Виталий Иосифович Берман
Ирина Васильевна Михайленко
Николай Иванович Ряжских
Original Assignee
Киевский Отдел Всесоюзного Научно-Исследовательского Института Гидромеханизации Санитарно-Технических И Специальных Строительных Работ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Киевский Отдел Всесоюзного Научно-Исследовательского Института Гидромеханизации Санитарно-Технических И Специальных Строительных Работ filed Critical Киевский Отдел Всесоюзного Научно-Исследовательского Института Гидромеханизации Санитарно-Технических И Специальных Строительных Работ
Priority to SU802936063A priority Critical patent/SU897963A1/en
Application granted granted Critical
Publication of SU897963A1 publication Critical patent/SU897963A1/en

Links

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Description

1one

Изобретение относитс  к строитель ству и предназначено дл  испытани  свайных фундаментов.The invention relates to construction and is intended for testing pile foundations.

Известна установка дл  статичес- кого испытани  свай, включающа  упорную балку, домкрат и захваты, взаимодействующие с анкерными сва ми, примем захваты выполнены в виде закрепленных на балке обойм с вкладышами и снабжены силовыми цилиндрами с подпружиненными штоками, сообщающимис  с рабочей полостью домкрата 1.The known installation for static testing of piles, including a thrust beam, a jack and grips interacting with anchor piles, will accept the grippers made in the form of holders with liners fixed on the beam and equipped with power cylinders with spring-loaded rods communicating with the working cavity of the jack 1.

К недостаткам этой установки относитс  сложность изготовлени  и эксплуатации гидрозахватов и отсутствие универсальности, так как детали захватов должны прилегать к поверхности анкерных свай, которые могут иметь различные геометрические параметры ..The disadvantages of this installation include the complexity of the manufacture and operation of hydraulic grippers and the lack of versatility, since the details of the grippers must lie on the surface of the anchor piles, which may have different geometrical parameters ..

Наиболее близким техническим решением к изобретению  вл етс  установка дл  статического испытани  свай,The closest technical solution to the invention is a plant for static testing of piles,

включающа  упорную балку, опертую на домкрат, установленные на концах балки через шаровые шарниры т говые приспособлени  с захватами, св занные с арматурными выступами анкерных 5 свай 2.including a thrust beam supported on a jack, mounted on the ends of the beam through ball joints, traction devices with grippers connected to reinforcing anchors of anchor 5 piles 2.

Недостатком этой установки  вл етс  ограниченна  возможность охвата арматурных выступов анкерных свай,например , если они  вл ютс  набивными сва ми, которые могут иметь более четырех арматурных выступов, а их высота может составить не более 20 см.The disadvantage of this installation is the limited possibility of covering the reinforcing protrusions of the anchor piles, for example, if they are ramming piles that can have more than four reinforcing protrusions, and their height can be no more than 20 cm.

Цель изобретени  - повышени  надежности работы и диапазона охвата.The purpose of the invention is to improve the reliability of work and the range of coverage.

Claims (2)

Поставленна  цель достигаетс  тем, что в известной установке дл  статического испытани  свай, включающей упорную балку, опертую на домкрат, установленные на концах балки через шаровые шарниры т говые приспособлени  с захватами, св занные с арматурными выступами анкерных свай, каждое т говое приспособление выполнено в виде силовой рамы с опорным диском на своем нижнем торце и снабжено трособлочной системой с верхними и нижними р дами блоков, причем верхни оси закреплены на силовой раме, а к нижним ос м блоков подвешены захваты . Каждый захват выполнен в виде обо мы с прижимными винтами и клинь ми, имеющими возможность продольно-верти кального смещени  относительно друг друга. На фиг. 1 изображена установка, общий вид; на фиг. 2 - узел I на фиг. 1 , на фиг. 3 захват, продольный разрез; на фиг. А - разрез А-Д на фиг. 3Описываема  установка дл  статического испытани  свай состоит из до крата 1, устанавливаемого на испытуемую сваю 2, упорной балки 3, на кот рую через шаровые шарниры 4 подвешены силовые рамы 5 с. опорными дисками 6, захватов 7, которые устанавливают с  на арматурных стержн х 8 анкерных свай 9, и троса 10, запасовываемого между блоками 11 захватов 7 и блоками 12 валов 13, радиально расположен ных на опорных дисках 6. Захват 7 включает в себ  корытообразную обойму 1 4 с отверстием 15 в дне Дл  пропуска арматурного стерж н  8. Внутри обоймы 1 , расположены: жестко закрепленный клин 16, продоль но смещаемый при помощи винтов 17 КЛ/1Н 18 и подпружиненные клинь  19 с насечкой 20. На оси 21 установлен блок 11 дл  троса 10 иусилительные шайбы 22. Ширина выточки блока 11 обусловлена соосностью троса 10 и ар матурных стержней 8 при их различных диаметрах. Установка работает следующим обра зом. На испытуемую сваю 2 устанавливаю домкрат 1 и монтируют упорную балку 3 с силовыми рамами 5, к которым посредством трособлочной системы подве шены захваты 7. Захваты 7 устанавливают на арматурные стержни 8 анкерных свай 9 выбирают слабину троса 1Q и закрепл ют его. При помощи винтез 17 арматурные стержни 8 предвари тельно зажимают между клинь ми 19 и начинают статическое испытание сваи. При подъеме упорной балки 3, а, следовательно , и силовых рам 5 арматурные стержни 8 заклиниваютс  между клинь ми 19, воспринима  равную нагрузку , котора  передаётс  при помощи трособлочной системы от упорной балки 3. После проведени  испытани  винты 17 привод т в исходное положение , и при помощи ударов по обойме 1 освобождают арматурные стержни 8. Установка захвата на каждый стержень позвол ет использовать любые анкерные системы, что особенно важно, когда они изготавливаютс  не в заводских услови х, а на месте. При достаточно частом расположении валов на опорных дисках и соответствующих их длинах одну и ту же конструкцию можно использовать дл  анкерных свай различных диаметров с различными диаметрами арматурных стержней. Распределение усилий между арматурными стержн ми анкерных свай при помощи тросоОпочной системы повышает надежность установки , так как величина их одинакова дл  всех стержней даже при их различных искривлени х. Формула изобретени  1.Установка дл  статического испытани  свай, включающа  упорную балку , опертую на домкрат, установленные на концах балки через шаровые шарниры т говые приспособлени  с захватами, св занные с арматурными выступами анкерных свай, отличающа с  тем, что, с целью повышени  надежности работы, каждое т говое присдособление выполнено в виде силовой рамы с опорным диском на своем нижнем торце и снабжено трособлочной системой с верхними и нижними р дами блоков , причем верхние оси блоков закреплены на силовой раме, а к нижним ос м блоков подвешены Захваты. 2.Установка по п. 1, отличающа с  тем, что каждый захват выполнен в виде обоймы с прижимными винтами и клинь ми, имеющими возможность продольно-вертикального смещени  относительно друг друга. Источники информации, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР № 690128, кл. Е 02 D 33/00, 1978. This goal is achieved by the fact that in a known installation for static testing of piles, including a thrust beam supported on a jack, mounted on the ends of the beam through ball joints, the pull fittings with grippers connected to the reinforcing protrusions of the anchor pile are each made in the form the power frame with a bearing disc at its lower end is equipped with a cable-blocking system with upper and lower rows of blocks, with the upper axles fixed on the power frame, and the grips are suspended from the lower axes of the blocks. Each grip is made in the form of an obama with clamping screws and wedges having the possibility of a longitudinal-vertical displacement relative to each other. FIG. 1 shows the installation, general view; in fig. 2 — node I in FIG. 1, in FIG. 3 grip, longitudinal section; in fig. A — section A – D in FIG. 3 The described installation for static testing of piles consists of up to crater 1, mounted on the test pile 2, thrust beam 3, on which the power frames are suspended for 5 seconds. bearing discs 6, grippers 7, which are mounted with on reinforcing rods x 8 anchor piles 9, and cable 10, stored between blocks 11 of grippers 7 and blocks of 12 shafts 13, radially located on supporting disks 6. Gripper 7 includes a trough-shaped holder 1 4 with a hole 15 in the bottom for passing the reinforcing bar 8. Inside the cage 1, there are: a fixed wedge 16, longitudinally displaced with screws 17 CL / 1H 18 and a spring-loaded wedge 19 with a notch 20. On the axis 21 a block 11 is installed for cable 10 and force washers 22. Block undercut width 11 is due to the alignment of the cable 10 and the armature rods 8 with their different diameters. The installation works as follows. I install a jack 1 on the test pile 2 and mount the thrust beam 3 with the power frames 5, to which the grippers 7 are suspended by means of the cable block system. The grippers 7 are mounted on the reinforcing rods 8 of the anchor piles 9 to choose the slack of the cable 1Q and fix it. With the help of the screw 17, the reinforcement bars 8 are preliminarily clamped between the wedges 19 and the static test of the pile is started. When lifting the support beam 3, and, consequently, of the power frames 5, the reinforcing bars 8 are wedged between the wedges 19, perceived equal load, which is transferred by means of the cable block system from the support beam 3. After the testing, the screws 17 are brought to the initial position, and by means of strikes on the yoke 1, the reinforcing bars 8 are released. The installation of the gripper on each rod allows the use of any anchor systems, which is especially important when they are made not in factory conditions, but on site. With a sufficiently frequent arrangement of the shafts on the bearing discs and the corresponding lengths of them, the same construction can be used for anchor piles of different diameters with different diameters of reinforcing bars. The distribution of forces between the reinforcing rods of anchor piles using a trunnion system increases the reliability of the installation, since their size is the same for all the rods, even with their different curvatures. Claim 1. An installation for static testing of piles, including a thrust beam supported on a jack, mounted at the ends of the beam through ball joints, traction devices with grippers associated with rebar anchors of the anchor piles, characterized in that, in order to improve reliability Each traction device is made in the form of a power frame with a supporting disc at its lower end and is equipped with a cable-block system with upper and lower rows of blocks, with the upper axes of the blocks fixed to the power frame, and to the lower m Grips axes suspended blocks. 2. The installation according to claim 1, characterized in that each gripper is made in the form of a cage with clamping screws and wedges having the possibility of a longitudinal-vertical displacement relative to each other. Sources of information taken into account in the examination 1. USSR author's certificate number 690128, cl. E 02 D 33/00, 1978. 2.Авторское свидетельство СССР по за вке № 2760975/29-33, кл. Е 02 D 33/00, 1979.2. USSR author's certificate for application number 2760975 / 29-33, cl. E 02 D 33/00, 1979. Т T
SU802936063A 1980-05-30 1980-05-30 Device for static testing of piles SU897963A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802936063A SU897963A1 (en) 1980-05-30 1980-05-30 Device for static testing of piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802936063A SU897963A1 (en) 1980-05-30 1980-05-30 Device for static testing of piles

Publications (1)

Publication Number Publication Date
SU897963A1 true SU897963A1 (en) 1982-01-15

Family

ID=20900288

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802936063A SU897963A1 (en) 1980-05-30 1980-05-30 Device for static testing of piles

Country Status (1)

Country Link
SU (1) SU897963A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5505561A (en) * 1994-01-18 1996-04-09 Perma Pile Foundation Restoration Systems, Inc. Self-piloting compressible piling
CN114319425A (en) * 2022-01-17 2022-04-12 中铁二十二局集团第一工程有限公司 Newly-built sheet pile wall-existing cantilever retaining wall embankment group wide combination retaining structure
CN115094964A (en) * 2022-08-11 2022-09-23 西南交通大学 Pile foundation uplift test device and method adopting assembled jack

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5505561A (en) * 1994-01-18 1996-04-09 Perma Pile Foundation Restoration Systems, Inc. Self-piloting compressible piling
CN114319425A (en) * 2022-01-17 2022-04-12 中铁二十二局集团第一工程有限公司 Newly-built sheet pile wall-existing cantilever retaining wall embankment group wide combination retaining structure
CN115094964A (en) * 2022-08-11 2022-09-23 西南交通大学 Pile foundation uplift test device and method adopting assembled jack

Similar Documents

Publication Publication Date Title
US5653556A (en) Clamping apparatus and methods for driving caissons into the earth
US5492437A (en) Self-aligning devices and methods for lifting and securing structures
CN113562629B (en) Lattice column positioning and verticality adjusting system
KR20180035427A (en) Apparatus for pile load test
CN110726615A (en) Loading device suitable for T-shaped beam column node test and using method thereof
SU897963A1 (en) Device for static testing of piles
CN115724331A (en) Prefabricated box girder hoisting device and rapid construction method
SU861476A1 (en) Method of testing piles by static load
KR20190055960A (en) Apparatus for pile load test
JP2001348816A (en) Installing method and device of precast segment overhanging installing bridge
KR102280432B1 (en) Variable steel girder structure for deflection prevention
JP2948545B2 (en) Loading test equipment
CN211922331U (en) Hanging beam formed by splicing prefabricated No. 1 box beam with small curvature radius and cast-in-place No. 0 box beam in hanging mode
CN111335188B (en) Hanging beam for prefabricating No. 1 box beam with small curvature radius and hanging and splicing cast-in-situ No. 0 box beam
CN209837123U (en) Pile foundation static load test device
CN211013830U (en) Be applicable to experimental loading device of T font beam column node
CN210368674U (en) Bridge cantilever pouring construction device based on inclined pull buckle hanging
CN109838087B (en) Reusable assembled building supporting device
CN209837671U (en) Repeatedly-usable assembled building supporting device
KR20170121523A (en) Apparatus for pile load test
CN112942109A (en) Method for mounting main cable saddle of single-tower self-anchored suspension bridge
US3055090A (en) Apparatus for bridge construction
JPS63197736A (en) Pin connection method of pc beam
CN214224752U (en) Clamp for simulation experiment of PHC tubular pile piling process