US1979547A - Construction of "in situ" concrete piles - Google Patents

Construction of "in situ" concrete piles Download PDF

Info

Publication number
US1979547A
US1979547A US628870A US62887032A US1979547A US 1979547 A US1979547 A US 1979547A US 628870 A US628870 A US 628870A US 62887032 A US62887032 A US 62887032A US 1979547 A US1979547 A US 1979547A
Authority
US
United States
Prior art keywords
pile
grout
concrete
column
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US628870A
Inventor
Hood Andrew
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US1979547A publication Critical patent/US1979547A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes

Definitions

  • Figure 3 is a part sectional elevation through the same boring at a different stage of construction.
  • Figure 4 shows a section through the same boring with the pile completed.

Description

Nov. 6, 1934. A. HOOD CONSTRUCTION OF "IN SITU" CONCRETE FILES Filed Aug. 15. 1932 INVENTOH ANDREW HOOD.
Patented Nov. 6, 1934 PATENT OFFICE CONSTRUCTION OF IN SITU CONCRETE FILES Andrew Hood, London, England Application August 15, 1932, Serial No. 628,870 In Great Britain August 24, 1931 6 Claims.
This invention relates to the construction of in situ concrete piles and has for its object to provide .an improved process and apparatus for the construction of such piles and an improved pile.
According to this invention precast units are employed being adapted to be built up in situto form the pile, the process consisting in boring and lining the bore with metal casing in any well known manner, inserting one or more precast hollow concrete units to form a hollow column within the metal casing, supplying grout under pressure to the hollow core and Withdrawing the metal casing either before or as the grout fills the core.
The metal casing may be sectional and the hollow concrete units may be reinforced, a small clearance being left between the unit and the casing. Passages may be formed or provided communicating between the hollow core and the outer surface of the column. The grout may be supplied to the hollow core through a. tube introduced down the core leading to the bottom. The metal casing may be progressively withdrawn as the grout fills the core or may be withdrawn in stages.
The invention further consists in the process of applying a load to the precast pile composed of a single unit or several units whilst freely positioned within the casing and before the introduction of the grout, by which means the foundation stratum beneath the toe unit is consolidated, the toe unitbeddedin, and the bearing capacity of the foundation stratum can be tested.
The invention'further consists in themethod of utilizing the natural resistance of the sectional metal casing to withdrawal for applying the test load to the column. After the above processes have been carried out and after the introduction of the grout but before it is set, the column may be subjected to the application of a load so .as to ensure continuity of the column and absence of voids.
One or more metal rods may be introduced into longitudinal passages formed in the precast concrete units either before or after the introduction of the grout. The said metal rods may be introduced for the whole or part of the length of the pile for the purpose of bonding the units together, and the rod may extend above the pile to bond the pile with the cap or other superstructure.
A precast concrete unit for use in the processes above described has joggled or dovetailed ends adapted to interlock with the adjacent unit when in position and is provided with one or more longitudinal passages and one or more transverse passages leading from the longitudinal passages to the outer surfaces of the unit through which the grout may be introduced. The precast concrete units are preferably reinforced individually by metal reinforcements in any well known manner. A different form of toe unit may be employed if desired and this may be formed of solid concrete precast and reinforced, the upper end being dovetailed or joggled to co-act with the next precast unit while the lower end is suitably shaped to provide a good weight contact with the stratum in which it is founded.
It will be understood that when the pile is completed the precast units are sheathed in grout concrete and in order to ensure a more perfect keying between the sheath and the units the edges of the units may be rounded or chamfered to provide a key for the grout at the junction of the units.
One form of precast unit made in accordance with this invention consists of a hollow or cylindricalreinforced concrete body having a rib or projection on the upper surface and a recess on the lower surface. The rib or projection and the recess may be slightly tapered, the recess at the bottom of one unit being adapted to engage and be located on the rib or projection at the top of the lower unit. The recess is deeper than the rib or projection and thus provides a reservoir for grout and accommodation for attaching the lowering device. A series of transverse passages communicate between the outer surface of the unit and the reservoir through which the grout introduced down the bore of the unit will find its way into the drill bore and form a concrete sheath surrounding the unit.
Referring to the drawing filed herewith which illustrates the construction of one form of in situ concrete pile made in accordance with one process according .to this invention Figure. 1 is a sectional elevation showing one form of pile being made in the boring.
Figure 2 is an elevation of the upper part of Figure 1 taken at right angles thereto.
Figure 3 is a part sectional elevation through the same boring at a different stage of construction.
Figure 4 shows a section through the same boring with the pile completed.
- The following is .a description of the construction of one form of in situ concrete pile made in accordance with one process according to this invention.
Boring. A boring 2 is made to the required bearing stratum 3 by. the usual methods and tools employed in well boring. The hollow steel casing 4 is sunk to the full depth. The diameter of the hole bored is governed by the greatest external diameter of the pilot or leading section of the casing. Samples of the strata are obtained from the core extracted and preserved for examination. When bearing stratum 3 is reached the formation of the pile is commenced.
Forming the pile.With the steel casing 4 sunk to the full depth of the bore the process of forming the built up body of the pile is commenced by introducing through the hollow casing 4 a solid precast toe unit 5 to engage with the bearing stratum 3. This done, the building up of the shaft of the pile is done by lowering a succession of hollow precast units 6 adapted to form the column of the pile. The form of precast concrete units 6 illustrated each consists of a hollow cylindrical concrete body portion having a central bore 6a extending from top to bottom, a spigot '7 on the upper surface and a socket 8 on the lower surface. The sides of the projection '7 and recess 8 are slightly tapered, the recess at the bottom of one unit engaging the projection on the unit below. The depth of the recess 8 is greater than the height of the projection 7 so that a reservoir 9 is formed for grout. The recess may also be used for engaging the lowering means which of course has to come away after the unit is in position. Transverse passages 10 formed in the body portion communicate between the reservoir 9 and the outer cylindrical surface of the unit through which grout introduced down the bore 6a of the unit will find its way into the casing 4 and also into the bore 2 as the casing 4 is withdrawn. The body portion is reinforced-by metal rods 11 in the usual manner. The top and bottom edges are chamfered at 62) to form a keying groove for cement at the junction of the units and the outer surface is preferably cast rough or grooved. The external diameter of the concrete units 6 is slightly less than the internal diameter of the casing 4. Thus there is built up a concrete column of any desired length forming the body of the pile. The lowering of the precast units may be done by means of any convenient apparatus' or by a specially designed lowering apparatus. The next operation is to apply to the top of the built up concrete column a loadwhich is obviously transmitted without any appreciable loss to the toe unit of the pile, thereby consolidating the foundation stratum and bedding in the toe unit. This is preferably done as illustrated by means of an hydraulic jack 12 acting on a cross head consisting of two H section joists 13 secured between two plates 13a, the upper plate bearing against a loose washer plate 13b, supported by rods 14 from a collar or gland l5 clamped onto the top section of the casing 4, the lower plate 13a having circular socket 130 secured thereto for pcsitioning the jack 12. The plates 13a extend the full length of the H section joists and are slotted at the ends to admit the rods 14. The withdrawal resistance offered by the steel casing 4 .is thus utilized to impose on the column of units a positive load which in practice may vary from approximately 30 to 60 tons according to the length of the casing and the nature of the sub-strata encountered. The jack is provided with a gauge 16. If the reading is maintained, then it indicates that the pile has not settled and that the foundation stratum is capable of bearing the load applied plus the weight of the pile. Thus a total load equal to the resistance of. the casing to extraction plus the weight of the built up concrete column may be imposed on the foundation stratum at the toe unit 5 of the pile and measured on a gauge attached to the jack. A special helmet 17 is preferably employed between the base of the jack 12 and the top of the uppermost precast concrete unit 6.
Pressure is maintained on the hydraulic jack until the required load is imposed on the precast concrete column or until the steel casing commences to lift; then the extraction of the casing is continued as hereafter described by power exerted from the boring tackle (not illustrated), the jack being removed for the time being.
The next operation is to apply a process of cementing to the built up concrete column which for the time being is partly supported by the steel casing 4 and this is done as follows:
A sectional pipe 18 (see Figure 3) is lowered through the central bore 6a of the column of precast concrete units until its bottom end just reaches the grout reservoir 9 immediately above the toe unit 5 and through this pipe cement grout is introduced under any desired pressure. The grout is forced through the transverse passages 10 into the space between the column of the built up pile and the adjacent sub-strata. During the process of cementation the casing 4 and the sectional pipe 18 are both progressively and methodically lifted or extracted until the Whole of the body of the pile has been surrounded and filled with grout.
Thus the bore 6a of the pile and all voids are filled and a valuable sheath of grout is formed around the pile for its full length engaging and combining with the adjacent strata.
The top and bottom edges of the precast units being chamfered at 61) form a V shaped key at their junction providing an effective. key for the grout when set.
Where the bearing or upper stratum is of a permeable nature such as ballast or sand the grout under pressure will engage with the strata and form large collars or thickenings on the pile. In Figure 4 is shown a permeable stratum 19 which has resulted in a thickening 20 being formed on the finished pile.
Before the steel casing 4 is entirely extracted the hydraulic jack is preferably again applied to ensure that the precast units are all rammed tightly together.
The process of cementation now completed, a steel rod 21 acting as a splice ordeveloping bar is inserted down the bore 6a. in the soft grout to any required depth, part of the rod 21 being left projecting from the top of the column.
After the lapse of sufficient time the grout will have set and be incorporated in the finished pile. Thus it will develop highskin friction with the strata and also be securely keyed to the precast shaft.
The finished pile constructed as above described and ready to take its superimposed working load possesses the unique features in the first case of having been subjected to an adequate and measured test load; such a test is obviously more informative and reliable than the old method of judging the bearing capacity by measuring the shoe resistance to penetration of a driven pile hammered to a set, and, in the second case the load carrying capacity of the pile is substantially further increased since the test load has been applied before the skin friction is developed between the surface of the grout skin and the strata.
Some of the novel features and outstanding advantages obtained by this invention are as follows:
(a) The need for testing completed piles is definitely unnecessary, expensive test loads and other heavy expenses in this connection being eliminated.
(b) Supervision of the piling by engineers, architects or other interested parties is reduced to a minimum since all the operations are positive and convincing; saving of expense in this connection.
(a) Piling in waterlogged ground is no detriment to this system; in fact, the presence of water is a help in the process, providing freer action of the cementation.
(d) The piles are subjected to a substantial test load during the process, indicating the load bearing capacity of the sub-strata and, in addition, the developed skin friction enhances the load bearing capacity of the completed piles to a very high degree.
(9) The intrinsic strength of the piles is obtained as desired without the use of heavy and costly continuous steel reinforcement.
(j) Piles can be formed with a minimum headroom of approximately 6 feet inside or around buildings with no danger, vibration, noise or other disturbances to adjacent or adjoining premises.
to) If necessary, the process of forming the piles can be stopped at any stage and recommenced later at will without detriment to the pile when completed.
(it) Piles can be formed raking or vertical as desired.
(1') The length of the piles required can be predetermined almost exactly on inspection of the samples of sub-strata revealed by boring.
(7') There is a minimum of space required for carrying out the process and the elimination of operation dangerous to workmen.
(7c) Cementing under pressure of pile shaft ensures absence of voids and close contact with sub strata.
What I claim and desire to secure by Letters Patent is:
1. The process of forming in situ reinforced concrete piles consisting in boring and lining the bore with metal casing forming a hollow column within the metal casing, supplying grout under pressure to the hollow column and withdrawing the metal casing.
2. The process of forming in situ reinforced concrete piles consisting in boring and lining the bore with sectional metal casing, forming a hollow concrete column within said casing having a small clearance and passages communicating between the inner and outer surfaces of the column, supplying grout under pressure to the hollow column through a tube leading to the bottom of the column and progressively withdrawing the metal casing and tube as the grout fills the column and is expressed through the said passages to fill the voids surrounding the column.
3. The process of forming in situ reinforced concrete piles consisting in boring and lining the bore with metal casing, forming a hollow column Within the metal casing, applying a load to the hollow column whilst freely positioned in the casing, supplying grout under pressure to the hollow column and withdrawing the metal casing.
4. The process of forming in situ reinforced concrete piles consisting in boring and lining the bore with metal casing, forming a hollow column within the metal casing, applying a load to the column whilst freely positioned in the casing, supplying grout under pressure to the hollow column, withdrawing the metal casing, and applying a load to the column after the introduction of the grout, but before it has set to ensure continuity of the column and absence of voids.
5. A concrete pile comprising a plurality of hollow precast concrete units assembled end to end and totally ensheathed and filled with grout.
6. A concrete pile comprising a plurality of hollow precast concrete units assembled end to end and filled with grout, the whole being totally ensheathed with grout to which is bonded a layer of aggregate from the surrounding strata into which the grout has permeated under pressure.
ANDREW HOOD.
US628870A 1931-08-24 1932-08-15 Construction of "in situ" concrete piles Expired - Lifetime US1979547A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB1979547X 1931-08-24

Publications (1)

Publication Number Publication Date
US1979547A true US1979547A (en) 1934-11-06

Family

ID=10895165

Family Applications (1)

Application Number Title Priority Date Filing Date
US628870A Expired - Lifetime US1979547A (en) 1931-08-24 1932-08-15 Construction of "in situ" concrete piles

Country Status (1)

Country Link
US (1) US1979547A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3073124A (en) * 1957-06-26 1963-01-15 Nadal Jose Soler Method for piles cast-in-situ
US3151464A (en) * 1959-05-25 1964-10-06 Nippon Sharyo Seizo Kk Foundation piles
US3213629A (en) * 1963-03-20 1965-10-26 Socony Mobil Oil Co Inc Apparatus and method for installation of a pile-jacket assembly in a marine bottom
US3277968A (en) * 1963-06-28 1966-10-11 Wood Marc Sa Screw piles
US3279195A (en) * 1960-10-07 1966-10-18 Taylor Woodrow Const Ltd Driving and/or extraction of piles and similar structural members
US3470701A (en) * 1967-09-19 1969-10-07 Lee A Turzillo Means for making concrete piles
US3507124A (en) * 1969-05-06 1970-04-21 Lee A Turzillo Method for making concrete piles
US3960008A (en) * 1974-12-12 1976-06-01 Goble George G Pile capacity testing means
US4126007A (en) * 1977-01-03 1978-11-21 L.B. Foster Company Compaction of soil
EP0404703A1 (en) * 1989-06-21 1990-12-27 Raymond Louis Foundation piles, methods, tools and devices for the construction of these piles

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3073124A (en) * 1957-06-26 1963-01-15 Nadal Jose Soler Method for piles cast-in-situ
US3151464A (en) * 1959-05-25 1964-10-06 Nippon Sharyo Seizo Kk Foundation piles
US3279195A (en) * 1960-10-07 1966-10-18 Taylor Woodrow Const Ltd Driving and/or extraction of piles and similar structural members
US3213629A (en) * 1963-03-20 1965-10-26 Socony Mobil Oil Co Inc Apparatus and method for installation of a pile-jacket assembly in a marine bottom
US3277968A (en) * 1963-06-28 1966-10-11 Wood Marc Sa Screw piles
US3470701A (en) * 1967-09-19 1969-10-07 Lee A Turzillo Means for making concrete piles
US3507124A (en) * 1969-05-06 1970-04-21 Lee A Turzillo Method for making concrete piles
US3960008A (en) * 1974-12-12 1976-06-01 Goble George G Pile capacity testing means
US4126007A (en) * 1977-01-03 1978-11-21 L.B. Foster Company Compaction of soil
EP0404703A1 (en) * 1989-06-21 1990-12-27 Raymond Louis Foundation piles, methods, tools and devices for the construction of these piles
FR2648839A1 (en) * 1989-06-21 1990-12-28 Louis Raymond FOUNDATION PILES, METHODS, TOOLS AND MACHINES FOR CONSTRUCTING THESE PILES

Similar Documents

Publication Publication Date Title
CN108914931A (en) A kind of ring-like foundation pile of the vertical shield of assembled and construction method
US1979547A (en) Construction of "in situ" concrete piles
US4401397A (en) Method and device for installing a shaft lining in shafts through an aquiferous formation
Meyerhof et al. An investigation of the bearing capacity of some bored and driven piles in London Clay
CN109024721B (en) Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN107642041A (en) The hollow clump of piles anchorage of super-large diameter
CN104711975B (en) Construction technology for long spiral cast-in-situ bored pile
CN107326898B (en) I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof
CN109537579A (en) The construction method of cast-in-situ bored pile
US3470701A (en) Means for making concrete piles
US3512365A (en) Method of forming a pile in situ
CN207582471U (en) A kind of Retaining Structure with Double-row Piles equipped with deep layer prestress anchorage cable
Mangushev et al. Analysis of practical application of screw-in cast piles
CN107642040A (en) The construction method heavy stone used as an anchor of the hollow clump of piles anchorage of super-large diameter
CN209339143U (en) A kind of concrete pipe pile construction equipment
CN110273413A (en) A kind of efficient construction method of prefabricated pile
CN109339044A (en) A kind of concrete pipe pile construction equipment
GB2378471A (en) Method of forming enlarged pile heads with pre-cast driven piles
CN207017255U (en) Mechanical pile system in hole
CN105952381A (en) Anchor rod drill bit capable of recycling anchor cable
CN207469230U (en) Drum prefabricated pile supporting construction is adjusted in a kind of cement soil wall interpolation rigidity
CN205677538U (en) A kind of anchor bit of Recyclable anchor rope
Marsland The use of in-situ tests in a study of the effects of fissures on the properties of stiff clays
CN220414223U (en) Pile anchor reinforcing device penetrating through weak rock stratum
CN215715241U (en) Novel post-tensioned prestressing rectangular cast-in-place pile