US20060275080A1 - Method and Apparatus for Offshore Drilling in Ice-Infested Waters - Google Patents
Method and Apparatus for Offshore Drilling in Ice-Infested Waters Download PDFInfo
- Publication number
- US20060275080A1 US20060275080A1 US11/422,382 US42238206A US2006275080A1 US 20060275080 A1 US20060275080 A1 US 20060275080A1 US 42238206 A US42238206 A US 42238206A US 2006275080 A1 US2006275080 A1 US 2006275080A1
- Authority
- US
- United States
- Prior art keywords
- base
- support shaft
- topside
- sea floor
- topside structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B43/00—Improving safety of vessels, e.g. damage control, not otherwise provided for
- B63B43/02—Improving safety of vessels, e.g. damage control, not otherwise provided for reducing risk of capsizing or sinking
- B63B43/10—Improving safety of vessels, e.g. damage control, not otherwise provided for reducing risk of capsizing or sinking by improving buoyancy
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/0017—Means for protecting offshore constructions
- E02B17/0021—Means for protecting offshore constructions against ice-loads
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
- E02B17/021—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto with relative movement between supporting construction and platform
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B2211/00—Applications
- B63B2211/06—Operation in ice-infested waters
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0039—Methods for placing the offshore structure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0056—Platforms with supporting legs
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0056—Platforms with supporting legs
- E02B2017/0073—Details of sea bottom engaging footing
- E02B2017/0086—Large footings connecting several legs or serving as a reservoir for the storage of oil or gas
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0095—Connections of subsea risers, piping or wiring with the offshore structure
Definitions
- the present invention relates to a method and apparatus for offshore drilling in ice-infested waters.
- the problem resides in a permanent polar ice pack that typically exists over much of this Arctic region and varies in extent depending upon the time of year.
- the size of the ice pack expands to positions very close to (and, in some instances, in direct contact with) the shoreline.
- ice sheets which are fixed to the shoreline cover these areas and may extend 25 miles or more offshore.
- the present invention is directed to a method for utilizing over open water a drilling platform comprising a base, a hollow, airtight topside structure, and a support shaft extending vertically from the base through the topside structure, the method including the steps of maintaining positive buoyancy of the topside structure, lowering the base to the sea floor; and thereafter raising the topside structure along the support shaft until it reaches the top of the support shaft.
- the present invention is directed to an offshore structure for placement on a sea floor in a body of water containing moving ice masses, which impart Environmental Loads to the structure;
- the offshore structure includes a base which contacts the sea floor, the base having sufficient horizontal cross-sectional area such that a bearing pressure and a horizontal shear force, which result from Environmental Loads and which are transferred to the sea floor foundation by the foundation base, are less than at least one of a predetermined shear capacity and a predetermined bearing capacity for the sea floor foundation; and a hollow, airtight topside structure located at or above the waterline of the body which is supported by a support shaft extending vertically from the base through the topside structure.
- the present invention provides for economical access to remote oil and gas reservoirs that have been traditionally inaccessible by conventional drilling methods by allowing for year-round offshore drilling in both deep and shallow waters in the Arctic region.
- the present invention also provides for substantial capital costs savings by reducing the amount of steel required typically associated with conventional offshore drilling facilities designed to operate in the Arctic region.
- FIG. 1 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention during transit.
- FIG. 2 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention during installation.
- FIG. 3 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention during operation.
- FIG. 4 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention after operation.
- the present invention is a mobile offshore drilling unit 10 that may be used in a body of water that contains moving ice masses.
- Mobile offshore drilling unit 10 has a topside structure 12 , a support shaft 14 , and a base 16 .
- the topside structure 12 may be of any design suitable for conducting offshore hydrocarbon drilling and/or production operations.
- the topside structure 12 preferably includes a drilling derrick 18 and a hole (not shown) through the topside structure 12 to allow the topside structure 12 to jack itself up and down a support shaft 14 .
- the topside structure 12 is hollow and watertight to provide sufficient positive buoyancy and hydrostatic stability for the mobile offshore drilling unit 10 during transit to, installation on, and/or removal from an offshore drilling or production site.
- the size of the topside structure 12 may vary, depending upon such factors that may include the floating performance of the mobile offshore drilling unit 10 during transit and the working space required for drilling and other related operations. Those skilled in the art will understand and be able to determine the optimal size of the topside structure 12 required for specific drilling operations.
- the support shaft 14 suitable for the subject invention may be any support shaft suitable for application on conventional jack-up units.
- the support shaft 14 is cylindrical and has a hollow inner diameter (hereinafter referred to as “the moon pool”) to allow for drilling and production operations to occur within the support shaft 14 .
- the moon pool a hollow inner diameter
- at least one guiding tube (not shown) is mounted along the inner wall of the support shaft 14 close to the bottom of the base 16 , more preferably at least two guiding tubes, even more preferably at least three guiding tubes, and most preferably at least four guiding tubes for best results.
- the size of the support shaft 14 may vary, depending upon such factors that may include water depth, ice load, wave load, seismic load, geotechnical conditions and the moon pool size required for drilling operations. Those skilled in the art will understand the optimal size of the support shaft 14 required for specific drilling operations.
- the base 16 suitable for the subject invention is designed to be placed on and in contact with the sea floor.
- the base 16 is large enough to prevent slippage between the base and the sea floor foundation, to prevent bearing capacity of the sea floor from being exceeded, and to prevent a toppling moment of the mobile offshore drilling unit 10 from occurring due to the Environment Load that may act on the mobile offshore drilling unit 10 .
- the base 16 has sufficient horizontal cross-sectional area such that the bearing pressure and a horizontal shear force, which result from the Environmental Loads and which are transferred to the sea floor foundation by the base 16 , are less than at least one of a predetermined shear capacity exerted by surface ice sheets and a predetermined bearing capacity for the sea floor.
- the size of the base 16 may vary, depending upon such factors that may include water depth, ice load, wave load, seismic load, and geotechnical conditions resident at the drilling and production site. Those skilled in the art will understand the optimal size of the support base 16 required for specific drilling operations.
- a channel (not shown) is built in the bottom of the base 16 . This channel connects the bottom of the support shaft 14 to the sea floor so that the base 16 can straddle across subsea pipelines and umbilicals installed on the well.
- the base 16 is raised to the bottom of the topside structure 12 so that the mobile offshore drilling unit 10 creates minimum draft during transit.
- the base 16 is deballasted to decrease draft during transit of mobile offshore drilling unit 10 .
- the topside structure 12 provides the hydrostatic stability during transit, thereby reducing the need for significant ballasting in the base 16 to maintain stability of the mobile offshore drilling unit 10 during transit. It is also preferred that the base 16 is maintained below the surface of the water during transit to reduce the Environmental Load across the larger cross-section of the base 16 .
- the mobile offshore drilling unit 10 can be moved by its own propulsion or towed by an external craft, such as a conventional towboat during open water season or an ice breaker during the winter season.
- the base 16 is ballasted down until it reaches the sea floor.
- the topside structure 12 is then jacked up along the support shaft 14 until it reaches the top of the support shaft 14 . Once the top of the support shaft 14 becomes level with the bottom of the derrick 18 , the topside structure 12 is preferably locked into place.
- at least one pile (not shown) will be driven through a guiding tube into the sea floor to help prevent skidding of the base 16 across the sea floor and to guide offshore drilling structures for future operations, such as subsea well intervention.
- the derrick 18 is preferably skidded over the moon pool (inside the shaft) to start drilling operations.
- drilling operations and well completions are conducted within the inner diameter of the support shaft 14 .
- the installation procedure is reversed and the base 16 is raised again for transit to the next location.
- the piles driven through the guide tubes into the sea floor during the installation of the mobile offshore drilling unit 10 restricts the lateral movement of the base 16 until sufficient clearance between the base 16 and sea floor is reached. This aids in the prevention of damage to equipment utilized during the drilling and completion of subsea wells.
- the piles will accurately guide the setdown of the mobile offshore drilling unit 10 onto the subsea well.
- the present invention provides for economical access to remote oil and gas reservoirs that have been traditionally inaccessible by conventional drilling methods by allowing for year-round offshore drilling in both deep and shallow waters in the Arctic region. This is primarily due to the use of a hollows and watertight topside structure as a stability device during transit and installation of the mobile offshore drilling unit. Consequently, there is no need for significant ballast in the base or a large shaft, thereby making the present invention more accessible to oil and gas reservoirs in shallower waters. Additionally, the use of a large base helps prevent slippage between the base and the sea floor foundation, to prevent bearing capacity of the sea floor from being exceeded, and to prevent a toppling moment of the mobile offshore drilling unit. The use of a large base in combination with only a single support shaft exposed to Environmental Loads allows for the mobile offshore drilling unit to operate on a year-round basis in the Arctic region, thereby making once inaccessible oil and gas reservoirs, accessible for exploration and production.
- the present invention also provides for substantial capital costs savings by reducing the amount of steel required typically associated with conventional offshore drilling facilities designed to operate in the Arctic region.
- the present invention uses the topside structure as a stability device during transit and installation of the mobile offshore drilling unit. Consequently, there is no need for significant ballast in the base or a large shaft. Additionally, after installation of the mobile offshore drilling unit, the topside structure jacks itself up to the top of the support shaft so that only the support shaft is exposed to Environmental Loads. As a result, the Environment Load impinging on the structure is substantially smaller, reducing the size requirement of the structure, and thereby resulting in a less expensive structure.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Ocean & Marine Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Earth Drilling (AREA)
Abstract
An offshore structure for placement on a sea floor in a body of water containing moving ice masses, which impart Environmental Loads to the structure; the offshore structure includes a base which contacts the sea floor, the base having sufficient horizontal cross-sectional area such that a bearing pressure and a horizontal shear force, which result from Environmental Loads and which are transferred to the sea floor foundation by the foundation base, are less than at least one of a predetermined shear capacity and a predetermined bearing capacity for the sea floor foundation; and a hollow, watertight topside structure located at or above the waterline of the body which is supported by a support shaft extending vertically from the base through the topside structure.
Description
- This application claims the benefit of the provisional U.S. Application Ser. No. 60/688,276, filed Jun. 7, 2005.
- The present invention relates to a method and apparatus for offshore drilling in ice-infested waters.
- Substantial known reserves of oil and gas exist in remote, often inaccessible areas, of the world. Many of these reserves are known to lie below ice-infested waters in the Arctic region, making year round exploration and production of such oil and gas reserves hazardous and uneconomical.
- In particular, the problem resides in a permanent polar ice pack that typically exists over much of this Arctic region and varies in extent depending upon the time of year. During the Arctic winter, the size of the ice pack expands to positions very close to (and, in some instances, in direct contact with) the shoreline. In those areas where the permanent ice pack does not come into direct contact with the shoreline, ice sheets which are fixed to the shoreline (known as land-fast ice) cover these areas and may extend 25 miles or more offshore.
- In the Arctic Ocean, for instance, the permanent ice pack slowly rotates and circulates, and land-fast ice also moves during the period in which it exists in the Arctic regions. The land-fast ice sheet moves randomly in response to tides, currents, winds and temperature changes. These ice masses in the Arctic may move as much as sixty feet per day and can exert substantial bearing pressures or horizontal shear forces. These pressures and forces exerted by such ice masses and/or waves are collectively referred to as “Environmental Loads.”
- In the past, it was believed that the major Environmental Loads acting on such offshore platforms resulted from moving ice masses impinging on the offshore platforms. Therefore, in the past, the limiting factor in the design of an offshore platform was whether it could resist the Environmental Loads. This resulted in efforts to design offshore platforms that resist such Environmental Loads and potentially allow for year-round drilling and production operations in the Arctic region.
- One such effort is U.S. Pat. No. 4,103,504 ('504 patent), which discloses a stationary offshore platform that employs pre-tensioned vibrating cables regularly spaced around the periphery of a top-side structure of the platform, forming a cable barrier around the top-side structure to break up ice prior to the ice making contact with the platform. The '504 patent also discloses the use of a compressible bladder to prevent the resulting broken ice from encroaching beyond the cable barrier. Another effort is U.S. Pat. No. 4,102,144 ('144 patent), which discloses a stationary offshore platform that employs an moveable ice-breaking shield surrounding a top-side structure of the platform; the shield elevates to break ice and is thereafter lowered to discharge the broken ice.
- While the platforms disclosed in the '504 and '144 patents may be effective for operation in deepwater Arctic applications, the large top heavy platforms are not designed to provide hydrostatic stability during the transit, installation and operation of the platforms, thereby preventing the installation and operation of a platform in shallower ice-infested waters. Additionally, such platforms require large amounts of costly Arctic grade steel, thereby substantially increasing the capital expense associated with building such platforms.
- Although these efforts have advanced the art of drilling and producing hydrocarbons in the Arctic region, there is still a need for economical mobile offshore structures that allow for year-round drilling and production of hydrocarbons in both deep and shallow water in the Arctic.
- We have now found that employing a hollow and watertight topside structure on a mobile offshore drilling unit provides sufficient positive buoyancy and hydrostatic stability for the drilling unit during the transit to, the installation on, and/or the removal from a offshore drilling or production site.
- We have also found that employing a large base in conjunction with a single support shaft base prevents slippage between the base and the sea floor foundation, the bearing capacity of the sea floor from being exceeded, and the toppling moment of the mobile offshore drilling units from being exceeded.
- Therefore, the present invention is directed to a method for utilizing over open water a drilling platform comprising a base, a hollow, airtight topside structure, and a support shaft extending vertically from the base through the topside structure, the method including the steps of maintaining positive buoyancy of the topside structure, lowering the base to the sea floor; and thereafter raising the topside structure along the support shaft until it reaches the top of the support shaft.
- In another embodiment, the present invention is directed to an offshore structure for placement on a sea floor in a body of water containing moving ice masses, which impart Environmental Loads to the structure; the offshore structure includes a base which contacts the sea floor, the base having sufficient horizontal cross-sectional area such that a bearing pressure and a horizontal shear force, which result from Environmental Loads and which are transferred to the sea floor foundation by the foundation base, are less than at least one of a predetermined shear capacity and a predetermined bearing capacity for the sea floor foundation; and a hollow, airtight topside structure located at or above the waterline of the body which is supported by a support shaft extending vertically from the base through the topside structure.
- The present invention provides for economical access to remote oil and gas reservoirs that have been traditionally inaccessible by conventional drilling methods by allowing for year-round offshore drilling in both deep and shallow waters in the Arctic region.
- The present invention also provides for substantial capital costs savings by reducing the amount of steel required typically associated with conventional offshore drilling facilities designed to operate in the Arctic region.
-
FIG. 1 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention during transit. -
FIG. 2 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention during installation. -
FIG. 3 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention during operation. -
FIG. 4 is a cross-sectional view, showing the mobile offshore drilling unit according to the subject invention after operation. - While this invention has many different embodiments, the drawings and detailed description illustrate the specific embodiments of the invention. However, the present disclosure is for the purposes of illustration and example, and is not intended to limit the invention to the specific embodiments disclosed herein.
- Referring now to
FIG. 1 , the present invention is a mobileoffshore drilling unit 10 that may be used in a body of water that contains moving ice masses. Mobileoffshore drilling unit 10 has atopside structure 12, asupport shaft 14, and abase 16. - The
topside structure 12 may be of any design suitable for conducting offshore hydrocarbon drilling and/or production operations. Thetopside structure 12, however, preferably includes adrilling derrick 18 and a hole (not shown) through thetopside structure 12 to allow thetopside structure 12 to jack itself up and down asupport shaft 14. It is also preferred that thetopside structure 12 is hollow and watertight to provide sufficient positive buoyancy and hydrostatic stability for the mobileoffshore drilling unit 10 during transit to, installation on, and/or removal from an offshore drilling or production site. The size of thetopside structure 12 may vary, depending upon such factors that may include the floating performance of the mobileoffshore drilling unit 10 during transit and the working space required for drilling and other related operations. Those skilled in the art will understand and be able to determine the optimal size of thetopside structure 12 required for specific drilling operations. - The
support shaft 14 suitable for the subject invention may be any support shaft suitable for application on conventional jack-up units. Preferably, however, thesupport shaft 14 is cylindrical and has a hollow inner diameter (hereinafter referred to as “the moon pool”) to allow for drilling and production operations to occur within thesupport shaft 14. It is preferred that at least one guiding tube (not shown) is mounted along the inner wall of thesupport shaft 14 close to the bottom of thebase 16, more preferably at least two guiding tubes, even more preferably at least three guiding tubes, and most preferably at least four guiding tubes for best results. The size of thesupport shaft 14 may vary, depending upon such factors that may include water depth, ice load, wave load, seismic load, geotechnical conditions and the moon pool size required for drilling operations. Those skilled in the art will understand the optimal size of thesupport shaft 14 required for specific drilling operations. - The
base 16 suitable for the subject invention is designed to be placed on and in contact with the sea floor. In a preferred embodiment, thebase 16 is large enough to prevent slippage between the base and the sea floor foundation, to prevent bearing capacity of the sea floor from being exceeded, and to prevent a toppling moment of the mobileoffshore drilling unit 10 from occurring due to the Environment Load that may act on the mobileoffshore drilling unit 10. In a preferred embodiment, thebase 16 has sufficient horizontal cross-sectional area such that the bearing pressure and a horizontal shear force, which result from the Environmental Loads and which are transferred to the sea floor foundation by thebase 16, are less than at least one of a predetermined shear capacity exerted by surface ice sheets and a predetermined bearing capacity for the sea floor. The size of thebase 16 may vary, depending upon such factors that may include water depth, ice load, wave load, seismic load, and geotechnical conditions resident at the drilling and production site. Those skilled in the art will understand the optimal size of thesupport base 16 required for specific drilling operations. In a preferred embodiment, a channel (not shown) is built in the bottom of thebase 16. This channel connects the bottom of thesupport shaft 14 to the sea floor so that thebase 16 can straddle across subsea pipelines and umbilicals installed on the well. - During transit of the mobile
offshore drilling unit 10 over open water, thebase 16 is raised to the bottom of thetopside structure 12 so that the mobileoffshore drilling unit 10 creates minimum draft during transit. Preferably, thebase 16 is deballasted to decrease draft during transit of mobileoffshore drilling unit 10. Thetopside structure 12 provides the hydrostatic stability during transit, thereby reducing the need for significant ballasting in thebase 16 to maintain stability of the mobileoffshore drilling unit 10 during transit. It is also preferred that thebase 16 is maintained below the surface of the water during transit to reduce the Environmental Load across the larger cross-section of thebase 16. The mobileoffshore drilling unit 10 can be moved by its own propulsion or towed by an external craft, such as a conventional towboat during open water season or an ice breaker during the winter season. - Referring now to
FIG. 2 , during installation, once the mobileoffshore drilling unit 10 is towed to the targeted location, thebase 16 is ballasted down until it reaches the sea floor. Thetopside structure 12 is then jacked up along thesupport shaft 14 until it reaches the top of thesupport shaft 14. Once the top of thesupport shaft 14 becomes level with the bottom of thederrick 18, thetopside structure 12 is preferably locked into place. In a preferred embodiment, after the mobileoffshore drilling unit 10 is installed and before drilling commences, at least one pile (not shown) will be driven through a guiding tube into the sea floor to help prevent skidding of thebase 16 across the sea floor and to guide offshore drilling structures for future operations, such as subsea well intervention. - Referring now to
FIG. 3 , upon completion of the installation, thederrick 18 is preferably skidded over the moon pool (inside the shaft) to start drilling operations. In a preferred embodiment, drilling operations and well completions are conducted within the inner diameter of thesupport shaft 14. - Referring now to
FIG. 4 , after drilling operations are completed and the open water season has arrived, the installation procedure is reversed and thebase 16 is raised again for transit to the next location. When thebase 16 is raised for transit, the piles driven through the guide tubes into the sea floor during the installation of the mobileoffshore drilling unit 10 restricts the lateral movement of the base 16 until sufficient clearance between the base 16 and sea floor is reached. This aids in the prevention of damage to equipment utilized during the drilling and completion of subsea wells. When the mobile offshore drilling unit is installed over existing subsea wells for intervention, the piles will accurately guide the setdown of the mobileoffshore drilling unit 10 onto the subsea well. - The present invention provides for economical access to remote oil and gas reservoirs that have been traditionally inaccessible by conventional drilling methods by allowing for year-round offshore drilling in both deep and shallow waters in the Arctic region. This is primarily due to the use of a hollows and watertight topside structure as a stability device during transit and installation of the mobile offshore drilling unit. Consequently, there is no need for significant ballast in the base or a large shaft, thereby making the present invention more accessible to oil and gas reservoirs in shallower waters. Additionally, the use of a large base helps prevent slippage between the base and the sea floor foundation, to prevent bearing capacity of the sea floor from being exceeded, and to prevent a toppling moment of the mobile offshore drilling unit. The use of a large base in combination with only a single support shaft exposed to Environmental Loads allows for the mobile offshore drilling unit to operate on a year-round basis in the Arctic region, thereby making once inaccessible oil and gas reservoirs, accessible for exploration and production.
- The present invention also provides for substantial capital costs savings by reducing the amount of steel required typically associated with conventional offshore drilling facilities designed to operate in the Arctic region. The present invention uses the topside structure as a stability device during transit and installation of the mobile offshore drilling unit. Consequently, there is no need for significant ballast in the base or a large shaft. Additionally, after installation of the mobile offshore drilling unit, the topside structure jacks itself up to the top of the support shaft so that only the support shaft is exposed to Environmental Loads. As a result, the Environment Load impinging on the structure is substantially smaller, reducing the size requirement of the structure, and thereby resulting in a less expensive structure.
Claims (12)
1. A method for utilizing over open water a drilling platform comprising a base, a hollow, watertight topside structure, and a support shaft extending vertically from the base through the topside structure, the method comprising the steps of:
(a) maintaining a positive buoyancy of the topside structure;
(b) lowering the base to the sea floor; and thereafter
(b) raising the topside structure along the support shaft until it reaches the top of the support shaft.
2. The method of claim 1 , wherein the topside structure is maintained at about the surface of the water during lowering step (b).
3. The method of claim 2 , further comprising the step of ballasting the base during lowering step (b).
4. The method of claim 3 , wherein the support shaft comprises a guiding tube.
5. The method of claim 4 , wherein a pile is installed through one or more guiding tube into the sea floor.
6. A method for transiting over body of water a drilling platform having a hollow topside structure, a cylindrical support shaft and a base, the method comprising the steps of:
(a) lowering the topside structure to the surface of the body of water;
(b) maintaining positive buoyancy of the topside structure over the body of water; and
(c) raising the base along a longitudinal axis of the support shaft wherein the base is maintained below the surface of the open water.
7. The method of claim 8 , further comprising the step of deballasting the base.
8. The method of claim 7 , wherein the topside structure is watertight.
9. An offshore structure for placement on a sea floor in a body of water containing moving ice masses, which impart Environmental Loads to the structure, comprising:
(a) a base which contacts the sea floor, the base having sufficient horizontal cross-sectional area such that a bearing pressure and a horizontal shear force, which result from Environmental Loads and which are transferred to the sea floor foundation by the foundation base, are less than at least one of a predetermined shear capacity and a predetermined bearing capacity for the sea floor foundation; and
(b) a hollow, watertight topside structure that is supported by a support shaft extending vertically from the base through the topside structure.
10. The offshore structure of claim 9 , wherein the topside structure is designed to maintain a positive buoyancy of the offshore structure in the body water.
11. The offshore structure of claim 10 , wherein the topside structure is moveable along a longitudinal axis of the support shaft.
12. The offshore structure of claim 11 , wherein a guiding tube is mounted along a surface of an inner diameter of the support shaft.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US11/422,382 US20060275080A1 (en) | 2005-06-07 | 2006-06-06 | Method and Apparatus for Offshore Drilling in Ice-Infested Waters |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US68827605P | 2005-06-07 | 2005-06-07 | |
US11/422,382 US20060275080A1 (en) | 2005-06-07 | 2006-06-06 | Method and Apparatus for Offshore Drilling in Ice-Infested Waters |
Publications (1)
Publication Number | Publication Date |
---|---|
US20060275080A1 true US20060275080A1 (en) | 2006-12-07 |
Family
ID=37102510
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/422,382 Abandoned US20060275080A1 (en) | 2005-06-07 | 2006-06-06 | Method and Apparatus for Offshore Drilling in Ice-Infested Waters |
Country Status (2)
Country | Link |
---|---|
US (1) | US20060275080A1 (en) |
WO (1) | WO2006133161A2 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2189576A1 (en) * | 2008-11-19 | 2010-05-26 | Flota Proyectos Singulares, S.A. | Foundation system for marine structures in deep water |
US8647017B2 (en) | 2011-02-09 | 2014-02-11 | Ausenco Canada Inc. | Gravity base structure |
US8657533B2 (en) | 2011-02-09 | 2014-02-25 | Ausenco Canada Inc. | Gravity base structure |
US20140326503A1 (en) * | 2011-11-23 | 2014-11-06 | Saipem S.P.A. | System and method of executing an underwater well drilling program in the bed of a body of water, and auxiliary floating unit |
WO2018148144A1 (en) * | 2017-02-13 | 2018-08-16 | Saudi Arabian Oil Company | Self-installing offshore platform |
US11685486B2 (en) | 2021-01-14 | 2023-06-27 | Saudi Arabian Oil Company | Resilient bumper and bumper system |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NO333296B1 (en) * | 2011-03-29 | 2013-04-29 | Kvaerner Eng | Mobile platform for offshore drilling and method of installation of the platform |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6761508B1 (en) * | 1999-04-21 | 2004-07-13 | Ope, Inc. | Satellite separator platform(SSP) |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
PL84214B1 (en) * | 1973-02-05 | 1976-03-31 | ||
DE2549000A1 (en) * | 1975-11-03 | 1977-05-12 | Strabag Bau Ag | PLATFORM FOR WORKING IN THE SEA |
US7037044B2 (en) * | 2003-10-15 | 2006-05-02 | Technip France | Deck-to-column connection for extendable draft platform |
-
2006
- 2006-06-06 US US11/422,382 patent/US20060275080A1/en not_active Abandoned
- 2006-06-06 WO PCT/US2006/021874 patent/WO2006133161A2/en active Application Filing
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6761508B1 (en) * | 1999-04-21 | 2004-07-13 | Ope, Inc. | Satellite separator platform(SSP) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2189576A1 (en) * | 2008-11-19 | 2010-05-26 | Flota Proyectos Singulares, S.A. | Foundation system for marine structures in deep water |
US8647017B2 (en) | 2011-02-09 | 2014-02-11 | Ausenco Canada Inc. | Gravity base structure |
US8657533B2 (en) | 2011-02-09 | 2014-02-25 | Ausenco Canada Inc. | Gravity base structure |
US20140326503A1 (en) * | 2011-11-23 | 2014-11-06 | Saipem S.P.A. | System and method of executing an underwater well drilling program in the bed of a body of water, and auxiliary floating unit |
US9512678B2 (en) * | 2011-11-23 | 2016-12-06 | Saipem S.P.A | System and method of executing an underwater well drilling program in the bed of a body of water, and auxiliary floating unit |
WO2018148144A1 (en) * | 2017-02-13 | 2018-08-16 | Saudi Arabian Oil Company | Self-installing offshore platform |
US10352010B2 (en) | 2017-02-13 | 2019-07-16 | Saudi Arabian Oil Company | Self-installing offshore platform |
US11685486B2 (en) | 2021-01-14 | 2023-06-27 | Saudi Arabian Oil Company | Resilient bumper and bumper system |
Also Published As
Publication number | Publication date |
---|---|
WO2006133161A3 (en) | 2007-04-05 |
WO2006133161A2 (en) | 2006-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2386747C2 (en) | Improved self-lifting drilling rig and similar drilling platforms | |
US6371695B1 (en) | Offshore caisson having upper and lower sections separated by a structural diaphragm and method of installing the same | |
US20060275080A1 (en) | Method and Apparatus for Offshore Drilling in Ice-Infested Waters | |
KR20190011716A (en) | A method for providing a seabed support unit and a shallow piercing terminal | |
US3793840A (en) | Mobile, arctic drilling and production platform | |
EA002258B1 (en) | Desk installation system for offshore structures | |
CA2813426C (en) | Ice worthy jack-up drilling unit with pre-loading tension system | |
WO2010085970A1 (en) | Mobile offshore platform | |
US8870497B2 (en) | Ice worthy jack-up drilling unit with conical piled monopod | |
US8807875B2 (en) | Ice worthy jack-up drilling unit with conical piled monopod and sockets | |
US4639167A (en) | Deep water mobile submersible arctic structure | |
KR20150140792A (en) | Arctic telescoping mobile offshore drilling unit | |
US3805534A (en) | Slide resistant platform anchor conductor silo | |
RU2477351C1 (en) | Ice-resistant monopod self-rising floating drilling rig | |
EP1167177A1 (en) | Offshore platform | |
CA2812597C (en) | Ice worthy jack-up drilling unit with conical piled monopod | |
CA2811946C (en) | Ice worthy jack-up drilling unit with conical piled monopod and sockets | |
RU2734326C1 (en) | Ice-resistant drilling complex for development of continental shelf and method of formation of ice-resistant drilling complex for development of continental shelf | |
KR20130120465A (en) | Ice worthy jack-up drilling unit with telescoping riser | |
KR20130139932A (en) | Ice worthy jack-up drilling unit secured to the seafloor | |
NO20150926A1 (en) | Sub-fixed floating platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: BP CORPORATION NORTH AMERICA INC., ILLINOIS Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:LI, GUANG;BEYNET, PIERRE A.;REEL/FRAME:017739/0731 Effective date: 20050802 |
|
STCB | Information on status: application discontinuation |