US20110108281A1 - Method of providing buoyancy for a drilling riser - Google Patents

Method of providing buoyancy for a drilling riser Download PDF

Info

Publication number
US20110108281A1
US20110108281A1 US12/590,509 US59050909A US2011108281A1 US 20110108281 A1 US20110108281 A1 US 20110108281A1 US 59050909 A US59050909 A US 59050909A US 2011108281 A1 US2011108281 A1 US 2011108281A1
Authority
US
United States
Prior art keywords
passageways
flotation
drilling riser
modules
lengthwise
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/590,509
Inventor
Benton Frederick Baugh
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
REELPOWER LICENSING CORP
TULSA POWER LICENSING CORP
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US12/590,509 priority Critical patent/US20110108281A1/en
Assigned to MEDALLION CAPITAL, INC. reassignment MEDALLION CAPITAL, INC. SECURITY AGREEMENT Assignors: TULSA POWER, INC.
Assigned to TULSA POWER LICENSING CORP. reassignment TULSA POWER LICENSING CORP. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BAUGH, BENTON F.
Assigned to TEXAS CAPITAL BANK, NATIONAL ASSOCIATION reassignment TEXAS CAPITAL BANK, NATIONAL ASSOCIATION SECURITY AGREEMENT Assignors: TULSA POWER LICENSING CORP.
Assigned to MEDALLION CAPITAL, INC. reassignment MEDALLION CAPITAL, INC. CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNOR PREVIOUSLY RECORDED ON REEL 023720 FRAME 0467. ASSIGNOR(S) HEREBY CONFIRMS THE TULSA POWER, INC.. Assignors: TULSA POWER LICENSING CORP.
Publication of US20110108281A1 publication Critical patent/US20110108281A1/en
Assigned to REELPOWER LICENSING CORP. reassignment REELPOWER LICENSING CORP. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BAUGH, BENTON F.
Assigned to TULSA POWER LICENSING CORP. reassignment TULSA POWER LICENSING CORP. RELEASE OF SECURITY INTEREST IN PATENTS Assignors: MEDALLION CAPITAL, INC.
Assigned to TEXAS CAPITAL BANK, NATIONAL ASSOCIATION reassignment TEXAS CAPITAL BANK, NATIONAL ASSOCIATION SECURITY AGREEMENT Assignors: TULSA POWER LICENSING CORP.
Assigned to TULSA POWER LICENSING CORP. reassignment TULSA POWER LICENSING CORP. CORRECTIVE DOCUMENT TO CORRECT ASSIGNMENT RECORDED AT REEL/FRAME 029483/0218 Assignors: TULSA POWER LICENSING CORP.
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/01Risers
    • E21B17/012Risers with buoyancy elements

Definitions

  • This invention relates to the general subject of providing buoyancy on sections of riser pipe for subsea drilling systems to minimize the in water weight of the drilling riser and to provide guidance for outside lines.
  • the field of this invention is that drilling risers for deep water blowout preventer systems are major pieces of capital equipment landed on the ocean floor in order to provide a conduit for the drill pipe and drilling mud while also providing pressure protection while drilling holes deep into the earth for the production of oil and gas.
  • the typical blowout preventer stacks have an 183 ⁇ 4 inch bore and are usually of 10,000 psi working pressure.
  • the blowout preventer stack assembly weighs in the range of five hundred to eight hundred thousand pounds. It is typically divided into a lower blowout preventer stack and a lower marine riser package.
  • the lower blowout preventer stack includes a connector for connecting to the wellhead at the bottom on the seafloor and contains several individual ram type blowout preventer assemblies, which will close on various pipe sizes and in some cases, will close on an open hole with what are called blind rams. Characteristically there is an annular preventer at the top, which will close on any pipe size or close on the open hole.
  • the lower marine riser package typically includes a connector at its base for connecting to the top of the lower blowout preventer stack, it contains a single annular preventer for closing off on any piece of pipe or the open hole, a flex joint, and a connection to a riser pipe which extends to the drilling vessel at the surface.
  • the purpose of the separation between the lower blowout preventer stack and the lower marine riser package is that the annular blowout preventer on the lower marine riser package is the preferred and most often used pressure control assembly. When it is used and either has a failure or is worn out, it can be released and retrieved to the surface for servicing while the lower blowout preventer stack maintains pressure competency at the wellhead on the ocean floor.
  • the riser pipe extending to the surface is typically a 21 inch O.D. pipe with a bore larger than the bore of the blowout preventer stack. It is a low pressure pipe and will control the mud flow which is coming from the well up to the rig floor, but will not contain the 10,000-15,000 psi that the blowout preventer stack will contain. Whenever high pressures must be communicated back to the surface for well control procedures, smaller pipes on the outside of the drilling riser, called the choke line and the kill line, provide this function. These will typically have the same working pressure as the blowout preventer stack and rather than have an 183 ⁇ 4-20 inch bore, they will have a 3-4 inch bore. There may be additional lines outside the primary pipe for delivering hydraulic fluid for control of the blowout preventer stack or boosting the flow of drilling mud back up through the drilling riser.
  • the object of this invention is to provide a method of providing flotation as a full circle with the structural benefits inherent is that shape.
  • a second object of this invention is provide flotation which provides the structure for aligning and positioning the outside lines.
  • a third object of this invention is to provide a working conduit from the drilling rig to lower instrumentation to various locations along the riser for determining current induced movement of the riser.
  • Another object of the present invention is to provide a working conduit from the drilling rig at the surface to blowout preventer stack at the sea floor to provide for control functions to occur at the blowout preventer stack.
  • FIG. 1 is a view of a deepwater drilling system using the present invention
  • FIG. 2 is a more detailed view of the riser and blowout preventer stack as seen in FIG. 1
  • FIG. 3 is a view of a portion of a conventional drilling riser.
  • FIG. 4 shows a perspective view of a pair of conventional buoyancy modules.
  • FIG. 5 is a view of a portion of a drilling riser utilizing the buoyancy of this invention.
  • FIG. 6 is a half section of the flotation being installed on a riser joint.
  • FIG. 7 is a half section of a riser joint with all the flotation loaded.
  • FIG. 8 is a half section showing an outside fluid line being installed in a conduit of the buoyancy.
  • FIG. 9 is a half section of a section of drilling riser using this invention.
  • FIG. 10 is a half section through lines “ 10 - 10 ” of FIG. 14 .
  • FIG. 11 is an end view of a conventional clamp.
  • FIG. 12 is a half section taken along lines “ 12 - 12 ” of FIG. 11 .
  • FIG. 13 is an end view of a conventional clamp similar to view 11 , but being partially made up.
  • FIG. 14 is a half section of a clamp of this invention taken along lines “ 14 - 14 ” of FIG. 10 .
  • FIG. 15 is an end view of a clamp of this drilling riser showing the test lines.
  • FIG. 16 is a graph illustrating the typical pressure decline curve of a freshly pressure line.
  • FIG. 1 a view of a complete system for drilling subsea wells 20 is shown in order to illustrate the utility of the present invention.
  • the drilling riser 22 is shown with a central pipe 24 , outside fluid lines 26 , and control lines 28 .
  • a flex joint 30 Below the drilling riser 22 is a flex joint 30 , lower marine riser package 32 , lower blowout preventer stack 34 and wellhead 36 landed on the seafloor 38 .
  • the lower Blowout Preventer stack 22 generally comprises a lower hydraulic connector for connecting to the subsea wellhead system 36 , usually 4 or 5 ram style Blowout Preventers, an annular preventer, and an upper mandrel for connection by the connector on the lower marine riser package 32 .
  • a choke and kill (C&K) connector 50 and a pipe 52 which is generally illustrative of a choke or kill line.
  • Pipe 52 goes down to valves 54 and 56 which provide flow to or from the central bore of the blowout preventer stack as may be appropriate from time to time.
  • a kill line will enter the bore of the Blowout Preventers below the lowest ram and has the general function of pumping heavy fluid to the well to overburden the pressure in the bore or to “kill” the pressure. The general implication of this is that the heavier mud will not be circulated, but rather forced into the formations.
  • a choke line will typically enter the well bore above the lowest ram and is generally intended to allow circulation to circulate heavier mud into the well to regain pressure control of the well.
  • Normal drilling circulation is the mud pumps 60 taking drilling mud 62 from tank 64 .
  • the drilling mud will be pumped up a standpipe 66 and down the upper end 68 of the drill pipe 46 . It will be pumped down the drill pipe 46 , out the drill bit 44 , and return up the annular area 70 between the outside of the drill pipe 21 and the bore of the hole being drilled, up the bore of the casing 42 , through the subsea wellhead system 36 , the lower blowout preventer stack 34 , the lower marine riser package 32 , up the drilling riser 24 , out a bell nipple 72 and back into the mud tank 64 .
  • the thin walled drilling riser 24 is typically not able to withstand the pressures involved. Rather than making the wall thickness of the relatively large bore drilling riser thick enough to withstand the pressure, the flow is diverted to a choke line 26 . It is more economic to have a relatively thick wall in a small pipe to withstand the higher pressures than to have the proportionately thick wall in the larger riser pipe.
  • one of the annular or ram Blowout Preventers are closed around the drill pipe and the flow coming up the annular area around the drill pipe is diverted out through choke valve 54 into the pipe 52 .
  • the flow passes up through C&K connector 50 , up pipe 26 which is attached to the outer diameter of the riser 24 , through choking means illustrated at 74 , and back into the mud tanks 64 .
  • a cable or hose 28 coming across a sheave 80 from a reel 82 on the vessel 84 is shown characteristically entering the top of the lower marine riser package.
  • These cables typically carry hydraulic, electrical, multiplex electrical, or fiber optic signals. Typically there are at least two of these systems, which are characteristically painted yellow and blue.
  • the cables or hoses 28 enter the top of the lower marine riser package 32 , they typically enter the top of control pod to deliver their supply or signals.
  • a series of accumulators are located on the lower marine riser package 32 or the lower Blowout Preventer stack 34 to store hydraulic fluid under pressure until needed.
  • Connector 90 at the bottom is hydraulically operated to provide a connection between the lower blowout preventer stack 34 and the subsea wellhead system 36 as shown in FIG. 1 .
  • Hydraulic connector 92 provides a connection between the lower marine riser package 32 and mandrel 94 on the lower blowout preventer stack 34 .
  • Control panel 96 is shown to control the reel 82 .
  • Centralizer 98 would be used to control the position of the riser as it is being pulled in currents to prevent it from be pushed into the side of the rotary table by the currents.
  • Fairings 100 can be used to provide a better flow profile and reduce the drag forces on the riser.
  • Winch 102 and chain 104 indicate that the fairings are of a “run through” type which means they are independently supported from the drilling rig, can be run after the riser is in the water, and can remain in place when most of the riser is retrieved, rather than the style which are fixed to individual riser joints.
  • FIG. 3 the connection of two sections of conventional drilling riser 110 is seen.
  • an upper flange 114 is seen on the upper end of a conventional riser joint 112 . It is connected to the flange on the lower end of the adjacent conventional riser joint 116 by lower flange 118 and a multiplicity of bolts 120 .
  • the pipe 122 between the upper flange 114 and the lower flange 118 on the same riser joint is typically of a 21 ′′ outer diameter, with a varying wall thickness depending primarily on water depth and the resulting tensile loadings.
  • All risers typically will have a choke line 124 and a kill line 126 as outside fluid lines, and may also have hydraulic supply lines and mud flow boost lines. Each of these lines are the typical 70 ft. in length as is the effective length of the conventional drilling riser.
  • Buoyancy module sections 130 and 132 are shown attached to the lower end of the conventional riser joint 116 and buoyancy modules 134 and 136 are shown attached to the upper end of conventional riser joint 112 .
  • the conventional riser joints are 70 ft. long and the flotation modules are conventionally 129 ′′ long. Six sections of the 129′′ long flotation are attached to each riser joint, leaving a gap of 60′′ or 5 feet in the area of the connection.
  • the space on the upper end of conventional riser joint 112 is used for the insertion of support dogs when running the riser.
  • the larger space on the bottom of the adjacent riser joint 116 is used for the insertion of a hydraulic make-up wrench when running the riser. It is conventional to use 6 support dogs, giving 6 spaces for bolts between the outside fluid lines.
  • FIG. 4 the profile 140 inside the buoyancy half circle module sections is shown.
  • bands 142 and 144 molded inside the modules which provide for a known contact with the pipe when the steel pipe is flexed one way or the other way.
  • There are three notches 146 , 148 , and 150 which allow the flotation modules to be installed onto the assembly when the outside fluid lines are in place.
  • There are notches 152 and 154 which allow the control lines 28 to be stored and clamped in place.
  • the weak points in these modules are a load on the center back, causing a tensile failure at 158 and a cantilever or diving board type failure at 159 .
  • FIG. 5 a similar section of riser 160 of the present invention is shown as was shown in FIG. 3 comprising of a lower riser section 162 and an upper riser section 164 .
  • the upper riser section 164 becomes lower riser section 162 and a fresh riser section becomes upper riser section 164 .
  • Lower riser section 162 has buoyancy modules 166 and 168 .
  • Upper riser section 164 has buoyancy modules 170 and 172 .
  • All buoyancy module sections 166 - 172 are a one piece full circle instead of half circle as shown in FIG. 4 , but approximately one half as long as the half sections on the conventional drilling riser.
  • Buoyancy module 166 is specific for the top location of the riser with slots or windows 173 for the insertion of support dogs.
  • the slots or windows 173 (and dogs to be inserted) are tall and narrow rather than flat to minimize circumferential space required for the dog support. This change will allow adequate roller contact in this area without having to have rotatable tracks.
  • Buoyancy module 164 is specific for the bottom location on each riser joint as hole 174 allows access to a single bolt 176 to make up a novel connection as discussed hereinafter. The nature of these two modules reduces the gap at the connection between the riser joints from 5 feet to a small chamfer 175 the size of the chamfer on all other flotation modules.
  • Buoyancy modules 168 and 172 are identical and are identical of all intermediate buoyancy modules on the riser joint. Construction of the modules as full circles of one half the length substantially increases the strength of the modules against roller loading failure. Full circle is much stronger than half circle, and half length is much stronger than double length due to shorter bending moment.
  • FIG. 6 a riser joint 200 is shown with the flotation being installed.
  • Central pipe 202 is shown with an upper flange 204 , but no lower flange.
  • Two loading stands 206 and 208 are shown.
  • Circular flotation modules 210 and 212 are shown slipped over the lower end 214 of the riser joint 200 which has no flange. At this time the lower end 214 will be picked up and the buoyancy modules 210 and 212 will be slid down to buoyancy module 216 and tab 218 will engage socket 220 to provide a known orientation between adjacent buoyancy modules. This will be continued until all buoyancy modules are installed and a lower support flange is bolted in place. If will be described in greater detail in FIG. 9 .
  • the riser joint 200 is completely outfitted with buoyancy modules and a lower support flange 222 .
  • a complete passageway 224 is shown from the upper end of the riser joint to the lower joint.
  • Passageway 224 represents 5 passageways at 60 degree spacing, with the sixth position having the tabs 218 , sockets 220 , and bolting as will be seen.
  • an outside fluid line 26 such as a choke or kill line is being slid into one of the passageways 224 .
  • Stabilizing centralizers 230 are installed onto the outside fluid line 26 to stabilize it within the passageways 224 , eliminating the conventional requirement for special clamps which are required to restrain the outside fluid lines.
  • Passageway 240 has outside fluid line 242 installed with a retaining pin 243 installed into a hole in the side of flange 204 to engage groove 244 to fix the outside fluid line 242 in place.
  • Stabilizing centralizers 230 are shown to stabilize fluid line 242 within passageway 240 .
  • Seals 246 seal outside fluid line 242 to outside fluid line 248 as will be discussed in more detail in FIG. 14 .
  • Passageway 250 has not received an outside fluid line, but rather is shown as providing a passageway for other services. These services can be to lower instrumentation 252 on a wire 254 such as is shown to measure vortex induced vibration in a riser. Alternately passageway 250 can provide a passageway all the way to the bottom like the vacuum tubes used in banks. A hose can be lowered down to deliver hydraulic fluid. A control connector can be lowered on a control line to provide backup control for a blowout preventer stack in case of controls difficulties. A “Go-Devil” on simple weight can be dropped to actuate a single function in an emergency situation. Basically passageway 250 becomes a utility passageway for anything which needs to be done along or at the bottom of the riser.
  • a receptacle 260 (See also FIG. 14 ) at the upper end of lower riser pipe 262 is engaged by nose 264 on the lower end of upper riser pipe 266 .
  • Seals 268 seal between receptacle 260 and nose 264 .
  • the upper end of lower riser pipe 262 has a clamping profile 270 and the lower end of upper riser pipe 266 has a clamping profile 272 .
  • Clamp segments 274 engage the clamping profiles 270 and 272 .
  • Tension band 276 urges clamp segments 274 into engagement with clamping profiles 270 and 272 to secure the connection.
  • the clamp segments 274 as shown in FIG. 9 are shown here to be four clamping segments of differing length 280 , 282 , 284 , and 286 .
  • Each segment is constrained to move radially into contract with the clamping profiles 270 and 272 as shown in FIG. 9 by keyways 290 , 292 , 294 , and 296 , respectively.
  • the tension band 276 is shown to be made of four section 300 , 302 . 304 , and 306 . They are hinged together by hinge pins 310 , 312 , and 314 . At the fourth connection a double pin arrangement is used. A threaded pin 320 is engaged by bolt 322 . A non-threaded pin 324 is engaged by shoulder 326 on bolt 322 .
  • a two section clamp 350 has clamp halves 352 and 354 tightened on clamp hubs 356 by bolts 358 .
  • the inner diameter 360 is intended to be pulled to be concentric with diameter 362 of the clamp hubs 356 .
  • the engagement of the clamp halves is shown to be on a taper 370 which has approximately a 25 degree slope. It is literally a wedge moving onto the clamp hubs.
  • FIG. 13 a view similar to FIG. 11 is shown, but with the clamps about 1 ⁇ 4′′ from full make-up.
  • Clamp sections 352 and 354 are actually touching clamp hubs 356 only at areas 380 and 382 respectively.
  • Little contact is made at areas 384 and 386 .
  • the situation is that of a wedge being drug sideways onto the clamp hubs.
  • the result of this type make-up is that the loading in the general areas of 380 and 382 will be high and the loading at 384 and 386 will be low.
  • the clamp sections of this type are struck with a sledge hammer at locations 388 and 390 to jar the clamp sections into a position of more uniform loading around the circumference.
  • make-up onto the tapered clamp hubs 270 and 272 of FIG. 9 is constrained to be done radially rather than sliding around the wedge surface.
  • the outer surface 400 of the clamping segments 280 , 282 , 284 , and 286 is a simple cylindrical surface. Outer surface 400 is engaged by simple cylindrical surface 402 of tension band sections 300 , 302 , 304 , and 306 . As the tension band is pulled to a smaller diameter by bolt 322 , the tension band segments 300 , 302 , 304 , and 306 slide circumferentially around the clamping segments 280 , 282 , 284 , and 284 .
  • the load on the clamping segments 282 and 284 will be less than the load on the clamping segments 280 and 286 by the friction on the back of clamping segments 280 and 286 . If the coefficient of friction is 0.15, the unit loadings on the clamp segments will be reduced by 15%, rather than the high loses seen by the wedging action of a conventional clamp.
  • the ratio of the loading area to the ratio of clamping area has been adjusted.
  • the loading area is shown on the left side of the figure and is divided to 80 degrees and 100 degrees.
  • double seals 246 on outside fluid line 242 are shown as seals 410 and 412 with a test port 414 located between seals 410 and 412 and test pressure connecting lines 416 .
  • Each of the outside fluid lines will have similar seals, test ports and test pressure connecting lines.
  • Seals 268 on upper riser pipe 266 are shown as seals 420 and 422 with a test port 424 located between seals 420 and 422 and a test pressure connecting line 426 .
  • Flange 204 is shown being supported by dogs 430 which are extended from a riser spider (not shown).
  • test pressure lines 440 come from each of the test ports on each of the outside fluid lines and the central pipe connections. Each of the lines go to double check valves 442 and are in turn directed to fitting 444 . In this way when a test pressure device is attached to fitting 444 , all of the hydraulic lines can be quickly tested to the maximum pressure which can be withstood by any of the lines. As a small area will be exposed to pressure, a higher pressure can be delivered to the test port than the lowest pressure pipe can withstand, likely twice as high as unpressured areas next to the seal area will tend to reinforce the test area.
  • Test pressure fitting 444 does not have a check valve in it such that pressure in any of the test lines 440 is solely sealed by a pair of check valves at 444 . If the check valves at 444 fail for any reason, the resultant leak will not be able to enter another set of check valves and back pressure any of the other fittings, but rather simply goes into the sea water.
  • make-up of the connection is now controlled by a single bolt, empirical studies can be done to determine the relationship of torque and turn of a properly made up connection.
  • the relationship of torque and turn can be input into a computer and measured each time a connection is made. When this is measured, it can be quickly compared to historical connections and determined if it is a proper make-up. If the make-up curve is too flat, it will likely mean that the connection is failing. If the make-up curve is too steep, it likely means that the bolt is galling. Rather than the 15 minutes required to make up a conventional 6 bolt connection, the single bolt make-up can be likely done within 1 minute and will have a computer generated confirmation of the quality of the make-up.
  • test pressure device During the 1 minute to make-up the connection, another employee can attach a test pressure device to the fitting 444 and do a 1 minute test on the various seals. In the one minute, the pressure in the test ports will not stabilize due to temperature cooling. However, they will decline in a predictable fashion and a computer will be able to predict that the seals have quality sealing. If desired, the employee can wait 3 to 5 minutes for confirmation that the pressure is stable, or has gone “flatline”.
  • Line 450 indicates that the pressure is being rapidly increased from zero to a maximum amount quickly.
  • a valve is shut off to block the supply.
  • the liquid and some air in the lines have been quickly pressurized and therefore heated some.
  • the pressure drops some until it stabilizes or goes “flatline”.
  • Line 454 is what a typical pressure curve looks like as it goes “flatline”.
  • At point 456 on this curve it has gone “flatline” after a period of time, i.e. 3 minutes.
  • Lines 458 and 460 show the limits of what the pressure curve is likely to look like during successful testing.
  • Line 462 shows a time during this period, i.e. 1 minute after pressurizing. If curve 458 and 460 have been determined by real life experience and at time 462 the curve is within the limits, there is a high degree of assurance that the test will be a successful test. If this data is fed into a computer, at time 462 the computer can determine that it is likely to be a successful test and indicate that operations can continue. The indication can be by a variety of means such as a printed report or a green light for GO and a red light for STOP.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

The method of providing flotation modules on subsea drilling riser joints comprising providing flotation modules as a full circle, installing said flotation modules sequentially onto the end of the central pipe of said drilling riser joints in a desired orientation, providing passageways through said flotation modules which extend from one end of said subsea drilling riser joints to the other end of said drilling riser joints.

Description

    TECHNICAL FIELD
  • This invention relates to the general subject of providing buoyancy on sections of riser pipe for subsea drilling systems to minimize the in water weight of the drilling riser and to provide guidance for outside lines.
  • CROSS-REFERENCE TO RELATED APPLICATIONS
  • Not applicable.
  • STATEMENT REGARDING FEDERALLY SPONSORED RESEARCH OR DEVELOPMENT
  • Not applicable
  • REFERENCE TO A “MICROFICHE APPENDIX”
  • Not applicable
  • BACKGROUND OF THE INVENTION
  • The field of this invention is that drilling risers for deep water blowout preventer systems are major pieces of capital equipment landed on the ocean floor in order to provide a conduit for the drill pipe and drilling mud while also providing pressure protection while drilling holes deep into the earth for the production of oil and gas. The typical blowout preventer stacks have an 18¾ inch bore and are usually of 10,000 psi working pressure. The blowout preventer stack assembly weighs in the range of five hundred to eight hundred thousand pounds. It is typically divided into a lower blowout preventer stack and a lower marine riser package.
  • The lower blowout preventer stack includes a connector for connecting to the wellhead at the bottom on the seafloor and contains several individual ram type blowout preventer assemblies, which will close on various pipe sizes and in some cases, will close on an open hole with what are called blind rams. Characteristically there is an annular preventer at the top, which will close on any pipe size or close on the open hole.
  • The lower marine riser package typically includes a connector at its base for connecting to the top of the lower blowout preventer stack, it contains a single annular preventer for closing off on any piece of pipe or the open hole, a flex joint, and a connection to a riser pipe which extends to the drilling vessel at the surface.
  • The purpose of the separation between the lower blowout preventer stack and the lower marine riser package is that the annular blowout preventer on the lower marine riser package is the preferred and most often used pressure control assembly. When it is used and either has a failure or is worn out, it can be released and retrieved to the surface for servicing while the lower blowout preventer stack maintains pressure competency at the wellhead on the ocean floor.
  • The riser pipe extending to the surface is typically a 21 inch O.D. pipe with a bore larger than the bore of the blowout preventer stack. It is a low pressure pipe and will control the mud flow which is coming from the well up to the rig floor, but will not contain the 10,000-15,000 psi that the blowout preventer stack will contain. Whenever high pressures must be communicated back to the surface for well control procedures, smaller pipes on the outside of the drilling riser, called the choke line and the kill line, provide this function. These will typically have the same working pressure as the blowout preventer stack and rather than have an 18¾-20 inch bore, they will have a 3-4 inch bore. There may be additional lines outside the primary pipe for delivering hydraulic fluid for control of the blowout preventer stack or boosting the flow of drilling mud back up through the drilling riser.
  • For the 50 years in which drilling risers have been utilized, there has been a stepwise evolution of risers generally solving sequential problems by adding one more component each time. That outside or auxiliary lines were added before flotation has meant that inventors using obvious techniques have added half or semi-circular sections of buoyancy to the risers. The half or semi-circular sections have had portions removed to go over clamps to support the outside or auxiliary lines and have been of a relatively weak structural shape. These disadvantages have been accepted as what you have to do to add flotation to the riser joints.
  • BRIEF SUMMARY OF THE INVENTION
  • The object of this invention is to provide a method of providing flotation as a full circle with the structural benefits inherent is that shape.
  • A second object of this invention is provide flotation which provides the structure for aligning and positioning the outside lines.
  • A third object of this invention is to provide a working conduit from the drilling rig to lower instrumentation to various locations along the riser for determining current induced movement of the riser.
  • Another object of the present invention is to provide a working conduit from the drilling rig at the surface to blowout preventer stack at the sea floor to provide for control functions to occur at the blowout preventer stack.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 is a view of a deepwater drilling system using the present invention
  • FIG. 2 is a more detailed view of the riser and blowout preventer stack as seen in FIG. 1
  • FIG. 3 is a view of a portion of a conventional drilling riser.
  • FIG. 4 shows a perspective view of a pair of conventional buoyancy modules.
  • FIG. 5 is a view of a portion of a drilling riser utilizing the buoyancy of this invention.
  • FIG. 6 is a half section of the flotation being installed on a riser joint.
  • FIG. 7 is a half section of a riser joint with all the flotation loaded.
  • FIG. 8 is a half section showing an outside fluid line being installed in a conduit of the buoyancy.
  • FIG. 9 is a half section of a section of drilling riser using this invention.
  • FIG. 10 is a half section through lines “10-10” of FIG. 14.
  • FIG. 11 is an end view of a conventional clamp.
  • FIG. 12 is a half section taken along lines “12-12” of FIG. 11.
  • FIG. 13 is an end view of a conventional clamp similar to view 11, but being partially made up.
  • FIG. 14 is a half section of a clamp of this invention taken along lines “14-14” of FIG. 10.
  • FIG. 15 is an end view of a clamp of this drilling riser showing the test lines.
  • FIG. 16 is a graph illustrating the typical pressure decline curve of a freshly pressure line.
  • DETAILED DESCRIPTION OF THE INVENTION
  • Referring now to FIG. 1, a view of a complete system for drilling subsea wells 20 is shown in order to illustrate the utility of the present invention. The drilling riser 22 is shown with a central pipe 24, outside fluid lines 26, and control lines 28.
  • Below the drilling riser 22 is a flex joint 30, lower marine riser package 32, lower blowout preventer stack 34 and wellhead 36 landed on the seafloor 38.
  • Below the wellhead 36, it can be seen that a hole was drilled for a first casing string, that string 40 was landed and cemented in place, a hole drilled thru the first string for a second string, the second string 42 cemented in place, and a hole is being drilled for a third casing string by drill bit 44 on drill string 46.
  • The lower Blowout Preventer stack 22 generally comprises a lower hydraulic connector for connecting to the subsea wellhead system 36, usually 4 or 5 ram style Blowout Preventers, an annular preventer, and an upper mandrel for connection by the connector on the lower marine riser package 32.
  • Below outside fluid line 26 is a choke and kill (C&K) connector 50 and a pipe 52 which is generally illustrative of a choke or kill line. Pipe 52 goes down to valves 54 and 56 which provide flow to or from the central bore of the blowout preventer stack as may be appropriate from time to time. Typically a kill line will enter the bore of the Blowout Preventers below the lowest ram and has the general function of pumping heavy fluid to the well to overburden the pressure in the bore or to “kill” the pressure. The general implication of this is that the heavier mud will not be circulated, but rather forced into the formations. A choke line will typically enter the well bore above the lowest ram and is generally intended to allow circulation to circulate heavier mud into the well to regain pressure control of the well.
  • Normal drilling circulation is the mud pumps 60 taking drilling mud 62 from tank 64. The drilling mud will be pumped up a standpipe 66 and down the upper end 68 of the drill pipe 46. It will be pumped down the drill pipe 46, out the drill bit 44, and return up the annular area 70 between the outside of the drill pipe 21 and the bore of the hole being drilled, up the bore of the casing 42, through the subsea wellhead system 36, the lower blowout preventer stack 34, the lower marine riser package 32, up the drilling riser 24, out a bell nipple 72 and back into the mud tank 64.
  • During situations in which an abnormally high pressure from the formation has entered the well bore, the thin walled drilling riser 24 is typically not able to withstand the pressures involved. Rather than making the wall thickness of the relatively large bore drilling riser thick enough to withstand the pressure, the flow is diverted to a choke line 26. It is more economic to have a relatively thick wall in a small pipe to withstand the higher pressures than to have the proportionately thick wall in the larger riser pipe.
  • When higher pressures are to be contained, one of the annular or ram Blowout Preventers are closed around the drill pipe and the flow coming up the annular area around the drill pipe is diverted out through choke valve 54 into the pipe 52. The flow passes up through C&K connector 50, up pipe 26 which is attached to the outer diameter of the riser 24, through choking means illustrated at 74, and back into the mud tanks 64.
  • On the opposite side of the drilling riser 24 is shown a cable or hose 28 coming across a sheave 80 from a reel 82 on the vessel 84. The cable 28 is shown characteristically entering the top of the lower marine riser package. These cables typically carry hydraulic, electrical, multiplex electrical, or fiber optic signals. Typically there are at least two of these systems, which are characteristically painted yellow and blue. As the cables or hoses 28 enter the top of the lower marine riser package 32, they typically enter the top of control pod to deliver their supply or signals. When hydraulic supply is delivered, a series of accumulators are located on the lower marine riser package 32 or the lower Blowout Preventer stack 34 to store hydraulic fluid under pressure until needed.
  • Referring now to FIG. 2, a portion of the complete system for drilling subsea wells 20 is shown in greater detail for better clarity. Connector 90 at the bottom is hydraulically operated to provide a connection between the lower blowout preventer stack 34 and the subsea wellhead system 36 as shown in FIG. 1. Hydraulic connector 92 provides a connection between the lower marine riser package 32 and mandrel 94 on the lower blowout preventer stack 34.
  • Control panel 96 is shown to control the reel 82. Centralizer 98 would be used to control the position of the riser as it is being pulled in currents to prevent it from be pushed into the side of the rotary table by the currents. Fairings 100 can be used to provide a better flow profile and reduce the drag forces on the riser. Winch 102 and chain 104 indicate that the fairings are of a “run through” type which means they are independently supported from the drilling rig, can be run after the riser is in the water, and can remain in place when most of the riser is retrieved, rather than the style which are fixed to individual riser joints.
  • Referring now to FIG. 3, the connection of two sections of conventional drilling riser 110 is seen. On the upper end of a conventional riser joint 112 an upper flange 114 is seen. It is connected to the flange on the lower end of the adjacent conventional riser joint 116 by lower flange 118 and a multiplicity of bolts 120. The pipe 122 between the upper flange 114 and the lower flange 118 on the same riser joint is typically of a 21″ outer diameter, with a varying wall thickness depending primarily on water depth and the resulting tensile loadings. All risers typically will have a choke line 124 and a kill line 126 as outside fluid lines, and may also have hydraulic supply lines and mud flow boost lines. Each of these lines are the typical 70 ft. in length as is the effective length of the conventional drilling riser.
  • Buoyancy module sections 130 and 132 are shown attached to the lower end of the conventional riser joint 116 and buoyancy modules 134 and 136 are shown attached to the upper end of conventional riser joint 112. The conventional riser joints are 70 ft. long and the flotation modules are conventionally 129″ long. Six sections of the 129″ long flotation are attached to each riser joint, leaving a gap of 60″ or 5 feet in the area of the connection. The space on the upper end of conventional riser joint 112 is used for the insertion of support dogs when running the riser. The larger space on the bottom of the adjacent riser joint 116 is used for the insertion of a hydraulic make-up wrench when running the riser. It is conventional to use 6 support dogs, giving 6 spaces for bolts between the outside fluid lines.
  • When the drilling riser sees side currents and rollers need to contact the riser assembly to keep it centralized as it is pulled, these long gaps at the connections can be a significant problem. This problem has been addressed in a separate patent application for the Thunderhorse PDQ drilling rig by adding a rotating track, which in one position provides a necessary track for roller and at another rotational orientation provides access to the support shoulders and access for insertion of the wrenches.
  • Referring now to FIG. 4, the profile 140 inside the buoyancy half circle module sections is shown. There are bands 142 and 144 molded inside the modules which provide for a known contact with the pipe when the steel pipe is flexed one way or the other way. There are three notches 146, 148, and 150 which allow the flotation modules to be installed onto the assembly when the outside fluid lines are in place. There are notches 152 and 154 which allow the control lines 28 to be stored and clamped in place. There are recesses 156 on each end to allow for clamps which restrain the outside fluid lines 26, and secure the axial position of the buoyancy modules such that they do not block the wrench space or the space for the support dogs.
  • The weak points in these modules are a load on the center back, causing a tensile failure at 158 and a cantilever or diving board type failure at 159.
  • Referring now to FIG. 5, a similar section of riser 160 of the present invention is shown as was shown in FIG. 3 comprising of a lower riser section 162 and an upper riser section 164. As can be appreciated, when the riser is lowered 70 ft. during the running operations, the upper riser section 164 becomes lower riser section 162 and a fresh riser section becomes upper riser section 164. Lower riser section 162 has buoyancy modules 166 and 168. Upper riser section 164 has buoyancy modules 170 and 172.
  • All buoyancy module sections 166-172 are a one piece full circle instead of half circle as shown in FIG. 4, but approximately one half as long as the half sections on the conventional drilling riser.
  • Buoyancy module 166 is specific for the top location of the riser with slots or windows 173 for the insertion of support dogs. The slots or windows 173 (and dogs to be inserted) are tall and narrow rather than flat to minimize circumferential space required for the dog support. This change will allow adequate roller contact in this area without having to have rotatable tracks.
  • Buoyancy module 164 is specific for the bottom location on each riser joint as hole 174 allows access to a single bolt 176 to make up a novel connection as discussed hereinafter. The nature of these two modules reduces the gap at the connection between the riser joints from 5 feet to a small chamfer 175 the size of the chamfer on all other flotation modules.
  • Buoyancy modules 168 and 172 are identical and are identical of all intermediate buoyancy modules on the riser joint. Construction of the modules as full circles of one half the length substantially increases the strength of the modules against roller loading failure. Full circle is much stronger than half circle, and half length is much stronger than double length due to shorter bending moment.
  • Referring now to FIG. 6, a riser joint 200 is shown with the flotation being installed. Central pipe 202 is shown with an upper flange 204, but no lower flange. Two loading stands 206 and 208 are shown. Circular flotation modules 210 and 212 are shown slipped over the lower end 214 of the riser joint 200 which has no flange. At this time the lower end 214 will be picked up and the buoyancy modules 210 and 212 will be slid down to buoyancy module 216 and tab 218 will engage socket 220 to provide a known orientation between adjacent buoyancy modules. This will be continued until all buoyancy modules are installed and a lower support flange is bolted in place. If will be described in greater detail in FIG. 9.
  • Referring now to FIG. 7, the riser joint 200 is completely outfitted with buoyancy modules and a lower support flange 222. A complete passageway 224 is shown from the upper end of the riser joint to the lower joint. Passageway 224 represents 5 passageways at 60 degree spacing, with the sixth position having the tabs 218, sockets 220, and bolting as will be seen.
  • Referring now to FIG. 8, an outside fluid line 26 such as a choke or kill line is being slid into one of the passageways 224. Stabilizing centralizers 230 are installed onto the outside fluid line 26 to stabilize it within the passageways 224, eliminating the conventional requirement for special clamps which are required to restrain the outside fluid lines.
  • Referring now to FIG. 9, a half section is shown of the riser joint of FIG. 5 thru two of the passageways 224. Passageway 240 has outside fluid line 242 installed with a retaining pin 243 installed into a hole in the side of flange 204 to engage groove 244 to fix the outside fluid line 242 in place. Stabilizing centralizers 230 are shown to stabilize fluid line 242 within passageway 240. Seals 246 seal outside fluid line 242 to outside fluid line 248 as will be discussed in more detail in FIG. 14.
  • Passageway 250 has not received an outside fluid line, but rather is shown as providing a passageway for other services. These services can be to lower instrumentation 252 on a wire 254 such as is shown to measure vortex induced vibration in a riser. Alternately passageway 250 can provide a passageway all the way to the bottom like the vacuum tubes used in banks. A hose can be lowered down to deliver hydraulic fluid. A control connector can be lowered on a control line to provide backup control for a blowout preventer stack in case of controls difficulties. A “Go-Devil” on simple weight can be dropped to actuate a single function in an emergency situation. Basically passageway 250 becomes a utility passageway for anything which needs to be done along or at the bottom of the riser.
  • A receptacle 260 (See also FIG. 14) at the upper end of lower riser pipe 262 is engaged by nose 264 on the lower end of upper riser pipe 266. Seals 268 seal between receptacle 260 and nose 264. The upper end of lower riser pipe 262 has a clamping profile 270 and the lower end of upper riser pipe 266 has a clamping profile 272. Clamp segments 274 engage the clamping profiles 270 and 272. Tension band 276 urges clamp segments 274 into engagement with clamping profiles 270 and 272 to secure the connection.
  • Referring now to FIG. 10, the clamp segments 274 as shown in FIG. 9 are shown here to be four clamping segments of differing length 280, 282, 284, and 286. Each segment is constrained to move radially into contract with the clamping profiles 270 and 272 as shown in FIG. 9 by keyways 290, 292, 294, and 296, respectively.
  • The tension band 276 is shown to be made of four section 300, 302. 304, and 306. They are hinged together by hinge pins 310, 312, and 314. At the fourth connection a double pin arrangement is used. A threaded pin 320 is engaged by bolt 322. A non-threaded pin 324 is engaged by shoulder 326 on bolt 322.
  • Referring now to the prior art of FIG. 11, the advantage for the novel design shown in FIG. 10 becomes apparent to those of skill in the art. A two section clamp 350 has clamp halves 352 and 354 tightened on clamp hubs 356 by bolts 358. The inner diameter 360 is intended to be pulled to be concentric with diameter 362 of the clamp hubs 356.
  • Referring now to FIG. 12, the engagement of the clamp halves is shown to be on a taper 370 which has approximately a 25 degree slope. It is literally a wedge moving onto the clamp hubs.
  • Referring now to FIG. 13, a view similar to FIG. 11 is shown, but with the clamps about ¼″ from full make-up. Clamp sections 352 and 354 are actually touching clamp hubs 356 only at areas 380 and 382 respectively. Literally no contact is made at areas 384 and 386. The situation is that of a wedge being drug sideways onto the clamp hubs. The result of this type make-up is that the loading in the general areas of 380 and 382 will be high and the loading at 384 and 386 will be low. In some cases the clamp sections of this type are struck with a sledge hammer at locations 388 and 390 to jar the clamp sections into a position of more uniform loading around the circumference.
  • The irregularity of this make-up can be tolerated on small clamps and clamps which have relatively low loading. On high load clamps such as on deepwater drilling risers, this irregularity of make-up is simply not acceptable.
  • Referring again to FIG. 10, make-up onto the tapered clamp hubs 270 and 272 of FIG. 9 is constrained to be done radially rather than sliding around the wedge surface. The outer surface 400 of the clamping segments 280, 282, 284, and 286 is a simple cylindrical surface. Outer surface 400 is engaged by simple cylindrical surface 402 of tension band sections 300, 302, 304, and 306. As the tension band is pulled to a smaller diameter by bolt 322, the tension band segments 300, 302, 304, and 306 slide circumferentially around the clamping segments 280, 282, 284, and 284. The load on the clamping segments 282 and 284 will be less than the load on the clamping segments 280 and 286 by the friction on the back of clamping segments 280 and 286. If the coefficient of friction is 0.15, the unit loadings on the clamp segments will be reduced by 15%, rather than the high loses seen by the wedging action of a conventional clamp.
  • To compensate for this difference in unit loadings, the ratio of the loading area to the ratio of clamping area has been adjusted. In this case the loading area is shown on the left side of the figure and is divided to 80 degrees and 100 degrees. The clamping area is shown on the right hand side of the drawing and is divided to 81.3 degrees and 89.7 degrees. This works out to (100/80)*(81.3/89.7)=1.13 if the sliding area were frictionless. If the coefficient friction was 0.13, the mechanical size changes would closely compensate for this difference. This means that the loads around circumference would be approximately equal rather from varying from high to potentially zero in conventional clamps.
  • Referring now to FIG. 14, double seals 246 on outside fluid line 242 are shown as seals 410 and 412 with a test port 414 located between seals 410 and 412 and test pressure connecting lines 416. Each of the outside fluid lines will have similar seals, test ports and test pressure connecting lines. Seals 268 on upper riser pipe 266 are shown as seals 420 and 422 with a test port 424 located between seals 420 and 422 and a test pressure connecting line 426.
  • Flange 204 is shown being supported by dogs 430 which are extended from a riser spider (not shown).
  • Referring now to FIG. 15, test pressure lines 440 come from each of the test ports on each of the outside fluid lines and the central pipe connections. Each of the lines go to double check valves 442 and are in turn directed to fitting 444. In this way when a test pressure device is attached to fitting 444, all of the hydraulic lines can be quickly tested to the maximum pressure which can be withstood by any of the lines. As a small area will be exposed to pressure, a higher pressure can be delivered to the test port than the lowest pressure pipe can withstand, likely twice as high as unpressured areas next to the seal area will tend to reinforce the test area. Test pressure fitting 444 does not have a check valve in it such that pressure in any of the test lines 440 is solely sealed by a pair of check valves at 444. If the check valves at 444 fail for any reason, the resultant leak will not be able to enter another set of check valves and back pressure any of the other fittings, but rather simply goes into the sea water.
  • As make-up of the connection is now controlled by a single bolt, empirical studies can be done to determine the relationship of torque and turn of a properly made up connection. The relationship of torque and turn can be input into a computer and measured each time a connection is made. When this is measured, it can be quickly compared to historical connections and determined if it is a proper make-up. If the make-up curve is too flat, it will likely mean that the connection is failing. If the make-up curve is too steep, it likely means that the bolt is galling. Rather than the 15 minutes required to make up a conventional 6 bolt connection, the single bolt make-up can be likely done within 1 minute and will have a computer generated confirmation of the quality of the make-up.
  • During the 1 minute to make-up the connection, another employee can attach a test pressure device to the fitting 444 and do a 1 minute test on the various seals. In the one minute, the pressure in the test ports will not stabilize due to temperature cooling. However, they will decline in a predictable fashion and a computer will be able to predict that the seals have quality sealing. If desired, the employee can wait 3 to 5 minutes for confirmation that the pressure is stable, or has gone “flatline”.
  • Referring now to FIG. 16, a pressure time graph is shown. Line 450 indicates that the pressure is being rapidly increased from zero to a maximum amount quickly. At point 452 a valve is shut off to block the supply. The liquid and some air in the lines have been quickly pressurized and therefore heated some. As the heat dissipates into the surrounding steel, the pressure drops some until it stabilizes or goes “flatline”. Line 454 is what a typical pressure curve looks like as it goes “flatline”. At point 456 on this curve it has gone “flatline” after a period of time, i.e. 3 minutes. Lines 458 and 460 show the limits of what the pressure curve is likely to look like during successful testing. It will have some limited variation based on how much liquid is in the lines and how much air is in the lines. Line 462 shows a time during this period, i.e. 1 minute after pressurizing. If curve 458 and 460 have been determined by real life experience and at time 462 the curve is within the limits, there is a high degree of assurance that the test will be a successful test. If this data is fed into a computer, at time 462 the computer can determine that it is likely to be a successful test and indicate that operations can continue. The indication can be by a variety of means such as a printed report or a green light for GO and a red light for STOP.
  • The particular embodiments disclosed above are illustrative only, as the invention may be modified and practiced in different but equivalent manners apparent to those skilled in the art having the benefit of the teachings herein. Furthermore, no limitations are intended to the details of construction or design herein shown, other than as described in the claims below. It is therefore evident that the particular embodiments disclosed above may be altered or modified and all such variations are considered within the scope and spirit of the invention. Accordingly, the protection sought herein is as set forth in the claims below.

Claims (26)

1. A method of providing flotation modules on subsea drilling riser joints comprising:
providing flotation modules as one-piece units that completely encircle respective of said drilling riser joints;
slidingly installing said flotation modules sequentially onto the end of a central pipe of each of said drilling riser joints;
providing a plurality of passageways which extend from one end of said subsea drilling riser joints to the other end of said drilling riser joints.
2. The method of claim 1, further comprising mounting said flotation modules end to end along said subsea drilling riser joints to thereby prevent gaps between floatation modules.
3. The method of claim 1 wherein said plurality of passageways are enclosed by flotation material of said flotation modules along a minimum of an entire continuous length of at least a few of said drilling riser joints.
4. The method of claim 1, further comprising selectively rotating said flotation modules on said central pipe to a desired rotational orientation.
5. The method of claim 1 further comprising inserting fluid lines in one or more of said passageways through said flotation modules.
6. The method of claim 5 further comprising providing centralizers on said fluid lines inside said one or more passageways.
7. The method of claim 1 further comprising lowering instrumentation down one of said passageways to monitor vortex induced vibration in said riser.
8. The method of claim 1 further comprising lowering a connector down one of said passageways to engage a connection point on a blowout preventer stack and providing a control signal.
9. The method of claim 1 further comprising dropping a go-devil down one of said passageways to actuate a function on a blowout preventer stack.
10. The method of claim 1 comprising providing that said plurality of passageways are enclosed by floatation material along their entire length.
11. A method of supporting outside fluid lines on a subsea drilling riser comprising:
installing flotation modules to a drilling riser before the outside fluid lines are installed; and
installing said outside fluid lines through passageways defined by floatation material in said flotation modules.
12. The method of claim 11 further comprising
providing stabilizers on said outside fluid lines to engage the bore of said passageways in said flotation modules.
13. The method of claim 12 further comprising providing that said passageways are enclosed by said flotation material along at a minimum of an entire continuous length of at least a few of said drilling riser joints.
14. The method of claim 11 further comprising slidingly installing said flotation modules to said drilling riser.
15. A system of flotation modules mounted on a plurality of riser joints, said flotation modules comprising flotation material, said system comprising:
a plurality of flotation modules which engage each other end to end along said plurality of riser joints to prevent gaps between said plurality of flotation modules, said plurality of flotation modules defining at least five lengthwise passageways in said flotation material around said riser joints;
a choke line supported in a first lengthwise passageway of said at least five lengthwise passageways, said choke line connecting to equipment positioned on a sea floor;
a kill line supported in a second lengthwise passageway of said at least five lengthwise passageways, said kill line connecting to said equipment positioned on said sea floor;
a hydraulic line supported in a third lengthwise passageway of said at least five lengthwise passageways, said hydraulic line connecting to said equipment positioned on said sea floor;
a booster line supported in a fourth lengthwise passageway of said at least five lengthwise passageway, said booster line connecting adjacent to a bottom of said plurality of riser joints and
a fifth lengthwise passageway of said at least five passageways extending along a least several of said plurality of riser joints, said fifth lengthwise passageway being continuously enclosed by floatation material of said flotation modules along a length thereof.
16. The system of flotation modules of claim 15, further comprising instrumentation operable for lowering and retrieval through said fifth lengthwise passageway.
17. A method of providing flotation modules on a plurality of subsea drilling riser joints comprising:
slidingly installing said flotation modules sequentially onto the end of a central pipe of each of said plurality of drilling riser joints; and
providing that said flotation modules are initially rotatable for selectively rotating said flotation modules on said drilling riser joints to a desired rotational orientation.
18. The method of claim 17, comprising slidingly installing said flotation modules to a drilling riser before the outside fluid lines are installed.
19. The method of claim 17, comprising providing a plurality of lengthwise passageways which extend from one end of said subsea drilling riser joints to the other end of said drilling riser joints.
20. The method of claim 17, further comprising mounting said flotation modules end to end along said plurality of subsea drilling riser joints to thereby prevent gaps between floatation modules.
21. The method of claim 17 further comprising inserting fluid lines in one or more lengthwise passageways through said flotation modules.
22. The method of claim 21 further comprising providing centralizers on said fluid lines inside said one or more lengthwise passageways.
23. The method of claim 17 further comprising lowering instrumentation down a lengthwise passageway to monitor vortex induced vibration in said riser.
24. The method of claim 17 further comprising lowering a connector down one a lengthwise passageway to engage a connection point on a blowout preventer stack and providing a control signal.
25. The method of claim 20 further comprising dropping a go-devil down a lengthwise passageway to actuate a function on a blowout preventer stack.
26. The method of claim 17 comprising providing a plurality of lengthwise passageways which are enclosed by floatation material along a minimum of an entire continuous length of at least a few of said plurality of drilling riser joints.
US12/590,509 2009-11-10 2009-11-10 Method of providing buoyancy for a drilling riser Abandoned US20110108281A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US12/590,509 US20110108281A1 (en) 2009-11-10 2009-11-10 Method of providing buoyancy for a drilling riser

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US12/590,509 US20110108281A1 (en) 2009-11-10 2009-11-10 Method of providing buoyancy for a drilling riser

Publications (1)

Publication Number Publication Date
US20110108281A1 true US20110108281A1 (en) 2011-05-12

Family

ID=43973293

Family Applications (1)

Application Number Title Priority Date Filing Date
US12/590,509 Abandoned US20110108281A1 (en) 2009-11-10 2009-11-10 Method of providing buoyancy for a drilling riser

Country Status (1)

Country Link
US (1) US20110108281A1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2498068A (en) * 2011-12-28 2013-07-03 Vetco Gray Inc Drilling riser joint or adapter with emergency ports
WO2013079914A3 (en) * 2011-11-29 2014-01-09 Wellstream International Limited Buoyancy compensating element and method
WO2013079915A3 (en) * 2011-11-29 2014-01-09 Wellstream International Limited Buoyancy compensating element and method
WO2014191744A3 (en) * 2013-05-29 2015-06-04 Ge Oil & Gas Uk Limited Pipe components and methods of manufacture
CN105625949A (en) * 2014-11-03 2016-06-01 上海海郑海洋建设工程技术有限公司 Marine riser and offshore drilling system
US20230031939A1 (en) * 2021-07-28 2023-02-02 Benton Frederick Baugh Drilling Riser Connector

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4332509A (en) * 1979-06-18 1982-06-01 Coflexip Riser pipe system for collecting and raising petroleum produced from an underwater deposit
US4596531A (en) * 1983-09-15 1986-06-24 Societe Nationale Elf Aquitaine (Production) Device for lightening an undersea production riser by means of floating bodies
US4646840A (en) * 1985-05-02 1987-03-03 Cameron Iron Works, Inc. Flotation riser
US5330294A (en) * 1989-10-17 1994-07-19 Institut Francais Du Petrole Riser for a great water depth
US20020112858A1 (en) * 1999-08-02 2002-08-22 Mcdaniel Richard Bruce Smooth buoyancy system for reducing vortex induced vibration in subsea systems
EP1310630A1 (en) * 1997-05-22 2003-05-14 Petroleum Equipment Supply Engineering Company Limited Fairing for a marine riser
US20050100414A1 (en) * 2003-11-07 2005-05-12 Conocophillips Company Composite riser with integrity monitoring apparatus and method
US8037939B2 (en) * 2005-10-04 2011-10-18 Institut Francais Du Petrole Riser pipe with rigid auxiliary lines

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4332509A (en) * 1979-06-18 1982-06-01 Coflexip Riser pipe system for collecting and raising petroleum produced from an underwater deposit
US4596531A (en) * 1983-09-15 1986-06-24 Societe Nationale Elf Aquitaine (Production) Device for lightening an undersea production riser by means of floating bodies
US4646840A (en) * 1985-05-02 1987-03-03 Cameron Iron Works, Inc. Flotation riser
US5330294A (en) * 1989-10-17 1994-07-19 Institut Francais Du Petrole Riser for a great water depth
EP1310630A1 (en) * 1997-05-22 2003-05-14 Petroleum Equipment Supply Engineering Company Limited Fairing for a marine riser
US20020112858A1 (en) * 1999-08-02 2002-08-22 Mcdaniel Richard Bruce Smooth buoyancy system for reducing vortex induced vibration in subsea systems
US20050100414A1 (en) * 2003-11-07 2005-05-12 Conocophillips Company Composite riser with integrity monitoring apparatus and method
US8037939B2 (en) * 2005-10-04 2011-10-18 Institut Francais Du Petrole Riser pipe with rigid auxiliary lines

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013079914A3 (en) * 2011-11-29 2014-01-09 Wellstream International Limited Buoyancy compensating element and method
WO2013079915A3 (en) * 2011-11-29 2014-01-09 Wellstream International Limited Buoyancy compensating element and method
CN103958818A (en) * 2011-11-29 2014-07-30 韦尔斯特里姆国际有限公司 Buoyancy compensating element and method
CN104114806A (en) * 2011-11-29 2014-10-22 韦尔斯特里姆国际有限公司 Buoyancy compensating element and method
US9151121B2 (en) * 2011-11-29 2015-10-06 Ge Oil & Gas Uk Limited Buoyancy compensating element and method
US9353579B2 (en) 2011-11-29 2016-05-31 Ge Oil & Gas Uk Limited Buoyancy compensating element and method
GB2498068A (en) * 2011-12-28 2013-07-03 Vetco Gray Inc Drilling riser joint or adapter with emergency ports
WO2014191744A3 (en) * 2013-05-29 2015-06-04 Ge Oil & Gas Uk Limited Pipe components and methods of manufacture
CN105625949A (en) * 2014-11-03 2016-06-01 上海海郑海洋建设工程技术有限公司 Marine riser and offshore drilling system
US20230031939A1 (en) * 2021-07-28 2023-02-02 Benton Frederick Baugh Drilling Riser Connector
US11725464B2 (en) * 2021-07-28 2023-08-15 Benton Frederick Baugh Drilling riser connector

Similar Documents

Publication Publication Date Title
US10012044B2 (en) Annular isolation device for managed pressure drilling
US9297214B2 (en) Marine subsea free-standing riser systems and methods
US7237623B2 (en) Method for pressurized mud cap and reverse circulation drilling from a floating drilling rig using a sealed marine riser
GB2515418B (en) Seal sub system
US6554072B1 (en) Co-linear tensioner and methods for assembling production and drilling risers using same
US6679472B2 (en) Pressure balanced choke and kill connector
US8272444B2 (en) Method of testing a drilling riser connection
US20110108281A1 (en) Method of providing buoyancy for a drilling riser
BR0111376B1 (en) tensioner / sliding joint assembly.
SG174947A1 (en) Aluminum auxiliary lines for drilling riser
US9422776B2 (en) Rotating control device having jumper for riser auxiliary line
US11629559B2 (en) Apparatus for connecting drilling components between rig and riser
US7163054B2 (en) Breechblock connectors for use with oil field lines and oil field equipment
CN108119078B (en) Connector for pressurized fluid flow path
US20110109081A1 (en) Drilling riser connector
US20110308815A1 (en) Multi-pressure flange connection
US9453375B2 (en) Riser with slim pin auxiliary line
US11725464B2 (en) Drilling riser connector
US20040163802A1 (en) Multi-channel high pressure swivel
US9702213B2 (en) Marine riser system
Montoya et al. Dorada Field Production System: A Solution To Individual Permanent Vertical Access To Several Wells From A Semi-Submersible

Legal Events

Date Code Title Description
AS Assignment

Owner name: MEDALLION CAPITAL, INC., MINNESOTA

Free format text: SECURITY AGREEMENT;ASSIGNOR:TULSA POWER, INC.;REEL/FRAME:023720/0467

Effective date: 20091231

AS Assignment

Owner name: TULSA POWER LICENSING CORP., CONNECTICUT

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BAUGH, BENTON F.;REEL/FRAME:023720/0832

Effective date: 20091231

AS Assignment

Owner name: TEXAS CAPITAL BANK, NATIONAL ASSOCIATION, TEXAS

Free format text: SECURITY AGREEMENT;ASSIGNOR:TULSA POWER LICENSING CORP.;REEL/FRAME:023731/0465

Effective date: 20091231

AS Assignment

Owner name: MEDALLION CAPITAL, INC., MINNESOTA

Free format text: CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNOR PREVIOUSLY RECORDED ON REEL 023720 FRAME 0467. ASSIGNOR(S) HEREBY CONFIRMS THE TULSA POWER, INC.;ASSIGNOR:TULSA POWER LICENSING CORP.;REEL/FRAME:023741/0535

Effective date: 20091231

AS Assignment

Owner name: REELPOWER LICENSING CORP., OKLAHOMA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BAUGH, BENTON F.;REEL/FRAME:029483/0218

Effective date: 20121217

AS Assignment

Owner name: TULSA POWER LICENSING CORP., OKLAHOMA

Free format text: RELEASE OF SECURITY INTEREST IN PATENTS;ASSIGNOR:MEDALLION CAPITAL, INC.;REEL/FRAME:030744/0455

Effective date: 20130603

AS Assignment

Owner name: TEXAS CAPITAL BANK, NATIONAL ASSOCIATION, TEXAS

Free format text: SECURITY AGREEMENT;ASSIGNOR:TULSA POWER LICENSING CORP.;REEL/FRAME:030936/0331

Effective date: 20130603

AS Assignment

Owner name: TULSA POWER LICENSING CORP., OKLAHOMA

Free format text: CORRECTIVE DOCUMENT TO CORRECT ASSIGNMENT RECORDED AT REEL/FRAME 029483/0218;ASSIGNOR:TULSA POWER LICENSING CORP.;REEL/FRAME:031689/0702

Effective date: 20131119

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION