TWM595267U - Engineering planning management system - Google Patents

Engineering planning management system Download PDF

Info

Publication number
TWM595267U
TWM595267U TW108211898U TW108211898U TWM595267U TW M595267 U TWM595267 U TW M595267U TW 108211898 U TW108211898 U TW 108211898U TW 108211898 U TW108211898 U TW 108211898U TW M595267 U TWM595267 U TW M595267U
Authority
TW
Taiwan
Prior art keywords
engineering
project
module
planning
item
Prior art date
Application number
TW108211898U
Other languages
Chinese (zh)
Inventor
李忠
林振東
林俊印
周宜新
Original Assignee
富邦人壽保險股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 富邦人壽保險股份有限公司 filed Critical 富邦人壽保險股份有限公司
Priority to TW108211898U priority Critical patent/TWM595267U/en
Publication of TWM595267U publication Critical patent/TWM595267U/en

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

一種工程規劃管理系統包括資料庫、需求接收模組、工程規劃模組、詢價管理模組、預算請購模組、工程採購發包模組和工程進度管理模組。資料庫用以儲存複數工程相關資訊及職場平面圖檔。需求接收模組用以接收需求單位傳送之第一需求資訊。工程規劃模組訊號連接該需求接收模組,工程規劃模組依據第一需求資訊產生工程作業所需之工程項目清單,其中工程項目清單包括至少一工程項目以及該至少一工程項目對應之工項資料。An engineering planning management system includes a database, a demand receiving module, an engineering planning module, an inquiry management module, a budget requisition module, an engineering procurement outsourcing module, and an engineering progress management module. The database is used to store multiple engineering related information and workplace floor plan files. The demand receiving module is used to receive the first demand information sent by the demand unit. The signal of the engineering planning module is connected to the demand receiving module, and the engineering planning module generates a list of engineering items required for the engineering operation according to the first demand information, wherein the engineering item list includes at least one engineering item and the corresponding engineering item of the at least one engineering item data.

Description

工程規劃管理系統Engineering planning management system

本新型係關於一種工程規劃管理系統,特別是一種方便企業內部的工程承辦單位規畫、控管和紀錄企業職場之工程作業的工程規劃管理系統。This new type relates to an engineering planning management system, especially an engineering planning management system that facilitates the planning, control, and recording of engineering operations in the enterprise's workplace by the project undertaking unit within the enterprise.

一般的企業若是需要建置新的辦公室,通常會以紙本的方式讓相關需求單位、核准單位、承辦單位、施工單位進行填寫資料、簽核、改圖…等書面作業。然而,紙本形式的表單不易追蹤管理,需求單位也無法即時控管辦公室的建置進度和施工品質。紙本形式的眾多表單通常會散落在各個承辦單位,無法統一管理且後續難以查詢。另外,辦公室的工程作業、資產系統並未形成電子化的資料連結,因此無法達成資源共享。因此,有必要提供一種新的工程規劃管理系統,其可解決上述問題。If a general enterprise needs to build a new office, it will usually ask the relevant demand unit, approval unit, contractor, and construction unit to complete the written work such as filling out the data, signing, and changing the drawings. However, the paper form is not easy to track and manage, and the demand unit cannot control the construction progress and construction quality of the office in real time. Numerous forms in paper form are usually scattered in various undertaking units, which cannot be managed in a unified manner and are difficult to query later. In addition, the office's engineering operations and asset systems have not formed an electronic data link, so resources cannot be shared. Therefore, it is necessary to provide a new engineering planning management system, which can solve the above problems.

本新型之主要目的係在提供一種方便企業內部的工程承辦單位規畫、控管和紀錄企業職場之工程作業的工程規劃管理系統。The main purpose of this new model is to provide an engineering planning and management system that facilitates the planning, control, and recording of the engineering work in the enterprise's workplace by the engineering contractor within the enterprise.

為達成上述之目的,本新型之工程規劃管理系統用以規劃並管理一工程作業,本新型之工程規劃管理系統包括資料庫、需求接收模組、工程規劃模組、詢價管理模組、預算請購模組、工程採購發包模組和工程進度管理模組。資料庫儲存複數工程相關資訊及職場平面圖檔。需求接收模組接收需求單位傳送之第一需求資訊。工程規劃模組訊號連接需求接收模組,工程規劃模組依據第一需求資訊產生工程作業所需之工程項目清單,其中工程項目清單包括至少一工程項目以及該至少一工程項目對應之一工項資料。詢價管理模組訊號連接資料庫及工程規劃模組。詢價管理模組包括詢價派商模組和詢價單整合模組。詢價派商模組係依據一派商規則於複數工程廠商資訊中找尋與至少一工程項目之一工程類別相符之複數工程報價廠商,並將詢價單傳送至複數工程報價廠商,其中詢價單包括至少一工程項目及一工項資料。詢價單整合模組接收並彙整複數工程報價廠商依據詢價單傳送之工程報價單以產生工程預算單。In order to achieve the above purpose, the new-type engineering planning management system is used to plan and manage an engineering operation. The new-type engineering planning management system includes a database, a demand receiving module, an engineering planning module, an inquiry management module, and a budget Requisition module, project procurement contracting module and project schedule management module. The database stores information about multiple projects and workplace plan files. The demand receiving module receives the first demand information sent by the demand unit. The signal of the engineering planning module is connected to the demand receiving module, and the engineering planning module generates a list of engineering items required for the engineering operation according to the first demand information, wherein the list of engineering items includes at least one engineering item and a corresponding item of the at least one engineering item data. Inquiry management module signal connects to database and engineering planning module. The inquiry management module includes an inquiry inquiry distributor module and an inquiry inquiry integration module. Inquiry distributor module is to search for multiple engineering quotation vendors that match one of the engineering categories of at least one engineering item in the plural engineering vendor information according to the one distributor rule, and send the inquiry quotation to the plural engineering quotation vendors, where the inquiry quotation Including at least one project and one project data. The inquiry form integration module receives and aggregates the engineering quotation sent by the multiple engineering quotation vendors based on the inquiry form to generate an engineering budget form.

藉由本新型的工程規劃管理系統的架構設計,可以方便使用者控管和紀錄職場建置流程,且在職場建置流程中的所有資料和所有產生的表單皆會被統一儲存在工程規劃管理系統,以達成將所有表單統一管理、資源共享,形成電子化的資料連結的功效,方便承辦人員後續查詢和追蹤管理。With the architectural design of the new-type engineering planning management system, it is convenient for users to control and record the workplace construction process, and all data and all generated forms in the workplace construction process will be stored in the engineering planning management system In order to achieve the unified management and resource sharing of all forms to form an electronic data link, it is convenient for contractors to follow up and track management.

為能讓 貴審查委員能更瞭解本新型之技術內容,特舉較佳具體實施例說明如下。以下請一併參考圖1至圖9關於本新型之工程規劃管理系統之系統架構圖、流程圖、申請單、工程項目清單、工程廠商清單、詢價單、工程報價單、工程預算單、請購單、工程進度表單、進度列表以及案件受理單之示意圖。In order to allow your reviewing committee to better understand the technical content of this new model, the following specific preferred embodiments are described below. The following please refer to Figures 1 to 9 for the system architecture diagram, flowchart, application form, project list, project manufacturer list, inquiry list, project quotation, and project budget list of this new type of engineering planning management system. Schematic diagram of purchase order, project progress form, progress list and case acceptance slip.

如圖1所示,在本新型的一實施例中,工程規劃管理系統1一台或多台伺服器以便一企業的工程承辦單位規畫、控管和紀錄企業職場之工程作業,其中本新型的工程作業包括舊有職場修繕作業或新建職場建置作業。本新型的工程規劃管理系統1依據工程作業進度透過網路與對應之簽核單位500、第一承辦單位700、工程報價廠商81a、承辦工程廠商830和需求單位900所使用的電腦或手機訊號連接。根據本新型之一具體實施例,第一承辦單位700、工程報價廠商81a、承辦工程廠商830和需求單位900的工作者可以操作電腦或手機以連線至工程規劃管理系統1,以配合工程規劃管理系統1進行工程作業。As shown in FIG. 1, in an embodiment of the present invention, one or more servers in the engineering planning management system 1 are used by an enterprise’s project undertaker to plan, control and record the engineering work in the enterprise’s workplace. The engineering work includes repairing old workplaces or building new workplaces. The new-type engineering planning management system 1 connects to the corresponding signing unit 500, the first contracting unit 700, the project quoting vendor 81a, the contracting project vendor 830 and the demanding unit 900 through the network according to the progress of the project operation. . According to a specific embodiment of the present invention, the workers of the first contractor 700, the project quotation vendor 81a, the contractor 830 and the demander 900 can operate a computer or mobile phone to connect to the project planning management system 1 to cooperate with the project planning The management system 1 performs engineering work.

如圖1所示,在本新型的一實施例中,工程規劃管理系統1包括需求接收模組10、工程規劃模組20、詢價管理模組30、預算請購模組40、工程採購發包模組50、工程進度管理模組70、資料庫80和工程資料彙整模組90。如圖1和圖3所示,在本新型的一實施例中,需求接收模組10提供一申請單11以供一需求單位900填寫第一需求資訊111,並接收需求單位900回傳之第一需求資訊111。As shown in FIG. 1, in an embodiment of the present invention, the engineering planning management system 1 includes a demand receiving module 10, an engineering planning module 20, an inquiry management module 30, a budget requisition module 40, and a project procurement contract A module 50, a project progress management module 70, a database 80, and a project data integration module 90. As shown in FIGS. 1 and 3, in an embodiment of the present invention, the demand receiving module 10 provides an application form 11 for a demand unit 900 to fill in the first demand information 111, and receives the first return of the demand unit 900. One demand information 111.

根據本新型之一具體實例,當工程作業為新建職場作業時,需求接收模組10更包括需求資訊通知模組13,工程規劃模組20更包括預定使用坪數產生模組23,第一需求資訊111得包括一人數資訊、一職級資訊及/或一隔間資訊,且當需求接收模組10收到第一需求資訊111之人數資訊後,接收模組10將該人數資訊提供給工程規劃模組20,工程規劃模組20之預定使用坪數產生模組23可依據第一需求資訊111之人數資訊、職級資訊及/或隔間資訊進行計算以產生一預定使用坪數,再透過需求資訊通知模組13通知第一承辦單位700找尋與預定使用坪數匹配之目標場地。其中,當人數相同而相應之職級不同時,預定使用坪數及/或隔間資訊不同。例如當二新建職場作業之總人數皆為10且主管與非主管比例分別為1:9與2:8時,主管比例較高的新建職場之預定使用坪數會大於主管比例較低的新建職場。According to a specific example of the present invention, when the engineering operation is a new workplace operation, the demand receiving module 10 further includes a demand information notification module 13, and the engineering planning module 20 further includes a scheduled usage number generation module 23, the first demand The information 111 may include a number of people information, a rank information and/or a compartment information, and when the demand receiving module 10 receives the number of people information of the first demand information 111, the receiving module 10 provides the number of people information to the project planning Module 20, the planned usage ping number generation module 23 of the engineering planning module 20 can calculate according to the number information, rank information and/or compartment information of the first demand information 111 to generate a predetermined usage ping number, and then pass the demand The information notification module 13 notifies the first undertaking unit 700 to find a target venue that matches the number of planned pings. Among them, when the number of people is the same and the corresponding ranks are different, the number of tents and/or compartment information to be used are different. For example, when the total number of jobs in the two new workplaces is 10 and the ratio of supervisors and non-supervisors is 1:9 and 2:8, respectively, the number of yards planned for new workplaces with higher supervisor ratios will be greater than those for new workplaces with lower supervisor ratios .

如圖1和圖4所示,工程規劃模組20訊號連接需求接收模組10,工程規劃模組20將第一需求資訊111傳送至製圖單位600以供製圖單位600依據第一需求資訊111繪製目標場地之室內設計圖;接著,工程規劃模組20用以接收目標場地之室內設計圖,並依據目標場地之室內設計圖與第一需求資訊111產生完成目標場地之新建職場作業所需之工程項目清單21,其中工程項目清單21包括至少一工程項目211以及對應之一工項資料212。在本實施例中,資料庫80儲存有複數工程相關資訊81及職場平面圖檔。As shown in FIGS. 1 and 4, the engineering planning module 20 connects the signal to the demand receiving module 10. The engineering planning module 20 transmits the first demand information 111 to the drawing unit 600 for the drawing unit 600 to draw based on the first demand information 111 The interior design drawing of the target site; then, the engineering planning module 20 is used to receive the interior design drawing of the target site, and generate the project required to complete the new workplace operation of the target site based on the interior design drawing of the target site and the first demand information 111 The project list 21, wherein the project list 21 includes at least one project 211 and one corresponding work item data 212. In this embodiment, the database 80 stores a plurality of engineering related information 81 and a workplace plan file.

根據本新型之另一具體實例,當工程作業為舊有職場修繕作業時,第一需求資訊111可為一修繕工程資訊,如:更換網路線路或更換辦公室隔間板等修繕作業。工程規劃模組20訊號連接需求接收模組10,工程規劃模組20依據第一需求資訊111產生工程作業(如: 更換網路線路或更換辦公室隔間板等修繕作業)所需之工程項目清單21,其中該工程項目清單21包括工程項目211以及工程項目211對應之工項資料212,工項資料212係包含用已完成工程項目所211必須之材料、物件與設備等。According to another specific example of the present invention, when the engineering operation is an old workplace repair operation, the first demand information 111 may be a repair engineering information, such as: repairing a network line or replacing an office partition board. The engineering planning module 20 connects the signal to the demand receiving module 10, and the engineering planning module 20 generates a list of engineering items required for engineering operations (such as: replacing network lines or replacing office partition boards and other repair operations) based on the first demand information 111 21, where the engineering project list 21 includes the engineering project 211 and the project data 212 corresponding to the engineering project 211, and the project data 212 includes materials, objects, and equipment necessary to use the completed engineering project 211.

如圖1和圖5、圖5a所示,詢價管理模組30訊號連接資料庫80及工程規劃模組20,詢價管理模組30包括一詢價派商模組31和一詢價單整合模組33。詢價派商模組31依據一派商規則於複數工程相關資訊81中找尋至少一工程項目211之一工程類別相符之複數工程報價廠商81a,並將詢價單32傳送至該複數工程報價廠商81a,其中詢價單32包括至少一工程項目211以及一工項資料212。As shown in FIGS. 1 and 5 and 5a, the inquiry management module 30 is connected to the database 80 and the engineering planning module 20. The inquiry management module 30 includes an inquiry distributor module 31 and an inquiry form Integrated module 33. Inquiry distributor module 31 finds plural engineering quotation vendors 81a in which at least one engineering item 211 matches one of the engineering categories in the plural engineering related information 81 according to a distributor rule, and transmits the inquiry quotation 32 to the plural engineering quotation vendors 81a , Where the inquiry list 32 includes at least one engineering item 211 and one work item data 212.

根據本新型之一實施例,派商規則為將該至少一工程項目211輪流分派工程類別中之複數工程報價廠商81a,前述輪流分派係指依一定預先排定好之順序分派或依一定預先設定好之規則分派。詢價單整合模組33用以接收並彙整複數工程報價廠商81a依據詢價單32傳送之一工程報價單331,詢價單整合模組33於接收各工程報價廠商81a傳送之工程報價單331後產生工程預算單332。在本實施中,詢價單整合模組33需收到所有複數工程報價廠商81a回傳之詢價單32後才會產生工程預算單332,若複數工程報價廠商81a之其中之一未傳送工程報價單331,詢價單整合模組33發出一提示訊息至工程報價廠商81a。如圖1和圖6所示,預算請購模組40訊號連接詢價單整合模組33,預算請購模組40接收工程預算單332並將工程預算單332傳送至一簽核單位500,其中工程預算單332包括至少一待發包工項3321(如圖7所示)。According to an embodiment of the present invention, the dispatching rule is to assign at least one engineering project 211 to a plurality of engineering quotation vendors 81a in the engineering category in turn. The foregoing rotating dispatching refers to dispatching according to a certain pre-arranged order or according to a certain preset Good rule distribution. The inquiry order integration module 33 is used to receive and aggregate a plurality of engineering quotation manufacturers 81a to transmit one engineering quotation 331 according to the inquiry quotation 32, and the inquiry order integration module 33 receives the engineering quotation 331 transmitted by each engineering quotation manufacturer 81a Afterwards, the project budget slip 332 was generated. In this implementation, the RFQ integration module 33 needs to receive all the RFQs returned by the plural engineering quotation vendors 81a before generating the engineering budget slip 332. If one of the plural engineering quotation vendors 81a has not transmitted the project The quotation form 331 and the inquiry form integration module 33 send a prompt message to the engineering quotation manufacturer 81a. As shown in FIGS. 1 and 6, the budget requisition module 40 is connected to the RFQ integration module 33. The budget requisition module 40 receives the project budget 332 and transmits the project budget 332 to a signing unit 500. Among them, the project budget sheet 332 includes at least one to-be-contracted work item 3321 (as shown in FIG. 7).

如圖1、圖7和圖8所示,工程採購發包模組50與預算請購模組40訊號連接以便接收簽核完成之工程預算單332。工程採購發包模組50根據待發包工項3321產生對應之至少一工程採購單52,並經一採購流程將該至少一待發包工項3321發包予一承辦工程廠商830。根據本新型之一具體實施例,工程預算單332包括複數待發包工項3321,工程採購發包模組50得一次產生多張工程採購單52,並經一採購流程將複數待發包工項3321發包予複數承辦工程廠商830。As shown in FIG. 1, FIG. 7 and FIG. 8, the project procurement and outsourcing module 50 is signal-connected to the budget requisition module 40 in order to receive the signed project budget 332. The engineering procurement contract issuing module 50 generates at least one engineering purchase order 52 according to the to-be-contracted work item 3321, and outsources the at least one to-be-contracted work item 3321 to a contractor 830 through a procurement process. According to a specific embodiment of the present invention, the project budget slip 332 includes a plurality of projects to be contracted 3321, the project procurement and contract issuing module 50 may generate multiple project purchase orders 52 at a time, and the plurality of projects to be contracted 3321 are contracted through a procurement process To multiple contractor engineering manufacturers 830.

如圖1和圖9所示,工程進度管理模組70依據一工程規劃進度E,管理各承辦工程廠商830之施工進度,根據本新型之一具體實施例,工程規劃進度E為一工程進度列表,工程進度列表包括複數預定工程,各複數預定工程包括一預定施工日以及一預定施工天數,工程進度管理模組70於預定施工日開始前兩天發出一施工通知給根據預定工程之承辦工程廠商830。在本實施例中,工程進度管理模組70可接收承辦工程廠商830於工程期間內回傳之一施工進度資訊,其中本新型之施工進度資訊包括一文字資訊及/或一圖像資訊。根據本新型之一具體實施例,承辦工程廠商830需定時利用照片(圖像資訊)或文字(文字資訊)回報當前工程進度。As shown in FIGS. 1 and 9, the project progress management module 70 manages the construction progress of each contractor 830 according to a project planning progress E. According to a specific embodiment of the present invention, the project planning progress E is a project progress list The project schedule includes a plurality of scheduled projects, each of which includes a scheduled construction day and a scheduled construction day. The project schedule management module 70 sends a construction notice to the contractor based on the scheduled project two days before the scheduled construction day begins 830. In this embodiment, the construction progress management module 70 may receive a piece of construction progress information returned by the contractor 830 during the construction period, where the construction progress information of the present invention includes text information and/or image information. According to a specific embodiment of the present invention, the contractor 830 needs to regularly use photos (image information) or text (text information) to report the current project progress.

如圖1所示,工程資料彙整模組90訊號連接需求接收模組10、工程規劃模組20、詢價管理模組30、預算請購模組40、工程採購發包模組50、工程進度管理模組70和資料庫80。於目標場地之工程作業完成後,工程資料彙整模組90將工程項目清單21、工程報價單331、工程預算單332、工程採購單52及/或承辦工程廠商830等資訊彙整產生一結案報告,並將結案報告儲存於資料庫80。As shown in FIG. 1, the project data integration module 90 signal connection demand receiving module 10, project planning module 20, inquiry management module 30, budget requisition module 40, project procurement outsourcing module 50, project progress management Module 70 and database 80. After the completion of the engineering operations at the target site, the engineering data integration module 90 aggregates the information of the engineering project list 21, engineering quotation 331, engineering budget 332, engineering purchase order 52, and/or contractor 830 to produce a closing report. And save the closing report in the database 80.

根據本新型之一具體實施例,如圖1和圖2所示,當一需求單位900需要執行工程作業之新建職場作業時,需求單位900可推派一位申請人(假設該申請人之姓名為陳大君)使用電腦以連線到工程規劃管理系統1,此時,工程規劃管理系統1會執行職場建置作業流程之步驟101:提供一申請單11,以接收一需求單位傳送之一第一需求資訊。According to a specific embodiment of the present invention, as shown in FIG. 1 and FIG. 2, when a demand unit 900 needs to perform engineering work in a new workplace operation, the demand unit 900 may appoint an applicant (assuming the applicant’s name For Chen Dajun) use a computer to connect to the engineering planning management system 1, at this time, the engineering planning management system 1 will perform the step 101 of the workplace construction process: provide an application form 11 to receive the first transmission from a demand unit Demand information.

如圖1和圖3所示,需求接收模組10提供一申請單11至需求單位900的電腦,以供申請人陳大君運用電腦填寫申請人資料(例如所屬單位和姓名)和第一需求資訊111。在本實施例中,第一需求資訊111包括一人數資訊、一職級資訊(例如總經理、經理等職級之人員是否會運用此職場和對應職級人員之數量,且較高職級的人員會配置較大的空間)、以及一隔間資訊(例如會議室、茶水間、機房、工作空間等等不同用處的房間,以及房間數量)。需求單位900填寫完資料後可按下申請單11下方的「送出」鈕,以使需求接收模組10接收需求單位900回傳之第一需求資訊111。As shown in FIGS. 1 and 3, the demand receiving module 10 provides a computer from an application form 11 to a demand unit 900 for the applicant Chen Dajun to use the computer to fill in the applicant’s information (such as the affiliation and name) and the first demand information 111 . In this embodiment, the first demand information 111 includes information on a number of people and information on a rank (for example, whether staff at the rank of general manager, manager, etc. will use this workplace and the number of staff at the corresponding rank. Large space), as well as information about a compartment (such as meeting rooms, pantry, computer room, work space, etc., and the number of rooms). After the demand unit 900 fills in the data, it can press the "send" button under the application form 11 to enable the demand receiving module 10 to receive the first demand information 111 returned by the demand unit 900.

接著,工程規劃管理系統1會執行步驟102:通知一第一承辦單位找尋與預定使用坪數匹配之目標場地。Next, the engineering planning management system 1 will perform step 102: notify a first contractor to find a target venue that matches the number of planned pings.

職場建置建構需求接收模組10收到第一需求資訊111後,會將第一需求資訊111的人數資訊傳送給工程規劃模組20,工程規劃模組20之預定使用坪數產生模組23會依據人數資訊產生一預定使用坪數。工程規劃模組20會將預定使用坪數傳送給職場建置建構需求接收模組10,需求資訊通知模組13會通知一第一承辦單位700找尋與該預定使用坪數匹配之目標場地。當第一承辦單位700尋得符合需求的目標場地後,將目標場地資訊提供給工程規劃模組20,接著工程規劃模組20會將第一需求資訊111之所有內容傳送至一製圖單位600以供製圖單位600依據第一需求資訊111繪製目標場地之室內設計圖。在其他實施例中,製圖單位600執行目標場地之室內設計圖繪製作業時還包含一圖面討論與確認作業,製圖單位600先繪製一圖面初稿給需求單位900,待需求單位900確認圖面後,製圖單位600產生一目標場地之室內設計圖。After receiving the first demand information 111, the workplace construction and construction demand receiving module 10 will send the number of people in the first demand information 111 to the engineering planning module 20, and the planned use number generating module 23 of the engineering planning module 20 A predetermined number of pings will be generated based on the number of people. The engineering planning module 20 will transmit the number of planned pings to the workplace construction and construction demand receiving module 10, and the demand information notification module 13 will notify a first undertaking unit 700 to find a target venue that matches the predetermined number of pings. When the first contractor 700 finds a target venue that meets the demand, the target venue information is provided to the engineering planning module 20, and then the engineering planning module 20 transmits all the content of the first demand information 111 to a drawing unit 600 to The drawing unit 600 draws the interior design drawing of the target venue according to the first demand information 111. In other embodiments, the drawing unit 600 includes a drawing discussion and confirmation operation when performing the interior design drawing operation of the target site. The drawing unit 600 first draws a first drawing to the demanding unit 900, and the waiting unit 900 confirms the drawing After that, the drawing unit 600 generates an interior design drawing of the target venue.

接著,工程規劃管理系統1會進行步驟103:依據第一需求資訊111產生工程作業所需之一工程項目清單21,其中工程項目清單21包括至少一工程項目211以及工程項目211對應之一工項資料212。Next, the engineering planning management system 1 will proceed to step 103: generate a list 21 of engineering items required for the engineering operation based on the first demand information 111, wherein the list 21 of engineering items includes at least one engineering item 211 and one corresponding to the engineering item 211 Information 212.

如圖1和圖4所示,工程規劃模組20接收製圖單位600完成並經需求單位900確認後之目標場地之室內設計圖,並依據目標場地之室內設計圖與第一需求資訊111之所有資訊,產生完成目標場地之職場建置作業所需之工程項目清單21。在本實施例中,工程項目清單21包括七個工程項目211和工程項目211對應之一工項資料212,例如為建置該目標場地需要的裝潢、家具、電器和搬遷,並列出各個工程項目211的具體要求如電器項目的冷氣數量、照明燈數量等等,但工程項目211的內容不以上述為限,其可依照不同的職場類型需求而改變。As shown in FIGS. 1 and 4, the engineering planning module 20 receives the interior design drawing of the target site completed by the drawing unit 600 and confirmed by the demand unit 900, and based on all the interior design drawings of the target site and the first demand information 111 Information, generate a list of engineering items 21 required to complete the workplace construction of the target site. In this embodiment, the engineering project list 21 includes seven engineering projects 211 and one project data 212 corresponding to the engineering project 211, such as the decoration, furniture, electrical appliances and relocation required for the construction of the target site, and lists each engineering project The specific requirements of 211 are such as the number of air-conditioners and the number of lighting lamps in the electrical project, but the content of the engineering project 211 is not limited to the above, and it can be changed according to the needs of different types of workplaces.

接著,工程規劃管理系統1會進行步驟104:依據一派商規則於複數工程廠商資訊中找尋與該至少一工程項目211之一工程類別相符之複數工程報價廠商81a,並將包含至少一工程項目211之詢價單32傳送給複數工程報價廠商81a,詢價單32包括工程項目211以及工項資料212。Next, the engineering planning management system 1 will proceed to step 104: find a plurality of engineering bidding vendors 81a that match one of the engineering categories of the at least one engineering project 211 in the plural engineering manufacturer information according to a distribution rule, and will include at least one engineering project 211 The inquiry sheet 32 is transmitted to the plural engineering quotation manufacturers 81a. The inquiry sheet 32 includes the engineering item 211 and the work item data 212.

如圖1、圖5和圖5a所示,詢價管理模組30之詢價派商模組31會依據一派商規則於資料庫80儲存的工程相關資訊81中,找尋與工程項目211之工程類別相符之複數工程報價廠商81a,並將工程項目211傳送給複數工程報價廠商81a。在本實施例中,派商規則為將工程項目211輪流分派工程類別中之複數工程報價廠商81a。在本實施例中,詢價派商模組31從工程相關資訊81中挑選出四家工程報價廠商81a:BB室內裝修、DD家具、FF電器和GG搬家,該些工程報價廠商81a之工程類別和工程項目211相符,並且詢價派商模組31傳送詢價單32給該些工程報價廠商81a以分配工程項目211,詢價單32包括工程項目211以及工項資料212;詢價派商模組31也通知該些工程報價廠商81a針對分配到的工程項目211和工項資料212報價。另外,在工程相關資訊81中,各家廠商旁邊有「資料」按鈕,當承辦人員按下該些按鈕時,可查看對應的廠商資料(例如聯絡方式、廠商營業內容、廠商合作紀錄…等等)。As shown in FIG. 1, FIG. 5 and FIG. 5a, the inquiry distributor module 31 of the inquiry management module 30 will search for the project related to the project 211 in the project related information 81 stored in the database 80 according to a distributor rule The plural engineering quotation vendors 81a that match the category, and transmit the engineering item 211 to the plural engineering quotation vendors 81a. In this embodiment, the distribution rule is to assign engineering projects 211 in turn to a plurality of engineering bidding vendors 81a in the engineering category. In this embodiment, the inquiry distributor module 31 selects four engineering quotation vendors 81a from the engineering related information 81: BB interior decoration, DD furniture, FF electrical appliances and GG moving. The engineering categories of these engineering quotation vendors 81a In line with the engineering project 211, and the inquiry and dispatch module 31 sends an inquiry sheet 32 to the engineering quotation vendors 81a to allocate the engineering project 211, the inquiry sheet 32 includes the engineering project 211 and the project data 212; The module 31 also notifies the engineering quotation vendors 81a to provide quotations for the assigned engineering items 211 and work item data 212. In addition, in the project-related information 81, there is a "data" button next to each manufacturer. When the contractor presses these buttons, you can view the corresponding manufacturer information (such as contact information, manufacturer business content, manufacturer cooperation record... etc. ).

接著,工程規劃管理系統1繼續進行步驟105:接收並彙整複數工程報價廠商81a依據詢價單32傳送之一工程報價單331,以使詢價單32整合模組於接收各工程報價廠81a商傳送之工程報價單331後產生工程預算單332;其中若複數工程報價廠商81a之其中之一未傳送工程報價單331,詢價單整合模組33發出一提示訊息至該工程報價廠商81a。Next, the engineering planning management system 1 proceeds to step 105: receiving and consolidating a plurality of engineering quotation vendors 81a to transmit one engineering quotation 331 according to the inquiry quotation 32, so that the inquiry quotation 32 integrates the module at the receiving factory quotation 81a After the transmitted engineering quotation 331, an engineering budget 332 is generated; if one of the plural engineering quotation vendors 81a does not transmit the engineering quotation 331, the inquiry order integration module 33 sends a prompt message to the engineering quotation vendor 81a.

如圖1和圖6所示,該些工程報價廠商81a會依據詢價單32內容預估該項工程所需的工程費用而產生工程報價單331,並工程報價單331回傳給工程規劃管理系統1,詢價單整合模組33會接收並彙整該些工程報價單331。在本實施例中,工程報價單331之內容例如分配到裝潢項目的BB室內裝修,針對該裝潢項目而提出5萬元報價。詢價單整合模組33也會檢核該些工程報價廠商81a是否皆回傳工程報價單331;若複數工程報價廠商81a之其中之一未傳送工程報價單331,詢價單整合模組33會發出一提示訊息(例如email或手機簡訊)至工程報價廠商81a以提醒對方盡快報價;若各個工程報價廠商81a皆回傳工程報價單331,則詢價單整合模組33於接收所有工程報價廠商81a傳送之工程報價單331後,才產生工程預算單332。As shown in FIGS. 1 and 6, the engineering quotation vendors 81a will estimate the engineering cost required for the project based on the content of the inquiry sheet 32 to generate the engineering quotation 331, and the engineering quotation 331 will be returned to the project planning management In system 1, the inquiry form integration module 33 receives and consolidates the engineering quotations 331. In this embodiment, the content of the engineering quotation 331, for example, is allocated to the BB interior decoration of the decoration project, and a 50,000 quotation is proposed for the decoration project. The RFQ integration module 33 will also check whether the engineering quotation vendors 81a all return the engineering quotation 331; if one of the multiple engineering quotation vendors 81a does not send the engineering quotation 331, the RFQ integration module 33 A reminder message (such as email or mobile phone message) will be sent to the engineering quotation vendor 81a to remind the other party to quote as soon as possible; if each engineering quotation vendor 81a returns the engineering quotation 331, the inquiry quotation integration module 33 receives all engineering quotations After the engineering quotation 331 transmitted by the manufacturer 81a, the engineering budget 332 is generated.

接著,工程規劃管理系統1會進行步驟106:接收工程預算單332並將工程預算單332傳送至一簽核單位500,其中工程預算單332包括至少一待發包工項。Next, the project planning management system 1 will proceed to step 106: receive the project budget slip 332 and transmit the project budget slip 332 to a signing unit 500, where the project budget slip 332 includes at least one contracted work item to be issued.

如圖1、圖6和圖7所示,預算請購模組40接收詢價單整合模組33產生的工程預算單332,並將工程預算單332傳送至一簽核單位500。工程預算單332列出各個工程報價廠商81a提供的各項工程費用、費用總和以及至少一待發包工項3321。簽核單位500之主管可以操作電腦連線到工程規劃管理系統1以檢視工程報價單331和工程預算單332,以得知工程項目的細節和價格是否符合需求,若符合則簽核該工程預算單332。As shown in FIGS. 1, 6 and 7, the budget requisition module 40 receives the engineering budget slip 332 generated by the inquiry order integration module 33 and transmits the engineering budget slip 332 to a signing unit 500. The project budget sheet 332 lists the project costs, the sum of the costs provided by each project quotation vendor 81a, and at least one project 3321 to be contracted. The supervisor of the approval unit 500 can operate the computer to connect to the project planning management system 1 to view the project quotation 331 and the project budget 332 to know whether the details and prices of the project meet the requirements, and if so, sign the project budget Single 332.

接著,工程規劃管理系統1會進行步驟107:接收簽核完成之工程預算單332,並根據該至少一待發包工項3321產生對應之至少一工程採購單52,並經一採購流程將該至少一待發包工項3321發包予一承辦工程廠商830。Next, the engineering planning management system 1 will proceed to step 107: receive the signed project budget sheet 332, and generate at least one project purchase order 52 according to the at least one contracted project 3321, and pass a A contracted project 3321 is issued to a contractor 830.

如圖1、圖6至圖8所示,工程採購發包模組50接收簽核單位500簽核完成之工程預算單332,且工程採購發包模組50根據該至少一待發包工項3321產生對應之工程採購單52,並經一採購流程將該至少一待發包工項3321發包予一承辦工程廠商830。As shown in FIGS. 1, 6 to 8, the project procurement and contract issuing module 50 receives the project budget sheet 332 completed by the signing unit 500, and the project procurement and contract issuing module 50 generates a correspondence according to the at least one project to be contracted 3321 The project purchase order 52, and through a procurement process, the at least one contracted item 3321 is contracted to a contractor 830.

接著,工程規劃管理系統1會執行步驟108:依據一工程規劃進度E管理承辦工程廠商830之施工進度。Next, the project planning management system 1 will perform step 108: manage the construction progress of the contractor 830 according to a project planning schedule E.

如圖1、圖9和圖10所示,工程進度管理模組70會依據一工程規劃進度E,管理承辦工程廠商830之施工進度,且工程進度管理模組70可接收承辦工程廠商830於一工程期間內回傳之一施工進度資訊,施工進度資訊包括一文字資訊及/或一圖像資訊。工程規劃進度E為一工程進度列表,工程進度列表包括複數預定工程,各複數預定工程包括一預定施工日以及一預定施工天數,工程進度管理模組70於預定施工日開始前兩天發出一施工通知給根據預定工程之各個承辦工程廠商830,以使各個承辦工程廠商830了解自己的承辦工程內容、預定施工日和預定施工天數。在其他實施例中,工程進度管理模組70進一步包含一提醒單元(圖未示),提醒單元可依據工程規劃進度E追蹤各項工程及其流程的進度,如工程或流程未能於一預定完成時間內完成,工程進度管理模組70會發出一通知以提醒相關人員,例如承辦人員、簽核單位500、承辦工程廠商830與需求單位900等,相關人員應於表定時間內完成工程或流程,如逾預定完成時間仍未接收到施工進度資訊,則工程進度管理模組70將發出一逾期通知給相關人員及其主管。在更多實施例中,在預定完成時間前更包含一預警時間,如逾預警時間仍未接收到施工進度資訊,則工程進度管理模組70將發出一進度提醒通知,如逾預定完成時間仍未接收到施工進度資訊,則工程進度管理模組70將發出一逾期通知給相關人員及其主管。As shown in FIG. 1, FIG. 9 and FIG. 10, the project schedule management module 70 will manage the construction schedule of the contracted project manufacturer 830 according to a project planning schedule E, and the project schedule management module 70 may receive the contracted project manufacturer 830 in one One piece of construction progress information is returned during the construction period, and the construction progress information includes a text information and/or an image information. The project planning progress E is a project progress list. The project progress list includes a plurality of scheduled projects. Each of the plurality of scheduled projects includes a scheduled construction day and a scheduled construction day. The project progress management module 70 issues a construction two days before the scheduled construction day begins Notify each contractor 830 of the contracted project according to the scheduled project, so that each contractor 830 understands the content of the contracted project, the scheduled construction day and the scheduled construction days. In other embodiments, the project progress management module 70 further includes a reminder unit (not shown). The reminder unit can track the progress of various projects and their processes according to the project planning progress E. If the project or the process fails to be scheduled Completed within the completion time, the project progress management module 70 will issue a notice to remind relevant personnel, such as the contractor, the signing unit 500, the contractor 830 and the demand unit 900, etc. The relevant personnel should complete the project within the specified time or In the process, if the construction progress information is not received after the scheduled completion time, the project progress management module 70 will issue an overdue notice to the relevant personnel and their supervisor. In more embodiments, an early warning time is included before the scheduled completion time. If the construction progress information is not received after the pre-warning time, the project progress management module 70 will issue a progress reminder notification. If the scheduled completion time is exceeded If the construction progress information is not received, the project progress management module 70 will issue an overdue notice to the relevant personnel and their supervisor.

各個承辦工程廠商830應依照排定的日期,前往該合適地點執行自己負責的作業;當承辦工程廠商830的作業內容完成,或是每一工作日結束時,承辦工程廠商830可使用手機拍攝當前作業成果,以顯示工程進度和品質,並將拍攝的照片及/或說明的文字回傳給工程規劃管理系統1。工程進度管理模組70會接收承辦工程廠商830回報的工程進度之照片及/或說明文字,以供建置職場的需求單位900查看文字說明或照片以確認工程進度和品質,前述承辦工程廠商830回報的工程進度可以是一施工日誌或一施工紀錄等。Each contractor 830 should go to the appropriate location to perform its own operations according to the scheduled date; when the contractor 830's work is completed, or at the end of each working day, the contractor 830 can use the mobile phone to shoot the current Operation results to show the progress and quality of the project, and return the photographs and/or explanatory texts taken to the project planning management system 1. The project progress management module 70 will receive the photos and/or explanatory texts of the project progress reported by the contractor 830 for the construction unit’s demand unit 900 to view the text descriptions or photos to confirm the project progress and quality. The aforementioned contractor 830 The reported progress of the project may be a construction log or a construction record.

在其他實施例中,工程進度管理模組70之提醒單元更包含一回報提醒功能,承辦工程廠商830應依照排定的日期提供工程進度回報給工程進度管理模組70,如承辦工程廠商830未依照排定的日期提供工程進度回報,工程進度管理模組70會發出一回報提醒訊息給承辦工程廠商830,用以提醒承辦工程廠商830回報施工日誌。In other embodiments, the reminder unit of the project progress management module 70 further includes a report reminder function. The contractor 830 should provide the project progress report to the project progress management module 70 according to the scheduled date. The project progress report is provided according to the scheduled date. The project progress management module 70 will send a report reminder message to the contractor 830 to remind the contractor 830 to report the construction log.

另外,承辦工程廠商830回報的文字說明或照片會被傳送到資料庫80,資料庫80會解讀承辦工程廠商830回報的文字說明或照片,並且統整至一工程進度追蹤列表F;如此一來,工程進度追蹤列表F顯示承辦工程廠商830的工程進度,以便建置職場的需求單位900察看工程進度。在本實施例中,工程進度追蹤列表F在表格上顯示「完成」、「已進行」等按鈕,當使用者按下該些按鈕時,便會跳出視窗以顯示對應的承包廠商回報的文字說明或照片,以便需求單位900即時控管建置進度和施工品質。工程進度追蹤列表F也提供評分意見的欄位,以供需求單位900對施工進度和品質評比和給予意見。In addition, the text description or photo reported by the contractor 830 will be sent to the database 80, and the database 80 will interpret the text description or photo reported by the contractor 830, and will be integrated into a project progress tracking list F; The project progress tracking list F shows the project progress of the contractor 830, so that the demand unit 900 for setting up a workplace can view the project progress. In this embodiment, the project progress tracking list F displays "complete" and "progressed" buttons on the table. When the user presses these buttons, a window will pop up to display the text description of the corresponding contractor's report Or photos, so that the demanding unit 900 can immediately control the construction progress and construction quality. The project progress tracking list F also provides a scoring field for the demand unit 900 to evaluate the construction progress and quality and give opinions.

最後,工程規劃管理系統1會執行步驟109:於目標場地之工程作業完成後,將工程項目清單21、工程報價單331、工程預算單332、工程採購單52及/或承辦工程廠商830等驗收資訊彙整產生一結案報告,並將結案報告儲存於資料庫。在其他實施例中,當工程項目清單中的每一個項目之狀態都呈現「完成」時,工程進度管理模組70判斷目標場地之工程作業為「完成」,承辦工程廠商830應提供工程項目清單21、工程報價單331、工程預算單332、工程採購單52及/或承辦工程廠商830等驗收資訊,如承辦工程廠商830未提供前述驗收資訊,工程進度管理模組70會發出一驗收資訊提醒訊息給承辦工程廠商830,用以提醒承辦工程廠商830提供驗收資訊。Finally, the engineering planning management system 1 will perform step 109: After the completion of the engineering operations at the target site, the project list 21, engineering quotation 331, engineering budget 332, engineering purchase order 52 and/or contractor 830 will be accepted. The information aggregation generates a closing report and stores the closing report in the database. In other embodiments, when the status of each item in the project list is "completed", the project progress management module 70 determines that the project operation at the target site is "completed", and the contractor 830 should provide the project list 21. Project quotation 331, project budget 332, project purchase order 52 and/or contractor 830 and other acceptance information. If the contractor 830 does not provide the aforementioned acceptance information, the project progress management module 70 will issue a reminder of acceptance information The message is given to the contractor 830 to remind the contractor 830 to provide acceptance information.

如圖1和圖11所示,於目標場地之職場建置作業完成後,工程資料彙整模組90會將工程項目清單21、工程報價單331、工程預算單332、工程採購單52及/或承辦工程廠商830等資訊彙整產生一結案報告,並將結案報告儲存於資料庫80,以供後續相關單位備查或作為往後建置職場的參考資料。資料庫80會再產生一案件受理進度單G,以顯示各個建置職場的案件的項目、申請日、申請人、進度(其包括現有案件的進度和結案報告);案件受理進度單G亦提供一「詳情」按鈕,使用者可以按下該按鈕,如此一來便會跳出一視窗以顯示在職場建置作業中,接收到的所有資料和所有產生的表單。As shown in FIGS. 1 and 11, after the workplace construction operation at the target site is completed, the project data integration module 90 will include the project list 21, project quotation 331, project budget 332, project purchase order 52 and/or The contractor 830 and other information will be aggregated to generate a closing report, and the closing report will be stored in the database 80 for future reference by relevant units for reference or as a reference for the future establishment of the workplace. The database 80 will generate another case acceptance progress sheet G to display the project items, application date, applicants, and progress of each case in the workplace (including the progress of the existing case and the closing report); the case acceptance progress sheet G is also provided A "details" button, the user can press the button, so that a window will pop up to display all the data received and all generated forms in the establishment of the workplace.

藉由本新型的工程規劃管理系統1的架構設計,可以方便使用者控管和紀錄職場建置流程,且在職場建置流程中的所有資料,包括但不限於本工程規劃管理系統1所有有關的文件、圖檔和產生的表單等皆會被統一儲存在工程規劃管理系統1,以達成將所有表單統一管理、資源共享,形成電子化的資料連結的功效,方便使用者後續查詢和追蹤管理。在其他實施例中,本新型之工程規劃管理系統1還可以包含一查詢模組(圖未示),查詢模組係與工程規劃管理系統1中的各模組連接,使用者可以提供一資料查詢請求,查詢模組可依據資料查詢請求向工程規劃管理系統1中的各模組發出資料提供請求,並自各模組接收相應的資料。With the architectural design of the new-type engineering planning management system 1, it is convenient for users to control and record the workplace construction process, and all the data in the workplace construction process, including but not limited to all relevant information of the project planning management system 1 Documents, drawing files and generated forms are all stored in the engineering planning management system 1, in order to achieve the unified management of all forms, resource sharing, and the formation of electronic data links. It is convenient for users to follow up and track management. In other embodiments, the engineering planning management system 1 of the present invention may further include an inquiry module (not shown). The inquiry module is connected to each module in the engineering planning management system 1, and the user can provide a data Inquiry request, the inquiry module can issue a data provision request to each module in the engineering planning management system 1 according to the data inquiry request, and receive corresponding data from each module.

在其他實施例中,本新型之工程規劃管理系統1還可以包含一存有複數報表模板之報表產製模組(圖未示),報表產製模組係與工程規劃管理系統1中的各模組連接,使用者可以提供一報表產製請求,報表產製模組可依據報表產製請求與相應的報表模板向工程規劃管理系統1中的複數模組發出資料提供請求,並自前述模組接收相應的資料後將資料與報表模板結合而產製出一完整之報表。In other embodiments, the new-type project planning management system 1 may further include a report production module (not shown) in which a plurality of report templates are stored. The report production module is different from the project planning management system 1 The module is connected, and the user can provide a report production request. The report production module can send a data provision request to a plurality of modules in the engineering planning management system 1 according to the report production request and the corresponding report template, and After receiving the corresponding data, the group will combine the data with the report template to produce a complete report.

在其他實施例中,本新型之工程規劃管理系統1還可以包含一保固管理模組(圖未示),當工程規劃管理系統1包含保固管理模組時,工程報價廠商81a所傳送之工程報價單331應包含一保固金額與保固期限,對應之工程預算單332與工程採購單52亦包含保固金額與保固期限,承辦工程廠商830應依據工程採購單52所載之保固金額存入一預定帳戶,保固管理模組依據工程採購單52所載之保固期限進行時限管理,當保固期限到期時,保固管理模組會發出一保固金額取回訊息給承辦工程廠商830。In other embodiments, the engineering planning management system 1 of the present invention may further include a warranty management module (not shown). When the engineering planning management system 1 includes the warranty management module, the engineering quotation transmitted by the engineering quotation vendor 81a The bill 331 should include a warranty amount and warranty period. The corresponding project budget sheet 332 and project purchase order 52 also include the warranty amount and warranty period. The contractor 830 should deposit a predetermined account based on the warranty amount stated in the project purchase order 52. The warranty management module performs time limit management according to the warranty period contained in the project purchase order 52. When the warranty period expires, the warranty management module will send a warranty amount retrieval message to the contractor 830.

需注意的是,前述各個模組除可配置為硬體裝置、軟體程式、韌體或其組合外,亦可藉電路迴路或其他適當型式配置;並且,各個模組除可以單獨之型式配置外,亦可以結合之型式配置。一個較佳實施例是各模組皆為軟體程式儲存於記憶體(圖未示)上,藉由伺服器中的一處理器(圖未示)執行各模組以達成本新型之功能。此外,本實施方式僅例示本新型之較佳實施例,為避免贅述,並未詳加記載所有可能的變化組合。然而,本領域之通常知識者應可理解,上述各模組或元件未必皆為必要。且為實施本發明,亦可能包含其他較細節之習知模組或元件。各模組或元件皆可能視需求加以省略或修改,且任兩模組間未必不存在其他模組或元件。It should be noted that the aforementioned modules can be configured as hardware devices, software programs, firmware, or a combination thereof, and can also be configured by circuit loops or other suitable types; and, each module can be configured in a separate type. , Can also be combined with the type configuration. A preferred embodiment is that each module is a software program stored in a memory (not shown), and each module is executed by a processor (not shown) in the server to achieve new functions. In addition, this embodiment only exemplifies the preferred embodiment of the present invention. In order to avoid redundancy, all possible combinations of changes are not described in detail. However, those of ordinary skill in the art should understand that the above modules or components are not necessarily necessary. In order to implement the present invention, other conventional modules or components in more detail may also be included. Each module or component may be omitted or modified as needed, and there may not be other modules or components between any two modules.

需注意的是,上述僅為實施例,而非限制於實施例。譬如 此不脫離本新型基本架構者,皆應為本專利所主張之權利範圍,而應以專利申請範圍為準。It should be noted that the above is only an embodiment, and not limited to the embodiment. For example, those who do not deviate from the basic structure of this new model shall all claim the scope of rights claimed by this patent, and shall be subject to the scope of patent application.

1:工程規劃管理系統1: Engineering planning management system

10:需求接收模組10: demand receiving module

11:申請單11: Application form

13:需求資訊通知模組13: Demand information notification module

20:工程規劃模組20: Engineering planning module

21:工程項目清單21: Engineering project list

211:工程項目211: Engineering project

212:工項資料212: Work data

23:預定使用坪數產生模組23: Plan to use Ping number generation module

30:詢價管理模組30: Inquiry management module

31:詢價派商模組31: Inquiry and Distributor Module

32:詢價單32: Inquiry

33:詢價單整合模組33: Inquiry form integration module

331:工程報價單331: Engineering quotation

332:工程預算單332: Engineering budget slip

3321:待發包工項3321: Outgoing contract work

40:預算請購模組40: budget purchase module

50:工程採購發包模組50: Engineering procurement contracting module

52:工程採購單52: Engineering purchase order

70:工程進度管理模組70: Engineering progress management module

80:資料庫80: database

81:工程相關資訊81: Engineering related information

90:工程資料彙整模組90: Engineering data integration module

111:第一需求資訊111: First demand information

500:簽核單位500: signing unit

600:製圖單位600: drawing unit

700:第一承辦單位700: the first undertaking unit

81a:工程報價廠商81a: Engineering quote vendor

830:承辦工程廠商830: Contractor

900:需求單位900: demand unit

E:工程規劃進度E: Project planning progress

F:工程進度追蹤列表F: Project progress tracking list

G:案件受理進度單G: Case acceptance progress slip

圖1係本新型之一實施例之工程規劃管理系統之系統架構圖。 圖2係本新型之一實施例之工程規劃管理系統之流程圖。 圖3係本新型之申請單之一實施例之示意圖。 圖4係本新型之工程項目清單之一實施例之示意圖。 圖5係本新型之工程廠商清單之一實施例之示意圖。 圖5a係本新型之詢價單之一實施例之示意圖。 圖6係本新型之工程報價單之一實施例之示意圖。 圖7係本新型之工程預算單之一實施例之示意圖。 圖8係本新型之請購單之一實施例之示意圖。 圖9係本新型之工程進度表單之一實施例之示意圖。 圖10係本新型之進度列表之一實施例之示意圖。 圖11係本新型之案件受理單之一實施例之示意圖。 FIG. 1 is a system architecture diagram of an engineering planning management system according to an embodiment of the present invention. FIG. 2 is a flowchart of an engineering planning management system according to an embodiment of the new model. FIG. 3 is a schematic diagram of an embodiment of the application form of the present invention. FIG. 4 is a schematic diagram of an embodiment of a project list of the new type. FIG. 5 is a schematic diagram of an embodiment of a list of engineering manufacturers of the new type. FIG. 5a is a schematic diagram of an embodiment of an inquiry form of the present invention. Fig. 6 is a schematic diagram of an embodiment of the new-type engineering quotation. FIG. 7 is a schematic diagram of an embodiment of the engineering budget slip of the new type. FIG. 8 is a schematic diagram of an embodiment of the new requisition. FIG. 9 is a schematic diagram of an embodiment of a project schedule of the new type. FIG. 10 is a schematic diagram of an embodiment of the progress list of the present invention. FIG. 11 is a schematic diagram of an embodiment of a case acceptance form of the new type.

10:需求接收模組 10: demand receiving module

1:工程規劃管理系統 1: Engineering planning management system

13:需求資訊通知模組 13: Demand information notification module

20:工程規劃模組 20: Engineering planning module

23:預定使用坪數產生模組 23: Plan to use Ping number generation module

30:詢價管理模組 30: Inquiry management module

31:詢價派商模組 31: Inquiry and Distributor Module

33:詢價單整合模組 33: Inquiry form integration module

40:預算請購模組 40: budget purchase module

50:工程採購發包模組 50: Engineering procurement contracting module

70:工程進度管理模組 70: Engineering progress management module

80:資料庫 80: database

81:工程相關資訊 81: Engineering related information

90:工程資料彙整模組 90: Engineering data integration module

500:簽核單位 500: signing unit

600:製圖單位 600: drawing unit

700:第一承辦單位 700: the first undertaking unit

81a:工程報價廠商 81a: Engineering quote vendor

830:承辦工程廠商 830: Contractor

900:需求單位 900: demand unit

Claims (14)

一種工程規劃管理系統,用於規劃與管理之一工程作業,該工程規劃管理系統包括:一資料庫,用以儲存複數工程相關資訊及職場平面圖檔;一需求接收模組,用以接收一需求單位傳送之一第一需求資訊;一工程規劃模組,訊號連接該需求接收模組,該工程規劃模組依據該第一需求資訊產生該工程作業所需之一工程項目清單,其中該工程項目清單包括至少一工程項目以及該至少一工程項目對應之一工項資料;一詢價管理模組,訊號連接該資料庫及該工程規劃模組,該詢價管理模組包括:一詢價派商模組,其係依據一派商規則於該複數工程廠商資訊中找尋與該至少一工程項目之一工程類別相符之複數工程報價廠商,並將一詢價單傳送至該複數工程報價廠商,其中該詢價單包括該至少一工程項目及該工項資料;以及一詢價單整合模組,用以接收並彙整該複數工程報價廠商依據該詢價單傳送之一工程報價單以產生一工程預算單。 An engineering planning management system for planning and managing an engineering operation. The engineering planning management system includes: a database for storing a plurality of engineering related information and workplace floor plan files; and a demand receiving module for receiving a demand The unit transmits a first demand information; an engineering planning module, the signal is connected to the demand receiving module, the engineering planning module generates a project item list required for the engineering operation according to the first demand information, wherein the engineering item The list includes at least one engineering project and one project data corresponding to the at least one engineering project; an inquiry management module, the signal connects the database and the engineering planning module, and the inquiry management module includes: an inquiry Quotient module, which is to find a plurality of engineering quotation vendors that match one of the engineering categories of the at least one engineering item in the plurality of engineering vendor information according to a distributor rule, and send an inquiry sheet to the plurality of engineering quotation vendors, where The inquiry form includes the at least one project and the project data; and an inquiry order integration module for receiving and compiling a plurality of engineering quotation vendors according to the inquiry form to send an engineering quotation to generate a project Budget slip. 如申請專利範圍第1項所述之工程規劃管理系統,其中該派商規則為於該工程類別中,輪流分派複數工程報價廠商。 The project planning management system as described in item 1 of the scope of the patent application, wherein the dispatching rule is that in the project category, multiple project quotation vendors are assigned in turn. 如申請專利範圍第2項所述之工程規劃管理系統,其中若該複數工程報價廠商之其中之一未傳送該工程報價單,該詢價單整合模組發出一提示訊息至該工程報價廠商。 The project planning management system as described in item 2 of the scope of patent application, wherein if one of the plural engineering quotation vendors does not send the engineering quotation, the inquiry order integration module sends a prompt message to the engineering quotation vendor. 如申請專利範圍第2項所述之工程規劃管理系統,其中該詢價單整合模組於接收各該工程報價廠商傳送之該工程報價單後產生該工程預算單。 The project planning management system as described in item 2 of the scope of patent application, wherein the inquiry form integration module generates the project budget form after receiving the project quotation sent by each project quotation manufacturer. 如申請專利範圍第1項所述之工程規劃管理系統,更包括一預算請購模組,其係訊號連接該詢價單整合模組,該預算請購模組接收該工程預算單並將該工程預算單傳送至一簽核單位,其中該工程預算單包括至少一待發包工項。 The project planning management system as described in item 1 of the patent application scope further includes a budget requisition module, which is a signal connected to the inquiry form integration module, and the budget requisition module receives the project budget form and sends the The project budget slip is transmitted to a signing unit, where the project budget slip includes at least one project to be outsourced. 如申請專利範圍第5項所述之工程規劃管理系統,更包括一工程採購發包模組,得與該預算請購模組訊號連接,以便接收簽核完成之該工程預算單,該工程採購發包模組根據該至少一待發包工項產生對應之至少一工程採購單,並經一採購流程將該至少一待發包工項發包予一承辦工程廠商。 The project planning and management system as described in item 5 of the patent application scope also includes a project procurement and outsourcing module, which can be connected to the budget requisition module signal in order to receive the signed project budget bill and the project procurement and outsourcing The module generates corresponding at least one engineering purchase order according to the at least one contracted work item, and subcontracts the at least one contracted work item to a contractor through a procurement process. 如申請專利範圍6項所述之工程規劃管理系統,更包括一工程進度管理模組,用以依據一工程規劃進度管理該承辦工程廠商之施工進度。 The project planning management system as described in item 6 of the patent application scope further includes a project schedule management module for managing the construction progress of the contracted project manufacturer based on a project planning schedule. 如申請專利範圍7項所述之工程規劃管理系統,其中該工程進度管理模組接收該承辦工程廠商於一工程期間內回傳之一施工進度資訊,該施工進度資訊包括一文字資訊及/或一圖像資訊。 The project planning management system as described in item 7 of the patent application scope, wherein the project progress management module receives a piece of construction progress information returned by the contractor during a project period, and the construction progress information includes a text message and/or a Image information. 如申請專利範圍第8項所述之工程規劃管理系統,更包括一工程資料彙整模組,該工程資料彙整模組於該目標場地之該工程作業完成後,將該工程項目清單、該工程報價單、該工程 預算單、該至少一工程採購單及/或該承辦工程廠商等資訊彙整產生一結案報告,並將該結案報告儲存於該資料庫。 The project planning management system as described in item 8 of the scope of patent application further includes an engineering data aggregation module. After the engineering operation of the target site is completed, the engineering data list and the engineering quotation Single, the project The information such as the budget bill, the at least one project purchase order, and/or the contractor’s contract manufacturer is aggregated to generate a closing report, and the closing report is stored in the database. 如申請專利範圍第7項所述之工程規劃管理系統,其中該工程規劃進度為一工程進度列表,該工程進度列表包括複數預定工程,各該複數預定工程包括一預定施工日以及一預定施工天數,該工程進度管理模組於該預定施工日開始前兩天發出一施工通知給根據該預定工程之該承辦工程廠商。 The project planning management system as described in item 7 of the patent application scope, wherein the project planning progress is a project progress list, the project progress list includes a plurality of scheduled projects, each of the plurality of scheduled projects includes a scheduled construction day and a scheduled construction day , The project schedule management module sends a construction notice to the contractor under the scheduled project two days before the scheduled construction date. 如申請專利範圍第1項所述之工程規劃管理系統,其中該工程作業為一舊有職場修繕作業或一新建職場作業,其中當該工程作業為新建職場作業時,該第一需求資訊包括一人數資訊與一職級資訊,且該工程規劃模組接收由一製圖單位傳送之一目標場地之一室內設計圖,並依據該室內設計圖與該第一需求資訊產生完成該新建職場作業所需之該工程項目清單。 The project planning management system as described in item 1 of the patent application scope, wherein the engineering operation is an old workplace repair operation or a new workplace operation, wherein when the engineering operation is a new workplace operation, the first demand information includes a The number of people and the first-level information, and the engineering planning module receives an interior design drawing of a target venue transmitted by a drawing unit, and generates the necessary information to complete the new workplace according to the interior design drawing and the first demand information The project list. 如申請專利範圍第11項所述之工程規劃管理系統,其中該第一需求資訊更包括一隔間資訊,該工程規劃模組將該第一需求資訊傳送至該製圖單位以供該製圖單位依據該第一需求資訊繪製該目標場地之該室內設計圖。 The engineering planning management system as described in item 11 of the patent application scope, wherein the first demand information further includes a compartment information, and the engineering planning module transmits the first demand information to the drawing unit for the drawing unit to base on The first demand information draws the interior design drawing of the target venue. 如申請專利範圍第11項所述之工程規劃管理系統,其中該需求接收模組更提供一申請單以供該需求單位輸入一人數資訊,該工程規劃模組更包括一預定使用坪數產生模組,其係依據該人數資訊產生一預定使用坪數。 The project planning management system as described in item 11 of the patent application scope, in which the demand receiving module further provides an application form for the demand unit to input a number of people, and the project planning module further includes a predetermined use ping number generation module Group, which generates a predetermined number of pings based on the number of people. 如申請專利範圍第13項所述之工程規劃管理系統,其中該需求接收模組更包括一需求資訊通知模組,其係用以通知一第一承辦單位找尋與該預定使用坪數匹配之該目標場地。 The project planning management system as described in item 13 of the patent application scope, wherein the demand receiving module further includes a demand information notification module, which is used to notify a first contractor to find the matching number of the planned usage Target venue.
TW108211898U 2019-09-06 2019-09-06 Engineering planning management system TWM595267U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW108211898U TWM595267U (en) 2019-09-06 2019-09-06 Engineering planning management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW108211898U TWM595267U (en) 2019-09-06 2019-09-06 Engineering planning management system

Publications (1)

Publication Number Publication Date
TWM595267U true TWM595267U (en) 2020-05-11

Family

ID=71897559

Family Applications (1)

Application Number Title Priority Date Filing Date
TW108211898U TWM595267U (en) 2019-09-06 2019-09-06 Engineering planning management system

Country Status (1)

Country Link
TW (1) TWM595267U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI754471B (en) * 2020-11-27 2022-02-01 巨力搬家貨運股份有限公司 Service estimation, contract signing and dispatch system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI754471B (en) * 2020-11-27 2022-02-01 巨力搬家貨運股份有限公司 Service estimation, contract signing and dispatch system

Similar Documents

Publication Publication Date Title
US7606628B2 (en) Design and manufacturing management system, method, and program
US6819967B2 (en) Relational database for producing bill-of-materials from planning information
US20040015367A1 (en) Business asset management system using virtual areas
US20070061774A1 (en) Apparatus, system, and method for managing project customization, compliance documentation, and communication
US20100017253A1 (en) Profiling service provider companies and technicians
US8417552B2 (en) Electronic select provider network
KR20130047776A (en) Stand alone domain each construction web site with auto maker and using it for the group system
US8001160B2 (en) Systems for managing construction projects
US6850904B2 (en) Relational database for producing bill-of-materials from planning information
KR101995686B1 (en) A Pipe Spool Production Management System and A Pipe Spool Production Management Method
TWM595267U (en) Engineering planning management system
CA2869731A1 (en) Wireless coverage infrastructure design
KR101535580B1 (en) Process management system and method thereof for digital media manufacturing
TWM611217U (en) Service estimation, contract signing and dispatch system
US20100017337A1 (en) Establishing a buyer/service provider relationship electronically
Kasim et al. Enhancing material tracking practices of material management in construction project
JP2020086478A (en) Distributed data management method and distributed data management apparatus
JP2008123469A (en) Management system of object management information, person management information and real estate information
WO2015141872A1 (en) Process management system for digital media production and method therefor
KR20080086560A (en) System and method for on-line design cooperation
KR102573901B1 (en) Cloud based many-to-many cooperative platform for sharing information
KR20140122469A (en) System and method for integrated business supporting service
JP6526896B1 (en) Shareholder benefit system and shareholder benefit method
WO2017191672A1 (en) Production planning assist device, production planning assist system, and production planning assist method
Saidi Possible applications of handheld computers to quantity surveying