US20020001506A1 - Method of resurfacing roads and bridge decks - Google Patents

Method of resurfacing roads and bridge decks Download PDF

Info

Publication number
US20020001506A1
US20020001506A1 US09/272,190 US27219099A US2002001506A1 US 20020001506 A1 US20020001506 A1 US 20020001506A1 US 27219099 A US27219099 A US 27219099A US 2002001506 A1 US2002001506 A1 US 2002001506A1
Authority
US
United States
Prior art keywords
layer
polymer modified
modified concrete
applying
road surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US09/272,190
Inventor
Jack H. Wilson
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
POLYCON Inc
Original Assignee
POLYCON Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by POLYCON Inc filed Critical POLYCON Inc
Priority to US09/272,190 priority Critical patent/US20020001506A1/en
Priority to AU38769/00A priority patent/AU3876900A/en
Priority to PCT/US2000/006413 priority patent/WO2000055427A1/en
Priority to CA002366009A priority patent/CA2366009A1/en
Assigned to POLYCON, INC. reassignment POLYCON, INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: WILSON, JACK H. SR.
Publication of US20020001506A1 publication Critical patent/US20020001506A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/24Methods or arrangements for preventing slipperiness or protecting against influences of the weather
    • E01C11/26Permanently installed heating or blowing devices ; Mounting thereof
    • E01C11/265Embedded electrical heating elements ; Mounting thereof
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/005Methods or materials for repairing pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • E01C7/147Repairing concrete pavings, e.g. joining cracked road sections by dowels, applying a new concrete covering
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/35Toppings or surface dressings; Methods of mixing, impregnating, or spreading them
    • E01C7/358Toppings or surface dressings; Methods of mixing, impregnating, or spreading them with a combination of two or more binders according to groups E01C7/351 - E01C7/356

Definitions

  • the invention relates to the field of road surface repair and in particular the repair of concrete bridge decks.
  • One object of the invention is to provide a bridge deck resurfacing material formed of a layer or layers of cementitious material and rock chips to provide a long lasting and high friction surface.
  • Another object of the invention is to provide a method of applying the materials to the road surface quickly to avoid long traffic delays.
  • Yet another object of the invention is to provide a method of filling in potholes prior to resurfacing the road.
  • Still another object of the invention is to provide a high friction road surface.
  • Yet another object of the invention is to provide anti-ponding lines in the road surface.
  • Another object of the invention is to provide anti-icing devices embedded in the road surface.
  • this invention is directed to the resurfacing of roads and in particular bridge decks.
  • the invention includes spreading with a squeegee a thin layer of polymer modified concrete over a bridge deck surface and then applying by broadcasting a layer of granite rock chips to the wet concrete to provide a high friction surface.
  • An optional second layer of the polymer modified concrete is then applied over the first layer of rock chips using the squeegee and an optional second layer of rock chips is then broadcast over that layer and then heavy quartz sand may be applied. If spalling or potholes are present in the road surface, these defects are repaired prior to the road resurfacing. Repair of potholes is accomplished by mixing granite aggregate rock chips with polymer modified concrete to form a putty which is then screeded into the potholes.
  • De-icing devices may also be added during the resurfacing project to prevent snow and ice from building up on the road surface.
  • Electric resistance heating elements are placed on the highway surface and covered with polymer modified concrete. The heating elements are preferably connected to solar cells and/or batteries or an electric generator to provide electricity to heat the road surface to sufficient temperature to prevent ice and snow from accumulating on the heated road surface.
  • FIG. 1 is a perspective view of a bridge deck in need of repair.
  • FIG. 2 is a view of the bridge deck of FIG. 1 having potholes, spalling and cracks repaired prior to application of the resurfacing material.
  • FIG. 3 shows the application of the polymer modified cement to the bridge deck
  • FIGS. 4 - 7 show the repair of a road surface in sequential cross-sections.
  • FIG. 8 shows a bridge deck having sections broken away to reveal layers.
  • FIG. 9 shows a bridge deck having heating wires placed in the wheel lanes prior to application of the resurfacing materials.
  • FIG. 1 shows a bridge deck 10 having defects 12 therein.
  • these defects 12 i.e. potholes, spalling, transverse cracks or popouts, etc.
  • the polymer modified concrete is preferably made by mixing 330 resin manufactured by Rohm & Haas with Quik Krete cement powder at a ratio of two gallons of resin per sixty pound bag of powder.
  • the rock chips are preferably granite chips in sieve size “0” (1 ⁇ 4′′ ⁇ 1 ⁇ 8′′) and in the defect repair portion of the bridge deck resurfacing project are mixed with the Quik Krete and resin to form a putty 14 and screeded into the defects 12 to form a level road surface 16 as shown in FIG. 2.
  • the rock chip and resin mixture is then allowed to set up. The time to set up will vary depending on weather conditions, but will generally be less than an hour.
  • the polymer modified concrete 18 is applied to the road surface 16 of the bridge deck 10 as shown in FIG. 3.
  • the polymer modified concrete layer 18 is applied to the road surface 16 using a squeegee machine 20 such as that described in my prior U.S. Pat. No. 5,735,952.
  • the squeegee machine 20 preferably uses a 12 foot wide squeegee 22 as shown which can cover an entire traffic lane in one pass with a thin coating of 1 ⁇ 8 inches to ⁇ fraction (1/16) ⁇ inches of polymer modified concrete.
  • a layer of rock chips 24 is applied while the polymer modified concrete layer 18 is still wet.
  • the rock chips 24 are applied by broadcasting using an air blower 26 giving the rock chips 24 enough velocity to embed into the polymer modified concrete layer 18 .
  • the rock chips 24 are preferably applied by using a blower on the shoulder lane next to the lane on which the polymer modified concrete layer 18 has been laid and blowing the rock chips 24 onto the polymer modified concrete layer 18 .
  • the polymer modified concrete layer 18 is then allowed to dry. This period may vary according to weather conditions, but generally is about 1 and 1 ⁇ 2 to 2 hours. Any loose rock chips are then blown off by an air blower 27 .
  • FIGS. 4 - 7 show sequential cross-sections of the road surface 16 as first the putty 14 is applied, then the polymer modified concrete layer 18 and finally the rock chips 24 .
  • FIG. 8 shows a completed bridge deck resurfacing with portions broken away to reveal the layers 18 , 24 , 28 and 30 of resurfacing material.
  • a second layer of polymer modified concrete 28 is applied over the first layer of rock chips 24 .
  • the second layer of polymer modified concrete 28 is of the same thickness as the first layer 18 .
  • a second layer of rock chips and optionally heavy quartz sand 30 is applied to the second layer of polymer modified concrete 28 using the blower technique described above.
  • de-icing devices may be installed on existing bridge decks and road surfaces.
  • heating elements 34 preferably in the form of copper wires of sufficient diameter to be durable and produce heat to warm the pavement 32 enough to melt ice and snow are placed on the wheel lanes 36 of the pavement 32 after application of the first polymer modified concrete layer 38 .
  • Layer 38 is shown as applied in three foot wide stripes covering the wheel lanes 36 of the pavement 32 .
  • the heating elements 34 are preferably laid in a grid pattern as shown in FIG. 6, but could also be placed in a zigzag pattern.
  • power is provided to the copper wires by batteries 40 and photovoltaic solar cells 42 .
  • a thermostat may be applied to the heating elements 34 to maintain a desired temperature of the road surface during sub-freezing weather.
  • the thermostat would be set at a temperature of about 40 degrees Fahrenheit so that the heating elements 34 will be activated when the surface temperature dips below 40 degrees.
  • a second layer of polymer modified concrete 44 is applied over the entire wheel lane 36 covering the heating elements 34 .
  • Layer 44 may also be applied to the entire road surface.
  • a layer 46 of rock chips and heavy sand is broadcast by blowing onto the polymer modified concrete layer 44 to embed the rock chips and sand into the top of the wet concrete.
  • the concrete layer 44 is allowed to dry prior to traffic being allowed to travel over the roadway.
  • FIG. 3 also shows the application of anti-ponding lines 48 to the polymer modified concrete layer 18 .
  • the anti-ponding lines 48 are formed in the polymer modified concrete layer 18 immediately after the application of the layer 24 of rock chips is broadcast onto the polymer modified concrete layer 18 but while the polymer modified cement 18 is still wet.
  • the polymer modified concrete layer 18 is preferably one-eighth to one -quarter inches in thickness which will facilitate deeper lines 48 .
  • the lines 48 are formed simply by drawing a rake 50 across the travel lane 52 to provide evenly spaced lines 48 perpendicular to the direction of travel.
  • the lines 48 create parallel shallow grooves 54 spaced approximately three-fourths of an inch to one inch apart which facilitate water flow off the bridge deck 16 and helps prevent ponding.

Abstract

The resurfacing of roads and in particular bridge decks includes spreading with a squeegee a thin layer of polymer modified concrete over a bridge deck surface and then applying by broadcasting a layer of rock chips to the wet concrete to provide a high friction surface. A second layer of the polymer modified concrete is then applied over the first layer of rock chips using the squeegee and a second layer of rock chips is then broadcast over that layer and then heavy quartz sand is applied. In another embodiment, heating wires are laid on the road surface and a thick layer of polymer modified concrete is applied over the wires to embed them in the polymer modified concrete. Then a single layer of rock is applied to the surface of the polymer modified concrete. If ruts or potholes are present in the road surface, these defects are repaired prior to the road resurfacing. Repair of potholes is accomplished by mixing granite aggregate rock chips with polymer modified concrete to form a putty which is then screeded into the potholes and ruts. Anti-ponding lines may be formed into the polymer modified concrete by raking the surface while it is still wet.

Description

    SUMMARY OF THE INVENTION
  • The invention relates to the field of road surface repair and in particular the repair of concrete bridge decks. [0001]
  • BACKGROUND OF THE INVENTION
  • It is a common occurrence for roads to become worn due to traffic. Wearing of roads can cause the concrete and asphalt road surfaces to become smooth and slick. Asphalt road surfaces can become rutted due to the combination of high temperatures and heavy trucks. These factors cause unsafe driving conditions. Other factors such as oil or other fluids leaking from vehicles can also create slick surfaces even when the smooth surfaces are otherwise dry. Concrete bridge decks also are subject to transverse cracking which allows water to seep in and corrode the steel reinforcing within the concrete bridge deck. Spalling is another defect in concrete bridge decks which causes the surface of the concrete to crumble leaving the aggregate exposed. [0002]
  • Resurfacing of worn bridge decks has utilized various methods. One expensive and time consuming method includes shot blasting the top portion of the concrete pavement to create high friction surface. This procedure involved causes damage to the concrete. Another repair method is the application of a thin coating of epoxy resin mixed with aggregate. Neither method is effective in filling in ruts or potholes or cracks. [0003]
  • Prior methods of road resurfacing and bridge deck repair are not as readily adaptable to providing added improvements to the pavement such as anti-ponding lines or ice preventing devices. [0004]
  • In view of the forgoing it can be seen that there is a need for a new method of road surface repair that is suitable for use in repair of bridge decks that avoids long traffic delays and provides a long lasting repair. [0005]
  • OBJECTS AND SUMMARY
  • One object of the invention is to provide a bridge deck resurfacing material formed of a layer or layers of cementitious material and rock chips to provide a long lasting and high friction surface. [0006]
  • Another object of the invention is to provide a method of applying the materials to the road surface quickly to avoid long traffic delays. [0007]
  • Yet another object of the invention is to provide a method of filling in potholes prior to resurfacing the road. [0008]
  • Still another object of the invention is to provide a high friction road surface. [0009]
  • Yet another object of the invention is to provide anti-ponding lines in the road surface. [0010]
  • Another object of the invention is to provide anti-icing devices embedded in the road surface. [0011]
  • In summary, this invention is directed to the resurfacing of roads and in particular bridge decks. The invention includes spreading with a squeegee a thin layer of polymer modified concrete over a bridge deck surface and then applying by broadcasting a layer of granite rock chips to the wet concrete to provide a high friction surface. An optional second layer of the polymer modified concrete is then applied over the first layer of rock chips using the squeegee and an optional second layer of rock chips is then broadcast over that layer and then heavy quartz sand may be applied. If spalling or potholes are present in the road surface, these defects are repaired prior to the road resurfacing. Repair of potholes is accomplished by mixing granite aggregate rock chips with polymer modified concrete to form a putty which is then screeded into the potholes. [0012]
  • Other improvements can be added to the bridge deck during the resurfacing process such as anti-ponding lines to facilitate runoff of water from the road surface and reduce hydroplaning. The lines create a series of grooves in the pavement surface extending from the centerline to the edge of the road perpendicular to the direction of travel. [0013]
  • De-icing devices may also be added during the resurfacing project to prevent snow and ice from building up on the road surface. Electric resistance heating elements are placed on the highway surface and covered with polymer modified concrete. The heating elements are preferably connected to solar cells and/or batteries or an electric generator to provide electricity to heat the road surface to sufficient temperature to prevent ice and snow from accumulating on the heated road surface.[0014]
  • Other objects, uses and advantages will be apparent from a reading of this description which proceeds with reference to the accompanying drawings forming a part thereof. [0015]
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 is a perspective view of a bridge deck in need of repair. [0016]
  • FIG. 2 is a view of the bridge deck of FIG. 1 having potholes, spalling and cracks repaired prior to application of the resurfacing material. [0017]
  • FIG. 3 shows the application of the polymer modified cement to the bridge deck; [0018]
  • FIGS. [0019] 4-7 show the repair of a road surface in sequential cross-sections.
  • FIG. 8 shows a bridge deck having sections broken away to reveal layers. [0020]
  • FIG. 9 shows a bridge deck having heating wires placed in the wheel lanes prior to application of the resurfacing materials.[0021]
  • DETAILED DESCRIPTION OF THE INVENTION
  • FIG. 1 shows a [0022] bridge deck 10 having defects 12 therein. Prior to resurfacing the bridge deck 10 these defects 12 (i.e. potholes, spalling, transverse cracks or popouts, etc.) must first be repaired. This is accomplished by filling in the defects with a mixture of polymer modified concrete and rock chips. The polymer modified concrete is preferably made by mixing 330 resin manufactured by Rohm & Haas with Quik Krete cement powder at a ratio of two gallons of resin per sixty pound bag of powder. The rock chips are preferably granite chips in sieve size “0” (¼″×⅛″) and in the defect repair portion of the bridge deck resurfacing project are mixed with the Quik Krete and resin to form a putty 14 and screeded into the defects 12 to form a level road surface 16 as shown in FIG. 2. The rock chip and resin mixture is then allowed to set up. The time to set up will vary depending on weather conditions, but will generally be less than an hour.
  • Next the polymer modified [0023] concrete 18 is applied to the road surface 16 of the bridge deck 10 as shown in FIG. 3. The polymer modified concrete layer 18 is applied to the road surface 16 using a squeegee machine 20 such as that described in my prior U.S. Pat. No. 5,735,952. The squeegee machine 20 preferably uses a 12 foot wide squeegee 22 as shown which can cover an entire traffic lane in one pass with a thin coating of ⅛ inches to {fraction (1/16)} inches of polymer modified concrete.
  • Still looking at FIG. 3, a layer of [0024] rock chips 24 is applied while the polymer modified concrete layer 18 is still wet. The rock chips 24 are applied by broadcasting using an air blower 26 giving the rock chips 24 enough velocity to embed into the polymer modified concrete layer 18. The rock chips 24 are preferably applied by using a blower on the shoulder lane next to the lane on which the polymer modified concrete layer 18 has been laid and blowing the rock chips 24 onto the polymer modified concrete layer 18. The polymer modified concrete layer 18 is then allowed to dry. This period may vary according to weather conditions, but generally is about 1 and ½ to 2 hours. Any loose rock chips are then blown off by an air blower 27.
  • FIGS. [0025] 4-7 show sequential cross-sections of the road surface 16 as first the putty 14 is applied, then the polymer modified concrete layer 18 and finally the rock chips 24.
  • FIG. 8 shows a completed bridge deck resurfacing with portions broken away to reveal the [0026] layers 18, 24, 28 and 30 of resurfacing material. A second layer of polymer modified concrete 28 is applied over the first layer of rock chips 24. The second layer of polymer modified concrete 28 is of the same thickness as the first layer 18. Next a second layer of rock chips and optionally heavy quartz sand 30 is applied to the second layer of polymer modified concrete 28 using the blower technique described above.
  • The process is repeated for each travel lane until the [0027] entire bridge deck 10 is resurfaced. The resurfaced lanes can be driven on in about 1 ½ to 2 hours, but the polymer modified concrete layers 18 and 28 will continue to cure for about seven days.
  • Referring now to FIG. 9, resurfacing bridge decks in this manner provides an ideal opportunity to install de-icing devices in the [0028] pavement 32. Prior to my invention applications of de-icing devices could be installed only as part of new construction. Now, with my invention, de-icing devices may be installed on existing bridge decks and road surfaces.
  • As shown in FIG. 6, [0029] heating elements 34, preferably in the form of copper wires of sufficient diameter to be durable and produce heat to warm the pavement 32 enough to melt ice and snow are placed on the wheel lanes 36 of the pavement 32 after application of the first polymer modified concrete layer 38. Layer 38 is shown as applied in three foot wide stripes covering the wheel lanes 36 of the pavement 32. However, it should be understood that the first layer 38 could cover the entire lane and the heating elements 34 could also be applied across the whole lane. The heating elements 34 are preferably laid in a grid pattern as shown in FIG. 6, but could also be placed in a zigzag pattern. Preferably, power is provided to the copper wires by batteries 40 and photovoltaic solar cells 42. However, power could also be provided by conventional power lines or a generator (both not shown). A thermostat may be applied to the heating elements 34 to maintain a desired temperature of the road surface during sub-freezing weather. Preferably, the thermostat would be set at a temperature of about 40 degrees Fahrenheit so that the heating elements 34 will be activated when the surface temperature dips below 40 degrees.
  • After the [0030] heating elements 34 are installed and first polymer modified concrete layer 38 is allowed to dry, a second layer of polymer modified concrete 44 is applied over the entire wheel lane 36 covering the heating elements 34. Layer 44 may also be applied to the entire road surface. Then a layer 46 of rock chips and heavy sand is broadcast by blowing onto the polymer modified concrete layer 44 to embed the rock chips and sand into the top of the wet concrete. The concrete layer 44 is allowed to dry prior to traffic being allowed to travel over the roadway.
  • FIG. 3 also shows the application of [0031] anti-ponding lines 48 to the polymer modified concrete layer 18. The anti-ponding lines 48 are formed in the polymer modified concrete layer 18 immediately after the application of the layer 24 of rock chips is broadcast onto the polymer modified concrete layer 18 but while the polymer modified cement 18 is still wet. The polymer modified concrete layer 18 is preferably one-eighth to one -quarter inches in thickness which will facilitate deeper lines 48. The lines 48 are formed simply by drawing a rake 50 across the travel lane 52 to provide evenly spaced lines 48 perpendicular to the direction of travel. The lines 48 create parallel shallow grooves 54 spaced approximately three-fourths of an inch to one inch apart which facilitate water flow off the bridge deck 16 and helps prevent ponding.
  • While this invention has been described as having a preferred design, it is understood that it is capable of further modifications, uses and/or adaptations of the invention following in general the principle of the invention and including such departures from the present disclosure as come within the known or customary practice in the art to which the invention pertains and as maybe applied to the central features hereinbefore set forth, and fall within the scope of the invention and the limits of the appended claims. [0032]

Claims (19)

I claim:
1. A method of resurfacing roads, comprising the steps of:
a) applying a first layer of polymer modified concrete over a road surface;
b) applying a first layer of rock chips over the polymer modified concrete layer;
c) applying a second layer of polymer modified concrete over the layer of rock chips; and,
d) applying a second layer of rock chips over the second layer of polymer modified concrete.
2. The method of resurfacing roads as set forth in claim 1, wherein the step of applying said first layer of polymer modified concrete to the road surface includes:
a) applying said first layer of polymer modified concrete in a thickness of approximately {fraction (1/16)}th to ⅛th inches using a squeegee to provide an even application of said concrete.
3. The method of resurfacing roads as set forth in claim 1, wherein the step of applying said first layer of rock chips over said first layer of polymer modified concrete includes:
a) blowing said rock chips onto said first layer of polymer modified concrete with sufficient force to embed said chips in said first layer of polymer modified concrete.
4. The method of resurfacing roads as set forth in claim 1, wherein the step of applying said second layer of polymer modified concrete over said second layer of rock chips over said layer of polymer modified concrete includes:
a) applying said second layer of polymer modified concrete in a thickness of approximately {fraction (1/16)}th to ⅛th inches in thickness using a squeegee to provide an even application of said concrete.
5. The method of resurfacing roads as set forth in claim 1, wherein the step of applying said second layer of rock chips over said second layer of polymer modified concrete includes:
a) blowing said rock chips onto said second layer of polymer modified concrete with sufficient force to embed said chips in said second layer of polymer modified concrete.
6. The method of resurfacing roads as set forth in claim 1, further including the step of:
a) filling in at least one pothole with a mixture of polymer modified concrete and rock chips and screeding said mixture to be substantially level with the road surface prior to application of said first layer of polymer modified concrete.
7. The method of resurfacing roads as set forth in claim 1, wherein the step of applying said first layer of rock chips over said first layer of polymer modified concrete includes:
a) blowing rock chips of no larger than ¼ inch in width onto said first layer of polymer modified concrete.
8. The method of resurfacing roads as set forth in claim 1, further including the step of:
a) allowing said first layer of polymer modified concrete to harden to form a firm supporting surface prior to application of said second layer of polymer modified concrete.
9. A method of resurfacing roads, comprising the steps of:
a) applying a layer of polymer modified concrete to a road surface;
b) broadcasting rock chips onto said layer of polymer modified concrete while said polymer modified concrete layer is wet; and,
c) raking said road surface while said polymer modified concrete is wet to form anti-ponding lines.
10. A method of resurfacing roads as set forth in claim 9, wherein the step of raking further includes:
a) forming said anti-ponding lines to extend from the center of the road surface to the edge of the road surface substantially perpendicular to the direction of travel of traffic on the road surface.
11. The method of resurfacing roads as set forth in claim 10, wherein the step of forming said anti-ponding lines further includes:
a) applying said lines spaced apart approximately three-fourths of an inch to one inch.
12. A method of resurfacing roads comprising the steps of:
a) applying a first layer of polymer modified concrete to the road surface;
b) placing electrical resistance heating elements on said first layer of polymer modified concrete;
c) applying a second layer of polymer modified concrete over said heating elements.
d) connecting said electrical heating elements to a power source.
13. The method of resurfacing roads as set forth in claim 12, further comprising the step of:
a) applying a layer of rock chips onto said second layer of polymer modified concrete while said second layer is wet.
14. The method of resurfacing roads as set forth in claim 12, wherein the step of placing said electrical heating elements on said first layer includes:
a) forming a grid of copper wires in the wheel lanes of the road surface.
15. The method of resurfacing roads as set forth in claim 12, wherein the step of placing said electrical heating elements on said first layer includes:
a) forming a zigzag pattern of copper wires in the wheel lanes of the road surface.
16. The method of resurfacing roads as set forth in claim 12, wherein the step of applying a first layer of polymer modified concrete to the road surface includes:
a) applying said first layer on the wheel lanes of the road surface.
17. The method of resurfacing roads as set forth in claim 16, wherein the step of applying a first layer of polymer modified concrete to the road surface includes:
a) applying said first layer in three foot wide strips to cover the wheel lanes of the road surface.
18. The method of resurfacing roads as set forth in claim 12, wherein the step of connecting said electrical heating elements to a power source includes:
a) connecting said electrical heating elements to a photovoltaic energy source.
19. The method of resurfacing roads as set forth in claim 12, wherein the step of connecting said electrical heating elements to a power source includes:
a) connecting said electrical heating elements to a battery.
US09/272,190 1999-03-18 1999-03-18 Method of resurfacing roads and bridge decks Abandoned US20020001506A1 (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
US09/272,190 US20020001506A1 (en) 1999-03-18 1999-03-18 Method of resurfacing roads and bridge decks
AU38769/00A AU3876900A (en) 1999-03-18 2000-03-17 Method of resurfacing roads and bridge decks
PCT/US2000/006413 WO2000055427A1 (en) 1999-03-18 2000-03-17 Method of resurfacing roads and bridge decks
CA002366009A CA2366009A1 (en) 1999-03-18 2000-03-17 Method of resurfacing roads and bridge decks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US09/272,190 US20020001506A1 (en) 1999-03-18 1999-03-18 Method of resurfacing roads and bridge decks

Publications (1)

Publication Number Publication Date
US20020001506A1 true US20020001506A1 (en) 2002-01-03

Family

ID=23038784

Family Applications (1)

Application Number Title Priority Date Filing Date
US09/272,190 Abandoned US20020001506A1 (en) 1999-03-18 1999-03-18 Method of resurfacing roads and bridge decks

Country Status (4)

Country Link
US (1) US20020001506A1 (en)
AU (1) AU3876900A (en)
CA (1) CA2366009A1 (en)
WO (1) WO2000055427A1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004016856A1 (en) * 2002-08-19 2004-02-26 Tatlah, Mohan, Sigh Method of heating substrates heating device and use thereof
US6793443B2 (en) 2002-01-25 2004-09-21 John E. Larsen, Jr. Piling solution
US6825444B1 (en) * 1999-01-29 2004-11-30 Board Of Regents Of University Of Nebraska Heated bridge deck system and materials and method for constructing the same
US20060240183A1 (en) * 2003-07-30 2006-10-26 Pollard John P A Asphalt surface treatment
US8043025B2 (en) 2001-02-28 2011-10-25 Owens Corning Intellectual Capital, Llc Mats for use in paved surfaces
JP2013067953A (en) * 2011-09-21 2013-04-18 Fukui Prefecture Method for controlling snow melting device and method for transmitting road surface state to traveling vehicle, using heat flow sensor for road surface
US8540455B1 (en) * 2012-07-03 2013-09-24 Donald P. Maddux Heated pavement sealant system
JP2017179928A (en) * 2016-03-30 2017-10-05 太平洋マテリアル株式会社 Construction method for pavement concrete, and pavement concrete
US20190177933A1 (en) * 2017-06-12 2019-06-13 Driskell Holdings, LLC Directional Surface Marking Safety and Guidance Devices and Systems
CN111535107A (en) * 2020-05-12 2020-08-14 广东明龙建设有限公司 Beautiful country greening road and construction method thereof

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8562247B2 (en) 2009-01-02 2013-10-22 Heatwurx, Inc. Asphalt repair system and method
US8556536B2 (en) 2009-01-02 2013-10-15 Heatwurx, Inc. Asphalt repair system and method
US9416499B2 (en) 2009-12-31 2016-08-16 Heatwurx, Inc. System and method for sensing and managing pothole location and pothole characteristics
US8801325B1 (en) 2013-02-26 2014-08-12 Heatwurx, Inc. System and method for controlling an asphalt repair apparatus
USD700633S1 (en) 2013-07-26 2014-03-04 Heatwurx, Inc. Asphalt repair device
CN104294732B (en) * 2014-10-20 2017-06-13 中交二公局东萌工程有限公司 A kind of high-elastic viscous stress absorbed layer
CN108951345A (en) * 2018-08-06 2018-12-07 南通鑫金建设集团有限公司 Zip mode quickly repairs the construction method of measures of cracks on concrete pavement

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1955421A (en) * 1934-04-17 Concrete structure and method of
US210101A (en) * 1878-11-19 Improvement in composition pavements
US3775018A (en) * 1971-07-22 1973-11-27 Cmi Corp Road texturing machine
WO1988003303A1 (en) * 1986-10-31 1988-05-05 Gemmer Hans Juergen Process for the provision of induction loops on railway track surfaces, heat or humidity detecting layers and control tracks for unmanned vehicles
US5494741A (en) * 1986-12-12 1996-02-27 Frank Fekete Time delayed thickening, slump-resistant polymer concrete compositions, methods of repairing concrete surfaces, concrete structures repaired therewith and articles of construction comprising a formed mass of said compositions in cured condition
US5079095A (en) * 1989-03-10 1992-01-07 Wendell Reed Method and composition for chip sealing a roadway
US5700385A (en) * 1996-01-04 1997-12-23 Jones; Thaddeus M. Apparatus for supporting and locating buried cable and similar devices

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6825444B1 (en) * 1999-01-29 2004-11-30 Board Of Regents Of University Of Nebraska Heated bridge deck system and materials and method for constructing the same
US8043025B2 (en) 2001-02-28 2011-10-25 Owens Corning Intellectual Capital, Llc Mats for use in paved surfaces
US6793443B2 (en) 2002-01-25 2004-09-21 John E. Larsen, Jr. Piling solution
WO2004016856A1 (en) * 2002-08-19 2004-02-26 Tatlah, Mohan, Sigh Method of heating substrates heating device and use thereof
US20060240183A1 (en) * 2003-07-30 2006-10-26 Pollard John P A Asphalt surface treatment
JP2013067953A (en) * 2011-09-21 2013-04-18 Fukui Prefecture Method for controlling snow melting device and method for transmitting road surface state to traveling vehicle, using heat flow sensor for road surface
US8540455B1 (en) * 2012-07-03 2013-09-24 Donald P. Maddux Heated pavement sealant system
JP2017179928A (en) * 2016-03-30 2017-10-05 太平洋マテリアル株式会社 Construction method for pavement concrete, and pavement concrete
US20190177933A1 (en) * 2017-06-12 2019-06-13 Driskell Holdings, LLC Directional Surface Marking Safety and Guidance Devices and Systems
US10697138B2 (en) * 2017-06-12 2020-06-30 Driskell Holdings, LLC Directional surface marking safety and guidance devices and systems
CN111535107A (en) * 2020-05-12 2020-08-14 广东明龙建设有限公司 Beautiful country greening road and construction method thereof

Also Published As

Publication number Publication date
AU3876900A (en) 2000-10-04
WO2000055427A1 (en) 2000-09-21
CA2366009A1 (en) 2000-09-21

Similar Documents

Publication Publication Date Title
US20020001506A1 (en) Method of resurfacing roads and bridge decks
US6193793B1 (en) Asphaltic compositions and uses therefor
US10364535B2 (en) Void reducing asphalt membrane composition, method and apparatus for asphalt paving applications
EP0750595A1 (en) Road surfacing composition and process
US20040116557A1 (en) Paving and sealing composition and method of use
CA1139973A (en) Method of sealing bridge deck joints
CN108442208A (en) A kind of pavement structure with Thermal conductivity
US5441360A (en) Asphaltic compositions and uses therefor
US3797951A (en) Wearing courses of stone and mastic on pavements
WO2002020661A1 (en) Paving and sealing composition and method of use
KR20110113793A (en) Snow melting apparatus on paved road and mehod for paving road
JPS63236802A (en) Freeze preventing paving body and paving construction method
CN107489079A (en) A kind of rollable prefabricated conducting concrete cover of snow melt defrost type
KR950006735B1 (en) Urgent road repairing meterial
RU2171237C1 (en) Method for pavement repair
JPH086805Y2 (en) Pavement structure around the bridge joint
EP4217541A1 (en) Marking trafficked pavement substrates using a dry polymer modified cement
Wani A Review of pavements and their types
JPH0721601Y2 (en) Pavement structure at joints such as roads
Hitch et al. Bituminous bases and surfacings for low-cost roads in the tropics
TE ST STRIPS Use of a Very Thin Overlay to Reestablish the Skid Resistance of a Concrete Pavement
Van Wijk et al. Novel Heating Technologies to Control the Surface Conditions of Pavements
Voskuilen et al. Winter problems with Porous Asphalt in the Netherlands
West Rehabilitation of Deteriorated Bridge Slabs
CN110578281A (en) construction method of civil aviation airport field way cement pavement structure layer

Legal Events

Date Code Title Description
AS Assignment

Owner name: POLYCON, INC., MISSISSIPPI

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:WILSON, JACK H. SR.;REEL/FRAME:011575/0996

Effective date: 20010130

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION