TW422904B - Construction method and form derricking device used in concrete steel beam and floor slab construction for steel building - Google Patents
Construction method and form derricking device used in concrete steel beam and floor slab construction for steel building Download PDFInfo
- Publication number
- TW422904B TW422904B TW89103303A TW89103303A TW422904B TW 422904 B TW422904 B TW 422904B TW 89103303 A TW89103303 A TW 89103303A TW 89103303 A TW89103303 A TW 89103303A TW 422904 B TW422904 B TW 422904B
- Authority
- TW
- Taiwan
- Prior art keywords
- steel
- formwork
- floor
- beams
- steel beam
- Prior art date
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
422904 五、發明說明(1) 本發明係有關一種「鋼骨建築物混 施工方法及其爷模裝置」,尤指一種針對樓== I雀聚疋成樓板之施工方法及其吊模裝置。 目前鋼骨建築物區域係立置多數支間隔分佈之鋼 :參閲第1、2圖〕,依據預定之樓層位置 將备鐧枉(1 〇 )彼此間分別組接縱向鋼樑(丄i '橫 向鋼樑(1 2 )’構成全面方格狀排列。然後由下往上逐 層進行置模灌漿,以依序完成各層混凝土鋼樑及樓板。 傳統鋼骨建築物進行樓板置模灌漿作業時,必須先在 已完工之樓板上立置無數支密集分佈之木柱,以供釘設上 一樓層之樓板面模板’及上一樓層鋼樑下方之底模板,進 一步將樓板面模板與底模板之間各釘設外側模板,供包圍 各鋼樑。然後在各鋼樑外周紮箍筋,以及在樓板面模板上 紮鋼筋,供進行澆鑄混凝土,最後再拆除全部之樓板面模 板、底模板及側模板’完成此樓層之混凝土鋼樑及樓板。 然後即重複上述之施工步驟,以進行更上—樓層之置模灌 漿。 由於傳統方式係由下往上立置固定無數支木柱,再進 行高處樓板面模板、底模板及側模板作業,以致施工緩慢 、因難,並且需要極多數模板工人。而當此樓層模板完成 後,即造成多數模板工人無事閒置,無法彈性調配人力, 並且施工期較長’增加成本。 本發明人有鑒於傳統混凝土鋼樑及樓板施工之各項實 際缺弊,因此乃針對其癥結所在,繼續加以謀求改善,補422904 V. Description of the invention (1) The present invention relates to a "concrete construction method for steel-frame buildings and its master mold device", in particular to a construction method and a hanging formwork device for a floor panel. At present, the steel-framed building area has a large number of steels distributed at intervals: refer to Figures 1 and 2]. According to the predetermined floor position, the preparations (10) are respectively assembled with longitudinal steel beams (丄 i ' The transverse steel beams (1 2) 'form a comprehensive grid-like arrangement. Then, the moulding and grouting is carried out layer by layer from bottom to top to complete the concrete steel beams and floor slabs in order. , It is necessary to first set up numerous densely distributed wooden columns on the completed floor to nail the floor formwork of the previous floor and the bottom formwork under the steel beam of the previous floor, and further combine the floor formwork and the bottom formwork. The outer formwork is set between each nail to surround the steel beams. Then stirrups are attached to the periphery of each steel beam, and steel bars are added to the floor formwork for casting concrete. Finally, all the floor formwork, bottom formwork and "Side formwork" completes the concrete steel beams and floor slabs of this floor. Then repeats the above construction steps to carry out the upper-floor mold grouting. Since the traditional method is to set up countless wooden columns from bottom to top Then, the floor formwork, bottom formwork and side formwork of the high place are performed, resulting in slow and difficult construction and the need for a large number of formworkers. When the floor formwork is completed, most formworkers are idle and unable to flexibly allocate manpower. And the construction period is longer, which increases costs. In view of the practical shortcomings of traditional concrete steel beams and floor slab construction, the inventor has continued to seek improvements and supplements according to their crux.
1761-1048.ptd 第6頁 4 2 29 041761-1048.ptd Page 6 4 2 29 04
五、發明說明(2) 其所缺,以期尋 ,終於完成本發 方法及其吊模裝 本發明之目 及樓板之施工方 吊桿之底模板, 各縱向鋼襟兩外 兩端跨置於支件 後採用伸縮桿往 供釘固各鋼樑外 最後再拆除全部 模板與吊桿係事 模板施工作業更 夠減少模板工人 性調配人力,避 合實際施工需要 有關本發明 功效,茲舉出可 更趨於明瞭。 首先,本發 方法及其吊模裝 、縱向鋼樑(1 層區域各水平方 )下方設置第3 鋼骨建 ,主要 及滑動 支件, 區域上 此時可 筋及後 土鋼樑 先立置 人力, 工可彈 ,可供 經過無數次研析、設計 凝土鋼樑及樓板之施工 築物混 預備多 調整位 供多數 設置頂 拆除水 續澆鑄 及樓板 木柱> 縮短施 性安排 建築業 求一項解 明「鋼骨 置」。 的即在提 法及其吊 以吊置於 側方各固 上,以在 上頂往伸 側模板* 模板,以 先組立, 為迅速確 ,並且相 免人員間 〇 為達成上 行實施例 明「鋼骨 置」係針 1 )及橫 格狀排列 、4 、5 決之道, 建築物混 供一種「 模裝置」 鋼樑下方 定一水平 伸縮桁架 縮桁架, 進而紮箍 完成混凝 並且不必 實,節省 關模板施 置及浪費 述目的, 並配合圖 建築物混 對第1 、 向鋼樑( 之縱橫向 ' 6圖所 凝土鋼樑 數立設有 置,並在 伸縮桁架 模板,然 平支件, 混凝土, 。由於底 因此整項 工期,能 ,能夠彈 利用,符 所採用之技術手段及其 面說明’以使整體設計 凝土鋼樑及樓板之施工 2圖所示鋼柱(1 〇) 12)而設計,以在樓 鋼樑(1 1 ) 、( 1 2 示之底模板(2 0 )。V. Description of the invention (2) What it lacks, in order to find out, and finally complete the method of the present invention and its hanging formwork to install the purpose of the present invention and the floor template of the suspender of the construction side of the floor. After the support members are used, the telescopic rod is used to nail the steel beams and then all the formwork and hangers are removed. The construction work is more sufficient to reduce the formwork worker ’s manpower deployment and avoid the actual construction needs related to the effects of the present invention. Become more clear. First, this method and its lifting formwork are installed, and a third steel frame is installed below the longitudinal steel beams (each horizontal in the first floor area), mainly for sliding support. At this time, the steel bars and the earth steel beams can be placed on the area first. Manpower, work flexibility, can be used for numerous research and analysis, design of concrete steel beams and floor slabs, construction preparation, multi-adjustment for most installations, top dismantling, continuous casting, and floor slabs > shortening construction arrangements Find an explanation of "steel frame placement". That is, in the mentioning and hanging on the side of each fixed, to the top to extend the side template * template, first to assemble, for rapid confirmation, and to avoid interpersonal 〇 to achieve the upward embodiment, " The “steel frame installation” system pin 1) and the horizontal grid arrangement, 4 and 5 make the building mixed with a “mold device”. A horizontal telescopic truss and shrink truss is fixed under the steel beam, and then the hoops are completed to coagulate and do not need to be solid. In order to save the construction and wasting of the purpose of the formwork, and to mix the building with the figure, the steel beams in the first and the vertical direction of the steel beam (the vertical and horizontal direction of the '6) are placed in several places, and the telescopic truss formwork, then flat Supports, concrete, etc. Due to the entire construction period, it can be used, can be used, in accordance with the technical means used and its surface description 'to enable the overall design of concrete steel beams and floor slab construction 2 steel columns (1 〇) 12) and designed to the floor steel beams (1 1), (12 shown in the bottom formwork (2 0).
1761 -1048.ptd 第7頁 422904 此一紋且3等}3止 置側3塊}、 一 板圖勾 向} ,設螺並3該3 C有 套兩C楔ο} 製翼8供橫ο >立之’{。3槽設 以} 口與21 彎下第, 或4 ο各} }帽}< 口面 ,4夾}<1 端之而} C ( 2312螵3帽開頂。}1對4板C 頂}。1 }件 C側33設2螺之端出6C再3模樑 >1定1 1支 板兩鎖CI}外脫3板,C底鋼 οι固3。1上 模段頭桿及桿接7}外C翼置具各向 OC焊c}c 一 底後接接}木鎖37往口下位夾使橫 3樑點段3樑焊 形中端一 3橫端C3}夾之}且,縱 C鋼步勾1鋼點 方前底合2其頂座^0一}0並}於 桿向一一 C向置 長或}鎖C及}吊座3設22 ,ο列 吊縱進製板縱橫 數CO供桿端吊C預1C位4排 例在可彎翼各各 多落3,木03 1 ’桿側C板定3定 施掛更則上在端 備角橫2C}中吊一、模}<固 實靠後端之係頂 預四桿ο出C桿4例免}}底5材置 此以寸頂 > 法後 須之吊2穿板吊3施避41整3線吊。,,尺}1方前 必}將C段模之C實以31調C 一 }方圖}整11工之 中ο ,板下底}具佳,CC動塊結ο下70調OC施3 法2}模}住ο夾較}具樑移楔連3正第1 ,3樑例} ⑶方CO底2定2於在9夾鋼可一可C之閱3上C鋼施2 ^(工板3出3固C掛。3述向步入}桿}參桿向實1 奶施模C穿C以板吊上C上橫一打5吊2請段4吊縱本C Μ項底桿身桿,楔供}件 縱進33由1 平1示於 樑 JL'整等吊桿接}底,8擋 於,6C藉C 水C所掛 鋼1761 -1048.ptd Page 7 422904 This pattern and 3rd grade} 3 stop side 3 pieces}, a board drawing hook}, set screw and 3 3 C has a set of two C wedges} wing 8 for horizontal ο > Lizhi '{. 3 slots are set with} mouth and 21 bend down, or 4 ο caps} < mouth surface, 4 clips} < 1 of the end} C (2312 螵 3 cap open top.) 1 pair of 4 plates C Top} .1} C side 33 sets 2 screw ends out of 6C and then 3 mould beams> 1 fixed 1 1 plate and two locks CI} 3 strips outside, C bottom steel ο fixed 3.1 upper die head rod And rod connection 7} outer C-wing set with OC welding in all directions c} c one bottom connection} wood lock 37 lower mouth clamp to make 3 beam point sections 3 beam welded middle end 3 cross end C3} } Moreover, the vertical C steel step hook 1 steel point square front bottom combination 2 its top seat ^ 0 a} 0 and} length in the rod direction one C direction or} lock C and} hanger 3 set 22, ο line hanging Longitudinal board vertical and horizontal number CO for rod end crane C pre 1C position 4 rows Example: each of the bendable wings can drop 3 more, wooden 03 1 'rod side C plate fixed 3 fixed application hanging on the end side angle 2C } Central crane one, mould} < Solid back-end tie-ups for pre-four poles, 4 cases of C poles free}} Bottom 5 materials are set to the inch top > After the method must be lifted 2 Avoid 41 whole 3-line hanging. ,, ruler} 1 square must be} C of the C segment mold is adjusted to 31 C} square map} in the entire 11 work ο, the bottom of the board is good, CC moving block ο Down 70 adjust OC and apply 3 methods 2} mode} hold ο clamp} with beam shift wedge connection 3 positive first, 3 beam example} ⑶ 方 CO 底2 set 2 on the 9 clip steel can be read 3 on the C steel to apply 2 ^ (work plate 3 out of 3 solid C hanging. 3 mentioned to step into the} rod} reference rod to the real 1 milk mold C wear C Use a plate to hang C horizontally, hit 5 cranes, 2 paragraphs, and 4 to suspend the bottom shaft of the C M item. Wedges are provided. 33 pieces are inserted by 1 and 1 are shown at the bottom of the beam. 8 block at, 6C borrows water from C
五、發明說明(4) r ’以在上支件(40)兩端各裝設如第9、l〇、"、 上^圖所示往外伸之支臂(4 1 )。該上支件(4 0 )兩 !各設一道長圓孔(4〇〇)〔或多數間隔孔〕,供防脫 洛型插銷(4 0 2 )杨入支f ( 4丄)之固定孔(4 〇丄 並且支臂(41)另側設上下擋件(43) 、(44 j ,以靠於上支件(4〇)之上下端’供調整支臂(41 f伸出位置支臂(41)末端同樣設有長園孔(4 ),供插銷(4〇5)插入支件(42)前後上支片 5)之固定孔(4〇4),並且上支片(45)另側 設上擋件(47)以勾掛於支臂(41)上。 ,在較佳實施例中’支件(42)採用方形管狀,並且 平行位於各縱向鋼樑(1 1 )之兩外侧方,在支件(4 2 L底端係以短木柱(48)抵撐於底模板(2〇)之橫木 杯(2 3)上,並且更介裝兩組斜面對靠之楔塊(49) ,以作高低調整,另外支件(4 2 )之前後下支片(4 6 )採用鐵釘釘合短木柱(48)。 °青參閱第10、丄1 ' 12圖,各相鄰縱向鋼樑(1 1)之支件(42)上,係供多數平行伸縮桁架(5〇) 之兩端支板(51)跨置,此伸縮桁架(5〇)具有活動 套配之内外桁架,以伸縮調整整體長度。然後在該等伸縮 術架(50)所圍成之區域表面設置頂模板(22),再 藉由立置於下一層已完工樓板上之伸縮桿(5 2)往上頂 住各伸縮桁架(5〇),構成穩固支撐。因此能夠 縱向鋼樑(11)之上支件(40)、支臂(41)、支 176i-1048.ptd —* ----— ___ 第9頁 - έ 4 2 2 9 0 4 五、發明說明(5) 件(42)及短木柱(48) ’而如第1 3圖所示在各底 模板(20)與頂模板(2 2)之間立置釘固側模板(2 1 ),以包圍各縱向鋼樑(i i ) «在較佳實施例中,底 模板(20)暨橫木桿(2 3)可進一步加撐伸縮桿(5 由於橫向鋼樑(1 2)不必支持伸縮桁架(5 〇), 因此橫向鋼樑(12)可省略上支件(4〇)、支臂(4 1)、支件(42)及短木柱(48)等,而可直接在其 底模板(2 0 )與頂模板(2 2 )之間釘固侧模板(2 1 )。然後針對各縱橫向鋼樑外周紮箍筋(6 〇 ),及在全 部頂模板(22)上紮鋼筋(6 1)〔請參閱第14圖〕 。此時即可澆鑄樓板及鋼樑混凝土( 7 〇 )〔請參閱第工 5圖〕’最後再如第16圖所示拆除全部底模板(2〇) 、側模板(21)及頂模板(22),以完成整層混凝土 鋼樑及樓板。 綜合以上所述,本發明「鋼骨建築物混凝土鋼樑及樓 板之施工方法及其吊模裝置」能夠事先組立底模板與吊桿 ’及滑動調整位置,並且不必先立置木柱,因此整項模板 施工作業更為迅速確實’節省人力’縮短施工期,能夠減 少模板工人,並且相關模板施工可彈性安排,能夠彈性調 配人力’避免人員閒置及浪費,可供建築業利用,符合實 際施工需要’爰依法提出發明專利申請。V. Description of the invention (4) r ′ The arms (4 1) extending outward as shown in Figures 9, 10, " and ^ above are installed at both ends of the upper support (40). The upper support piece (40) has two long circular holes (400) (or a plurality of spaced holes) for fixing holes (4 0 2) of the anti-fall-out pin (4 0) Yang into the branch f (4 丄). 4 〇 丄 and the other side of the support arm (41) is provided with upper and lower stops (43), (44 j, to lean against the upper and lower ends of the upper support (4)) for the adjustment arm (41 f extended position support arm ( 41) The end is also provided with a long round hole (4), for the bolt (40) to be inserted into the fixing hole (4) of the upper and lower supporting pieces (42) of the support (42), and the other side of the upper supporting piece (45) An upper stopper (47) is set to hang on the support arm (41). In a preferred embodiment, the 'supporting member (42) adopts a square tube and is located parallel to the two outer sides of each longitudinal steel beam (1 1) At the bottom of the support (4 2 L, a short wooden post (48) is supported on the horizontal wooden cup (2 3) of the bottom formwork (20), and two sets of oblique facing wedges ( 49) for height adjustment, and the other supporting piece (4 2) uses iron nails to fasten the short supporting post (4 6) before and after the lower supporting piece (4 6). ° Refer to Figure 10, 丄 1'12, each phase The supports (42) adjacent to the longitudinal steel beam (1 1) are two for most parallel telescopic trusses (50). The support plate (51) is straddled, and the telescopic truss (50) has movable inner and outer trusses to adjust the overall length by telescoping. Then, a top template (22) is provided on the surface of the area surrounded by the telescopic trusses (50) ), And then with the telescopic rods (52) standing on the completed floor of the next floor up against the telescopic trusses (50), to form a stable support. Therefore, the vertical steel beam (11) can be supported above ( 40), support arm (41), support 176i-1048.ptd — * ----— ___ Page 9-着 4 2 2 9 0 4 5. Description of the invention (5) pieces (42) and short wooden columns ( 48) 'And as shown in Fig. 13 between the bottom formwork (20) and the top formwork (2 2), a nailed side formwork (2 1) is erected to surround each longitudinal steel beam (ii) «在 更In the preferred embodiment, the bottom formwork (20) and the crossbar (23) can further support the telescopic rod (5 because the transverse steel beam (12) does not need to support the telescopic truss (50), so the transverse steel beam (12) The upper support piece (40), the support arm (41), the support piece (42), and the short wooden post (48) can be omitted, and it can be directly on the bottom template (20) and the top template (22). Side nailing template (2 1). Then for each vertical Tie stirrups (60) on the outer periphery of the transverse steel beam and steel bars (6 1) on all the top formwork (22) [see Figure 14]. At this time, the floor slab and the steel beam concrete (70) can be cast. Please refer to Figure 5] 'Finally, remove all bottom formwork (20), side formwork (21) and top formwork (22) as shown in Figure 16 to complete the entire layer of concrete steel beams and floors. As mentioned in the present invention, the "construction method of concrete steel beams and floor slabs of steel-reinforced buildings and the hanging formwork device thereof" can preliminarily assemble the bottom formwork and the suspender 'and adjust the sliding position, and it is not necessary to first place a wooden column, so the entire formwork is constructed. The operation is more rapid and indeed saves manpower, shortens the construction period, can reduce the formwork worker, and the related formwork construction can be flexibly arranged, and manpower can be flexibly allocated to avoid personnel idle and waste, which can be used by the construction industry and meets the actual construction needs. File an invention patent application.
1761-1048.ptd 第ίο頁 4229041761-1048.ptd p. 422904
第1圖係鋼骨建築物鋼柱與鋼樑結構之正視圖。 第2圖係第1圖之俯視圖β 第3圖係本發明實施例鋼樑吊置底模板之正視囷。 第4圖係第3圖鋼樑夾具之立體圖。 第5圖係第3圖底模板之立體圖。 第6圖係第3圖之局部放大圖。 第7圖係第3圖另一種吊桿之示意圖。 第8圖係第3圖又一種吊桿之示意圖。 第9圖係接續第3圖組接兩側支件之示意圖。 第1 0圖係接續第9圖組立伸縮桁架、頂模板及伸 之示意圖。 和 第1 1圖係第1 〇圖之側視圖。 第1 2圖係第1 1圖之局部放大圖。 第1 3圖係第1 〇圖拆除兩側支件以組立側模板之示意 第1 4圖係接續第 第1 5圓係接續第 第1 6圖係接續第 圖中標示如下: 13圖進行紮箍筋 1 4圖進行澆鑄混 1 5圖拆除全部模 之示意圖。 凝土之示意圖。 板之示意圖。 (1 0 )鋼柱 (1 2 )橫向鋼樑 (1 4 )下翼板 (2 0 )底模板 (2 2 )頂模板 (1 1 )縱向鋼樑 (1 3 )上翼板 (2 1 )側模板 (2 3 )橫木桿Figure 1 is a front view of the steel column and steel beam structure of a steel skeleton building. Fig. 2 is a top view of Fig. 1; Fig. 3 is a front view of a steel beam hanging bottom formwork according to an embodiment of the present invention. Figure 4 is a perspective view of the steel beam fixture of Figure 3. Figure 5 is a perspective view of the bottom template of Figure 3. Figure 6 is a partially enlarged view of Figure 3. Figure 7 is a schematic view of another boom in Figure 3. Fig. 8 is a schematic diagram of another boom in Fig. 3. Figure 9 is a schematic diagram of the two side assemblies following Figure 3. Figure 10 is a schematic diagram of the assembled telescopic truss, roof template and extension following Figure 9. And FIG. 11 is a side view of FIG. 10. Figure 12 is a partial enlarged view of Figure 11; Fig. 13 is the diagram of Fig. 10 showing the removal of the support on both sides to form a side template. Fig. 14 is the continuation of the 15th circle. Continuation of the 16th is the continuation of the 16th. Fig. 16 is the continuation of the diagram. Figure 14 of the stirrups is cast and mixed. Figure 15 is a schematic diagram of removing all the molds. Schematic illustration of condensate. Schematic of the board. (1 0) Steel column (1 2) Transverse steel beam (1 4) Lower wing plate (2 0) Bottom formwork (2 2) Top formwork (1 1) Longitudinal steel beam (1 3) Upper wing plate (2 1) Side formwork (2 3)
422904 圖式簡單說明 3 0 ) 3 2) 3 4) 3 6) 3 8) 3 0 0 3 10 3 4 0 4 0) 4 2) 4 4) 4 6) 4 8) 4 0 0 4 0 2 4 0 4 5 0) 5 2 ) 6 0) 7 0) 吊桿 接桿 夾具 夾口 開口槽 )吊桿 )水平段 )線材 上支件 支件 下擋件 下支片 短木柱 )長圓孔 )插銷 )固定孔 伸縮桁架 伸縮桿 箍筋 混凝土 (31)接頭 (3 3 )螺帽 (3 5 )楔塊 (3 7 )吊座 (3 9 )止擋件 (3 0 1 )吊桿 (3 1 1 )勾段 (41)支臂 (4 3 )上擋件 (4 5 )上支片 (4 7 )上擋件 (4 9 )楔塊 (4 0 1 )固定孔 (4 0 3 )長圓孔 (4 0 5 )插銷 (51)支板 (6 1 )鋼筋422904 Brief description of the diagram 3 0) 3 2) 3 4) 3 6) 3 8) 3 0 0 3 10 3 4 0 4 0) 4 2) 4 4) 4 6) 4 8) 4 0 0 4 0 2 4 0 4 5 0) 5 2) 6 0) 7 0) Suspension post holder clamp opening slot) Suspender) Horizontal section) Wire upper support support lower support lower support piece short wooden post) long hole) latch ) Fixed hole telescopic truss telescopic rod stirrup concrete (31) joint (3 3) nut (3 5) wedge (3 7) hanger (3 9) stopper (3 0 1) boom (3 1 1 ) Hook section (41) Arm (4 3) Upper stopper (4 5) Upper support piece (4 7) Upper stopper (4 9) Wedge (4 0 1) Fixing hole (4 0 3) Long round hole ( 4 0 5) Bolt (51) Support plate (6 1) Rebar
1761-1048.ptd 第12頁1761-1048.ptd Page 12
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW89103303A TW422904B (en) | 2000-02-25 | 2000-02-25 | Construction method and form derricking device used in concrete steel beam and floor slab construction for steel building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW89103303A TW422904B (en) | 2000-02-25 | 2000-02-25 | Construction method and form derricking device used in concrete steel beam and floor slab construction for steel building |
Publications (1)
Publication Number | Publication Date |
---|---|
TW422904B true TW422904B (en) | 2001-02-21 |
Family
ID=21658893
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
TW89103303A TW422904B (en) | 2000-02-25 | 2000-02-25 | Construction method and form derricking device used in concrete steel beam and floor slab construction for steel building |
Country Status (1)
Country | Link |
---|---|
TW (1) | TW422904B (en) |
-
2000
- 2000-02-25 TW TW89103303A patent/TW422904B/en not_active IP Right Cessation
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108643544B (en) | High-altitude overhanging construction platform support system and construction method | |
CN108265885B (en) | Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column | |
CN107227814B (en) | Sectional construction method for large cantilever concrete structure | |
CN212507296U (en) | High formwork system | |
CN217028088U (en) | Cantilever tripod template support | |
JPS6348753Y2 (en) | ||
CN215253499U (en) | Scaffold device | |
CN211923466U (en) | Elevator shaft regularization operation platform | |
CN212425155U (en) | Lifting system arranged on concrete structure floor slab | |
CN212802705U (en) | Elastic suspension hanging and pulling device suitable for large-span steel bar truss floor support plate | |
CN112854577A (en) | Self-formwork-supporting cast-in-place floor and construction method thereof | |
CN109914792B (en) | Underground garage beam formwork construction method | |
TW422904B (en) | Construction method and form derricking device used in concrete steel beam and floor slab construction for steel building | |
CN216786863U (en) | Cast-in-place box girder 0# block template system | |
CN215760439U (en) | High-low span concrete bottom plate formwork structure | |
CN215670918U (en) | Operation frame for high slope lattice beam | |
CN210238307U (en) | Crossbeam die block fixing system with adjustable height in bridge construction | |
CN1200185C (en) | Construction method and concrete-steel beams and floor slabs of building with steel frame and its form hoist | |
CN211368398U (en) | Frame climbing structure | |
KR200392341Y1 (en) | Fixing Device for Aerial Scaffolding | |
CN203531349U (en) | Novel high-bearing easily-dismantled overhanging type scaffold | |
RU2004126670A (en) | INSTALLATION FOR ESTABLISHING A PLATE OF THE INTER-FLOOR COVERING OF THE BUILDING AND THE METHOD OF ITS CONSTRUCTION | |
JP2000320142A (en) | Device and method for reinforcement assembly in construction work | |
CN220266311U (en) | Be used for bridge floor wet joint template construction equipment | |
CN220620985U (en) | Wall post steel bar binding operation platform convenient to turnover |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GD4A | Issue of patent certificate for granted invention patent | ||
MM4A | Annulment or lapse of patent due to non-payment of fees |