US20070273196A1 - Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts - Google Patents

Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts Download PDF

Info

Publication number
US20070273196A1
US20070273196A1 US09/773,524 US77352401A US2007273196A1 US 20070273196 A1 US20070273196 A1 US 20070273196A1 US 77352401 A US77352401 A US 77352401A US 2007273196 A1 US2007273196 A1 US 2007273196A1
Authority
US
United States
Prior art keywords
carriers
drum
pair
hoist ropes
drums
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US09/773,524
Inventor
John Vergne
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JS Redpath Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US09/773,524 priority Critical patent/US20070273196A1/en
Assigned to J.S. REDPATH LIMITED reassignment J.S. REDPATH LIMITED ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: DE LA VERGNE, JOHN NICHOLAS
Publication of US20070273196A1 publication Critical patent/US20070273196A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B17/00Hoistway equipment
    • B66B17/04Mining-hoist cars or cages
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/03Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws

Definitions

  • the present invention relates to mining and more particularly to the hoisting of refuse materials from a mine shaft work site.
  • Shaft excavation in hard rock is carried out by drilling and loading the drilled bores with explosives which are then detonated. The broken rock must then be hoisted to the surface. This is typically done with large steel buckets.
  • a standard double drum mine hoist is normally employed to hoist the shaft buckets up and to lower them down.
  • the same hoist may later be employed for hoisting the ore from the mine, not with buckets but with rectangular-shaped conveyances called “skips”.
  • the standard double drum hoist has been found to be no longer satisfactory, because it cannot handle the length of wire rope combined with the weight in the bucket.
  • the present invention provides a device for excavating a mine shaft, comprising a pair of drums, each drum having a pair of regions, each region wound with one of a pair of hoist ropes; four refuse carriers, each attached to one of the hoist ropes and drive means for driving the drums to deliver two carriers at a time to a work site in the shaft.
  • a device for removing refuse material from a work site in a mine shaft comprising a pair of drums, each drum having a pair of regions, each region to engage one of a pair of hoist ropes; four carriers for carrying the refuse material each carrier being attached to one of the hoist ropes, drive means for driving the drums, wherein the device is operable to deliver, in repetition, two groups of two carriers to the work site.
  • the drive means includes at least one drive motor and a transmission arrangement for driving both of the drums and the hoist ropes on one drum are wound oppositely to the hoist ropes on the other drum. In this manner, one drum lifts two loaded refuse carriers while the other drum lowers the other two empty refuse carriers.
  • a positioning means positions the carriers at the work site and provides four paths, each of which guides a corresponding carrier.
  • the positioning means includes four guide regions, each to receive one carrier.
  • the carrier may be provided by a bucket or other suitable conveyance for hoisting broken rock from the work site.
  • the driving step includes the step of coupling both of the drums to a single drive motor and a transmission arrangement.
  • the method includes the step of winding the hoist ropes on one drum opposite to the hoist ropes on the other drum, the step of positioning the carriers at the work site and the step of determining a difference in weight between the two carriers at the site.
  • the positioning step further includes the step of providing four guide regions, each to provide a path for one carrier.
  • the present invention provides a device for excavating a mine shaft, comprising a drum having a pair of regions, each region wound with one of a pair of hoist ropes; a pair of refuse carriers, each of which is attached to one of the hoist ropes and drive means for driving the drum to deliver the carriers to a work site in the shaft.
  • the present invention should significantly improve the rate of advance of sinking very deep shafts, with reduced electrical energy consumed to perform the task.
  • FIG. 1 is a plan view of a shaft excavation
  • FIG. 2 is a sectional view taken on line 2 - 2 of FIG. 1 ;
  • FIG. 3 is schematic view of a device for used in the excavation of FIG. 1 .
  • a device 10 for removing refuse material from a work site in a mine shaft 12 has a pair of drums 14 , 16 , each of which has a pair of regions 14 a, 14 b, 16 a, 16 b.
  • One of four hoist ropes 18 a, 18 b, 20 a and 20 b is wound on each region. It can be seen from FIG. 3 that the hoist ropes on drum 14 are wound oppositely to the hoist ropes on the other drum 16 .
  • Each carrier 30 a, 30 b, 32 a, 32 b in this case in the form of buckets, are provided for carrying refuse material between the work site and the surface.
  • Each bucket is attached to one of the hoist ropes.
  • a drive means is provided for driving the drums, wherein the device is operable to deliver, in repetition, two groups of two buckets to the work site.
  • the drive means includes a single drive motor 34 and a transmission arrangement 34 a for driving both drums.
  • more than one motor may be used and the transmission may include a mechanical electrical or other suitable transmission unit.
  • the axles of the drums are joined by a universal joint shown at 34 b, for delivering power from the motor 34 to the drum 16 via drum 14 .
  • a positioning means shown generally at 40 positions the buckets at the work site 12 .
  • the positioning means includes a frame assembly 42 with four guide regions or wells 44 which in turn provide four paths, each for a corresponding bucket.
  • FIG. 2 shows a shaft excavation with one arrangement for two buckets at the work site, in this case the bottom of the shaft excavation in position where the buckets may be weighed before being simultaneously hoisted to the surface.
  • the device 10 utilizes the unused compartment of the drums of a conventional multi-rope mine hoist by being wound with an additional wire rope, being substantially identical to the length, weight, construction and diameter of the wire rope already wound in the other compartment of each drum.
  • the free end the wire ropes are each fitted to a shaft sinking bucket of substantially identical weight and volumetric capacity, that is within about three percent.
  • the drums are driven in the same direction, but because the drums are wound opposite to one another, one drum winds up its wire ropes while the other unwinds its wire ropes.
  • the motor drives the drum 16 to wind up the wire ropes 20 a, 20 b and thus hoist the buckets upward toward the surface.
  • the buckets 32 a, 32 b (empty and at the surface) are lowered as a result of the unwinding of the wire ropes 18 a, 18 b.
  • Each bucket is also provided with a guidance device (known as a cross-head) shown at 46 , wherein each guidance device is of substantially identical weight and dimension.
  • the guidance device is used to keep the shaft sinking bucket confined to its designated travel path as it rises and descends in the shaft.
  • the filled buckets maybe weighed by a device that determines the rope-end load by measuring the hydraulic pressure of compensating support devices at the sheave wheel atop the head frame, or by other means such as a simple level made from a clear plastic hose filled with water. In this latter case, if the filled buckets hang to the same level, normally they are of equal weight. Once the shaft men are suitably trained, they may be able to judge, by eye, when the buckets have substantially the same weight, to make measurement otherwise unnecessary.
  • the weights of the filled buckets should be within 1 ⁇ 2 tonne (500 kilograms) of one another. If not, broken rock is removed from the heavier bucket or added to the lighter bucket before both are hoisted simultaneously to surface.
  • a weighing system that can determine that the rope-end loads are nearly equal is desirable, in some cases, to ensure that the buckets reach the dump position on surface simultaneously. This is due to the fact that the wire ropes stretch under load. As a consequence, if the loading is not equal the buckets will reach surface one ahead of the other.
  • e FL/EA
  • e the difference in elevation of the buckets when they have reached the surface dump in the head frame
  • F the rope-end load in Kilonewtons (kn.)
  • L the length of wire rope between the surface dump and the shaft bottom in meters
  • E the modulus of elasticity of the roper in Gigapascals (GPa)
  • A is the area of circle enclosing the wire rope section in square millimeters.
  • device 10 provides a method for hoisting or elevating shot ( or broken) rock more efficiently during the excavation of a deep mine shaft. This is done by simultaneously hoisting two shaft sinking buckets (or other conveyances) toward the surface of the shaft, while two others are lowered into the shaft. This allows the full capacity of a multi-rope double drum winder (such as a BMR hoist, for example) to be utilized for shaft sinking. Moreover, it increases the efficiency of the electrical motors driving the BMR hoist since it may be run at near its design capacity.
  • a multi-rope double drum winder such as a BMR hoist, for example
  • the above device makes use of a pair of drums, each coupled with a pair of buckets, there may be some cases where a single drum can be used instead of two.
  • the single drum would have a pair of regions, each region wound with one of a pair of hoist ropes.
  • Each of a pair of refuse carrier may then be attached to one of the hoist ropes and drive means can be provided for driving the single drum to deliver the carriers to a work site in the shaft.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Earth Drilling (AREA)

Abstract

Disclosed is a device for excavating a mine shaft, comprising a pair of drums, each drum having a pair of regions. Each region is wound with one of a pair of hoist ropes. The device is provided with four refuse carriers, each of which is attached to one of the hoist ropes. Drive means is also provided for driving the drums to deliver two carriers at a time to a work site in the shaft.

Description

    BACKGROUND OF THE INVENTION
  • 1. Field of the Invention
  • The present invention relates to mining and more particularly to the hoisting of refuse materials from a mine shaft work site.
  • 2. Description of the Related Art
  • Shaft excavation in hard rock is carried out by drilling and loading the drilled bores with explosives which are then detonated. The broken rock must then be hoisted to the surface. This is typically done with large steel buckets.
  • For shafts less than one and one-half kilometers deep, a standard double drum mine hoist is normally employed to hoist the shaft buckets up and to lower them down. The same hoist may later be employed for hoisting the ore from the mine, not with buckets but with rectangular-shaped conveyances called “skips”. However, as the working depth of recent mines has exceeded two kilometers, the standard double drum hoist has been found to be no longer satisfactory, because it cannot handle the length of wire rope combined with the weight in the bucket.
  • One mining concern is known to have attempted to overcome the problem by using a multi-rope hoist known as the “Koepe” winder or friction hoist in a mine shaft with a depth of nearly two kilometers. However, this hoist was found to be unsatisfactory because the “tail ropes” had a tendency of tangling and the hoist rope was found to have a severely short life span (in some cases as little as six weeks).
  • Others have modified the double drum hoist by dividing each drum into two separate compartments and by winding identically sized ropes of standard diameter in each compartment. In this case, the ropes from one drum were attached to a single conveyance (skip). This type of hoist has enjoyed great commercial success and is known today as the BMR (Blair multi-rope) hoist. The BMR hoist is in use at nearly all deep mines in two configurations, one using a mechanical coupling (double universal joint) to connect a single motor to the shafts of both hoist drums. The other makes use of an electric coupling between the single motor and the hoist drum shafts.
  • When a very deep shaft is to be sunk (or excavated) for a new mine it is normal practice to use a BMR hoist to remove the broken rock, since the BMR hoist can later be used when the mine is in operation to raise ore. However, during the shaft sinking stage, the BMR hoist is not fully utilized. The two ropes on each drum cannot be attached to one shaft sinking bucket, in view of the above mentioned tangling problem. In addition, in order to make the BMR hoist applicable for both shaft sinking and mine operation, the hoist motor was found to be severely over-sized for the shaft sinking phase. This meant that the motor had to run at reduced capacity (approximately one half the horsepower requirement for which it was designed. In addition, the efficiency of an over-sized electrical motor is reduced when operating at a fraction of its design rating and this resulted in a waste of about ten percent of the electrical power fed to the hoist.
  • Mine shafts are currently being excavated and contemplated for excavation to even greater depths (approximately 2½ kilometers). Therefore, there remains an urgent need for a practical device which is capable of hoisting broken rock during a shaft sinking procedure for extremely deep mine shafts, with sufficient speed and economy.
  • SUMMARY OF THE INVENTION
  • Briefly stated, the present invention provides a device for excavating a mine shaft, comprising a pair of drums, each drum having a pair of regions, each region wound with one of a pair of hoist ropes; four refuse carriers, each attached to one of the hoist ropes and drive means for driving the drums to deliver two carriers at a time to a work site in the shaft.
  • In another aspect of the present invention, there is provided a device for removing refuse material from a work site in a mine shaft, comprising a pair of drums, each drum having a pair of regions, each region to engage one of a pair of hoist ropes; four carriers for carrying the refuse material each carrier being attached to one of the hoist ropes, drive means for driving the drums, wherein the device is operable to deliver, in repetition, two groups of two carriers to the work site.
  • Preferably, the drive means includes at least one drive motor and a transmission arrangement for driving both of the drums and the hoist ropes on one drum are wound oppositely to the hoist ropes on the other drum. In this manner, one drum lifts two loaded refuse carriers while the other drum lowers the other two empty refuse carriers.
  • In one embodiment, a positioning means positions the carriers at the work site and provides four paths, each of which guides a corresponding carrier. In one example the positioning means includes four guide regions, each to receive one carrier.
  • The carrier may be provided by a bucket or other suitable conveyance for hoisting broken rock from the work site.
  • In yet another of its aspects, there is provided a method for excavating a mine shaft, comprising the steps of:
  • providing a pair of drums;
  • dividing each drum into a pair of regions;
  • winding each region with one of a pair of hoist ropes;
  • providing four refuse carriers and attaching each to one of the hoist ropes; and
  • driving the drums in order deliver two carriers at a time to a work site in the shaft.
  • Preferably, the driving step includes the step of coupling both of the drums to a single drive motor and a transmission arrangement.
  • In one embodiment, the method includes the step of winding the hoist ropes on one drum opposite to the hoist ropes on the other drum, the step of positioning the carriers at the work site and the step of determining a difference in weight between the two carriers at the site. Preferably, the positioning step further includes the step of providing four guide regions, each to provide a path for one carrier.
  • In yet another of its aspects, the present invention provides a device for excavating a mine shaft, comprising a drum having a pair of regions, each region wound with one of a pair of hoist ropes; a pair of refuse carriers, each of which is attached to one of the hoist ropes and drive means for driving the drum to deliver the carriers to a work site in the shaft.
  • The present invention should significantly improve the rate of advance of sinking very deep shafts, with reduced electrical energy consumed to perform the task.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • A preferred embodiment of the present invention will be provided, by way of example only, with reference to the appended drawings, in which:
  • FIG. 1 is a plan view of a shaft excavation;
  • FIG. 2 is a sectional view taken on line 2-2 of FIG. 1; and
  • FIG. 3 is schematic view of a device for used in the excavation of FIG. 1.
  • DESCRIPTION OF THE PREFERRED EMBODIMENTS
  • Referring to the figures, there is provided a device 10 for removing refuse material from a work site in a mine shaft 12. The device has a pair of drums 14, 16, each of which has a pair of regions 14 a, 14 b, 16 a, 16 b. One of four hoist ropes 18 a, 18 b, 20 a and 20 b is wound on each region. It can be seen from FIG. 3 that the hoist ropes on drum 14 are wound oppositely to the hoist ropes on the other drum 16.
  • Four carriers 30 a, 30 b, 32 a, 32 b, in this case in the form of buckets, are provided for carrying refuse material between the work site and the surface. Each bucket is attached to one of the hoist ropes.
  • A drive means is provided for driving the drums, wherein the device is operable to deliver, in repetition, two groups of two buckets to the work site. The drive means includes a single drive motor 34 and a transmission arrangement 34 a for driving both drums. However, more than one motor may be used and the transmission may include a mechanical electrical or other suitable transmission unit. In this case, the axles of the drums are joined by a universal joint shown at 34 b, for delivering power from the motor 34 to the drum 16 via drum 14.
  • A positioning means shown generally at 40 positions the buckets at the work site 12. The positioning means includes a frame assembly 42 with four guide regions or wells 44 which in turn provide four paths, each for a corresponding bucket.
  • FIG. 2 shows a shaft excavation with one arrangement for two buckets at the work site, in this case the bottom of the shaft excavation in position where the buckets may be weighed before being simultaneously hoisted to the surface.
  • Thus, the device 10 utilizes the unused compartment of the drums of a conventional multi-rope mine hoist by being wound with an additional wire rope, being substantially identical to the length, weight, construction and diameter of the wire rope already wound in the other compartment of each drum. The free end the wire ropes are each fitted to a shaft sinking bucket of substantially identical weight and volumetric capacity, that is within about three percent.
  • During operation, the drums are driven in the same direction, but because the drums are wound opposite to one another, one drum winds up its wire ropes while the other unwinds its wire ropes. With two buckets, for example buckets 30 a, 30 b, filled with broken rock at the work site, the motor drives the drum 16 to wind up the wire ropes 20 a, 20 b and thus hoist the buckets upward toward the surface. Meanwhile, the buckets 32 a, 32 b (empty and at the surface) are lowered as a result of the unwinding of the wire ropes 18 a, 18 b.
  • Each bucket is also provided with a guidance device (known as a cross-head) shown at 46, wherein each guidance device is of substantially identical weight and dimension. The guidance device is used to keep the shaft sinking bucket confined to its designated travel path as it rises and descends in the shaft.
  • When the two descending buckets reach the positioning means 40 near the shaft bottom their cross-heads are automatically detached when they abut the frame assembly 42 situated in their travel path. The two buckets are lowered further through the wells 44 to a point just beneath the frame assembly 40 called the “hanging mark”. At this point, when the shaft men are ready for the buckets on the shaft bottom they “ring it down”, by sending a message to the surface for the motor to be operated at reduced speed, so that the buckets can travel downward at reduced speed without guidance to a leveled area on the pile of broken rock. Here the buckets are filled with broken rock by a machine designed for that purpose and known to those skilled in the art.
  • When the buckets are full, a message is then conveyed to the surface and the motor is activated in reverse, causing the buckets to be hoisted to just clear the broken rock pile. Here, the wire ropes are allowed to “steady” themselves. The filled buckets maybe weighed by a device that determines the rope-end load by measuring the hydraulic pressure of compensating support devices at the sheave wheel atop the head frame, or by other means such as a simple level made from a clear plastic hose filled with water. In this latter case, if the filled buckets hang to the same level, normally they are of equal weight. Once the shaft men are suitably trained, they may be able to judge, by eye, when the buckets have substantially the same weight, to make measurement otherwise unnecessary.
  • Generally, the weights of the filled buckets should be within ½ tonne (500 kilograms) of one another. If not, broken rock is removed from the heavier bucket or added to the lighter bucket before both are hoisted simultaneously to surface.
  • A weighing system that can determine that the rope-end loads are nearly equal is desirable, in some cases, to ensure that the buckets reach the dump position on surface simultaneously. This is due to the fact that the wire ropes stretch under load. As a consequence, if the loading is not equal the buckets will reach surface one ahead of the other. To determine the allowable out of balance load the following formula may be used:
    e=FL/EA
    where e is the difference in elevation of the buckets when they have reached the surface dump in the head frame, F is the rope-end load in Kilonewtons (kn.), L is the length of wire rope between the surface dump and the shaft bottom in meters, E is the modulus of elasticity of the roper in Gigapascals (GPa) and A is the area of circle enclosing the wire rope section in square millimeters.
  • Thus for a difference in “end load” (weight of the bucket and its payload) of 500 kg, will produce a force of 4.9 kn at the rope-end. With a length of 2.600 kilometers; a modulus of 65 GPa; and a rope diameter of 51 millimeters, this weight difference will produce a differential rope stretch of 0.096 meters.
  • Thus, device 10 provides a method for hoisting or elevating shot ( or broken) rock more efficiently during the excavation of a deep mine shaft. This is done by simultaneously hoisting two shaft sinking buckets (or other conveyances) toward the surface of the shaft, while two others are lowered into the shaft. This allows the full capacity of a multi-rope double drum winder (such as a BMR hoist, for example) to be utilized for shaft sinking. Moreover, it increases the efficiency of the electrical motors driving the BMR hoist since it may be run at near its design capacity.
  • While the above device makes use of a pair of drums, each coupled with a pair of buckets, there may be some cases where a single drum can be used instead of two. In this case, the single drum would have a pair of regions, each region wound with one of a pair of hoist ropes. Each of a pair of refuse carrier may then be attached to one of the hoist ropes and drive means can be provided for driving the single drum to deliver the carriers to a work site in the shaft.

Claims (25)

1. A device for excavating a mine shaft, comprising a pair of drums, each drum having a pair of regions, each region wound with one of a pair of hoist ropes; four refuse carriers, each attached to one of said hoist ropes and drive means for driving said drums to deliver two carriers at a time to a work site in the shaft.
2. A device as defined in claim 1 wherein the drive means includes a single drive motor and a transmission arrangement for driving both of said drums.
3. A device as defined in claim 1 wherein the hoist ropes on one drum are wound oppositely to the hoist ropes on the other drum.
4. A device as defined in claim 1 further comprising positioning means for positioning said carriers at said work site.
5. A device as defined in claim 4 wherein said positioning means provides four paths, each path for a corresponding carrier.
6. A device as defined in claim 5 wherein said positioning means includes four guide regions, each to receive one carrier.
7. A device as defined in claim 1 further comprising means for determining a difference in weight between the two carriers at said site.
8. A device as defined in claim 1 wherein each carrier includes a bucket.
9. A device for removing refuse material from a work site in a mine shaft, comprising a pair of drums, each drum having a pair of regions, each region wound with one of a pair of hoist ropes; four carriers for carrying the refuse material each carrier being attached to one of said hoist ropes, drive means for driving said drums, wherein the device is operable to deliver, in repetition, two groups of two carriers to the work site.
10. A device as defined in claim 9 wherein the drive means includes at least one drive motor and a transmission arrangement for driving both of said drums.
11. A device as defined in claim 9 wherein the hoist ropes on one drum are wound oppositely to the hoist ropes on the other drum.
12. A device as defined in claim 9 further comprising positioning means for positioning said carriers at said work site.
13. A device as defined in claim 12 wherein said positioning means provides four paths, each path for a corresponding carrier.
14. A device as defined in claim 13 wherein said positioning means includes four sleeve regions, each to receive one carrier.
15. A device as defined in claim 9 wherein each carrier includes a bucket.
16. A device as defined in claim 9 further comprising means for determining a difference in weight between the two carriers at said site.
17. A method for excavating a mine shaft, comprising the steps of:
providing a pair of drums;
dividing each drum into a pair of regions;
winding each region with one of a pair of hoist ropes;
providing four refuse carriers and attaching each to one of said hoist ropes; and
driving the drums in order deliver two carriers at a time to a work site in the shaft.
18. A method as defined in claim 17 wherein the driving step includes the step of coupling both of said drums to a single drive motor and a transmission arrangement.
19. A method as defined in claim 17 further comprising the step of winding the hoist ropes on one drum opposite to the hoist ropes on the other drum.
20. A method as defined in claim 17 further comprising the step of positioning said carriers at said worksite.
21. A method as defined in claim 20 wherein the positioning step includes the step of providing four paths, each path for a corresponding carrier.
22. A method as defined in claim 21 wherein the positioning step further includes the step of providing four guide regions, each to receive one carrier.
23. A method as defined in claim 17 further comprising the step of determining a difference in weight between the two carriers at said site.
24. A method as defined in claim 17 wherein each carrier includes a bucket.
25. A device for excavating a mine shaft, comprising a drum having a pair of regions, each region wound with one of a pair of hoist ropes; a pair of refuse carriers, each of which is attached to one of said hoist ropes and drive means for driving said drum to deliver the carriers to a work site in the shaft.
US09/773,524 2000-02-03 2001-02-02 Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts Abandoned US20070273196A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US09/773,524 US20070273196A1 (en) 2000-02-03 2001-02-02 Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US18004400P 2000-02-03 2000-02-03
US09/773,524 US20070273196A1 (en) 2000-02-03 2001-02-02 Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts

Publications (1)

Publication Number Publication Date
US20070273196A1 true US20070273196A1 (en) 2007-11-29

Family

ID=38748841

Family Applications (1)

Application Number Title Priority Date Filing Date
US09/773,524 Abandoned US20070273196A1 (en) 2000-02-03 2001-02-02 Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts

Country Status (1)

Country Link
US (1) US20070273196A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120318581A1 (en) * 2009-06-30 2012-12-20 Rocky Lynn Webb Forming a shaft for an underground mine
CN104590974A (en) * 2014-11-28 2015-05-06 中信重工机械股份有限公司 Multi-rope composite type mine elevator
US10385691B2 (en) * 2013-08-23 2019-08-20 Technological Resources Pty. Limited Skip and crosshead

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3572703A (en) * 1968-04-25 1971-03-30 Chesapeake Automated Products Three dimensional game and vendor apparatus
US3789280A (en) * 1970-11-12 1974-01-29 Westinghouse Canada Ltd Multicable drum hoisting system
US3982728A (en) * 1974-06-10 1976-09-28 Fullerton, Hodgart & Barclay Limited Braking apparatus for hoists
US5678805A (en) * 1994-11-10 1997-10-21 Moser; Harold E. Method and apparatus for retrieving lost golf balls including golf ball picker and power drive device for moving the picker
US6102372A (en) * 1997-07-23 2000-08-15 Mannesmann Ag Rope arrangement for the suspension of attachment means at a carrying device arranged above it
US20060197073A1 (en) * 2005-03-02 2006-09-07 Studer Ronald M Bi-directional winch
US7556240B1 (en) * 2006-09-15 2009-07-07 Mw Industries, Inc. Rig drawworks

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3572703A (en) * 1968-04-25 1971-03-30 Chesapeake Automated Products Three dimensional game and vendor apparatus
US3789280A (en) * 1970-11-12 1974-01-29 Westinghouse Canada Ltd Multicable drum hoisting system
US3982728A (en) * 1974-06-10 1976-09-28 Fullerton, Hodgart & Barclay Limited Braking apparatus for hoists
US5678805A (en) * 1994-11-10 1997-10-21 Moser; Harold E. Method and apparatus for retrieving lost golf balls including golf ball picker and power drive device for moving the picker
US6102372A (en) * 1997-07-23 2000-08-15 Mannesmann Ag Rope arrangement for the suspension of attachment means at a carrying device arranged above it
US20060197073A1 (en) * 2005-03-02 2006-09-07 Studer Ronald M Bi-directional winch
US7273207B2 (en) * 2005-03-02 2007-09-25 Studer Ronald M Bi-directional winch
US7556240B1 (en) * 2006-09-15 2009-07-07 Mw Industries, Inc. Rig drawworks

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120318581A1 (en) * 2009-06-30 2012-12-20 Rocky Lynn Webb Forming a shaft for an underground mine
US8591151B2 (en) * 2009-06-30 2013-11-26 Technological Resouces Pty. Ltd. Forming a shaft for an underground mine
US10385691B2 (en) * 2013-08-23 2019-08-20 Technological Resources Pty. Limited Skip and crosshead
CN104590974A (en) * 2014-11-28 2015-05-06 中信重工机械股份有限公司 Multi-rope composite type mine elevator

Similar Documents

Publication Publication Date Title
CN101434358A (en) Elevator for deep foundation pit excavation by inverse construction method, and excavation system and method
CN101215940A (en) Boring and pole setting machine
CN115162942A (en) Rotary drilling rig drill rod component and rotary drilling rig
US20070273196A1 (en) Method and apparatus for utilizing the full capacity of a particular type of mine hoist for excavating deep shafts
AU778801B2 (en) Excavating a mine shaft
CA2313840A1 (en) Excavating a mine shaft
CN102344086B (en) Method for replacing lifting ropes of multi-rope frictional geared winch
CN101475120A (en) Coal mine automatic weighting and hoisting system
Carbogno Mine hoisting in deep shafts in the 1st half of 21st Century
RU137573U1 (en) MECHANIZED COMPLEX FOR PERFORMING VERTICAL TRUNKS OF MINING ENTERPRISES
CN214836104U (en) Low-clearance cast-in-situ bored pile construction pile machine
CN201334293Y (en) Hoist and excavation construction system used for deep foundation pit excavation using top-down method
CN207987947U (en) Overhanging type aquatic pile foundation operation platform
RU2039280C1 (en) Excavating and loading complex for opencast mining
WO2006024097A1 (en) Haulage system for pit mining
WO2021160798A1 (en) Method for introducing a soil penetrating tool into a soil and underground construction device
CN103213906B (en) Underground coal mine hydraulic filling double track lifting locomotive and hydraulic control system thereof
JP2002234484A (en) Load test method for work barge
RU186195U1 (en) Quarry lifting device
KR102639994B1 (en) Hoisting apparatus
CN206615949U (en) The improved Winch for mine dispatch of structure
JPH11200358A (en) Method and device for creating sand pile
CN216277871U (en) Hydraulic integrated machine for drilling and deslagging in vertical shaft
CN106638746B (en) Integrated casing drilling machine
CN206615948U (en) Reinforced mining car hauler

Legal Events

Date Code Title Description
AS Assignment

Owner name: J.S. REDPATH LIMITED, CANADA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:DE LA VERGNE, JOHN NICHOLAS;REEL/FRAME:012381/0677

Effective date: 20010528

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION