US20050011654A1 - Ballast excavating chain - Google Patents

Ballast excavating chain Download PDF

Info

Publication number
US20050011654A1
US20050011654A1 US10/890,036 US89003604A US2005011654A1 US 20050011654 A1 US20050011654 A1 US 20050011654A1 US 89003604 A US89003604 A US 89003604A US 2005011654 A1 US2005011654 A1 US 2005011654A1
Authority
US
United States
Prior art keywords
guide
track
excavating chain
transverse
plane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
US10/890,036
Other versions
US6848514B1 (en
Inventor
Josef Theurer
Adolf Schauer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Franz Plasser Bahnbaumaschinen Industrie GmbH
Original Assignee
Franz Plasser Bahnbaumaschinen Industrie GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Franz Plasser Bahnbaumaschinen Industrie GmbH filed Critical Franz Plasser Bahnbaumaschinen Industrie GmbH
Assigned to FRANZ PLASSER BAHNBAUMASCHINEN-INDUSTRIEGESELLSCHAFT M.B.H reassignment FRANZ PLASSER BAHNBAUMASCHINEN-INDUSTRIEGESELLSCHAFT M.B.H ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: SCHAUER, ADOLF, THEURER, JOSEF
Publication of US20050011654A1 publication Critical patent/US20050011654A1/en
Application granted granted Critical
Publication of US6848514B1 publication Critical patent/US6848514B1/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/04Removing the ballast; Machines therefor, whether or not additionally adapted for taking-up ballast
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/08Dredgers; Soil-shifting machines mechanically-driven with digging elements on an endless chain
    • E02F3/12Component parts, e.g. bucket troughs
    • E02F3/14Buckets; Chains; Guides for buckets or chains; Drives for chains
    • E02F3/142Buckets; Chains; Guides for buckets or chains; Drives for chains tools mounted on buckets or chains which loosen the soil, e.g. cutting wheels, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/08Dredgers; Soil-shifting machines mechanically-driven with digging elements on an endless chain
    • E02F3/12Component parts, e.g. bucket troughs
    • E02F3/14Buckets; Chains; Guides for buckets or chains; Drives for chains
    • E02F3/143Buckets; Chains; Guides for buckets or chains; Drives for chains chains; chain links; scraper chains
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/02Removing or re-contouring ballast
    • E01B2203/024Inclined chain

Definitions

  • the present invention relates to an arrangement of an excavating chain for conveying ballast of a track bed extending in a first plane, the excavating chain being comprised of a succession of linked chain links and being driven in a second plane inclined with respect to the first plane in an operating stage, and a guide wherein the excavating chain is guided, the guide comprising a transverse guide section positioned in a line of intersection of the first and second planes, in the operating stage, and longitudinal guide sections, the longitudinal guide sections being connected to ends of the transverse guide section by joints having a vertical axis and the guide sections defining a guide channel for the excavating chain, the guide channel being defined by a lower glide track and an upper glide track extending parallel to the second plane and an end glide track extending perpendicularly to the second plane, the end glide track connecting the lower and upper glide tracks.
  • FIG. 1 is a side elevation view of a conventional ballast cleaning machine with a ballast excavating chain
  • FIG. 2 is a schematic top view of the ballast excavating chain
  • FIGS. 3 and 4 are enlarged fragmentary views showing the deflection of the ballast excavating chain between the guide sections;
  • FIGS. 5 and 6 are fragmentary views showing top and side views, respectively, of a conventional arrangement for deflecting the ballast excavating chain.
  • FIG. 7 is a view of the deflection area, showing the position of the joint, and the guide channel in section.
  • FIG. 1 illustrates ballast cleaning machine 2 with arrangement 1 of an excavating chain for conveying ballast 5 of track bed 3 extending in first plane 8 .
  • the endless excavating chain is guided around raised track 4 , excavates dirty or encrusted ballast 5 , conveys it to screening apparatus 6 for cleaning, whence the cleaned ballast is returned to the track in a known manner.
  • the ballast excavating chain is comprised of a succession of chain links 15 linked to each other by bolts 14 and is driven in a second plane 7 inclined with respect to first plane 8 in an operating stage.
  • the excavating chain is guided in a guide comprising a transverse guide section 9 positioned in a line of intersection of the first and second planes 7 , 8 , in the operating stage, and longitudinal guide sections 12 .
  • the longitudinal guide sections are connected to ends of the transverse guide section by joints 10 having vertical axis 21 .
  • the guide sections define guide channel 13 (see FIG. 5 ) for the excavating chain.
  • the guide channel is defined by lower and upper glide tracks 17 , 17 extending parallel to second plane 7 and end glide track 18 extending perpendicularly to the second plane, the end glide track 18 connecting the lower and upper glide tracks 17 , 17 .
  • the glide tracks are of a highly wear-resistant material and are replaceably attached to guide channel 13 .
  • transverse guide section 9 may be elongated for work in widened track switches, which changes the angular relationship between transverse guide section 9 and longitudinal guide sections 12 .
  • the end glide track 18 of transverse guide section 9 is arcuately curved at 19 around joints 10 connecting the ends of the transverse guide section to adjoining longitudinal guide sections 12 , 12 .
  • Curved end glide track 18 of the transverse guide section encloses an acute dihedral angle ⁇ , preferably about 45°, with an imaginary plane of elongation of the end glide track of a respective one of the longitudinal guide sections (shown in phantom lines in FIG. 4 ) whereby the excavating chain is deflected solely from the transverse to the longitudinal guide sections by contact with end glide track 18 .
  • transverse guide section ends 20 are so curved that the excavating chain comes into contact with end glide track 18 only when the angle between transverse guide section 9 and longitudinal guide sections 12 changes. This is shown in FIG. 2 in phantom lines.
  • end glide track 18 of transverse guide section 9 is arcuately curved about a center defined by vertical axis 21 of joints 10 around which the end guide track is curved.
  • a distance a extending perpendicularly to end glide track 18 of longitudinal guide section 12 adjoining joints 10 is identical to radius r of arcuately curved end glide track 19 of transverse guide section 9 .
  • the arcuately curved end glide track of the transverse guide section forms a circular segment with an angle ⁇ of 60°.
  • the arcuately curved end glide track comprises a second arcuately curved end glide track 24 between linear portion 23 of transverse guide section 9 and arcuately curved end glide track 20 , and the second arcuately curved end glide track is arcuately curved about a center positioned on line 26 extending parallel to linear transverse guide section portion 23 and passing through vertical axis 21 of joints 10 .
  • This special configuration of the curved end glide track enables the ballast excavating chain to be deflected solely by frictional contact with the curved end glide track and without the need for a guide roller.
  • the excavating chain is driven, for example, with a tensile force of 110 kilonewton in the direction of the downwardly pointing arrow in FIG. 3 .
  • joints 10 are offset in relation to lower glide track 17 of guide channel 13 so that the joints are arranged below second plane 7 extending centrally through end glide track 18 , in a direction perpendicular to the second plane, and the excavating chain is deflected solely from the transverse to the longitudinal guide sections by frictional contact with the end glide track adjacent the joints. Because of the lowered positioning of joints 10 , which connect the longitudinal guide sections to the ends of the transverse guide section, the track may be in such a lower raised position that an underside of a track tie, indicated by phantom line 16 , extends immediately above the joints. If desired, joints 10 may be arranged fully on underside 22 of guide channel 13 .
  • the glide tracks 17 , 18 are of highly wear-resistant material and are detachably attached to the guide channel 13 in a transition from the transverse guide section 9 to the longitudinal guide sections 12 .

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Chain Conveyers (AREA)
  • Framework For Endless Conveyors (AREA)

Abstract

An arrangement of an excavating chain for conveying ballast of a track bed comprises a guide comprising a transverse guide section articulately connected to longitudinal guide sections defining a guide channel having an end glide track along which the excavating chain is guided. The longitdunal guide sections are connected to the ends of the transverse guide section joints arranged below the second plane extending centrally through the end glide track and the excavating chain is deflected solely from the transverse to the longitudinal guide sections by frictional contact with the end glide track adjacent the joints.

Description

    BACKGROUND OF THE INVENTION
  • 1. Field of the Invention
  • The present invention relates to an arrangement of an excavating chain for conveying ballast of a track bed extending in a first plane, the excavating chain being comprised of a succession of linked chain links and being driven in a second plane inclined with respect to the first plane in an operating stage, and a guide wherein the excavating chain is guided, the guide comprising a transverse guide section positioned in a line of intersection of the first and second planes, in the operating stage, and longitudinal guide sections, the longitudinal guide sections being connected to ends of the transverse guide section by joints having a vertical axis and the guide sections defining a guide channel for the excavating chain, the guide channel being defined by a lower glide track and an upper glide track extending parallel to the second plane and an end glide track extending perpendicularly to the second plane, the end glide track connecting the lower and upper glide tracks.
  • 2. Description of the Prior Art
  • U.S. Pat. Nos. 4,014,389 and 4,614,238 and DE 31 51 652, whose disclosures are incorporated herein by way of reference, disclose arrangements of this type, wherein an endless ballast conveyor chain is revolved around a track to excavate the ballast supporting the track and to convey the excavated ballast. The chain is guided by a transverse guide section in contact with the ballast bed during operation and longitudinal guide sections linked to the ends of the transverse guide section by joints. Guide rollers extending coaxially with the axes of the joints deflect the excavating chain from the transverse to the longitudinal guide sections. The pivotal connection between the guide sections is necessary to enable the excavating chain to be slightly displaced relative to the track. This facilitates work in restricted areas of the track. It also makes it possible to elongate the transverse guide section for operation in widened track switches. Since efficient ballast cleaning machines require the ballast excavating chain to be subjected to a tensile force of about 100 kilonewton during excavation, the amply lubricated guide rollers are subject to extrmely high loads and must be frequently replaced.
  • SUMMARY OF THE INVENTION
  • It is the primary object of this invention to provide an arrangement of the indicated type whose functioning is improved without interfering with the articulate connection between the guide sections.
  • This and other objects are accomplished in accordance with the invention if the joints are arranged below the second plane extending centrally through the end glide track and the excavating chain is deflected solely from the transverse to the longitudinal guide sections by frictional contact with the end glide track adjacent the joints.
  • This enables the excavating chain to be deflected from the transverse to the longitudinal guide sections solely by frictional contact with the end glide track without the need for guide rollers. This has the great advantage that the track needs to be raised less high from the ballast bed for inserting the transverse guide section therebelow. Accordingly, the stress on the track is smaller and, due to the fact that the track does not have to be raised to the extent required heretofore, the wheel base of the ballast cleaning machine carrying the excavating chain may be reduced. Also, the very expensive conventionally used guide rollers may be dispensed with. Without guide rollers, the deflection radius may be increased so that the loads to which the excavating chain is subjected may be noticeably reduced.
  • BRIEF DESCRIPTION OF THE DRAWING
  • The above and other objects, advantages and features of the present invention will become more apparent from the following detailed description of a now preferred embodiment thereof, taken in conjunction with the accompanying drawing wherein
  • FIG. 1 is a side elevation view of a conventional ballast cleaning machine with a ballast excavating chain;
  • FIG. 2 is a schematic top view of the ballast excavating chain;
  • FIGS. 3 and 4 are enlarged fragmentary views showing the deflection of the ballast excavating chain between the guide sections;
  • FIGS. 5 and 6 are fragmentary views showing top and side views, respectively, of a conventional arrangement for deflecting the ballast excavating chain; and
  • FIG. 7 is a view of the deflection area, showing the position of the joint, and the guide channel in section.
  • DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
  • Referring now to the drawing, FIG. 1 illustrates ballast cleaning machine 2 with arrangement 1 of an excavating chain for conveying ballast 5 of track bed 3 extending in first plane 8. During operation, the endless excavating chain is guided around raised track 4, excavates dirty or encrusted ballast 5, conveys it to screening apparatus 6 for cleaning, whence the cleaned ballast is returned to the track in a known manner.
  • As shown in FIGS. 2 and 3, the ballast excavating chain is comprised of a succession of chain links 15 linked to each other by bolts 14 and is driven in a second plane 7 inclined with respect to first plane 8 in an operating stage. The excavating chain is guided in a guide comprising a transverse guide section 9 positioned in a line of intersection of the first and second planes 7, 8, in the operating stage, and longitudinal guide sections 12. The longitudinal guide sections are connected to ends of the transverse guide section by joints 10 having vertical axis 21. The guide sections define guide channel 13 (see FIG. 5) for the excavating chain. The guide channel is defined by lower and upper glide tracks 17, 17 extending parallel to second plane 7 and end glide track 18 extending perpendicularly to the second plane, the end glide track 18 connecting the lower and upper glide tracks 17, 17. The glide tracks are of a highly wear-resistant material and are replaceably attached to guide channel 13.
  • As indicated in phantom lines in FIG. 2, transverse guide section 9 may be elongated for work in widened track switches, which changes the angular relationship between transverse guide section 9 and longitudinal guide sections 12.
  • As best illustrated in FIGS. 3 and 4, the end glide track 18 of transverse guide section 9 is arcuately curved at 19 around joints 10 connecting the ends of the transverse guide section to adjoining longitudinal guide sections 12, 12. Curved end glide track 18 of the transverse guide section encloses an acute dihedral angle α, preferably about 45°, with an imaginary plane of elongation of the end glide track of a respective one of the longitudinal guide sections (shown in phantom lines in FIG. 4) whereby the excavating chain is deflected solely from the transverse to the longitudinal guide sections by contact with end glide track 18. In other words, transverse guide section ends 20 are so curved that the excavating chain comes into contact with end glide track 18 only when the angle between transverse guide section 9 and longitudinal guide sections 12 changes. This is shown in FIG. 2 in phantom lines.
  • As shown in the embodiment illustrated in FIG. 3, end glide track 18 of transverse guide section 9 is arcuately curved about a center defined by vertical axis 21 of joints 10 around which the end guide track is curved.
  • As shown in FIGS. 3 and 4, a distance a extending perpendicularly to end glide track 18 of longitudinal guide section 12 adjoining joints 10 is identical to radius r of arcuately curved end glide track 19 of transverse guide section 9. The arcuately curved end glide track of the transverse guide section forms a circular segment with an angle β of 60°. The arcuately curved end glide track comprises a second arcuately curved end glide track 24 between linear portion 23 of transverse guide section 9 and arcuately curved end glide track 20, and the second arcuately curved end glide track is arcuately curved about a center positioned on line 26 extending parallel to linear transverse guide section portion 23 and passing through vertical axis 21 of joints 10.
  • This special configuration of the curved end glide track enables the ballast excavating chain to be deflected solely by frictional contact with the curved end glide track and without the need for a guide roller. In an efficient ballast cleaning machine, the excavating chain is driven, for example, with a tensile force of 110 kilonewton in the direction of the downwardly pointing arrow in FIG. 3.
  • This differs from the prior art arrangement 1 shown in FIGS. 6 and 7, in which the excavating chain is deflected by guide roller 27 rotatable about vertical axis 21 of the joint linking the ends of transverse guide section 9 to longitudinaly guide sections 12. The guide roller projects through an opening of the end glide track 18 beyond the glide plane. This has the above-noted disadvantages and, in addition, subjects chain bolts 14 to extreme loads.
  • As shown in FIG. 7, joints 10 are offset in relation to lower glide track 17 of guide channel 13 so that the joints are arranged below second plane 7 extending centrally through end glide track 18, in a direction perpendicular to the second plane, and the excavating chain is deflected solely from the transverse to the longitudinal guide sections by frictional contact with the end glide track adjacent the joints. Because of the lowered positioning of joints 10, which connect the longitudinal guide sections to the ends of the transverse guide section, the track may be in such a lower raised position that an underside of a track tie, indicated by phantom line 16, extends immediately above the joints. If desired, joints 10 may be arranged fully on underside 22 of guide channel 13.
  • The glide tracks 17, 18 are of highly wear-resistant material and are detachably attached to the guide channel 13 in a transition from the transverse guide section 9 to the longitudinal guide sections 12.

Claims (2)

1. An arrangement of an excavating chain for conveying ballast of a track bed extending in a first plane, the excavating chain being comprised of a succession of linked chain links and being driven in a second plane inclined with respect to the first plane in an operating stage, and a guide wherein the excavating chain is guided, the guide comprising a transverse guide section positioned in a line of intersection of the first and second planes, in the operating stage, and longitudinal guide sections, the longitudinal guide sections being connected to ends of the transverse guide section by joints having a vertical axis and the guide sections defining a guide channel for the excavating chain, the guide channel being defined by a lower glide track and an upper glide track extending parallel to the second plane and an end glide track extending perpendicularly to the second plane, the end glide track connecting the lower and upper glide tracks, wherein the joints are arranged below the second plane extending centrally through the end glide track and the excavating chain is deflected solely from the transverse to the longitudinal guide sections by frictional contact with the end glide track adjacent the joints.
2. The arrangement of claim 1, wherein the glide tracks are of highly wear-resistant material and are detachably attached to the guide channel in a transition from the transverse guide section to the longitudinal guide sections.
US10/890,036 2003-07-18 2004-07-13 Ballast excavating chain Expired - Fee Related US6848514B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
ATGM514/2003 2003-07-18
AT0051403U AT6488U3 (en) 2003-07-18 2003-07-18 ROOM CHAIN WITH LOWERED JOINT

Publications (2)

Publication Number Publication Date
US20050011654A1 true US20050011654A1 (en) 2005-01-20
US6848514B1 US6848514B1 (en) 2005-02-01

Family

ID=28679310

Family Applications (1)

Application Number Title Priority Date Filing Date
US10/890,036 Expired - Fee Related US6848514B1 (en) 2003-07-18 2004-07-13 Ballast excavating chain

Country Status (11)

Country Link
US (1) US6848514B1 (en)
EP (1) EP1498547B1 (en)
JP (1) JP4791715B2 (en)
CN (1) CN1280487C (en)
AT (2) AT6488U3 (en)
AU (1) AU2004202890B2 (en)
DE (1) DE502004004012D1 (en)
DK (1) DK1498547T3 (en)
ES (1) ES2286560T3 (en)
PL (1) PL1498547T3 (en)
UA (1) UA83622C2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1643035A2 (en) * 2004-10-02 2006-04-05 GBM Wiebe Gleisbaumaschinen GmbH Method of renewing a ballastway
CN104195895A (en) * 2014-09-04 2014-12-10 昆明学院 Vibration rotary excavating type stone removing machine used between sleepers

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA014618B1 (en) * 2008-06-06 2010-12-30 Ооо "Вест-Тер" Raking working chain of a crushed stone cleaning machine (cscm)
US8069977B2 (en) * 2009-02-26 2011-12-06 Jervis B. Webb Company Slider bed conveyor
AT10793U3 (en) * 2009-06-17 2010-06-15 Plasser Bahnbaumasch Franz STORAGE CAR FOR THE TRANSPORT OF SHALL GOODS
AT510712B1 (en) * 2011-06-20 2012-06-15 Plasser Bahnbaumasch Franz MACHINE FOR CLEANING THE SCOT OF A TRAIL
DE102012202680A1 (en) * 2012-02-22 2013-08-22 K&K Maschinenentwicklungs GmbH & Co. KG Excavation chain for removing track bed material
AT512163B1 (en) * 2012-06-12 2013-06-15 Plasser Bahnbaumasch Franz Machine with a clearing chain for the transport of gravel and procedures
FR3101892B1 (en) * 2019-10-14 2021-09-10 Matisa Materiel Ind Sa Articulated assembly of two links and associated excavation chain
CN111268363A (en) * 2020-03-09 2020-06-12 江苏经贸职业技术学院 Logistics sorting facility

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4014389A (en) * 1974-08-14 1977-03-29 Franz Plasser Bahnbaumaschinen-Industrie-Gesellschaft M.B.H. Endless ballast conveyor chain
US4614238A (en) * 1983-01-10 1986-09-30 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Arrangement for excavating bulk material from a track bed

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT370463B (en) * 1981-04-22 1983-04-11 Plasser Bahnbaumasch Franz DEFLECTION AND GUIDE DEVICE FOR CONTINUOUS ROOM AND CONVEYOR CHAINS OF TRACK CONSTRUCTION MACHINES
AT375426B (en) * 1982-09-20 1984-08-10 Plasser Bahnbaumasch Franz FOERDER- OR ROOM CHAIN ARRANGEMENT FOR A TRACKING MACHINE
DE3302047A1 (en) * 1983-01-22 1984-07-26 Gewerkschaft Eisenhütte Westfalia, 4670 Lünen Deflection curve for central scraper chain conveyors, especially for use in underground extraction operations
DE3502985A1 (en) * 1985-01-30 1985-06-13 Reinold 4690 Herne Krohm Curve-negotiating conveyor
DE29921440U1 (en) * 1999-12-07 2001-01-18 KRONES AG, 93073 Neutraubling Curve guide for a flat top chain

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4014389A (en) * 1974-08-14 1977-03-29 Franz Plasser Bahnbaumaschinen-Industrie-Gesellschaft M.B.H. Endless ballast conveyor chain
US4614238A (en) * 1983-01-10 1986-09-30 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Arrangement for excavating bulk material from a track bed

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1643035A2 (en) * 2004-10-02 2006-04-05 GBM Wiebe Gleisbaumaschinen GmbH Method of renewing a ballastway
EP1643035A3 (en) * 2004-10-02 2006-04-19 GBM Wiebe Gleisbaumaschinen GmbH Method of renewing a ballastway
CN104195895A (en) * 2014-09-04 2014-12-10 昆明学院 Vibration rotary excavating type stone removing machine used between sleepers

Also Published As

Publication number Publication date
PL1498547T3 (en) 2007-09-28
EP1498547A1 (en) 2005-01-19
ES2286560T3 (en) 2007-12-01
AU2004202890A1 (en) 2005-02-03
AT6488U3 (en) 2004-10-25
ATE364108T1 (en) 2007-06-15
DK1498547T3 (en) 2007-09-03
JP2005041694A (en) 2005-02-17
EP1498547B1 (en) 2007-06-06
DE502004004012D1 (en) 2007-07-19
US6848514B1 (en) 2005-02-01
AU2004202890B2 (en) 2007-07-19
JP4791715B2 (en) 2011-10-12
UA83622C2 (en) 2008-08-11
AT6488U2 (en) 2003-11-25
CN1280487C (en) 2006-10-18
CN1576463A (en) 2005-02-09

Similar Documents

Publication Publication Date Title
US6848514B1 (en) Ballast excavating chain
US6981556B2 (en) Ballast excavating chain
US4614238A (en) Arrangement for excavating bulk material from a track bed
US8448781B2 (en) Conveyor chain for mining machinery
AU722775B2 (en) A wagon for drawing off long-welded rails stored on transport wagons
GB2125754A (en) Improvements in or relating to a conveyor system
US5271166A (en) Conveyor chain arrangement for ballast cleaning machine
JPS5829362B2 (en) Chain conveyor chain
US6792870B2 (en) Machine for removing an old track and laying a new track
US5156256A (en) Elevated auxiliary conveying apparatus
RU2266359C1 (en) Ballast removing chain for transportation of ballast bed crushed stone
AU784772B2 (en) A clearing chain for a track maintenance machine
RU2264496C1 (en) Excavation chain
US817365A (en) Switch-point connector.
GB2330123A (en) Conveyor for longwall mining machine

Legal Events

Date Code Title Description
AS Assignment

Owner name: FRANZ PLASSER BAHNBAUMASCHINEN-INDUSTRIEGESELLSCHA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:THEURER, JOSEF;SCHAUER, ADOLF;REEL/FRAME:015567/0577;SIGNING DATES FROM 20040624 TO 20040628

FPAY Fee payment

Year of fee payment: 4

FPAY Fee payment

Year of fee payment: 8

REMI Maintenance fee reminder mailed
LAPS Lapse for failure to pay maintenance fees
STCH Information on status: patent discontinuation

Free format text: PATENT EXPIRED DUE TO NONPAYMENT OF MAINTENANCE FEES UNDER 37 CFR 1.362

FP Lapsed due to failure to pay maintenance fee

Effective date: 20170201