Prior art keywords
resources
availability
disruption
account
business
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/051,154
Inventor
Ching-Hua Chen-Ritzo
Pawan Raghunath Chowdhary
Thomas Robert Ervolina
Dharmashankar Subramanian
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US12/051,154 priority Critical patent/US20080208658A1/en
Publication of US20080208658A1 publication Critical patent/US20080208658A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0201Market modelling; Market analysis; Collecting market data
    • G06Q30/0202Market predictions or forecasting for commercial activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0201Market modelling; Market analysis; Collecting market data
    • G06Q30/0204Market segmentation
    • G06Q30/0205Location or geographical consideration
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/02Manufacture or treatment of semiconductor devices or of parts thereof
    • H01L21/04Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer
    • H01L21/18Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer the devices having semiconductor bodies comprising elements of Group IV of the Periodic System or AIIIBV compounds with or without impurities, e.g. doping materials
    • H01L21/26Bombardment with radiation
    • H01L21/263Bombardment with radiation with high-energy radiation
    • H01L21/265Bombardment with radiation with high-energy radiation producing ion implantation
    • H01L21/26586Bombardment with radiation with high-energy radiation producing ion implantation characterised by the angle between the ion beam and the crystal planes or the main crystal surface
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/02Manufacture or treatment of semiconductor devices or of parts thereof
    • H01L21/04Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer
    • H01L21/18Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer the devices having semiconductor bodies comprising elements of Group IV of the Periodic System or AIIIBV compounds with or without impurities, e.g. doping materials
    • H01L21/28Manufacture of electrodes on semiconductor bodies using processes or apparatus not provided for in groups H01L21/20 - H01L21/268
    • H01L21/283Deposition of conductive or insulating materials for electrodes conducting electric current
    • H01L21/285Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation
    • H01L21/28506Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation of conductive layers
    • H01L21/28512Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation of conductive layers on semiconductor bodies comprising elements of Group IV of the Periodic System
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/02Manufacture or treatment of semiconductor devices or of parts thereof
    • H01L21/04Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer
    • H01L21/18Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer the devices having semiconductor bodies comprising elements of Group IV of the Periodic System or AIIIBV compounds with or without impurities, e.g. doping materials
    • H01L21/28Manufacture of electrodes on semiconductor bodies using processes or apparatus not provided for in groups H01L21/20 - H01L21/268
    • H01L21/283Deposition of conductive or insulating materials for electrodes conducting electric current
    • H01L21/285Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation
    • H01L21/28506Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation of conductive layers
    • H01L21/28512Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation of conductive layers on semiconductor bodies comprising elements of Group IV of the Periodic System
    • H01L21/28525Deposition of conductive or insulating materials for electrodes conducting electric current from a gas or vapour, e.g. condensation of conductive layers on semiconductor bodies comprising elements of Group IV of the Periodic System the conductive layers comprising semiconducting material
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/70Manufacture or treatment of devices consisting of a plurality of solid state components formed in or on a common substrate or of parts thereof; Manufacture of integrated circuit devices or of parts thereof
    • H01L21/71Manufacture of specific parts of devices defined in group H01L21/70
    • H01L21/768Applying interconnections to be used for carrying current between separate components within a device comprising conductors and dielectrics
    • H01L21/76838Applying interconnections to be used for carrying current between separate components within a device comprising conductors and dielectrics characterised by the formation and the after-treatment of the conductors
    • H01L21/76877Filling of holes, grooves or trenches, e.g. vias, with conductive material
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L29/00Semiconductor devices adapted for rectifying, amplifying, oscillating or switching, or capacitors or resistors with at least one potential-jump barrier or surface barrier, e.g. PN junction depletion layer or carrier concentration layer; Details of semiconductor bodies or of electrodes thereof  ; Multistep manufacturing processes therefor
    • H01L29/66Types of semiconductor device ; Multistep manufacturing processes therefor
    • H01L29/66007Multistep manufacturing processes
    • H01L29/66075Multistep manufacturing processes of devices having semiconductor bodies comprising group 14 or group 13/15 materials
    • H01L29/66227Multistep manufacturing processes of devices having semiconductor bodies comprising group 14 or group 13/15 materials the devices being controllable only by the electric current supplied or the electric potential applied, to an electrode which does not carry the current to be rectified, amplified or switched, e.g. three-terminal devices
    • H01L29/66409Unipolar field-effect transistors
    • H01L29/66477Unipolar field-effect transistors with an insulated gate, i.e. MISFET
    • H01L29/6656Unipolar field-effect transistors with an insulated gate, i.e. MISFET using multiple spacer layers, e.g. multiple sidewall spacers
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L29/00Semiconductor devices adapted for rectifying, amplifying, oscillating or switching, or capacitors or resistors with at least one potential-jump barrier or surface barrier, e.g. PN junction depletion layer or carrier concentration layer; Details of semiconductor bodies or of electrodes thereof  ; Multistep manufacturing processes therefor
    • H01L29/66Types of semiconductor device ; Multistep manufacturing processes therefor
    • H01L29/66007Multistep manufacturing processes
    • H01L29/66075Multistep manufacturing processes of devices having semiconductor bodies comprising group 14 or group 13/15 materials
    • H01L29/66227Multistep manufacturing processes of devices having semiconductor bodies comprising group 14 or group 13/15 materials the devices being controllable only by the electric current supplied or the electric potential applied, to an electrode which does not carry the current to be rectified, amplified or switched, e.g. three-terminal devices
    • H01L29/66409Unipolar field-effect transistors
    • H01L29/66477Unipolar field-effect transistors with an insulated gate, i.e. MISFET
    • H01L29/66568Lateral single gate silicon transistors
    • H01L29/66575Lateral single gate silicon transistors where the source and drain or source and drain extensions are self-aligned to the sides of the gate
    • H01L29/6659Lateral single gate silicon transistors where the source and drain or source and drain extensions are self-aligned to the sides of the gate with both lightly doped source and drain extensions and source and drain self-aligned to the sides of the gate, e.g. lightly doped drain [LDD] MOSFET, double diffused drain [DDD] MOSFET
    • HELECTRICITY
    • H10SEMICONDUCTOR DEVICES; ELECTRIC SOLID-STATE DEVICES NOT OTHERWISE PROVIDED FOR
    • H10BELECTRONIC MEMORY DEVICES
    • H10B12/00Dynamic random access memory [DRAM] devices
    • H10B12/01Manufacture or treatment
    • H10B12/02Manufacture or treatment for one transistor one-capacitor [1T-1C] memory cells
    • H10B12/03Making the capacitor or connections thereto
    • H10B12/033Making the capacitor or connections thereto the capacitor extending over the transistor
    • H10B12/0335Making a connection between the transistor and the capacitor, e.g. plug
    • HELECTRICITY
    • H10SEMICONDUCTOR DEVICES; ELECTRIC SOLID-STATE DEVICES NOT OTHERWISE PROVIDED FOR
    • H10BELECTRONIC MEMORY DEVICES
    • H10B12/00Dynamic random access memory [DRAM] devices
    • H10B12/30DRAM devices comprising one-transistor - one-capacitor [1T-1C] memory cells
    • H10B12/48Data lines or contacts therefor
    • H10B12/485Bit line contacts
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/02Manufacture or treatment of semiconductor devices or of parts thereof
    • H01L21/04Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer
    • H01L21/18Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer the devices having semiconductor bodies comprising elements of Group IV of the Periodic System or AIIIBV compounds with or without impurities, e.g. doping materials
    • H01L21/22Diffusion of impurity materials, e.g. doping materials, electrode materials, into or out of a semiconductor body, or between semiconductor regions; Interactions between two or more impurities; Redistribution of impurities
    • H01L21/225Diffusion of impurity materials, e.g. doping materials, electrode materials, into or out of a semiconductor body, or between semiconductor regions; Interactions between two or more impurities; Redistribution of impurities using diffusion into or out of a solid from or into a solid phase, e.g. a doped oxide layer
    • H01L21/2251Diffusion into or out of group IV semiconductors
    • H01L21/2254Diffusion into or out of group IV semiconductors from or through or into an applied layer, e.g. photoresist, nitrides
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/02Manufacture or treatment of semiconductor devices or of parts thereof
    • H01L21/04Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer
    • H01L21/18Manufacture or treatment of semiconductor devices or of parts thereof the devices having at least one potential-jump barrier or surface barrier, e.g. PN junction, depletion layer or carrier concentration layer the devices having semiconductor bodies comprising elements of Group IV of the Periodic System or AIIIBV compounds with or without impurities, e.g. doping materials
    • H01L21/22Diffusion of impurity materials, e.g. doping materials, electrode materials, into or out of a semiconductor body, or between semiconductor regions; Interactions between two or more impurities; Redistribution of impurities
    • H01L21/225Diffusion of impurity materials, e.g. doping materials, electrode materials, into or out of a semiconductor body, or between semiconductor regions; Interactions between two or more impurities; Redistribution of impurities using diffusion into or out of a solid from or into a solid phase, e.g. a doped oxide layer
    • H01L21/2251Diffusion into or out of group IV semiconductors
    • H01L21/2254Diffusion into or out of group IV semiconductors from or through or into an applied layer, e.g. photoresist, nitrides
    • H01L21/2257Diffusion into or out of group IV semiconductors from or through or into an applied layer, e.g. photoresist, nitrides the applied layer being silicon or silicide or SIPOS, e.g. polysilicon, porous silicon
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/70Manufacture or treatment of devices consisting of a plurality of solid state components formed in or on a common substrate or of parts thereof; Manufacture of integrated circuit devices or of parts thereof
    • H01L21/77Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate
    • H01L21/78Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate with subsequent division of the substrate into plural individual devices
    • H01L21/82Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate with subsequent division of the substrate into plural individual devices to produce devices, e.g. integrated circuits, each consisting of a plurality of components
    • H01L21/822Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate with subsequent division of the substrate into plural individual devices to produce devices, e.g. integrated circuits, each consisting of a plurality of components the substrate being a semiconductor, using silicon technology
    • H01L21/8232Field-effect technology
    • H01L21/8234MIS technology, i.e. integration processes of field effect transistors of the conductor-insulator-semiconductor type
    • H01L21/823418MIS technology, i.e. integration processes of field effect transistors of the conductor-insulator-semiconductor type with a particular manufacturing method of the source or drain structures, e.g. specific source or drain implants or silicided source or drain structures or raised source or drain structures
    • H01L21/823425MIS technology, i.e. integration processes of field effect transistors of the conductor-insulator-semiconductor type with a particular manufacturing method of the source or drain structures, e.g. specific source or drain implants or silicided source or drain structures or raised source or drain structures manufacturing common source or drain regions between a plurality of conductor-insulator-semiconductor structures
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/70Manufacture or treatment of devices consisting of a plurality of solid state components formed in or on a common substrate or of parts thereof; Manufacture of integrated circuit devices or of parts thereof
    • H01L21/77Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate
    • H01L21/78Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate with subsequent division of the substrate into plural individual devices
    • H01L21/82Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate with subsequent division of the substrate into plural individual devices to produce devices, e.g. integrated circuits, each consisting of a plurality of components
    • H01L21/822Manufacture or treatment of devices consisting of a plurality of solid state components or integrated circuits formed in, or on, a common substrate with subsequent division of the substrate into plural individual devices to produce devices, e.g. integrated circuits, each consisting of a plurality of components the substrate being a semiconductor, using silicon technology
    • H01L21/8232Field-effect technology
    • H01L21/8234MIS technology, i.e. integration processes of field effect transistors of the conductor-insulator-semiconductor type
    • H01L21/823475MIS technology, i.e. integration processes of field effect transistors of the conductor-insulator-semiconductor type interconnection or wiring or contact manufacturing related aspects
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L23/00Details of semiconductor or other solid state devices
    • H01L23/48Arrangements for conducting electric current to or from the solid state body in operation, e.g. leads, terminal arrangements ; Selection of materials therefor
    • H01L23/482Arrangements for conducting electric current to or from the solid state body in operation, e.g. leads, terminal arrangements ; Selection of materials therefor consisting of lead-in layers inseparably applied to the semiconductor body
    • H01L23/485Arrangements for conducting electric current to or from the solid state body in operation, e.g. leads, terminal arrangements ; Selection of materials therefor consisting of lead-in layers inseparably applied to the semiconductor body consisting of layered constructions comprising conductive layers and insulating layers, e.g. planar contacts
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L29/00Semiconductor devices adapted for rectifying, amplifying, oscillating or switching, or capacitors or resistors with at least one potential-jump barrier or surface barrier, e.g. PN junction depletion layer or carrier concentration layer; Details of semiconductor bodies or of electrodes thereof  ; Multistep manufacturing processes therefor
    • H01L29/02Semiconductor bodies ; Multistep manufacturing processes therefor
    • H01L29/06Semiconductor bodies ; Multistep manufacturing processes therefor characterised by their shape; characterised by the shapes, relative sizes, or dispositions of the semiconductor regions ; characterised by the concentration or distribution of impurities within semiconductor regions
    • H01L29/10Semiconductor bodies ; Multistep manufacturing processes therefor characterised by their shape; characterised by the shapes, relative sizes, or dispositions of the semiconductor regions ; characterised by the concentration or distribution of impurities within semiconductor regions with semiconductor regions connected to an electrode not carrying current to be rectified, amplified or switched and such electrode being part of a semiconductor device which comprises three or more electrodes
    • H01L29/107Substrate region of field-effect devices
    • H01L29/1075Substrate region of field-effect devices of field-effect transistors
    • H01L29/1079Substrate region of field-effect devices of field-effect transistors with insulated gate
    • H01L29/1083Substrate region of field-effect devices of field-effect transistors with insulated gate with an inactive supplementary region, e.g. for preventing punch-through, improving capacity effect or leakage current
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L2924/00Indexing scheme for arrangements or methods for connecting or disconnecting semiconductor or solid-state bodies as covered by H01L24/00
    • H01L2924/0001Technical content checked by a classifier
    • H01L2924/0002Not covered by any one of groups H01L24/00, H01L24/00 and H01L2224/00
    • HELECTRICITY
    • H10SEMICONDUCTOR DEVICES; ELECTRIC SOLID-STATE DEVICES NOT OTHERWISE PROVIDED FOR
    • H10BELECTRONIC MEMORY DEVICES
    • H10B12/00Dynamic random access memory [DRAM] devices
    • H10B12/01Manufacture or treatment
    • H10B12/02Manufacture or treatment for one transistor one-capacitor [1T-1C] memory cells
    • H10B12/05Making the transistor

Definitions

  • the present invention relates to the estimation of changes in the availability of resources for the creation and delivery of goods and/or services resulting from the impact of a global disruption or crisis, including, but not limited to, the circumstances created by a pandemic.
  • Examples of the impact that a crisis may have on the availability of resources include, but are not limited to, the following:
  • a firm Under normal (i.e., non-crisis) conditions, a firm typically considers only a subset of the resources previously listed in its business-as-usual planning process(es). For example, a manufacturing firm may use a process called ‘material requirements planning’ (MRP) for managing its manufacturing process.
  • MRP material requirements planning
  • MRP material requirements planning
  • a manufacturer can predict the availability of their goods, either for distribution to retailers or delivery to customers, based simply on the availability of the necessary raw materials and parts. Therefore, conventional MRP systems take as input the availability of these raw materials and parts.
  • a manufacturing firm may also use a process referred to as ‘capacity planning’ (CP) to estimate its capacity for producing goods.
  • capacity refers to both machine capacity and labor capacity. Therefore, combining MRP with CP, under normal conditions, a manufacturer may consider only machine, labor and raw material/part availability when managing their manufacturing process. While resources such as clean water, electricity, network connectivity, telecommunications and third party logistics services may also be necessary to the manufacturer's operations, they are typically assumed to be unconstrained or otherwise taken for granted under normal conditions. Therefore, these latter such resource types are typically not considered as inputs in MRP or CP systems.
  • a firm may be able to mitigate the potential impact of a crisis on the availability of resources by implementing one or more mitigation plans. For example, in the case of a disruption caused by a hurricane, structural damage to materials stored in warehouses could be reduced by reinforcing or otherwise protecting warehouse windows. In the case of a disruption caused by a pandemic, employees could be provided with vaccinations to reduce the probability of infection. Additionally, employees could be cross-trained so that they have overlapping skills and can ‘fill in’ for absent workers in the event of a crisis. These are all examples of potential mitigation plans.
  • the present invention provides a method and system for estimating the availability of resources that may affect a firm's business operations as a result of a crisis or disruption, by:
  • FIG. 1 shows the use of a supply model according to the present invention.
  • FIG. 2 shows a system configured according to the present invention.
  • FIG. 3 shows a sample output assessing the effect of a crisis on supply according to the present invention.
  • the present invention seeks to provide estimates of the impact of crises or otherwise disruptive events on supply by extending and adapting traditional supply estimation techniques by assessing the impact of a disruption on resources that may be assumed to be unconstrained under normal conditions, and which may affect the ability of the firm to produce its product(s) and/or which may impact the availability of resources typically accounted for in business planning under normal conditions.
  • a computer estimates supply requirements by (i) receiving as input a forecast of a firm's “baseline” supply of human resources, various forms of infrastructure and raw materials, (ii) correcting the forecast to account for the impact of a crisis, while also taking into account the potential effects of one or more mitigation policies, and (iii) providing the corrected forecast of the availability of supply of human resources, various forms of infrastructure and raw materials as output, and (iv) providing an additional output that includes a forecast of the availability one or more resources during said crisis that may not have been included in the said forecast of business resource availability under baseline conditions, whose availability is derived from one or more of the following: the availability of other resources that may have been included in the said forecast of business resource availability under baseline conditions, input parameter values.
  • the availability of resource type “site-open” (described in model details) is derived from the availability of employees and the business policy that determines when a site will be made accessible.
  • the availability resource type “hub” (described in model details) at one location is derived from the availability of “localxport” resources and human resources in one or more other locations.
  • the supply model takes as input the “baseline” availability of each relevant type of resource, in one or more geographical locations and over one or more time periods. This baseline corresponds to the availability of resources under normal, non-crisis conditions.
  • Outputs produced by the present invention may include a time-profile of resource availability over the planning horizon, for each resource type and each geographical location of interest.
  • the types of resources, or supply, that may be considered by the present invention span at least the following three categories:
  • Human resources, or people may be modeled as a function of the number of employees that are working on-site, working from home, or absent, in each geographical location in each time period in the planning horizon. These numbers can be obtained, for example, from an existing epidemiological model which captures human behavioral effects. Productivity factors for employees in each of these three states may also be modeled as follows:
  • X h,lt Fraction of employees working at home, at location, l, and time, t.
  • Human resources can be further categorized by, for example, job type, skill set, industry expertise, years of experience and years of education. The same general approach for estimating the impact of a crisis on human resource availability would apply in these cases.
  • the availability of one or more raw materials from suppliers may be modeled in terms of a linear dependence between the availability of a supplier's workforce and the ability of the supplier to deliver raw materials.
  • S t,ladjusted localxport S t,l localxport *Average ⁇ Y road,l,t ,Y water,l,t ,Y elec,l,t ,Y network,l,t ,Y air,l,t ⁇ .
  • This infrastructure resource type models the dependency of the firm on the availability of logistics hubs (typically, these are major international airports). Any given hub may service one or more geographical regions. A set of hubs may service overlapping geographical regions. The availability of a hub depends on the availability of human resources and local infrastructure in the location of the hub:
  • H(l) A set of hub locations that may service location, l.
  • S t,l,adjusted hub Adjusted availability of logistics hubs in location, l, at time, t.
  • the adjusted availability of logistics hubs in location l and time period t may be given by,
  • S t,l,adjusted hub S t,l hub *Average ⁇ h in (H(l) ⁇ [( Y road,h,t +Y water,h,t +Y elec,h,t, +Y network,h,t, +Y air,h,t +( ⁇ X s,l,t + ⁇ X h,l,t ))/6].
  • This infrastructure resource type reflects on whether a site or facility is open or closed. It takes on value of 0, or 1. 0 denotes a closed site, and 1 denotes an open site. When a site is closed, then the availability of one or more resources located at, or associated with, that site may be considered unavailable. Site availability (or “site-open”) is computed as follows:
  • S t,l parts Baseline Supply of supplier parts from location l, at time, t.
  • S t,l,adjusted parts Adjusted supply of supplier parts from location, l, at time, t, due to the crisis.
  • S t,l,adjusted parts Min( S t,l parts ,S t,l parts *(1+ ⁇ )*(1 ⁇ ( ⁇ X s,l,t + ⁇ X h,l,t ))* Y ).
  • This sub-type models the effect of local infrastructure in a given location. It is a measure of availability of infrastructure which has been defined to include Air-travel, Water, Roads, Networks and Electricity:
  • Y elec,l,t Proportional availability of Utilities and Electricity, in location, l, and at time, t.
  • the adjusted availability of global air freight capacity may be given by
  • the present invention is capable of assessing the effects of mitigation actions on the availability of resources.
  • employee cross-training may be implemented as a mitigation policy in a supply model according to the present invention.
  • Such a model requires as input a set of cross-trained resource types, each of which is defined in terms of regular resource types that contribute towards the creation and composition of a cross-trained type.
  • a cross-trained resource type named JAVA_C++ could be defined as being composed of people drawn from regular resource types, namely JAVA and C++, which contribute towards creating the cross-trained type, JAVA_C++.
  • the set of cross-trained resource types, along with the corresponding regular resource type definitions, is input for each supply location of interest.
  • the cross-trained resource type, which is desired as a mitigation policy in any given location, is assumed to be created from its associated regular resource types that are present in the same location.
  • R(CR l,i ) Set of regular resources that contribute to the composition of cross-trained resource type, i, in location, l.
  • the model preserves head count by ensuring that the cross-trained set of resources are created from the associated regular set of resources. In other words, for each unit increase in the size of any cross-trained resource type, there is a corresponding unit decrease in the size of some regular resource type that is associated with the cross-trained resource type.
  • Java 100 C++: 200 Java_C++: 0 Starting at week 5, the following resource profile is used as the baseline set of people supply, in Yorktown Heights.
  • Java 50 C++: 100 Java_C++: 150 Note that the head-count is conserved across the cross-training mitigation policy. There are a total of 300 heads in either case.
  • the mitigation results from the observation that, the cross-trained resource type, Java_C++ is able to service requests for both Java as well as C++ programming tasks.
  • the present invention is capable of estimating the availability of resources in cases where there exist dependencies between the resources being estimated. For example, the availability of resource type “siteopen” may further depend on the availability of human resources with specific job role of “facility operations”.
  • additional user-input policy parameters include, without limitation:
  • This example illustrates a specific example of how the invention calculates resource availability when the resource depends on another resource.
  • Resources which do not depend on other resources are called independent resources.
  • Resources which depend on other resources are called dependent resources.
  • the supply model is first invoked on the independent resources.
  • the output of the supply model on the independent resources is then fed in as input to the supply model on the dependent resources.
  • a method, a system, and a machine-readable medium with instructions for a computer or other data processing apparatus to estimate the availability of one or more business resources in the event of a crisis or other disruption by:
  • FIG. 1 there is shown a set of crisis parameters 101 being used as input by a supply calculator 110 , which also receives data concerning baseline resource availability 102 and mitigation policies 103 .
  • the supply calculator 110 produces an adjusted resource availability 120 , which is used as input by a resource interdependency calculator 130 , which receives a capacity calculating function for determining resource availability as a function of interactions of resource types 109 .
  • the resource interdependency calculator 130 produces output in the form of crisis-impacted resource availability 190 to be used in supply chain or other business planning.
  • FIG. 2 shows a system configured according to the present invention.
  • a computer 200 with a machine-readable medium 201 containing machine-readable instructions 202 for the computer 200 to receive a baseline business resource availability forecast as input and to provide a forecast corrected for crisis conditions as output.
  • Said computer 200 receives operator instructions via a keyboard 210 .
  • the computer 200 obtains the baseline business resource availability forecast data via a network 230 , either directly from databases 250 a , 250 b , 250 c or from a server 240 obtaining the baseline business resource availability forecast data from databases 250 a , 250 b , 250 c .
  • the computer 200 then corrects the firm's baseline business resource availability forecast data to account for the impact of a crisis and provides a forecast corrected for crisis conditions as output either in human-readable format via a computer screen 221 or printer 225 or in machine-readable format over the network 230 as input to the server 240 .
  • FIG. 3 shows a sample output assessing the effect of a crisis on supply according to the present invention.

Abstract

The availability of relevant business resources, or supply, during a global crisis or disruption are estimated by using a forecast of a baseline supply of human resources and various forms of infrastructure and raw materials for a firm as input. That forecast is corrected to account for the impact of a crisis or other disruption, and a corrected forecast as output is provided. The corrected forecast reflects changes in the availability of business resources due to the crisis or disruption, dependencies between resources, as well as any mitigating effects resulting from the implementation of mitigation policies.

Description

    BACKGROUND OF THE INVENTION
  • 1. Field of the Invention
  • The present invention relates to the estimation of changes in the availability of resources for the creation and delivery of goods and/or services resulting from the impact of a global disruption or crisis, including, but not limited to, the circumstances created by a pandemic.
  • 2. Background Description
  • Under a disruption or crisis, the availability of resources affecting the production of goods and/or services by a firm may be impacted. It is important for a firm to understand how the availability of various resources necessary for the production and delivery of goods and/or services to their customers may change due to a crisis, or disruptive event, since this will ultimately affect the firm's ability to operate profitably during, and in the aftermath of the crisis.
  • Examples of the impact that a crisis may have on the availability of resources (also more generally referred to as “supply”) include, but are not limited to, the following:
      • Reduced availability of firm's employees;
      • Reduced availability of firm's partners' or suppliers' employees;
      • Reduced availability of infrastructure (potentially including, but not limited to, air, water, road, telecommunications, buildings, information technology and electricity);
      • Reduced availability of logistics hubs (e.g., international shipping ports and airports);
      • Reduced availability of raw materials and office supplies/equipment from suppliers; and
  • Reduced availability of services procured or outsourced by the firm.
  • Under normal (i.e., non-crisis) conditions, a firm typically considers only a subset of the resources previously listed in its business-as-usual planning process(es). For example, a manufacturing firm may use a process called ‘material requirements planning’ (MRP) for managing its manufacturing process. In MRP, typically only raw materials or parts are considered to be a constraining resource (i.e., physical items used directly in the assembly or production of the final product(s)). The premise of MRP is that a manufacturer can predict the availability of their goods, either for distribution to retailers or delivery to customers, based simply on the availability of the necessary raw materials and parts. Therefore, conventional MRP systems take as input the availability of these raw materials and parts.
  • Additionally, a manufacturing firm may also use a process referred to as ‘capacity planning’ (CP) to estimate its capacity for producing goods. Typically, in this context, capacity refers to both machine capacity and labor capacity. Therefore, combining MRP with CP, under normal conditions, a manufacturer may consider only machine, labor and raw material/part availability when managing their manufacturing process. While resources such as clean water, electricity, network connectivity, telecommunications and third party logistics services may also be necessary to the manufacturer's operations, they are typically assumed to be unconstrained or otherwise taken for granted under normal conditions. Therefore, these latter such resource types are typically not considered as inputs in MRP or CP systems.
  • Under disruptive or crisis conditions, however, resources that are not typically considered to be critical or constraining, may become critical or constraining. Thus, the availability of such resources may significantly affect the firm's ability to meet the demand for its product(s).
  • SUMMARY OF THE INVENTION
  • A firm may be able to mitigate the potential impact of a crisis on the availability of resources by implementing one or more mitigation plans. For example, in the case of a disruption caused by a hurricane, structural damage to materials stored in warehouses could be reduced by reinforcing or otherwise protecting warehouse windows. In the case of a disruption caused by a pandemic, employees could be provided with vaccinations to reduce the probability of infection. Additionally, employees could be cross-trained so that they have overlapping skills and can ‘fill in’ for absent workers in the event of a crisis. These are all examples of potential mitigation plans.
  • The present invention provides a method and system for estimating the availability of resources that may affect a firm's business operations as a result of a crisis or disruption, by:
      • Accounting for how a crisis may impact the availability of resources that a firm typically factors into its conventional business planning processes (e.g., in manufacturing, examples of such conventional processes may include MRP and/or CP)
      • Accounting for how a crisis may impact the availability of resources that a firm typically does not factor into its conventional business planning processes
      • Accounting for dependencies between the availability of resources that a firm typically factors into its conventional business planning processes and those that it does not
      • Assessing how one or more mitigation strategies may impact the aforementioned effects of a crisis on resource availability Performing at least one of the above for one or more geographical locations and for one or more time periods, accounting for potential dependencies between locations and time periods.
    BRIEF DESCRIPTION OF THE DRAWINGS
  • The foregoing and other objects, aspects and advantages will be better understood from the following detailed description of a preferred embodiment of the invention with reference to the drawings, in which:
  • FIG. 1 shows the use of a supply model according to the present invention.
  • FIG. 2 shows a system configured according to the present invention.
  • FIG. 3 shows a sample output assessing the effect of a crisis on supply according to the present invention.
  • DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS OF THE INVENTION
  • The present invention seeks to provide estimates of the impact of crises or otherwise disruptive events on supply by extending and adapting traditional supply estimation techniques by assessing the impact of a disruption on resources that may be assumed to be unconstrained under normal conditions, and which may affect the ability of the firm to produce its product(s) and/or which may impact the availability of resources typically accounted for in business planning under normal conditions. According to the present invention, a computer estimates supply requirements by (i) receiving as input a forecast of a firm's “baseline” supply of human resources, various forms of infrastructure and raw materials, (ii) correcting the forecast to account for the impact of a crisis, while also taking into account the potential effects of one or more mitigation policies, and (iii) providing the corrected forecast of the availability of supply of human resources, various forms of infrastructure and raw materials as output, and (iv) providing an additional output that includes a forecast of the availability one or more resources during said crisis that may not have been included in the said forecast of business resource availability under baseline conditions, whose availability is derived from one or more of the following: the availability of other resources that may have been included in the said forecast of business resource availability under baseline conditions, input parameter values. For example, the availability of resource type “site-open” (described in model details) is derived from the availability of employees and the business policy that determines when a site will be made accessible. As another example, the availability resource type “hub” (described in model details) at one location is derived from the availability of “localxport” resources and human resources in one or more other locations.
  • The details of the supply estimation model are described next.
  • Supply Model Details
  • The supply model takes as input the “baseline” availability of each relevant type of resource, in one or more geographical locations and over one or more time periods. This baseline corresponds to the availability of resources under normal, non-crisis conditions. Outputs produced by the present invention may include a time-profile of resource availability over the planning horizon, for each resource type and each geographical location of interest. The types of resources, or supply, that may be considered by the present invention span at least the following three categories:
      • Human Resources;
      • Raw Materials; and
      • Infrastructure, which comprises, without limitation, sub-types such as
        • “localxport”: a measure of availability of infrastructure which has been defined to include Air-travel, Water, Roads, Networks and Electricity
        • “hub”: a measure of the availability of global logistical hubs
        • “site-open”: a measure of the availability of a firm's facilities
        • “lift”: a measure of the availability of the global air freight capacity
          Details regarding the method for modeling each of the above types of resources are provided in the sections that follow.
    Human Resources
  • Human resources, or people, may be modeled as a function of the number of employees that are working on-site, working from home, or absent, in each geographical location in each time period in the planning horizon. These numbers can be obtained, for example, from an existing epidemiological model which captures human behavioral effects. Productivity factors for employees in each of these three states may also be modeled as follows:
      • Xs,l,t: Fraction of employees working at on-site at location, l, and time, t.
      • α: Productivity factor for employees working at site, 0≦α≦1. A default (for example, α=0.95) may be set.
  • Xh,lt: Fraction of employees working at home, at location, l, and time, t.
      • β: Productivity factor for employees working at home, 0≦β≦1. A default (for example, β=0.80) may be set.
      • Xa,l,t: Fraction of employees absent at site, at location l, and time, t.
      • St,l people: Baseline supply of people at location l.
      • St,l,adjusted people: Adjusted supply of people at location l, at time, t, due to the crisis.
        Thus, the effective availability of employees at location l in time period t is given by:

  • S t,l,adjusted people =S t,l people*(αX s,l,t +βX h,l,t)
  • Human resources can be further categorized by, for example, job type, skill set, industry expertise, years of experience and years of education. The same general approach for estimating the impact of a crisis on human resource availability would apply in these cases.
  • Raw Material from Suppliers
  • The availability of one or more raw materials from suppliers may be modeled in terms of a linear dependence between the availability of a supplier's workforce and the ability of the supplier to deliver raw materials.
      • γ: Supplier Sensitivity. This parameter models the sensitivity of supplier's capacity to people availability. It stands for the proportional drop in supplier's capacity, per unit proportional drop in net employee availability. A default value may be set (for example, a default value of 0.5 would mean that, if net employee availability at a supplier location drops by 10%, then supplier parts capacity would drop by 5%, i.e., 5%=0.5×10%).
      • κ: Supplier Buffer. This parameter models the buffer that each supplier has planned for delivery of material to the firm. It stands for the proportion of the baseline supply amount, which is the
      • St,l,adjusted localxport: Adjusted supply of “localxport”, in location, l, and at time, t.
    Thus,

  • S t,ladjusted localxport =S t,l localxport*Average{Yroad,l,t ,Y water,l,t ,Y elec,l,t ,Y network,l,t ,Y air,l,t}.
  • 2. “Hub”
  • This infrastructure resource type models the dependency of the firm on the availability of logistics hubs (typically, these are major international airports). Any given hub may service one or more geographical regions. A set of hubs may service overlapping geographical regions. The availability of a hub depends on the availability of human resources and local infrastructure in the location of the hub:
  • St,l hub: Baseline Supply of “hub”, in location, l, and at time, t.
  • H(l): A set of hub locations that may service location, l.
  • St,l,adjusted hub: Adjusted availability of logistics hubs in location, l, at time, t.
  • The adjusted availability of logistics hubs in location l and time period t may be given by,

  • S t,l,adjusted hub =S t,l hub*Average{h in (H(l)}[(Y road,h,t +Y water,h,t +Y elec,h,t, +Y network,h,t, +Y air,h,t+(αX s,l,t +βX h,l,t))/6].
  • 3. “Site-Open”
  • This infrastructure resource type reflects on whether a site or facility is open or closed. It takes on value of 0, or 1. 0 denotes a closed site, and 1 denotes an open site. When a site is closed, then the availability of one or more resources located at, or associated with, that site may be considered unavailable. Site availability (or “site-open”) is computed as follows:
      • St,l site-open: Baseline Supply availability of facility/site, in location, l, and at time, t. St,l site-open is assumed to be equal to 1, i.e., the site is considered open, in the baseline.
      • St,l,adjusted site-open: Adjusted availability of facility/site, in location, l, and at time, t.
      • η: Site closure threshold fraction. Fraction of employee absenteeism, above which, a site will be closed. A default value may be set (for example, a default value of 0.9 would mean that a site is considered closed if absenteeism exceeds 90%).
        The adjusted availability of a site in location l in time period t may be given by

  • St,l,adjusted site-open=1, if η<=Xa,l,t, and

  • St,l,adjusted site-open=0, otherwise.
  • 4. “Lift”
  • This infrastructure resource type models the availability of global air freight capacity:
      • St lift: Baseline Supply of global “lift”, at time, t. This is an estimate (or actual) of air freight capacity that is typically available under non-crisis conditions at time, t, in order to deliver on the baseline demand.
      • δ: Scaling factor for reduction in global air-lift supply. A default value (for example, 80% or 0.8) may be set.
      • St,adjusted lift: Adjusted supply of global air-lift. buffer planned by the supplier over and above the baseline amount, for delivery to the firm. A default value (for example, 0.10) may be set.
  • St,l parts: Baseline Supply of supplier parts from location l, at time, t. St,l,adjusted parts: Adjusted supply of supplier parts from location, l, at time, t, due to the crisis.
  • Thus the adjusted availability of supplier parts in location l in time period t due to a crisis may be given by,

  • S t,l,adjusted parts=Min(S t,l parts ,S t,l parts*(1+κ)*(1−(αX s,l,t +αX h,l,t))*Y).
  • Infrastructure-Related Supply
  • The dependence of a firm's operations on infrastructure-related types of supply may be modeled in terms of the following items:
  • 1. “Localxport”
  • This sub-type models the effect of local infrastructure in a given location. It is a measure of availability of infrastructure which has been defined to include Air-travel, Water, Roads, Networks and Electricity:
      • St,l localxport: Baseline Supply of “localxport”, in location, l, and at time, t.
      • Yroad,l,t: Proportional availability of Roads, in location, l, and at time, t.
      • Ywater,l,t: Proportional availability of Clean Water, in location, l, and at time, t.
  • Yelec,l,t: Proportional availability of Utilities and Electricity, in location, l, and at time, t.
      • Ynetwork,l,t: Proportional availability of Network Communications, in location, l, and at time, t.
  • Yair,l,t: Proportional availability of Air-travel, in location, l, at time, t.
  • The adjusted availability of global air freight capacity may be given by

  • S t,adjusted lift =S t lift*δ.
  • The present invention is capable of assessing the effects of mitigation actions on the availability of resources. For example, employee cross-training may be implemented as a mitigation policy in a supply model according to the present invention. Such a model requires as input a set of cross-trained resource types, each of which is defined in terms of regular resource types that contribute towards the creation and composition of a cross-trained type.
  • Example
  • A cross-trained resource type named JAVA_C++ could be defined as being composed of people drawn from regular resource types, namely JAVA and C++, which contribute towards creating the cross-trained type, JAVA_C++. The set of cross-trained resource types, along with the corresponding regular resource type definitions, is input for each supply location of interest. The cross-trained resource type, which is desired as a mitigation policy in any given location, is assumed to be created from its associated regular resource types that are present in the same location.
  • Other user-input policy parameters include, without limitation:
      • ω: Yes/No: Whether cross-training policy is in place, or not. It takes values, 0 or 1. A default value may be set (for example, a default value of zero would indicate no cross-training in place).
      • χ: Cross-training extent. This is a percentage value that stands for the extent of cross-training implementation. A value of 25% means that 25% of the relevant regular resource types get cross-trained. A default value may be set (for example, a default value of zero would indicate no cross-training had occurred).
      • T: Time at which cross-trained resource availability starts.
      • CRl,i,t: Cross-trained resource type, i, in location, l, at time, t.
  • R(CRl,i): Set of regular resources that contribute to the composition of cross-trained resource type, i, in location, l.
  • The model preserves head count by ensuring that the cross-trained set of resources are created from the associated regular set of resources. In other words, for each unit increase in the size of any cross-trained resource type, there is a corresponding unit decrease in the size of some regular resource type that is associated with the cross-trained resource type.
  • Example
  • Let there be 100 Java programmers and 200 C++ programmers in the baseline set of people supply in location Yorktown Heights. Also let there be a cross-trained resource type, Java_C++, which is associated with regular resource types Java and C++. Further, let the extent of cross-training be 50%, and let the cross-training start time index (in weeks) be T=5. For weeks 1 through 4, the following resource profile is used as the baseline set of people supply.
  • Java: 100
    C++: 200
    Java_C++: 0

    Starting at week 5, the following resource profile is used as the baseline set of people supply, in Yorktown Heights.
  • Java: 50
    C++: 100
    Java_C++: 150

    Note that the head-count is conserved across the cross-training mitigation policy. There are a total of 300 heads in either case. The mitigation results from the observation that, the cross-trained resource type, Java_C++ is able to service requests for both Java as well as C++ programming tasks.
      • CRl,i,t=χ*Sum{r(R(CRl,i)}[(St,l,adjusted people,r|without cross-training)/Nr], if t>=T, and ω=1
      • CRl,i,t=0, otherwise
      • St,l,adjusted people,r=(St,l,adjusted people,r|without cross-training)*χ, if t>=T, and ω=1
      • St,l,adjusted people,r=St,l,adjusted people,r|without cross-training, otherwise
        where
      • Nr: The number of cross-trained resource types that the regular resource type, r,
        contributes towards
      • St,l,adjusted people,r|without cross-training: The adjusted (people) availability of resource type, r, at time, t, in location, l, when there is no cross-training policy in place.
  • The present invention is capable of estimating the availability of resources in cases where there exist dependencies between the resources being estimated. For example, the availability of resource type “siteopen” may further depend on the availability of human resources with specific job role of “facility operations”.
  • In this case, additional user-input policy parameters include, without limitation:
      • f: Min Facility Operations threshold. This is the minimum number of Human Resource with job role “facility operations” that must be available for site to open.
        To calculate the availability of “siteopen” the availability of the facility operations resource is calculated first. Let Yt,l,adjusted facility-operations represent the adjusted availability of human resource type “facility operations”. It is calculated according to the present invention described above for human resources. The adjusted availability of the siteopen resource for a site in location l in time period t may be given by

  • St,l,adjusted site-open=1, if η<=Xa,l,t, and Yt,l,adjusted facility-operations>=f and

  • St,l,adjusted site-open=0, otherwise.
  • This example illustrates a specific example of how the invention calculates resource availability when the resource depends on another resource. Resources which do not depend on other resources are called independent resources. Resources which depend on other resources are called dependent resources. To effectively estimate availability of all the resources, the supply model is first invoked on the independent resources. The output of the supply model on the independent resources is then fed in as input to the supply model on the dependent resources.
  • Thus, according to the present invention, there is provided a method, a system, and a machine-readable medium with instructions for a computer or other data processing apparatus to estimate the availability of one or more business resources in the event of a crisis or other disruption, by:
      • Receiving as input a forecast and/or forecast data of business resource availability under baseline conditions and a data set of parameter values representing, for example, one or a plurality of business policies, crisis severity, human factors and resource dependencies;
      • Determining a corrected forecast of business resource availability to account for an impact of a disruption by taking into account change in the availability of one or more resources accounted for in conventional business planning processes due to said disruption and change in the availability of one or more resources not accounted for in conventional business planning processes due to said disruption; and
      • Providing the corrected forecast of business resource availability as output.
        The disruption or crisis may or may not be an epidemiological crisis. Examples of resources that may typically be accounted for in the business planning processes may or may not include raw materials, machinery and/or human resources. Examples of resources that are typically not accounted for in said business planning processes may or may not include, without limitation:
      • Network connectivity and/or other utilities
      • Clean water and electricity
      • Roads
      • Maritime port and shipping capacity
      • Air travel capacity
      • Air freight capacity
      • Global logistics hubs
      • Site/facility access and/or
      • Availability of human resources belonging to a firm's suppliers and/or partners.
        The correction of the forecast to account for the potential impact of a crisis or disruption may further take into account dependencies between resources accounted for in conventional business planning processes and resources that are not accounted for in conventional business planning processes. The corrected resource availability forecast may also take into account any potential changes in available resources due to the effects of one or more mitigation policies. Input may be provided for one or more geographic locations and/or one or more time periods, taking into account any dependencies between locations and time periods.
  • Referring now to the drawings, and more particularly to FIG. 1, there is shown a set of crisis parameters 101 being used as input by a supply calculator 110, which also receives data concerning baseline resource availability 102 and mitigation policies 103. The supply calculator 110 produces an adjusted resource availability 120, which is used as input by a resource interdependency calculator 130, which receives a capacity calculating function for determining resource availability as a function of interactions of resource types 109. Finally, the resource interdependency calculator 130 produces output in the form of crisis-impacted resource availability 190 to be used in supply chain or other business planning.
  • FIG. 2 shows a system configured according to the present invention. A computer 200 with a machine-readable medium 201 containing machine-readable instructions 202 for the computer 200 to receive a baseline business resource availability forecast as input and to provide a forecast corrected for crisis conditions as output. Said computer 200 receives operator instructions via a keyboard 210. The computer 200 obtains the baseline business resource availability forecast data via a network 230, either directly from databases 250 a, 250 b, 250 c or from a server 240 obtaining the baseline business resource availability forecast data from databases 250 a, 250 b, 250 c. The computer 200 then corrects the firm's baseline business resource availability forecast data to account for the impact of a crisis and provides a forecast corrected for crisis conditions as output either in human-readable format via a computer screen 221 or printer 225 or in machine-readable format over the network 230 as input to the server 240.
  • FIG. 3 shows a sample output assessing the effect of a crisis on supply according to the present invention.
  • While the invention has been described in terms of its preferred embodiments, those skilled in the art will recognize that the invention can be practiced with modification within the spirit and scope of the appended claims.

Claims (17)

1. A method of estimating the availability of one or more business resources in the event of a crisis or other disruption, comprising the steps of:
using a computer to receive as input
a forecast of business resource availability under baseline conditions, and
a set of parameter values representing one or more of business policies, human factors, severity of said crisis or disruption, and dependencies between resources;
using a computer to determine a corrected forecast of business resource availability to account for an impact of a disruption by taking into account
change in the availability of one or more resources accounted for in conventional business planning processes due to said disruption, and
change in the availability of one or more resources not accounted for in conventional business planning processes due to said disruption; and
using a computer to provide said corrected forecast of business resource availability as output.
2. The method of claim 1 wherein the disruption is an epidemiological crisis.
3. The method of claim 1 wherein resources accounted for in said conventional business planning processes include one or more of
raw materials,
machinery, and
human resources.
4. The method of claim 3 wherein said conventional business planning processes lack accounting for one or more resources selected from the group consisting of
network connectivity,
clean water,
electricity,
roads,
maritime port and shipping capacity,
air travel capacity,
air freight capacity,
global logistics hubs,
site access, and
availability of human resources of one or more of the firm's suppliers.
5. The method of claim 1, wherein the step of correcting the forecast of resource availability to account for the potential impact of a disruption takes into account a dependency between resources accounted for in a conventional business planning process and resources not accounted for in a conventional business planning process.
6. The method of claim 1 wherein the step of correcting the forecast of resource availability to account for the potential impact of a disruption takes into account one or more potential changes in available resources due to an effect of one or more mitigation policies.
7. The method of claim 1 wherein input is provided for one or more geographic locations and time periods, taking into account each dependency between a location and a time period.
8. The method of claim 1 wherein output is provided for one or more geographical locations and time periods, taking into account each dependency between a location and a time period.
9. A system for estimating the availability of one or more business resources in the event of a crisis or other disruption, comprising:
a computer receiving as input
forecast data of business resource availability under baseline conditions, and
a data set of parameter values representing one or more of business policies, human factors, severity of said crisis or disruption, and dependencies between resources;
a computer determining a corrected forecast of business resource availability to account for an impact of a disruption by taking into account
change in the availability of one or more resources accounted for in conventional business planning processes due to said disruption, and
change in the availability of one or more resources not accounted for in conventional business planning processes due to said disruption; and
a computer providing said corrected forecast of business resource availability as output.
10. The system of claim 9 wherein the disruption is an epidemiological crisis.
11. The system of claim 9 wherein the resources accounted for in said conventional business planning processes include one or more of
raw materials,
machinery, and
human resources.
12. The method of claim 9 wherein said conventional business planning processes lack accounting for one or more resources selected from the group consisting of
network connectivity,
clean water,
electricity,
roads,
maritime port and shipping capacity,
air travel capacity,
air freight capacity,
global logistics hubs,
site access, and
availability of human resources of one or more of the firm's suppliers.
13. The system of claim 9, wherein determining the corrected forecast of resource availability to account for the potential impact of a disruption takes into account a dependency between resources accounted for in a conventional business planning process and resources not accounted for in a conventional business planning process.
14. The system of claim 9 wherein determining the corrected forecast of resource availability to account for the potential impact of a disruption takes into account one or more potential changes in available resources due to a effect of one or more mitigation policies.
15. The system of claim 9 wherein input is provided for one or more geographic locations and time periods, taking into account each dependency between a location and a time period.
16. The system of claim 9 wherein output is provided for one or more geographical locations and time periods, taking into account each dependency between a location and a time period.
17. A machine-readable medium for estimating the availability of one or more business resources in the event of a crisis or other disruption, on which is provided:
machine-readable instructions for a computer to receive as input
a forecast of business resource availability under baseline conditions, and
a set of parameter values representing one or more of business policies, human factors, severity of said crisis or disruption, and dependencies between resources;
machine-readable instructions for a computer to determine a corrected forecast of business resource availability to account for an impact of a disruption by taking into account
change in the availability of one or more resources accounted for in conventional business planning processes due to said disruption, and
change in the availability of one or more resources not accounted for in conventional business planning processes due to said disruption; and
machine-readable instructions for a computer to provide said corrected forecast of business resource availability as output.
US12/051,154 2002-08-29 2008-03-19 Method and system for estimating supply impact on a firm under a global crisis Abandoned US20080208658A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US12/051,154 US20080208658A1 (en) 2002-08-29 2008-03-19 Method and system for estimating supply impact on a firm under a global crisis

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
US10/230,948 US6670682B1 (en) 2002-08-29 2002-08-29 Multilayered doped conductor
US10/650,563 US6858534B2 (en) 2002-08-29 2003-08-28 Method of manufacturing a multilayered doped conductor for a contact in an integrated device
US10/989,530 US7195995B2 (en) 2002-08-29 2004-11-16 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device
US11/627,064 US20070124190A1 (en) 2002-08-29 2007-01-25 Method and system for estimating supply impact on a firm under a global crisis
US12/051,154 US20080208658A1 (en) 2002-08-29 2008-03-19 Method and system for estimating supply impact on a firm under a global crisis

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US11/627,064 Continuation US20070124190A1 (en) 2002-08-29 2007-01-25 Method and system for estimating supply impact on a firm under a global crisis

Publications (1)

Publication Number Publication Date
US20080208658A1 true US20080208658A1 (en) 2008-08-28

Family

ID=29735522

Family Applications (7)

Application Number Title Priority Date Filing Date
US10/230,948 Expired - Lifetime US6670682B1 (en) 2002-08-29 2002-08-29 Multilayered doped conductor
US10/650,563 Expired - Lifetime US6858534B2 (en) 2002-08-29 2003-08-28 Method of manufacturing a multilayered doped conductor for a contact in an integrated device
US10/989,530 Expired - Lifetime US7195995B2 (en) 2002-08-29 2004-11-16 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device
US11/627,067 Expired - Lifetime US7385259B2 (en) 2002-08-29 2007-01-25 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device
US11/627,064 Abandoned US20070124190A1 (en) 2002-08-29 2007-01-25 Method and system for estimating supply impact on a firm under a global crisis
US11/681,246 Abandoned US20070148930A1 (en) 2002-08-29 2007-03-02 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device
US12/051,154 Abandoned US20080208658A1 (en) 2002-08-29 2008-03-19 Method and system for estimating supply impact on a firm under a global crisis

Family Applications Before (6)

Application Number Title Priority Date Filing Date
US10/230,948 Expired - Lifetime US6670682B1 (en) 2002-08-29 2002-08-29 Multilayered doped conductor
US10/650,563 Expired - Lifetime US6858534B2 (en) 2002-08-29 2003-08-28 Method of manufacturing a multilayered doped conductor for a contact in an integrated device
US10/989,530 Expired - Lifetime US7195995B2 (en) 2002-08-29 2004-11-16 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device
US11/627,067 Expired - Lifetime US7385259B2 (en) 2002-08-29 2007-01-25 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device
US11/627,064 Abandoned US20070124190A1 (en) 2002-08-29 2007-01-25 Method and system for estimating supply impact on a firm under a global crisis
US11/681,246 Abandoned US20070148930A1 (en) 2002-08-29 2007-03-02 Method of manufacturing a multilayered doped conductor for a contact in an integrated circuit device

Country Status (1)

Country Link
US (7) US6670682B1 (en)

Families Citing this family (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6809016B1 (en) * 2003-03-06 2004-10-26 Advanced Micro Devices, Inc. Diffusion stop implants to suppress as punch-through in SiGe
US6846720B2 (en) * 2003-06-18 2005-01-25 Agency For Science, Technology And Research Method to reduce junction leakage current in strained silicon on silicon-germanium devices
US7268052B1 (en) * 2003-09-24 2007-09-11 Cypress Semiconductor Corporation Method for reducing soft error rates of memory cells
US7112501B2 (en) * 2003-10-20 2006-09-26 Oki Electric Industry Co., Ltd. Method of fabrication a silicon-on-insulator device with a channel stop
KR100576359B1 (en) * 2003-12-04 2006-05-03 삼성전자주식회사 Semiconductor devices having transistor with source and drain regions facing asymmetrically and methods of fabricating the same
KR100521440B1 (en) * 2003-12-27 2005-10-13 동부아남반도체 주식회사 Method for fabricating the halo region in NMOS transistor
US7078723B2 (en) * 2004-04-06 2006-07-18 Taiwan Semiconductor Manufacturing Company, Ltd. Microelectronic device with depth adjustable sill
US20050260776A1 (en) * 2004-05-19 2005-11-24 Taiwan Semiconductor Manufacturing Co., Ltd. Structure and method for extraction of parasitic junction capacitance in deep submicron technology
JP2006173538A (en) * 2004-12-20 2006-06-29 Oki Electric Ind Co Ltd Semiconductor device
JP2006287096A (en) * 2005-04-04 2006-10-19 Sharp Corp Semiconductor storage device and manufacturing method therefor
JP4718894B2 (en) * 2005-05-19 2011-07-06 株式会社東芝 Manufacturing method of semiconductor device
US7423347B2 (en) * 2006-01-19 2008-09-09 Taiwan Semiconductor Manufacturing Company, Ltd. In-situ deposition for cu hillock suppression
US7670895B2 (en) 2006-04-24 2010-03-02 Freescale Semiconductor, Inc Process of forming an electronic device including a semiconductor layer and another layer adjacent to an opening within the semiconductor layer
KR100803666B1 (en) * 2006-07-26 2008-02-19 삼성전자주식회사 Stacked semiconductor device and method of manufacturing the same
KR100865548B1 (en) * 2006-12-28 2008-10-28 주식회사 하이닉스반도체 Method for fabricating semiconductor device
US7742324B2 (en) * 2008-02-19 2010-06-22 Micron Technology, Inc. Systems and devices including local data lines and methods of using, making, and operating the same
US9190494B2 (en) * 2008-02-19 2015-11-17 Micron Technology, Inc. Systems and devices including fin field-effect transistors each having U-shaped semiconductor fin
US8866254B2 (en) * 2008-02-19 2014-10-21 Micron Technology, Inc. Devices including fin transistors robust to gate shorts and methods of making the same
US7915659B2 (en) 2008-03-06 2011-03-29 Micron Technology, Inc. Devices with cavity-defined gates and methods of making the same
US8546876B2 (en) 2008-03-20 2013-10-01 Micron Technology, Inc. Systems and devices including multi-transistor cells and methods of using, making, and operating the same
US7808042B2 (en) 2008-03-20 2010-10-05 Micron Technology, Inc. Systems and devices including multi-gate transistors and methods of using, making, and operating the same
US7898857B2 (en) * 2008-03-20 2011-03-01 Micron Technology, Inc. Memory structure having volatile and non-volatile memory portions
US7969776B2 (en) 2008-04-03 2011-06-28 Micron Technology, Inc. Data cells with drivers and methods of making and operating the same
US8076229B2 (en) * 2008-05-30 2011-12-13 Micron Technology, Inc. Methods of forming data cells and connections to data cells
US8148776B2 (en) 2008-09-15 2012-04-03 Micron Technology, Inc. Transistor with a passive gate
US8617982B2 (en) * 2010-10-05 2013-12-31 Novellus Systems, Inc. Subtractive patterning to define circuit components
US20120130774A1 (en) * 2010-11-18 2012-05-24 Dror Daniel Ziv Analyzing performance using video analytics
US8294511B2 (en) 2010-11-19 2012-10-23 Micron Technology, Inc. Vertically stacked fin transistors and methods of fabricating and operating the same
US20150248679A1 (en) * 2014-02-28 2015-09-03 International Business Machines Corporation Pulse-width modulated representation of the effect of social parameters upon resource criticality
US9899234B2 (en) 2014-06-30 2018-02-20 Lam Research Corporation Liner and barrier applications for subtractive metal integration
US10402759B2 (en) * 2015-01-22 2019-09-03 Visier Solutions, Inc. Systems and methods of adding and reconciling dimension members
KR102530671B1 (en) 2015-12-31 2023-05-10 삼성전자주식회사 Method of fabricating the semiconductor device
US10510851B2 (en) * 2016-11-29 2019-12-17 Taiwan Semiconductor Manufacturing Company, Ltd. Low resistance contact method and structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6006192A (en) * 1997-03-12 1999-12-21 International Business Machines Corporation Method for production planning in an uncertain demand environment
US20040064436A1 (en) * 2002-07-16 2004-04-01 Jodi Breslin System and method for managing business continuity
US20040107133A1 (en) * 2002-12-02 2004-06-03 Pershing Investments, Llc. Capacity planning method and system
US20050165633A1 (en) * 2004-01-28 2005-07-28 Huber Robert C. Method for reducing adverse effects of a disaster or other similar event upon the continuity of a business
US20060085323A1 (en) * 2004-10-14 2006-04-20 Cisco Technology Inc. System and method for analyzing risk within a supply chain
US20080015889A1 (en) * 2006-07-17 2008-01-17 Brad Fenster System and apparatus for managing risk
US20080133299A1 (en) * 2006-10-20 2008-06-05 Oracle International Corp. Planning a response to an unplanned event

Family Cites Families (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5268319A (en) * 1988-06-08 1993-12-07 Eliyahou Harari Highly compact EPROM and flash EEPROM devices
US6043562A (en) 1996-01-26 2000-03-28 Micron Technology, Inc. Digit line architecture for dynamic memory
US6319804B1 (en) * 1996-03-27 2001-11-20 Advanced Micro Devices, Inc. Process to separate the doping of polygate and source drain regions in dual gate field effect transistors
KR100250744B1 (en) * 1996-06-21 2000-05-01 김영환 Forming method of the polycide layer in a semiconductor device
US5882993A (en) * 1996-08-19 1999-03-16 Advanced Micro Devices, Inc. Integrated circuit with differing gate oxide thickness and process for making same
US6066894A (en) * 1997-02-07 2000-05-23 United Microelectronics Corporation Semiconductor device and a method of manufacturing the same
JP3544833B2 (en) * 1997-09-18 2004-07-21 株式会社東芝 Semiconductor device and manufacturing method thereof
US5981332A (en) 1997-09-30 1999-11-09 Siemens Aktiengesellschaft Reduced parasitic leakage in semiconductor devices
US6130145A (en) 1998-01-21 2000-10-10 Siemens Aktiengesellschaft Insitu doped metal policide
US6067680A (en) * 1998-04-29 2000-05-30 Micron Technology, Inc. Semiconductor processing method of forming a conductively doped semiconductive material plug within a contact opening
US6087214A (en) 1998-04-29 2000-07-11 Vlsi Technology, Inc. Arrangement and method for DRAM cell using shallow trench isolation
TW434866B (en) * 1999-08-13 2001-05-16 Taiwan Semiconductor Mfg Manufacturing method for contact plug
US6482707B1 (en) 2000-03-21 2002-11-19 Micron Technology, Inc. Method of improving static refresh
US6613620B2 (en) * 2000-07-31 2003-09-02 Semiconductor Energy Laboratory Co., Ltd. Semiconductor device and method of manufacturing the same
KR100441682B1 (en) * 2001-06-14 2004-07-27 삼성전자주식회사 Semiconductor device having LDD-type source/drain regions and fabrication method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6006192A (en) * 1997-03-12 1999-12-21 International Business Machines Corporation Method for production planning in an uncertain demand environment
US20040064436A1 (en) * 2002-07-16 2004-04-01 Jodi Breslin System and method for managing business continuity
US20040107133A1 (en) * 2002-12-02 2004-06-03 Pershing Investments, Llc. Capacity planning method and system
US20050165633A1 (en) * 2004-01-28 2005-07-28 Huber Robert C. Method for reducing adverse effects of a disaster or other similar event upon the continuity of a business
US20060085323A1 (en) * 2004-10-14 2006-04-20 Cisco Technology Inc. System and method for analyzing risk within a supply chain
US20080015889A1 (en) * 2006-07-17 2008-01-17 Brad Fenster System and apparatus for managing risk
US20080133299A1 (en) * 2006-10-20 2008-06-05 Oracle International Corp. Planning a response to an unplanned event

Also Published As

Publication number Publication date
US7385259B2 (en) 2008-06-10
US6670682B1 (en) 2003-12-30
US20070114615A1 (en) 2007-05-24
US6858534B2 (en) 2005-02-22
US7195995B2 (en) 2007-03-27
US20050064689A1 (en) 2005-03-24
US20070148930A1 (en) 2007-06-28
US20040042283A1 (en) 2004-03-04
US20070124190A1 (en) 2007-05-31

Similar Documents

Publication Publication Date Title
US20080208658A1 (en) Method and system for estimating supply impact on a firm under a global crisis
US10372593B2 (en) System and method for resource modeling and simulation in test planning
Bititci Modelling of performance measurement systems in manufacturing enterprises
Roemer et al. Concurrent crashing and overlapping in product development
Love et al. Using systems dynamics to better understand change and rework in construction project management systems
US7584116B2 (en) Monitoring a demand forecasting process
US7991631B2 (en) Managing a multi-supplier environment
US8050959B1 (en) System and method for modeling consortium data
US20050043977A1 (en) E-business value web
US10628769B2 (en) Method and system for a cross-domain enterprise collaborative decision support framework
US20140012603A1 (en) Capacity planning and modeling for optimization of task outcomes
US20070073576A1 (en) Resource capacity planning
US8015043B2 (en) Method and apparatus for workforce demand forecasting
CA2623863A1 (en) Update processes in an enterprise planning system
US9600784B2 (en) Estimating value of information technology service management based on process complexity analysis
JP2008527500A (en) Automated project office and system and method for automated risk assessment and reporting
Yan et al. Stochastic models for air cargo terminal manpower supply planning in long‐term operations
US20200065733A1 (en) Method and system for estimating efforts for software managed services production support engagements
Syahputra et al. System Analysis and Design of Fishery Supply Chain Risk in Aceh: A Case Study
Weking et al. Analysis if E–Ticketing Service Information System Application using COBIT 5 Framework
Bangash et al. Inventory requirements planning at lucent technologies
Agius et al. Workload equity in vehicle routing with a medium-term perspective
US8660884B2 (en) Method and system for estimating demand impact on a firm under crisis
Bradley Managing manufacturing assets and subcontracting policies
Turgay et al. Risk Mitigation for SMEs: A Step-by-Step Guide to Implementing an Effective Framework

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION