US20170284080A1 - Fold-Out Prefabricated Structure and Method for the Assembly Thereof - Google Patents

Fold-Out Prefabricated Structure and Method for the Assembly Thereof Download PDF

Info

Publication number
US20170284080A1
US20170284080A1 US15/511,010 US201515511010A US2017284080A1 US 20170284080 A1 US20170284080 A1 US 20170284080A1 US 201515511010 A US201515511010 A US 201515511010A US 2017284080 A1 US2017284080 A1 US 2017284080A1
Authority
US
United States
Prior art keywords
pillars
elements
porticos
structure according
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US15/511,010
Inventor
Angel Vidal de la Fuente
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of US20170284080A1 publication Critical patent/US20170284080A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/344Structures characterised by movable, separable, or collapsible parts, e.g. for transport with hinged parts
    • E04B1/3441Structures characterised by movable, separable, or collapsible parts, e.g. for transport with hinged parts with articulated bar-shaped elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/344Structures characterised by movable, separable, or collapsible parts, e.g. for transport with hinged parts
    • E04B1/3442Structures characterised by movable, separable, or collapsible parts, e.g. for transport with hinged parts folding out from a core cell
    • E04B1/3444Structures characterised by movable, separable, or collapsible parts, e.g. for transport with hinged parts folding out from a core cell with only lateral unfolding
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/02Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
    • E04B7/022Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs consisting of a plurality of parallel similar trusses or portal frames

Definitions

  • the present patent application is comprised in the sector of construction and the object thereof is a fold-out prefabricated structure and method for the assembly thereof. Once folded out, the structure acquires a fixed width, determined during the manufacturing phase, and the desired length and shape, to be formed during the folding out phase. It is made up of porticos that are independent from one another, formed by at least two pillars and an upper structure.
  • the parts forming the structure are:
  • a base built in one or several pieces, of materials and shape susceptible to being fixed to the surface, and prepared for being cut or separated into as many portions as there are pillars.
  • Among its functions are that of maintaining the set of the structure attached at its lower part, forcing the pillars to remain erect and attached to same, allowing the entire folded up structure to be stood upright, allowing the pillars or sets of pillars to be moved on portions thereof and allowing all or portions of said base to be fixed to the surface, transmitting the stresses withstood by the pillars.
  • the structure is delivered folded up, taking up a smaller size than what it will take up once it is folded out.
  • a structure having three porticos would take up a total volume of 645.53 cm in length, 200.00 cm in width and 175.00 cm in depth ( FIGS. 2, 3 and 4 ).
  • the maximum weight can withstand significant oscillations due to the diversity of the construction materials and the variability of the dimensions of pillars and truss rafters.
  • a structure having three reinforced concrete porticos has a mass close to nine tons.
  • a heavy duty vehicle would be necessary for moving this structure.
  • the weight in wood or steel, for example, would be drastically less and would make the on-site deliver even easier.
  • the stiff pieces (of steel, wood, ready-mix concrete or other similar materials) must be taken to the site independently and put in place one by one.
  • This mechanism requires the presence of at least two operators on foot and an additional operator for operating the crane, the support of which will be necessary throughout the entire process. All this entails a high factory and site costs.
  • this technique is particularly time-consuming as the dependent fragment hardening periods cannot overlap, and it is particularly material-consuming given the high number of phases, the loss of materials caused by bad weather, the limit to the number of uses of the formworks, the transport requirements given their high number, and taking into account that each concrete-pouring phase furthermore requires a concrete truck and a crane. As a consequence, it also demands a lot of manpower.
  • the method for assembly object of invention enables concentrating resource consumption in the factory and reducing it at the construction site, where it is more expensive.
  • the structure can be moved in a single trip and the need for crane is generally limited to the time required for the initial unloading, since after that activity no piece of the structure has to be lifted again, with the subsequent savings in energy, and enabling assembly by a single person.
  • This invention is characterized by its folding out scalability and flexibility, such that it is possible to benefit from the savings generated in buildings of various shapes, sizes and materials.
  • the invention simplifies the creation of the structure required in the construction and restoration of homes, warehouses, garages, etc., with drastic savings in the purchasing price and in the need for mechanical and human resources.
  • FIGS. 1 to 12 A basic embodiment of a rectangular plan structure, with two rows of three identical porticos, having vertical pillars, two truss rafters per portico, having straight elements with a rectangular section, and folded out by means of auxiliary structures formed by metal bars, depicted in FIGS. 1 to 12 for better understanding thereof, and it will be described in detail below making reference to the attached drawings, in which:
  • FIG. 1 is a schematic plan view of a surface prepared to be used by the structure object of invention, where locations 18 , 19 , 20 , 21 , 22 and 23 correspond with the final position of each of the pillars, whereas the point 24 represents the location prepared for the provisional fixing of the pillar 10 .
  • FIG. 2 is an elevational view of the recently unloaded and still folded up structure, resting on the surface of FIG. 1 .
  • FIG. 5 is a plan view of the piece forming the base depicting the portions where it will be divided throughout the assembly process.
  • FIG. 6 is a profile view of a portico at an intermediate point of the process of it being opened.
  • FIG. 7 is a profile view of a portico once it has been opened.
  • FIG. 8 is a plan view of the structure and the surface once the porticos are finally open.
  • FIG. 9 is an elevational view of the structure and the surface once the porticos are finally open, with the auxiliary structures prepared for moving the second and third porticos.
  • FIG. 10 is an elevational view of the structure and the surface once the movement of the second and third porticos has ended.
  • FIG. 11 is an elevational view of the structure and the surface once the movement of the second and third porticos has ended and the auxiliary structures have been placed for moving the third portico.
  • FIG. 12 is an elevational view of the structure and the surface once the movement of the third portico has ended.
  • FIG. 14 is a profile view of an example of a still folded up structure in which various porticos open out radially from a central pillar, where inner articulations and an upper structure by way of a horizontal beam have been used.
  • FIG. 15 is a profile view of an example of a folded out structure in which various porticos open out radially from a central pillar, where inner articulations and an upper structure by way of a horizontal beam have been used.
  • FIG. 16 is a plan view of an example of a structure in which various porticos open out radially from a central pillar.
  • FIG. 17 is a profile view of an example of a structure in which an “upper structure-pillar” set is coupled to the portico formed by “pillar-upper structure-pillar”, such that the intermediate pillar ( 34 ) is shared by two upper structures.
  • FIG. 18 is a plan view of an example of a structure in which an “upper structure-pillar” set is coupled to the portico formed by “pillar-upper structure-pillar”, such that the intermediate pillar ( 34 ) is shared by two upper structures.
  • FIG. 19 is a schematic profile view of an example of a structure incorporating intermediate elements ( 31 ) for creating additional floors.
  • FIG. 20 is a profile view of an example of a structure in which the upper structure is formed by a number of elements greater than two.
  • FIG. 21 is a profile view of the structure of FIG. 20 , in an intermediate portico opening phase in which the elements of the upper structure that are placed against the pillars have reached their final folding out angle.
  • FIG. 22 is a profile view of the structure of FIG. 21 once the porticos are finally open.
  • FIGS. 2, 3 and 4 The process for folding out the mentioned structure having three porticos ( FIGS. 2, 3 and 4 ), formed by two vertical pillars and two truss rafters, all of them having a rectangular section and being straight, with a base that will be divided by means of cuts, will be described below.
  • first one of the side porticos must be fixed and the rest must move longitudinally.
  • the number of porticos is irrelevant for the assembly technique and mechanism, and porticos can be acquired that are grouped together or separated, whichever is most appropriate in each case, because it is perfectly viable to use several structures for a single project.
  • the most efficient process would begin by fixing one of the central porticos in its final position, followed by the movement of the remaining porticos in opposite directions, depending on the side of the already fixed portico on which they are located, such that movement stress is minimal.
  • the process will begin at one of the ends.
  • the assembly begins with unloading the structure, at which time the pillar 8 must be placed in their final position ( 18 ), where their corresponding portion of the base ( 2 ) will be fixed by means of suitable techniques (welding, screws, bonding, etc.).
  • suitable techniques welding, screws, bonding, etc.
  • the current example requires a provisional fixing between the portion of the base ( 4 ) of the pillar ( 10 ) and the surface in position ( 24 ). This securing confers a static position to the first row of pillars and allows opening the second one to its final position without requiring a crane or heavy machinery.
  • auxiliary structures ( 14 ) must be assembled assuring the relative arrangement between sets of pillars while the opening takes place, and the suitable movement mechanism, for example, winches and cables, towing vehicles, jacks, wheels, etc., must be provided.
  • a longitudinal cut ( 17 ) is made dividing the base into two rows ( FIG. 5 ), and the stiffening elements between both rows ( 29 ) are cut. Only if all these elements are arranged is it possible to open the free row, which will remain erect as a result of the auxiliary structures ( FIG. 6 ), until both the pillar 11 and the articulations of the upper structure ( 25 and 26 ) reach their final position ( FIGS. 7 and 8 ).
  • the truss rafters of the present example are prepared for reaching angles of 30° and 150° with respect to the horizontal.
  • the portion of the base 5 of the pillar 11 will be fixed at point 21 and the portion 4 of the pillar 10 will be released from its provisional securing at 24 .
  • the articulations of all the porticos will also be immobilized either by fixing means for fixing same or by means of attaching the definitive elements of the structure to one another, since they will not require any mobility again.
  • the auxiliary structures ( 14 ) must be assembled between the pillars of the most recently fixed portico and the portico that is going to be moved next ( FIG. 9 ) and eliminating the attachment provided by the stiffening elements of the pillars and the truss rafters ( 29 ), as well as the attachment of the base (cut 15 of FIG. 5 ) of both porticos to proceed to the uncoupling thereof. Therefore, the entire structure not yet fixed (porticos formed by pillars 9 , 10 , 12 and 13 ) still forms a single moving set, unlike the already secured porticos. Movement ( FIG. 10 ) and fixing of the following portico (pillars 9 and 12 , through their respective portions of the base 3 and 6 ) are performed with the movement mechanism.
  • the remaining stiffening elements ( 29 ) In order to move the last of the porticos, the remaining stiffening elements ( 29 ) must be removed, the auxiliary structures must be installed between the last and next to last porticos ( FIG. 11 ), the movement mechanism must be installed, the corresponding cut must be made in the base ( 16 ), and finally, it must be moved to the final position where the portions of the base 4 and 7 of the pillars 10 and 13 ( FIG. 12 ) are fixed.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a fold-out prefabricated construction structure and method for the assembly thereof. The structure, having bays of desired width, length and shape, is made up of porticos formed by pillars and an upper structure (27). The method involves positioning the base (1) on a surface (28) and provisionally fixing at least one portion of said base. This allows opening the porticos with the help of auxiliary structures created for this purpose (14). The elements of the structure are fixed to one another, and to the surface of the portions of the base in their final position. Each of the porticos not yet fixed must be moved to their final position, in a successive manner and separately from the closest fixed portico, together with the rest of still free attached porticos, and suitably fixed to the surface.

Description

  • The present patent application is comprised in the sector of construction and the object thereof is a fold-out prefabricated structure and method for the assembly thereof. Once folded out, the structure acquires a fixed width, determined during the manufacturing phase, and the desired length and shape, to be formed during the folding out phase. It is made up of porticos that are independent from one another, formed by at least two pillars and an upper structure.
  • To correctly fold out and subsequently use the structure there has to be a surface on which this can be done (28).
  • The parts forming the structure are:
  • A base built in one or several pieces, of materials and shape susceptible to being fixed to the surface, and prepared for being cut or separated into as many portions as there are pillars. Among its functions are that of maintaining the set of the structure attached at its lower part, forcing the pillars to remain erect and attached to same, allowing the entire folded up structure to be stood upright, allowing the pillars or sets of pillars to be moved on portions thereof and allowing all or portions of said base to be fixed to the surface, transmitting the stresses withstood by the pillars.
  • The pillars can have the height desired, even being able to go beyond the attachment point with the upper elements, and they are generally vertical, although it is possible to use any other arrangement, and can be of any section (circular, triangular, pentagonal, etc., or variable). The pillars can be different from one another in the same portico and between different porticos.
  • The upper structure can consist of any number of elements, which do not necessarily have to be identical to one another. Their final arrangement can form the desired angle, even being fixed by way of a horizontal beam, which makes it easier to create floor slabs. Furthermore, it is possible to determine whether or not the truss rafters will project out of the structure. This allows using the invention in pre-existing walls. Finally, the upper structures will generally be the same in all the porticos of one and the same structure, but they can have different shapes and compositions. The elements of the upper structure are attached to one another and to the pillars by means of articulations.
  • The structure is delivered folded up, taking up a smaller size than what it will take up once it is folded out.
  • With pillars of 267.00 cm in length and two truss rafters of 448.00 cm, a structure having three porticos would take up a total volume of 645.53 cm in length, 200.00 cm in width and 175.00 cm in depth (FIGS. 2, 3 and 4). The maximum weight can withstand significant oscillations due to the diversity of the construction materials and the variability of the dimensions of pillars and truss rafters. For example, a structure having three reinforced concrete porticos has a mass close to nine tons. A heavy duty vehicle would be necessary for moving this structure. The weight in wood or steel, for example, would be drastically less and would make the on-site deliver even easier.
  • Various techniques today allow making construction structures. The most common techniques involve the assembly of independent prefabricated pieces at their destination or the in situ construction thereof, requiring that workers and heavy machinery be available and travel for days or weeks, particularly if concrete is used. These needs entail higher costs for constructing any type of building and greatly limit any initiatives in this sense.
  • If the use of prefabricated elements is chosen, the stiff pieces (of steel, wood, ready-mix concrete or other similar materials) must be taken to the site independently and put in place one by one. This mechanism requires the presence of at least two operators on foot and an additional operator for operating the crane, the support of which will be necessary throughout the entire process. All this entails a high factory and site costs.
  • When prefabricated elements are not used, the reinforced concrete structures are made directly on site by at least two operators and a crane. To that end, it is necessary to use hand-crafted formworks with boards, props and other components. Due to the intrinsic progressiveness of the concrete hardening process, significant wait times must be accepted before being able to continue with the next element. For the same reason, all the elements withstanding bending (beams, slabs, etc.) cannot be under a load until 28 days after pouring the concrete. Therefore, this technique is particularly time-consuming as the dependent fragment hardening periods cannot overlap, and it is particularly material-consuming given the high number of phases, the loss of materials caused by bad weather, the limit to the number of uses of the formworks, the transport requirements given their high number, and taking into account that each concrete-pouring phase furthermore requires a concrete truck and a crane. As a consequence, it also demands a lot of manpower.
  • Unlike all these situations, the method for assembly object of invention enables concentrating resource consumption in the factory and reducing it at the construction site, where it is more expensive. The structure can be moved in a single trip and the need for crane is generally limited to the time required for the initial unloading, since after that activity no piece of the structure has to be lifted again, with the subsequent savings in energy, and enabling assembly by a single person. This invention is characterized by its folding out scalability and flexibility, such that it is possible to benefit from the savings generated in buildings of various shapes, sizes and materials. In summary, the invention simplifies the creation of the structure required in the construction and restoration of homes, warehouses, garages, etc., with drastic savings in the purchasing price and in the need for mechanical and human resources.
  • BRIEF DESCRIPTION OF FIGURES
  • A basic embodiment of a rectangular plan structure, with two rows of three identical porticos, having vertical pillars, two truss rafters per portico, having straight elements with a rectangular section, and folded out by means of auxiliary structures formed by metal bars, depicted in FIGS. 1 to 12 for better understanding thereof, and it will be described in detail below making reference to the attached drawings, in which:
  • [FIG. 1] is a schematic plan view of a surface prepared to be used by the structure object of invention, where locations 18, 19, 20, 21, 22 and 23 correspond with the final position of each of the pillars, whereas the point 24 represents the location prepared for the provisional fixing of the pillar 10.
  • [FIG. 2] is an elevational view of the recently unloaded and still folded up structure, resting on the surface of FIG. 1.
  • [FIG. 3] is a profile view of the structure in the same state as in FIG. 2.
  • [FIG. 4] is a plan view of the folded up structure.
  • [FIG. 5] is a plan view of the piece forming the base depicting the portions where it will be divided throughout the assembly process.
  • [FIG. 6] is a profile view of a portico at an intermediate point of the process of it being opened.
  • [FIG. 7] is a profile view of a portico once it has been opened.
  • [FIG. 8] is a plan view of the structure and the surface once the porticos are finally open.
  • [FIG. 9] is an elevational view of the structure and the surface once the porticos are finally open, with the auxiliary structures prepared for moving the second and third porticos.
  • [FIG. 10] is an elevational view of the structure and the surface once the movement of the second and third porticos has ended.
  • [FIG. 11] is an elevational view of the structure and the surface once the movement of the second and third porticos has ended and the auxiliary structures have been placed for moving the third portico.
  • [FIG. 12] is an elevational view of the structure and the surface once the movement of the third portico has ended.
  • [FIG. 13] is a profile view of an example of a structure including a truss as reinforcement in the upper structure.
  • [FIG. 14] is a profile view of an example of a still folded up structure in which various porticos open out radially from a central pillar, where inner articulations and an upper structure by way of a horizontal beam have been used.
  • [FIG. 15] is a profile view of an example of a folded out structure in which various porticos open out radially from a central pillar, where inner articulations and an upper structure by way of a horizontal beam have been used.
  • [FIG. 16] is a plan view of an example of a structure in which various porticos open out radially from a central pillar.
  • [FIG. 17] is a profile view of an example of a structure in which an “upper structure-pillar” set is coupled to the portico formed by “pillar-upper structure-pillar”, such that the intermediate pillar (34) is shared by two upper structures.
  • [FIG. 18] is a plan view of an example of a structure in which an “upper structure-pillar” set is coupled to the portico formed by “pillar-upper structure-pillar”, such that the intermediate pillar (34) is shared by two upper structures.
  • [FIG. 19] is a schematic profile view of an example of a structure incorporating intermediate elements (31) for creating additional floors.
  • [FIG. 20] is a profile view of an example of a structure in which the upper structure is formed by a number of elements greater than two.
  • [FIG. 21] is a profile view of the structure of FIG. 20, in an intermediate portico opening phase in which the elements of the upper structure that are placed against the pillars have reached their final folding out angle.
  • [FIG. 22] is a profile view of the structure of FIG. 21 once the porticos are finally open.
  • [FIG. 23] is a profile view of an example of a structure designed with moved articulations in the pillars.
  • DESCRIPTION OF SOME FORM OF CARRYING OUT THE INVENTION
  • The process for folding out the mentioned structure having three porticos (FIGS. 2, 3 and 4), formed by two vertical pillars and two truss rafters, all of them having a rectangular section and being straight, with a base that will be divided by means of cuts, will be described below. To illustrate all possible cases, first one of the side porticos must be fixed and the rest must move longitudinally. However, there is complete flexibility here because the number of porticos is irrelevant for the assembly technique and mechanism, and porticos can be acquired that are grouped together or separated, whichever is most appropriate in each case, because it is perfectly viable to use several structures for a single project.
  • Furthermore, for structures with more than 2 porticos, the most efficient process would begin by fixing one of the central porticos in its final position, followed by the movement of the remaining porticos in opposite directions, depending on the side of the already fixed portico on which they are located, such that movement stress is minimal. However, to avoid redundancies in the description, the process will begin at one of the ends.
  • The assembly begins with unloading the structure, at which time the pillar 8 must be placed in their final position (18), where their corresponding portion of the base (2) will be fixed by means of suitable techniques (welding, screws, bonding, etc.). After securing the first portion of the base, the current example requires a provisional fixing between the portion of the base (4) of the pillar (10) and the surface in position (24). This securing confers a static position to the first row of pillars and allows opening the second one to its final position without requiring a crane or heavy machinery. To that end, one or several auxiliary structures (14) must be assembled assuring the relative arrangement between sets of pillars while the opening takes place, and the suitable movement mechanism, for example, winches and cables, towing vehicles, jacks, wheels, etc., must be provided. When all these elements are in position, a longitudinal cut (17) is made dividing the base into two rows (FIG. 5), and the stiffening elements between both rows (29) are cut. Only if all these elements are arranged is it possible to open the free row, which will remain erect as a result of the auxiliary structures (FIG. 6), until both the pillar 11 and the articulations of the upper structure (25 and 26) reach their final position (FIGS. 7 and 8). The truss rafters of the present example (27) are prepared for reaching angles of 30° and 150° with respect to the horizontal. The portion of the base 5 of the pillar 11 will be fixed at point 21 and the portion 4 of the pillar 10 will be released from its provisional securing at 24. The articulations of all the porticos will also be immobilized either by fixing means for fixing same or by means of attaching the definitive elements of the structure to one another, since they will not require any mobility again.
  • There are a number of solutions for the upper part of the structure. Both the articulations attaching the pillars with the truss rafters and the truss rafters to one another, and the form of attachment of these points, are completely versatile, generating a wide range of possibilities in the finish of both roofs and floor slabs. Furthermore, when the upper part of the structure is made up of more than 2 elements, additional actions must be carried out to open it. Specifically, temporary fixing elements (32) reducing the movements of all those elements to standard protocol must be used. In such case, the porticos are opened in stages and the elements are gradually fixed as they reach the desired position. To complete the folding out, this activity must be performed in a successive manner until all the upper elements are fixed (FIGS. 20, 21 and 22).
  • The activities included in the following paragraph describe in detail the process of moving the porticos and must be performed n−2 times, where n is the number of porticos. This is because all the central porticos (i.e., those that are neither the first nor the last) share a single movement routine. Given that this invention exemplifies a structure having three porticos, the following routine is carried out just once.
  • The auxiliary structures (14) must be assembled between the pillars of the most recently fixed portico and the portico that is going to be moved next (FIG. 9) and eliminating the attachment provided by the stiffening elements of the pillars and the truss rafters (29), as well as the attachment of the base (cut 15 of FIG. 5) of both porticos to proceed to the uncoupling thereof. Therefore, the entire structure not yet fixed (porticos formed by pillars 9, 10, 12 and 13) still forms a single moving set, unlike the already secured porticos. Movement (FIG. 10) and fixing of the following portico ( pillars 9 and 12, through their respective portions of the base 3 and 6) are performed with the movement mechanism. This movement can be done in a single run if is a rectangular plan structure, i.e., if the final position of the porticos is parallel. If the final position of the porticos is not going to be parallel, separate movements for each pillar must be performed.
  • In order to move the last of the porticos, the remaining stiffening elements (29) must be removed, the auxiliary structures must be installed between the last and next to last porticos (FIG. 11), the movement mechanism must be installed, the corresponding cut must be made in the base (16), and finally, it must be moved to the final position where the portions of the base 4 and 7 of the pillars 10 and 13 (FIG. 12) are fixed.
  • Lastly, the auxiliary structures and the movement mechanism are disassembled.

Claims (11)

1. A prefabricated construction structure having any number of porticos that allows obtaining a final structure of various shapes and dimensions, which is delivered folded-up, comprising a base (1) built in one or several pieces, susceptible to being fixed to the surface and prepared for being cut or separated into as many portions as there are pillars, said pillars (8, 9, 10, 11, 12, 13) having any dimensions, shape, section and inclination, attached to the base, which can be different from one another, an upper structure (27) made up of elements of any length, shape and section, which can be different from one another, with finishes that allow fitting with others at the chosen angle, attached to one another and to the pillars by articulations or other moving elements (25, 26), which are delivered folded-up and expanded to their final position throughout the fold-out process, stiffening elements (29) providing strength to the conglomerate and allowing groups of structural elements to be opened and moved as a result of auxiliary structures (14) assuring the relative arrangement between sets of pillars during the required fold-out movements.
2. The prefabricated structure according to claim 1, characterized in that the base and the pillars form a single piece.
3. The prefabricated structure according to claim 1, characterized in that the high part of the pillars and the upper structure incorporate the elements required for configuring a truss (30).
4. The prefabricated structure according to claim 1, characterized in that various porticos open out from a single central pillar (33), having said pillar in common.
5. The prefabricated structure according to claim 1, characterized in that other “upper structure-pillar” sets are coupled to the portico formed by “pillar-upper structure-pillar”, such that the intermediate pillars (34) are shared by two upper structures.
6. The prefabricated structure according to claim 1, characterized in that it incorporates intermediate structural elements (31) that allow creating additional floors.
7. The prefabricated structure according to claim 1, characterized in that the number of elements forming the upper structure is greater than two, where temporary fixing elements (32) are required for the sequential folding out of the elements.
8. The prefabricated structure according to claim 1, characterized in that the articulations are located at intermediate points of the elements of the structure, either the pillars or upper elements, by way of moved articulations (35).
9. A method for forming a structure according to claim 1, consisting of positioning the base (1) on a surface (28), provisionally fixing at least one portion of said base to the surface, opening the porticos by moving the non-fixed pillars (11, 12, 13) using a movement mechanism and one or several auxiliary structures (14) assuring the stability of the structure and the relative arrangement between both sets of pillars, definitively immobilizing the attachment of the upper elements to one another and to the pillars once they are completely opened, fixing the portions of base of the pillars that have acquired their final position on the surface, and for each of the porticos or pillars not yet fixed, in a successive manner, eliminating the stiffening elements (29), attaching it to the adjacent fixed portico, moving it to its final position, using the auxiliary structures, together with the rest of porticos yet to be fixed contiguous to same, if there are any, and fixing it by means of a method suitable for the surface.
10. The construction structure according to claim 1, folded out by means of the method for the assembly thereof according to claim 8.
11. The method for forming the structure according to claim 8, wherein the function of the auxiliary structures (14), of maintaining relative arrangement of the moved pillar, is undertaken by alternative solutions, such solutions being able to include the use of heavy machinery.
US15/511,010 2015-01-20 2015-01-20 Fold-Out Prefabricated Structure and Method for the Assembly Thereof Abandoned US20170284080A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/ES2015/070034 WO2016116638A1 (en) 2015-01-20 2015-01-20 Fold-out prefabricated structure

Publications (1)

Publication Number Publication Date
US20170284080A1 true US20170284080A1 (en) 2017-10-05

Family

ID=56416461

Family Applications (1)

Application Number Title Priority Date Filing Date
US15/511,010 Abandoned US20170284080A1 (en) 2015-01-20 2015-01-20 Fold-Out Prefabricated Structure and Method for the Assembly Thereof

Country Status (6)

Country Link
US (1) US20170284080A1 (en)
EP (1) EP3249126A4 (en)
CN (1) CN107109836A (en)
CA (1) CA2974161A1 (en)
RU (1) RU2017127770A (en)
WO (1) WO2016116638A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220127840A1 (en) * 2019-02-13 2022-04-28 Gruppo Italtelo S.P.A. Extendable structure and relative movement method
US20220228361A1 (en) * 2019-05-15 2022-07-21 Polyform Construction Pty Ltd Polyform Folding Building System
US20220364353A1 (en) * 2021-05-12 2022-11-17 Folding Holdings Llc Frame for sectional foldable prefabricated building
US20230068992A1 (en) * 2021-09-02 2023-03-02 Skidmore Ownings & Merrill Llp Actuated foldable building system module

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
USRE31641E (en) * 1979-12-17 1984-08-07 Nomadic Structures, Inc. Collapsible articulated wall structure
US6499705B1 (en) * 2002-01-04 2002-12-31 Ming-Liang Tsai Multi-purpose supporting structure
US20120180404A1 (en) * 2011-01-13 2012-07-19 Scouten Alan Portable housing system
US8881470B1 (en) * 2013-12-31 2014-11-11 Gary D. Lass Collapsible structure
US9051725B2 (en) * 2013-04-18 2015-06-09 James Bert FARMER Portable building

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR493537A (en) * 1917-08-08 1919-08-12 Des Filatures Corderies Et Tissages D Angers Demountable tent with folding elements
FR2468699B1 (en) * 1979-10-26 1986-02-28 Martin Jean FOLDABLE ELEMENT OF FRAME FOR CONSTRUCTION
US4527362A (en) * 1982-04-30 1985-07-09 Martin Marietta Corporation Deployable truss
JPH0559821A (en) * 1991-08-30 1993-03-09 Taisei Corp Foldable temporary roof
ES2368539B1 (en) * 2008-09-25 2012-09-24 Marco Antonio Luengo Fernández QUICK MOUNTED METAL PORTIC FOR QUICK ASSEMBLY, AND PROCEDURE FOR PERFORMING SUCH ASSEMBLY.
CN201507130U (en) * 2009-08-20 2010-06-16 张华平 Mobile stage bracket
JP5615568B2 (en) * 2010-02-26 2014-10-29 桑田テント株式会社 Width-variable telescopic all-weather membrane roof
AU2011226892B2 (en) * 2011-09-27 2014-03-27 Lift Link Housing Pty Ltd Rapid Deployment Modular Structures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
USRE31641E (en) * 1979-12-17 1984-08-07 Nomadic Structures, Inc. Collapsible articulated wall structure
US6499705B1 (en) * 2002-01-04 2002-12-31 Ming-Liang Tsai Multi-purpose supporting structure
US20120180404A1 (en) * 2011-01-13 2012-07-19 Scouten Alan Portable housing system
US9051725B2 (en) * 2013-04-18 2015-06-09 James Bert FARMER Portable building
US8881470B1 (en) * 2013-12-31 2014-11-11 Gary D. Lass Collapsible structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220127840A1 (en) * 2019-02-13 2022-04-28 Gruppo Italtelo S.P.A. Extendable structure and relative movement method
US11927008B2 (en) * 2019-02-13 2024-03-12 Gruppo Italtelo S.P.A. Extendable structure and relative movement method
US20220228361A1 (en) * 2019-05-15 2022-07-21 Polyform Construction Pty Ltd Polyform Folding Building System
US11976459B2 (en) * 2019-05-15 2024-05-07 Polyform Construction Pty Ltd Polyform folding building system
US20220364353A1 (en) * 2021-05-12 2022-11-17 Folding Holdings Llc Frame for sectional foldable prefabricated building
US11536018B2 (en) * 2021-05-12 2022-12-27 Folding Holdings Llc Frame for sectional foldable prefabricated building
US20230068992A1 (en) * 2021-09-02 2023-03-02 Skidmore Ownings & Merrill Llp Actuated foldable building system module

Also Published As

Publication number Publication date
RU2017127770A3 (en) 2019-02-04
EP3249126A1 (en) 2017-11-29
CA2974161A1 (en) 2016-07-28
CN107109836A (en) 2017-08-29
RU2017127770A (en) 2019-02-04
WO2016116638A1 (en) 2016-07-28
EP3249126A4 (en) 2018-08-01

Similar Documents

Publication Publication Date Title
US20170284080A1 (en) Fold-Out Prefabricated Structure and Method for the Assembly Thereof
JP4843709B2 (en) Construction method of large space building
MXPA04009388A (en) Tilt-up concrete wall panel form and method of fabricating same.
WO2012101088A1 (en) Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower
TWI662172B (en) Construction method for a building
JP2018520285A (en) Prefabricated column and beam type construction
JP6339923B2 (en) How to build a building frame
CN205153530U (en) Structure is assembled to integral template of reinforced concrete floor
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
US3851024A (en) Reinforced concrete construction method
JP5001897B2 (en) Building construction method
JP3112312U (en) Steel prefab building
EP2586924B1 (en) Self-supporting steel truss for mixed steel-concrete truss systems
US8615967B1 (en) Construction element for erecting structure, and method of erecting structure with use thereof
CN113047627A (en) Finished steel reinforcement cage grading assembly method suitable for bearing metal column template
KR101748770B1 (en) Complex structure and its construction method
JP2007154565A (en) Joint structure and construction method of column and beam-less slab
JP2020002715A (en) Built-up structure, assembly method of built-up structure, and structure
KR20200113901A (en) Method for constructing flat slab structure with drop panel
JP5248784B2 (en) Column and beam joint structure
KR101240376B1 (en) The frame assembly of steel house
JP2000192664A (en) Method for construction of building
JP2017115495A (en) Construction method
CN110130522A (en) Grillage unifies lining structure and production method
JP2010144388A (en) Method for constructing skeleton of steel-reinforced concrete structure

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION