US20090110482A1 - Reinforced ice for road surfaces and a method of fabricating thereof - Google Patents

Reinforced ice for road surfaces and a method of fabricating thereof Download PDF

Info

Publication number
US20090110482A1
US20090110482A1 US11/977,325 US97732507A US2009110482A1 US 20090110482 A1 US20090110482 A1 US 20090110482A1 US 97732507 A US97732507 A US 97732507A US 2009110482 A1 US2009110482 A1 US 2009110482A1
Authority
US
United States
Prior art keywords
ice
roadway
composite
strength members
composite ice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US11/977,325
Inventor
Thomas LaGrotta
Michael LaGrotta
Anthony LaGrotta
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Abbott GmbH and Co KG
Original Assignee
Abbott GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Abbott GmbH and Co KG filed Critical Abbott GmbH and Co KG
Priority to US11/977,325 priority Critical patent/US20090110482A1/en
Assigned to ABBOTT GMBH & CO. KG reassignment ABBOTT GMBH & CO. KG ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BERNDL, GUNTHER, DEGENHARDT, MATTHIAS, MAEGERLEIN, MARKUS
Publication of US20090110482A1 publication Critical patent/US20090110482A1/en
Priority to US13/290,191 priority patent/US20120076581A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ

Definitions

  • the present invention is directed, in general, to the use of reinforced ice for road surfaces over water.
  • roads are made out of ice over naturally frozen lakes and other bodies of water to permit the transport of goods and materials to outlying areas by trucks, automobiles and other vehicles.
  • the current method making roads out of ice, or ice roads is to allow a body of water to freeze and thereafter use the frozen surface as a roadbed without any type of reinforcement.
  • ice is also used to re-surface roads that are in poor driving condition.
  • the present invention provides a method of fabricating ice roads using wood pulp mixed with water or re-surfacing roads in cold climates. Additional features of the invention will be described hereinafter that form the subject of the claims of the invention. Those skilled in the art should appreciate that they can readily use the disclosed conception and specific embodiment as a basis for designing or modifying other structures for carrying out the same purposes of the present invention. Those skilled in the art should also realize that such equivalent constructions do not depart from the spirit and scope of the invention.
  • FIG. 1 illustrates a diagram of an embodiment of ice road constructed according to the principles of the present invention.
  • FIG. 2 illustrates a flow diagram of an embodiment of a method of fabricating an ice road carried out according to the principles of the present invention.
  • the present invention provides a roadway that utilizes wood pulp embedded in frozen water or ice to form a composite structure.
  • Wood pulp is used in the composite structure of the ice to assist in creating a surface with a higher compressive and tensile strength and to assist in dispersing the weight of the vehicles over a greater area.
  • the wood pulp is in suspension in the ice to form the composite structure.
  • the composite ice is a much stronger structure than natural ice.
  • research has shown that natural ice has a modulus of around 22.5 kg/cm 2 but since natural ice is very inconsistent its modulus could be as low as 5 kg/cm 2 . Where as the composite ice has a modulus that is much more consistent, that is much less variability in its strength. Its modulus is 25% higher than natural ice. Typical composites will have a modulus of 77 kg/cm 2 .
  • the composite structure is more capable of carrying greater weight before failure.
  • the composite structure is also much more ductile them natural ice and has been shown to be able to withstand high velocity rifle shots without shattering.
  • the composite ice is also 4 to 5 times stronger than natural ice in tension.
  • the addition of the wood pulp to the ice makes the ice more resistant to thawing because of it insulating properties.
  • the composite structure possesses properties that would allow you to build a roadway that for a given thickness could support a heavier load, withstand vehicles being driven at a higher speeds and would last longer than the natural ice as the temperature rose above freezing.
  • the thickness of the composite ice does not need to be as thick as natural ice to ensure the safe transport of materials across the roadway.
  • the consistence of the composite ice reduces the cost of maintaining the roadway, since less testing and analysis has to be done to maintain the roadway.
  • FIG. 1 illustrated is a diagram of an embodiment of the ice road surface, constructed according to the principles of the present invention.
  • First barriers 120 must be built on each side of the roadway that will be filled with the materials used to create the composite ice road. These barriers 120 can be built using naturally available materials such as snow, or manmade materials such as plastic tubes that can be filled with water.
  • the mixture of water and wood pulp 130 is put between the barriers and allowed to freeze.
  • the mixture is 14 percent wood pulp to water based upon volume.
  • the mixture can either be pumped or sprayed in place.
  • additional strength members 140 are needed to support the roadway load then only part of the water and wood pulp mixture 130 is added and allowed to freeze and then the strength members 140 are added to the roadway.
  • the additional strength members can consist of cables laid along the direction of traffic on the roadway or netting added to the road way. These cables or netting can be made of metal, synthetic or natural fibers. The choice of material will depend upon the strength needed and the cost of the materials.
  • the remaining mixture of water and wood pulp 130 is then added to the roadway.
  • a traction layer 160 can be added to the roadway to improve the vehicles traction.
  • This traction surface 160 can consist of a mixture of water and gravel. The percent of gravel that is added is a function of how much traction is required and what size gravel is used.
  • FIG. 2 illustrates a flow diagram of a method of fabricating an ice road carried out according to the principles of the present invention. This block diagram lays out the step by step procedures for building a composite ice roadway.
  • step 210 The procedure begins in step 210 . After the lake has frozen 220 enough to support light construction equipment, construction of the road can begin. The composite road surface is built over this natural ice base.
  • the roadway is then laid out 230 and the barriers that will hold the composite ice are constructed. Once the barriers are in place the mixture of water and wood pulp is added between the barriers 240 .lf the design of the roadway requires the inclusion of additional strength members 250 , they are added at this time. Then another layer of composite ice 260 is added to the roadway.
  • a safety color layer is placed on the roadway. Then a wear layer of composite ice 280 is added to the roadway. Once this layer has frozen, a traction layer 290 can be added to the roadway.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Road Signs Or Road Markings (AREA)

Abstract

The present invention provides a method of fabricating road surfaces in cold climates for ice roads. In one embodiment the road surface includes: a combination of water and sawdust that is placed on the road surface and frozen.

Description

    TECHNICAL FIELD OF THE INVENTION
  • The present invention is directed, in general, to the use of reinforced ice for road surfaces over water.
  • BACKGROUND OF THE INVENTION
  • In cold climates roads are made out of ice over naturally frozen lakes and other bodies of water to permit the transport of goods and materials to outlying areas by trucks, automobiles and other vehicles. The current method making roads out of ice, or ice roads, is to allow a body of water to freeze and thereafter use the frozen surface as a roadbed without any type of reinforcement. In these same climates ice is also used to re-surface roads that are in poor driving condition.
  • The use of natural ice for the road surface and support is subject to weather conditions and the inherent strength of the ice created from only frozen water. These ice roads are unreliable and of unknown strength. Further they require the truck and other means of transport to proceed at slow speeds, because the natural ice will bend forming a wave in front of the truck. As the trucks speed increase this wave grows and eventually caused the ice to crack. Also the trucks weight must be restricted to prevent the ice from cracking.
  • The use of natural ice results in the natural ice melting at temperatures above freezing.
  • Therefore, improvements in the strength of the ice roads and making the ice roads more resistant to thawing would be beneficial and to the businesses that require their products, materials and supplies to be shipped over the ice roads, and in addition will improve the safety of the vehicle drivers
  • SUMMARY OF THE INVENTION
  • The present invention provides a method of fabricating ice roads using wood pulp mixed with water or re-surfacing roads in cold climates. Additional features of the invention will be described hereinafter that form the subject of the claims of the invention. Those skilled in the art should appreciate that they can readily use the disclosed conception and specific embodiment as a basis for designing or modifying other structures for carrying out the same purposes of the present invention. Those skilled in the art should also realize that such equivalent constructions do not depart from the spirit and scope of the invention.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • For a more complete understanding of the present invention, reference is now made to the following descriptions taken in conjunction with the accompanying drawings, in which:
  • FIG. 1 illustrates a diagram of an embodiment of ice road constructed according to the principles of the present invention; and
  • FIG. 2 illustrates a flow diagram of an embodiment of a method of fabricating an ice road carried out according to the principles of the present invention.
  • DETAILED DESCRIPTION
  • The present invention provides a roadway that utilizes wood pulp embedded in frozen water or ice to form a composite structure. Wood pulp is used in the composite structure of the ice to assist in creating a surface with a higher compressive and tensile strength and to assist in dispersing the weight of the vehicles over a greater area. The wood pulp is in suspension in the ice to form the composite structure. The composite ice is a much stronger structure than natural ice. Research has shown that natural ice has a modulus of around 22.5 kg/cm2 but since natural ice is very inconsistent its modulus could be as low as 5 kg/cm2. Where as the composite ice has a modulus that is much more consistent, that is much less variability in its strength. Its modulus is 25% higher than natural ice. Typical composites will have a modulus of 77 kg/cm2. Thus, the composite structure is more capable of carrying greater weight before failure.
  • The composite structure is also much more ductile them natural ice and has been shown to be able to withstand high velocity rifle shots without shattering. The composite ice is also 4 to 5 times stronger than natural ice in tension.
  • Additionally, the addition of the wood pulp to the ice makes the ice more resistant to thawing because of it insulating properties.
  • The composite structure possesses properties that would allow you to build a roadway that for a given thickness could support a heavier load, withstand vehicles being driven at a higher speeds and would last longer than the natural ice as the temperature rose above freezing.
  • Also, given the fact that the composite is more consistent than natural ice, the thickness of the composite ice does not need to be as thick as natural ice to ensure the safe transport of materials across the roadway. The consistence of the composite ice reduces the cost of maintaining the roadway, since less testing and analysis has to be done to maintain the roadway.
  • All of the advantages describe above for making roads over frozen lakes also apply to using the composite ice approach to re-surface roads in poor condition located in cold climates.
  • Turning now to FIG. 1, illustrated is a diagram of an embodiment of the ice road surface, constructed according to the principles of the present invention.
  • Once the lake 100 has frozen to the point that the natural ice 110 will support light construction equipment the construction of the composite roadway can begin. First barriers 120 must be built on each side of the roadway that will be filled with the materials used to create the composite ice road. These barriers 120 can be built using naturally available materials such as snow, or manmade materials such as plastic tubes that can be filled with water.
  • Once the barriers 120 are in place, the mixture of water and wood pulp 130 is put between the barriers and allowed to freeze. The mixture is 14 percent wood pulp to water based upon volume. The mixture can either be pumped or sprayed in place. If additional strength members 140 are needed to support the roadway load then only part of the water and wood pulp mixture 130 is added and allowed to freeze and then the strength members 140 are added to the roadway. The additional strength members can consist of cables laid along the direction of traffic on the roadway or netting added to the road way. These cables or netting can be made of metal, synthetic or natural fibers. The choice of material will depend upon the strength needed and the cost of the materials. The remaining mixture of water and wood pulp 130 is then added to the roadway.
  • Once the roadway freezes, water based, colored dye 150 is placed over the roadway and allowed to freeze. Then another layer of composite ice mixture 130 is place on the roadway. This represents the wear surface for the roadway. Any time the colored dye is exposed, the road maintenance crews will know that another layer of composite ice needs to be added to the roadway to ensure that the roadway is safe.
  • On top of this top road surface, a traction layer 160 can be added to the roadway to improve the vehicles traction. This traction surface 160 can consist of a mixture of water and gravel. The percent of gravel that is added is a function of how much traction is required and what size gravel is used.
  • FIG. 2 illustrates a flow diagram of a method of fabricating an ice road carried out according to the principles of the present invention. This block diagram lays out the step by step procedures for building a composite ice roadway.
  • The procedure begins in step 210. After the lake has frozen 220 enough to support light construction equipment, construction of the road can begin. The composite road surface is built over this natural ice base.
  • The roadway is then laid out 230 and the barriers that will hold the composite ice are constructed. Once the barriers are in place the mixture of water and wood pulp is added between the barriers 240.lf the design of the roadway requires the inclusion of additional strength members 250, they are added at this time. Then another layer of composite ice 260 is added to the roadway.
  • At this point the roadway would be ready for traffic, but additional feature such as a safety warning layer and a traction layer can be added.
  • After the basic roadway is formed a safety color layer is placed on the roadway. Then a wear layer of composite ice 280 is added to the roadway. Once this layer has frozen, a traction layer 290 can be added to the roadway.
  • Although the present invention has been described in detail, those skilled in the art should understand that they can make various changes, substitutions and alterations herein without departing from the spirit and scope of the invention in its broadest form.

Claims (12)

1. A method of creating a road surface comprising a mixture of water and wood pulp that is spread onto the existing surface.
2. A roadway wear safety warning system comprising a color layer to an ice road or composite ice road surface.
3. A composite ice roadway surface of claim 1 to which there is added strength members made of metal cables.
4. A composite ice roadway surface of claim 1 to which there is added strength members made of synthetic fiber cables.
5. A composite ice roadway surface of claim 1 to which there is added strength members made of natural fiber cables.
6. A composite ice roadway surface of claim 1 to which there is added strength members made of metal netting.
7. A composite ice roadway surface of claim 1 to which there is added strength members made of synthetic fiber netting.
8. A composite ice roadway surface of claim 1 to which there is added strength members made of natural fiber netting.
9. Abandoned.
10. Abandoned.
11. A composite ice roadway surface of claim 1 by which the roadway is formed by the use of naturally occurring snow and ice for construction barriers.
12. A composite ice roadway surface of claim 1 by which the roadway is formed by the use of man made materials for construction barriers.
US11/977,325 2007-10-25 2007-10-25 Reinforced ice for road surfaces and a method of fabricating thereof Abandoned US20090110482A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US11/977,325 US20090110482A1 (en) 2007-10-25 2007-10-25 Reinforced ice for road surfaces and a method of fabricating thereof
US13/290,191 US20120076581A1 (en) 2007-10-25 2011-11-07 Reinforced ice for road surfaces and a method of fabricating thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US11/977,325 US20090110482A1 (en) 2007-10-25 2007-10-25 Reinforced ice for road surfaces and a method of fabricating thereof

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US13/290,191 Continuation US20120076581A1 (en) 2007-10-25 2011-11-07 Reinforced ice for road surfaces and a method of fabricating thereof

Publications (1)

Publication Number Publication Date
US20090110482A1 true US20090110482A1 (en) 2009-04-30

Family

ID=40583041

Family Applications (2)

Application Number Title Priority Date Filing Date
US11/977,325 Abandoned US20090110482A1 (en) 2007-10-25 2007-10-25 Reinforced ice for road surfaces and a method of fabricating thereof
US13/290,191 Abandoned US20120076581A1 (en) 2007-10-25 2011-11-07 Reinforced ice for road surfaces and a method of fabricating thereof

Family Applications After (1)

Application Number Title Priority Date Filing Date
US13/290,191 Abandoned US20120076581A1 (en) 2007-10-25 2011-11-07 Reinforced ice for road surfaces and a method of fabricating thereof

Country Status (1)

Country Link
US (2) US20090110482A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120076581A1 (en) * 2007-10-25 2012-03-29 Lagrotta Thomas Reinforced ice for road surfaces and a method of fabricating thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2565710C1 (en) * 2014-05-14 2015-10-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Амурский гуманитарно-педагогический государственный университет" (ФГБОУ ВПО "АмГПГУ") Method to increase bearing capacity of ice cover
US11248353B1 (en) 2020-08-01 2022-02-15 Luke G. Millam Method of making a hemp reinforced ice road

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3818711A (en) * 1972-02-18 1974-06-25 Atlantic Richfield Co Stabilizing arctic ground cover
US3986783A (en) * 1972-08-24 1976-10-19 Atlantic Richfield Company Ice road building method and machine
US4440520A (en) * 1980-08-08 1984-04-03 Atlantic Richfield Company Ice aggregate road and method and apparatus for constructing same
US4544304A (en) * 1980-08-08 1985-10-01 Atlantic Richfield Company Ice aggregate road and method and apparatus for constructing same
US4571117A (en) * 1985-02-05 1986-02-18 Johnson Paul Method and apparatus for forming an ice road over snow-covered terrain
US4767239A (en) * 1987-01-08 1988-08-30 Amoco Corporation Method and apparatus for constructing an ice structure
US6659683B1 (en) * 1997-08-26 2003-12-09 Kohyu Sangyo Yugen Kaisha Anti-slipping agent for frozen road surface and spreading method thereof, and apparatus for spreading the anti-slipping agent for frozen road surface

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3359739A (en) * 1963-10-11 1967-12-26 Phillips Petroleum Co Earthen reservoir with frozen roof covering and method of forming the same
US3289425A (en) * 1965-07-27 1966-12-06 Exxon Research Engineering Co Ice reinforcement
US3371586A (en) * 1965-07-30 1968-03-05 Arkady Fedorovich Nikolaev Apparatus for packing snow to obtain a snow and ice cover surface
US4057967A (en) * 1976-05-14 1977-11-15 Suntech, Inc. Reinforced ice matrix
US4094149A (en) * 1976-07-30 1978-06-13 Exxon Production Research Company Offshore structure in frigid environment
US4205928A (en) * 1976-07-30 1980-06-03 Exxon Production Research Company Offshore structure in frigid environment
US4080797A (en) * 1976-07-30 1978-03-28 Exxon Production Research Company Artificial ice pad for operating in a frigid environment
SE412623B (en) * 1978-08-03 1980-03-10 Graenges Ab PROCEDURE FOR SELECTIVE UNDERGRADUATION AND STABILIZATION OF BACKGROUND
US4523879A (en) * 1982-04-16 1985-06-18 Exxon Production Research Co. Ice barrier construction
US4606674A (en) * 1984-04-23 1986-08-19 Capron Mark E Structural wheel element
US4666342A (en) * 1984-06-08 1987-05-19 Recherches B.C. Michel Inc. Ice berm for use as a foundation for an arctic offshore structure
US4549364A (en) * 1984-10-26 1985-10-29 Thermal Power Corporation Apparatus and method for making snow roads
US5027613A (en) * 1990-05-04 1991-07-02 Pare Robert L Floating ice rink
JP2700164B2 (en) * 1991-03-01 1998-01-19 株式会社スノーヴァ Method for producing ice sheet and artificial snow
JP2000336604A (en) * 1999-05-31 2000-12-05 Nippon Hodo Co Ltd Vehicle test course road surface
US7476052B2 (en) * 2001-09-20 2009-01-13 Brett Osmund Hall Retractable fluid-filled speed bump/vehicle restrictor
JP2004346289A (en) * 2003-05-20 2004-12-09 Takeuchi Mokuzai Kogyo Kk Anti-slip agent for use on frozen road surface, and method for manufacturing the same
US7124521B1 (en) * 2003-12-08 2006-10-24 Adam Paul Medoro Apparatus for resurfacing an ice surface
RU2268334C1 (en) * 2004-12-21 2006-01-20 Дмитрий Николаевич Устюгов Method of and device for building compacted snow road pavement (versions)
US20090110482A1 (en) * 2007-10-25 2009-04-30 Lagrotta Thomas Reinforced ice for road surfaces and a method of fabricating thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3818711A (en) * 1972-02-18 1974-06-25 Atlantic Richfield Co Stabilizing arctic ground cover
US3986783A (en) * 1972-08-24 1976-10-19 Atlantic Richfield Company Ice road building method and machine
US4440520A (en) * 1980-08-08 1984-04-03 Atlantic Richfield Company Ice aggregate road and method and apparatus for constructing same
US4544304A (en) * 1980-08-08 1985-10-01 Atlantic Richfield Company Ice aggregate road and method and apparatus for constructing same
US4571117A (en) * 1985-02-05 1986-02-18 Johnson Paul Method and apparatus for forming an ice road over snow-covered terrain
US4767239A (en) * 1987-01-08 1988-08-30 Amoco Corporation Method and apparatus for constructing an ice structure
US6659683B1 (en) * 1997-08-26 2003-12-09 Kohyu Sangyo Yugen Kaisha Anti-slipping agent for frozen road surface and spreading method thereof, and apparatus for spreading the anti-slipping agent for frozen road surface

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120076581A1 (en) * 2007-10-25 2012-03-29 Lagrotta Thomas Reinforced ice for road surfaces and a method of fabricating thereof

Also Published As

Publication number Publication date
US20120076581A1 (en) 2012-03-29

Similar Documents

Publication Publication Date Title
CN109082962B (en) Environment-friendly construction method for expressway
US20090110482A1 (en) Reinforced ice for road surfaces and a method of fabricating thereof
US3110981A (en) Highway maintenance of elevated structures
US4086015A (en) Crash moderation system for roads, highways, railways, airfields and harbors
US20070098495A1 (en) Method and composition for reducing the occurrence of icing on roads, bridges and overpasses
Chen et al. Fiber reinforced polymer patching binder for concrete pavement rehabilitation and repair
CN110306401A (en) The semi-rigid anti-crack road surface construction method of extremely frigid zones
CN204491357U (en) Road and bridge two-way heat tube snow removing cooling system
KR102276812B1 (en) Planar heating element for road
CN104314003A (en) Long-life reinforcing mesh flexible fiber reinforced concrete bridge deck pavement structure
CN212152994U (en) Road surface structure of high-capacity bus rapid transit system station
RU2700996C1 (en) Railway crossing and method of making reverberative plates for it
Simonova Evaluation of functional safety of cement concrete and composite pavements exposed to weather conditions
US1265404A (en) Speed-arrester for vehicles.
Scaht et al. Application of a porous interlayer for road temperature control
Krayushkina et al. Perspectives of usage of seamless and fiber basalt filament for construction and rehabilitation of motor roads and airfields
Pokharel et al. New advances in novel polymeric alloy geocell-reinforced base course for paved roads
CN211228112U (en) Bridge deck with snow melting and deicing functions and containing phase change materials
RU2696703C1 (en) Construction method of motor road
CN209652664U (en) A kind of anti-cracking high-strength degree highway pavement
RU2550710C1 (en) Method to increase durability of asphalt surface of motor road
DE102010044294A1 (en) Arrangement for enhanced spatial load transfer of wheel loads in e.g. street, has geogrids with geocells installed in traffic area to dissipate forces such as thrust and shear forces of vehicle laterally into traffic area
CN205399120U (en) Wear -resisting road surface of cling compound structure
KR102178005B1 (en) Concrete paving slab structure using honeycomb composite material
CN204059141U (en) A kind of antifreeze pavement of road

Legal Events

Date Code Title Description
AS Assignment

Owner name: ABBOTT GMBH & CO. KG, GERMANY

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:BERNDL, GUNTHER;DEGENHARDT, MATTHIAS;MAEGERLEIN, MARKUS;REEL/FRAME:021176/0615;SIGNING DATES FROM 20080513 TO 20080526

STCB Information on status: application discontinuation

Free format text: EXPRESSLY ABANDONED -- DURING EXAMINATION