SU969819A1 - Method of field testing of sagging soil - Google Patents

Method of field testing of sagging soil Download PDF

Info

Publication number
SU969819A1
SU969819A1 SU813278405A SU3278405A SU969819A1 SU 969819 A1 SU969819 A1 SU 969819A1 SU 813278405 A SU813278405 A SU 813278405A SU 3278405 A SU3278405 A SU 3278405A SU 969819 A1 SU969819 A1 SU 969819A1
Authority
SU
USSR - Soviet Union
Prior art keywords
column
field testing
soil
sagging
drilling
Prior art date
Application number
SU813278405A
Other languages
Russian (ru)
Inventor
Иосиф Генрихович Рабинович
Original Assignee
Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им.Н.М.Герсеванова
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им.Н.М.Герсеванова filed Critical Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им.Н.М.Герсеванова
Priority to SU813278405A priority Critical patent/SU969819A1/en
Application granted granted Critical
Publication of SU969819A1 publication Critical patent/SU969819A1/en

Links

Landscapes

  • Geophysics And Detection Of Objects (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Description

1ЛОНКОВЫМ снар дом столбика породы} на фиг. 2 - замачивание столбика и измерение его просадки.The skylight of the rock column} in FIG. 2 - soaking the column and measuring its drawdown.

Способ осуществл етс  следующим образом,.The method is carried out as follows.

Сначала осуществл ют отделение испытываемого грунта от окружающего грунта путем бурени  скважин 1 при помощи колонкового снар да, состо щего из коронки 2, предназначенной дл  выбуривани  столбика породы 3, колонковых труб 4, служащих дл  прима столбика породы и соедин емых в колонку ниппел ми 5, бурильной штанги б, соедин емой с колонковой трубой переходником 7 и приводимой во вращение буровым станком. Бурение производ т с продувкой забо  и кольцевого зазора 8 между трубами и стенками скважин сжатым воздухом (направление его движени  показано на фиг. 1 стрелками). После бурени  скважины на глубину просадочной толщи НПР с оставлением столбика породы 3 высотой Н„р в колонне колонковых труб 4 последнюю закрепл ют на .весу при помощи xoiviyTa 9 и отсоедин ю переходник 7 и бурильну штангу 6. Затем укладывают на верх столбика 3 защитную фильтрующую прокладку 10, устанавливают на верх колонны колонковых труб емкост 11 с перфорированным днищем 12 и специальными отверсти ми 13, через кото| ые пропускают марки-стержни, заглубл емые в верхнюю часть столбика породы 3, служащие дл  измерени  его просадки.First, the test soil is separated from the surrounding soil by drilling wells 1 with a coring device consisting of a crown 2, intended for drilling out rock column 3, core pipes 4, used for receiving the rock column and connecting them to the column with nipples 5, a drill rod b connected to the core pipe by an adapter 7 and driven by a drilling machine. The drilling is carried out with blowing of the bottom and annular gap 8 between the pipes and the walls of the wells with compressed air (the direction of its movement is shown in Fig. 1 by arrows). After drilling a well to the depth of the subsidence of the LPR, leaving the rock column 3 high Hf in the column of core pipes 4, the latter is fixed on the weight using xoiviyTa 9 and disconnecting adapter 7 and the drill rod 6. Then the protective filter is placed on the top of column 3 The gasket 10 is mounted on top of the column of a column pipe with a capacitance 11 with a perforated bottom 12 and special holes 13 through which | The rods mark rods, recessed into the upper part of rock column 3, are used to measure its subsidence.

Далее осуществл ют замачивание столбика породы 3, подава  воду через емкость 11 и измер   просадку его поверхности по понижению марокстержней относительно днища 12 емкости 11.Next, the rock column 3 is soaked by supplying water through the tank 11 and measuring the subsidence of its surface by lowering the rod bar relative to the bottom 12 of the tank 11.

Применение предлагаемого способа позволит по сравнению с прототипом снизить трудоемкость и стоимость испытани  просадки в 10-15 раз, а его длительность - до 3-4 сут (вместо 10-15 сут.).The application of the proposed method will allow, in comparison with the prototype, to reduce the complexity and cost of testing a drawdown by 10-15 times, and its duration - up to 3-4 days (instead of 10-15 days).

Claims (2)

1.Руководство по проектированию оснований зданий и сооружений.Изд.2, М., Стройиздат, 1978, с. 223.1. Guidelines for the design of foundations of buildings and structures. Id.2, M., Stroyizdat, 1978, p. 223. 2.Авторское свидетельство СССР по за вке 2830618/29-33,2. USSR author's certificate on application 2830618 / 29-33, кл. Е 02 D 3/10, 1979 (прототип).cl. E 02 D 3/10, 1979 (prototype). фиг.FIG. 00 фиг гfig g
SU813278405A 1981-04-14 1981-04-14 Method of field testing of sagging soil SU969819A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813278405A SU969819A1 (en) 1981-04-14 1981-04-14 Method of field testing of sagging soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813278405A SU969819A1 (en) 1981-04-14 1981-04-14 Method of field testing of sagging soil

Publications (1)

Publication Number Publication Date
SU969819A1 true SU969819A1 (en) 1982-10-30

Family

ID=20954352

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813278405A SU969819A1 (en) 1981-04-14 1981-04-14 Method of field testing of sagging soil

Country Status (1)

Country Link
SU (1) SU969819A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104820086A (en) * 2015-04-30 2015-08-05 山东科技大学 Rock stratum and ground surface subsidence simulation box type test device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104820086A (en) * 2015-04-30 2015-08-05 山东科技大学 Rock stratum and ground surface subsidence simulation box type test device

Similar Documents

Publication Publication Date Title
CN105181199B (en) A kind of side hole stress relief method of detecting earth stress
US3934658A (en) Modular underwater well platform system
CN104747184A (en) Measurement-while-drilling method and device for three-dimensional wave velocity imaging of rock mass in front of tunnel face
JP7027392B2 (en) Boring device for geological survey
SU969819A1 (en) Method of field testing of sagging soil
CN114136558A (en) Sonar seepage detection method for underground diaphragm wall of deep foundation pit near subway
NO167679C (en) OBJECTABLE OIL EQUIPMENT AND CORE SOIL FOR PRODUCING THE SAME.
CN209976468U (en) Drilling device for hydrogeological test
CN110207657B (en) Thick unconsolidated formation mining rock stratum movement and surface subsidence detection device
CN109137953B (en) Underwater rapid soil taking construction equipment
EP0039589A3 (en) Submerged buoyant offshore drilling and production tower and apparatus and method for installing same
CN113482562B (en) Covering layer core-taking touch probe test device and using method
CN216525808U (en) Monitoring system for pore pressure and inclination of soil body around constructed bridge pile
CN113917525A (en) Underground vibration field test sensor array arrangement device and working method thereof
US3275081A (en) Method of lining water wells and noncorrosive liner therefor
RU2063497C1 (en) Method for erecting foundation
CN111733813A (en) One-column one-pile manual and mechanical dry operation combined hole forming construction method
CN220377262U (en) Bridge pile foundation protects a section of thick bamboo structure under water
CN220487498U (en) Portable land exploration equipment
CN220729700U (en) Geotechnical engineering reconnaissance sampling equipment
SU773199A1 (en) Method of lowering a cased well into ground
CN210829234U (en) Along with boring sounding device with downthehole centralizer
SU802506A1 (en) Casing column of well
SU838500A1 (en) Liquid sampling device
SU1668557A1 (en) Method for erecting "wall in ground"