid.
  • the terms primary power supply and utility power supply will be used interchangeably throughout the present disclosure.
  • the secondary power supply 12 can be one of multiple different types of power supply systems capable of providing electric power to operate various different electric loads within a home or small business. It is contemplated that the secondary power supply 12 could be a standby generator operated off of a supply of gas, a photovoltaic generator that includes a series of separate solar cells, one or more electric storage batteries, a wind turbine or any other type of power supply that is capable of generating sufficient electric power to operate and drive electric loads.
  • the secondary power supply 12 is connected to a transfer switch panel 14 while the primary power supply 10 is connected to a main distribution panel 16 through an electricity meter 18 .
  • the electricity meter 18 monitors and measures the amount of electric power drawn by electric loads through the main distribution panel 16 .
  • the main distribution panel 16 includes a series of individual circuit breakers (not shown) that control the flow of electricity to one or more loads connected to the circuit breaker.
  • a plurality of non-essential loads 20 are connected to the individual circuit breakers contained within the main distribution panel 16 .
  • the non-essential loads 20 can be electric loads or switching circuits within a home that are connected to non-essential devices or circuits in a home, such as televisions, lighting, electrical outlets and other electric loads within the home that may not be needed upon a power failure.
  • the primary power supply 10 is interrupted, such as through a utility shutdown or interruption due to storms or other types of unexpected conditions, the electric loads designated as non-essential will not be available upon activation of the secondary power supply 12 .
  • a number of essential loads 22 are connected to the transfer switch panel 14 .
  • the switching elements in the transfer switch panel 14 allows electric power from the utility power source 10 to flow through the individual switching elements within the transfer switch panel 14 to power the essential loads 22 .
  • each of the essential loads 22 along with the non-essential loads 20 , will be powered by the primary power supply 10 .
  • the transfer switch panel 14 senses such interruption and adjusts the position of the individual switches within the transfer switch panel such that electric power from the secondary power supply 12 is provided to the essential loads 22 through the transfer switch panel 14 .
  • the transfer switch panel 14 will initiate operation of the secondary power supply 12 , such as a standby generator, before transitioning the connection to the secondary power supply. In this manner, when the primary power supply 10 is interrupted, power is not interrupted to the essential loads 22 .
  • the transfer switch panel 14 senses this condition and again adjusts the position of the switching elements contained within the transfer switch panel 14 such that power is supplied to the essential loads 22 from the primary power supply 10 rather than the secondary power supply 12 .
  • the transfer switch panel 14 may then turn off operation of the secondary power supply 12 , such as the standby generator.
  • the transfer switch panel 14 functions to provide electric power to all of the essential loads 22 from either the primary power supply 10 or the secondary power supply 12 .
  • the switching elements contained within the transfer switch panel 14 are configured such that power is supplied to the essential loads 22 from either one of the two power sources, but never both.
  • FIG. 2 illustrates an improved power supply switching system 24 constructed in accordance with the present disclosure.
  • the switching system 24 includes a primary power supply 10 and at least one secondary power supply 12 .
  • the smart switching system 24 utilizes a smart switching panel 26 to selectively control which of the two power supplies 10 , 12 are used to power the electric loads 28 .
  • the electric loads 28 are not classified as non-essential loads or essential loads as was the case in FIG. 1 .
  • the smart switching panel 26 includes a plurality of switching elements 30 that are each connected to both the primary power supply 10 and the secondary power supply 12 . It is contemplated that the switching panel 26 could include up to forty separate switching elements 30 where each of the separate switching elements 30 would control the supply of electric power to connected electric loads 28 or electric circuits. However, configurations having more than forty switching elements or fewer than forty switching elements are also contemplated. Although a single load 28 is shown in FIG. 2 as connected to each of the switching elements 30 , the load 28 could represent multiple devices, one or more electric circuits or just a single device. Each of the switching elements 30 provides electric power to the electric load 28 through a current sensor 32 . The current sensor 32 monitors the current drawn by the associated electric load 28 . It is contemplated that the combination of the switching element 30 and current sensor 32 would provide a similar function to a circuit breaker which it will replace.
  • Each of the switching elements 30 and current sensors 32 are connected to a controller 34 .
  • the controller 34 can be located either within the smart switching panel 26 or in a location near the smart switching panel 26 such that the controller 34 can control the position of the switching elements 30 and receive current sensing information from each of the plurality of current sensors 32 .
  • the controller 34 can be one of any of a wide variety of controllers, such as a microprocessor, that is able to receive information from the current sensors 32 and generate control signals to each of the switching elements 30 .
  • the switching elements 30 can be one of a wide variety of electric switching elements. It is contemplated that each of the switching elements 30 could be a MOSFET whose operative position is controlled by a control signal from the controller 34 through one of the control lines 36 . Alternatively, the switching element 30 could be an insulated-gate bipolar transistor (IGBT), which is a three-terminal power semiconductor device. In other implementations, the switching element could be a multi-position relay or any other type of switching device whose position can be controlled through signals from the controller 34 .
  • IGBT insulated-gate bipolar transistor
  • the controller 34 When the controller 34 receives a current measurement along one of the sensing lines 38 that exceeds the threshold rating, the controller 34 will generate a signal to the switching element 30 to move the switching element to an open position.
  • the controller 34 can be configured to provide an alert indicating to the home owner that the current draw exceeded the current threshold.
  • the alert could be a visual signal, an electronic message or any other type of alert that can be received by a home owner.
  • the switching element 30 will function as an enhanced circuit breaking element that can notify the home owner of the over current condition and can indicate which electric device cause such over current.
  • each of the switching elements 30 is able to selectively supply power from either the primary power supply 10 or the secondary power supply 12 to the electric load 28 connected thereto.
  • the position of the switching elements 30 is controlled independently and separately from the other switching elements 30 .
  • the controller 34 may elect to provide the electricity to the load from the secondary power supply 12 .
  • Large power consuming devices, such as air conditioners, may at the same time be connected to the primary power supply 10 .
  • the controller 34 can selectively switch one or multiple switching elements 30 to supply electricity to selected loads 28 from the secondary power supply 12 . Conversely, if the cost of electricity is very low, some or all of the loads may be connected to the primary power supply 10 . In this manner, the controller 34 can selectively connect some of the electric loads 28 to the secondary power supply 12 while connecting other electric loads 28 to the primary power supply 10 .
  • the smart switching panel 26 shown in FIG. 1 the smart switching panel 26 shown in FIG.
  • the 2 can selectively control the connection of the electric loads 28 to either the primary power supply 10 or the secondary power supply 12 based upon a variety of conditions, including the cost of electricity, the availability of the secondary power supply 12 or a wide variety of other conditions. This ability capitalizes on the presence of the secondary power supply rather than just using the secondary power supply 12 when the primary power supply 10 is not available.
  • the smart switching panel 26 could include forty or more separate switching elements 30 , each of which would be connected to one or more electric loads 28 . It is contemplated that more than one electric load or electric circuit 28 could be connected to each switching element 30 . As an example, low power-consuming electric loads and electric circuits could be grouped together for each of the switching elements 30 while large power-consuming loads, such as an air conditioner, would be connected to a separate switching element 30 (e.g. would be the only load on a switching circuit).
  • a user device 42 can be connected to the controller 34 through the wireless network 40 .
  • the wireless network 40 could be either a short-range wireless network or could be a global network, such as the internet.
  • the user device 42 would be able to both dictate the operation of the controller 34 and monitor the electricity consumption by each of the individual loads 28 monitored by the series of individual current sensors 32 . Over current situations that cause any of the switching elements 30 to open would also be reported on the user device 42 . It is contemplated that the identity of the electric device that caused the over current situation to occur could also be reported to the user.
  • the user may be able to set electricity rate thresholds using the user device 42 . For example, the user may set a price per kilowatt hour, that when exceeded, would cause the controller to switch more loads to the secondary power supply 12 .
  • the user may have three or more power sources.
  • the controller may be configured to utilize each power source to power the electrical loads 28 based on a cost of each power source. For example, a first power source may have a cost of $1.00 per kw/h, a second power source may have a cost of $0.50 per kw/h and a third power source may have a cost of $0.25 per kw/h.
  • the controller 34 may be configured to first power as many loads as possible using the third power source, then power as many remaining loads as possible with the second power sources, and finally power the remaining loads with the first power source.
  • the controller 34 may be configured to sell extra energy from one or more of the other power sources to offset the cost of powering the loads.
  • the controller 34 may have real time access to energy costs for each of the loads, allowing the controller 34 to modify the power source powering each of the loads in real time to maximize cost savings for the user.
  • the controller 34 may be configured to communicate with the utility, such that the controller can utilize one or more other power sources (e.g. second or third power sources) at different times of the day to reduce the burden on the utility grid.
  • the utility may provide additional discounted rates to the user if they can reduce energy being purchased from the grid at certain times of the day.
  • FIG. 3 further illustrates the configuration of the secondary power supply 12 .
  • the secondary power supply could be an electric storage battery array 44 or a photovoltaic generator 46 that includes a plurality of solar cells.
  • the embodiment shown in FIG. 3 illustrates two separate secondary power supplies, it is contemplated that the secondary power supply could be comprised of one or the other of the two types of sources shown.
  • Each of the secondary power supplies 12 would be connected to a DC-AC inverter 48 that converts the DC voltage source to an AC voltage source that would then be supplied to the smart switching panel 26 .
  • the operation of the inverter 48 could be monitored wirelessly from a control terminal 50 .
  • the inverter 48 functions not only to convert the DC voltage source to an AC voltage source, but also to monitor the operation and status of both types of secondary power supplies, including the electric storage batteries 44 and photovoltaic generator 46 .
  • a controller 34 can be in direct communication with the smart switching panel 26 .
  • a second controller 52 could be used to control the smart switching panel 26 through the wireless network 40 .
  • the remotely located controller 52 would thus allow a user or utility the ability to control the connection of either the secondary power supply 12 or the primary power supply 10 to each of the plurality of electric loads 28 .
  • the controller 52 could include a visual display 54 and an input device 56 that would allow the user to both monitor the current operation of the smart panel 26 and modify the operation through the input device 56 .
  • the combination of the controller 52 , display 54 and input device 56 could exist in a single unit, such as a smartphone or tablet computer.
  • the smart switching panel 26 allows for the operation of one or more of the electric loads 28 from the secondary power supply 12 even when the primary power supply 10 is available. Unlike the prior art system shown in FIG. 1 , the smart switching panel 26 can switch the supply of electricity from either the primary power supply 10 or secondary power supply 12 to individual loads at any time when both the primary power supply 10 and the secondary power supply 12 are available.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Direct Current Feeding And Distribution (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A smart switching panel for selectively connecting either a primary power supply or a secondary power supply to a plurality of electric loads. The switching panel includes a plurality of switching elements each connected to both the primary and secondary power supplies. A controller of the switching panel operates to cause the switching element to transition between a first position in which the primary power supply is connected to the electric load, a second position in which the secondary power supply is connected to the electric load and an open condition. A current sensor is positioned to monitor the amount of current drawn by the electric load and is connected to the controller such that the controller can monitor the amount of current drawn by each of the electric loads. The controller can transition each of the switching elements to the open condition when the current draw exceeds a current threshold.

Description

    CROSS REFERENCE TO RELATED APPLICATION
  • The present application is based on and claims priority to U.S. Provisional Patent Application Ser. No. 62/596,450, filed Dec. 8, 2017, the disclosure of which is incorporated herein by reference.
  • BACKGROUND
  • The present disclosure generally relates to a switching panel for use with a primary power supply and a secondary power supply. More specifically, the present disclosure relates to a smart switching panel that allows each of a plurality of electric loads to be selectively and separately switched between a primary power supply and a secondary power supply.
  • Presently, many different types of secondary power supplies are being utilized at a home or small business level to provide either an alternative to the utility power supply or to provide back up power upon a loss of the primary, utility power supply. These different types of secondary power supplies are designed to replace the utility power supply upon power loss or to replace the utility power supply to reduce the cost of energy consumption at the home or business.
  • Secondary power supplies can come in many different forms. For example, the secondary power supply could be a backup generator that runs on a gas supply, a grid of solar panels, a wind turbine or a bank of rechargeable electric storage batteries. The rechargeable electric storage batteries are typically charged by the utility power supply but could be charged by a wind turbine or a grid of solar panels. In each case, some type of switching panel or transfer switch panel is used to transfer the source of power feeding multiple electric loads from the primary, utility power supply to the secondary power supply. The transfer switching panel typically transfers power from the primary power supply to the secondary power supply for a plurality of electric loads that are designated as essential loads. Such a transfer switch allows for the continuous supply of power to the essential loads upon an interruption to the primary power supply. Although this type of system functions well to provide continuous power to the essential loads, the currently available transfer switch panels underutilize the available power from the secondary power supply.
  • Therefore, a need exists for an improved switching panel to maximize the usage of the available secondary power supply. The present disclosure recognizes the under utilization of the secondary power supply and provides a system and method that is able to utilize the power available from one or more secondary power supplies both during power interruption from the primary power supply and when the primary power supply is available.
  • SUMMARY
  • The present disclosure relates to a smart switching panel for use with a plurality of electric loads. The smart switching panel includes a plurality of individual switching elements that each are connected to a primary power supply and a secondary power supply. Each of the switching elements is connected to at least one electric load and can be transitioned between first and second conditions. In the first condition, electric power from the primary power supply is supplied to the electric load. In the second condition, electric power from the secondary power supply is supplied to the electric load.
  • A current sensor is positioned between the switching element and the electric load to monitor the amount of current drawn through the switching element by the loads connected to the switching element.
  • A controller is configured to receive information as to the amount of current draw by each load from the current sensor. The controller is connected to each of the switching elements through a control line to control the operative position of the switching element between the first position, the second position and an open position. In this manner, the controller can selectively connect either the primary power supply or the secondary power supply to each of the loads or disconnect the load from both power supplies to isolate the load. In an over current condition, the controller can transition the switching element to the open condition.
  • A user can monitor the operation of the smart switching system through the controller. The user can select the condition of each of the switching elements to selectively control whether the primary power supply or the secondary power supply is used to drive the individual electric loads. The controller can be accessed either directly or through a wireless network. The controller can also be operated in an automatic mode to select which of the primary and secondary power supplies is connected to each of the loads. This determination can be based on many different variables, including the cost of electricity and the state of the secondary power supply.
  • Various other features, objects and advantages of the invention will be made apparent from the following description taken together with the drawings.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • The drawings illustrate the best mode presently contemplated of carrying out the disclosure. In the drawings:
  • FIG. 1 is a schematic illustration of a prior art switching system;
  • FIG. 2 is a schematic illustration of the smart switching system and smart switching panel of the present disclosure for switching between the primary and secondary power supplies; and
  • FIG. 3 is a second schematic illustration showing the connections between the secondary power supplies and the individual loads in a home
  • DETAILED DESCRIPTION
  • FIG. 1 illustrates a prior art configuration for switching between a primary power supply 10 and a secondary power supply 12. In the embodiment shown in FIG. 1, the primary power supply 10 is a utility that provides a source of electric power through a conventional electric grid. The terms primary power supply and utility power supply will be used interchangeably throughout the present disclosure.
  • The secondary power supply 12 can be one of multiple different types of power supply systems capable of providing electric power to operate various different electric loads within a home or small business. It is contemplated that the secondary power supply 12 could be a standby generator operated off of a supply of gas, a photovoltaic generator that includes a series of separate solar cells, one or more electric storage batteries, a wind turbine or any other type of power supply that is capable of generating sufficient electric power to operate and drive electric loads.
  • In the embodiment shown in FIG. 1, the secondary power supply 12 is connected to a transfer switch panel 14 while the primary power supply 10 is connected to a main distribution panel 16 through an electricity meter 18. As is well known, the electricity meter 18 monitors and measures the amount of electric power drawn by electric loads through the main distribution panel 16. The main distribution panel 16 includes a series of individual circuit breakers (not shown) that control the flow of electricity to one or more loads connected to the circuit breaker. In the embodiment shown in FIG. 1, a plurality of non-essential loads 20 are connected to the individual circuit breakers contained within the main distribution panel 16. The non-essential loads 20 can be electric loads or switching circuits within a home that are connected to non-essential devices or circuits in a home, such as televisions, lighting, electrical outlets and other electric loads within the home that may not be needed upon a power failure. When the primary power supply 10 is interrupted, such as through a utility shutdown or interruption due to storms or other types of unexpected conditions, the electric loads designated as non-essential will not be available upon activation of the secondary power supply 12.
  • As illustrated in FIG. 1, a number of essential loads 22 are connected to the transfer switch panel 14. During normal operation of the primary power supply 10, the switching elements in the transfer switch panel 14 allows electric power from the utility power source 10 to flow through the individual switching elements within the transfer switch panel 14 to power the essential loads 22. If the primary power supply 10 is operating normally, each of the essential loads 22, along with the non-essential loads 20, will be powered by the primary power supply 10. However, when the primary power supply 10 is interrupted, the transfer switch panel 14 senses such interruption and adjusts the position of the individual switches within the transfer switch panel such that electric power from the secondary power supply 12 is provided to the essential loads 22 through the transfer switch panel 14. In some embodiments, the transfer switch panel 14 will initiate operation of the secondary power supply 12, such as a standby generator, before transitioning the connection to the secondary power supply. In this manner, when the primary power supply 10 is interrupted, power is not interrupted to the essential loads 22.
  • When the primary power supply 10 again comes online, the transfer switch panel 14 senses this condition and again adjusts the position of the switching elements contained within the transfer switch panel 14 such that power is supplied to the essential loads 22 from the primary power supply 10 rather than the secondary power supply 12. The transfer switch panel 14 may then turn off operation of the secondary power supply 12, such as the standby generator.
  • As can be understood in FIG. 1, the transfer switch panel 14 functions to provide electric power to all of the essential loads 22 from either the primary power supply 10 or the secondary power supply 12. The switching elements contained within the transfer switch panel 14 are configured such that power is supplied to the essential loads 22 from either one of the two power sources, but never both.
  • FIG. 2 illustrates an improved power supply switching system 24 constructed in accordance with the present disclosure. As with the embodiment shown in FIG. 1, the switching system 24 includes a primary power supply 10 and at least one secondary power supply 12. However, unlike the system shown in FIG. 1, the smart switching system 24 utilizes a smart switching panel 26 to selectively control which of the two power supplies 10, 12 are used to power the electric loads 28. In the embodiment shown in FIG. 2, the electric loads 28 are not classified as non-essential loads or essential loads as was the case in FIG. 1.
  • The smart switching panel 26 includes a plurality of switching elements 30 that are each connected to both the primary power supply 10 and the secondary power supply 12. It is contemplated that the switching panel 26 could include up to forty separate switching elements 30 where each of the separate switching elements 30 would control the supply of electric power to connected electric loads 28 or electric circuits. However, configurations having more than forty switching elements or fewer than forty switching elements are also contemplated. Although a single load 28 is shown in FIG. 2 as connected to each of the switching elements 30, the load 28 could represent multiple devices, one or more electric circuits or just a single device. Each of the switching elements 30 provides electric power to the electric load 28 through a current sensor 32. The current sensor 32 monitors the current drawn by the associated electric load 28. It is contemplated that the combination of the switching element 30 and current sensor 32 would provide a similar function to a circuit breaker which it will replace.
  • Each of the switching elements 30 and current sensors 32 are connected to a controller 34. The controller 34 can be located either within the smart switching panel 26 or in a location near the smart switching panel 26 such that the controller 34 can control the position of the switching elements 30 and receive current sensing information from each of the plurality of current sensors 32. The controller 34 can be one of any of a wide variety of controllers, such as a microprocessor, that is able to receive information from the current sensors 32 and generate control signals to each of the switching elements 30.
  • The switching elements 30 can be one of a wide variety of electric switching elements. It is contemplated that each of the switching elements 30 could be a MOSFET whose operative position is controlled by a control signal from the controller 34 through one of the control lines 36. Alternatively, the switching element 30 could be an insulated-gate bipolar transistor (IGBT), which is a three-terminal power semiconductor device. In other implementations, the switching element could be a multi-position relay or any other type of switching device whose position can be controlled through signals from the controller 34.
  • When the controller 34 receives a current measurement along one of the sensing lines 38 that exceeds the threshold rating, the controller 34 will generate a signal to the switching element 30 to move the switching element to an open position. The controller 34 can be configured to provide an alert indicating to the home owner that the current draw exceeded the current threshold. The alert could be a visual signal, an electronic message or any other type of alert that can be received by a home owner. In this manner, the switching element 30 will function as an enhanced circuit breaking element that can notify the home owner of the over current condition and can indicate which electric device cause such over current.
  • As can be understood by the configuration shown in FIG. 2, each of the switching elements 30 is able to selectively supply power from either the primary power supply 10 or the secondary power supply 12 to the electric load 28 connected thereto. The position of the switching elements 30 is controlled independently and separately from the other switching elements 30. Thus, if one of the loads 28 is consuming only a very small supply of electricity, the controller 34 may elect to provide the electricity to the load from the secondary power supply 12. Large power consuming devices, such as air conditioners, may at the same time be connected to the primary power supply 10.
  • If the controller 34 receives information through the wireless network 40 that the cost of electricity from the primary power supply 10 is very high (e.g. exceeds a predetermined threshold), the controller 34 can selectively switch one or multiple switching elements 30 to supply electricity to selected loads 28 from the secondary power supply 12. Conversely, if the cost of electricity is very low, some or all of the loads may be connected to the primary power supply 10. In this manner, the controller 34 can selectively connect some of the electric loads 28 to the secondary power supply 12 while connecting other electric loads 28 to the primary power supply 10. Unlike past embodiments shown in FIG. 1, the smart switching panel 26 shown in FIG. 2 can selectively control the connection of the electric loads 28 to either the primary power supply 10 or the secondary power supply 12 based upon a variety of conditions, including the cost of electricity, the availability of the secondary power supply 12 or a wide variety of other conditions. This ability capitalizes on the presence of the secondary power supply rather than just using the secondary power supply 12 when the primary power supply 10 is not available.
  • In the embodiment shown in FIG. 2, the smart switching panel 26 could include forty or more separate switching elements 30, each of which would be connected to one or more electric loads 28. It is contemplated that more than one electric load or electric circuit 28 could be connected to each switching element 30. As an example, low power-consuming electric loads and electric circuits could be grouped together for each of the switching elements 30 while large power-consuming loads, such as an air conditioner, would be connected to a separate switching element 30 (e.g. would be the only load on a switching circuit).
  • As illustrated in FIG. 2, a user device 42 can be connected to the controller 34 through the wireless network 40. The wireless network 40 could be either a short-range wireless network or could be a global network, such as the internet. Through this connection, the user device 42 would be able to both dictate the operation of the controller 34 and monitor the electricity consumption by each of the individual loads 28 monitored by the series of individual current sensors 32. Over current situations that cause any of the switching elements 30 to open would also be reported on the user device 42. It is contemplated that the identity of the electric device that caused the over current situation to occur could also be reported to the user. In some embodiments, the user may be able to set electricity rate thresholds using the user device 42. For example, the user may set a price per kilowatt hour, that when exceeded, would cause the controller to switch more loads to the secondary power supply 12.
  • In some embodiments, the user may have three or more power sources. The controller may be configured to utilize each power source to power the electrical loads 28 based on a cost of each power source. For example, a first power source may have a cost of $1.00 per kw/h, a second power source may have a cost of $0.50 per kw/h and a third power source may have a cost of $0.25 per kw/h. The controller 34 may be configured to first power as many loads as possible using the third power source, then power as many remaining loads as possible with the second power sources, and finally power the remaining loads with the first power source. In some embodiments, such as where one of the power sources is a utility power source, the controller 34 may be configured to sell extra energy from one or more of the other power sources to offset the cost of powering the loads. In some embodiments, the controller 34 may have real time access to energy costs for each of the loads, allowing the controller 34 to modify the power source powering each of the loads in real time to maximize cost savings for the user. Further, the controller 34 may be configured to communicate with the utility, such that the controller can utilize one or more other power sources (e.g. second or third power sources) at different times of the day to reduce the burden on the utility grid. In some instances, the utility may provide additional discounted rates to the user if they can reduce energy being purchased from the grid at certain times of the day.
  • FIG. 3 further illustrates the configuration of the secondary power supply 12. In the embodiment shown in FIG. 3, the secondary power supply could be an electric storage battery array 44 or a photovoltaic generator 46 that includes a plurality of solar cells. Although the embodiment shown in FIG. 3 illustrates two separate secondary power supplies, it is contemplated that the secondary power supply could be comprised of one or the other of the two types of sources shown.
  • Each of the secondary power supplies 12 would be connected to a DC-AC inverter 48 that converts the DC voltage source to an AC voltage source that would then be supplied to the smart switching panel 26. The operation of the inverter 48 could be monitored wirelessly from a control terminal 50. The inverter 48 functions not only to convert the DC voltage source to an AC voltage source, but also to monitor the operation and status of both types of secondary power supplies, including the electric storage batteries 44 and photovoltaic generator 46.
  • As discussed previously, a controller 34 can be in direct communication with the smart switching panel 26. Alternatively, or in combination, a second controller 52 could be used to control the smart switching panel 26 through the wireless network 40. The remotely located controller 52 would thus allow a user or utility the ability to control the connection of either the secondary power supply 12 or the primary power supply 10 to each of the plurality of electric loads 28. It is contemplated that the controller 52 could include a visual display 54 and an input device 56 that would allow the user to both monitor the current operation of the smart panel 26 and modify the operation through the input device 56. The combination of the controller 52, display 54 and input device 56 could exist in a single unit, such as a smartphone or tablet computer.
  • As can be understood in the drawing figures and the above description, the smart switching panel 26 allows for the operation of one or more of the electric loads 28 from the secondary power supply 12 even when the primary power supply 10 is available. Unlike the prior art system shown in FIG. 1, the smart switching panel 26 can switch the supply of electricity from either the primary power supply 10 or secondary power supply 12 to individual loads at any time when both the primary power supply 10 and the secondary power supply 12 are available.
  • This written description uses examples to disclose the invention, including the best mode, and also to enable any person skilled in the art to make and use the invention. The patentable scope of the invention is defined by the claims, and may include other examples that occur to those skilled in the art. Such other examples are intended to be within the scope of the claims if they have structural elements that do not differ from the literal language of the claims, or if they include equivalent structural elements with insubstantial differences from the literal languages of the claims.

Claims (21)

1-20. (canceled)
21. A switching panel for providing electrical power to a plurality of electric loads from a primary power supply or a secondary power supply, comprising:
a plurality of switching elements each connected to both the primary power supply and the secondary power supply and to at least one electric load within the plurality of electric loads, wherein each of the plurality of switching elements is operable in a first condition and a second condition;
a controller operatively connected to each of the plurality of switching elements, wherein the controller is operable to independently control a condition of each of the switching elements; and
a plurality of current sensors each in communication with the controller, wherein each of the current sensors is positioned between one of the switching elements and at least one electric load of the plurality of electric loads associated with the switching element, wherein each of the plurality of current sensors is operable to detect a current draw of the at least one electric load associated with the switching element;
wherein the primary power supply and secondary power supply are configured to supply power to the switching panel simultaneously; and
wherein the controller is configured to transition one or more of the plurality of switching elements from the first condition to the second condition upon receiving an indication that the detected current draw of the electric load associated with the switching element is below a threshold current value.
22. The switching panel of claim 21, wherein each of the plurality of switching elements is configured to transition to an open condition upon receiving an indication from a corresponding one of the current sensors that a sensed current downstream of the switching element has exceeded a second threshold current value.
23. The switching panel of claim 22, wherein the at least one electric load associated with the switching element is connected to the primary power supply when the switching element is in the first condition, is connected to the secondary power supply when the switching element is in the second condition, and is disconnected from both the primary power supply and the secondary power supply when the switching element is in the open condition.
24. The switching panel of claim 22, wherein the primary power supply is a utility power supply.
25. The switching panel of claim 22, wherein the secondary power supply is chosen from a group consisting of: solar cells, electric storage batteries, a wind turbine, a photovoltaic generator, and a generator.
26. The switching panel of claim 25, wherein the secondary power supply includes two or more power sources.
27. The switching panel of claim 21, further comprising a tertiary power supply, wherein the tertiary power supply is connected to each of the plurality of switching elements, wherein each of the plurality of switching elements is further operable in a third condition, wherein the tertiary power supply is configured to supply power to the switching panel simultaneously with the primary power supply and the secondary power supply, and wherein the controller is configured to transition one or more of the plurality of switching elements to the third condition to connect the tertiary power supply to at least one electric load of the plurality of electric loads.
28. The switching panel of claim 21, wherein each of the switching elements is a MOSFET.
29. The switching panel of claim 21, wherein each of the switching elements is an insulated-gate bipolar transistor.
30. The switching panel of claim 21, wherein each of the switching elements is a multi-position relay.
31. The switching panel of claim 21, wherein the secondary power supply is connected to a DC-AC inverter, wherein the DC-AC inverter is configured to supply AC electrical power to the plurality of switching elements.
32. A switching panel for providing electrical power to a plurality of electric loads from multiple power supplies, comprising:
a plurality of switching elements, each switching element being connected to each of a first power supply and a second power supply, and configured to transmit electrical power received from the first power supply or the second power supply to at least one electric load of the plurality of electric loads, each of the plurality of switching elements being operable in a first condition and a second condition;
a controller operatively connected to each of the plurality of switching elements, wherein the controller is operable to independently control a condition of each of the plurality of switching elements; and
a plurality of current sensors each in communication with the controller, wherein each of the current sensors is positioned between one of the switching elements and the at least one electric load of the plurality of electric loads associated with the switching element, wherein each of the plurality of current sensors is operable to detect a current draw of the at least one electric load;
wherein the controller is configured to transition one or more of the plurality of switching elements from the first condition to the second condition upon receiving an indication that an energy cost associated with the first power supply exceeds a threshold value; and
wherein the first power supply and second power supply are configured to supply power to the switching panel simultaneously.
33. The switching panel of claim 32, wherein each of the plurality of switching elements is configured to transition to an open condition upon receiving an indication from a corresponding one of the current sensors that a sensed current downstream of the switching element has exceeded a threshold current value.
34. The switching panel of claim 33, wherein the at least one electric load associated with the switching element is connected to the first power supply when the switching element is in the first condition, is connected to the second power supply when the switching element is in the second condition, and is disconnected from both the first power supply and the second power supply when the switching element is in the open condition.
35. The switching panel of claim 32, wherein the first power supply is a utility power supply.
36. The switching panel of claim 32, wherein the second power supply is chosen from a group consisting of: solar cells, electric storage batteries, a wind turbine, a photovoltaic generator, and a generator.
37. The switching panel of claim 32, wherein the second power supply is connected to a DC-AC inverter, wherein the DC-AC inverter is configured to supply AC electrical power to the plurality of switching elements.
38. The switching panel of claim 32, further comprising a third power supply, wherein the third power supply is connected to each of the plurality of switching elements, wherein each of the plurality of switching elements is further operable in a third condition, wherein the third power supply is configured to supply power to the switching panel simultaneously with the first power supply and the second power supply, and wherein the controller is configured to transition one or more of the plurality of switching elements to the third condition to connect the third power supply to at least one electric load of the plurality of electric loads.
39. A switching panel for providing electrical power to an electric load from multiple power supplies configured to supply power to the switching panel simultaneously, the switching panel comprising:
a switching element connected to each of a first power supply and a second power supply, and configured to transmit electrical power received from the first power supply or the second power supply to at least one electric load coupled to the switching element, the switching element being operable in a first condition, a second condition, and an open condition;
a controller operatively connected to the switching element and operable to control a condition of the switching element; and
a current sensor in communication with the controller, wherein the current sensor is positioned between the switching element and the electric load, wherein the current sensor is operable to detect a current draw of the electric load;
wherein the controller is configured to transition the switching element from the first condition to the second condition upon receiving an indication that the detected current draw of the electric load associated is below a threshold current value.
40. The switching panel of claim 39, wherein a DC-AC inverter is positioned between the second power supply and the switching panel, the DC-AC inverter being configured invert DC electrical power from the second power supply into AC electrical power to supply AC electrical power to the switching element.
US17/490,782 2017-12-08 2021-09-30 Smart switching panel for secondary power supply Pending US20220021234A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US17/490,782 US20220021234A1 (en) 2017-12-08 2021-09-30 Smart switching panel for secondary power supply

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US201762596450P 2017-12-08 2017-12-08
US16/211,812 US11139681B2 (en) 2017-12-08 2018-12-06 Smart switching panel for secondary power supply
US17/490,782 US20220021234A1 (en) 2017-12-08 2021-09-30 Smart switching panel for secondary power supply

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US16/211,812 Continuation US11139681B2 (en) 2017-12-08 2018-12-06 Smart switching panel for secondary power supply

Publications (1)

Publication Number Publication Date
US20220021234A1 true US20220021234A1 (en) 2022-01-20

Family

ID=66697350

Family Applications (2)

Application Number Title Priority Date Filing Date
US16/211,812 Active 2039-05-01 US11139681B2 (en) 2017-12-08 2018-12-06 Smart switching panel for secondary power supply
US17/490,782 Pending US20220021234A1 (en) 2017-12-08 2021-09-30 Smart switching panel for secondary power supply

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US16/211,812 Active 2039-05-01 US11139681B2 (en) 2017-12-08 2018-12-06 Smart switching panel for secondary power supply

Country Status (1)

Country Link
US (2) US11139681B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11509165B2 (en) * 2017-08-24 2022-11-22 Myers Emergency Power Systems Llc Automatic transfer switch for lighting loads with integral load shedding by dimming control
US11581725B2 (en) 2018-07-07 2023-02-14 Intelesol, Llc Solid-state power interrupters
US11349296B2 (en) 2018-10-01 2022-05-31 Intelesol, Llc Solid-state circuit interrupters
US11170964B2 (en) 2019-05-18 2021-11-09 Amber Solutions, Inc. Intelligent circuit breakers with detection circuitry configured to detect fault conditions
US11670946B2 (en) 2020-08-11 2023-06-06 Amber Semiconductor, Inc. Intelligent energy source monitoring and selection control system
KR20220095608A (en) * 2020-12-30 2022-07-07 에스케이하이닉스 주식회사 Auxiliary power management device and electronic system including the same

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090063228A1 (en) * 2007-08-28 2009-03-05 Forbes Jr Joseph W Method and apparatus for providing a virtual electric utility
DK2372861T3 (en) * 2010-04-01 2013-03-25 Racktivity Nv DYNAMIC LOAD EQUIPMENT CONTROL UNIT
US8570715B2 (en) * 2011-06-21 2013-10-29 Darcy Cook Load center with branch-level current sensors integrated into power buses on a unit with on-board circuit breaker mounts
JP6480096B2 (en) * 2013-04-19 2019-03-06 京セラ株式会社 Power control system, power control apparatus, and control method for power control system
US10014713B1 (en) * 2014-07-31 2018-07-03 Amazon Technologies, Inc. Redundant secondary power support system
US9728965B2 (en) * 2014-09-29 2017-08-08 The United States Of America As Represented By The Secretary Of The Army Scalable universal power supply and power converter
JP6694592B2 (en) * 2016-07-07 2020-05-20 株式会社オートネットワーク技術研究所 Relay device

Also Published As

Publication number Publication date
US20190181679A1 (en) 2019-06-13
US11139681B2 (en) 2021-10-05

Similar Documents

Publication Publication Date Title
US20220021234A1 (en) Smart switching panel for secondary power supply
EP2924840B1 (en) Power supply system, power conversion apparatus, and measurement point switching apparatus
JP6155532B2 (en) Power supply system
EP2451042A1 (en) Power distribution system
US9923357B2 (en) Power supply system, distributed power source system, management apparatus, and power supply control method
US9711967B1 (en) Off grid backup inverter automatic transfer switch
KR101220773B1 (en) Intelligent Cabinet-Panel Having Energy Managing Function in the Smart Grid Environment
KR101264142B1 (en) New and renewable energy system for home and/or microgrid application
US20120235492A1 (en) Power supply system
JP6190224B2 (en) Power storage system
WO2012165154A1 (en) Power supply system
KR20170038640A (en) Power control system and method for ESS apparatus
CN109891705B (en) Power supply device and power storage device
EP3439133B1 (en) Power supply device, power supply method, and power storage device
JP2015220791A (en) Power supply control device
JP2019205309A (en) Power supply system
JP5506559B2 (en) Power shut-off device, table tap and distribution board
EP3032682B1 (en) Power supply system, power conversion device, and distribution board
JP2012253842A (en) Power supply system
JP2016158496A (en) Distributed power supply system
JP2015220821A (en) Power supply system and power supply control device
JP2014217177A (en) Power supply system and power storage device
WO2014027462A1 (en) Energy management device, and energy-management-device control method
JP6272123B2 (en) Power supply control device
JP6299514B2 (en) Power supply system

Legal Events

Date Code Title Description
AS Assignment

Owner name: BRIGGS & STRATTON, LLC, WISCONSIN

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BRIGGS & STRATTON CORPORATION;REEL/FRAME:057678/0614

Effective date: 20200917

Owner name: BRIGGS & STRATTON CORPORATION, WISCONSIN

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:NORTHWAY, BRIAN;MILLER, MICHAEL A.;REEL/FRAME:057660/0801

Effective date: 20181204

AS Assignment

Owner name: WELLS FARGO BANK, NATIONAL ASSOCIATION, AS COLLATERAL AGENT, ILLINOIS

Free format text: SECURITY INTEREST;ASSIGNOR:BRIGGS & STRATTON, LLC;REEL/FRAME:062729/0725

Effective date: 20230213

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED