US20170067313A1 - Straddle tool with disconnect between seals - Google Patents
Straddle tool with disconnect between seals Download PDFInfo
- Publication number
- US20170067313A1 US20170067313A1 US15/115,589 US201415115589A US2017067313A1 US 20170067313 A1 US20170067313 A1 US 20170067313A1 US 201415115589 A US201415115589 A US 201415115589A US 2017067313 A1 US2017067313 A1 US 2017067313A1
- Authority
- US
- United States
- Prior art keywords
- disconnector
- assembly
- cups
- borehole assembly
- aperture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 239000004568 cement Substances 0.000 claims abstract description 48
- 238000005406 washing Methods 0.000 claims abstract description 22
- 238000000034 method Methods 0.000 claims abstract description 16
- 239000012530 fluid Substances 0.000 claims description 15
- 238000005086 pumping Methods 0.000 claims description 7
- 206010016256 fatigue Diseases 0.000 claims description 2
- 238000010304 firing Methods 0.000 claims description 2
- 239000003208 petroleum Substances 0.000 claims description 2
- 238000005553 drilling Methods 0.000 claims 1
- 230000007246 mechanism Effects 0.000 claims 1
- 230000004888 barrier function Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000003566 sealing material Substances 0.000 description 2
- 238000007664 blowing Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/12—Packers; Plugs
- E21B33/124—Units with longitudinally-spaced plugs for isolating the intermediate space
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
- E21B33/134—Bridging plugs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
- E21B33/14—Methods or devices for cementing, for plugging holes, crevices or the like for cementing casings into boreholes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B34/00—Valve arrangements for boreholes or wells
- E21B34/06—Valve arrangements for boreholes or wells in wells
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B37/00—Methods or apparatus for cleaning boreholes or wells
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/11—Perforators; Permeators
- E21B43/116—Gun or shaped-charge perforators
-
- E21B2034/002—
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B2200/00—Special features related to earth drilling for obtaining oil, gas or water
- E21B2200/04—Ball valves
Definitions
- the field of the invention is methods for plugging and abandoning wells and more particularly methods that allow multiple operations in a single trip including among other steps running and setting a bridge plug, perforation, washing the perforations, delivering cement under pressure into the perforations and pulling the bottom hole assembly from the location without swabbing the well.
- a bottom hole assembly enables a one trip procedure to set a bridge plug and release from that bridge plug with the BHA.
- a perforating gun is fired and a straddle tool above the gun in repositioned to wash the perforations as the opposed packer cups are moved along the perforations.
- a dropped ball closes a circulation port above the upper packer cups and the ball seat is blown out.
- a disconnect releases the lower part of the straddle tool with the lower packer cups that are uphole oriented.
- Cement can now be delivered past the upper packer cups and pressurized to squeeze the cement into the perforations using the upper cups to hold the pressure.
- Another ported sub above the upper cups has a port opened to prevent swabbing as the BHA is removed.
- the invention is a drill pipe string ( 11 )-borne borehole assembly ( 10 ) comprising a washing tool assembly ( 18 ), comprising:
- FIG. 1 is the run in position of the BHA of the invention
- FIG. 2 is the BHA of FIG. 1 in the position having set the plug, released the plug, perforated, washed behind casing and circulated out debris, split the wash tool and started conducting delivery of cement.
- FIG. 3 illustrates a section of the BHA of the invention.
- the BHA 10 has a bridge plug 12 and an associated setting device 14 located above.
- the setting device 14 is preferably pressure operated against a seated ball (not shown) but other types of devices can be used without departing from the invention.
- a perforating gun 16 is mounted above the actuator followed by a wash tool assembly 18 that preferably has a lower ported sub 20 with ports 22 a pair of lower packer cups 24 and 26 followed by a ported body 28 with fluid outlets 30 for washing the perforations as will be explained below.
- a disconnect 32 is located immediately below the upper cups 34 and 36 which are both looking downhole. Cups 24 and 26 are looking uphole.
- Upper ported sub 38 has port openings 40 There is a flow passage 42 that runs between ports 22 and 40 .
- Ports 40 can be selectively closed with an internal sliding sleeve associated with a ball seat that can shift the sleeve before the ball seal gets blown out for the purposes of delivering the cement or other sealing material as will be explained below.
- This internal assembly is not shown but it is of a type well known in the art.
- another ported sub 44 that has a selectively opened port or ports 46 to allow circulating out of excess cement and to prevent well swabbing when pulling out of the hole by allowing fluid to bypass cups 34 and 36 on the trip out of the hole with the BHA 10 through now opened ports 46 .
- the one trip method works by virtue of running in the BHA 10 into a cased ( 11 ) hole, for example.
- the bridge plug 12 and its plug actuator 14 are placed far enough below the perforations to be made by the gun 16 so that when the gun 16 later is dropped, the gun 16 will be far enough below the perforations formed so as to not interfere with the step of washing through the perforations that comes later.
- the plug actuator 14 When the bridge plug 12 , which is of a type known in the art, is properly positioned the plug actuator 14 is energized, preferably with pressure, and the actuation of the plug also causes preferably a second disconnector ( 13 ) to release the actuator 14 from the gun 16 so that the BHA 10 can be repositioned to properly position the perforating gun 16 to one or more positions for conducting the perforation.
- the wash tool assembly is then positioned either near the top or near the bottom of the section of the casing wherin perforations have just been made by the gun 16 , and the fluid from the surface is pumped through ports 30 that are between cups 26 and 34 such that pressure driven fluid at high velocity can be flushed out through the perforations to clean them and the annulus by removing debris from them with the fluid going into the perforations and coming out in the casing main bore either below cup 24 or above cup 36 .
- the fluid that comes out below cup 24 may then enter ports 22 and pass up through passage 42 on the way to communicating with ports 40 that are above cup 36 .
- main bore passage ( 51 ) ends at ports 30 that before disconnection at disconnector ( 32 ) allows surface pumping to reach ports 30 for the washing procedure that preferably takes place as the BHA 10 moving axially in the borehole along the perforations.
- direction of the washing tool assembly ( 18 ) can be top down or bottom up or any other pattern as long as the entire span of perforations gets exposed to the fluid jet stream that comes out of the ports 30 .
- the next big step is to pump cement or some other seal material.
- the ports 40 need to be closed and a large passage ( 54 ) needs to be opened for the pumped cement at a location where the pumped cement can be pressurized into the perforations after delivery.
- the internal sleeve in sub 40 that is shifted by a ball landing on a seat where the seat gets blown out after shifting is actuated with pressure on the seated ball.
- FIG. 2 shows the disconnector ( 32 ) apart so that the guns 16 and lower cups 24 and 26 as well as the body of the tool 18 with the lower part of the disconnector 32 are dropped downhole onto the plug actuator 14 .
- the perforation guns 16 were earlier released from the plug actuator 14 and raised before they got fired. Now with the disconnector ( 32 ) split, the guns 16 fall down to the actuator 14 . The weight of the gun will contribute to pulls down the lower swab cups 24 , 26 ).
- the ports 40 are closed with the shifting of the internal sleeve and the blowing out of the ball seat with the ball, shown schematically in FIG. 2 as 48 .
- the cement or other sealing material represented by arrow 50 can be pumped out through full-bore aperture ( 54 ) and the cement will be forced into the perforations 52 .
- the lower cups 24 and 26 although earlier dropped still can act to stop the cement that falls down to fill the borehole. Alternatively the cement can go down to the bridge plug 12 .
- the cups 34 or 36 can offer cement retention to pressures of about 5000 PSI to aid in forcing the cement represented by arrow 50 into the perforations.
- the closing of ports 40 forces the pressurized cement below the cups 34 and 36 .
- the cement in the borehole can be drilled out in a separate trip and a cement bond log can be run to determine the integrity of the cement in the perforations 52 .
- the tool 18 is moved as the cement is pumped out through the full-bore aperture ( 54 ) to push the cement into the entire interval.
- the bridge plug 12 is set far enough below the perforation so that when the disconnect 32 separates that portion of the BHA 10 that drops is still laying well below the perforations 52 so as to not interfere with subsequent cementing or later production from those perforations if they are to be reopened for any reason.
- the upper cups 34 and 36 still function as a pressure retainer as does lower cup 26 backed up with cup 24 .
- the tool 18 is unique in that it serves multiple function of jetting the perforations clean through ports 30 at high fluid velocities but is then reconfigured by coming apart at the disconnect ( 32 ) between opposed cups in such a way as to open the aperture ( 54 ) with a bigger flow channel ( 51 ) for the cement to shorten the cementing time and the pumping power required to deliver the cement.
- This tool 18 also has a bypass from above cup 36 at ports 40 through to below cup 24 at ports 22 . This bypass is independent of the passage that directs wash fluid to ports 30 when tool 18 is intact and allows large bore flow of cement out lower end aperture ( 54 ) after the disconnect 32 is operated.
- packer cups are discussed as the seals other types of seals are envisioned such as inflatable or mechanically or hydraulically set resettable packers, for example.
- An advantage of the packer cups is that even when released they have a possibility to hold cement pressure and even if the lower cups 24 and 26 do not hold there is still the bridge plug ( 12 ) as a backup.
- the tool 18 in the background art is illustrated in a plug and abandon method, the tool 18 has a new application wherein different flow regimes are needed for different functions at different times while saving a trip out of the hole to accomplish both functions.
- a part of the well is isolated with a packer or bridge plug ( 12 ).
- the perforations are formed and then cleaned with a wash tool ( 18 ) that flushes fluid out through the perforations between spaced barriers, the lower and upper swab cups ( 24 , 26 , 34 , 36 ) as the assembly ( 18 ) is moved to allow washing through all the perforations in a desired direction while providing a bypass path around the spaced isolators for return fluid to the surface around the tool interval between the spaced seals.
- the bypass ( 42 ) upper port ( 40 ) is then closed and the washing tool assembly ( 18 ) is split at the disconnector ( 32 ) between the seals to open a large flow passage ( 54 ) for the subsequent pumping out of cement with any potential bypass paths ( 40 ) around the top seals that remain with the BHA closed off
- the cement is squeezed out and through the perforations using the upper seals ( 34 , 36 ) still with the BHA to retain pressure up to about 5000 PSI to ensure good cement penetration into the perforations.
- the lower seals even though dropped by the time cement is pumped, may still hold pressure but if they don't, the bridge plug is there for that purpose.
- the pump out sub is then activated and after picking up the excess cement can be circulated out and swabbing of the well is prevented because the open port on top of the upper seal can be a bypass through the upper packer cups because the path is open to lower end 54 .
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
A bottom hole assembly (BHA) enables a one trip procedure to set a bridge plug and release from that bridge plug with the BHA. A perforating gun is fired and a straddle tool above the gun in repositioned to wash the perforations as the opposed packer cups are moved along the perforations. At the end of the washing step a dropped ball closes a circulation port above the upper packer cups and the ball seat is blown out. A disconnect releases the lower part of the straddle tool with the lower packer cups that are uphole oriented. Cement can now be delivered past the upper packer cups and pressurized to squeeze the cement into the perforations using the upper cups to hold the pressure. Another ported sub above the upper cups has a port opened to prevent swabbing as the BHA is removed.
Description
- The field of the invention is methods for plugging and abandoning wells and more particularly methods that allow multiple operations in a single trip including among other steps running and setting a bridge plug, perforation, washing the perforations, delivering cement under pressure into the perforations and pulling the bottom hole assembly from the location without swabbing the well.
- In many instances where a well has to be plugged and abandoned a series of steps are taken to build what amounts to a cement plug but the procedure has in the past been done in a series of discrete steps. One way was to run a perforating gun below a packer and fire the gun and inject cement into the newly created perforations as shown in U.S. Pat. No. 5,372,298. Pressure set washing tools for perforations are shown in U.S. Pat. No. 4,279,306. Systems that run a perforating gun between spaced plugs and release the lower plug to perforate and then set the upper plug to pump cement between the plugs is shown in GB 2414492 A1.
- The plugging and abandonment requirements have changed over time and currently the basic steps are to set a bridge plug to act as a lower cement retainer and then perforate the cased hole. When perforating is complete the perforations have to be cleaned before the cement is delivered. The excess cement needs to be circulated out and it is preferred that the cement is squeezed into the perforations to anchor the plug that extends into the main bore. The perforating gun can either be dropped or retrieved before cementing. The bottom hole assembly used in the cement delivery then needs to be pulled out of the hole. While equipment exists to accomplish many of these tasks individually the use of discrete equipment for specific functions to be performed in a precise order has necessitated the use of multiple trips. Depending on the well depth and surface location these multiple trips necessitated additional rig time that as some locations can run up to hundreds of thousands of US dollars a day. Accordingly, there is a need for devices that facilitate moving from one procedure to the next in the same trip to save rig time and completion costs. Those skilled in the art will better appreciate the various aspects of the invention with regard to the equipment and methods that allow an array of completion procedures to be conducted in one trip from a review of the detailed description of the preferred embodiment and the associated figures while appreciating that the full scope of the invention is to be determined from the appended claims.
- A bottom hole assembly (BHA) enables a one trip procedure to set a bridge plug and release from that bridge plug with the BHA. A perforating gun is fired and a straddle tool above the gun in repositioned to wash the perforations as the opposed packer cups are moved along the perforations. At the end of the washing step a dropped ball closes a circulation port above the upper packer cups and the ball seat is blown out. A disconnect releases the lower part of the straddle tool with the lower packer cups that are uphole oriented. Cement can now be delivered past the upper packer cups and pressurized to squeeze the cement into the perforations using the upper cups to hold the pressure. Another ported sub above the upper cups has a port opened to prevent swabbing as the BHA is removed.
- The invention is a drill pipe string (11)-borne borehole assembly (10) comprising a washing tool assembly (18), comprising:
-
- a main body (28) having an axial main bore passage (51) with one or more laterally directed perforation wash ports (30), provided with
- one or more lower swab cups (24, 26) below and one or more upper swab cups (34, 36) above said main body (28),
- a lower ported sub (20) having at least one port (22) below said lower swab cups (24, 26) and a bypass passage (42) to
- an upper ported sub (38) with at least one port (40) above said upper swab cups (34, 36),
- characterized by
- an actuated valve (381, 382) arranged for closing said one or more upper port (40);
a disconnector (32) for said main body (28) including said main bore passage (51) for forming a wide aperture (54) at a remaining lower end of said disconnected main bore passage (51) for pumping out cement.
The invention is also a method for plugging a cased petroleum well comprising the steps of:
- a) assembling on a drill pipe string (11) a borehole assembly (BHA) (10) comprising
a bridge plug (12) on a plug setting tool (14) arranged below perforation guns (16) further arranged below a wash tool assembly (18) with a main bore (51) and with upper swab cups (34, 36) and lower swab cups (24, 26) which are bypass ported by upper ports (38) via a passage (42) to lower ports (22), and an intermediate ported body (28) with wash ports (30) arranged for washing through perforated casing, - b) running in said BHA (10) until said bridge plug (12) and said perforation guns (16) are sufficiently below a zone in the casing to be perforated,
- c) setting and releasing said bridge plug (12),
- d) positioning and firing said perforating guns (16) perforating said zone of said casing,
- e) positioning said wash tool assembly (18, 28, 30) and washing behind said now perforated casing, and circulating out washed-out debris,
characterized by - f) closing upper ports (40) in upper bypass port (38),
- g) using a disconnector (32) arranged below said upper swab cups (34, 36) and said upper ports (40, 38), of said wash tool assembly (18), thereby disconnecting and releasing a lower half of said wash tool assembly (18) with said perforating guns (16), so forming a main bore (51) aperture (54) at or below an upper half of said disconnector (32), and letting them drop,
- h) pumping down cement via said main bore aperture (54), cementing from a lower portion of said perforated range and continuing upwardly until said perforated range is cemented.
Further advantageous features are defined in the attached dependent claims. -
FIG. 1 is the run in position of the BHA of the invention; -
FIG. 2 is the BHA ofFIG. 1 in the position having set the plug, released the plug, perforated, washed behind casing and circulated out debris, split the wash tool and started conducting delivery of cement. -
FIG. 3 illustrates a section of the BHA of the invention. - Referring to
FIG. 1 , the BHA 10 has abridge plug 12 and an associatedsetting device 14 located above. Thesetting device 14 is preferably pressure operated against a seated ball (not shown) but other types of devices can be used without departing from the invention. Aperforating gun 16 is mounted above the actuator followed by awash tool assembly 18 that preferably has a lower portedsub 20 with ports 22 a pair oflower packer cups 24 and 26 followed by a portedbody 28 withfluid outlets 30 for washing the perforations as will be explained below. Adisconnect 32 is located immediately below theupper cups Cups 24 and 26 are looking uphole. Upper portedsub 38 has port openings 40 There is aflow passage 42 that runs betweenports 22 and 40. Ports 40 can be selectively closed with an internal sliding sleeve associated with a ball seat that can shift the sleeve before the ball seal gets blown out for the purposes of delivering the cement or other sealing material as will be explained below. This internal assembly is not shown but it is of a type well known in the art. At the top of the BHA is another portedsub 44 that has a selectively opened port orports 46 to allow circulating out of excess cement and to prevent well swabbing when pulling out of the hole by allowing fluid to bypasscups ports 46. - The one trip method works by virtue of running in the BHA 10 into a cased (11) hole, for example. The
bridge plug 12 and itsplug actuator 14 are placed far enough below the perforations to be made by thegun 16 so that when thegun 16 later is dropped, thegun 16 will be far enough below the perforations formed so as to not interfere with the step of washing through the perforations that comes later. When the bridge plug 12, which is of a type known in the art, is properly positioned theplug actuator 14 is energized, preferably with pressure, and the actuation of the plug also causes preferably a second disconnector (13) to release theactuator 14 from thegun 16 so that theBHA 10 can be repositioned to properly position the perforatinggun 16 to one or more positions for conducting the perforation. When thegun 16 is properly positioned and set off to create the perforations the wash tool assembly is then positioned either near the top or near the bottom of the section of the casing wherin perforations have just been made by thegun 16, and the fluid from the surface is pumped throughports 30 that are betweencups cup 36. The fluid that comes out below cup 24 may then enterports 22 and pass up throughpassage 42 on the way to communicating with ports 40 that are abovecup 36. It should be noted that the main bore passage (51) ends atports 30 that before disconnection at disconnector (32) allows surface pumping to reachports 30 for the washing procedure that preferably takes place as theBHA 10 moving axially in the borehole along the perforations. Again the direction of the washing tool assembly (18) can be top down or bottom up or any other pattern as long as the entire span of perforations gets exposed to the fluid jet stream that comes out of theports 30. - At the conclusion of the washing of the perforation that is determined by a number of factors such as how many passes were made with the
wash tool assembly 18, or the nature of the fluid that is returning, for example, the next big step is to pump cement or some other seal material. In order to do that two things occur. The ports 40 need to be closed and a large passage (54) needs to be opened for the pumped cement at a location where the pumped cement can be pressurized into the perforations after delivery. To do this the internal sleeve in sub 40 that is shifted by a ball landing on a seat where the seat gets blown out after shifting is actuated with pressure on the seated ball. The ports 40 are then closed and the passage for the cement is back to full bore (51) as the ball and seat have been blown out. Prior to the closing of ports 40 thedisconnector 32 is actuated with internal pressure on another barrier that lands on a seat neardisconnector 32. Thus, the order of operations is to part thedisconnect 32 at a location between thecups perforation wash tool 18 is open at aperture (54) through the now open upper half ofdisconnector 32, and thesmaller ports 30 that directed the fluid jetting for cleaning the perforations do not have to conduct the cement or other seal material.FIG. 2 shows the disconnector (32) apart so that theguns 16 andlower cups 24 and 26 as well as the body of thetool 18 with the lower part of thedisconnector 32 are dropped downhole onto theplug actuator 14. It should be mentioned again here that theperforation guns 16 were earlier released from theplug actuator 14 and raised before they got fired. Now with the disconnector (32) split, theguns 16 fall down to theactuator 14. The weight of the gun will contribute to pulls down the lower swab cups 24, 26). - Once the
FIG. 2 position is obtained then the ports 40 are closed with the shifting of the internal sleeve and the blowing out of the ball seat with the ball, shown schematically inFIG. 2 as 48. Now the cement or other sealing material represented by arrow 50 can be pumped out through full-bore aperture (54) and the cement will be forced into the perforations 52. The lower cups 24 and 26, although earlier dropped still can act to stop the cement that falls down to fill the borehole. Alternatively the cement can go down to thebridge plug 12. Thecups cups - When the requisite volume of cement has been pumped or the pressure builds to a predetermined point indicating the perforations are full as is the bore the next step is to open
ports 46 on pump outsub 44 so that excess cement can be circulated out. The opening ofports 46 also prevents well swabbing as flow fromabove cup 36 can get out belowcup 34 through open end 52. - Optionally, at a later time if there is a desire to reopen the well, the cement in the borehole can be drilled out in a separate trip and a cement bond log can be run to determine the integrity of the cement in the perforations 52.
- The
tool 18 is moved as the cement is pumped out through the full-bore aperture (54) to push the cement into the entire interval. Thebridge plug 12 is set far enough below the perforation so that when thedisconnect 32 separates that portion of theBHA 10 that drops is still laying well below the perforations 52 so as to not interfere with subsequent cementing or later production from those perforations if they are to be reopened for any reason. Despite the separation between thecups disconnect 32 is operated theupper cups lower cup 26 backed up with cup 24. Thetool 18 is unique in that it serves multiple function of jetting the perforations clean throughports 30 at high fluid velocities but is then reconfigured by coming apart at the disconnect (32) between opposed cups in such a way as to open the aperture (54) with a bigger flow channel (51) for the cement to shorten the cementing time and the pumping power required to deliver the cement. Thistool 18 also has a bypass fromabove cup 36 at ports 40 through to below cup 24 atports 22. This bypass is independent of the passage that directs wash fluid toports 30 whentool 18 is intact and allows large bore flow of cement out lower end aperture (54) after thedisconnect 32 is operated. - While packer cups are discussed as the seals other types of seals are envisioned such as inflatable or mechanically or hydraulically set resettable packers, for example. An advantage of the packer cups is that even when released they have a possibility to hold cement pressure and even if the
lower cups 24 and 26 do not hold there is still the bridge plug (12) as a backup. While thetool 18 in the background art is illustrated in a plug and abandon method, thetool 18 has a new application wherein different flow regimes are needed for different functions at different times while saving a trip out of the hole to accomplish both functions. - Those skilled in the art will appreciate that the present one trip method is illustrated where a part of the well is isolated with a packer or bridge plug (12). The perforations are formed and then cleaned with a wash tool (18) that flushes fluid out through the perforations between spaced barriers, the lower and upper swab cups (24, 26, 34, 36) as the assembly (18) is moved to allow washing through all the perforations in a desired direction while providing a bypass path around the spaced isolators for return fluid to the surface around the tool interval between the spaced seals. The bypass (42) upper port (40) is then closed and the washing tool assembly (18) is split at the disconnector (32) between the seals to open a large flow passage (54) for the subsequent pumping out of cement with any potential bypass paths (40) around the top seals that remain with the BHA closed off The cement is squeezed out and through the perforations using the upper seals (34, 36) still with the BHA to retain pressure up to about 5000 PSI to ensure good cement penetration into the perforations. The lower seals even though dropped by the time cement is pumped, may still hold pressure but if they don't, the bridge plug is there for that purpose. The pump out sub is then activated and after picking up the excess cement can be circulated out and swabbing of the well is prevented because the open port on top of the upper seal can be a bypass through the upper packer cups because the path is open to
lower end 54.
Claims (20)
1. A drill pipe string borne borehole assembly comprising a washing tool assembly, comprising:
a main body having an axial main bore passage with one or more laterally directed perforation wash ports, provided with one or more lower swab cups below and one or more upper swab cups above said main body;
a lower ported sub having at least one port below said lower swab cups and a bypass passage to an upper ported sub with at least one port above said upper swab cups,
an actuated valve arranged for closing said one or more upper port; and
a disconnector for said main body including said main bore passage for forming a wide aperture at a remaining lower end of said disconnected main bore passage for pumping out cement.
2. The borehole assembly according to claim 1 , further comprising a perforation gun arranged below said washing tool assembly.
3. The borehole assembly of claim 2 , comprising below said perforation gun a plug actuator arranged for setting a bridge plug in said casing, and a second disconnector arranged between said perforation gun and said plug.
4. The borehole assembly of claim 3 , said second disconnector arranged between said perforation gun and said plug actuator.
5. The borehole assembly of claim 1 , wherein said aperture is larger than said washing port.
6. The borehole assembly of claim 1 , wherein said disconnector is ball or pressure operated.
7. The borehole assembly of claim 1 , wherein said upper and lower swab cups are opposed in facing mirror image.
8. The borehole assembly of claim 1 , wherein said disconnector is arranged for releasing a portion of said body that includes said wash port and said lower swab cups to expose said aperture end of said main bore.
9. The borehole assembly of claim 8 , wherein said lower swab cups sealingly engage the casing after said disconnector has released to retain pressure against fluid delivered through said exposed aperture of said passage.
10. The borehole assembly of claim 1 , wherein said upper swab cups continue to engage the casing after said disconnector has released to retain pressure against fluid delivered through said exposed aperture of said passage.
11. A method for plugging a cased petroleum well comprising the steps of:
a) assembling on a drill pipe string a borehole assembly comprising a bridge plug on a plug setting tool arranged below perforation guns further arranged below a wash tool assembly with a main bore and with upper swab cups and lower swab cups which are bypass ported by upper ports via a passage to lower ports, and an intermediate ported body with wash ports arranged for washing through perforated casing;
b) running in said BHA until said bridge plug and said perforation guns are sufficiently below a zone in the casing to be perforated, perforated;
c) setting and releasing said bridge plug;
d) positioning and firing said perforating guns perforating said zone of said casing;
e) positioning said wash tool assembly and washing behind said now perforated casing, and circulating out washed-out debris;
f) closing upper ports in upper bypass port;
g) using a disconnector arranged below said upper swab cups and said upper ports, of said wash tool assembly, thereby disconnecting and releasing a lower half of said wash tool assembly with said perforating guns, so forming a main bore aperture at or below an upper half of said disconnector, and letting them drop; and
h) pumping down cement via said main bore aperture, cementing from a lower portion of said perforated range and continuing upwardly until said perforated range is cemented.
12. The method of claim 11 , controlling one or more of said operations using pumped ball and seat release mechanisms and releasing said seats using pressure on shear pins of said seats.
13. The method of claim 12 , drilling through said cemented interval of said perforated casing and running a test log to verify the cementing, and cementing it.
14. The borehole assembly of claim 2 , wherein said aperture is larger than said washing port.
15. The borehole assembly of claim 3 , wherein said aperture is larger than said washing port.
16. The borehole assembly of claim 4 , wherein said aperture is larger than said washing port.
17. The borehole assembly of claim 2 , wherein said disconnector is ball or pressure operated.
18. The borehole assembly of claim 3 , wherein said disconnector is ball or pressure operated.
19. The borehole assembly of claim 4 , wherein said disconnector is ball or pressure operated.
20. The borehole assembly of claim 5 , wherein said disconnector is ball or pressure operated.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/NO2014/000010 WO2015115905A1 (en) | 2014-01-31 | 2014-01-31 | Straddle tool with disconnect between seals |
Publications (1)
Publication Number | Publication Date |
---|---|
US20170067313A1 true US20170067313A1 (en) | 2017-03-09 |
Family
ID=50179905
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US15/115,589 Abandoned US20170067313A1 (en) | 2014-01-31 | 2014-01-31 | Straddle tool with disconnect between seals |
Country Status (3)
Country | Link |
---|---|
US (1) | US20170067313A1 (en) |
EP (1) | EP3099891A1 (en) |
WO (1) | WO2015115905A1 (en) |
Cited By (29)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160138370A1 (en) * | 2014-11-18 | 2016-05-19 | Baker Hughes Incorporated | Mechanical diverter |
US20200056446A1 (en) * | 2018-08-14 | 2020-02-20 | Saudi Arabian Oil Company | Tandem Cement Retainer and Bridge Plug |
WO2020081236A1 (en) * | 2018-10-18 | 2020-04-23 | Geodynamics, Inc. | Pulse based perf and wash system and method |
CN112177561A (en) * | 2019-07-03 | 2021-01-05 | 中国石油化工股份有限公司 | Bridge plug feeder, cementing plug pipe column and cementing plug process |
US11041352B2 (en) * | 2015-05-21 | 2021-06-22 | Thru Tubing Solutions, Inc. | Advancement of a tubular string into a wellbore |
US11136849B2 (en) | 2019-11-05 | 2021-10-05 | Saudi Arabian Oil Company | Dual string fluid management devices for oil and gas applications |
US11156052B2 (en) | 2019-12-30 | 2021-10-26 | Saudi Arabian Oil Company | Wellbore tool assembly to open collapsed tubing |
US11199064B2 (en) | 2018-10-31 | 2021-12-14 | Halliburton Energy Services, Inc. | Integrated debris catcher and plug system |
US11230904B2 (en) | 2019-11-11 | 2022-01-25 | Saudi Arabian Oil Company | Setting and unsetting a production packer |
US11253819B2 (en) | 2020-05-14 | 2022-02-22 | Saudi Arabian Oil Company | Production of thin film composite hollow fiber membranes |
US11260351B2 (en) | 2020-02-14 | 2022-03-01 | Saudi Arabian Oil Company | Thin film composite hollow fiber membranes fabrication systems |
US11274515B2 (en) * | 2016-11-07 | 2022-03-15 | Equinor Energy As | Method of plugging and pressure testing a well |
US11280155B2 (en) * | 2019-03-13 | 2022-03-22 | Halliburton Energy Services, Inc. | Single trip wellbore cleaning and sealing system and method |
US11448026B1 (en) | 2021-05-03 | 2022-09-20 | Saudi Arabian Oil Company | Cable head for a wireline tool |
US20220307345A1 (en) * | 2021-03-29 | 2022-09-29 | Conocophillips Company | Method and apparatus for use in plug and abandon operations |
US20220381109A1 (en) * | 2019-11-12 | 2022-12-01 | Schlumberger Technology Corporation | Stage cementing collar with cup tool |
US11549329B2 (en) | 2020-12-22 | 2023-01-10 | Saudi Arabian Oil Company | Downhole casing-casing annulus sealant injection |
US11598178B2 (en) | 2021-01-08 | 2023-03-07 | Saudi Arabian Oil Company | Wellbore mud pit safety system |
US11655685B2 (en) | 2020-08-10 | 2023-05-23 | Saudi Arabian Oil Company | Downhole welding tools and related methods |
US11680459B1 (en) | 2022-02-24 | 2023-06-20 | Saudi Arabian Oil Company | Liner system with integrated cement retainer |
US11767732B2 (en) | 2021-03-29 | 2023-09-26 | Halliburton Energy Services, Inc. | Systems and methods for plugging a well |
US11828128B2 (en) | 2021-01-04 | 2023-11-28 | Saudi Arabian Oil Company | Convertible bell nipple for wellbore operations |
US11859815B2 (en) | 2021-05-18 | 2024-01-02 | Saudi Arabian Oil Company | Flare control at well sites |
US11905791B2 (en) | 2021-08-18 | 2024-02-20 | Saudi Arabian Oil Company | Float valve for drilling and workover operations |
US11913298B2 (en) | 2021-10-25 | 2024-02-27 | Saudi Arabian Oil Company | Downhole milling system |
US11993992B2 (en) | 2022-08-29 | 2024-05-28 | Saudi Arabian Oil Company | Modified cement retainer with milling assembly |
US12018565B2 (en) | 2022-05-24 | 2024-06-25 | Saudi Arabian Oil Company | Whipstock to plug and abandon wellbore below setting depth |
US12054999B2 (en) | 2021-03-01 | 2024-08-06 | Saudi Arabian Oil Company | Maintaining and inspecting a wellbore |
US12116326B2 (en) | 2021-11-22 | 2024-10-15 | Saudi Arabian Oil Company | Conversion of hydrogen sulfide and carbon dioxide into hydrocarbons using non-thermal plasma and a catalyst |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NO342616B1 (en) * | 2015-09-11 | 2018-06-18 | Wellguard As | A plugging tool, and method of plugging a well |
NO20161976A1 (en) * | 2016-12-13 | 2018-06-11 | Archer Oiltools As | A drill pipe string borne well test tool |
GB2563236B (en) * | 2017-06-07 | 2020-04-01 | Ardyne Holdings Ltd | Improvements in or relating to well abandonment |
GB2582745B (en) | 2019-03-27 | 2021-09-29 | Ardyne Holdings Ltd | Improvements in or relating to well abandonment |
NO346193B1 (en) * | 2019-06-17 | 2022-04-11 | Archer Oiltools As | Toolstring assembly and method for releasing and removing a stuck casing |
NO346617B1 (en) | 2020-03-09 | 2022-10-31 | Hydra Systems As | A fluid diverter tool, system and method of diverting a fluid flow in a well |
NO20210361A1 (en) * | 2021-03-19 | 2022-09-20 | Archer Oiltools As | Method of perforating, washing, cementing, and cutting and pulling a casing |
US11891868B2 (en) | 2021-11-30 | 2024-02-06 | Baker Hughes Oilfield Operations Llc | Extrusion ball actuated telescoping lock mechanism |
US11891869B2 (en) | 2021-11-30 | 2024-02-06 | Baker Hughes Oilfield Operations | Torque mechanism for bridge plug |
US11814926B2 (en) | 2021-11-30 | 2023-11-14 | Baker Hughes Oilfield Operations Llc | Multi plug system |
US11927067B2 (en) | 2021-11-30 | 2024-03-12 | Baker Hughes Oilfield Operations Llc | Shifting sleeve with extrudable ball and dog |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3593797A (en) * | 1969-05-16 | 1971-07-20 | Schlumberger Technology Corp | Method and apparatus for consolidating a subsurface earth formation |
US4279306A (en) | 1979-08-10 | 1981-07-21 | Top Tool Company, Inc. | Well washing tool and method |
US4270608A (en) * | 1979-12-27 | 1981-06-02 | Halliburton Company | Method and apparatus for gravel packing multiple zones |
US4431058A (en) * | 1981-03-16 | 1984-02-14 | Baker International Corporation | Wash tool method for subterranean wells |
US5372298A (en) | 1992-01-07 | 1994-12-13 | The Regents Of The University Of California | Transient liquid phase ceramic bonding |
GB2414492B (en) | 2004-05-26 | 2008-03-05 | U W G Ltd | Apparatus and method |
US7337840B2 (en) * | 2004-10-08 | 2008-03-04 | Halliburton Energy Services, Inc. | One trip liner conveyed gravel packing and cementing system |
NO335972B1 (en) * | 2011-01-12 | 2015-04-07 | Hydra Systems As | Procedure for combined cleaning and plugging in a well, washing tool for directional flushing in a well, and use of the washing tool |
-
2014
- 2014-01-31 EP EP14706704.5A patent/EP3099891A1/en not_active Withdrawn
- 2014-01-31 WO PCT/NO2014/000010 patent/WO2015115905A1/en active Application Filing
- 2014-01-31 US US15/115,589 patent/US20170067313A1/en not_active Abandoned
Cited By (34)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160138370A1 (en) * | 2014-11-18 | 2016-05-19 | Baker Hughes Incorporated | Mechanical diverter |
US11041352B2 (en) * | 2015-05-21 | 2021-06-22 | Thru Tubing Solutions, Inc. | Advancement of a tubular string into a wellbore |
US11274515B2 (en) * | 2016-11-07 | 2022-03-15 | Equinor Energy As | Method of plugging and pressure testing a well |
US11680454B2 (en) | 2016-11-07 | 2023-06-20 | Equinor Energy As | Method of plugging and pressure testing a well |
US20200056446A1 (en) * | 2018-08-14 | 2020-02-20 | Saudi Arabian Oil Company | Tandem Cement Retainer and Bridge Plug |
US10837254B2 (en) | 2018-08-14 | 2020-11-17 | Saudi Arabian Oil Company | Tandem cement retainer and bridge plug |
US11391113B2 (en) | 2018-08-14 | 2022-07-19 | Saudi Arabian Oil Company | Tandem cement retainer and bridge plug |
WO2020081236A1 (en) * | 2018-10-18 | 2020-04-23 | Geodynamics, Inc. | Pulse based perf and wash system and method |
US11773692B2 (en) | 2018-10-18 | 2023-10-03 | Geodynamics, Inc. | Pulse based perf and wash system and method |
US11199064B2 (en) | 2018-10-31 | 2021-12-14 | Halliburton Energy Services, Inc. | Integrated debris catcher and plug system |
US11280155B2 (en) * | 2019-03-13 | 2022-03-22 | Halliburton Energy Services, Inc. | Single trip wellbore cleaning and sealing system and method |
CN112177561A (en) * | 2019-07-03 | 2021-01-05 | 中国石油化工股份有限公司 | Bridge plug feeder, cementing plug pipe column and cementing plug process |
US11136849B2 (en) | 2019-11-05 | 2021-10-05 | Saudi Arabian Oil Company | Dual string fluid management devices for oil and gas applications |
US11230904B2 (en) | 2019-11-11 | 2022-01-25 | Saudi Arabian Oil Company | Setting and unsetting a production packer |
US20220381109A1 (en) * | 2019-11-12 | 2022-12-01 | Schlumberger Technology Corporation | Stage cementing collar with cup tool |
US12044098B2 (en) * | 2019-11-12 | 2024-07-23 | Schlumberger Technology Corporation | Stage cementing collar with cup tool |
US11156052B2 (en) | 2019-12-30 | 2021-10-26 | Saudi Arabian Oil Company | Wellbore tool assembly to open collapsed tubing |
US11260351B2 (en) | 2020-02-14 | 2022-03-01 | Saudi Arabian Oil Company | Thin film composite hollow fiber membranes fabrication systems |
US11253819B2 (en) | 2020-05-14 | 2022-02-22 | Saudi Arabian Oil Company | Production of thin film composite hollow fiber membranes |
US11655685B2 (en) | 2020-08-10 | 2023-05-23 | Saudi Arabian Oil Company | Downhole welding tools and related methods |
US11549329B2 (en) | 2020-12-22 | 2023-01-10 | Saudi Arabian Oil Company | Downhole casing-casing annulus sealant injection |
US11828128B2 (en) | 2021-01-04 | 2023-11-28 | Saudi Arabian Oil Company | Convertible bell nipple for wellbore operations |
US11598178B2 (en) | 2021-01-08 | 2023-03-07 | Saudi Arabian Oil Company | Wellbore mud pit safety system |
US12054999B2 (en) | 2021-03-01 | 2024-08-06 | Saudi Arabian Oil Company | Maintaining and inspecting a wellbore |
US11767732B2 (en) | 2021-03-29 | 2023-09-26 | Halliburton Energy Services, Inc. | Systems and methods for plugging a well |
US20220307345A1 (en) * | 2021-03-29 | 2022-09-29 | Conocophillips Company | Method and apparatus for use in plug and abandon operations |
US11448026B1 (en) | 2021-05-03 | 2022-09-20 | Saudi Arabian Oil Company | Cable head for a wireline tool |
US11859815B2 (en) | 2021-05-18 | 2024-01-02 | Saudi Arabian Oil Company | Flare control at well sites |
US11905791B2 (en) | 2021-08-18 | 2024-02-20 | Saudi Arabian Oil Company | Float valve for drilling and workover operations |
US11913298B2 (en) | 2021-10-25 | 2024-02-27 | Saudi Arabian Oil Company | Downhole milling system |
US12116326B2 (en) | 2021-11-22 | 2024-10-15 | Saudi Arabian Oil Company | Conversion of hydrogen sulfide and carbon dioxide into hydrocarbons using non-thermal plasma and a catalyst |
US11680459B1 (en) | 2022-02-24 | 2023-06-20 | Saudi Arabian Oil Company | Liner system with integrated cement retainer |
US12018565B2 (en) | 2022-05-24 | 2024-06-25 | Saudi Arabian Oil Company | Whipstock to plug and abandon wellbore below setting depth |
US11993992B2 (en) | 2022-08-29 | 2024-05-28 | Saudi Arabian Oil Company | Modified cement retainer with milling assembly |
Also Published As
Publication number | Publication date |
---|---|
EP3099891A1 (en) | 2016-12-07 |
WO2015115905A1 (en) | 2015-08-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20170067313A1 (en) | Straddle tool with disconnect between seals | |
RU2733998C2 (en) | Multistage stimulation device, systems and methods | |
CA3077883C (en) | Downhole tool assembly with debris relief, and method for using same | |
US10487626B2 (en) | Fracturing valve and fracturing tool string | |
US10900323B2 (en) | Method and stimulation sleeve for well completion in a subterranean wellbore | |
US20130180721A1 (en) | Downhole Fluid Treatment Tool | |
AU2012244360B2 (en) | Resettable ball seat | |
US9133675B2 (en) | Downhole tool and method | |
US9611722B2 (en) | Top down liner cementing, rotation and release method | |
US12044098B2 (en) | Stage cementing collar with cup tool | |
US11773692B2 (en) | Pulse based perf and wash system and method | |
US20160298422A1 (en) | Multi-zone fracturing in a random order | |
CA2873541A1 (en) | Fracturing valve and fracturing tool string | |
US11649694B2 (en) | Open hole multi-zone single trip completion system | |
CA2901074A1 (en) | Sleeve system for use in wellbore completion operations | |
GB2448632A (en) | Multi-State object activated valve with additional isolating member | |
US12123290B2 (en) | System and method for stimulating multiple zones | |
US20240102370A1 (en) | System and method for stimulating multiple zones | |
CA2919330A1 (en) | Toe initiator valve having an associated object catching seat | |
WO2016060570A1 (en) | Cementing method allowing initial liner top pressure integrity confirmation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: ARCHER OILTOOLS AS, NORWAY Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:CONNELL, PAUL LOWELL;NORHEIM, LARS HARALD;SIGNING DATES FROM 20160823 TO 20160824;REEL/FRAME:039587/0564 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |