SU898100A1 - Power-operated filling-in partition - Google Patents
Power-operated filling-in partition Download PDFInfo
- Publication number
- SU898100A1 SU898100A1 SU802896714A SU2896714A SU898100A1 SU 898100 A1 SU898100 A1 SU 898100A1 SU 802896714 A SU802896714 A SU 802896714A SU 2896714 A SU2896714 A SU 2896714A SU 898100 A1 SU898100 A1 SU 898100A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- shield
- jumper
- roof
- soil
- jacks
- Prior art date
Links
Landscapes
- Revetment (AREA)
Description
II
Изобретение относитс к горной промышленности и может быть использовано при гидравлической закладке выработанного пространства на крутых пластах горизонтальными полосами по простиранию в восход щем пор дке .The invention relates to the mining industry and can be used in the hydraulic laying of the worked-out space on steep seams by horizontal stripes along the strike in the upstream order.
Известна закладочна перемычка, включающа щит, состо щий из двух шарнирно соединенных между собой секций, обща длина которых больще рассто ни между почвой и кровлей пласта J.The backfill liner is known, which includes a shield consisting of two sections hinged among themselves, the total length of which is longer than the distance between the soil and the roof of the seam J.
Недостатком такой перемычки вл етс отсутствие приспособлений дл механизации ее передвижки.The disadvantage of this jumper is the lack of devices for mechanizing its shifting.
Известна также механизированна закладочна перемычка, включающа щит, состо щий из двух шарнирно соединенных между собой секций, упирающихс в почву и кровлю пласта, домкраты распора и передвижки, фильтрующее полотно, при этом щит снабжен шарнирно соединенными между собойA mechanized backfill liner is also known, comprising a shield consisting of two sections hinged between each other, resting against the soil and the roof of the formation, jacks of expansion and shifting, filtering sheet, while the shield is provided with hinges connected to each other.
балками, позвол ющими передвигать щит, отступа от закладочного массива методом шагани 2 ,beams allowing the shield to be moved from the backfill array by stepping 2,
Недостатками указанной перемычки вл ютс сложность конструкции и отсутствие приспособлений дл механизированного перемещени ее вверх по восстанию пласта вдоль закладочного массива.The disadvantages of this jumper are the complexity of the design and the lack of devices for mechanized moving it up the rise of the reservoir along the filling mass.
Целью изобретени вл етс упрощение конструкции и обеспечение перемещени перемычки вверх по восстанию пласта вдоль закладочного массива .The aim of the invention is to simplify the design and ensure that the jumper moves upwards along the bed uprising along the filling mass.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU802896714A SU898100A1 (en) | 1980-02-11 | 1980-02-11 | Power-operated filling-in partition |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU802896714A SU898100A1 (en) | 1980-02-11 | 1980-02-11 | Power-operated filling-in partition |
Publications (1)
Publication Number | Publication Date |
---|---|
SU898100A1 true SU898100A1 (en) | 1982-01-15 |
Family
ID=20883855
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU802896714A SU898100A1 (en) | 1980-02-11 | 1980-02-11 | Power-operated filling-in partition |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU898100A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103161498A (en) * | 2013-03-20 | 2013-06-19 | 中国矿业大学 | Method for filling coal pillar beside roadway in steep coal seam section |
-
1980
- 1980-02-11 SU SU802896714A patent/SU898100A1/en active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103161498A (en) * | 2013-03-20 | 2013-06-19 | 中国矿业大学 | Method for filling coal pillar beside roadway in steep coal seam section |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2287060C1 (en) | Mechanized face-end support, which supports connection area between longwall face and drift | |
SU898100A1 (en) | Power-operated filling-in partition | |
GB2188661A (en) | Dams for backfilling longwall workings | |
US3969904A (en) | Method of laying a pipeline in a trench | |
SU1656134A1 (en) | Temporary face support | |
SU693028A1 (en) | Power mine roof support for mining coal and filling-up excavated space | |
SU1528326A3 (en) | Powered hydraulic support for sets of coal-winding faces | |
SU723173A1 (en) | Power roof support section | |
SU414423A1 (en) | MECHANIZED MINE MOUNT FOR EFFICIENCY OF HEAVY-DEPRESSED LAYERS | |
SU1687792A1 (en) | Section of mechanized timbering | |
RU2059827C1 (en) | Set for steeply deepen seams | |
SU924399A1 (en) | Mechanized mining roof support section | |
SU1521881A1 (en) | Power support unit | |
SU724725A1 (en) | Unit for excavating gently sloping thick coal seams | |
RU2010976C1 (en) | Powered support for thick seams | |
SU1521880A1 (en) | Base of power support unit | |
SU1543087A1 (en) | Front-loading unit | |
SU929835A1 (en) | Planer unit | |
SU750096A1 (en) | Power roof support | |
SU1028851A1 (en) | Power roof-supporting unit | |
SU875085A1 (en) | Power mine roof support | |
SU48066A1 (en) | Clearing for a clearing a slab | |
RU2069762C1 (en) | Device for connection of powered support unit with conveyer | |
SU1469156A1 (en) | Mechanized formwork for constructing safety strips | |
SU1002583A1 (en) | Method of mining thick sloping beds and mechanized unit for performing same |