TW421691B - Wall-upward and slab-downward construction method - Google Patents

Wall-upward and slab-downward construction method Download PDF

Info

Publication number
TW421691B
TW421691B TW87106646A TW87106646A TW421691B TW 421691 B TW421691 B TW 421691B TW 87106646 A TW87106646 A TW 87106646A TW 87106646 A TW87106646 A TW 87106646A TW 421691 B TW421691 B TW 421691B
Authority
TW
Taiwan
Prior art keywords
floor
formwork
wall
cymbal
layer
Prior art date
Application number
TW87106646A
Other languages
Chinese (zh)
Inventor
Tzung-He Wu
Original Assignee
Wu Tzung He
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wu Tzung He filed Critical Wu Tzung He
Priority to TW87106646A priority Critical patent/TW421691B/en
Application granted granted Critical
Publication of TW421691B publication Critical patent/TW421691B/en

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

This wall-upward and slab-downward construction method includes following procedures. (1) Pre-set self-raising wall form unit between two neighboring columns, upon which wall and column are constructed upward one floor after another. (2) Settle U-shape form at beams of each floor, and place several posts underneath the U-forms with counter short posts inside the U-forms to support another post of the upper floor. (3) Leave the working deck of the self-raising form unit after the form is lifted up to the top floor. Then, hang several cables with at least one layer of floor form settled under it to allow the floor constructed downward one floor after another. According to the construction method mentioned, the wall-upward and slab-downward construction is possible with a short schedule and low cost.

Description

4 2 1 6 9 1 ( _銮號8Π06646_ 年月日 |修正 _ 五、發明說明(1) 一種「牆上板下之施工方法」,尤指一種得由下往上 逐層建構牆面、立柱及横粱,再由上往下逐層建構樓板, 俾以縮短施工工期’並節省施工成本。 按,一般建築樓房係於地基上先完成立柱,而在立柱 之間搭建有相對的牆面模板,而得在兩牆面模板之間灌漿 以構成牆面;再於立柱上架設樓面模板及橫粱模板,並於 樓面模板及橫樑模板的下方以複數個支撐柱頂撐,然後再 進行灌聚而.得以構成樓板在於完成的樓板上方建構立柱 及牆面,如此交替施工’方得以建成大樓。 然在建完一層的樓板後’必須等上一段相當長的時 間,使混凝土完全凝固後’方可再往上搭建牆面及立柱, 所以’在施工上礦日.費時,施工期相當長,因而增加施工 成本。 再者,由於建構樓板時,於樓面模板的下方必須裝設 數量非常多的支撐柱’方得以撐住樓面模板及灌漿時^ = 凝土重量’因此’在搭建樓面模板時較為麻煩不便,相對 地在完成該層的樓板後’ X須--‘將樓面模板拆除,再將 其搬運至上層搭建起來,所以在完工後的善後工作也十分 麻煩,同樣會延長施工工期,而浪費施工成本。 又’習知建構樓板時,必須注意支撐柱承載重量,否 則在灌漿後,因混凝土的重量相當重,而容'易發生支撐柱 無法承受混凝土的重量而崩模的意外。 另外,建構牆面及立柱時,如同搭建樓面模板—樣, 建完一層後,則須將下層的模板全部拆除後再往上搭建, 且須在樓板完成後方可再往上搭建,因此,在施工上也十4 2 1 6 9 1 (_ 銮 号 8Π06646_ year month date | correction _ V. Description of the invention (1) A "construction method under the wall panel", especially a wall and column that must be constructed layer by layer from bottom to top And beams, and then build the floor slabs from top to bottom, to shorten the construction period and save construction costs. According to the general building building is tied to the foundation first to complete the columns, and the opposite wall formwork is set between the columns. You have to grout between the two wall formwork to form the wall surface; then set up the floor formwork and beam formwork on the columns, and support the column formwork with a plurality of support pillars under the floor formwork and beam formwork, and then proceed Encapsulation. To form a floor, the columns and walls are constructed above the completed floor, so that alternate construction can be completed 'to build the building. However, after the floor of the first floor is completed,' it must wait a considerable time for the concrete to completely solidify. 'Only the walls and columns can be built up, so' the construction and mining day. It takes time and the construction period is quite long, which increases the construction cost. Moreover, when the floor is constructed, it must be installed below the floor formwork. A very large number of support pillars were used to support the floor formwork and grouting ^ = the weight of the condensate. Therefore, 'the floor formwork was more troublesome and inconvenient, and the floor slab on this floor was relatively' Xbear-- ' The floor formwork is dismantled and then moved to the upper floor to build it, so the aftercare work after completion is also very troublesome, which will also prolong the construction period and waste construction costs. Also, when constructing the floor, you must pay attention to the support column load Weight, otherwise after the grouting, the weight of the concrete is quite heavy, and it is easy to accidentally collapse the supporting column because it cannot support the weight of the concrete. In addition, when constructing walls and columns, it is like building a floor formwork. After the first floor is completed, the formwork of the lower floor must be removed and built up, and it can only be built up after the floor is completed.

第4頁 42 1 69 1 修正 _案號 87106M6 五、發明說明(2) 分麻煩不便 本發明 板後,必須 及立柱’如 工期,因而 而設計出一 模板機構預 機構逐層向 建U形模, 裝有複數個 得再支撐上 機構移昇至 並在其吊裝 面模板,而 板,據上述 及横粱,再 成的時間, 層分次進行 柱的麻煩, 又該樓面模 撐強度,並 降移即可拆 由是, 逐層建構牆 俾以縮短施 人有感於習 等上一段相 此交替循環 增加施工的 種得縮短施 设在相鄰兩 上建構牆面 於其下方裝 相對於支柱 一樓層横樑 頂層後,得 複數個鋼索 得逐層放下 之施工方法 由上往下逐 即可先進行 樓板部份, 俾以縮短施 板係藉由懸 可免除使用 模*因此得 本發明之主 面、立柱及 工工期,並 知建構大樓 當長的時間 施工,較礦 成本。本發 工期的施工 立柱之間, 及立柱;又 設有複數個 頂端的短支 下方的另一 留下自昇牆 ’且在該鋼 樓面模板, ’得由下往 層建構樓板 牆面、立柱 並可免除架 工的工期, 吊的方式支 支撐柱的麻 便於拆模, 要目的,旨 橫粱,再由 節省施工成 時’由於建 ’方可再往 曰費時,而 明人因而著 方法,係將 而得藉由自 於各樓層的 支柱,且在 柱’並於短 支柱;該自 面模板機構 索下方裝設 使其得由上 上逐層建構 ,而得免除 及橫樑部份 設支撐樓面 並可節省施 撐,因而得 煩.,且將樓 旅且可重覆 在提供一種 上往下逐層 本。 完一層的樓 上搭建牆面 延長施工的 手構思,終 一自昇牆面 昇牆面模板 橫樑部份搭 U形模内插 支柱的上方 昇牆面模板 的工作台, 至少一層樓 往下建構樓 牆面、立柱 專待樓板完 ’然後再分 模板之支撐 工的成本; 有較佳的支 面模板往下 使用。 得由下往上 建構樓板,Page 4 42 1 69 1 Amendment_Case No. 87106M6 V. Description of the invention (2) After inconvenience, the board of the invention must be connected with the pillars, such as the construction period, so a template mechanism pre-mechanism is designed to build the U-shaped mold layer by layer. It is equipped with a plurality of re-supporting upper mechanisms that are moved to and lifted on its hoisting surface formwork, and the board, according to the above and the time of the beam, rebuilds the column in stages, and the floor formwork strength, It can be dismantled by moving downwards. The walls are constructed layer by layer to shorten the experience of the person. The previous section alternates with the cycle to increase the number of types of construction. The installation is shortened. After the top of the beam on the first floor of the pillar, the construction method of multiple steel cables that can be lowered layer by layer can be carried out from top to bottom, and the floor part can be carried out first. The main face of the invention, the columns and the construction period, and know that the construction of the building should take a long time to construct, which is more expensive than mine. Between the construction columns during the construction period, and the columns; there are also a plurality of short branches at the top, and another one is left with a jack-up wall ', and in the steel floor formwork,' the floor wall must be constructed from the bottom to the floor, The column can also save the construction period of the frame. The hemp supporting the column is easy to remove the mold. The purpose and purpose of the beam are to save time when the construction is completed. The method is to use the pillars from each floor, and the pillars and the short pillars; the self-faced formwork mechanism cable is installed below it so that it can be constructed layer by layer from the top to the top, and the beam section can be eliminated. It can be annoying to set up a supporting floor and save support, and the building trip can be repeated to provide a layer by layer. After finishing the first floor, the wall is extended to construct the manual concept of the construction. Finally, a jack-up wall formwork beam crossbeam part is covered with a U-shaped formwork and an upper pillar wall formwork workbench. At least one floor is constructed downward. Floor walls and columns are waiting for the floor slabs to finish, and then the cost of the supporting work of the formwork is divided; there are better supporting formwork used downwards. You have to build the floor from the bottom up,

第5頁 421691 ' 案號87106646 年月日 修正 懸用 如 由使述 藉除 詳 係免 示 板可 圖 模並 各 面,。列 樓度用下 種強使合 1撐覆配 供支重兹 1 提的及, 280 在佳模實 55 板2 則較拆詳 3模柱7模機 ,有於確 面形枝索面揚 的得便明 牆U短鋼樓捲 目而可加 明 一因且更 說 又,,作 單 之#煩創 簡 一—_ 一—- ο 3)明支麻本 之145672 W發式的使 號 5本方柱為 件 管台 | 的撐:柱樑柱板心作 £'吊支 后 立橫支樓空工 白 昇 牆 面模板機構 2 Η 形 滑 桿 2 1 Η 形 滑 桿 2 1 户 中 間 板 2 1 1 齒 條 2 1 2 齒 條 2 1 3 翼 板 2 1 4 翼 板 2 1 r 逆 齒 條 2 1 5 定 位 機 構 2 2 架 體 2 2 1 滾 輪 組 2 2 2 滾 輪 2 2 2 定 位 塊 2 2 3 液 壓 缸 2 2 4 昇 降 液 壓缸 2 3 模 板 2 4 結 構 架 2 5 匚 型 夾 框 2 6 勾 端 2 6 1 擋 塊 2 6 2 彈 簧 2 6 3 塾 塊 2 7Page 5 421691 'Case No. 87106646 Amendment Inactive If used, the borrowing details can be exempted and the drawings can be combined on all sides. The column strength uses the following strength to make the 1 support cover with the support weight, which is mentioned above, 280 in the good mold 55 plate 2 is more detailed than the 3 mold column 7 mold machine, it is more accurate in shape Debian Ming wall U short steel building volume can be added one more reason, let alone say, Zuo Zhi Zhi ## 创 创 简 一 —_ 一 —- ο 3) Ming Zhi Ma Benzhi 145672 W hair style No. 5 This square column is a piece of pipe platform | The brace of the column: the column beam, the column and the heart of the plate are made of the crane's back, the horizontal branch of the building, and the empty white rise wall formwork mechanism 2 Η shaped slide 2 1 Η shaped slide 2 2 Intermediate plate 2 1 1 Rack 2 1 2 Rack 2 1 3 Flange 2 1 4 Flange 2 1 r Inverse rack 2 1 5 Positioning mechanism 2 2 Frame 2 2 1 Roller set 2 2 2 Roller 2 2 2 Positioning Block 2 2 3 Hydraulic Cylinder 2 2 4 Lifting Hydraulic Cylinder 2 3 Formwork 2 4 Structural Frame 2 5 Clamp Frame 2 6 Hook End 2 6 1 Stopper 2 6 2 Spring 2 6 3 Block 2 7

第6頁 421691 案號87106646 年月日 修正 五、發明說明(4) 明 柱工牆 其數恰方 下個設管模模 及間有間、2 發 立一構 於複2上 留數裝心面面 圖之¾中1構 本 兩有建 ,有5的 得複方空樓樓 五 '裝的2機 , 的設上 5裝柱CO ,設下個在下。第1間' 桿位 示 鄰裝向 模插支5。後裝7數放降示如2之1滑定 所 相間層 形内短柱1層上索複層次所,、22形該 圖 在之逐U5該支5頂其鋼裝逐逐圖212、H而 三 設22 建模而短柱至在在套時層四構2構1在, 第 預構構 搭形,於支昇並且上6逐第機桿機2且3 及 2機機 份U2並一移,,7板以如板滑位桿,1 圖 構板板 部在5,另207索樓6,模形定滑22 二 機模模 4且柱度的構2索鋼構板6面Η兩形1條 第 板面面 樑,支高方機台鋼該建樓板牆的在Η2齒 、 模牆牆 橫1短的下板作一在於過樓昇立而該條一 圖:面昇昇 的5的64模工裝且得穿構自直,中齒有 一驟牆自自 層柱端板樑面的吊,1得建之兩2其一設 第步昇個由 樓支頂樓横牆2上877下法於2,有另 閱之自數藉 各個1至層昇構其板管索往方係構3設上 參下一複得。於數5部樓自機,模心鋼上工其機2各面 請如將於而1又複柱底一該板1面空使由施,位缸側對 ,法}並,柱}有支4上}模ο樓該俾得述示定壓兩相 先方a ,ο立b設於粱樓C面2層而,而前所兩液1的 首工C間2及C裝對橫支C牆機一,上,如圖有降1, 施 之台3 方相於再 昇揚少188 六設昇21 之 1作面 下個等得 自捲至7板板 第裝一板2 :) ,¾ ίίPage 6 421691 Case No. 87106646 Amended on May 5, V. Description of the invention (4) The number of Mingzhu wall is exactly the next, there is a tube mold and there is a space between them, 2 sets of a structure on the complex 2 to leave a few hearts In the above-mentioned diagram, ¾ of the 1 structure has two constructions, and 5 of the 2 units of the compound empty building have 5 units, and 5 units of CO are installed, and the next one is located below. No. 1 'pole position is shown next to the mold insert support 5. After installation, the number of 7 is shown below, as shown in Figure 2-1, the inter-layered short column, the upper layer, the upper layer, the layer 22, the figure is U5, the branch 5 top, and the steel is installed one by one. 212, H And three sets of 22 modeling and short columns to the time of the set of four structures, two structures, one, the first pre-configuration configuration, in the support and up 6th to the second rod machine 2 and 3 and 2 machine parts U2 and one Move, the 7 plate is like a plate slide bar, the 1 plate structure plate is at 5, the other 207 cable building 6, the mold is fixed 22, the two machine mold 4 and the column structure 2 cable steel structure plate 6 face Η The two beams of the first slab surface, supporting the high-end machine platform steel, the lower slab of the building slab wall is 2 teeth, and the mold wall is horizontal and short. The 5 and 64 die tooling must be constructed from straight, the middle tooth has a sudden wall from the beam end of the column end plate, 1 can be built two, one of them can be set up step by step on the top floor of the horizontal wall 2 877 down the method at 2, there is a separate reading to borrow from each 1 to the layer of the structure of its tube tube to the side of the system 3 set up the next reference. In several buildings, the mold core steel works on the machine 2 on each side of the machine. If you are going to, then the bottom of the column and the bottom of the board. The side of the board is empty, and the side of the cylinder is opposite. Support 4 on the top of the mold. The building can be described as a constant pressure two-phase first square a, and the stand b is located on the 2nd floor of the C surface of the beam building. C wall machine one, up, as shown in Figure 1, there is a drop of 3, Shi Zhitai, and then lift up less 188, 6 set up 21 1 for the next, etc., from the roll to the 7 board, the first board 2 :) , ¾

I 4 2 16 9 1 .'个 _案號 87106646_年月日_^ 五、發明說明(5) 2係於一架體2 2 1的兩側各裝設有兩滾輪組2 2 2 ,該' 滾輪組2 2 2係由三個滾輪2 2 2 a所組成,其得三面夾 靠在該Η形滑桿2 1 、21 /的翼板214、214一末 端,又於定位機構2 2兩側各樞設有三個定位塊2 2 3 , . 該定位塊2 2 3係由一液壓缸2 2 4所帶動使其得往復擺 動而抵靠在Η形滑桿2 1上的齒條2 1 2 、2 1 3 ;得藉 由兩定位機構2 2及昇降液壓缸2 3依序動作,俾使兩Η 形滑桿2 1 、2 1 /得交互上下移動,以移昇裝設在其中 之一的Η形滑桿2 1 /上的模板2 4。 又該固定於立柱1上之Η形滑桿2 1外側設有一逆齒 條2 1 5,並於Η形滑桿2 1上裝設有一 c型夾框2 6 , 而該C形夾框2 6的末端向内設有勾端2 6 1 ,其得勾扣0 在Η形滑桿2 1的翼板2 1 4上,又於匚形夾框2 6内樞 設有一擋塊2 6 2 ,而該擋塊2 6 2得藉由一彈簧2 6 3 推頂,使其抵靠在逆齒條2 1 5上,又該c型夾框2 6得 裝設在一墊塊2 7上,且該墊塊2 7固定在立柱1上,得 · 藉由定位機構2 2及昇降液壓缸2 3將Η形滑桿2 1向上 推昇,且在上層立柱1的直線位置上裝設有複數個匚型夾 框2 6 ,而可直接將Η形滑桿2 1直接推昇至上層的預設 位置,而不須拆卸Η形滑桿2 1 ,所以得免除拆卸Η形滑 桿2 1的麻煩;並得使Η形滑桿2 1避開建築物之横粱, 而可便於裝設Η形滑桿2 1 。 根據上述施工方法之自昇牆面模板機構2,得在第一 } 樓層兩相鄰立柱1的預設位置上各裝設Η形滑桿2 1 ,而 1 位在外側的兩Η形滑桿2 1 >則以結構架2 5連接,並且I 4 2 16 9 1. '_ Case number 87106646_ year month date_ ^ V. Description of the invention (5) 2 is attached to a frame 2 2 1 on each side of the two roller sets 2 2 2, the '' The roller set 2 2 2 is composed of three rollers 2 2 2 a, which are clamped on three sides against one end of the wing plates 214, 214 of the cymbal slider 2 1, 21 /, and the positioning mechanism 2 2 two. There are three positioning blocks 2 2 3 on each side of the pivot. The positioning block 2 2 3 is driven by a hydraulic cylinder 2 2 4 to make it reciprocate and swing against the rack 2 1 on the cymbal slider 2 1 2, 2 1 3; The two positioning mechanisms 22 and the lifting hydraulic cylinder 23 can be moved in sequence, so that the two cymbal sliders 2 1 and 2 1 can be moved up and down alternately to move the installation in it One of the cymbal sliders 2 1/4 on the template 2. An inverse rack 2 1 5 is provided on the outside of the cymbal slider 2 1 fixed on the column 1, and a c-shaped clamp frame 2 6 is mounted on the cymbal slider 2 1, and the C-shaped clamp frame 2 The end of 6 is provided with a hook end 2 6 1 which has a hook buckle 0 on the wing plate 2 1 4 of the cymbal slider 2 1 and a stopper 2 6 2 at the inner pivot of the cymbal clip frame 2 6. And the stopper 2 6 2 must be pushed up by a spring 2 6 3 to make it abut against the reverse rack 2 1 5, and the c-shaped clamp frame 2 6 must be installed on a pad 2 7 And the pad 2 7 is fixed on the column 1 to obtain the positioning mechanism 2 2 and the lifting hydraulic cylinder 2 3 to push the cymbal slider 2 1 upward, and it is installed on the linear position of the upper column 1 A plurality of 夹 -shaped clamp frames 2 6 can directly push the Η-shaped slider 2 1 to a preset position on the upper layer without removing the , -shaped slider 2 1, so the removal of the Η-shaped slider 2 1 may be eliminated. It is also necessary to avoid the cymbal slider 2 1 from the beams of the building, and it is convenient to install the cymbal slider 2 1. According to the self-elevating wall formwork mechanism 2 of the above construction method, it is necessary to install stell-shaped sliders 2 1 at the preset positions of two adjacent columns 1 on the first} floor, and two stern-shaped sliders on the outside 2 1 > are connected by a structural frame 2 5 and

第8頁 421691 - _案號871Q6646_年月日__- 五、發明說明(6) * 在結構架2 5上向内牆面的部份組裝模板2 4 ,如第七圖~ 所示,而得在兩相對的模板2 4之間灌漿,以建構成牆面 3及立柱1 ;若要將模板2 4往上移昇時,得將位在下方 之定位機構2 2的A部及B部的定位塊2 2 3藉由液壓缸 . 2 2 4向外推頂而抵靠定位在Η形滑桿2 1 、2 1 >的齒 條2 1 2、2 1 3上,而位在上方之定位機構2 2的C部 及D部的定位塊2 2 3則藉由液壓缸2 2 4向内收縮,使 定位塊2 2 3不抵靠在Η形滑桿2 1 、2 1 /的齒條2 1 2及2 1 3上,此時該昇降液壓缸2 3向下收縮,使位在 上方的定位機構2 2向下滑移,如第八圖所示;然後位在 上方之定位機構2 2的C部藉由液壓缸2 2 4將定位塊2 2 3推抵在Η形滑桿2 1 >的齒條2 1 2、2 1 3上,而A 位在下方之定位機構2 2的B部定位塊籍由液壓缸2 2 4 使其脫離Η形滑桿2 1、2 1 /上的齒條2 1 2、2 1 3 ,此時該昇降液壓缸2 3向上推頂,而將供裝設模板2 4的Η形滑桿2 1 >向上移昇,如此即將模板2 4向上推 移,而不需拆除模板2 4 ,並且將模板2 4直接推移至上 . 層的牆面位置,當其推至預設高度後,則上、下方的定位 機構2 2所有未抵靠在齒條2 1 2、2 1 3上的定位塊2 2 3全部藉由液壓缸2 2 4向外推移,以將模板2 4定 位。 再者,當上層的牆面3及立柱1完成後,該模板2 4 及用以固定模板2 4的結構架2 5則固定在已完成的牆面1 } 3及立柱1上,然後如同前述之動作方式,不同處在於此1 次是向上拉昇位於内部的.Η形滑桿2 1 〃,而非位在外部Page 8 421691-_Case No. 871Q6646_ Year Month and Day __- V. Description of the Invention (6) * Assemble the template 2 4 on the structural frame 25 to the inner wall surface, as shown in the seventh figure ~, It is necessary to grout between two opposite formwork plates 24 to build the wall surface 3 and the column 1; if the formwork plate 2 4 is to be moved upward, the A and B parts of the positioning mechanism 2 2 located below The positioning block 2 2 3 of the middle part is pushed by the hydraulic cylinder. 2 2 4 pushes against the rack 2 1 2 and 2 1 3 positioned on the cymbal slider 2 1, 2 1 > The positioning block 2 2 3 of the C and D parts of the upper positioning mechanism 2 2 is contracted inward by the hydraulic cylinder 2 2 4 so that the positioning block 2 2 3 does not abut against the cymbal slider 2 1, 2 1 / The racks 2 1 2 and 2 1 3 are retracted, and the lifting hydraulic cylinder 23 is contracted downward to move the positioning mechanism 2 2 above, as shown in the eighth figure; The C part of the positioning mechanism 2 2 pushes the positioning block 2 2 3 against the rack 2 1 2 &2; of the slide bar 2 1 by the hydraulic cylinder 2 2 4 and the A position is positioned below The positioning block of the part B of the mechanism 2 2 is separated from the cymbal slide 2 2 by the hydraulic cylinder 2 2 4 / the rack 2 1 2 2 1 3, at this time, the lifting hydraulic cylinder 2 3 is pushed upwards, and the slide bar 2 1 for mounting the template 2 4 is moved upward, so that the template 2 4 is moved upward without removing the template. 2 4, and move the template 2 4 directly to the top. When the wall position of the layer is pushed to the preset height, the upper and lower positioning mechanisms 2 2 are not against the rack 2 1 2, 2 1 3 The upper positioning blocks 2 2 3 are all pushed outward by the hydraulic cylinder 2 2 4 to position the template 2 4. Furthermore, when the upper wall 3 and the pillar 1 are completed, the template 2 4 and the structural frame 25 for fixing the template 2 4 are fixed on the completed wall 1} 3 and the pillar 1, and then as before The difference is that this time it is pulled up to the inside. The Η-shaped slider 2 1 〃 instead of the outside

第9頁 4 2 16 9 1 :' _案號871Q6646_年月日__/ 五、發明說明(7) ' 的Η形滑桿2 1 ,如此即得將Η形滑桿2 1 >往上移昇,· 如第十圖所示 如前所述,上下交替移昇該Η形滑桿2 1 、2 1 /即 可將模板2 4及結構架2 5逐層向上移昇建築牆面3及立 . 柱1 ;且當逐層向上建構時,該用以建構橫樑4的u形模 5 ,其内插裝有複數個短支柱5 2,且在相對於短枝柱5 2的u形模5下方裝設有支柱5 1 ,又於短支柱5 2上方 支撐上一樓層橫樑4下方的另一支柱51 ,俾使橫樑4得 連同牆面3及立柱1逐層向上建構;並且該模板2 4得由 底層向上移昇重覆使用,所以得節省施工成本。 而當牆面3及立柱1已建構到屋頂時,該自昇牆面模 板機構2已爬昇至頂層,得在自昇牆面模板機構2的工作6 台2 0留下,其它部份拆下,並在工作台上吊裝複數個鋼 索7 ,且該鋼索7係由捲揚機2 0 1帶動,而在鋼索7下 方的裝設一層樓面模板8,且該樓面模板8恰等於横樑4 所圍成的矩形區域,而得藉由捲揚機2 0 1將樓面模板8 吊降至樓板6的位置,如此即可在該層位置灌漿以建構樓 板6 ;若要再往下建構樓板6時,則可藉由捲揚機2 0 1 將樓面模板8繼續往下降至下一樓層的位置,而得往下繼 續灌漿建構下層樓板6;且在鋼索7上套裝有複數個空心 管7 1 ,該空心管7 1得於建構樓板6時逐層放在樓面模 板8上,俾使鋼索7得穿過樓板6以逐層逐次降下樓面模 板8 ,而得由上往下逐層建構樓板6 ,如第四圖所示。 -s 另,該鋼索7上得同時裝設複數個預設樓層的樓面模 j" 板8 ,而得一次在一層的樓面模板8進行灌漿,而可以逐Page 9 4 2 16 9 1: '_Case No. 871Q6646_Year Month and Day __ / V. Description of the invention (7)' Η-shaped slider 2 1, so that the Η-shaped slider 2 1 > to Move up, as shown in the tenth figure, as mentioned above, move the cymbal sliders 2 1 and 2 1 up and down to move the formwork 2 4 and the structural frame 2 5 up and down the building wall. 3 and up. Column 1; and when it is constructed layer by layer, the u-shaped mold 5 for constructing the beam 4 is interposed with a plurality of short pillars 5 2 and the u A pillar 5 1 is installed below the form 5 and another pillar 51 below the beam 4 on the previous floor is supported above the short pillar 5 2 so that the beam 4 can be constructed layer by layer along with the wall 3 and the column 1; and the The formwork 24 must be lifted and used repeatedly from the bottom layer, so the construction cost must be saved. And when the wall 3 and the column 1 have been constructed on the roof, the self-elevating wall formwork mechanism 2 has climbed to the top floor, and 6 units 2 0 of the self-elevating wall formwork mechanism 2 must be left, and the other parts are removed. A plurality of steel cables 7 are hoisted on the workbench, and the steel cables 7 are driven by a hoist 2 01, and a floor formwork 8 is installed below the steel rope 7, and the floor formwork 8 is exactly equal to the beam 4 The enclosed rectangular area has to be hoisted to the floor 6 by the hoisting machine 201, so that the floor 6 can be grouted to construct the floor 6; if the floor 6 is to be constructed further down, Then, the floor formwork 8 can be further lowered to the position of the next floor by the hoist 2 01, and the lower floor slab 6 can be constructed by grouting downward; and a plurality of hollow tubes 7 1 are set on the steel cable 7, and the hollow The tube 7 1 is placed on the floor formwork 8 one by one when the floor 6 is constructed, so that the steel cable 7 must pass through the floor 6 to lower the floor form 8 one by one, and the floor 6 can be constructed layer by layer from top to bottom. As shown in the fourth figure. -s In addition, the steel cable 7 may be equipped with floor templates j " slabs 8 of a plurality of preset floors at the same time, and grouting may be performed on the floor template 8 of the first floor at a time.

第ίο頁 421691 案號87106646 年月日 修正 而板模6第 ,樓面板如 00成樓樓丨 板構的之6 模段段成板 面分分完樓 樓層各已構 個分使在建 數以,得層 。複漿7而逐 示設灌索,段 所裝行鋼置分 圖隔進下位以 一間〇〇放6俾 十層板1板, 第分模ο樓6 如等面2的板 ,上樓機層樓 6 7的揚樓構 板索層捲一建。 8)樓鋼一由下層示 W成該在藉至樓所 S構又次再降一圖 |建 一 .,8下二 i'層 得6板的十 ,拆支的 模得 部 以及式模 面8 内 所柱方崩 樓板 及 ,撐的而 下模 3 禮支申倒 降面 面 支裝懸傾 ,樓 牆 式架7生 此該 、 方除索發 因以 1 的免鋼柱 ,所 柱 吊可由撐 構, 立 懸此藉支 建6 的 由因係用 下板。部 藉,8使 往樓用外 係柱板式 上構費將 8樓模方 由建省得 板支面知 係在節, 模設樓習 8可以時 面裝於除 板即得樓 樓式由免 模層而大 於方且可 面樓因構 由知.,,。樓一,建 且習煩此況該下用於 並如麻因情且至使由 須的,外 8覆 不除撐意 板重 ,一 以省 係利並 板築一所節 法專查 樓建部,以 方明審 構上全建得 工發予 建往須搭樣 施備貴 層再不層同 下具局 逐可且上, 板已鈞 下即;至間 上理 往,本移時 牆,盼 上工成搬及 之果, 由完工板力 露效利 再板施模人 揭之專 ,樓省將省 所述明 成的節式節 明上發 完層以方得 發成請 構該期的而 本達申 建待工工, ,能出 上等的人便 述實提 往須工以簡 所確法 下不施再為 上且依 由,短,較。以,爰 4此縮板上本合無, 樑因得模工成綜所件 橫,而除施工 昔要 的6因拆在施 往之 42 1 69 1 案號 87106646 年月曰 修正 五、發明說明(9) 准予專利,實為感禱。Page 421691 Case No. 87106646 was amended on the day of the month and the slab is 6th, the floor slab is like 00 Chenglou 丨 the 6th slab segment of the slab structure is divided into slabs and divided into floors. Each floor has been constructed. , Get the layer. The compound 7 is installed and the ditch is installed one by one, and the steel installed in the section is placed in the lower part, and the floor is placed with one floor, one floor, one floor, and one floor, and the floor is placed on the floor. The first floor of the Yangtze building structure with 6 floors and 7 floors was rolled up. 8) The first floor of the steel building is shown as W, and it should be borrowed to the floor of the building. The structure is lowered again. The inside 8 pillars collapsed the floor slabs, and the supporting molds were lowered. 3 The Li Zhishen fell down and the surface supports were suspended and tilted. The floor wall frame 7 was built in this way. The column crane can be supported by the support structure, and the lower plate of the cause 6 is built by this support. Borrowed by the Ministry of Foreign Affairs, the cost of the 8-story building with the external bollard slab-type construction fee will be used to save the 8th-floor mold from the province's board support surface. The floor is larger than the square and the floor can be known for structural reasons. ,,. Building one, built and used in this situation should be used for the same reason as the cause of the situation, so as to avoid the need to support the weight, one to build a special section of the law to save money The Ministry of Construction, Yiming Fangming reviewed the construction of the entire industrial development and development to build to be required to prepare a layer of equipment, and then the different layers of the next layer must be followed by the next step, the board has been down immediately; The results of Shang Gongcheng's move will be revealed by the finished board force and the model maker, and the provincial government will send the completed sections of the Mingcheng section to the completion floor in order to complete the period. While Bender applied for the construction workers, those who can show the best will report to the required workers in accordance with the simple method, no longer be superior and compliant, short, and more. Therefore, 爰 4 does not fit on this shrink board. The beam is made by the molder to become a comprehensive building, and the 6 due to the construction is dismantled. 42 1 69 1 Case No. 87106646 Note (9) The grant of patent is really a prayer.

liB 4 2 1691 1 _案號87106646_年月曰 修正_ 圖式簡單說明 第一圖 係本發明之自昇牆面模板機構設置在兩預設立柱 之間由下往上建構立柱及牆面之示意圖(一) 第二圖 係本發明之自昇牆面模板機構設置在兩預設立柱 之間由下往上建構立柱及牆面之示意圖(二) 第三圖 係本發明之自昇牆面模板機構設置在兩預設立柱 之間由下往上建構立柱及牆面之示意圖(三) 第四圖 係本發明由上往下建構樓板之示意圖 第五圖 係本發明之自昇牆面模板機構設置在立柱上之剖 視圖 第六圖 係本發明之自昇牆面模板機構的頂視圖 第七圖 係本發明之自昇牆面模板機構設置在兩預設立柱 之間的上視圖 第八圖 係本發明之自昇牆面模板機構向上移昇之動作實 施例(一) 第九圖 係本發明之自昇牆面模板機構向上移昇之動作實 施例(二) 第十圖 係本發明之自昇牆面模板機構向上移昇之動作實 施例(三) 第十一圖 係本發明由上往下建構樓板之另一實施示意圖 (一) 第十二圖 係本發明由上往下建構樓板之另一實施示意圖liB 4 2 1691 1 _Case No. 87106646_ Years and Months Revision _ Brief Description of the Drawings The first diagram is a self-elevating wall formwork mechanism of the present invention, which is arranged between two pre-established columns to construct the columns and the wall from the bottom to the top. Schematic diagram (a) The second diagram is a schematic diagram of the self-elevating wall formwork mechanism of the present invention, which is arranged between two pre-established columns, from the bottom to the top to construct the column and the wall (two) The third diagram is the self-elevating wall of the present invention Schematic diagram of the formwork mechanism set up between the two pre-established columns from the bottom to the top to construct the columns and the wall (3) The fourth diagram is a schematic diagram of the floor slab constructed from the top of the present invention The fifth diagram is the self-rising wall formwork of the present invention Sectional view of the mechanism provided on the upright post. The sixth view is a top view of the self-elevating wall formwork mechanism of the present invention. The seventh view is an upper view of the self-elevating wall formwork mechanism of the present invention. The upward movement example of the self-elevating wall formwork mechanism of the present invention (1) The ninth picture is the upward movement example of the self-elevating wall formwork mechanism of the present invention (2) The tenth diagram is the operation of the present invention Jack-up wall formwork mechanism Example of upward movement (3) Figure 11 is another schematic diagram of the present invention constructing a floor from top to bottom (1) Figure 12 is another schematic diagram of the present invention constructing a floor from top to bottom

第13頁Page 13

Claims (1)

421691 1 修正 ____.案破 8710664R 六、申請專利範圍 1· 一種「牆上板下之施工方法」,包括: (a )將一自昇牆面模板機構(2 )預設在相鄰的兩立 Ϊ ( 1 ’並於複數個自昇牆面模板機構(2 )之間裝設有 二f作台(20) ’而得藉由自昇牆面模板機構(2)逐層向上 建構牆面(3 )及立柱(1 ); (b )又於各樓層的横樑(4)部份搭建口形模(5),於 ^下方裝設有複數個支柱(51),且在u形模(5)内插裝有 複數個相對於支柱(51)頂端的短支柱(52),而該短支柱 (52)恰等於横粱(4)底部至樓板(6)面的高度,並於短支柱 (52)的上方得再支撐上一樓層橫樑(4)下方的另一支柱 (51);421691 1 Amendment ____. Case broken 8710664R VI. Patent application scope 1. A "construction method under the wall panel" includes: (a) presetting a self-elevating wall formwork mechanism (2) to two adjacent ones The stand (1 'and two f-workbenches (20)' are installed between a plurality of jacking wall formwork mechanisms (2) ', so that the wall surface can be constructed layer by layer by the jacking wall formwork mechanism (2). (3) and uprights (1); (b) A mouth-shaped mold (5) is also installed on the beam (4) on each floor, a plurality of pillars (51) are installed below the ^, and the u-shaped mold ( 5) A plurality of short pillars (52) opposite to the top of the pillar (51) are interposed, and the short pillars (52) are exactly equal to the height from the bottom of the beam (4) to the floor (6) surface, and (52) The other pillar (51) below the beam (4) on the previous floor must be supported above; (c )該自昇牆面模板機構(2)移羿至頂層後,得留 下自昇牆面模板機構(2)的工作台(2〇),並在工作台(20) 上裝設複數個捲揚機(2〇1),其上吊裝一鋼索(7),且在鋼 索(7)並於其下方裝設至少一層樓面模板(8),又該鋼索 (7 )上套裝複數個空心管(7丨),該空心管(7丨)得於建構樓 板(6)時逐層放在樓面模板(8)上,俾使鋼索(7)得穿過樓 板(6)以逐層逐次降下樓面模板(8),而得由上往下建構樓 板(6 )。 2. 如申請專利範圍第1項所述之「牆上板下之施工方法」 ’其中該鋼索(7)上得同時裝設複數個預設樓層的樓面模 板(8) ’而得一次在一層的樓面模板(8)進行灌漿,以逐層 建構成樓板(6)。 3. 如申請專利範圍第1項所述之「牆上板下之施工方法」(c) After the self-elevating wall formwork mechanism (2) is moved to the top layer, the workbench (2) of the self-elevating wall formwork mechanism (2) must be left, and a plurality of workbenches (20) are installed on the workbench (20). A hoist (2101), a steel cable (7) is hoisted thereon, and at least one floor formwork (8) is installed below the steel cable (7), and a plurality of hollow tubes are set on the steel cable (7) (7 丨), the hollow pipe (7 丨) is placed on the floor formwork (8) layer by layer when the floor slab (6) is constructed, so that the steel cable (7) must pass through the floor slab (6) to be lowered one by one. Floor formwork (8), and floor slabs (6) must be constructed from top to bottom. 2. According to the "Construction method under the wall panel" described in item 1 of the scope of the patent application, 'The steel cable (7) may be installed with floor templates (8) of a plurality of preset floors at the same time.' The floor formwork (8) on the first floor is grouted to construct the floor slab (6) layer by layer. 3. "Construction method under wall panel" as described in item 1 of the scope of patent application 第14頁 421 69 1 案號 87106646 年 月 曰 修正 六、申請專利範圍 ,其中該鋼索(7)上等分層間隔裝設複數個樓面模板(8), 得一次在一層的樓面模板(8)進行灌漿以構成樓板(6),再 藉由捲揚機(201)放下鋼索(7),使各樓面模板(8)降至下 一樓層的樓板(6)位置,而得在已完成之樓板(6)的下一樓 層建構樓板(6),俾以分段逐層建構樓板(6)。 4.如申請專利範圍第1項所述之「牆上板下之施工方法」 ,其中該自昇牆面模板機構(2),其係於兩直立的Η形滑 桿(21)、(21’)之間裝設有兩定位機構(22),而在兩定位 機構(2 2 )之間裝設有一昇降液壓缸(2 3 ),其中該Η形滑桿 (2 1 )、( 2 Γ )的中間板(2 1 1 )兩側各設有一齒條(2 1 2 ),且 在Η形滑桿(2 1 )、( 2 Γ )的相對面上另設有一齒條(2 1 3 ), 而該定位機構(2 2 )係於一架體(2 21)的兩側各裝設有兩滾 輪組( 222 ),該滚輪組( 2 2 2 )係由三個滾輪( 2 2 2a)所組成, 其得三面夾靠在Η形滑桿(21)、(2Γ)的翼板(214)、 (2 1 4 ’)末端,又於定位機構(2 2 )兩側各樞設有三個定位塊 (2 2 3 ),該定位塊(2 2 3 )係由一液壓缸(2 2 4 )所帶動使其得 往復擺動而抵靠在Η形滑桿(2 1 )上的齒條(2 1 2 )、( 2 1 3 ); 得藉由兩定位機構(22)及昇降液壓缸(23)依序動作,俾使 兩Η形滑桿(21)、(2Γ)得交互上下移動,以移昇裝設在 其中之一的Η形滑桿(2 Γ )上的模板(2 4 );又該固定於立 柱(1 )上之Η形滑桿(2 1 )外侧設有一逆齒條(2 1 5 ),並於 Η形滑桿(2 1 )上裝設有一〔型夾框(2 6 ),而該c形爽框 (26)的末端向内設有勾端(261),其得勾扣在Η形滑桿 (21)的翼板(214)上,又於匚形夾框(26)内樞設有一擋塊Page 14 421 69 1 Case No. 87106646 Amendment VI. Scope of patent application, in which the steel cable (7) is installed with multiple floor formwork plates (8) at equal intervals, and the floor formwork on the first floor ( 8) Grouting to form the floor slab (6), and then lowering the steel cable (7) by the hoist (201), lowering each floor formwork (8) to the position of the floor (6) on the next floor. The floor (6) is constructed on the next floor of the floor (6), and the floor (6) is constructed layer by layer. 4. The "construction method under the wall plate" as described in item 1 of the scope of patent application, wherein the self-elevating wall formwork mechanism (2) is attached to two upright cymbal slide bars (21), (21 ') Are provided with two positioning mechanisms (22), and a lifting hydraulic cylinder (2 3) is installed between the two positioning mechanisms (2 2), wherein the Η-shaped slide bar (2 1), (2 Γ A rack (2 1 2) is provided on each side of the middle plate (2 1 1), and a rack (2 1 3) is provided on the opposite side of the cymbal slider (2 1), (2 Γ). ), And the positioning mechanism (2 2) is attached to two sides of a frame body (2 21) with two roller sets (222), and the roller set (2 2 2) is composed of three rollers (2 2 2a) ), It is clamped on three sides against the ends of the wings (214), (2 1 4 ') of the cymbal slider (21), (2Γ), and three pivots are provided on each side of the positioning mechanism (2 2). Positioning block (2 2 3), the positioning block (2 2 3) is driven by a hydraulic cylinder (2 2 4) to make it reciprocate to swing against the rack on the cymbal slider (2 1) (2 1 2), (2 1 3); It is necessary to use two positioning mechanisms (22) and a lifting hydraulic cylinder (23) according to Action, so that the two cymbal sliders (21), (2Γ) have to be moved up and down alternately to lift the template (2 4) mounted on one of the cymbal sliders (2 Γ); An inverse rack (2 1 5) is provided on the outside of the cymbal slider (2 1) on the column (1), and a [type clamp frame (2 6) is installed on the cymbal slider (2 1), The end of the c-shaped cool frame (26) is provided with a hook end (261) inward, which has to be hooked on the wing plate (214) of the Η-shaped slide bar (21), and the 匚 -shaped clamp frame (26). A stop at the inner pivot 第15頁 421691 1 _案號 87106646_年月日__ 六、申請專利範園 (2 6 2 ),而該擋塊(2 6 2 )得藉由一彈簧(2 6 3 )推頂,使其抵 靠在逆齒條(2 1 5 )上,又該C型爽框(2 6 )得裝設在一墊塊 (27)上,且該墊塊(27)固定在立柱(1)上,得藉由定位機 構(22)及昇降液壓缸(23)將Η形滑桿(21)向上推昇,且在 上層立柱(1 )的直線位置上裝設有複數個C型夾框(2 6 ), 而可直接將Η形滑桿(2 1 )直接推昇至上層的預設位置,而 不須拆卸Η形滑桿(2 1 ),所以得免除拆卸Η形滑桿(2 1 )的 麻煩;並得使Η形滑桿(2 1 )避開建築物之橫粱,而可便於 裝設Η形滑桿(21 ).。Page 15 421691 1 _Case No. 87106646_Year_Month__ Six. Apply for a patent garden (2 6 2), and the stopper (2 6 2) has to be ejected by a spring (2 6 3), so that It abuts on the reverse rack (2 1 5), and the C-shaped cool frame (2 6) must be installed on a pad (27), and the pad (27) is fixed on the upright (1) , The positioning slide mechanism (22) and the lifting hydraulic cylinder (23) must be used to push the cymbal slider (21) upward, and a plurality of C-shaped clamp frames (2) are installed on the linear position of the upper column (1). 6), and the cymbal slider (2 1) can be directly pushed up to the preset position on the upper floor without disassembling the cymbal slider (2 1), so the removal of the cymbal slider (2 1) is eliminated It is also necessary to avoid the cymbal slider (21) from the beams of the building, so that the cymbal slider (21) can be easily installed. 第16頁Page 16
TW87106646A 1998-04-29 1998-04-29 Wall-upward and slab-downward construction method TW421691B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW87106646A TW421691B (en) 1998-04-29 1998-04-29 Wall-upward and slab-downward construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW87106646A TW421691B (en) 1998-04-29 1998-04-29 Wall-upward and slab-downward construction method

Publications (1)

Publication Number Publication Date
TW421691B true TW421691B (en) 2001-02-11

Family

ID=21630002

Family Applications (1)

Application Number Title Priority Date Filing Date
TW87106646A TW421691B (en) 1998-04-29 1998-04-29 Wall-upward and slab-downward construction method

Country Status (1)

Country Link
TW (1) TW421691B (en)

Similar Documents

Publication Publication Date Title
CN214575640U (en) U-shaped synchronous construction formwork system for vertical and horizontal structures of cast concrete
CN111576234B (en) Safe and rapid construction method for turnover-type high pier
CN113293694B (en) Turnover formwork frame structure for efficient pier body construction and construction process
JP3013688B2 (en) Construction method of concrete structure
CN210140771U (en) Construction work platform hoisting frame of high mound of bridge
JPH10339033A (en) Concrete multistory building construction device and construction method for concrete oblique post
TW421691B (en) Wall-upward and slab-downward construction method
CN217761022U (en) Comprehensive operation trolley for construction of air cushion type surge chamber of hydropower station
CN115182269A (en) Method for assembling ultrahigh pier large-section heavy hydraulic creeping formwork in multiple times
CN105019657A (en) Building construction system
CN110409800B (en) High-precision formwork construction method for cast-in-situ bare concrete wind tunnel
CN110469126B (en) Binding trolley for concrete reinforcing steel bars and binding construction method thereof
CN2197410Y (en) Scaffolding installation
JP2874576B2 (en) Moving scaffold for retaining wall construction
CN105178602A (en) Building construction system
CN210636798U (en) Creeping formwork structure applied to vertical wall and frame column of wind tunnel corner section
CN218521829U (en) Novel caisson inner core template integrating reinforcement
CN220246891U (en) Pit forming integrated template device suitable for foundation pit
CN2459394Y (en) Construction frame for building
CN219604164U (en) Variable cross-section special-shaped steel tower crown mounting device
CN218059930U (en) Steel pipe concrete arch bridge arch rib vertical splicing hydraulic jig frame
CN215561952U (en) Integrated operation platform for binding and positioning reinforcement of turnover formwork high pier
CN213418468U (en) Device for pouring concrete into high-rise building supporting and hanging formwork
CN217810514U (en) Pier inner supporting frame capable of being used for binding pier body steel bars and being used for turnover
CN218563020U (en) A smooth creeping formwork system that is used for core section of thick bamboo to pour construction upside down

Legal Events

Date Code Title Description
GD4A Issue of patent certificate for granted invention patent
MM4A Annulment or lapse of patent due to non-payment of fees