US20130111985A1 - Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects - Google Patents

Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects Download PDF

Info

Publication number
US20130111985A1
US20130111985A1 US13/671,430 US201213671430A US2013111985A1 US 20130111985 A1 US20130111985 A1 US 20130111985A1 US 201213671430 A US201213671430 A US 201213671430A US 2013111985 A1 US2013111985 A1 US 2013111985A1
Authority
US
United States
Prior art keywords
fluid
pressure
closeable chamber
change
real time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/671,430
Other languages
English (en)
Inventor
Daniel Marco Veeningen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Intelliserv LLC
Original Assignee
Intelliserv LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Intelliserv LLC filed Critical Intelliserv LLC
Priority to US13/671,430 priority Critical patent/US20130111985A1/en
Priority to PCT/US2012/064191 priority patent/WO2014074099A1/fr
Assigned to Intelliserv, L.L.C. reassignment Intelliserv, L.L.C. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: VEENINGEN, Daniel Marco
Publication of US20130111985A1 publication Critical patent/US20130111985A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/06Measuring temperature or pressure
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • E21B33/06Blow-out preventers, i.e. apparatus closing around a drill pipe, e.g. annular blow-out preventers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/10Locating fluid leaks, intrusions or movements
    • E21B47/117Detecting leaks, e.g. from tubing, by pressure testing
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/12Means for transmitting measuring-signals or control signals from the well to the surface, or from the surface to the well, e.g. for logging while drilling

Definitions

  • the disclosure relates generally to systems and methods for conducting a pressure test of well system equipment. More particularly, the disclosure relates to systems and methods for reliably and efficiently pressure testing wellbore fluid containment system (FCS) equipment, such as blowout preventers (BOPs), choke and kill lines, wellhead hangers, casing, liner and liner hangers, tubing hangers, completions, mechanical barriers such as packers, cement plugs and other equipment. Further, the disclosure relates to both high pressure testing and low pressure testing of FCS equipment.
  • FCS wellbore fluid containment system
  • a well or well system In drilling for oil and gas from an offshore hydrocarbon producing well, a well or well system is provided that includes a drilling rig with a riser section and a drill string used to convey drilling fluid down the drill string and through a wellhead to a drill bit disposed within a wellbore of a formation.
  • a drilling rig with a riser section and a drill string used to convey drilling fluid down the drill string and through a wellhead to a drill bit disposed within a wellbore of a formation.
  • the walls of the wellbore are sometimes encased via the installation of tubular casing strings in the wellbore. Cement may be displaced into the wellbore so as to secure the individual casing strings to the wall of the wellbore.
  • Drilling fluid and circulation material i.e., cuttings from the formation
  • Drilling fluid and circulation material i.e., cuttings from the formation
  • Drilling fluid and circulation material recirculate from the drill bit back to the drilling rig via an annulus formed between the drill string and the cased wall of the wellbore, and via the annulus formed between the drill string and the riser section that encircles it.
  • a FCS of the well system is configured to provide a fluid tight barrier between fluid within the well system (e.g., drilling fluid, circulation material, formation fluid, etc.) and the surrounding environment.
  • the FCS includes all critical sealing points, including the BOP itself and each of its individual rams, the choke manifold and kill manifolds, an internal blowout preventer (IBOP), as well as other components.
  • IBOP internal blowout preventer
  • the FCS may be stressed in situations where a fluid pressure differential results between the well system and the surrounding environment. For instance, a wellbore or formation fluid influx, also called a “kick”, can cause an unstable and unsafe condition at the drilling rig.
  • a FCS of the well system may be used to prevent formation fluid from breaching the well system by “chocking” or “killing” the well and regain control.
  • the fluid pressure within the well system may rapidly decrease in the event of a low pressure kick, for instance, when a low pressure cavity within the formation is breached during drilling.
  • Some of the seals and sealing points within the well system may be pressure assisted, and thus rely on the pressure of the fluid around it to help seal. Thus, these pressure assisted seals may be jeopardized in the event of a low pressure kick.
  • the fluid pressure within the wellbore may decrease substantially as the hydrostatic head of the fluid within the marine riser (e.g., high density drilling fluid, etc.) is typically larger than the hydrostatic head by the seawater
  • the FCS is subject to a variety of testing regimens. For instance, components of the FCS undergoes periodic positive testing that includes low pressure testing, which may be performed at approximately 350 pounds per square inch (psi) and high pressure testing which may be conducted at approximately 10,000-15,000 psi, to ensure the FCS is capable of withstanding a pressurization due to an uncontrolled influx of formation fluid or in the event of a low pressure kick that may jeopardize pressure assisted seals. Also, the FCS undergoes inflow or negative pressure testing to ensure the integrity of the casing and cement installed in the wellbore, the wellhead assembly, as well as other components of the FCS, prior to uninstalling the marine riser.
  • periodic positive testing that includes low pressure testing, which may be performed at approximately 350 pounds per square inch (psi) and high pressure testing which may be conducted at approximately 10,000-15,000 psi, to ensure the FCS is capable of withstanding a pressurization due to an uncontrolled influx of formation fluid or in the event of a low pressure kick that may je
  • FCS test plug may be landed against a sealing surface within the FCS, followed by subsequent pressurization of the FCS.
  • pressure testing of the FCS must be conducted upon installation and before 14 days have elapsed since the last BOP pressure test. Low and high pressure tests must be conducted for each individual component, and each component must demonstrate that it holds a reasonably stable pressure. For instance, in practice a pressure decay rate of 4 pounds per square inch (psi) per minute or less is seen as reasonably stable.
  • graph 100 illustrates fluid pressures in relation to time at different positions along a vertically-oriented subsea drill string during a high pressure test.
  • Pressure curve 110 illustrates the fluid pressure at a point within the drill string near the sea floor, with curves 120 , 130 and 140 illustrating fluid pressure at progressively shallower points along the drill string, with curve 140 illustrating fluid pressure at the shallowest point, near the surface. Due to being located at different vertical depths along the drill string, curve 110 is at the highest pressure, while curve 140 is at the lowest pressure of the curves.
  • the high pressure test can be divided into three phases: a pumping phase ( 112 , 122 , 132 and 142 ), a shut-in phase ( 114 , 124 , 134 and 144 ) and a depressurization phase ( 116 , 126 , 136 and 146 ).
  • the pumping phase takes places when testing fluid is pumped into the well system in order to pressurize the FCS.
  • Testing fluid may be pumped into the drill string by a cement unit or mud pump disposed at the drilling rig of the well system.
  • shut-in phases 114 , 124 , 134 and 144 have a beginning ( 114 a, 124 a, 134 a and 144 a ) and an ending ( 114 b, 124 b, 134 b and 144 b ).
  • the pressure at the beginning 114 a, 124 a, 134 a and 144 a exceeds the pressure at the end 114 b , 124 b , 134 b and 144 b of the shut-in phase.
  • each shut-in phase includes a pressurization point ( 114 c, 124 c, 134 c and 144 c ) where additional testing fluid is pumped into the well system to slightly increase fluid pressure within the FCS, known in the field as “bumping up the pressure.”
  • This additional fluid may be pumped in at the pressurization point during the shut-in phase in order to return the fluid pressure within the FCS to the appropriate test pressure, a level similar to that existing near the beginning of the tests, at points 114 a, 124 a, 134 a and 144 a.
  • the pressure decay occurring during the shut-in phases (e.g., 114 , 124 , 134 and 144 ) for each pressure curve (e.g., 110 , 120 , 130 and 140 ) is due to heat transfer from pressurized fluid within the FCS to fluid in the surrounding environment.
  • heat transfer is greater for testing fluid near the surface, as opposed to testing fluid within the FCS that is disposed farther downhole.
  • the greater amount of heat transfer near the surface is due to friction generated during the process of pumping the testing fluid into the well system (e.g., via a cement unit or mud pump) for the purpose of pressurizing testing fluid within the FCS.
  • an analog, low resolution circular chart surface recorder may be used by drilling personnel on the drilling rig to observe a continuous pressure reading of the FCS. Even in cases where the tested FCS component is not leaking, the pressure test may often last over half an hour or longer before the pressure within the FCS begins to stabilize enough such that a continuous five minute period of successful pressure stabilization may be recorded.
  • FCS pressure tests are sometimes judged as successful before full stabilization (e.g., decay of 4 psi/min or less), thus allowing for the risk that remaining pressure decay may be due to a leak within the FCS, in addition to PVT effects.
  • this phenomenon is especially impactful at higher testing pressures, as are required in deeper, hot wells and where oil based mud (OBM) or synthetic oil based mud (SOBM) is used as the testing fluid in offshore wells with a subsea BOP in deepwater.
  • OBM oil based mud
  • SOBM synthetic oil based mud
  • the well may be abandoned by uninstalling the riser, BOP and other components of the well system, and sealing the wellhead to prevent fluid communication between the wellbore and the surrounding environment. Therefore, prior to removing the marine riser, the negative pressure test is conducted to simulate the reduced hydrostatic well pressure that exist if the riser is removed or during abandonment by substituting seawater in the fluid column from the wellhead to surface.
  • the reduced fluid pressure during the inflow or negative pressure testing operation creates a negative pressure differential across the wellbore and/or sealed wellhead.
  • the process for simulating the negative pressure environment is created within the wellbore prior to abandoning the well via either the mechanical stab-in plug (MSP) method or the choke and kill line (CKL) method.
  • MSP mechanical stab-in plug
  • CKL choke and kill line
  • a temporary or permanently installed tool is disposed within the wellbore configured to act as a barrier preventing inflow into the wellbore.
  • a special mechanical stab-in plug which may be either permanent or retrievable, is disposed within the wellbore that is configured to seal off the lower section of wellbore while also providing the ability of allowing the drill string or other conduit to be stabbed through it, once relatively low density fluids (e.g., base oil, water, etc.) was pumped into the lower, sealed portion of the wellbore, creating a negative pressure differential across the MSP plug.
  • relatively low density fluids e.g., base oil, water, etc.
  • a ram or other sealable mechanism of the BOP is actuated to fluidically isolate the wellbore and wellhead from the riser disposed above the BOP.
  • relatively low density fluid is pumped into the wellbore via the choke and/or kill lines in order to create a negative pressure differential across the sealed ram of the BOP.
  • a method for pressure testing a well system comprises providing fluid into a closeable chamber of the well system, measuring in real time a change in fluid pressure within the closeable chamber using a sensor disposed within the well system and measuring in real time a temperature change of fluid within the closeable chamber using a sensor disposed within the well system.
  • the closeable chamber is provided with a fluid having a higher density than water.
  • the closeable chamber is provided with a fluid having a density substantially equal to water.
  • the closeable chamber comprises at least a portion of a drill string.
  • the closeable chamber comprises at least a portion of a choke line.
  • the closeable chamber comprises at least a portion of a kill line.
  • the method may further comprise using real time pressure and temperature measurements to calculate real time pressure decay of fluid within the closeable chamber, wherein the pressure decay arises from changes in the volume of fluid within the closeable chamber over time.
  • the method may further comprise stabbing into a plug of the well system with the drill string to allow for fluid communication between the drill string and a volume of fluid disposed below the plug.
  • the closeable chamber comprises at least a portion of a blowout preventer.
  • the method may further comprise sealing the blowout preventer to prevent fluid communication between a drill string of the well system and an annulus adjacent to the blowout preventer.
  • the method may further comprise measuring in real time a pressure change in the closeable chamber using a sensor disposed within the well system.
  • the closeable chamber comprises a component of a completion system.
  • the component of the completion system comprises a tubing hanger.
  • the method may further comprise communicating a signal from the sensor using a wired pipe communication network.
  • a method for pressure testing a well system comprises providing a fluid into a closeable chamber of the well system and determining in real time a change in fluid pressure in the closeable chamber, wherein the change in pressure arises from a change in the volume of fluid within the closeable chamber.
  • the method further comprises determining in real time a change in fluid pressure within the closeable chamber arising from a change in temperature of the fluid.
  • determining in real time a change in fluid pressure within the closeable chamber arising from a change in the volume of fluid within the closeable chamber comprises measuring in real time a change in fluid pressure within the closeable chamber using a sensor disposed within the well system.
  • determining in real time a change in fluid pressure within the closeable chamber arising from a change in temperature of the fluid comprises measuring in real time a temperature change of fluid within the closeable chamber using a sensor disposed within the well system. In an embodiment, determining in real time a change in fluid pressure within the closeable chamber arising from a change in temperature of the fluid comprises calculating the change in temperature over time for a section of a wired pipe communication network. In an embodiment, the method further comprises summing the pressure decay arising from changes in temperature over time for the section of the wired pipe communication network. In an embodiment, the method further comprises subtracting the summed pressure decay arising from changes in temperature over time from the total fluid pressure decay within the closeable chamber. In an embodiment, the closeable chamber comprises at least a portion of a blowout preventer. In an embodiment, the closeable chamber comprises at least a portion of a wellhead.
  • a method for pressure testing a well system comprises providing fluid into a closeable chamber of the well system, measuring in real time a change in fluid pressure within the closeable chamber using a sensor of a wired pipe communication network disposed within the well system, measuring in real time a temperature change of fluid within the closeable chamber using a sensor of the wired pipe communication network disposed within the well system and calculating in real time the pressure decay arising from a change in the volume of fluid disposed within the closeable chamber using the pressure and temperature measurements.
  • the closeable chamber comprises at least a portion of a blowout preventer.
  • the closeable chamber comprises at least a portion of a component of an upper completion system.
  • Embodiments described herein comprise a combination of features and characteristics intended to address various shortcomings associated with certain prior devices, systems, and methods.
  • the various features and characteristics described above, as well as others, will be readily apparent to those skilled in the art upon reading the following detailed description, and by referring to the accompanying drawings.
  • FIG. 1 is a graph illustrating pressure curves generated during a pressure test of a drilling system
  • FIG. 2 is a schematic representation of an embodiment of a well system configured to conduct a fluid containment system pressure test in accordance with principles described herein in accordance with principles described herein;
  • FIGS. 3A-3D are perspective views, some in cross-section, showing components of the wired pipe communication network shown in FIG. 2 ;
  • FIG. 4A is a graph illustrating pressure curves generated during a pressure test of a well system, such as the well system shown in FIG. 2 ;
  • FIG. 4B is a graph illustrating temperature curves generated during a pressure test of a well system, such as the well system shown in FIG. 2 ;
  • FIG. 5 is a graph illustrating temperature curves generated during a pressure test of a drilling system, such as the well system shown in FIG. 2 ;
  • FIG. 6 is a schematic representation showing the well system shown in FIG. 2 configured to conduct a completion system pressure test in accordance with principles described herein;
  • FIGS. 7A-7B are schematic representations of the well system shown in FIG. 2 configured to conduct a negative pressure test using an MSP method in accordance with principles described herein;
  • FIGS. 8A and 8B are schematic representations of the well system shown in FIG. 2 configured to conduct a negative pressure test using a CKL method in accordance with principles described herein.
  • the terms “including” and “comprising” are used in an open-ended fashion, and thus should be interpreted to mean “including, but not limited to . . . .”
  • the term “couple” or “couples” is intended to mean either an indirect or direct connection. Thus, if a first device couples to a second device, that connection may be through a direct connection, or through an indirect connection via other devices, components, and connections.
  • the terms “axial” and “axially” generally mean along or parallel to a given axis (e.g., given axis of a body or a port), while the terms “radial” and “radially” generally mean perpendicular to the given axis.
  • an axial distance refers to a distance measured along or parallel to the given axis
  • a radial distance means a distance measured perpendicular to the given axis.
  • the phrase “communication coupler” refers to a device or structure that communicates a signal across the respective ends of two adjacent tubular members, such as the threaded box/pin ends of adjacent pipe joints; and the phrase “wired drill pipe” or “WDP” refers to one or more tubular members, including drill pipe, drill collars, casing, tubing, subs, and other conduits, that are configured for use in a drill string and include a wired link.
  • wireless link refers to a pathway that is at least partially wired along or through a WDP joint for conducting signals
  • communication link refers to a plurality of communicatively-connected tubular members, such as interconnected WDP joints for conducting signals over a distance.
  • a system and method for pressure testing components of a well system is disclosed herein.
  • Embodiments described herein may be employed in various drilling and production applications; however, it has particular application as a system and method for detecting leaks during a test of well system via accounting for and calibrating against PVT effects during the pressure testing of pressure containing components of the well system, such as a fluid containment system (FCS). Further, it has particular application with regard to offshore well drilling and production systems.
  • FCS fluid containment system
  • an offshore well drilling system 10 generally includes an offshore semi-submersible drilling rig 20 disposed at the water line 12 with a derrick 24 and deck 22 having a testing fluid system (TFS) 21 disposed thereon.
  • System 10 further includes a riser 30 that extends between the rig 20 and a wellhead 60 disposed at the sea floor 14 , a FCS 40 , a drill string 50 disposed within a marine riser 30 and having a central axis 55 and internal passageway 50 b .
  • Well system 10 further includes casing 70 that extends downward from a casing hanger 61 of wellhead 60 and is secured in place via cement 72 .
  • TFS 21 is disposed at rig floor 22 and comprises a mud pit 25 , a cement unit 27 and a fluid conduit 28 .
  • Conduit 28 provides a fluid flowpath 29 for the passage of testing fluid 29 a from mud pit 25 , through cement unit 27 , and to the passageway 50 b of drill string 50 .
  • Cement unit 27 comprises a high pressure, reciprocating fluid pump. However, in other embodiments cement unit 27 may comprise other components configured to pressurize a fluid.
  • Testing fluid 29 comprises a drilling fluid that may be at a high density or high weight (e.g., drilling fluid, SOBM, completion fluid, etc.) relative to the ambient water 13 disposed below water line 12 .
  • fluid 29 typically has a high enough density to overcome the pressure of fluid within the adjacent formation 16 .
  • testing fluid may also comprise a relatively lower density fluid, such as water.
  • FCS 40 generally includes components configured to retain and manage fluid pressure within well system 10 (e.g., drill string 50 , FCS 40 and annulus 35 ).
  • FCS 40 includes BOP 41 , choke line 44 , kill line 46 and an internal blowout preventer (IBOP) 48 , wellhead and the casing and or liner and float valves.
  • IBOP internal blowout preventer
  • Rams 42 of BOP 41 are configured to provide an annular seal 43 about drill string 50 upon actuation, dividing annulus 35 into a first or upper section 35 a extending between rig 20 and seal 43 and a second or middle section 35 b extending from seal 43 downward to a FCS testing plug 49 coupled to drill string 50 .
  • a third or lower section 35 c extends from wellhead 60 into the wellbore 62 .
  • Testing plug 49 is configured to prevent fluid flow between middle portion 35 b of annulus 35 and a lower portion 35 c extending into wellbore 62 .
  • Testing plug 49 forms an annular seal 49 c against an annular surface 61 a of hanger 61 disposed within wellhead 60 .
  • Testing plug 49 is coupled to an end of two adjacent tubular joints or sections 52 that extend between nodes 51 and physically engages upper annular surface 61 a of hanger 61 via lower annular surface 49 a.
  • a radial port or opening 45 is provided in the drillstring 50 to act as a route of fluid communication between drillstring 50 and the annulus 35 above testing plug 49 .
  • a volume of formation fluid or a kick of fluid from the formation 16 that has a relatively higher pressure than drilling fluid disposed within wellbore 62 may flow into wellbore 62 and travel upward through lower section 35 c of annulus 35 (testing plug 49 is not installed in well system 10 during the act of drilling).
  • the formation kick may be trapped or isolated within lower section 35 c of annulus 35 via actuating one or more rams 42 of BOP 41 to provide the annular seal 43 .
  • Choke line 44 and kill line 46 may be used to provide for alternate routes of fluid communication between rig 20 and annulus 35 such that the kill fluid (e.g., water, weighted drilling mud, etc.) is pumped into FCS 40 to prevent further upward flow of fluid from formation 16 .
  • the kill fluid e.g., water, weighted drilling mud, etc.
  • Choke line 44 generally includes a lower valve 44 a, a manifold 44 b and an upper valve 44 c. Fluid flow through choke line 44 may be restricted by closing lower valve 44 a or upper valve 44 c.
  • choke manifold 44 b includes a plurality of valves, chokes and other equipment, and as such is configured to manage and regulate flow through choke line 44 .
  • a kill line such as kill line 46 may be used to “kill” the well by reversing, stopping or at least substantially restricting the flow of fluid from the formation into the wellbore 62 by pumping heavy fluid into the entire fluid circulation system (e.g., annulus 35 , choke line 44 , kill line 46 , etc.) from the rig 20 .
  • Kill line 46 comprises a lower valve 46 a, a kill manifold 46 b and an upper valve 46 c.
  • flow through kill line 46 may be substantially restricted or controlled via valves 46 a, 46 c and manifold 46 b.
  • valves 46 a, 46 c and manifold 46 b are pressure tested as well.
  • IBOP 48 is disposed at an upper end 50 a of drill string 50 at the rig 20 and is configured to manage fluid pressure within drill string 50 .
  • high pressure formation fluid may begin flowing upward through string 50 via an opening or port of the string 50 disposed within wellbore 62 (e.g., at the drill bit).
  • IBOP 48 includes a valve that allows for the passage of fluid into string 50 but may be closed to restrict fluid from flowing out of string 50 through IBOP 48 in the event of a formation kick.
  • IBOP 48 may be used in effectively controlling a formation kick, IBOP 48 is pressure tested during the pressure testing of FCS 40 .
  • drill string 50 comprises a plurality of nodes 51 (e.g., 51 a - 51 e ) coupled between a plurality of tubular joints 52 .
  • Wired or networked drill pipe incorporating distributed sensors can transmit data from anywhere along the drill string 50 to the rig 20 for analysis.
  • Nodes 51 are provided at desired intervals along the drill string 50 .
  • Network nodes 51 essentially function as signal repeaters to regenerate and/or boost data signals and mitigate signal attenuation as data is transmitted up and down the drill string.
  • the nodes 51 may also include measurement assemblies.
  • the nodes 51 may be integrated into an existing section of drill string or a downhole tool along the drill string 50 .
  • tubular joints 52 include a first pipe end 53 having, for example, a first induction coil 53 a and a second pipe end 54 having, for example, a second induction coil 54 a.
  • Nodes 51 comprise a portion of a wired pipe communication network 56 that provides an electromagnetic signal path that is used to transmit information along the drill string 50 .
  • the communication network 56 or broadband network telemetry, may thus include multiple nodes 51 based along the drill string 50 .
  • Communication links or wired conductors 52 a may be used to connect the nodes 51 to one another, and may comprise cables or other transmission media integrated directly into sections of the drill string 50 .
  • the cable may be routed through the central wellbore of the drill string 50 , or routed externally to the drill string 50 , or mounted within a groove, slot or passageway in the drill string 50 .
  • Signals from the plurality of sensors of nodes 51 along the drill string 50 are transmitted to rig 20 through wire conductors 52 a along the drill string 50 .
  • Communication links 52 a between the nodes 51 may also use wireless connections.
  • a plurality of packets may be used to transmit information along the nodes 51 . Further detail with respect to suitable nodes, a network, and data packets are disclosed in U.S. Pat. No. 7,207,396 (Hall et al., 2007), hereby incorporated in its entirety by reference.
  • Various types of sensors 57 may be employed along the drill string 50 in various embodiments, including without limitation, axially spaced pressure sensors, temperature sensors, and others.
  • the sensors 57 may be disposed on the nodes 51 positioned along the drill string, disposed on tools incorporated into the drill string, or a combination thereof. Thus, sensors 57 of nodes 51 may measure temperature, pressure, etc., of fluid within string 50 or annulus 35 of well system 10 .
  • Network nodes 51 are disposed along the drill string 50 between joints 52 .
  • the booster assemblies are spaced at 1,500 ft. (500 m) intervals to boost the data signal as it travels the length of the drill string 50 to prevent signal degradation.
  • Network nodes 51 are also located at these intervals to allow measurements to be taken along the length of the drill string 50 .
  • the distributed network nodes 51 provide measurements that give the driller additional insight into what is happening along the potentially miles-long stretch of the drill string 50 .
  • Rig 20 includes a well site computer 58 that may display information for the drilling operator.
  • the wired pipe communication network 56 transmits information from each of a plurality of sensors 57 to a surface computer 58 .
  • Information may also be transmitted from computer 58 to another computer 59 , located at a site remote from the well, with this computer 59 allowing an individual in the office remote from the well to review the data output by the sensors 57 .
  • sensors 57 Although only a few sensors 57 are shown in the figures, those skilled in the art will understand that a larger number of sensors may be disposed along a drill string (e.g., drill string 50 ) when drilling, and that all sensors associated with any particular node may be housed within or annexed to the node 51 , so that a variety of sensors rather than a single sensor will be associated with that particular node.
  • a drill string e.g., drill string 50
  • a BOP e.g., BOP 41
  • FCS FCS 40
  • the wired pipe communication network 56 allows wellsite personnel to identify potential remedial actions for the migrated wellbore influx.
  • the measurements used are independent from surface measurements.
  • One or more embodiments of a well drilling system 10 comprising a fluid containment system 40 and a testing fluid system 21 having been disclosed, one or more embodiments of a method of pressure testing components of the FCS 40 are also disclosed herein. Further, one or more embodiments of a method for evaluating or troubleshooting the results of a failed pressure test of components of FCS 40 are disclosed herein.
  • a FCS pressure testing method generally includes the steps of engaging a testing plug of the FCS against a sealing surface within the FCS (e.g., a casing hanger), disposing a quantity of testing fluid (e.g., drilling fluid, etc.) within the FCS, isolating a component of the FCS (e.g., actuating a ram of the BOP, closing a valve of the choke line, etc.), displacing an additional quantity of testing fluid into the FCS to increase the fluid pressure within the FCS to a predetermined testing pressure, shut-in the FCS by ceasing the displacement of testing fluid into the FCS, continuously in real-time monitor fluid pressure within the FCS via an wired pipe communication network for a period of time.
  • a testing fluid e.g., drilling fluid, etc.
  • ram 42 of BOP 41 may be pressure tested as part of the regime for pressure testing each individual component of FCS 40 .
  • testing plug 49 is coupled to drill string 50 and displaced downward through marine riser 30 until annular surface 49 a of tool 49 engages annular surface 61 a of tubing hanger 61 to create annular seal 49 c, which divides annulus 35 into upper section 35 a and lower section 35 c.
  • high density testing fluid 29 (e.g., drilling fluid, SOBM, competition fluid, etc.) is disposed within drill string 50 and riser 30 at a relatively low pressure (e.g., approximately 300-350 psi) using cement unit 27 and flowpath 29 a .
  • ram 42 of BOP 41 is actuated to form an annular seal 43 against an outer surface of drill string 50 , substantially preventing testing fluid from a port 45 of string 50 from flowing upward into the upper section 35 a of annulus 35 .
  • annular seals 49 c and 43 form middle section or closable chamber 35 b within marine riser 30 .
  • pressure and temperature of fluid within annulus 35 and drill string 50 is continuously measured at different vertical depths along string 50 via nodes 51 a, 51 b, 51 c, etc.
  • pressure and temperature of fluid within chamber 35 b is continuously measured via node 51 c while pressure and temperature in upper portion 35 a are measured via nodes 51 a and 51 b and the temperature and pressure of lower portion 35 c are measured by nodes 51 d and 51 e.
  • Measurements taken by sensors 57 at nodes 51 are continuously transmitted to computers 58 or 59 at rig 20 via wired pipe communication network 56 .
  • fluid pressure within drillstring 50 and chamber 35 b of annulus 35 is increased to a predetermined testing pressure by displacing a volume of testing fluid 29 into chamber 35 b via port 45 .
  • Testing fluid 29 is pumped using cement unit 27 into drill string 50 via fluid flowpath 29 a, which comprises mud pit 25 , cement unit 27 and passageway 50 b of string 50 .
  • Testing fluid 29 within chamber 35 b is subsequently pressurized to approximately between 5,000-15,000 psi by cement unit 27 .
  • testing fluid 29 is disposed within choke line 44 and kill line 46 , preventing fluid within chamber 35 b from flowing up lines 44 , 46 , via the weight of the fluid 29 disposed within lines 44 , 46 .
  • FIGS. 4A and 4B illustrate graphs of data that may be generated by nodes 51 (e.g., 51 a , 51 b and 51 c ) during a high pressure test of components of FCS 40 .
  • Curves 502 and 508 illustrate the temperature and pressure curves, respectively, captured in real time by top node 51 a.
  • Curves 504 and 510 illustrate the temperature and pressure curves, respectively, captured in real time by middle node 51 b.
  • Curves 506 and 512 illustrate the temperature and pressure curves, respectively, captured in real time by bottom node 51 c.
  • Nodes 51 a, 51 b and 51 c are each within fluid communication with one another, and thus expansion of fluid disposed proximal to one node will result in a measured fluid pressure increase by all three nodes.
  • a pumping phase 207 is followed by a shut-in phase 208 , having a beginning 208 a and an ending 208 b, marks the period of time after pumping has finished and before FCS 40 has been depressurized, which is then followed by a depressurization phase 209 .
  • testing fluid 29 is pumped into drillstring 50 via cement unit 27 ,which in turn displaces a volume of fluid into chamber 35 c , pressurizing the chamber 35 c to the BOP testing pressure.
  • shut-in phase 208 initiates with the cessation of pumping from cement unit 27 , stopping the flow of testing fluid 29 into drillstring 50 at rig 20 .
  • ram 42 must successfully hold the BOP test pressure for a specified period of time. In one example, ram 42 must hold 15,000 psi for a period of five minutes. Friction from pumping results in an increase in temperature of the additional testing fluid 29 pumped into FCS 40 and string 50 from mud pit 25 .
  • the data captured by nodes 51 a, 51 b and 51 c of FIG. 2 quantify both pressure and temperature of the fluid within FCS 40 , allowing the computers 58 , 59 , to correct against PVT effects in order to determine the amount of pressure decay during the shut-in phase 208 that is arises from the decay in temperature, and not due to a possible leak. Due to the relationship between pressure, volume, and temperature, a pressure decrease may only be caused by decay in temperature. A leak within a FCS results in a decrease in the volume of fluid present in the FCS and in turn a decrease in fluid pressure within the FCS.
  • the ability to extract the amount of pressure decay due to the decay in temperature allows for a more time efficient shut-in phase for non-leaking FCSs as the pressure decay due to decay in fluid temperature will be quantified and extracted, leaving a near-zero change in pressure over time, illustrating that the system is holding pressure and has successfully passed the pressure test.
  • FIG. 5 illustrates the relationship between the total pressure decay (dP) 602 , the pressure decay arising from a decay in temperature (dP T ) 604 and the pressure decay arising from a decrease in the volume of fluid (dp V ) 606 disposed in a non-leaking FCS, where the total pressure decay is substantially arising from the decay in temperature and thus the decay in pressure arising from a change in volume is near zero.
  • the pressure and temperature of sections of the drill string 50 are measured in real time in order to determine the dP V for each section, and after the dP V is observed from the computers 58 , 59 , as holding substantially constant pressure for approximately five minutes, the pressure test would be successful.
  • other components of FCS 40 may be pressure tested in a similar manner. For instance, other individual rams of BOP 41 may be actuated to create an annular seal within annulus 35 , forming a cavity defined by the ram's annular seal and the seal 49 a produced by BOP testing plug 49 .
  • lower valves 44 a, 46 a, manifolds 44 b, 46 b, and upper valves 44 c , 46 c , of choke line 44 and kill line 46 may be pressure tested.
  • high density testing fluid 29 is pumped into drillstring 50 via cement unit 27 .
  • Ram 42 of BOP 41 may be actuated to create annular seal 43 .
  • a component of lines 44 , 46 may be sealed (e.g., lower valve 44 a ).
  • the sealed component e.g., valve 44 a
  • the sealed component may be pressure tested to see if it holds the BOP test pressure for a requisite period of time (e.g., five minutes).
  • nodes are placed (e.g., nodes similar to nodes 51 ) within choke line 44 or kill line 46 in order to continuously measure and transmit pressure and temperature readings from lines 44 , 46 and quantify any pressure decay within lines 44 , 46 , due to temperature decay so as to determine if there has been a decay in pressure due to a decrease in the volume of fluid disposed within lines 44 , 46 .
  • lines 44 and 46 e.g., wired conductors 52 a, etc.
  • lines 44 and 46 e.g., wired conductors 52 a, etc.
  • pressure would be measured in real time from nodes disposed in lines 44 , 46
  • temperature measurements would be read from nodes disposed within drill string 50 , as heated fluid would be pumped into string 50 from cement unit 27 .
  • FIG. 6 illustrates well system 10 configured to conduct a high pressure test of an upper completion system of the FCS 40 , including tubing 81 and casing 70 .
  • a lower completion and an upper completion may be installed within wellbore 62 prior to the beginning of the production phase of well system 10 .
  • FIG. 6 illustrates well system 10 configured to conduct a high pressure test of an upper completion system of the FCS 40 , including tubing 81 and casing 70 .
  • upper completion 80 generally includes tubing 81 coupled to a tubing hanger 82 to serve as the main support for production tubing and to act as a sealing point of the riser 30 at the wellhead 60 , and casing 70 which is installed and cemented in place via cement 72 to seal the wellbore 62 from the formation, thus making wellbore 62 a closeable chamber configured to prevent formation fluid from leaking into the wellbore 62 .
  • Tubing 81 includes a port 86 that provides fluid communication between wellbore or chamber 62 and the internal passageway 50 b of string 50 .
  • Tubing hanger 82 upon installation in wellhead 60 , creates an annular seal 82 a that prevents fluid communication between wellbore 62 and the annulus 35 within marine riser 30 .
  • Tubing 81 and tubing hanger 82 are installed via a tubing hanger running tool 83 that is coupled to the downhole terminal end 50 c of drill pipe 50 .
  • tubing hanger 82 and running tool 83 are coupled together as tubing 81 is displaced downward into wellbore 62 .
  • a lower completion may be installed within wellbore 62 that includes production packers to isolate particular zones of wellbore 62 , plugs, circulating devices, etc.
  • running tool 83 may be decoupled from tubing hanger 82 , allowing for the removal of drill pipe 50 and running tool 83 from the marine riser 30 .
  • Testing of seal 82 a includes inflow or negative pressure testing and positive pressure testing at both high (e.g., approximately 70% of maximum capacity) and low pressures.
  • high density fluid e.g., drilling fluid, completion fluid, etc.
  • a cement unit 27 down through the drill string 50 , out through a port 86 (as indicated by the arrows shown in FIG. 6 ) and into the wellbore 62 .
  • Nodes 51 disposed within annulus 35 are used to indicate real time pressure and temperature of the fluid in both passageway 50 b of string 50 and wellbore to determine the real time decay in pressure due to an increase in volume caused by a leak in the upper completion 90 , dP V . If seal 82 a of tubing hanger 82 and the seal between casing 70 and formation 16 are properly sealed, the pressure and temperature data transmitted from nodes 51 (e.g., 51 a - 51 c, etc.) will indicate a nearly constant dP V , thus indicating successful a positive pressure test of upper completion 90 .
  • nodes 51 and network 56 may also be used for performing a pressure test of an installed lower completion.
  • nodes 51 of tubing 82 may be disposed within individual production zones that are sealed via a plurality of production packers. The annular seal created by each installed production packer may be tested by pressurizing each individual sealed production zone and measuring in real time the fluid pressure and temperature within the particular tested zone.
  • inflow or negative pressure testing is commonly required for wells with a subsea BOP or a mudline suspension system to verify barriers and well integrity for those instances that the wellbore may be exposed to a reduced hydrostatic pressure as may be the case once the marine riser is eliminated or during abandonment.
  • Wellbores of well systems such as system 10 , may be subjected to negative pressures upon abandonment (e.g., pressure within wellbore 62 may be lower than in the surrounding environment 13 ), when wellhead 60 is sealed and BOP 41 and riser 30 have been removed.
  • Formation fluid within the wellbore may be of a higher pressure than the seawater surrounding the wellhead, creating a negative pressure across wellhead 60 that may lead to an inflow of fluid from formation 16 into the wellbore 62 if FCS 40 fails to seal wellbore 62 .
  • inflow or negative pressure testing involves creating a negative pressure environment within the wellbore (e.g., wellbore 62 ) through the use of low density fluids, possibly seawater.
  • FIGS. 9A and 9B illustrate a negative pressure testing setup using the MSP method.
  • a mechanical packer or plug 804 is installed in wellbore 62 .
  • barrier 804 may be a temporary or removable plug such as the RTTS (Halliburton tool (3000 N. Sam Houston Pkwy E. Houston, Tex. 77032 U.S.A) which is a retrievable mechanical stab-in packer.
  • RTTS Hextstststs, a temporary or removable plug such as the RTTS (Halliburton tool (3000 N. Sam Houston Pkwy E. Houston, Tex. 77032 U.S.A) which is a retrievable mechanical stab-in packer.
  • RTTS Real-Time Transporter
  • barrier 804 may also be a permanently installed MSP.
  • the plug or barrier 804 having a valve 804 a is installed within the wellbore 62 , providing an annular seal 804 b , isolating an upper section 62 a from a lower section or closeable chamber 62 b of wellbore 62 .
  • the wellbore 62 is sealed from the surrounding formation using a barrier 806 installed at the downhole end of the casing 70 .
  • the plug 804 seals the wellbore 62 from annulus 35 of riser 30 when the drill string 50 is not stabbed (protruding) into it (as shown in FIG. 7A ).
  • string 50 may be displaced downward into wellbore 62 and “stabbed” into the plug 804 such that valve 804 a of plug 804 opens, allowing fluid disposed within string 50 to be pumped into the lower portion or chamber 62 b of the wellbore 62 .
  • drill string 50 is partially or completely filled with a relatively less dense fluid 829 compared to the heavier drilling or completion fluid.
  • the negative pressure testing fluid is water.
  • fluid 829 may be base oil or other relatively less dense fluids.
  • relatively higher pressure formation fluid may flow upward into the downhole end of drill string 50 , displacing the relatively less dense water 829 upward toward rig.
  • the real time pressure and temperature within the drill string 50 may be measured using nodes 51 (e.g., 51 a - 51 d ), which may be used to measure a possible decay in fluid pressure due to an increase in volume caused by a leak, dP V .
  • nodes 51 e.g., 51 a - 51 d
  • FIGS. 8A and 8B illustrate an alternative method for negative or low pressure testing wellbore 62 before abandoning a well using the CKL method.
  • the downhole end of wellbore 62 is sealed by barrier 806 , casing 70 and wellhead 60 , and lower valves 44 a, 46 a, are in a closed position, forming a closeable chamber 831 generally including wellbore 62 , string 50 and annulus 35 .
  • kill line 46 is then partially or completely filled with negative testing fluid 829 via being pumped from cement unit 27 while a ram or annular (e.g., ram 42 ) of BOP 41 is actuated to create annular seal 43 , isolating wellbore 62 from annulus 45 of marine riser 30 .
  • lower valves 44 a, 46 a are opened to provide fluid communication between wellbore 62 and lines 44 and 46 .
  • Nodes 51 a - 51 d measure real time pressure and temperature values within the drill string 50 and wellbore 62 , indicating a real time pressure decay within wellbore 62 due to a leak between wellbore 62 and either the formation 16 or the ambient water 13 .
  • an inflow or negative pressure test on a completion of well system 10 such as upper completion 80 .
  • relatively low density fluid such as water or base oil may be disposed within passage 50 b of string 50 and put into fluid communication with wellbore 62 via port 86 . Due to the lower density of the fluid disposed within string 50 , the amount of static fluid pressure or head applied to wellbore 62 from passage 50 b is substantially reduced, thus the upper completion 80 's ability to withstand inflow or negative pressure between wellbore 62 and formation 16 .

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Remote Sensing (AREA)
  • Measuring Fluid Pressure (AREA)
US13/671,430 2011-11-07 2012-11-07 Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects Abandoned US20130111985A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US13/671,430 US20130111985A1 (en) 2011-11-07 2012-11-07 Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects
PCT/US2012/064191 WO2014074099A1 (fr) 2012-11-07 2012-11-08 Procédé pour l'essai efficace de la pression et du flux entrant d'un système de confinement de fluide par détection de fuite en temps réel avec quantification des effets pvt

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US201161556781P 2011-11-07 2011-11-07
US13/671,430 US20130111985A1 (en) 2011-11-07 2012-11-07 Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects

Publications (1)

Publication Number Publication Date
US20130111985A1 true US20130111985A1 (en) 2013-05-09

Family

ID=47263583

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/671,430 Abandoned US20130111985A1 (en) 2011-11-07 2012-11-07 Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects

Country Status (2)

Country Link
US (1) US20130111985A1 (fr)
WO (1) WO2014074099A1 (fr)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140123747A1 (en) * 2012-11-05 2014-05-08 Intelliserv, Llc Systems and methods for conducting pressure tests on a wellbore fluid containment system
US20140262269A1 (en) * 2013-03-13 2014-09-18 Superior Energy Services, L.L.C. Method to repair leaks in a cemented annulus
WO2016036362A1 (fr) * 2014-09-03 2016-03-10 Halliburton Energy Services, Inc. Outil d'isolation de tube ascenseur pour puits en eaux profondes
WO2016161143A1 (fr) 2015-03-31 2016-10-06 Engip Llc Système hydrostatique de mise à l'essai des vibrations destiné à la prévention des éruptions
US9470082B1 (en) * 2015-05-05 2016-10-18 Backoff, Llc Blowout-preventer-stack one-trip test tool and method
US20160334300A1 (en) * 2015-05-11 2016-11-17 HilFlo, LLC Hydrostatic Pressure Test Method
US20170074748A1 (en) * 2015-03-31 2017-03-16 Engip Llc Normalized Hydrostatic Test Method
US20180052071A1 (en) * 2015-03-31 2018-02-22 Engip Llc Method and System for Determining a Fluid Leak
US10113650B2 (en) 2016-01-12 2018-10-30 Engip, LLC Dual seat valve
US10132164B2 (en) * 2015-12-18 2018-11-20 Schlumberger Technology Corporation Systems and methods for in-situ measurements of mixed formation fluids
WO2019097220A1 (fr) * 2017-11-15 2019-05-23 Ardyne Holdings Limited Perfectionnements apportés ou se rapportant à l'abandon de puits et à la récupération de fentes
US10330561B2 (en) 2015-03-31 2019-06-25 Engip, LLC Method for testing for fluid leaks
NO20180592A1 (en) * 2018-04-26 2019-10-28 Scanwell Tech As Method of testing an integrity of a structure comprising a chamber, and related apparatus
CN111395992A (zh) * 2020-03-27 2020-07-10 甘肃省建材科研设计院有限责任公司 堵漏方法
WO2020223203A1 (fr) * 2019-04-29 2020-11-05 Baker Hughes Oilfield Operations Llc Détection de fuite basée sur la température pour obturateurs anti-éruption
US10996132B2 (en) 2015-03-31 2021-05-04 ENgip, LLP Method for testing for fluid leaks
US11041380B2 (en) 2016-05-26 2021-06-22 Metrol Technology Limited Method of pressure testing
US11105198B2 (en) 2016-03-31 2021-08-31 Schlumberger Technology Corporation Methods for in-situ multi-temperature measurements using downhole acquisition tool
WO2022026683A1 (fr) * 2020-07-31 2022-02-03 Schlumberger Technology Corporation Système d'analyse de tampon de forage
WO2022026727A1 (fr) 2020-07-31 2022-02-03 Schlumberger Technology Corporation Système d'analyse de bouchon de trou

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10487611B2 (en) 2015-02-13 2019-11-26 Schlumberger Technology Corporation Deployment method for coiled tubing
WO2016130620A1 (fr) * 2015-02-13 2016-08-18 Schlumberger Technology Corporation Obturateur anti-éruption à déploiement à verrouillage
US10934792B2 (en) 2015-02-13 2021-03-02 Schlumberger Technology Corporation Powered sheave with wireline pushing capability
US10465472B2 (en) 2015-02-13 2019-11-05 Schlumberger Technology Corporation Deployment valves operable under pressure
WO2016130619A1 (fr) 2015-02-13 2016-08-18 Schlumberger Technology Corporation Barres de déploiement cisaillables à multiples passages et câbles
CN110529066B (zh) * 2019-07-12 2021-10-29 中国石油化工股份有限公司 试井测试用防喷堵头

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050269079A1 (en) * 2003-12-26 2005-12-08 Franklin Charles M Blowout preventer testing system
US20090236144A1 (en) * 2006-02-09 2009-09-24 Todd Richard J Managed pressure and/or temperature drilling system and method
US20120316788A1 (en) * 2009-10-06 2012-12-13 Schlumberger Technology Corporation a corporation Formation Testing Planning And Monitoring
US20130087388A1 (en) * 2011-10-09 2013-04-11 Intelliserv, Llc Wellbore influx detection with drill string distributed measurements
US20140123747A1 (en) * 2012-11-05 2014-05-08 Intelliserv, Llc Systems and methods for conducting pressure tests on a wellbore fluid containment system

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4090395A (en) * 1977-03-28 1978-05-23 Exxon Production Research Company Casing seal and blowout preventer tester and test method
CA2155918C (fr) * 1994-08-15 2001-10-09 Roger Lynn Schultz Systeme integre de forage et d'evaluation de puits, et methode connexe
EP1270870B1 (fr) * 2001-06-22 2006-08-16 Cooper Cameron Corporation Appareil pour tester un obturateur anti-éruption
US7207396B2 (en) 2002-12-10 2007-04-24 Intelliserv, Inc. Method and apparatus of assessing down-hole drilling conditions

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050269079A1 (en) * 2003-12-26 2005-12-08 Franklin Charles M Blowout preventer testing system
US20090236144A1 (en) * 2006-02-09 2009-09-24 Todd Richard J Managed pressure and/or temperature drilling system and method
US20120316788A1 (en) * 2009-10-06 2012-12-13 Schlumberger Technology Corporation a corporation Formation Testing Planning And Monitoring
US20130087388A1 (en) * 2011-10-09 2013-04-11 Intelliserv, Llc Wellbore influx detection with drill string distributed measurements
US20140123747A1 (en) * 2012-11-05 2014-05-08 Intelliserv, Llc Systems and methods for conducting pressure tests on a wellbore fluid containment system

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140123747A1 (en) * 2012-11-05 2014-05-08 Intelliserv, Llc Systems and methods for conducting pressure tests on a wellbore fluid containment system
US20140262269A1 (en) * 2013-03-13 2014-09-18 Superior Energy Services, L.L.C. Method to repair leaks in a cemented annulus
US9605490B2 (en) 2014-09-03 2017-03-28 Halliburton Energy Services, Inc. Riser isolation tool for deepwater wells
WO2016036362A1 (fr) * 2014-09-03 2016-03-10 Halliburton Energy Services, Inc. Outil d'isolation de tube ascenseur pour puits en eaux profondes
GB2544659B (en) * 2014-09-03 2020-12-09 Halliburton Energy Services Inc Riser isolation tool for deepwater wells
GB2544659A (en) * 2014-09-03 2017-05-24 Halliburton Energy Services Inc Riser isolation tool for deepwater wells
US10330561B2 (en) 2015-03-31 2019-06-25 Engip, LLC Method for testing for fluid leaks
US20170074748A1 (en) * 2015-03-31 2017-03-16 Engip Llc Normalized Hydrostatic Test Method
US20180052071A1 (en) * 2015-03-31 2018-02-22 Engip Llc Method and System for Determining a Fluid Leak
US11105706B2 (en) 2015-03-31 2021-08-31 Engip, LLC Hydrostatic and vibration test method for a blowout preventer
EP3277918A4 (fr) * 2015-03-31 2018-11-21 Engip LLC Système hydrostatique de mise à l'essai des vibrations destiné à la prévention des éruptions
US10267705B2 (en) * 2015-03-31 2019-04-23 HilFlo, LLC Hydrostatic and vibration test system for a blowout preventative
US10996132B2 (en) 2015-03-31 2021-05-04 ENgip, LLP Method for testing for fluid leaks
US20160290889A1 (en) * 2015-03-31 2016-10-06 Engip Llc Hydrostatic and Vibration Test System for a Blowout Preventative
US10393616B2 (en) 2015-03-31 2019-08-27 HilFlo, LLC Hydrostatic and vibration test method for a blowout preventer
WO2016161143A1 (fr) 2015-03-31 2016-10-06 Engip Llc Système hydrostatique de mise à l'essai des vibrations destiné à la prévention des éruptions
US9470082B1 (en) * 2015-05-05 2016-10-18 Backoff, Llc Blowout-preventer-stack one-trip test tool and method
US20160334300A1 (en) * 2015-05-11 2016-11-17 HilFlo, LLC Hydrostatic Pressure Test Method
US10132164B2 (en) * 2015-12-18 2018-11-20 Schlumberger Technology Corporation Systems and methods for in-situ measurements of mixed formation fluids
US10655737B2 (en) 2016-01-12 2020-05-19 Engip Llc Dual seat valve
US10113650B2 (en) 2016-01-12 2018-10-30 Engip, LLC Dual seat valve
US11725511B2 (en) 2016-03-31 2023-08-15 Schlumberger Technology Corporation Methods for in-situ multi-temperature measurements using downhole acquisition tool
US11105198B2 (en) 2016-03-31 2021-08-31 Schlumberger Technology Corporation Methods for in-situ multi-temperature measurements using downhole acquisition tool
US11041380B2 (en) 2016-05-26 2021-06-22 Metrol Technology Limited Method of pressure testing
WO2019097220A1 (fr) * 2017-11-15 2019-05-23 Ardyne Holdings Limited Perfectionnements apportés ou se rapportant à l'abandon de puits et à la récupération de fentes
NO20180592A1 (en) * 2018-04-26 2019-10-28 Scanwell Tech As Method of testing an integrity of a structure comprising a chamber, and related apparatus
NO346330B1 (en) * 2018-04-26 2022-06-07 Scanwell Tech As Method of testing an integrity of a structure comprising a chamber, and related apparatus
US11112328B2 (en) 2019-04-29 2021-09-07 Baker Hughes Oilfield Operations Llc Temperature based leak detection for blowout preventers
WO2020223203A1 (fr) * 2019-04-29 2020-11-05 Baker Hughes Oilfield Operations Llc Détection de fuite basée sur la température pour obturateurs anti-éruption
CN111395992A (zh) * 2020-03-27 2020-07-10 甘肃省建材科研设计院有限责任公司 堵漏方法
WO2022026683A1 (fr) * 2020-07-31 2022-02-03 Schlumberger Technology Corporation Système d'analyse de tampon de forage
WO2022026727A1 (fr) 2020-07-31 2022-02-03 Schlumberger Technology Corporation Système d'analyse de bouchon de trou
EP4189212A4 (fr) * 2020-07-31 2023-12-20 Services Pétroliers Schlumberger Système d'analyse de bouchon de trou
EP4189213A4 (fr) * 2020-07-31 2023-12-27 Services Pétroliers Schlumberger Système d'analyse de tampon de forage

Also Published As

Publication number Publication date
WO2014074099A1 (fr) 2014-05-15

Similar Documents

Publication Publication Date Title
US20130111985A1 (en) Method for efficient pressure and inflow testing of a fluid containment system through real time leak detection with quantification of pvt effects
US6192983B1 (en) Coiled tubing strings and installation methods
US7062960B2 (en) Blow out preventer testing apparatus
US7438135B2 (en) Method of suspending, completing and working over a well
US8899349B2 (en) Methods for determining formation strength of a wellbore
GB2555637A (en) Method of plugging and pressure testing a well
US20140123747A1 (en) Systems and methods for conducting pressure tests on a wellbore fluid containment system
US7845415B2 (en) Direct connecting downhole control system
US20130087388A1 (en) Wellbore influx detection with drill string distributed measurements
US20140027113A1 (en) Systems and methods for reducing pvt effects during pressure testing of a wellbore fluid containment system
US9359874B2 (en) Systems and methods for killing a well
US6430990B1 (en) Pipe testing apparatus
GB2337780A (en) Surface assembled spoolable coiled tubing strings
AU2014268178B2 (en) Differential pressure indicator for downhole isolation valve
US8997872B1 (en) Cap assembly for use with a tubing spool of a wellhead
US20210079750A1 (en) Method and apparatus for suspending a well
Veeningen Better well control through safe drilling margin identification, influx analysis and direct measurement method for deepwater
Haris et al. Workover and Completion Operations in East Java Sour Gas Field, Indonesia
US10280740B2 (en) Sandface liner with power, control and communication link via a tie back string
US20230110038A1 (en) Methods and tools for determining bleed-off pressure after well securement jobs
Rahmani et al. Full-scale testing shows advantages of a quantitative approach to interpreting inflow tests
Garrison et al. Reinventing Deepwater Exploratory Testing
Fleckenstein et al. Annular Casing Seal Test Method
Buchanan Completion System Enabling Simultaneous Injection and Production from Alternating Transverse Fractures in a Horizontal Well
RU2338058C1 (ru) Скважинная установка гарипова

Legal Events

Date Code Title Description
AS Assignment

Owner name: INTELLISERV, L.L.C., TEXAS

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:VEENINGEN, DANIEL MARCO;REEL/FRAME:029842/0312

Effective date: 20121108

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION