US20190295010A1 - System and method for automated cross-dock operations - Google Patents
System and method for automated cross-dock operations Download PDFInfo
- Publication number
- US20190295010A1 US20190295010A1 US16/435,997 US201916435997A US2019295010A1 US 20190295010 A1 US20190295010 A1 US 20190295010A1 US 201916435997 A US201916435997 A US 201916435997A US 2019295010 A1 US2019295010 A1 US 2019295010A1
- Authority
- US
- United States
- Prior art keywords
- dock
- freight
- instructions
- cross
- deck
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G63/00—Transferring or trans-shipping at storage areas, railway yards or harbours or in opening mining cuts; Marshalling yard installations
- B65G63/002—Transferring or trans-shipping at storage areas, railway yards or harbours or in opening mining cuts; Marshalling yard installations for articles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G67/00—Loading or unloading vehicles
- B65G67/02—Loading or unloading land vehicles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G69/00—Auxiliary measures taken, or devices used, in connection with loading or unloading
- B65G69/28—Loading ramps; Loading docks
- B65G69/30—Non-permanently installed loading ramps, e.g. transportable
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
- G06Q10/047—Optimisation of routes or paths, e.g. travelling salesman problem
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/08—Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q10/083—Shipping
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G07—CHECKING-DEVICES
- G07C—TIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
- G07C5/00—Registering or indicating the working of vehicles
- G07C5/08—Registering or indicating performance data other than driving, working, idle, or waiting time, with or without registering driving, working, idle or waiting time
- G07C5/0841—Registering performance data
- G07C5/085—Registering performance data using electronic data carriers
- G07C5/0866—Registering performance data using electronic data carriers the electronic data carrier being a digital video recorder in combination with video camera
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/08—Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q10/087—Inventory or stock management, e.g. order filling, procurement or balancing against orders
-
- G—PHYSICS
- G08—SIGNALLING
- G08G—TRAFFIC CONTROL SYSTEMS
- G08G1/00—Traffic control systems for road vehicles
- G08G1/01—Detecting movement of traffic to be counted or controlled
- G08G1/017—Detecting movement of traffic to be counted or controlled identifying vehicles
-
- G—PHYSICS
- G08—SIGNALLING
- G08G—TRAFFIC CONTROL SYSTEMS
- G08G1/00—Traffic control systems for road vehicles
- G08G1/20—Monitoring the location of vehicles belonging to a group, e.g. fleet of vehicles, countable or determined number of vehicles
- G08G1/205—Indicating the location of the monitored vehicles as destination, e.g. accidents, stolen, rental
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04N—PICTORIAL COMMUNICATION, e.g. TELEVISION
- H04N7/00—Television systems
- H04N7/18—Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
- H04N7/181—Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast for receiving images from a plurality of remote sources
Definitions
- the present invention relates to the field of freight, shipping, and dock management; more particularly, to an automated cross-dock management system, method, and/or apparatus; even more particularly, to an optimized and automated cross-dock management system, method, and/or apparatus for use with less-than-truckload carriers.
- LTL less-than-truckload
- cross-docking Once freight is picked up, it is brought back to a facility where it is transferred across a dock (a process commonly referred to as “cross-docking”). This process typically involves manually unloading the load (or portion thereof) from one trailer and loading it onto another.
- An system for improving cross-dock operations is described in U.S. Pat. No. 9,367,827, issued Jun. 14, 2016, the entire content of which is hereby incorporated by reference in its entirety.
- AGVs automated guided vehicles
- AGVs are typically not suited for cross-dock operations, especially in an LTL environment.
- an AGV may need to convey an entire movable platform (MP) which can weigh up to 24,000 pounds (or more).
- MP movable platform
- AGVs currently being used in most warehouses can typically only convey a few hundred pounds at most.
- most current AGVs can only move in a grid-like pattern whereas cross-dock operations require much more advanced collision avoidance systems because manual workers may also be present.
- the AGVs may need to perform a variety of functions such as moving MPs, moving decks, and/or moving individual pieces of freight.
- Current AGVs and cross-dock systems are not equipped to handle and/or calculate these types of moves. What is needed is a cross-dock management system capable of effectively using AGVs to supplement or entirely replace manual moves in a cross-dock environment.
- Such a cross-dock system must be highly adaptable to handle exceptions, such as AGV recharging or maintenance, and should enable cross-dock operations to be extended to operate 24 hours a day, seven days a week
- the present invention provides an automated cross-dock management system configured to optimize moves on a cross-dock.
- the automated cross-dock management system uses inbound manifest data to calculate ordered move instructions for all inbound movable platforms, inbound modular decks, and inbound freight.
- the ordered move instructions can be assigned to be carried out by manual conveyance vehicles or by AGVs based upon a plurality of criteria.
- the automated cross-dock management system is also able to detect damaged freight on the cross-dock using a combination of video streams from video cameras.
- FIG. 1 depicts a perspective view of a typical dock currently used by LTL carriers.
- FIG. 2A depicts an optimized dock according to a first aspect of the present invention.
- FIG. 2B depicts another optimized dock according to a second aspect of the present invention.
- FIGS. 3A and 3B depicts a movable platform with decks divided into sections and subsections using identifiers.
- FIG. 4 depicts a system diagram showing the hardware and resources employed during operation of the optimized dock of FIGS. 2A and 2B .
- FIG. 5 depicts a sample instruction screen used by a worker to execute a move instruction.
- FIG. 6 depicts a flowchart showing the steps used in unloading and loading a movable platform.
- FIG. 7A depicts a flowchart showing the steps used to move a deck using a pair of AGVs.
- FIG. 7B depicts a flowchart showing the steps used to move a deck using a single AGV.
- FIG. 8 depicts a flowchart showing the steps used to execute freight instructions.
- FIG. 9 depicts a flowchart showing the steps used to determine movement instructions for the movement database using input data.
- FIG. 10 depicts the dock of FIG. 1 configured to be used with movable platforms.
- FIG. 11 depicts a shared optimized dock in accordance with the present invention.
- FIG. 12 depicts a flowchart showing the steps used when two or more shippers share the same optimized dock.
- the word “exemplary” means “serving as an example, instance, or illustration.”
- the embodiments described herein are not limiting, but rather are exemplary only. It should be understood that the described embodiments are not necessarily to be construed as preferred or advantageous over other embodiments.
- the terms “embodiments of the invention,” “embodiments,” or “invention” do not require that all embodiments of the invention include the discussed feature, advantage, or mode of operation.
- LTL carriers typically transport freight originating from a common origin destined to many different locations around the country via a system of terminals.
- the freight is brought back to a facility where it is transferred across a dock 102 (cross-docked), which involves unloading the freight from one trailer and loading it onto another.
- Freight can move through one or more terminals 100 (e.g., small terminals or distribution centers) in a hub-and-spoke network until the freight reaches its destination terminal and/or is delivered.
- freight may be received at its origin via one of several methods: loose pallets, boxes, cartons, crates, drums, barrels, or the like; by MP 204 with decks 336 ( FIGS. 3A-3B ), an 8′ ⁇ 8′ (or similarly sized) platform used for double or triple stacking of freight on a MP 204 by which cargo consisting of loose pallets, boxes, cartons, crates or the like are stacked upon going to either a single destination or multiple destinations; by single MP 204 , MP 204 without decks 336 as described in U.S. Pat. No. 9,367,827, issued Jun.
- decks 336 and cargo consisting of loose pallets, boxes, cartons, crates or the like are stacked upon going to either a single destination or multiple destinations; or by multiple MPs 204 such as in a full truckload, rail container, ocean container, or the like consisting of two or more MPs 204 going to either a single destination or multiple destinations.
- freight having non-standard dimensions may be combined and/or placed in standardized containers having known dimensions.
- standardized containers allow for easier moving of the freight either by a manual move or AGV move.
- the standardized containers primarily function to make the cargo “AGV-friendly” or “AGV-compatible.”
- FIG. 1 depicted is a typical terminal 100 used by current LTL carriers.
- dock 102 is long and narrow. Typically, dock 102 is 60 feet in width or less.
- An inbound door 104 of dock 102 is used for unloading trailers 110 and a second (outbound) door 106 is used for loading trailers 110 .
- Unloading is generally sequenced in a last in, first out (LIFO) process.
- LIFO last in, first out
- freight 112 is conveyed across dock 102 using a conveyance vehicle 114 , such as a forklift.
- the conveyance vehicle as referred to herein, may be manually operated, remotely operated, or completely autonomous (AGV). Further, at least one load door is required for every load point, but multiple doors may be necessary for multiple schedules to the same load point.
- freight 112 Since loading is generally sequenced from the nose to the rear, freight 112 is typically docked in a bay outside the door to allow for co-mingling of the freight 112 on the trailer 110 for the optimum load. This practice creates congestion, wasteful re-handling time, and additional cost. Also, because dock 102 is long and narrow, the maneuverability of workers 108 using conveyance vehicles 114 is severely limited, especially when there is a large quantity of freight 112 on dock 102 .
- An optimized cross-dock management system 200 in accordance with a first embodiment of the present invention transforms the process for moving LTL freight across the dock 202 by adding a novel combination of mechanics, technology, and automation as depicted in FIG. 2A .
- an optimized dock 202 may be employed that is two to three times wider and two to three times shorter than a traditional dock; thus, an optimized dock 202 may more closely resemble a square or large rectangle. Designed properly, an optimized dock 202 may require one-third the number of doors as dock 102 without sacrificing capacity.
- the optimized dock can 202 be wide enough such that a predetermined number (e.g., 2 to 10, more preferably 3 to 9, most preferably, 5 to 7) of MPs 204 can be spaced out per dock door.
- the distance between dock doors may be, for example, 12 feet or more.
- MPs 204 allows for an entire trailer to be unloaded or loaded and conveyed in less than five minutes, thus increasing efficiency and saving money.
- MPs 204 may be used to provide optimized load building and planning via real-time data and sensing technology, such as barcodes (2D or 3D), radio-frequency identification (RFID) tags, three dimensional (3D) imaging, Bluetooth low energy (BLE), magnetics, sensor fusion, global positioning system (GPS) tracking, and the like.
- the MP 204 has a height of 4′′ or less.
- the MP 204 may have removable side panels, walls, or other retraining materials, such as ropes, nets, and/or rods that contain, or otherwise restrain, loose pallets or shipment parcels placed thereon.
- the MP's shape is preferably a cube or a rectangular prism, but other shapes are anticipated to meet a specific need or trailer shape, such as a triangular prism or cylinder.
- a roof panel may also be employed with an enclosed MP 204 , but is not required.
- the MP 204 may employ a plurality of wheels, castors, or the like.
- the MP 204 may comprise cut outs (e.g., a rectangular notch), at the base of each side of the platform, that are configured to receive fork lift prongs from any directions.
- the movable platform may even be powered (e.g., motorized).
- the MP 204 may be vertically removed from the trailer using, for example, a crane or other hoisting apparatus.
- FIGS. 3A and 3 B A sample MP 204 compatible with the present invention is depicted in FIGS. 3A (side view) and 3 B (perspective view).
- This MP 204 is described in more detail in co-pending U.S. Provisional Application Ser. No. 62/414,952, filed Oct. 31, 2016, and 62/414,967, filed Oct. 31, 2016, the entireties of which are hereby incorporated by reference.
- each MP 204 comprises a plurality of decks 336 which are placed upon vertical posts 338 .
- each deck 336 can be adjusted using a conveyance vehicle 114 by inserting the tines of the conveyance vehicle 114 into slots 340 and moving the deck 336 to a different height on posts 338 .
- Each set of four vertical posts 338 can accommodate one or more decks 336 . However, it is preferably that each set of four posts 338 only accommodates a single deck 336 for simplicity of operations and to maximize the space available on MP 204 for freight 112 .
- any freight 112 on the movable platform can be further identified by a section identifier A-F which identifies a more specific location of the freight 112 on the deck 336 of MP 204 .
- the left and right sides of MP 204 may be assigned identifiers 342 , such as a color or other ID.
- each post 338 on MP 204 may be assigned a readable tag 344 . Assigning this combination of sections A-F, identifiers 342 , and tags 344 allows a position on movable platform 204 or deck 336 to be specified with great accuracy.
- a worker executing a move instruction can be supplied with a section, a post location, and a side which specifies where freight 112 is to be placed on MP 204 .
- the additional granularity provided by this additional identification information provides the necessary information for AGVs 114 to execute move instructions for MPs 204 , decks 336 , and/or freight 112 as will be described later.
- section B can be used to identify all freight located on top of the front most deck 336 above section A and in front of section D.
- Each section A-F specifies a location (front, center, rear) and a height (ground level or deck) on MP 204 .
- each identifier 342 identifies a side of the MP 204 and each tag 344 identifies a specific post on the MP 204 .
- the workers 108 may use conveyance vehicles to move the MPs 204 about dock 202 .
- Workers 108 may also be supplemented with AGVs 114 .
- Conveyance vehicles 114 AGVs or otherwise, may include a forklift, towing or pushing vehicle, or other manipulating components, working alone or as a team.
- each conveyance vehicle 114 may be supplied with remote control functionality allowing for local remote control, on dock 202 , or centralized remote control, which is performed at a monitoring facility. Remote control may be useful when moves need to be completed overnight (e.g., to handle a late arrival), allowing a single operator to perform moves from a monitoring facility for multiple terminals 100 . This allows terminals 100 to be active 24/7 without requiring a worker 108 at each facility.
- instructions from instruction database 410 can be provided directly to the AGV 114 and the movement of the AGV 114 about dock 202 may be performed by following markers on (or wires in) the floor, or by other navigation sensor-based means, such as vision, magnets, lasers, GPS, infrared sensors, cameras, RFID array 416 , or any other known means. It should be obvious to one of ordinary skill in the art that the conveyance vehicles can be supplemented with or upgraded with future navigation technologies still in development.
- AGVs 114 may also be utilized to move decks 336 and/or freight 112 about dock 202 from a first MP 204 to a second MP 204 .
- AGVs 114 may also be utilized to move decks 336 and/or freight 112 about dock 202 from a first MP 204 to a second MP 204 .
- By moving an entire deck 336 and the freight 112 thereon in a single move what previously would have taken multiple moves can now be accomplished in a single move.
- the sector information about the deck 336 , the identifiers 342 , and the tags 344 all of which are stored in the cross-dock management system 200 , can be utilized to assist in the move.
- the plurality of MPs 204 are the size of the bed of a typical pup trailer (e.g., 28′ in length, 100′′ wide, 100′′ tall).
- MPs 204 could also take on the form of other lengths, smaller or larger, as long as they fit inside a trailer 110 .
- two MPs 13′ in length could be deployed inside a pup trailer as well as three MPs 8′ in length.
- Any combination of MP lengths, larger or smaller can be combined to fit inside a trailer. It would also be implied that the combination of MPs 204 , large or small, can fit inside any sized trailer, larger or smaller than 28′. This allows an entire trailer to be unloaded at once by simply removing MP 204 from the trailer 110 .
- the MP 204 After the MP 204 has been removed from a trailer 110 , it is conveyed to an assigned space 206 as will be described later. As depicted in FIG. 2A , the spaces 206 are arranged in a grid pattern which provides several advantages. First, because an entire trailer 110 can be unloaded quickly, the trailer 110 can quickly be removed from the unloading door 104 . Thus, many less unloading and loading doors are needed for cross-dock management system 200 . Also, MPs 204 which contain decks 336 or freight 112 that must be exchanged can be placed in spaces 206 next to each other which reduces the movement required of each conveyance vehicle 114 .
- each MP 204 can be accessed from all four sides which provides many more routes which reduces congestion (by providing more moving paths) and also allows multiple conveyance vehicles 114 to access the same MP 204 for simultaneous unloading and loading.
- MP 204 also makes irregular freight 112 easier to handle since it can be loaded onto the movable platform on dock 202 where there is much more room to maneuver than in the trailer 110 . Further, since a combination of different types of conveyance vehicles 114 can be utilized, this reduces the number of workers needed to man each dock 202
- FIG. 2B depicts another embodiment of dock 202 in which spaces 206 are angled 30-45° degrees with respect to the spaces 206 depicted in FIG. 2A .
- Some terminals 110 have support posts 208 , or other obstacles, spaced at regular intervals. These posts 208 may interfere with the grid of spaces 206 depicted in FIG. 2A .
- the angled spaces 206 facilitate a more efficient conveyance operation in terminals 100 with posts 208 by allowing the conveyance operator to pull straight through the dock 202 to drop off or pick-up the MP 204 . This can often be accomplished in one move.
- parking an MP 204 was like parallel parking a car because posts 208 and MPs 204 had to be avoided.
- a conveyance vehicle 114 would require multiple backwards and forwards moves to get the MP 204 placed into the space 206 .
- the spaces 206 are shown using an outline showing where an MP 204 can be placed.
- the outline of spaces 206 may physically appear on the floor, which is needed to allow workers 108 to correctly position MPs 204 .
- the floor of terminal 100 can be reconfigured as needed. For example, if the number of MPs 204 on the floor is low, only a portion of terminal 100 may need to be used and MPs 204 may be confined to certain sections of terminal 100 .
- This “sectoring” allows other areas of the terminal 100 to be utilized for other purposes.
- a first section of terminal 100 can be designated for MPs 104
- a second section could be used for storage
- a third section could be placed off-limits to AGVs 114 . This allows the floor-space of terminal 100 to be optimized for daily usage.
- FIG. 4 depicts a system diagram showing the hardware and resources employed by cross-dock management system 200 used to optimize unloading and loading of trailers 110 and movement of MPs 204 , decks 336 , and freight 112 on dock 202 .
- input data 402 e.g., manifests, arrivals
- Input data 402 provides cross-dock management system 200 with the initial information needed to optimize the loading and unloading of trailers 110 as well as the conveyance of MPs 204 , decks 336 , and freight 112 across dock 202 .
- manifest data may include the number of inbound trailers 110 ; number of inbound MPs 204 ; number of inbound decks 336 ; freight 112 dimensions and weight; origin and destination of each MP 204 , deck 336 , and piece of freight 112 ; flags indicating if freight is AGV-compatible; etc.
- the received input data 402 is stored in a local warehouse database 406 so that it can be utilized by initial setup optimization 408 to determine optimal instructions for the unloading and loading of MPs 204 .
- the initial setup optimization 408 is a series of algorithms that utilizes the input data 402 to determine optimal instructions which minimize loading and unloading time; identify which freight 112 , decks 336 , and MPS 204 require movement and/or no movement; group common destination freight 112 , minimize MP 204 , deck 336 , and freight 112 movement time; reduce empty carries and moves; prioritize certain moves based on service and transit service requirements; reduce travel distance; and optimize the number of workers 108 and/or AGVs 114 required based upon the number of moves. Any of the instructions can manually be overridden by a supervisor or other worker 108 by utilizing supervisor/user interface 436 .
- instructions database 410 Once the instructions are determined, they are stored in instructions database 410 .
- the instructions are classified into two categories: AGV instructions and human instructions. This classification can be based on classification data included in the manifest (e.g., AGV-friendly freight 112 ).
- a first set of instructions specifies moves that can be carried out before daily shipments arrive such as conveyance, MP 204 placement, and/or any other moves which can be used to prepare dock 202 prior to arrival of trailers 110 . These moves could be carried out overnight by AGVs 114 or by remotely controlled conveyance vehicles 114 .
- a second set of instructions specifies where each arriving MP 204 is to be placed and what specific freight 112 or decks 336 need to be moved to/from each MP 204 .
- the instructions specify in which space 206 each MP 204 is to be conveyed and what specific freight 112 or decks 336 need to be moved to/from each MP 204 .
- the instructions are provided to each worker on a tablet 412 wirelessly connected to the instructions database 410 .
- Tablet 412 may be any device having a display that is capable of receiving instructions from instruction database 410 .
- tablet 412 is a portable communications device with a touch screen and one or means for user input such as a keyboard, barcode reader, RFID reader, etc.
- FIG. 5 depicts a sample instruction screen 500 that may be shown on tablet 412 providing an instruction to worker 108 .
- the upper section 502 of instruction screen 500 indicates the worker's name 504 .
- the upper section 502 may also indicate other actions that can be performed by worker 108 , such as next instruction button 506 which worker 108 may utilize to skip the currently shown instruction (e.g., worker detected freight damage).
- a left section of 508 of instruction screen 500 indicates a pickup location for the move. In the depicted example, the worker 108 is instructed to pick up freight from “Bay 2 B” which specifies a particular space 206 on dock 202 .
- the right section 508 provides the destination information for the freight 112 .
- the destination information indicates a destination space “Bay 10 F.”
- the right section 510 depicts a visual placement for the freight on movable platform 104 using MP visualization 512 .
- MP visualization 512 depicts a side view of MP 204 showing posts 338 and decks 336 in abstract. Essentially, MP visualization 512 depicts MP 204 using a similar view to that of FIG. 3A showing sections A-F. MP visualization 512 is further provided with a color to indicate which side (left/right) of MP 204 that freight 112 should be placed. MP visualization 512 also indicates which post 338 next to which freight 112 is to be placed.
- MP visualization 512 provides a simple interface which conveys a great deal of information to worker 108 quickly and efficiently. By viewing MP visualization 512 , a worker quickly knows which space 206 , deck 336 , and post 338 at which the freight 112 is to be placed. It should also be apparent that a similar MP visualization 512 can be provided to a worker 108 for picking up freight 110 in left section 508 .
- the instructions sent to tablet 412 may also provide an optimized moving path (directions).
- the instructions provided on tablet 412 may also be supplemented by or replaced by augmented reality devices, such as head mounted displays (HMDs).
- HMDs head mounted displays
- the tablet 412 may display instructions screen 500 while a HMD provides turn-by-turn instructions or augments the dock 202 with a moving path for worker 108 .
- the instructions may include moves for entire decks 336 and all the freight thereon if the freight is intended for the same destination.
- the instruction may cause the tablet 412 to display additional information including shipment origin, priority moves, destination, weight, dimensions, departure time, due date, unload assignment movable platform dock location and shipment parcel location within the MP 204 , and load assignment movable platform dock location and shipment parcel location.
- a reader attached to the tablet 412 may be used to verify each move.
- a worker 108 first scans the identifier (e.g., barcode, RFID tag) on freight 112 or deck 336 and scans the identifier on the MP 204 or deck 336 . Then, the worker conveys the freight 112 or deck 336 to its destination and scans the destination MP 204 , deck 336 , post 338 and/or freight 112 to verify that the move has been completed.
- the identifier e.g., barcode, RFID tag
- the provided instructions may also include a height of the originating deck 336 and the height at which the deck 336 is to be moved to on the destination movable platform 202 .
- the heights at which decks 336 are placed on posts 338 are uniform on each MP 204 which allows all moves to be standardized at each dock 202 .
- next instruction preferably, based upon the previous destination in order to reduce overall travel distance.
- the next instruction may also be based on a priority of the instruction. It should be obvious to one of ordinary skill in the art that MPs 204 , decks 336 , posts 338 , and freight 112 can be labeled with any combination of identifiers such a barcodes, RFID tags, NFC tags, or any other machine readable code.
- each movable platform 204 is equipped with a collision avoidance system 414 which may include a camera, radar sensor, sonar sensor, etc. at a front end (i.e., opposite from the worker) of MP 204 .
- the collision avoidance system 414 can connect to the tablet 412 by a suitable wired or wireless connection such as Wi-Fi or Bluetooth.
- the collision avoidance system 414 allows a worker 108 to safely maneuver a MP 204 in and out of trailers 110 and across dock 202 .
- the collision avoidance system 114 may be provided with a light source to help the worker during the loading or unloading process.
- Additional technologies including, but not limited to, temperature and vibration sensors, light sensors to determine if the trailer door is opened, weight sensors, obstacle detection as described in U.S. Provisional Application Ser. No. 62/414,952, filed Oct. 31, 2016, and a GPS or cellular device for tracking may also be equipped on the MP 204 .
- the cross-dock management system 200 may utilize other sensors as a backup to tablets 412 as will be described with reference again to FIG. 4 .
- RFID array 416 which preferably comprises a plurality of RFID readers arranged in a grid above dock 202 .
- Each of the RFID readers in RFID array 416 is coupled to an RFID server 418 which is capable of real-time tracking of each MP 204 , post 338 , deck 336 , piece of freight 112 , AGV 114 , and/or worker 108 located on dock 202 .
- the tracking information from RFID server 418 is periodically or constantly provided to a network server 420 which can be used by real time instruction algorithms 422 to verify that each instruction has been carried out properly. If the real time instruction algorithms 422 detect that any instructions have been carried out improperly or that MP 204 , post 338 , deck 336 , piece of freight 112 , AGV 114 , and/or worker 108 has moved to an incorrect location, the instructions database 410 can be corrected in real time to correct any errors. Further, if an incorrect or improper move is detected, an alert may be generated to notify appropriate personnel of the error. The incorrect moves can also be stored in the local warehouse database 406 to determine any trends or for later handling. This information could be used to monitor compliancy or malfunctioning AGVs 114 .
- the RFID tags used in combination with the present invention can store data indicative of, for example, shipment origin, destination, weight, cube, groupings, AGV-compliancy, dimensions, number of shipment parcels, due date, etc. or may simply indicate a tracking number.
- the RFID tag and any associated RFID reader may be configured to work using one or more RFID technologies, including, without limitation: (1) a Passive Reader Active Tag (PRAT) system; (2) an Active Reader Passive Tag (ARPT) system has an active reader, which transmits interrogator signals and also receives authentication replies from passive tags; and (3) an Active Reader Active Tag (ARAT) system uses active tags awakened with an interrogator signal from the active reader.
- PRAT Passive Reader Active Tag
- ARPT Active Reader Passive Tag
- ARAT Active Reader Active Tag
- a PRAT system has a passive reader that only receives radio signals from active tags (e.g., battery operated, transmit only).
- the reception range of a PRAT system reader can be adjusted from 1-2,000 feet, allowing flexibility in applications such as asset protection and supervision.
- a variation of the ARAT system could also use a Battery-Assisted Passive (BAP) tag which operates like a passive tag, but has a small battery to power the tag's return reporting signal.
- BAP Battery-Assisted Passive
- passive ultra-high frequency (UHF) RFID tags may be used to identify, locate and track items within the dock and/or yard. Suitable UHF RFID tags, and associated RFID readers. While RFID is generally described herein, other technologies may be used in addition to, or in lieu of, RFID to facilitate tracking of the movable platforms and/or shipment parcel(s), such as near field communication (“NFC”).
- NFC near field communication
- Cross-dock management system 200 may also include a video server 424 also in communication with network server 422 .
- a first function of video server 424 is security which is handled by security module 426 .
- video server 424 is capable of receiving video feeds from each device on dock 202 equipped with a video camera.
- dock 202 may be equipped with a standard security system found at most terminals 100 used for monitoring theft and facility access.
- the video feeds from one or more of the security cameras in the security system could be supplied to video server 424 .
- Other video sources may include video feeds from cameras mounted on conveyance vehicles or AGVs 114 (e.g., part of collision avoidance system 414 ).
- video or camera information acquired by dimensioner array 442 may also be monitored by video server 424 .
- Security module 426 may monitor all of the aforementioned described video feeds and detect movement to create alerts for security personnel. Further, each time an alert occurs, security module 426 may store the video associated with the event in video database 428 .
- a comparison damage module 430 may be utilized to detect damaged freight 112 by comparing each piece of imaged freight 112 to previous images of the same freight 112 acquired at an earlier point in time (e.g., earlier in the day, at another terminal 110 , at pickup, etc.) using a difference algorithm to determine changes in freight 112 . If any significant changes are detected in freight 112 (e.g., above a certain change threshold), the comparison damage module 430 generates an exception which triggers a review of the freight 112 by a supervisor or other personnel. As will be described in more detail later, all exceptions are stored and classified in exceptions database 432 .
- the video feeds may also be monitored by a machine learning damage module 434 .
- Machine learning damage module 434 uses machine learning to detect damage in the video feeds.
- the machine learning damage module 434 may initially be supplied with various examples of freight damage images. Artificial intelligence can then be utilized to categorize and generalize the initial input information to determine damage and generate exceptions. As exceptions are corroborated by human review, the AI of machine learning damage module 434 modifies its behavior appropriately. Over time, the machine learning damage module 434 becomes more sophisticated at detecting damage to freight 112 and would be capable of detecting damage in hard to image areas, such as on the top of MP 204 which is out of sight of workers 108 . Similarly, if any damage is detected by machine learning damage module 434 , an exception is generated which is stored in exceptions database 432 for further review.
- the real time instruction algorithms 422 are able to handle any exceptions or other problems that may occur in real time.
- the real time instruction algorithms 422 are provided with a supervisor or worker interface 436 which allows a supervisor to prioritize certain MPs 204 or freight 112 . If a supervisor receives a telephone call or communication indicating that certain freight 112 has been prioritized or must reach a new and different final destination, the supervisor can use worker interface 436 to provide this information to cross-dock management system 200 .
- the real time instruction algorithms 422 then computes an exception which is stored in exception database 432 and revised instructions are provided to instruction database 410 . In this manner, the workflow of workers 108 and AGVs 114 on dock 202 is not interrupted. The workers 108 and AGVs 114 are simply provided new and/or updated instructions to carry out.
- Real time instruction algorithms 422 can also receive input from external real time data 438 such as weather, trailer delays, etc. For example, another terminal 100 may inform the cross-dock management system 200 of trailer delays or breakdowns. In another example, the real time instruction algorithms 422 may be notified of external real time data 438 including weather events or road closures which will affect either inbound and/or outbound trailers 110 .
- external real time data 438 such as weather, trailer delays, etc.
- another terminal 100 may inform the cross-dock management system 200 of trailer delays or breakdowns.
- the real time instruction algorithms 422 may be notified of external real time data 438 including weather events or road closures which will affect either inbound and/or outbound trailers 110 .
- Cross-dock management system 200 may also provide output data 440 to a shared network to other terminals 100 . In this manner, all of the cross-dock management systems 200 among the various terminals 100 are linked together.
- the sharing of output data 440 has many benefits. For example, if a certain geographical region has been hit by a natural disaster, MPs 204 can be rerouted to different terminals 100 to circumnavigate the area affected by the natural disaster. Thus, having multiple terminals 100 that are geographically distributed can be turned into an advantage by allowing the rerouting of trailers 110 in real time.
- new destination instructions can be communicated to mobile trailers 110 via a wireless communication interface such as cellular, radio, etc.
- the freight 112 carried on each MP 204 is constrained by the trailer 110 that it must fit into. For example, most pup trailers are not allowed to convey more than 24,000 pounds. And, the width, length, and height are constraints that the pallets and parcels cannot exceed.
- Input data 402 generally contains the weight of each piece of freight 112 .
- the dimensions of freight 112 can vary greatly (e.g., long and narrow or cylindrical). Therefore, the cross-dock management system 200 may also employ a dimensioner array 442 which monitors the dimensions of each MP 204 to ensure that it does not exceed the interior size of the trailer 110 .
- Each space 206 on the dock 202 may be provided with its own dimensioner or one dimensioner may cover multiple spaces 206 .
- a dimensioner is an imaging device capable of monitoring the boundaries of the MP 204 as well as the height of the decks 336 and freight 112 placed upon the MP 204 .
- the information from the dimensioner array 442 is collected and stored by dimensioner server 444 .
- dimensioner server 444 may provide any video data to video server 424 for further analysis.
- the information collected by dimensioner server 444 may be utilized by the real time instruction algorithms 422 if it is detected that a particular MP 204 has exceeded acceptable constraints to length, width, and height. If any excess is detected, the real time instruction algorithms 422 provide new instructions to instructions database 410 . Also, the dimensioner server 444 can be used to detect where irregular shaped freight 112 can be placed. For example, certain LTL shipments, such as ladders, could be placed on top of a MP 204 as long as the resulting load does not exceed a predetermined height and/or weight requirement.
- the dimensioner array 442 can also be used to track the length, width, and height of the freight 112 placed on decks 336 to ensure it does not exceed a certain size limit. If it is determined that the size limit is exceeded, the real time instruction algorithms 422 can calculate new instructions to alleviate any problems.
- the dimensioner server 444 also generates exceptions if any irregularities on an MP 104 are discovered. For example, if the dimensioner server 442 detects that the width or length of an MP 204 is irregular, this may indicate that freight 112 is placed incorrectly or is in danger of falling off MP 204 or decks 336 .
- Dimensioner array 442 may utilize any combination of known or future technologies capable of determining the outer dimensions of an object.
- dimensioner array 442 may include vision systems such as HD video cameras or infrared laser scanners having low tolerances (e.g., 1 ⁇ 2′′ or less).
- the dimensioner array 442 may scan an entire MP 204 , a single deck 336 , or individual pieces of freight 112 .
- the dimensioner array 442 can provide real time dimension data as freight 112 is conveyed.
- Each space 206 may be outfitted with its own dimensioner. Or, in other embodiments, a dimensioner may be outfitted on one or more drones which can cover multiple spaces 206 .
- the weight of the freight 112 placed on deck 336 must also be tracked because each deck 336 is assigned a weight limit which is constrained by the amount of weight to be placed on posts 338 .
- the weight of decks 336 can be tracked using multiple means.
- the conveyance vehicles or AGVs 114 used to move decks 336 may be outfitted with weight sensors (e.g., in the tines) that are able to detect the amount of weight being moved.
- the real time instruction algorithms 422 can then utilize this data to verify that an upper weight limit has not been exceeded for each deck 336 or to calculate new instructions.
- each space 206 may be provided with a scale or other weight measuring device to ensure that the MP 204 does not exceed a certain weight limit.
- the weight sensors may also be pressure sensitive to determine if the load on each movable platform is distributed equally or logically (e.g., to place more weight on the end of MP 204 to prevent possible sag in the middle).
- the real time instruction algorithms 422 can use the data from other sensors 446 (e.g., temperature, humidity) to make any necessary corrections to instructions database 410 . It should be apparent to one of ordinary skill in the art that sensors may be added or deleted from cross-dock management system at any time simply by installing or removing the sensors and adapting the real time instruction algorithms 422 appropriately.
- Cross-dock management system 200 also incorporates an AGV server 448 which is used to aid the navigation of each AGV 114 as well as monitor its real time location and status.
- the AGV server 448 may utilize position information gathered by RFID server 418 to determine if each AGV 114 is in its correct location on dock 202 .
- the AGV server 448 can also be utilized to network all AGVs 114 so that each AGV 114 is aware of all AGV locations in real time.
- AGV server 448 may also be utilized to calculate the paths required for each AGV 114 to execute move instructions from instructions database 410 and to verify that each instruction is correctly performed.
- AGV server 448 also incorporates remote control (RC) module 450 which allows any AGV 114 to be remotely controlled as has already been described.
- RC remote control
- AGV server 448 provides an interface which allows AGVs 114 to be automated and or remotely controlled.
- the real time instruction algorithms 422 can also take into account the cycling of AGVs 114 that must occur. That is, each AGV 114 will eventually need to be recharged, refueled, or be decommissioned for maintenance. In those instances, the real time instruction algorithms 422 would reallocate moves to new AGVs 114 or temporarily assign workers if no additional AGVs 114 are available. In this manner, the workflow on the dock 202 is not interrupted.
- the AGVs 114 may each utilize different guidance systems or each AGV 114 may utilize one or more different guidance methods in isolation or in combination.
- the AGVs 114 tasked with moving MPs 204 may only need to use a much simpler guidance method such as a combination of guide tape and natural feature navigation, ceiling tag (or other visual marker) navigation, infrared sensors, marker grid navigation.
- Infrared navigation offers the advantage that it is not interrupted by interference from visible lights.
- Passive infrared tags placed throughout the dock 202 may indicate a specific location on dock 202 .
- AGV navigation can be supplemented by other navigation techniques such as odometry, active RFID, passive RFID, and/or SLAM (simultaneous location and mapping).
- AGVs 114 tasked with moving decks 336 or individual pieces of freight 112 would require the use of one or more sophisticated guidance methods such as laser target navigation, inertial navigation, vision guidance, and/or geoguidance.
- a properly setup AGV guidance system would allow for multiple improvements within cross-dock management system 200 .
- a fully (or mostly) automated AGV system would have much less downtime than one staffed solely by workers 108 because no rest or stops would occur. Further, because the navigation is very precise, the distance between spaces 206 could possibly be reduced, allowing even more spaces 206 to be placed on dock 202 .
- the AGVs 114 may also be modular as has already been described. For example, each AGV 114 may be outfitted with a video camera to supplement the video gathered by video server 424 .
- the AGVs 114 may also be able to receive modular attachments to perform other functions such as cleaning (e.g., vacuum or broom attachment) or placing securement (e.g., shoring beams).
- an inbound trailer 110 containing a MP 204 arrives at the terminal 100 in step 602 .
- the trailer 110 is then directed to a particular door in step 604 using instructions retrieved from instructions database 410 .
- the MP 204 is then unloaded from the trailer in step 606 and scanned by a worker using tablet 412 .
- the RFID array 416 will have scanned any RFID tags contained on the MP 204 since it is now located on dock 202 .
- the RFID array 416 identifies an RFID tag or tags that should not be present (e.g., not in the manifest data) so that the correct destination of the freight 112 can be determined. This allows misplaced freight 112 to be identified much earlier during transmission of the cargo.
- the MP 204 is then conveyed into its optimized space 206 on dock 202 in step 608 .
- the worker 108 verifies that the MP 204 has been properly moved by scanning an identifier associated with the optimized space 206 along with any of the identifiers provided on MP 204 in step 610 .
- the RFID array 416 or other sensors 446 may also be utilized to verify that the MP 204 is in the optimized space 206 .
- Step 612 Any securement, such as shoring beams or cargo straps, are then removed from MP 204 in step 612 .
- Step 612 can be performed manually by workers 108 or by an AGV 114 as has already been described. After it is verified that all securement has been removed in step 614 , the unloading/loading of MP 204 commences.
- workers 108 are provided with the worker instructions and AGVs 114 are provided with AGV instructions from instructions database 410 in step 616 .
- the workers 108 and AGVs 114 carry out all assigned moves for the MP 204 in step 618 .
- the specifics of step 618 as to how specific instructions, such as deck or freight movements, are carried out by AGVs 114 will be described with reference to FIGS. 7A, 7B , and 8 later.
- the instructions carried out by the workers 108 and AGVs 114 in step 618 can be classified as either a freight move (moving a single parcel or pallet) or a deck instruction (moving decks 336 ).
- Deck instructions are advantageous because what previously would have taken several freight moves can now be accomplished in a single deck move. Also, because the freight on the deck 336 is not touched, there is far less likelihood that the freight on deck 336 will become damaged during a deck move. With decks 336 , it is possible that freight placed thereon is only handled individually at the origin and destination docks 202 .
- step 620 After all instructions for MP 204 have been carried out, securement must be placed in step 620 (either manually or using an AGV). After the cross-dock management system 200 is notified that the securement has been placed in 622 , an alert is generated to notify the supervisor (or similar personnel) that the MP 204 is ready to be inspected. In step 624 , a supervisor verifies that MP 204 meets all specifications and that securement has been placed properly. For example, the supervisor may check to see if any freight 112 has been damaged.
- secured MP 204 is conveyed to a particular door to a waiting, empty trailer 110 in step 626 .
- the empty trailer 110 does not have to wait at dock 202 and instead can wait in a yard.
- the correct trailer 110 in the yard can be notified and assigned a door to drive to for loading.
- the cross-dock management system 200 of the present invention only requires the presence of trailers 100 at doors if a MP 204 is being unloaded or loaded.
- Step 628 associates the outbound MP 204 with a particular trailer and creates new manifest data that can be provided to the next terminal 100 .
- the MP 204 is then loaded onto the trailer 110 in step 630 and the trailer 110 departs in step 432 .
- Steps 602 - 632 are repeated for each inbound MP 104 on dock 202 .
- step 702 It is first determined in step 702 if all freight on a particular deck 336 is destined for the same outbound MP 204 or storage area (to be described later). If the determination is positive, the beginning of the move of deck 336 is started in step 704 .
- the AGVs 114 utilized to move deck 336 in this described method are pairs of AGVs 114 which engage the sides of decks 336 in unison as will now be described.
- the AGV team is initiated and moves into position on the sides of deck 336 which is to be moved in step 704 in accordance with the provided deck instruction.
- Each AGV 114 then positions itself to the level of the deck 336 to be moved in step 706 .
- the height of each deck 336 on each MP 204 is known (e.g., from the manifest data or other calculated instructions) and this information is provided in the deck instruction.
- Each AGV 114 then engages deck 336 on each side in step 708 . If deck 336 does not include slots 340 , other gripping means may be utilized for the AGV 114 to attach to deck 336 (e.g., deck 336 can be lifted from beneath).
- Each AGV then lifts deck 336 above posts 338 in step 710 .
- Deck 336 is longitudinally conveyed to the end of MP 204 in step 712 .
- deck 336 is lowered to travel height by the AGVs 114 (e.g., to prevent toppling) in step 714 .
- the supplied deck instruction includes a destination for the deck 336 .
- the deck 336 may be conveyed to (a) another MP 204 or (b) a storage area as shown in decision step 716 . If the destination is another MP 204 , deck 336 is conveyed to the appropriate end of a destination MP 204 in step 718 .
- the AGVs 114 then raise deck 336 to the appropriate height for placement in step 720 and then lower deck 336 onto posts 338 in step 722 . Deck 336 is then released in step 724 at which point the AGVs 114 are available for the next move. Alternatively, if the destination for the deck 336 is a storage area after step 716 , the AGVs 114 convey the deck 336 to the storage area in step 726 .
- step 750 It is first determined in step 750 if all freight on a particular deck 336 is destined for the same outbound MP 204 or storage area. If the determination is positive, the beginning of the move of deck 336 is started in step 752 . First, the AGV 114 is initiated and moves into position at deck 336 which is to be moved in step 754 in accordance with the provided deck instruction. The AGV 114 then positions itself to the level of the deck 336 to be moved in step 756 and raises its tines in step 756 .
- each deck 336 on each MP 204 is known (e.g., from the manifest data or other calculated instructions) and this information is provided in the deck instruction.
- the AGV 114 then slots 340 in deck 336 and lifts deck 336 in step 758 .
- the supplied deck instruction includes a destination for the deck 336 .
- the deck 336 may be conveyed to (a) another MP 204 or (b) a storage area as shown in decision step 764 . If the destination is another MP 204 , deck 336 is conveyed to the appropriate location of a destination MP 204 in step 766 .
- the AGV 114 then raises deck 336 to the appropriate height for placement in step 768 and then lower deck 336 onto posts 338 in step 770 .
- Deck 336 is then released in step 772 at which point the AGV 114 is available for the next move.
- the AGV 114 conveys the deck 336 to the storage area in step 774 .
- the initial setup optimization 408 may determine, based on the manifest data, that the freight on one or more decks 336 can be more optimally rearranged to increase the capacity utilization of trailers 110 . This process may only occur if the initial setup optimization 408 determines that a predetermined number of decks 336 can be rearranged, thus making rearranging freight 112 worthwhile.
- workers 108 or AGVs 114 are utilized to move the decks 336 to be rearranged to a freight area in step 802 .
- the rearranging is preferably done in a separate area of the dock 202 away from spaces 206 because of the more cautious moves required when moving freight 112 .
- the freight 112 on decks 336 is rearranged according to instructions calculated by initial setup optimization 408 in step 804 .
- freight 112 from the storage area may be moved to empty spaces on decks 336 in step 806 .
- the decks 336 can then be placed on MPs 204 in step 808 .
- AGVs 114 may be utilized in combination with the present invention.
- a first type of AGV 114 may be utilized to move MPs 204 in/out of trailers 110 and onto dock 202 .
- These AGVs 114 may require simpler construction than others because they only need to hook onto MPs 204 and move them around dock 202 .
- a second type of AGV 114 may be utilized to execute deck instructions or, in certain environments, single freight instructions as described with reference to FIG. 8 .
- this second type of AGV 114 could operate alone or in pairs to move decks 336 about dock 202 as has been described in FIGS. 7A and 7B .
- a first AGV 114 may act as a master AGV and be in communication with cross-dock management system 200 to receive instructions and carry out orders.
- the second AGV 114 would be controlled by the master AGV and function as a slave AGV.
- the slave AGV would be less costly as it would not require all of the features and communication equipment of the master AGV.
- a third type of AGV 114 could be utilized to execute single freight instructions, primarily (moving of single freight 112 from a first MP 204 to a second MP 204 ). Since these AGVs 114 would only be responsible for moving smaller freight 112 (less than a full deck 336 ), they would be less expensive to produce and maintain. They would also require a much smaller footprint than the first or second type of AGV 114 described above. It should be obvious that the less space that is taken up by AGVs 114 on the dock 202 , there is less potential for collisions and other mishaps. As an example, these AGVs 114 may simply have a weight bearing platform with automated rollers on top. The AGVs 114 could use a centralized system of rollers to pick up and drop off freight 112 . Such AGVs 114 may be useful for long haul movements such as moving freight from dock 202 to a storage area and vice versa.
- AGV 114 it is also possible for a single type of AGV 114 to execute all of the moves required by the present invention. Such an AGV may potentially be more costly, but maintenance and other costs could be kept to a minimum because different systems/sets of AGVs 114 would not have to be maintained across multiple docks 202 .
- Each deck instruction contains the location of the source deck 336 and a location of the destination MP 202 . Further, the deck instruction also includes the height at which the source deck is located. As already stated, the heights at which decks 336 are placed on posts 338 are preferably standardized. Therefore, each deck height can be assigned a unique identifier ( 1 - x ), similar to the section identifiers. Thus, the sections A-F and the differing deck placement heights can all be standardized by using a combination of a section identifier and a height identifier on each MP 204 .
- An example deck instruction would be as follows: ORIGIN: [MP identifier, section identifier, height identified]-DESTINATION[MP identifier, section identifier, height identifier]. Such a deck instruction includes all necessary information to move a deck 336 from an origin to a destination.
- Freight instructions may also be structured in a similar manner. However, more information may be needed in a freight instruction for both the origin and the destination. Similar to deck instructions, freight instructions may utilize a similar structure. A freight instruction may additionally include a quadrant location (using identifiers 342 and/or tags 344 ) location for further specificity. That is, the more information that can be provided to the cross-dock management system 200 about the particulars of the dock 202 and the particulars of moves, the more that can be automated.
- the initial setup optimization 408 is able to divide instructions into worker instructions and AGV instructions using a variety of criteria. For example, because deck/MP instructions are simpler and MPs 204 and decks 336 are fairly large and standardized, only those moves may be automated while the other moves may be carried out by workers 108 . Any combination of automation/manual moves are compatible with the present invention because the instructions are the same regardless. The only difference is the receiver of the instruction (worker 108 or AGV 114 ) and these instructions be rerouted on the fly by the real time instruction algorithms 422 .
- AGV server 448 may keep track of how many moves each AGV 114 has executed. If it is determined that a particular AGV 114 has been overburdened, this information may be supplied to real time instruction algorithms 422 so that the moves among AGVs 114 are distributed more evenly. This would allow the work load assigned to each AGV 114 to be balanced which would lead to less breakdowns and maintenance.
- individual pieces of freight may also be assigned unique identifiers to note special properties or allow them to be moved using an AGV.
- some freight may be marked as delicate.
- Delicate freight is preferably manually loaded onto a deck 336 or a MP 204 .
- the deck 336 may be loaded manually first and then an AGV 114 could be used to move the loaded deck 336 into a final position. It is a particular strength of the present invention that it can handle interruptions and automatically reroute the workflow around dock 202 to handle those interruptions (such as the needed loading of a manual deck 336 ).
- the system of the present invention knows the inbound manifest data, which would also include such freight indicators, the other instructions could be optimized to minimize the impact to workflow while the delicate freight (or other awkward freight) is being loaded manually.
- the storage facility in which decks 336 are placed may take many forms. If there is a requirement for only occasional storage of decks 336 (e.g., delayed schedule or delivery, etc.), the storage area may simply be a portion of dock 202 having assigned spaces for decks 336 .
- the cross-dock management system 200 would simply log the location of each placed deck 336 , similar to the MPs 204 , so that it could be recalled when needed.
- a rack system could be utilized in which a number of racks (e.g., composed of four posts 338 ) could be arranged on dock 202 or at a different location.
- Each rack would be assigned an identifier and the height that each deck is stored at would be noted by cross-dock management system for later recall of the deck.
- a rack system maximizes floor space.
- the racks could be placed against the walls of the dock 202 to minimize the floor space taken up.
- the storage facility may be an entirely separate and automated facility if multiple decks 336 are to be stored long term. Such a facility would be useful, for example, for individuals traveling abroad that need to store items for long periods of time. Such individuals could be rented storage space in various sizes (an entire movable platform, a single deck, or combinations thereof) and those could be stored/retrieved at any time.
- FIG. 9 depicts a flowchart showing the steps utilized by initial setup optimization 408 to calculate instructions from input data 402 .
- the input data 402 is received and stored in local warehouse database 406 .
- all outbound load points are identified by initial setup optimization 408 in step 904 .
- the number of MPs 204 for each load point can be determined in step 906 .
- an inbound MP 204 may have freight 112 or decks 336 which need to be transferred to three different destinations and would require at least two additional MPs 204 (i.e., because the inbound MP 204 is reused as an outbound MP 204 once it has been unloaded/reloaded).
- the initial setup optimization determines which freight 112 or decks 336 need to be handled in step 908 . For example, if the majority of pieces on a MP 204 are intended for the same terminal 100 , only a few select pieces need to be removed/loaded onto the MP 204 until it is ready to be loaded onto a waiting trailer 110 . This can significantly speed up the loading/loading process over the conventional LIFO process. Similarly, if all of the freight 112 located on a deck 336 is intended for the same destination, only a single deck instruction needs to be calculated. If additional MPs 204 are needed, the initial setup optimization 408 adds additional MP movements to the instructions in step 910 . Also, has already been described, additional MPs 204 can be placed overnight by AGVs 114 before any trailers 110 arrive.
- the initial setup optimization 408 will use a bin stacking algorithm to determine an optimal height at which each deck and/or freight 112 is to be placed during a deck or freight instruction.
- the initial setup optimization 408 calculates the deck instruction using the weight as well as the known dimensions (l ⁇ w ⁇ h) of each deck 336 .
- the real time instruction algorithms 322 can correct any wrong instructions which have been calculated during the initial setup optimization.
- the initial setup optimization 408 determines an optimized space 206 for each MP 204 on dock 202 in step 912 .
- the initial setup optimization 408 also determines the number of workers 108 and/or AGVs 114 required to complete all necessary moves in step 914 . This step avoids having too many or too few workers 108 or AGVs 114 located on dock 102 .
- the initial setup optimization 408 determines all piece level moves for the workers 108 and AGVs 114 (freight instructions and deck instructions) in step 916 .
- the instructions are then stored in instructions database 410 in step 918 .
- Step 902 - 918 are repeated daily for each set of input data 402 that is received by cross-dock management system 200 .
- the origin dock 202 can better ascertain what equipment will be needed to conduct the first leg of the shipment (i.e., number of movable platforms needed, number of trailers needed). Further, classifying the information at pickup allows the freight 112 to be tagged at the earliest possible location (i.e., at pickup) and greatly reduces the possibility that freight 112 will be mislabeled or end up at the wrong terminal 100 . For example, if it is noted early on that a MP 204 has freight intended for a single destination, the cross-dock management system 200 can route this MP 204 without having to calculate any deck instructions or freight instructions, thus reducing the complexity of the instruction calculations. Similarly, for decks 336 having freight for a single destination, only deck instructions have to be calculated.
- FIG. 10 depicts terminal 100 of FIG. 1 adapted for use with MPs 204 .
- dock 102 can be made to be compatible with MPs 204 using the dock configuration shown in FIG. 10 .
- MPs 204 are placed at every other door 902 to allow access to three sides of MP 204 both on the inbound doors 104 and outbound doors 106 . This creates a central aisle 904 which allows for easy movement of MPs 204 and freight 112 .
- initial setup optimization 408 and real time instruction algorithms 422 can be adapted to work with the dock configuration shown in FIG. 10 .
- FIG. 11 depicts a shared dock 1102 which is share between independent carriers located in the same geographical region that have a partnership for the purposes of sharing data.
- predictive analytics can optimize loads by combining partner carrier freight (e.g., shipment parcels) onto the same MP 204 , further reducing truck schedules and cost.
- a first side 1104 of dock 1102 is occupied by a first carrier and a second side 1106 of dock 1102 is occupied by a second carrier.
- First side 1104 and second side 1106 may be split equally or according to the terms of a partnership agreement.
- Information about MPs 204 and RFID tags can be made available from the first side 1104 to the second side 1106 , and vice versa.
- each side 1104 and 1106 is preferably controlled by its own cross-dock management system 200 to provide data confidentiality.
- the two cross-dock management systems 200 may be linked in order to share limited data.
- the cross-dock management system 200 associated with first side 1104 may determine that it is more economically feasible to have the second side 1106 deliver certain parcels.
- the second side 1106 may agree or disagree to each request from first side 1104 .
- FIG. 12 depicts a flowchart showing the collaboration between two cross-dock management systems 200 which share dock 1002 .
- the cross-dock management system 200 associated with first side 1104 is cross-dock management system A and the cross-dock management system 200 associated with first side 1104 is cross-dock management system B.
- Cross-dock management systems A and B each feed collaboration data into collaboration heuristic model 1202 .
- Collaboration data may include information such as the number of available spaces on MPs 204 , the destinations of all MPs 204 , manifest data about any overflow freight 112 (i.e., a parcel which would require an extra shipment or does not fit within available MPs 204 ), etc.
- the collaboration heuristic model 1202 compares the collaboration data from cross-dock management systems A and B and determines options 1204 for carrier A and options 1206 for carrier B.
- Carrier A and Carrier B can agree/disagree to each option or cross-dock management systems A and B may be programmed to automatically accept/deny certain options in step 1208 . Any options that agreed upon will be updated in the instructions database 410 as computed by real time instruction algorithms 422 in step 1210 .
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Data Mining & Analysis (AREA)
- Mechanical Engineering (AREA)
- Multimedia (AREA)
- Aviation & Aerospace Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Control Of Position, Course, Altitude, Or Attitude Of Moving Bodies (AREA)
Abstract
Disclosed herein is an automated cross-dock management system configured to optimize moves on a cross-dock. The automated cross-dock management system uses inbound manifest data to calculate ordered move instructions for all inbound movable platforms, inbound modular decks, and inbound freight. The ordered move instructions can be assigned to be carried out by manual conveyance vehicles or by automated guided vehicles based upon a plurality of criteria. The automated cross-dock management system is also able to detect damaged freight on the cross-dock using a combination of streams from video cameras.
Description
- The present applications claims priority to U.S. Provisional Application Ser. No. 62/415,054, filed Oct. 31, 2016, the entire content of which is hereby incorporated by reference in its entirety.
- The present invention relates to the field of freight, shipping, and dock management; more particularly, to an automated cross-dock management system, method, and/or apparatus; even more particularly, to an optimized and automated cross-dock management system, method, and/or apparatus for use with less-than-truckload carriers.
- Within the shipping industry exists a segment of transportation that focuses on less-than-truckload (LTL) freight loads, which can vary from a single item to a nearly full truckload. To transport freight originating from a common origin destined for multiple locations around the country or region, LTL carriers often employ a hub-and-spoke network of terminals.
- Once freight is picked up, it is brought back to a facility where it is transferred across a dock (a process commonly referred to as “cross-docking”). This process typically involves manually unloading the load (or portion thereof) from one trailer and loading it onto another. An system for improving cross-dock operations is described in U.S. Pat. No. 9,367,827, issued Jun. 14, 2016, the entire content of which is hereby incorporated by reference in its entirety.
- In recent years, there have been many improvements in warehouse operations. Specifically, large e-commerce retailers and shipping services have begun to use automated guided vehicles (AGVs) to move freight around warehouses. Typically, these AGVs are lower-cost devices that are designed to move freight placed upon them from a first location to a second location in the warehouse. These AGVs use a simple navigation method using markers and have basic collision sensors to avoid bumping into other AGVs.
- However, these AGVs are typically not suited for cross-dock operations, especially in an LTL environment. First, in a cross-dock operation, an AGV may need to convey an entire movable platform (MP) which can weigh up to 24,000 pounds (or more). AGVs currently being used in most warehouses can typically only convey a few hundred pounds at most. Further, most current AGVs can only move in a grid-like pattern whereas cross-dock operations require much more advanced collision avoidance systems because manual workers may also be present.
- Additionally, as will be described later, the AGVs may need to perform a variety of functions such as moving MPs, moving decks, and/or moving individual pieces of freight. Current AGVs and cross-dock systems are not equipped to handle and/or calculate these types of moves. What is needed is a cross-dock management system capable of effectively using AGVs to supplement or entirely replace manual moves in a cross-dock environment. Such a cross-dock system must be highly adaptable to handle exceptions, such as AGV recharging or maintenance, and should enable cross-dock operations to be extended to operate 24 hours a day, seven days a week
- The present invention provides an automated cross-dock management system configured to optimize moves on a cross-dock. The automated cross-dock management system uses inbound manifest data to calculate ordered move instructions for all inbound movable platforms, inbound modular decks, and inbound freight. The ordered move instructions can be assigned to be carried out by manual conveyance vehicles or by AGVs based upon a plurality of criteria. The automated cross-dock management system is also able to detect damaged freight on the cross-dock using a combination of video streams from video cameras.
- These and other advantages of the present invention will be readily understood with the reference to the following specifications and attached drawings wherein:
-
FIG. 1 depicts a perspective view of a typical dock currently used by LTL carriers. -
FIG. 2A depicts an optimized dock according to a first aspect of the present invention. -
FIG. 2B depicts another optimized dock according to a second aspect of the present invention. -
FIGS. 3A and 3B depicts a movable platform with decks divided into sections and subsections using identifiers. -
FIG. 4 depicts a system diagram showing the hardware and resources employed during operation of the optimized dock ofFIGS. 2A and 2B . -
FIG. 5 depicts a sample instruction screen used by a worker to execute a move instruction. -
FIG. 6 depicts a flowchart showing the steps used in unloading and loading a movable platform. -
FIG. 7A depicts a flowchart showing the steps used to move a deck using a pair of AGVs. -
FIG. 7B depicts a flowchart showing the steps used to move a deck using a single AGV. -
FIG. 8 depicts a flowchart showing the steps used to execute freight instructions. -
FIG. 9 depicts a flowchart showing the steps used to determine movement instructions for the movement database using input data. -
FIG. 10 depicts the dock ofFIG. 1 configured to be used with movable platforms. -
FIG. 11 depicts a shared optimized dock in accordance with the present invention. -
FIG. 12 depicts a flowchart showing the steps used when two or more shippers share the same optimized dock. - Preferred embodiments of the present invention will be described herein below with reference to the accompanying drawings. In the following description, well-known functions or constructions are not described in detail because they may obscure the invention in unnecessary detail. While the present invention is generally directed to LTL operations for use in the trucking industry, the teachings may be applied to other shipping industries, just as those by air, sea, and rail. Therefore, the teachings should not be constructed as being limited to only the trucking industry. For this disclosure, the following terms and definitions shall apply:
- As used herein, the word “exemplary” means “serving as an example, instance, or illustration.” The embodiments described herein are not limiting, but rather are exemplary only. It should be understood that the described embodiments are not necessarily to be construed as preferred or advantageous over other embodiments. Moreover, the terms “embodiments of the invention,” “embodiments,” or “invention” do not require that all embodiments of the invention include the discussed feature, advantage, or mode of operation.
- As noted above, LTL carriers typically transport freight originating from a common origin destined to many different locations around the country via a system of terminals. Typically, once freight is picked up, the freight is brought back to a facility where it is transferred across a dock 102 (cross-docked), which involves unloading the freight from one trailer and loading it onto another. Freight can move through one or more terminals 100 (e.g., small terminals or distribution centers) in a hub-and-spoke network until the freight reaches its destination terminal and/or is delivered.
- In this present invention, freight may be received at its origin via one of several methods: loose pallets, boxes, cartons, crates, drums, barrels, or the like; by
MP 204 with decks 336 (FIGS. 3A-3B ), an 8′×8′ (or similarly sized) platform used for double or triple stacking of freight on aMP 204 by which cargo consisting of loose pallets, boxes, cartons, crates or the like are stacked upon going to either a single destination or multiple destinations; bysingle MP 204,MP 204 withoutdecks 336 as described in U.S. Pat. No. 9,367,827, issued Jun. 14, 2016 (the entire content of which is herein incorporated by reference), by whichdecks 336 and cargo consisting of loose pallets, boxes, cartons, crates or the like are stacked upon going to either a single destination or multiple destinations; or bymultiple MPs 204 such as in a full truckload, rail container, ocean container, or the like consisting of two ormore MPs 204 going to either a single destination or multiple destinations. - In some embodiments, freight having non-standard dimensions may be combined and/or placed in standardized containers having known dimensions. Such standardized containers allow for easier moving of the freight either by a manual move or AGV move. The standardized containers primarily function to make the cargo “AGV-friendly” or “AGV-compatible.”
- Referring first to
FIG. 1 , depicted is atypical terminal 100 used by current LTL carriers. As shown,dock 102 is long and narrow. Typically,dock 102 is 60 feet in width or less. Aninbound door 104 ofdock 102 is used for unloadingtrailers 110 and a second (outbound)door 106 is used for loadingtrailers 110. Unloading is generally sequenced in a last in, first out (LIFO) process. Thus, pallets or parcels (freight 112) in the nose (front) of thetrailer 110 that need to be unloaded must first have theentire trailer 110 unloaded to provide access to the desiredfreight 112. As aworker 108cross-docks freight 112 from theinbound door 104 to theoutbound door 106, half of the time is typically spent without any load (i.e., empty carries), which wastes both time and money. Typicallyfreight 112 is conveyed acrossdock 102 using aconveyance vehicle 114, such as a forklift. The conveyance vehicle, as referred to herein, may be manually operated, remotely operated, or completely autonomous (AGV). Further, at least one load door is required for every load point, but multiple doors may be necessary for multiple schedules to the same load point. Since loading is generally sequenced from the nose to the rear,freight 112 is typically docked in a bay outside the door to allow for co-mingling of thefreight 112 on thetrailer 110 for the optimum load. This practice creates congestion, wasteful re-handling time, and additional cost. Also, becausedock 102 is long and narrow, the maneuverability ofworkers 108 usingconveyance vehicles 114 is severely limited, especially when there is a large quantity offreight 112 ondock 102. - An optimized
cross-dock management system 200 in accordance with a first embodiment of the present invention transforms the process for moving LTL freight across thedock 202 by adding a novel combination of mechanics, technology, and automation as depicted inFIG. 2A . To facilitate the optimizedcross-dock management system 200, an optimizeddock 202 may be employed that is two to three times wider and two to three times shorter than a traditional dock; thus, an optimizeddock 202 may more closely resemble a square or large rectangle. Designed properly, an optimizeddock 202 may require one-third the number of doors asdock 102 without sacrificing capacity. Alternatively, the optimized dock can 202 be wide enough such that a predetermined number (e.g., 2 to 10, more preferably 3 to 9, most preferably, 5 to 7) ofMPs 204 can be spaced out per dock door. The distance between dock doors may be, for example, 12 feet or more. When aMP 204 is removed from atrailer 110 it can be conveyed onto thedock 202. - Further, the use of
MPs 204 allows for an entire trailer to be unloaded or loaded and conveyed in less than five minutes, thus increasing efficiency and saving money.MPs 204 may be used to provide optimized load building and planning via real-time data and sensing technology, such as barcodes (2D or 3D), radio-frequency identification (RFID) tags, three dimensional (3D) imaging, Bluetooth low energy (BLE), magnetics, sensor fusion, global positioning system (GPS) tracking, and the like. Preferably, theMP 204 has a height of 4″ or less. - The
MP 204 may have removable side panels, walls, or other retraining materials, such as ropes, nets, and/or rods that contain, or otherwise restrain, loose pallets or shipment parcels placed thereon. When an enclosedMP 204 is employed (e.g., when walls, panels, or the like are used), the MP's shape is preferably a cube or a rectangular prism, but other shapes are anticipated to meet a specific need or trailer shape, such as a triangular prism or cylinder. A roof panel may also be employed with anenclosed MP 204, but is not required. To facilitate movement, theMP 204 may employ a plurality of wheels, castors, or the like. To facilitate use with a forklift, theMP 204 may comprise cut outs (e.g., a rectangular notch), at the base of each side of the platform, that are configured to receive fork lift prongs from any directions. In certain aspects, the movable platform may even be powered (e.g., motorized). In certain aspects, for example, when an open air trailer is used, theMP 204 may be vertically removed from the trailer using, for example, a crane or other hoisting apparatus. - A
sample MP 204 compatible with the present invention is depicted inFIGS. 3A (side view) and 3B (perspective view). Features of thisMP 204 is described in more detail in co-pending U.S. Provisional Application Ser. No. 62/414,952, filed Oct. 31, 2016, and 62/414,967, filed Oct. 31, 2016, the entireties of which are hereby incorporated by reference. Herein will be described the features ofMP 204 that are relevant to the logistics of the present application. As shown, eachMP 204 comprises a plurality ofdecks 336 which are placed uponvertical posts 338. The height of eachdeck 336 can be adjusted using aconveyance vehicle 114 by inserting the tines of theconveyance vehicle 114 intoslots 340 and moving thedeck 336 to a different height onposts 338. Each set of fourvertical posts 338 can accommodate one ormore decks 336. However, it is preferably that each set of fourposts 338 only accommodates asingle deck 336 for simplicity of operations and to maximize the space available onMP 204 forfreight 112. - If three
decks 336 are located on asingle MP 204, anyfreight 112 on the movable platform can be further identified by a section identifier A-F which identifies a more specific location of thefreight 112 on thedeck 336 ofMP 204. Further, the left and right sides ofMP 204 may be assignedidentifiers 342, such as a color or other ID. Additionally, eachpost 338 onMP 204 may be assigned areadable tag 344. Assigning this combination of sections A-F,identifiers 342, and tags 344 allows a position onmovable platform 204 ordeck 336 to be specified with great accuracy. For example, a worker executing a move instruction, as will be described later, can be supplied with a section, a post location, and a side which specifies wherefreight 112 is to be placed onMP 204. Additionally, the additional granularity provided by this additional identification information provides the necessary information forAGVs 114 to execute move instructions forMPs 204,decks 336, and/orfreight 112 as will be described later. - For example, section B can be used to identify all freight located on top of the front
most deck 336 above section A and in front of section D. Each section A-F specifies a location (front, center, rear) and a height (ground level or deck) onMP 204. Further, eachidentifier 342 identifies a side of theMP 204 and eachtag 344 identifies a specific post on theMP 204. - As already stated, in some embodiments, the
workers 108 may use conveyance vehicles to move theMPs 204 aboutdock 202.Workers 108 may also be supplemented withAGVs 114.Conveyance vehicles 114, AGVs or otherwise, may include a forklift, towing or pushing vehicle, or other manipulating components, working alone or as a team. Further, eachconveyance vehicle 114 may be supplied with remote control functionality allowing for local remote control, ondock 202, or centralized remote control, which is performed at a monitoring facility. Remote control may be useful when moves need to be completed overnight (e.g., to handle a late arrival), allowing a single operator to perform moves from a monitoring facility formultiple terminals 100. This allowsterminals 100 to be active 24/7 without requiring aworker 108 at each facility. - As will be described in more detail later, instructions from
instruction database 410 can be provided directly to theAGV 114 and the movement of theAGV 114 aboutdock 202 may be performed by following markers on (or wires in) the floor, or by other navigation sensor-based means, such as vision, magnets, lasers, GPS, infrared sensors, cameras,RFID array 416, or any other known means. It should be obvious to one of ordinary skill in the art that the conveyance vehicles can be supplemented with or upgraded with future navigation technologies still in development. - In some embodiments,
AGVs 114 may also be utilized to movedecks 336 and/orfreight 112 aboutdock 202 from afirst MP 204 to asecond MP 204. By moving anentire deck 336 and thefreight 112 thereon in a single move, what previously would have taken multiple moves can now be accomplished in a single move. In an automated system, the sector information about thedeck 336, theidentifiers 342, and thetags 344, all of which are stored in thecross-dock management system 200, can be utilized to assist in the move. - Preferably, the plurality of
MPs 204 are the size of the bed of a typical pup trailer (e.g., 28′ in length, 100″ wide, 100″ tall). However,MPs 204 could also take on the form of other lengths, smaller or larger, as long as they fit inside atrailer 110. For example twoMPs 13′ in length could be deployed inside a pup trailer as well as threeMPs 8′ in length. Any combination of MP lengths, larger or smaller can be combined to fit inside a trailer. It would also be implied that the combination ofMPs 204, large or small, can fit inside any sized trailer, larger or smaller than 28′. This allows an entire trailer to be unloaded at once by simply removingMP 204 from thetrailer 110. After theMP 204 has been removed from atrailer 110, it is conveyed to an assignedspace 206 as will be described later. As depicted inFIG. 2A , thespaces 206 are arranged in a grid pattern which provides several advantages. First, because anentire trailer 110 can be unloaded quickly, thetrailer 110 can quickly be removed from the unloadingdoor 104. Thus, many less unloading and loading doors are needed forcross-dock management system 200. Also,MPs 204 which containdecks 336 orfreight 112 that must be exchanged can be placed inspaces 206 next to each other which reduces the movement required of eachconveyance vehicle 114. And, eachMP 204 can be accessed from all four sides which provides many more routes which reduces congestion (by providing more moving paths) and also allowsmultiple conveyance vehicles 114 to access thesame MP 204 for simultaneous unloading and loading.MP 204 also makesirregular freight 112 easier to handle since it can be loaded onto the movable platform ondock 202 where there is much more room to maneuver than in thetrailer 110. Further, since a combination of different types ofconveyance vehicles 114 can be utilized, this reduces the number of workers needed to man eachdock 202 -
FIG. 2B depicts another embodiment ofdock 202 in whichspaces 206 are angled 30-45° degrees with respect to thespaces 206 depicted inFIG. 2A . Someterminals 110 havesupport posts 208, or other obstacles, spaced at regular intervals. Theseposts 208 may interfere with the grid ofspaces 206 depicted inFIG. 2A . Theangled spaces 206 facilitate a more efficient conveyance operation interminals 100 withposts 208 by allowing the conveyance operator to pull straight through thedock 202 to drop off or pick-up theMP 204. This can often be accomplished in one move. In the prior dock layout ofFIG. 2A , parking anMP 204 was like parallel parking a car becauseposts 208 andMPs 204 had to be avoided. Aconveyance vehicle 114 would require multiple backwards and forwards moves to get theMP 204 placed into thespace 206. - In
FIGS. 2A-2B , thespaces 206 are shown using an outline showing where anMP 204 can be placed. The outline ofspaces 206 may physically appear on the floor, which is needed to allowworkers 108 to correctly positionMPs 204. However, in a terminal 100 where all MP moves are carried out byAGVs 114, there is no need for the spaces to be shown on the ground because other navigation techniques, to be described later, can be utilized to place theMPs 204 intospaces 206. In this scenario, the floor ofterminal 100 can be reconfigured as needed. For example, if the number ofMPs 204 on the floor is low, only a portion ofterminal 100 may need to be used andMPs 204 may be confined to certain sections ofterminal 100. This “sectoring” allows other areas of the terminal 100 to be utilized for other purposes. For example, a first section ofterminal 100 can be designated forMPs 104, a second section could be used for storage, and a third section could be placed off-limits toAGVs 114. This allows the floor-space ofterminal 100 to be optimized for daily usage. -
FIG. 4 depicts a system diagram showing the hardware and resources employed bycross-dock management system 200 used to optimize unloading and loading oftrailers 110 and movement ofMPs 204,decks 336, andfreight 112 ondock 202. First, input data 402 (e.g., manifests, arrivals) arrives atcross-dock management system 200 via asecure internet connection 404.Input data 402 providescross-dock management system 200 with the initial information needed to optimize the loading and unloading oftrailers 110 as well as the conveyance ofMPs 204,decks 336, andfreight 112 acrossdock 202. One of ordinary skill in the art would recognize that manifest data may include the number ofinbound trailers 110; number ofinbound MPs 204; number ofinbound decks 336;freight 112 dimensions and weight; origin and destination of eachMP 204,deck 336, and piece offreight 112; flags indicating if freight is AGV-compatible; etc. - The received
input data 402 is stored in alocal warehouse database 406 so that it can be utilized byinitial setup optimization 408 to determine optimal instructions for the unloading and loading ofMPs 204. Specifically, theinitial setup optimization 408 is a series of algorithms that utilizes theinput data 402 to determine optimal instructions which minimize loading and unloading time; identify whichfreight 112,decks 336, andMPS 204 require movement and/or no movement; groupcommon destination freight 112, minimizeMP 204,deck 336, andfreight 112 movement time; reduce empty carries and moves; prioritize certain moves based on service and transit service requirements; reduce travel distance; and optimize the number ofworkers 108 and/orAGVs 114 required based upon the number of moves. Any of the instructions can manually be overridden by a supervisor orother worker 108 by utilizing supervisor/user interface 436. - Once the instructions are determined, they are stored in
instructions database 410. The instructions are classified into two categories: AGV instructions and human instructions. This classification can be based on classification data included in the manifest (e.g., AGV-friendly freight 112). - A first set of instructions specifies moves that can be carried out before daily shipments arrive such as conveyance,
MP 204 placement, and/or any other moves which can be used to preparedock 202 prior to arrival oftrailers 110. These moves could be carried out overnight byAGVs 114 or by remotely controlledconveyance vehicles 114. A second set of instructions specifies where each arrivingMP 204 is to be placed and whatspecific freight 112 ordecks 336 need to be moved to/from eachMP 204. - The instructions specify in which
space 206 eachMP 204 is to be conveyed and whatspecific freight 112 ordecks 336 need to be moved to/from eachMP 204. The instructions are provided to each worker on atablet 412 wirelessly connected to theinstructions database 410.Tablet 412 may be any device having a display that is capable of receiving instructions frominstruction database 410. In a preferred embodiment,tablet 412 is a portable communications device with a touch screen and one or means for user input such as a keyboard, barcode reader, RFID reader, etc. -
FIG. 5 depicts asample instruction screen 500 that may be shown ontablet 412 providing an instruction toworker 108. As shown, theupper section 502 ofinstruction screen 500 indicates the worker'sname 504. Theupper section 502 may also indicate other actions that can be performed byworker 108, such asnext instruction button 506 whichworker 108 may utilize to skip the currently shown instruction (e.g., worker detected freight damage). A left section of 508 ofinstruction screen 500 indicates a pickup location for the move. In the depicted example, theworker 108 is instructed to pick up freight from “Bay 2B” which specifies aparticular space 206 ondock 202. - The
right section 508 provides the destination information for thefreight 112. As shown, the destination information indicates a destination space “Bay 10F.” Further, the right section 510 depicts a visual placement for the freight onmovable platform 104 usingMP visualization 512.MP visualization 512 depicts a side view ofMP 204 showingposts 338 anddecks 336 in abstract. Essentially,MP visualization 512 depictsMP 204 using a similar view to that ofFIG. 3A showing sections A-F.MP visualization 512 is further provided with a color to indicate which side (left/right) ofMP 204 thatfreight 112 should be placed.MP visualization 512 also indicates which post 338 next to whichfreight 112 is to be placed. Thus, the final destination forfreight 112 can easily be highlighted onMP visualization 512 by shading 514.MP visualization 512 provides a simple interface which conveys a great deal of information toworker 108 quickly and efficiently. By viewingMP visualization 512, a worker quickly knows whichspace 206,deck 336, and post 338 at which thefreight 112 is to be placed. It should also be apparent that asimilar MP visualization 512 can be provided to aworker 108 for picking upfreight 110 inleft section 508. - The instructions sent to
tablet 412 may also provide an optimized moving path (directions). The instructions provided ontablet 412 may also be supplemented by or replaced by augmented reality devices, such as head mounted displays (HMDs). For example, thetablet 412 may display instructions screen 500 while a HMD provides turn-by-turn instructions or augments thedock 202 with a moving path forworker 108. - Also, the instructions may include moves for
entire decks 336 and all the freight thereon if the freight is intended for the same destination. In some embodiments, the instruction may cause thetablet 412 to display additional information including shipment origin, priority moves, destination, weight, dimensions, departure time, due date, unload assignment movable platform dock location and shipment parcel location within theMP 204, and load assignment movable platform dock location and shipment parcel location. - As each instruction (i.e., move) is performed by a
worker 108 or anAGV 114, a reader (RFID or barcode) attached to thetablet 412 may be used to verify each move. For example, before a move is completed, aworker 108 first scans the identifier (e.g., barcode, RFID tag) onfreight 112 ordeck 336 and scans the identifier on theMP 204 ordeck 336. Then, the worker conveys thefreight 112 ordeck 336 to its destination and scans thedestination MP 204,deck 336,post 338 and/orfreight 112 to verify that the move has been completed. Fordecks 336, the provided instructions may also include a height of the originatingdeck 336 and the height at which thedeck 336 is to be moved to on the destinationmovable platform 202. Preferably, the heights at whichdecks 336 are placed onposts 338 are uniform on eachMP 204 which allows all moves to be standardized at eachdock 202. - After a move, the
worker 108 orAGV 114 is then supplied with the next instruction, preferably, based upon the previous destination in order to reduce overall travel distance. The next instruction may also be based on a priority of the instruction. It should be obvious to one of ordinary skill in the art thatMPs 204,decks 336,posts 338, andfreight 112 can be labeled with any combination of identifiers such a barcodes, RFID tags, NFC tags, or any other machine readable code. - In some embodiments, each
movable platform 204 is equipped with acollision avoidance system 414 which may include a camera, radar sensor, sonar sensor, etc. at a front end (i.e., opposite from the worker) ofMP 204. Thecollision avoidance system 414 can connect to thetablet 412 by a suitable wired or wireless connection such as Wi-Fi or Bluetooth. Thecollision avoidance system 414 allows aworker 108 to safely maneuver aMP 204 in and out oftrailers 110 and acrossdock 202. Thecollision avoidance system 114 may be provided with a light source to help the worker during the loading or unloading process. - Additional technologies including, but not limited to, temperature and vibration sensors, light sensors to determine if the trailer door is opened, weight sensors, obstacle detection as described in U.S. Provisional Application Ser. No. 62/414,952, filed Oct. 31, 2016, and a GPS or cellular device for tracking may also be equipped on the
MP 204. - As
freight 112,decks 336, andMPs 204 are being moved arounddock 202, it is important to keep track of the location of everything so it does not end up at the wrong final destination. Equipping eachworker 108 with atablet 412 helps to ensure that each instruction is carried out properly. However, aworker 108 may still movefreight 112 ordeck 336 without scanning it properly. Thus, thecross-dock management system 200 may utilize other sensors as a backup totablets 412 as will be described with reference again toFIG. 4 . - Such systems also enable
AGVs 114 to be deployed instead of or in addition to workers, thus enablingcross-dock management system 200 to be fully automated, if needed. A first example of such a system that may be employed by cross-dock management system isRFID array 416 which preferably comprises a plurality of RFID readers arranged in a grid abovedock 202. Each of the RFID readers inRFID array 416 is coupled to anRFID server 418 which is capable of real-time tracking of eachMP 204,post 338,deck 336, piece offreight 112,AGV 114, and/orworker 108 located ondock 202. The tracking information fromRFID server 418 is periodically or constantly provided to anetwork server 420 which can be used by realtime instruction algorithms 422 to verify that each instruction has been carried out properly. If the realtime instruction algorithms 422 detect that any instructions have been carried out improperly or thatMP 204,post 338,deck 336, piece offreight 112,AGV 114, and/orworker 108 has moved to an incorrect location, theinstructions database 410 can be corrected in real time to correct any errors. Further, if an incorrect or improper move is detected, an alert may be generated to notify appropriate personnel of the error. The incorrect moves can also be stored in thelocal warehouse database 406 to determine any trends or for later handling. This information could be used to monitor compliancy or malfunctioningAGVs 114. - The RFID tags used in combination with the present invention can store data indicative of, for example, shipment origin, destination, weight, cube, groupings, AGV-compliancy, dimensions, number of shipment parcels, due date, etc. or may simply indicate a tracking number. The RFID tag and any associated RFID reader may be configured to work using one or more RFID technologies, including, without limitation: (1) a Passive Reader Active Tag (PRAT) system; (2) an Active Reader Passive Tag (ARPT) system has an active reader, which transmits interrogator signals and also receives authentication replies from passive tags; and (3) an Active Reader Active Tag (ARAT) system uses active tags awakened with an interrogator signal from the active reader. A PRAT system has a passive reader that only receives radio signals from active tags (e.g., battery operated, transmit only). The reception range of a PRAT system reader can be adjusted from 1-2,000 feet, allowing flexibility in applications such as asset protection and supervision. A variation of the ARAT system could also use a Battery-Assisted Passive (BAP) tag which operates like a passive tag, but has a small battery to power the tag's return reporting signal. For example, passive ultra-high frequency (UHF) RFID tags may be used to identify, locate and track items within the dock and/or yard. Suitable UHF RFID tags, and associated RFID readers. While RFID is generally described herein, other technologies may be used in addition to, or in lieu of, RFID to facilitate tracking of the movable platforms and/or shipment parcel(s), such as near field communication (“NFC”).
-
Cross-dock management system 200 may also include avideo server 424 also in communication withnetwork server 422. A first function ofvideo server 424 is security which is handled bysecurity module 426. Preferably,video server 424 is capable of receiving video feeds from each device ondock 202 equipped with a video camera. For example,dock 202 may be equipped with a standard security system found atmost terminals 100 used for monitoring theft and facility access. The video feeds from one or more of the security cameras in the security system could be supplied tovideo server 424. Other video sources may include video feeds from cameras mounted on conveyance vehicles or AGVs 114 (e.g., part of collision avoidance system 414). And, as will be discussed later, video or camera information acquired bydimensioner array 442 may also be monitored byvideo server 424. -
Security module 426 may monitor all of the aforementioned described video feeds and detect movement to create alerts for security personnel. Further, each time an alert occurs,security module 426 may store the video associated with the event invideo database 428. - The various described video feeds may also be utilized to provide damage identification. A
comparison damage module 430 may be utilized to detect damagedfreight 112 by comparing each piece of imagedfreight 112 to previous images of thesame freight 112 acquired at an earlier point in time (e.g., earlier in the day, at another terminal 110, at pickup, etc.) using a difference algorithm to determine changes infreight 112. If any significant changes are detected in freight 112 (e.g., above a certain change threshold), thecomparison damage module 430 generates an exception which triggers a review of thefreight 112 by a supervisor or other personnel. As will be described in more detail later, all exceptions are stored and classified inexceptions database 432. - The video feeds may also be monitored by a machine
learning damage module 434. Machinelearning damage module 434 uses machine learning to detect damage in the video feeds. For example, the machinelearning damage module 434 may initially be supplied with various examples of freight damage images. Artificial intelligence can then be utilized to categorize and generalize the initial input information to determine damage and generate exceptions. As exceptions are corroborated by human review, the AI of machinelearning damage module 434 modifies its behavior appropriately. Over time, the machinelearning damage module 434 becomes more sophisticated at detecting damage tofreight 112 and would be capable of detecting damage in hard to image areas, such as on the top ofMP 204 which is out of sight ofworkers 108. Similarly, if any damage is detected by machinelearning damage module 434, an exception is generated which is stored inexceptions database 432 for further review. - The real
time instruction algorithms 422 are able to handle any exceptions or other problems that may occur in real time. For example, the realtime instruction algorithms 422 are provided with a supervisor orworker interface 436 which allows a supervisor to prioritizecertain MPs 204 orfreight 112. If a supervisor receives a telephone call or communication indicating thatcertain freight 112 has been prioritized or must reach a new and different final destination, the supervisor can useworker interface 436 to provide this information tocross-dock management system 200. The realtime instruction algorithms 422 then computes an exception which is stored inexception database 432 and revised instructions are provided toinstruction database 410. In this manner, the workflow ofworkers 108 andAGVs 114 ondock 202 is not interrupted. Theworkers 108 andAGVs 114 are simply provided new and/or updated instructions to carry out. - Real
time instruction algorithms 422 can also receive input from externalreal time data 438 such as weather, trailer delays, etc. For example, another terminal 100 may inform thecross-dock management system 200 of trailer delays or breakdowns. In another example, the realtime instruction algorithms 422 may be notified of externalreal time data 438 including weather events or road closures which will affect either inbound and/oroutbound trailers 110. -
Cross-dock management system 200 may also provideoutput data 440 to a shared network toother terminals 100. In this manner, all of thecross-dock management systems 200 among thevarious terminals 100 are linked together. The sharing ofoutput data 440 has many benefits. For example, if a certain geographical region has been hit by a natural disaster,MPs 204 can be rerouted todifferent terminals 100 to circumnavigate the area affected by the natural disaster. Thus, havingmultiple terminals 100 that are geographically distributed can be turned into an advantage by allowing the rerouting oftrailers 110 in real time. In some embodiments, new destination instructions can be communicated tomobile trailers 110 via a wireless communication interface such as cellular, radio, etc. - The
freight 112 carried on eachMP 204 is constrained by thetrailer 110 that it must fit into. For example, most pup trailers are not allowed to convey more than 24,000 pounds. And, the width, length, and height are constraints that the pallets and parcels cannot exceed.Input data 402 generally contains the weight of each piece offreight 112. However, in LTL shipping, the dimensions offreight 112 can vary greatly (e.g., long and narrow or cylindrical). Therefore, thecross-dock management system 200 may also employ adimensioner array 442 which monitors the dimensions of eachMP 204 to ensure that it does not exceed the interior size of thetrailer 110. Eachspace 206 on thedock 202 may be provided with its own dimensioner or one dimensioner may covermultiple spaces 206. Preferably, a dimensioner is an imaging device capable of monitoring the boundaries of theMP 204 as well as the height of thedecks 336 andfreight 112 placed upon theMP 204. The information from thedimensioner array 442 is collected and stored bydimensioner server 444. And, as previously described,dimensioner server 444 may provide any video data tovideo server 424 for further analysis. - The information collected by
dimensioner server 444 may be utilized by the realtime instruction algorithms 422 if it is detected that aparticular MP 204 has exceeded acceptable constraints to length, width, and height. If any excess is detected, the realtime instruction algorithms 422 provide new instructions toinstructions database 410. Also, thedimensioner server 444 can be used to detect where irregular shapedfreight 112 can be placed. For example, certain LTL shipments, such as ladders, could be placed on top of aMP 204 as long as the resulting load does not exceed a predetermined height and/or weight requirement. - The
dimensioner array 442 can also be used to track the length, width, and height of thefreight 112 placed ondecks 336 to ensure it does not exceed a certain size limit. If it is determined that the size limit is exceeded, the realtime instruction algorithms 422 can calculate new instructions to alleviate any problems. - As with any of the other described systems, such as the
RFID server 418, thedimensioner server 444 also generates exceptions if any irregularities on anMP 104 are discovered. For example, if thedimensioner server 442 detects that the width or length of anMP 204 is irregular, this may indicate thatfreight 112 is placed incorrectly or is in danger of falling offMP 204 ordecks 336. -
Dimensioner array 442 may utilize any combination of known or future technologies capable of determining the outer dimensions of an object. For example,dimensioner array 442 may include vision systems such as HD video cameras or infrared laser scanners having low tolerances (e.g., ½″ or less). Thedimensioner array 442 may scan anentire MP 204, asingle deck 336, or individual pieces offreight 112. Thedimensioner array 442 can provide real time dimension data asfreight 112 is conveyed. Eachspace 206 may be outfitted with its own dimensioner. Or, in other embodiments, a dimensioner may be outfitted on one or more drones which can covermultiple spaces 206. - The weight of the
freight 112 placed ondeck 336 must also be tracked because eachdeck 336 is assigned a weight limit which is constrained by the amount of weight to be placed onposts 338. The weight ofdecks 336 can be tracked using multiple means. For example, the conveyance vehicles orAGVs 114 used to movedecks 336 may be outfitted with weight sensors (e.g., in the tines) that are able to detect the amount of weight being moved. The realtime instruction algorithms 422 can then utilize this data to verify that an upper weight limit has not been exceeded for eachdeck 336 or to calculate new instructions. -
Other sensors 446 may also be utilized to monitorMPs 204. For example, eachspace 206 may be provided with a scale or other weight measuring device to ensure that theMP 204 does not exceed a certain weight limit. The weight sensors may also be pressure sensitive to determine if the load on each movable platform is distributed equally or logically (e.g., to place more weight on the end ofMP 204 to prevent possible sag in the middle). The realtime instruction algorithms 422 can use the data from other sensors 446 (e.g., temperature, humidity) to make any necessary corrections toinstructions database 410. It should be apparent to one of ordinary skill in the art that sensors may be added or deleted from cross-dock management system at any time simply by installing or removing the sensors and adapting the realtime instruction algorithms 422 appropriately. -
Cross-dock management system 200 also incorporates anAGV server 448 which is used to aid the navigation of eachAGV 114 as well as monitor its real time location and status. For example, theAGV server 448 may utilize position information gathered byRFID server 418 to determine if eachAGV 114 is in its correct location ondock 202. TheAGV server 448 can also be utilized to network allAGVs 114 so that eachAGV 114 is aware of all AGV locations in real time.AGV server 448 may also be utilized to calculate the paths required for eachAGV 114 to execute move instructions frominstructions database 410 and to verify that each instruction is correctly performed. -
AGV server 448 also incorporates remote control (RC)module 450 which allows anyAGV 114 to be remotely controlled as has already been described. Thus,AGV server 448 provides an interface which allowsAGVs 114 to be automated and or remotely controlled. - If
multiple AGVs 114 are used ondock 202, the realtime instruction algorithms 422 can also take into account the cycling ofAGVs 114 that must occur. That is, eachAGV 114 will eventually need to be recharged, refueled, or be decommissioned for maintenance. In those instances, the realtime instruction algorithms 422 would reallocate moves tonew AGVs 114 or temporarily assign workers if noadditional AGVs 114 are available. In this manner, the workflow on thedock 202 is not interrupted. - The
AGVs 114 may each utilize different guidance systems or eachAGV 114 may utilize one or more different guidance methods in isolation or in combination. For example, theAGVs 114 tasked with movingMPs 204 may only need to use a much simpler guidance method such as a combination of guide tape and natural feature navigation, ceiling tag (or other visual marker) navigation, infrared sensors, marker grid navigation. Infrared navigation offers the advantage that it is not interrupted by interference from visible lights. Passive infrared tags placed throughout thedock 202 may indicate a specific location ondock 202. AGV navigation can be supplemented by other navigation techniques such as odometry, active RFID, passive RFID, and/or SLAM (simultaneous location and mapping). -
AGVs 114 tasked with movingdecks 336 or individual pieces offreight 112 would require the use of one or more sophisticated guidance methods such as laser target navigation, inertial navigation, vision guidance, and/or geoguidance. A properly setup AGV guidance system would allow for multiple improvements withincross-dock management system 200. First, a fully (or mostly) automated AGV system would have much less downtime than one staffed solely byworkers 108 because no rest or stops would occur. Further, because the navigation is very precise, the distance betweenspaces 206 could possibly be reduced, allowing evenmore spaces 206 to be placed ondock 202. - The
AGVs 114 may also be modular as has already been described. For example, eachAGV 114 may be outfitted with a video camera to supplement the video gathered byvideo server 424. TheAGVs 114 may also be able to receive modular attachments to perform other functions such as cleaning (e.g., vacuum or broom attachment) or placing securement (e.g., shoring beams). - For illustration purposes, the steps utilized to unload and load
MPs 204 on atrailer 110 will be described in detail using the flowchart ofFIG. 6 referencing thedocks 202 shown inFIG. 2A or 2B and the various components ofcross-dock management system 200 shown inFIG. 4 . First, aninbound trailer 110 containing aMP 204 arrives at the terminal 100 in step 602. Thetrailer 110 is then directed to a particular door in step 604 using instructions retrieved frominstructions database 410. TheMP 204 is then unloaded from the trailer instep 606 and scanned by aworker using tablet 412. Also, at this point, theRFID array 416 will have scanned any RFID tags contained on theMP 204 since it is now located ondock 202. If theRFID array 416 identifies an RFID tag or tags that should not be present (e.g., not in the manifest data), an exception is generated so that the correct destination of thefreight 112 can be determined. This allowsmisplaced freight 112 to be identified much earlier during transmission of the cargo. - Using the instructions provided by
instructions database 410, theMP 204 is then conveyed into its optimizedspace 206 ondock 202 instep 608. Theworker 108 verifies that theMP 204 has been properly moved by scanning an identifier associated with the optimizedspace 206 along with any of the identifiers provided onMP 204 instep 610. Alternatively, or in addition, theRFID array 416 orother sensors 446 may also be utilized to verify that theMP 204 is in the optimizedspace 206. - Any securement, such as shoring beams or cargo straps, are then removed from
MP 204 instep 612. Step 612 can be performed manually byworkers 108 or by anAGV 114 as has already been described. After it is verified that all securement has been removed in step 614, the unloading/loading ofMP 204 commences. - At this point,
workers 108 are provided with the worker instructions andAGVs 114 are provided with AGV instructions frominstructions database 410 in step 616. For eachMP 204, theworkers 108 andAGVs 114 carry out all assigned moves for theMP 204 instep 618. The specifics ofstep 618 as to how specific instructions, such as deck or freight movements, are carried out byAGVs 114 will be described with reference toFIGS. 7A, 7B , and 8 later. - The instructions carried out by the
workers 108 andAGVs 114 instep 618 can be classified as either a freight move (moving a single parcel or pallet) or a deck instruction (moving decks 336). Deck instructions are advantageous because what previously would have taken several freight moves can now be accomplished in a single deck move. Also, because the freight on thedeck 336 is not touched, there is far less likelihood that the freight ondeck 336 will become damaged during a deck move. Withdecks 336, it is possible that freight placed thereon is only handled individually at the origin anddestination docks 202. - After all instructions for
MP 204 have been carried out, securement must be placed in step 620 (either manually or using an AGV). After thecross-dock management system 200 is notified that the securement has been placed in 622, an alert is generated to notify the supervisor (or similar personnel) that theMP 204 is ready to be inspected. In step 624, a supervisor verifies thatMP 204 meets all specifications and that securement has been placed properly. For example, the supervisor may check to see if anyfreight 112 has been damaged. - Next, using instructions retrieved from
instructions database 410, securedMP 204 is conveyed to a particular door to a waiting,empty trailer 110 in step 626. It should be noted that since aMP 204 can be quickly unloaded and unloaded as has been described, theempty trailer 110 does not have to wait atdock 202 and instead can wait in a yard. Then, when theMP 204 is ready to be loaded (e.g., after steps 624 or 626), thecorrect trailer 110 in the yard can be notified and assigned a door to drive to for loading. Thus, it should be apparent that this provides a significant advantage over traditional LTL methods at which trailers generally have to stay at the door for long periods while they are unloaded or loaded. Thecross-dock management system 200 of the present invention only requires the presence oftrailers 100 at doors if aMP 204 is being unloaded or loaded. - Before
MP 204 is loaded intotrailer 410, a worker scans an identifier associated withMP 204 along with an identifier associated with thetrailer 110 or door in step 628. This process can also be automated usingRFID array 416. Step 628 associates theoutbound MP 204 with a particular trailer and creates new manifest data that can be provided to thenext terminal 100. - The
MP 204 is then loaded onto thetrailer 110 in step 630 and thetrailer 110 departs instep 432. Steps 602-632 are repeated for eachinbound MP 104 ondock 202. - The steps utilized for moving
decks 336 with a pair ofAGVs 114 in a deck instruction will be described with reference toFIG. 7A . It is first determined instep 702 if all freight on aparticular deck 336 is destined for the sameoutbound MP 204 or storage area (to be described later). If the determination is positive, the beginning of the move ofdeck 336 is started instep 704. TheAGVs 114 utilized to movedeck 336 in this described method are pairs ofAGVs 114 which engage the sides ofdecks 336 in unison as will now be described. First, the AGV team is initiated and moves into position on the sides ofdeck 336 which is to be moved instep 704 in accordance with the provided deck instruction. EachAGV 114 then positions itself to the level of thedeck 336 to be moved instep 706. As has been explained, the height of eachdeck 336 on eachMP 204 is known (e.g., from the manifest data or other calculated instructions) and this information is provided in the deck instruction. EachAGV 114 then engagesdeck 336 on each side instep 708. Ifdeck 336 does not includeslots 340, other gripping means may be utilized for theAGV 114 to attach to deck 336 (e.g.,deck 336 can be lifted from beneath). - Each AGV then lifts
deck 336above posts 338 instep 710.Deck 336 is longitudinally conveyed to the end ofMP 204 instep 712. At this point,deck 336 is lowered to travel height by the AGVs 114 (e.g., to prevent toppling) instep 714. The supplied deck instruction includes a destination for thedeck 336. As previously mentioned, thedeck 336 may be conveyed to (a) anotherMP 204 or (b) a storage area as shown indecision step 716. If the destination is anotherMP 204,deck 336 is conveyed to the appropriate end of adestination MP 204 instep 718. TheAGVs 114 then raisedeck 336 to the appropriate height for placement instep 720 and thenlower deck 336 ontoposts 338 instep 722.Deck 336 is then released instep 724 at which point theAGVs 114 are available for the next move. Alternatively, if the destination for thedeck 336 is a storage area afterstep 716, theAGVs 114 convey thedeck 336 to the storage area instep 726. - The steps utilized for moving
decks 336 with asingle AGV 114 having a pair of forklift tines will now be described with reference toFIG. 7B . It is first determined instep 750 if all freight on aparticular deck 336 is destined for the sameoutbound MP 204 or storage area. If the determination is positive, the beginning of the move ofdeck 336 is started instep 752. First, theAGV 114 is initiated and moves into position atdeck 336 which is to be moved instep 754 in accordance with the provided deck instruction. TheAGV 114 then positions itself to the level of thedeck 336 to be moved instep 756 and raises its tines instep 756. As has been explained, the height of eachdeck 336 on eachMP 204 is known (e.g., from the manifest data or other calculated instructions) and this information is provided in the deck instruction. TheAGV 114 thenslots 340 indeck 336 and liftsdeck 336 instep 758. -
AGV 114 reverses direction untildeck 336 clearsposts 338 instep 760. At this point,deck 336 is lowered to travel height by the AGV 114 (e.g., to prevent toppling) instep 762. The supplied deck instruction includes a destination for thedeck 336. As previously mentioned, thedeck 336 may be conveyed to (a) anotherMP 204 or (b) a storage area as shown indecision step 764. If the destination is anotherMP 204,deck 336 is conveyed to the appropriate location of adestination MP 204 instep 766. TheAGV 114 then raisesdeck 336 to the appropriate height for placement instep 768 and thenlower deck 336 ontoposts 338 instep 770.Deck 336 is then released instep 772 at which point theAGV 114 is available for the next move. Alternatively, if the destination for thedeck 336 is a storage area afterstep 764, theAGV 114 conveys thedeck 336 to the storage area instep 774. - Referring now to
FIG. 8 , described is a process that occurs when theinitial setup optimization 408 determines that a plurality ofdecks 336 can be more optimally rearranged to directfreight 112 to its proper destination. For example, theinitial setup optimization 408 may determine, based on the manifest data, that the freight on one ormore decks 336 can be more optimally rearranged to increase the capacity utilization oftrailers 110. This process may only occur if theinitial setup optimization 408 determines that a predetermined number ofdecks 336 can be rearranged, thus making rearrangingfreight 112 worthwhile. - First,
workers 108 orAGVs 114 are utilized to move thedecks 336 to be rearranged to a freight area instep 802. The rearranging is preferably done in a separate area of thedock 202 away fromspaces 206 because of the more cautious moves required when movingfreight 112. After all thedecks 336 have been placed in the freight area, thefreight 112 ondecks 336 is rearranged according to instructions calculated byinitial setup optimization 408 instep 804. Next, in order to make use of any leftover space ondecks 336,freight 112 from the storage area may be moved to empty spaces ondecks 336 instep 806. Thedecks 336 can then be placed onMPs 204 instep 808. - It is contemplated that one or more different types of
AGVs 114 may be utilized in combination with the present invention. For example, a first type ofAGV 114 may be utilized to moveMPs 204 in/out oftrailers 110 and ontodock 202. TheseAGVs 114 may require simpler construction than others because they only need to hook ontoMPs 204 and move them arounddock 202. - A second type of
AGV 114 may be utilized to execute deck instructions or, in certain environments, single freight instructions as described with reference toFIG. 8 . With regards to movingdecks 336, this second type ofAGV 114 could operate alone or in pairs to movedecks 336 aboutdock 202 as has been described inFIGS. 7A and 7B . If in pairs, afirst AGV 114 may act as a master AGV and be in communication withcross-dock management system 200 to receive instructions and carry out orders. Thesecond AGV 114 would be controlled by the master AGV and function as a slave AGV. The slave AGV would be less costly as it would not require all of the features and communication equipment of the master AGV. - A third type of
AGV 114 could be utilized to execute single freight instructions, primarily (moving ofsingle freight 112 from afirst MP 204 to a second MP 204). Since theseAGVs 114 would only be responsible for moving smaller freight 112 (less than a full deck 336), they would be less expensive to produce and maintain. They would also require a much smaller footprint than the first or second type ofAGV 114 described above. It should be obvious that the less space that is taken up byAGVs 114 on thedock 202, there is less potential for collisions and other mishaps. As an example, theseAGVs 114 may simply have a weight bearing platform with automated rollers on top. TheAGVs 114 could use a centralized system of rollers to pick up and drop offfreight 112.Such AGVs 114 may be useful for long haul movements such as moving freight fromdock 202 to a storage area and vice versa. - However, it is also possible for a single type of
AGV 114 to execute all of the moves required by the present invention. Such an AGV may potentially be more costly, but maintenance and other costs could be kept to a minimum because different systems/sets ofAGVs 114 would not have to be maintained acrossmultiple docks 202. - Each deck instruction contains the location of the
source deck 336 and a location of thedestination MP 202. Further, the deck instruction also includes the height at which the source deck is located. As already stated, the heights at whichdecks 336 are placed onposts 338 are preferably standardized. Therefore, each deck height can be assigned a unique identifier (1-x), similar to the section identifiers. Thus, the sections A-F and the differing deck placement heights can all be standardized by using a combination of a section identifier and a height identifier on eachMP 204. An example deck instruction would be as follows: ORIGIN: [MP identifier, section identifier, height identified]-DESTINATION[MP identifier, section identifier, height identifier]. Such a deck instruction includes all necessary information to move adeck 336 from an origin to a destination. - Freight instructions may also be structured in a similar manner. However, more information may be needed in a freight instruction for both the origin and the destination. Similar to deck instructions, freight instructions may utilize a similar structure. A freight instruction may additionally include a quadrant location (using
identifiers 342 and/or tags 344) location for further specificity. That is, the more information that can be provided to thecross-dock management system 200 about the particulars of thedock 202 and the particulars of moves, the more that can be automated. - As has already been described, the
initial setup optimization 408 is able to divide instructions into worker instructions and AGV instructions using a variety of criteria. For example, because deck/MP instructions are simpler andMPs 204 anddecks 336 are fairly large and standardized, only those moves may be automated while the other moves may be carried out byworkers 108. Any combination of automation/manual moves are compatible with the present invention because the instructions are the same regardless. The only difference is the receiver of the instruction (worker 108 or AGV 114) and these instructions be rerouted on the fly by the realtime instruction algorithms 422. - As another example,
AGV server 448 may keep track of how many moves eachAGV 114 has executed. If it is determined that aparticular AGV 114 has been overburdened, this information may be supplied to realtime instruction algorithms 422 so that the moves amongAGVs 114 are distributed more evenly. This would allow the work load assigned to eachAGV 114 to be balanced which would lead to less breakdowns and maintenance. - In some embodiment, individual pieces of freight may also be assigned unique identifiers to note special properties or allow them to be moved using an AGV. For example, some freight may be marked as delicate. Delicate freight is preferably manually loaded onto a
deck 336 or aMP 204. For example, if freight is marked as delicate and there is enough delicate freight to fill adeck 336, thedeck 336 may be loaded manually first and then anAGV 114 could be used to move the loadeddeck 336 into a final position. It is a particular strength of the present invention that it can handle interruptions and automatically reroute the workflow arounddock 202 to handle those interruptions (such as the needed loading of a manual deck 336). Also, since the system of the present invention knows the inbound manifest data, which would also include such freight indicators, the other instructions could be optimized to minimize the impact to workflow while the delicate freight (or other awkward freight) is being loaded manually. - The storage facility in which
decks 336 are placed may take many forms. If there is a requirement for only occasional storage of decks 336 (e.g., delayed schedule or delivery, etc.), the storage area may simply be a portion ofdock 202 having assigned spaces fordecks 336. Thecross-dock management system 200 would simply log the location of each placeddeck 336, similar to theMPs 204, so that it could be recalled when needed. However, if a great number ofdecks 336 need to be stored, a rack system could be utilized in which a number of racks (e.g., composed of four posts 338) could be arranged ondock 202 or at a different location. Each rack would be assigned an identifier and the height that each deck is stored at would be noted by cross-dock management system for later recall of the deck. A rack system maximizes floor space. In particular, the racks could be placed against the walls of thedock 202 to minimize the floor space taken up. - Still, in another embodiment, the storage facility may be an entirely separate and automated facility if
multiple decks 336 are to be stored long term. Such a facility would be useful, for example, for individuals traveling abroad that need to store items for long periods of time. Such individuals could be rented storage space in various sizes (an entire movable platform, a single deck, or combinations thereof) and those could be stored/retrieved at any time. -
FIG. 9 depicts a flowchart showing the steps utilized byinitial setup optimization 408 to calculate instructions frominput data 402. First, instep 902, theinput data 402 is received and stored inlocal warehouse database 406. Based on the received manifests ininput data 402, all outbound load points are identified byinitial setup optimization 408 instep 904. Using this information, the number ofMPs 204 for each load point can be determined instep 906. For example, aninbound MP 204 may havefreight 112 ordecks 336 which need to be transferred to three different destinations and would require at least two additional MPs 204 (i.e., because theinbound MP 204 is reused as anoutbound MP 204 once it has been unloaded/reloaded). - Next, for each
inbound MP 204, the initial setup optimization determines whichfreight 112 ordecks 336 need to be handled instep 908. For example, if the majority of pieces on aMP 204 are intended for thesame terminal 100, only a few select pieces need to be removed/loaded onto theMP 204 until it is ready to be loaded onto a waitingtrailer 110. This can significantly speed up the loading/loading process over the conventional LIFO process. Similarly, if all of thefreight 112 located on adeck 336 is intended for the same destination, only a single deck instruction needs to be calculated. Ifadditional MPs 204 are needed, theinitial setup optimization 408 adds additional MP movements to the instructions instep 910. Also, has already been described,additional MPs 204 can be placed overnight byAGVs 114 before anytrailers 110 arrive. - If
decks 336 andfreight 112 are capable of being moved ondock 202, theinitial setup optimization 408 will use a bin stacking algorithm to determine an optimal height at which each deck and/orfreight 112 is to be placed during a deck or freight instruction. Theinitial setup optimization 408 calculates the deck instruction using the weight as well as the known dimensions (l×w×h) of eachdeck 336. As already noted, the real time instruction algorithms 322 can correct any wrong instructions which have been calculated during the initial setup optimization. - Based upon a plurality of criteria (weight, number of parcels, number of inbound/
outbound MPs 204, number of pieces to be handled), theinitial setup optimization 408 determines an optimizedspace 206 for eachMP 204 ondock 202 instep 912. Theinitial setup optimization 408 also determines the number ofworkers 108 and/orAGVs 114 required to complete all necessary moves instep 914. This step avoids having too many or toofew workers 108 orAGVs 114 located ondock 102. - Based upon the number of assigned
workers 108 and AGVs 114 (step 914) and the number of pieces to be handled (step 908), theinitial setup optimization 408 determines all piece level moves for theworkers 108 and AGVs 114 (freight instructions and deck instructions) instep 916. The instructions are then stored ininstructions database 410 instep 918. Step 902-918 are repeated daily for each set ofinput data 402 that is received bycross-dock management system 200. - In LTL shipping, shippers may desire to ship anywhere from a single piece of freight to an entire trailer, or anything in between. Therefore, for each shipper and pickup, it may be important to note and classify the shipments being picked up or dropped off at each facility. Further, this information will later be compiled into manifest data provided to each terminal 100 (and later used to calculate instructions and to route freight). Therefore, the more that is known about freight at the origin, the better the various cross-dock systems can manage the freight through the hub and spoke
terminals 100. The following classifications of freight provided by a shipper at an original are possible: - A) Loose freight
- B) Full deck with freight for (a) single destination or (b) multiple destination
- C) Full MP with freight for (a) single destination or (b) multiple destinations
- D) Multiple MPs with freight for (a) single destination or (b) multiple destination
- By classifying the pickups into these different categories, the
origin dock 202 can better ascertain what equipment will be needed to conduct the first leg of the shipment (i.e., number of movable platforms needed, number of trailers needed). Further, classifying the information at pickup allows thefreight 112 to be tagged at the earliest possible location (i.e., at pickup) and greatly reduces the possibility thatfreight 112 will be mislabeled or end up at thewrong terminal 100. For example, if it is noted early on that aMP 204 has freight intended for a single destination, thecross-dock management system 200 can route thisMP 204 without having to calculate any deck instructions or freight instructions, thus reducing the complexity of the instruction calculations. Similarly, fordecks 336 having freight for a single destination, only deck instructions have to be calculated. -
FIG. 10 depictsterminal 100 ofFIG. 1 adapted for use withMPs 204. In some instances, it may not be feasible for an LTL shipper to modify the layout ofdock 102. However,dock 102 can be made to be compatible withMPs 204 using the dock configuration shown inFIG. 10 . As shown,MPs 204 are placed at everyother door 902 to allow access to three sides ofMP 204 both on theinbound doors 104 andoutbound doors 106. This creates acentral aisle 904 which allows for easy movement ofMPs 204 andfreight 112. It should be apparent to one of ordinary skill in the art thatinitial setup optimization 408 and realtime instruction algorithms 422 can be adapted to work with the dock configuration shown inFIG. 10 . -
FIG. 11 depicts a shareddock 1102 which is share between independent carriers located in the same geographical region that have a partnership for the purposes of sharing data. In such cases, predictive analytics can optimize loads by combining partner carrier freight (e.g., shipment parcels) onto thesame MP 204, further reducing truck schedules and cost. As shown, afirst side 1104 ofdock 1102 is occupied by a first carrier and asecond side 1106 ofdock 1102 is occupied by a second carrier.First side 1104 andsecond side 1106 may be split equally or according to the terms of a partnership agreement. Information aboutMPs 204 and RFID tags can be made available from thefirst side 1104 to thesecond side 1106, and vice versa. However, eachside cross-dock management system 200 to provide data confidentiality. The twocross-dock management systems 200 may be linked in order to share limited data. As an example, thecross-dock management system 200 associated withfirst side 1104 may determine that it is more economically feasible to have thesecond side 1106 deliver certain parcels. Thesecond side 1106 may agree or disagree to each request fromfirst side 1104. -
FIG. 12 depicts a flowchart showing the collaboration between twocross-dock management systems 200 which share dock 1002. Thecross-dock management system 200 associated withfirst side 1104 is cross-dock management system A and thecross-dock management system 200 associated withfirst side 1104 is cross-dock management system B. Cross-dock management systems A and B each feed collaboration data intocollaboration heuristic model 1202. Collaboration data may include information such as the number of available spaces onMPs 204, the destinations of allMPs 204, manifest data about any overflow freight 112 (i.e., a parcel which would require an extra shipment or does not fit within available MPs 204), etc. Thecollaboration heuristic model 1202 compares the collaboration data from cross-dock management systems A and B and determinesoptions 1204 for carrier A andoptions 1206 for carrier B. Carrier A and Carrier B can agree/disagree to each option or cross-dock management systems A and B may be programmed to automatically accept/deny certain options instep 1208. Any options that agreed upon will be updated in theinstructions database 410 as computed by realtime instruction algorithms 422 instep 1210. - The above-cited patents and patent publications are hereby incorporated by reference in their entirety. Although various embodiments have been described with reference to a particular arrangement of parts, features, and the like, these are not intended to exhaust all possible arrangements or features, and indeed many other embodiments, modifications, and variations will be ascertainable to those of skill in the art. Thus, it is to be understood that the invention may therefore be practiced otherwise than as specifically described above.
- While the present invention has been described with respect to what is presently considered to be the preferred embodiments, it is to be understood that the invention is not limited to the disclosed embodiments. To the contrary, the invention is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims. The scope of the following claims is to be accorded the broadest interpretation so as to encompass all such modifications and equivalent structures and functions.
Claims (5)
1. A cross-dock management system comprising:
a cross-dock having a plurality of doors at opposing ends of the cross-dock for receiving inbound trailers and for loading outbound trailers
a plurality of spaces arranged in a grid pattern on the cross-dock,
wherein the grid pattern comprises at least three rows and at least three columns, and
wherein the separated spaces are angled approximately 30-45° with respect to the plurality of doors;
a plurality of movable platforms arranged on the cross-dock in the separated spaces,
wherein an area of each movable platform is substantially the same as an area of the separated spaces;
wherein the plurality of movable platforms comprise:
a plurality of vertical posts; and
a plurality of engagement members on each vertical post configured to receive modular decks placed on the plurality of engagement members at varying heights;
a plurality of conveyance vehicles,
wherein a first subset of the plurality of conveyance vehicles are manually operated conveyance vehicles, and
wherein a second subset of the plurality of conveyance vehicles are automated guided vehicles (AGVs);
a local database for storing received manifest data,
wherein the manifest data includes information classifying inbound movable platforms, inbound modular decks, and inbound freight as AGV-compatible or AGV-incompatible; and
an initial setup optimization server for determining a plurality of ordered move instructions for moving the inbound movable platforms, the inbound modular decks, and the inbound freight based upon the manifest data,
wherein a first subset of the ordered move instructions are assigned to and performed by the AGVs, and
wherein a second subset of the ordered move instructions are assigned to and performed by the manually operated conveyance vehicles.
2. The cross-dock management system according to claim 1 , wherein the ordered move instructions are divided into movable platform instructions, modular deck instructions, and freight instructions.
3. The cross-dock management system according to claim 2 , wherein all movable platform instructions are included in the first subset of the ordered move instructions.
4. The cross-dock management system according to claim 2 , wherein all modular deck instructions are included in the first subset of the ordered move instructions.
5. The cross-dock management system according to claim 4 , wherein all freight instructions are included in the second subset of the ordered move instructions.
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US16/435,997 US20190295010A1 (en) | 2016-10-31 | 2019-06-10 | System and method for automated cross-dock operations |
US16/749,173 US11354605B2 (en) | 2016-10-31 | 2020-01-22 | System and method for automated cross-dock operations |
US17/735,621 US20220261709A1 (en) | 2016-10-31 | 2022-05-03 | System and method for automated cross-dock operations |
US18/376,651 US20240028980A1 (en) | 2016-10-31 | 2023-10-04 | System and method for automated cross-dock operations |
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US201662415054P | 2016-10-31 | 2016-10-31 | |
US15/798,729 US10147059B2 (en) | 2016-10-31 | 2017-10-31 | System and method for automated cross-dock operations |
US16/169,523 US20190057331A1 (en) | 2016-10-31 | 2018-10-24 | System and method for automated cross-dock operations |
US16/435,997 US20190295010A1 (en) | 2016-10-31 | 2019-06-10 | System and method for automated cross-dock operations |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US16/169,523 Continuation US20190057331A1 (en) | 2016-10-31 | 2018-10-24 | System and method for automated cross-dock operations |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US16/749,173 Continuation US11354605B2 (en) | 2016-10-31 | 2020-01-22 | System and method for automated cross-dock operations |
Publications (1)
Publication Number | Publication Date |
---|---|
US20190295010A1 true US20190295010A1 (en) | 2019-09-26 |
Family
ID=60451177
Family Applications (6)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US15/798,729 Active US10147059B2 (en) | 2016-10-31 | 2017-10-31 | System and method for automated cross-dock operations |
US16/169,523 Abandoned US20190057331A1 (en) | 2016-10-31 | 2018-10-24 | System and method for automated cross-dock operations |
US16/435,997 Abandoned US20190295010A1 (en) | 2016-10-31 | 2019-06-10 | System and method for automated cross-dock operations |
US16/749,173 Active 2038-03-27 US11354605B2 (en) | 2016-10-31 | 2020-01-22 | System and method for automated cross-dock operations |
US17/735,621 Abandoned US20220261709A1 (en) | 2016-10-31 | 2022-05-03 | System and method for automated cross-dock operations |
US18/376,651 Pending US20240028980A1 (en) | 2016-10-31 | 2023-10-04 | System and method for automated cross-dock operations |
Family Applications Before (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US15/798,729 Active US10147059B2 (en) | 2016-10-31 | 2017-10-31 | System and method for automated cross-dock operations |
US16/169,523 Abandoned US20190057331A1 (en) | 2016-10-31 | 2018-10-24 | System and method for automated cross-dock operations |
Family Applications After (3)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US16/749,173 Active 2038-03-27 US11354605B2 (en) | 2016-10-31 | 2020-01-22 | System and method for automated cross-dock operations |
US17/735,621 Abandoned US20220261709A1 (en) | 2016-10-31 | 2022-05-03 | System and method for automated cross-dock operations |
US18/376,651 Pending US20240028980A1 (en) | 2016-10-31 | 2023-10-04 | System and method for automated cross-dock operations |
Country Status (5)
Country | Link |
---|---|
US (6) | US10147059B2 (en) |
EP (1) | EP3533006A1 (en) |
CA (1) | CA3041094C (en) |
MX (1) | MX2019004978A (en) |
WO (1) | WO2018081730A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109683504A (en) * | 2017-10-18 | 2019-04-26 | 北京京东尚科信息技术有限公司 | Outbound control method, device, electronic equipment and storage medium |
US20210357995A1 (en) * | 2017-02-27 | 2021-11-18 | Maruichi Warehouse Co., Ltd. | Information processing device |
Families Citing this family (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11775892B2 (en) | 2013-10-03 | 2023-10-03 | Crc R&D, Llc | Apparatus and method for freight delivery and pick-up |
US9367827B1 (en) * | 2014-12-15 | 2016-06-14 | Innovative Logistics, Inc. | Cross-dock management system, method and apparatus |
WO2018081730A1 (en) * | 2016-10-31 | 2018-05-03 | Innovative Logistics, Inc. | System and method for automated cross-dock operations |
KR102331763B1 (en) * | 2017-06-22 | 2021-11-26 | 현대자동차주식회사 | Apparatus and method for controlling autonomous driving and parking through navigation apparatus equipped in vehicle |
US10787315B2 (en) * | 2017-08-28 | 2020-09-29 | Google Llc | Dynamic truck route planning between automated facilities |
US20210334736A1 (en) * | 2017-08-31 | 2021-10-28 | Crc R&D, Llc | Management of vehicular traffic at a facility having allocable space resources |
CA3074289C (en) | 2017-08-31 | 2023-09-26 | Crc R&D, Llc | Management of vehicular traffic at a facility having allocable space resources |
US11841216B2 (en) * | 2018-04-30 | 2023-12-12 | Zebra Technologies Corporation | Methods and apparatus for freight dimensioning using a laser curtain |
US20190362311A1 (en) * | 2018-05-22 | 2019-11-28 | United States Postal Service | Systems and methods for item tracking and delivery |
CN109669427A (en) * | 2018-07-12 | 2019-04-23 | 北京图森未来科技有限公司 | Realize the system and relevant device of automatic transport of goods |
CN109544081B (en) * | 2018-12-08 | 2021-06-11 | 武汉普罗格集成科技有限公司 | Logistics sorting mode matching method and system |
US11443396B2 (en) * | 2019-02-25 | 2022-09-13 | Walmart Apollo, Llc | Systems and methods for prioritizing trailers at receiving facility |
JP7308064B2 (en) * | 2019-04-01 | 2023-07-13 | 日野自動車株式会社 | Operation management system |
CN111653098B (en) * | 2020-06-04 | 2022-04-26 | 南京航空航天大学 | Intersection passing sequence optimization method for automatic guided vehicle with multiple loading capacity |
WO2022012725A1 (en) * | 2020-07-13 | 2022-01-20 | Portchain Aps | Method of operating a container carrier terminal |
JP7439747B2 (en) * | 2020-12-24 | 2024-02-28 | トヨタ自動車株式会社 | Conveyance system, conveyance method, and program |
JP7512221B2 (en) | 2021-02-24 | 2024-07-08 | 住友重機械工業株式会社 | Cargo Handling System |
CN113256050B (en) * | 2021-03-01 | 2024-01-09 | 一汽物流有限公司 | Robot annular storage system and AGV hybrid scheduling method and system |
CN113998358B (en) * | 2021-10-28 | 2023-01-31 | 深圳市库宝软件有限公司 | Method, device, equipment, storage medium and program product for picking up goods |
CN115359656B (en) * | 2022-08-12 | 2024-04-02 | 青岛港国际股份有限公司 | Automatic container terminal yard end interaction zone lane distribution method |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030050819A1 (en) * | 2001-08-31 | 2003-03-13 | Koenigbauer Mary Jo | Computer-implemented, integrated system and method for managing global logistics |
US20050125247A1 (en) * | 2003-05-13 | 2005-06-09 | Ding Steven A. | Industrial vehicle fleet management system |
US20070279224A1 (en) * | 2006-06-06 | 2007-12-06 | James Peter Branigan | System and Method for Swapping Tag Reads Based on Statistical Analysis of Known Environment |
US20090293756A1 (en) * | 2008-06-03 | 2009-12-03 | Kaci Intermodal Systems, Llc | System, network and method for transporting cargo |
US20100241532A1 (en) * | 2009-03-17 | 2010-09-23 | Paul Biddle | System, method, and computer program product for third-party and fourth-party logistics |
US20120191272A1 (en) * | 2011-01-24 | 2012-07-26 | Sky-Trax, Inc. | Inferential load tracking |
US20120239224A1 (en) * | 2011-03-18 | 2012-09-20 | Mccabe Paul P | Integration of an autonomous industrial vehicle into an asset management system |
US9367827B1 (en) * | 2014-12-15 | 2016-06-14 | Innovative Logistics, Inc. | Cross-dock management system, method and apparatus |
US10147059B2 (en) * | 2016-10-31 | 2018-12-04 | Innovative Logistics, Inc. | System and method for automated cross-dock operations |
Family Cites Families (47)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2678139A (en) | 1951-08-25 | 1954-05-11 | Alfred M Gildersleeve | Trailer or like body freight loading device |
US3667635A (en) | 1969-07-14 | 1972-06-06 | Hackney & Sons Inc J A | Combined truck body and wheeled rack and method of loading and unloading a van |
US3880299A (en) | 1972-07-17 | 1975-04-29 | Rapistan Inc | Warehousing system |
US3938678A (en) | 1974-09-18 | 1976-02-17 | Kern Ruy E | Cargo transport system |
US4231695A (en) | 1978-07-10 | 1980-11-04 | Weston Sr Robert M | Cargo loading and unloading apparatus for trucks |
DE2951271A1 (en) | 1979-12-20 | 1981-07-02 | EWV Eisenbahnwaggon GmbH & Co KG Vermietungsgesellschaft, 4350 Recklinghausen | Pallet assembly for railway wagons or containers - has rollers running onto rails, in container or rail car from loading ramp locked in position during transit |
US5011358A (en) | 1988-10-25 | 1991-04-30 | Andersen Eric T | Height indicator for a fork lift truck |
US5454672A (en) | 1993-03-17 | 1995-10-03 | G & G Intellectual Properties, Inc. | Adjustable load-carrying frame for fully utilizing transport enclosure space |
JP2904684B2 (en) | 1993-09-01 | 1999-06-14 | 川崎製鉄株式会社 | Loading position optimizing device and loading position determining method |
CA2144886A1 (en) | 1995-03-17 | 1996-09-18 | William J. Doherty | Video camera guidance system for forklifts |
US5799585A (en) | 1996-10-21 | 1998-09-01 | Lock Nest, L.L.C. | Stackable pallet |
WO2001019712A1 (en) | 1999-09-14 | 2001-03-22 | William Hagenzieker | Cargo-transfer apparatus and method |
AU2001271966A1 (en) | 2000-07-11 | 2002-01-21 | Honda Of America Mfg., Inc. | Super cross-dock logistics system and method |
US8050625B2 (en) | 2000-12-22 | 2011-11-01 | Terahop Networks, Inc. | Wireless reader tags (WRTs) with sensor components in asset monitoring and tracking systems |
US6937992B1 (en) | 2000-12-29 | 2005-08-30 | Arrowstream, Inc. | Transport vehicle capacity maximization logistics system and method of same |
US6529797B2 (en) | 2001-03-05 | 2003-03-04 | Dell Products L.P. | System and method for automatically releasing collections of goods for shipment |
US20050149226A1 (en) | 2002-04-09 | 2005-07-07 | Ebox, Inc. | Warehousing system and method |
US7030760B1 (en) | 2001-08-07 | 2006-04-18 | Seecontrol, Inc. | Method and apparatus for ensuring reliable loading of materials on aricraft and other vehicles |
US6669089B2 (en) | 2001-11-12 | 2003-12-30 | 3M Innovative Properties Co | Radio frequency identification systems for asset tracking |
US7101139B1 (en) | 2003-05-06 | 2006-09-05 | Benedict Charles E | Automated material handling system with motorized transfer vehicles |
US7991505B2 (en) | 2003-08-29 | 2011-08-02 | Casepick Systems, Llc | Materials-handling system using autonomous transfer and transport vehicles |
US7865398B2 (en) | 2003-09-30 | 2011-01-04 | Microsoft Corporation | Radio frequency identification tag on picking container and display of picklist to order filler |
US7603299B1 (en) | 2004-05-28 | 2009-10-13 | Target Brands, Inc. | Automated receiving system |
US20060015532A1 (en) | 2004-07-19 | 2006-01-19 | Mizell L W | Method and system for integrated foodservice management |
US8731708B2 (en) | 2005-03-10 | 2014-05-20 | Amazon Technologies, Inc. | Method and apparatus for multi-destination item selection using motes |
US8626540B2 (en) | 2005-05-23 | 2014-01-07 | Oracle International Corporation | Method and apparatus for transportation planning based on mission-specific vehicle capacity constraints |
US7327262B2 (en) | 2005-10-12 | 2008-02-05 | Mantic Point Solutions Limited | System and method for electronic article surveillance |
US20070136079A1 (en) | 2005-12-08 | 2007-06-14 | Sap Ag | Method and system for planned transportation cross-docking |
US20070174148A1 (en) | 2005-12-30 | 2007-07-26 | Francesca Schuler | Method for resource management in a supply chain |
US20070156491A1 (en) | 2005-12-30 | 2007-07-05 | Francesca Schuler | Method and system for request processing in a supply chain |
US7454811B1 (en) * | 2006-01-17 | 2008-11-25 | Christopher Lon Stotka | Cross-dock system |
US7739147B2 (en) | 2006-06-06 | 2010-06-15 | International Business Machines Corporation | System and method for pallet identification based on threshold of case-level tags |
US20080103944A1 (en) | 2006-10-30 | 2008-05-01 | Mobile Logistics Management L.L.C. | Intelligent Pallet |
US20080167817A1 (en) | 2007-01-06 | 2008-07-10 | Transbotics Corporation | Automated cargo loading systems and methods |
US9060848B2 (en) | 2007-02-14 | 2015-06-23 | Ziemer Holding Ag | Ophthalmological apparatus for breakdown of eye tissue |
US20100108760A1 (en) | 2008-11-03 | 2010-05-06 | Michael Wayne Eccleston | System and method for tracking distribution of items |
FR2939113B1 (en) | 2008-12-01 | 2012-07-06 | Thomas Petalas | SYSTEM FOR AUTOMATICALLY PLACING LOADS |
BRPI1006813A2 (en) | 2009-01-17 | 2016-04-12 | Boomerang Systems Inc | automatic storage system and transport vehicle |
EP2473415A4 (en) | 2009-08-04 | 2013-04-10 | Maurice Baker Pty Ltd | Mobile pallet with locking mechanism for a container |
US8734078B2 (en) | 2010-08-12 | 2014-05-27 | Bec Companies Inc. | Automated automotive vehicle parking/storage system |
US20120101956A1 (en) | 2010-10-26 | 2012-04-26 | International Business Machines Corporation | Autonomous validation of received shipments |
US20120112904A1 (en) | 2010-11-08 | 2012-05-10 | Hammel Companies, Inc. | System and Method for Tracking, Monitoring and Deriving the Location of Transient Objects by Monitoring the Location of Equipment Used to Move the Objects |
KR20140101117A (en) | 2013-02-08 | 2014-08-19 | 박준용 | Managemant system of parcel service company or its method |
US8965561B2 (en) | 2013-03-15 | 2015-02-24 | Cybernet Systems Corporation | Automated warehousing using robotic forklifts |
GB201316129D0 (en) | 2013-09-10 | 2013-10-23 | Joloda International Ltd | Skate and skate loading system |
CN203520452U (en) | 2013-09-18 | 2014-04-02 | 浙江中烟工业有限责任公司 | Goods allocation digitization warehouse management system |
US8972045B1 (en) | 2013-09-23 | 2015-03-03 | Amazon Technologies, Inc. | Inter-facility transport in inventory management and fulfillment systems |
-
2017
- 2017-10-30 WO PCT/US2017/059080 patent/WO2018081730A1/en unknown
- 2017-10-30 CA CA3041094A patent/CA3041094C/en active Active
- 2017-10-30 MX MX2019004978A patent/MX2019004978A/en unknown
- 2017-10-30 EP EP17804022.6A patent/EP3533006A1/en active Pending
- 2017-10-31 US US15/798,729 patent/US10147059B2/en active Active
-
2018
- 2018-10-24 US US16/169,523 patent/US20190057331A1/en not_active Abandoned
-
2019
- 2019-06-10 US US16/435,997 patent/US20190295010A1/en not_active Abandoned
-
2020
- 2020-01-22 US US16/749,173 patent/US11354605B2/en active Active
-
2022
- 2022-05-03 US US17/735,621 patent/US20220261709A1/en not_active Abandoned
-
2023
- 2023-10-04 US US18/376,651 patent/US20240028980A1/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030050819A1 (en) * | 2001-08-31 | 2003-03-13 | Koenigbauer Mary Jo | Computer-implemented, integrated system and method for managing global logistics |
US20050125247A1 (en) * | 2003-05-13 | 2005-06-09 | Ding Steven A. | Industrial vehicle fleet management system |
US20070279224A1 (en) * | 2006-06-06 | 2007-12-06 | James Peter Branigan | System and Method for Swapping Tag Reads Based on Statistical Analysis of Known Environment |
US20090293756A1 (en) * | 2008-06-03 | 2009-12-03 | Kaci Intermodal Systems, Llc | System, network and method for transporting cargo |
US20100241532A1 (en) * | 2009-03-17 | 2010-09-23 | Paul Biddle | System, method, and computer program product for third-party and fourth-party logistics |
US20120191272A1 (en) * | 2011-01-24 | 2012-07-26 | Sky-Trax, Inc. | Inferential load tracking |
US20120239224A1 (en) * | 2011-03-18 | 2012-09-20 | Mccabe Paul P | Integration of an autonomous industrial vehicle into an asset management system |
US9367827B1 (en) * | 2014-12-15 | 2016-06-14 | Innovative Logistics, Inc. | Cross-dock management system, method and apparatus |
US10147059B2 (en) * | 2016-10-31 | 2018-12-04 | Innovative Logistics, Inc. | System and method for automated cross-dock operations |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20210357995A1 (en) * | 2017-02-27 | 2021-11-18 | Maruichi Warehouse Co., Ltd. | Information processing device |
CN109683504A (en) * | 2017-10-18 | 2019-04-26 | 北京京东尚科信息技术有限公司 | Outbound control method, device, electronic equipment and storage medium |
Also Published As
Publication number | Publication date |
---|---|
CA3041094C (en) | 2021-10-19 |
US10147059B2 (en) | 2018-12-04 |
US11354605B2 (en) | 2022-06-07 |
US20200160236A1 (en) | 2020-05-21 |
US20240028980A1 (en) | 2024-01-25 |
US20180121864A1 (en) | 2018-05-03 |
EP3533006A1 (en) | 2019-09-04 |
WO2018081730A1 (en) | 2018-05-03 |
CA3041094A1 (en) | 2018-05-03 |
US20220261709A1 (en) | 2022-08-18 |
US20190057331A1 (en) | 2019-02-21 |
MX2019004978A (en) | 2019-08-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11354605B2 (en) | System and method for automated cross-dock operations | |
US11934992B2 (en) | Cross-dock management system, method and apparatus | |
AU2020201348B2 (en) | Autonomous condensing of pallets of items in a warehouse | |
US10265871B2 (en) | Collaborative inventory monitoring | |
KR102204950B1 (en) | Optimization of warehouse layout based on customizable goals | |
KR102188458B1 (en) | Autonomous shuffling of pallets of goods in warehouse |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STPP | Information on status: patent application and granting procedure in general |
Free format text: NON FINAL ACTION MAILED |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |