SU755569A1 - Plant for producing reinforced concrete articles in cassette-type moulds - Google Patents
Plant for producing reinforced concrete articles in cassette-type moulds Download PDFInfo
- Publication number
- SU755569A1 SU755569A1 SU782636153A SU2636153A SU755569A1 SU 755569 A1 SU755569 A1 SU 755569A1 SU 782636153 A SU782636153 A SU 782636153A SU 2636153 A SU2636153 A SU 2636153A SU 755569 A1 SU755569 A1 SU 755569A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- wall
- guides
- reinforced concrete
- cassette
- plant
- Prior art date
Links
Landscapes
- Moulds, Cores, Or Mandrels (AREA)
Description
Изобретение относится к изготовлению железобетонных изделий в кассетных формах.The invention relates to the manufacture of concrete products in cassette forms.
Известны установки, содержащие опорную раму, разделительные перегородки на опорных системах, бортоснастку с расходными конусами, виброустройства и механизмы перемещения [1].Installations are known that contain a support frame, dividing partitions on support systems, airborne equipment with feed cones, vibration devices, and displacement mechanisms [1].
Наиболее близким решением из известных является установка, содержащая раму с направляющими для перемещения посредством привода формовочно-тепловых стенок, механизм их сборки, формовочное устройство, механизм распалубки, чистки и смазки отсеков, устройство для укладки арматурных каркасов и кантователи для поворота вертикальных тепловых стенок в горизонтальное положение и обратно [2].The closest known solution is an installation comprising a frame with guides for moving by means of a drive of the molding-thermal walls, an assembly mechanism, a molding device, a stripping mechanism, cleaning and lubricating the compartments, a device for laying reinforcement cages and tilters for turning the vertical thermal walls into a horizontal position and back [2].
Недостатки известных установок состоят в необходимости иметь дополнительные площади для размещения кантователей и путей возврата тепловых отсеков.The disadvantages of the known installations are the need to have additional space to accommodate tilters and ways to return the thermal compartments.
Цель изобретения — сокращение производственных площадей, необходимых для размещения установки.The purpose of the invention is to reduce the production space required for the installation of the installation.
Эта цель достигается тем, что установка для изготовления железобетонных изде2This goal is achieved by the fact that the installation for the manufacture of reinforced concrete products
лий в кассетных формах, содержащая опорную раму с параллельно расположенными балками с направляющими, тепловые стенки с опорными катками и замками, механизмы перемещения и кантования тепловых стенок, запирания и открывания замков, бетоноукладчик с приводом вертикальных перемещений, снабжен дополнительными балками, расположенными в верхней части рамы над накатом тепловых стенок, а механизм кантования выполнен в виде у-образЮ ных наклонных направляющих с парой подпружиненных шарнирно соединенных рычагов, каждый из которых имеет на одном конце шарнирную защелку.in cassette forms, containing a support frame with parallel beams with guides, thermal walls with support rollers and locks, mechanisms for moving and tilting thermal walls, locking and opening locks, a concrete paver with a drive of vertical movements, is equipped with additional beams located in the upper part of the frame over the thermal walls, and the tilting mechanism is made in the form of y-shaped inclined guides with a pair of spring-loaded articulated levers, each of which has m end hinge latch.
На фиг. 1 изображен общий вид уста15 новки; на фиг. 2 — узел I; на фиг. 3 — вид А; на фиг. 4 — узел II.FIG. 1 shows a general view of the mouth of the 15 ; in fig. 2 - node I; in fig. 3 - view A; in fig. 4 - node II.
Установка включает раму 1, выполненную в виде пространственной металлоконЯ струкции с верхней и нижней балками 2, на которых смонтированы направляющие 3 и балки 4, на которых смонтированы направляющие 5 и 6. По торцам смонтированы кантователи 7 и 8.The installation includes a frame 1, made in the form of a spatial metal structure with upper and lower beams 2, on which guides 3 and beams 4 are mounted, on which guides 5 and 6 are mounted. On the ends, tilters 7 and 8 are mounted.
755569755569
33
Установка снабжена формовочно-тепловыми стенками 9, выполненными е катками К) и замковыми механизмами 11. На направляющих 6 установлена самоходная машина 12 чистки и смазки формовочных поверхностей стенок 9. На раме 13 смой ί ш.ювнн бункер 14 с возможностью подъема-опускания посредством привода 15. На раме 1. в соответствии с расположением замковых механизмов 11, размещены попарно механизмы 16 запирания замков 11 и механизмы 17 открывания этих замков. Между балками 4 смонтирован транспортный механизм в виде шагового толкателя 18. Он выполнен в виде подвижных возвратнопоступательных штанг с утапливающимися упорами, взаимодействующими с торцами стенок 9. Кроме того, на раме 1 смонтированы механизмы подачи 19 и механизм распалубки 20.The installation is equipped with heat-forming walls 9, made by rollers K) and locking mechanisms 11. On the guides 6 a self-propelled machine 12 for cleaning and lubricating the molding surfaces of the walls 9 is installed. On the frame 13, smoy ί sh. 15. On the frame 1. in accordance with the location of the locking mechanisms 11, arranged in pairs are mechanisms 16 for locking locks 11 and mechanisms 17 for opening these locks. Between the beams 4, a transport mechanism is mounted in the form of a step plunger 18. It is made in the form of movable reciprocating rods with retractable supports interacting with the ends of the walls 9. In addition, the feed mechanisms 19 and the form-removal mechanism 20 are mounted on the frame 1.
Механизм кантования 7 состоит из двух направляющих 21, внутри которых расположены винты 22 и захватные головки 23. выполненные в виде гайки, навинченной на винт 22, и направляющих 24 с механизмом блокировки, выполненным в виде качающегося двуплечевого рычага 25, приводимого силовым цилиндром 26. Привод винта 22 во вращательное движение осуществляется от редуктора 27, с выходным валом которого винт 22 соединен муфтой.The tilting mechanism 7 consists of two guides 21, inside which are located the screws 22 and gripping heads 23. made in the form of a nut, screwed onto the screw 22, and guides 24 with a locking mechanism, made in the form of a swinging double-arm lever 25, driven by a power cylinder 26. Drive screw 22 in the rotational movement is carried out from the gearbox 27, with the output shaft of which the screw 22 is connected by a coupling.
Направляющая 21 соединена в своей верхней части с направляющей 5 балки 4, а в нижней части с направляющей 3 нижней балки 2.The guide 21 is connected in its upper part with the guide 5 of the beam 4, and in the lower part with the guide 3 of the lower beam 2.
Каждая из захватных головок 23 снабжена защелкой 28, связанной с подпружиненным рычагом 29 шарнирно рычажной системы, образованной рычагом 29, тягой 30, рычагом 31 и пружиной 32. На направляющей 21 закреплен упор 33.Each of the gripping heads 23 is provided with a latch 28 connected with a spring-loaded lever 29 of an articulated lever system formed by the lever 29, the plunger 30, the lever 31 and the spring 32. A stop 33 is fixed on the guide 21.
Работает установка следующим образом.The installation works as follows.
Скантованная в горизонтальное положение кантователем 7 стенка 9 устанавливается на направляющих 5, по которым она проталкивается с заданным шагом в направлении к кантователю 8 шаговым толкателем 18. В процессе проталкивания формовочная полость каждой стенки 9 подвергается чистке и смазке, осуществляемой машиной 12 и заряжается арматурой. В процессе проталкивания катки 10 стенок 9 попадают в направляющие кантователя 8, который производит кантование стенки 9 в вертикальное положение. После этого стенка 9 захватывается захватным органом механизма подачи 19, который прижимает стенку 9 к пакету, ранее собранному из стенки 9. При прижиме к пакету стенок замковые механизмы 11 стенки 9 сочленяются с замковыми механизмами ранее присоединенной к пакету предыдущей стенки 9. После остановки всего пакета механизм запирания 16 производит стяжку стенки 9 с ранее собранным пакетом стенок, после чего формовоч4Horizontal wall tangent 7 wall 9 is installed on the guides 5, along which it is pushed with a given step in the direction to tilter 8 step pusher 18. During the pushing process, the molding cavity of each wall 9 is cleaned and lubricated by the machine 12 and charged with reinforcement. In the process of pushing rollers 10 walls 9 fall into the guides tilter 8, which produces the tilting of the wall 9 in a vertical position. After this, the wall 9 is captured by the gripping body of the feed mechanism 19, which presses the wall 9 to the bag previously assembled from the wall 9. When the wall is pressed to the bag, the locking mechanisms 11 of the wall 9 are articulated with the locking mechanisms of the previous wall 9 previously attached to the bag. the locking mechanism 16 produces a wall tie 9 with a previously assembled package of walls, followed by a mold
ная полость стенки 9 бетонируется посредством подъемно-опускного бетоноукладчика 14.Naya cavity of the wall 9 is concreted by means of a lifting paver 14.
По окончании формовки бетоноукладчик 14 поднимается в крайнее верхнее положение для пропуска к кантователю 8 очередной стенки 9, заряженной арматурой.At the end of the molding, the paver 14 rises to the extreme upper position to pass to the tilter 8 of the next wall 9, loaded with reinforcement.
После бетонирования стенка 9 подключается к теплоносителю (пару) и производится тепловая обработка заформоваиного изделия. Тепловая обработка производится до момента, пока стенка 9 не подойдет к посту распалубки, расположенному перед кантователем 7. На посту распалубки стенка 9 посредством механизма 17 открывания замков 11 выводится из зацепления с пакетом стенок и отключается от теплоносителя (пара) и производится распалубка изделия, после чего стенка 9 кантуется кантователем 7 из вертикального положения в горизонтальное и устанавливается на направляющих 5.After concreting, the wall 9 is connected to the coolant (steam) and the heat treatment of the molded product is performed. The heat treatment is performed until the wall 9 reaches the dismantling post located in front of the tilter 7. At the dismantling post, the wall 9 is disengaged from the wall package through the mechanism 17 for opening the locks 11 and disconnected from the heat carrier (pair) and the product is disassembled, after of which the wall 9 is turned over by the tilter 7 from the vertical position to the horizontal one and is mounted on the guides 5.
Кантование стенки 9 на кантователе 7 происходит следующим образом. После отрыва стенки 9 от пакета, последняя механизмом распалубки 20 подводится к кантователю 7, при этом нижние катки вертикально расположенной стенки 9 нажимают на защелки 28 и закатываются на опорные поверхности захватных головок 23, расположенные внутри направляющей 21, а верхние катки — в паз направляющей 24. В этот момент нижние плечи рычагов 25 находятся в откинутом . положении, обеспечивающем свободный проход верхних катков в паз направляющей 24. После захода верхних катков стенки 9 в паз направляющей 24 механизмы блокировки переводят рычаги 25 в положение, при котором нижние концы рычагов 25 перекрывают пазы направляющих 24, а верхние концы рычагов 25 выходят из паза направляющей 24. После этого включается привод вращения винтов 22, в результате чего захватные головки 23, перемещаясь вдоль винтов 22, увлекают за собой катки, находящиеся с ними в зацеплении, а другие катки стенки 9 в это время перемещаются внутри паза направляющей 24, и выходят на опорную поверхность направляющих 5. После того, как на этот же уровень выйдут и катки, находящиеся в зацеплении с захватными головками 23, упор 33 опустит защелки 28 до уровня опорной поверхности захватных головок 23, а механизм блокировки переведет рычаги 25 в положение, при котором верхние концы его перекрывают пазы направляющих 24 и создают опору для катков, бывших в зацеплении с головками 23. После этого шаговый толкатель 18 перемещает стен ку 9, окантованную в горизонтальное положение на подготовительные технологические посты, т. е. цикл работы установки повторяется. Работа кантователя 8 происходит в обратном порядке по отношению к работеThe tilting of the wall 9 on the tilter 7 is as follows. After separation of the wall 9 from the package, the latter mechanism of stripping 20 is fed to the tilter 7, while the lower rollers of the vertically positioned wall 9 press the latches 28 and roll onto the supporting surfaces of the gripping heads 23 located inside the guide 21, and the upper rollers - into the groove of the guide 24 At this moment, the lower shoulders of the levers 25 are in the folded back. a position allowing free passage of the upper rollers to the groove of the guide 24. After the upper rollers of the wall 9 enter the groove of the guide 24, the locking mechanisms move the levers 25 to a position in which the lower ends of the levers 25 overlap the slots of the guides 24 and the upper ends of the levers 25 exit the slot of the guide 24. After that, the rotational drive of the screws 22 is turned on, as a result of which the gripping heads 23, moving along the screws 22, carry along the rollers which are engaged with them, and the other rollers of the wall 9 at this time move inside As a guide 24, and go to the support surface of the guide 5. After the rollers are engaged with the gripping heads 23, the stop 33 lowers the latches 28 to the level of the supporting surfaces of the gripping heads 23, and the locking mechanism will move the levers 25 into a position in which its upper ends overlap the grooves of the guides 24 and create support for the rollers that were engaged with the heads 23. After that, the step plunger 18 moves the wall 9, edged in a horizontal position to the preparatory technologies -meteorological positions, ie. e. the installation work cycle is repeated. The work of the tilter 8 is in reverse order with respect to the work
ί ю69ί Ю69
5five
кантователя 7, поскольку кантователь 8 переводит стенки 9 из горизонтального положения в вертикальное.tilter 7, because tilter 8 translates the wall 9 from a horizontal position to a vertical one.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU782636153A SU755569A1 (en) | 1978-06-21 | 1978-06-21 | Plant for producing reinforced concrete articles in cassette-type moulds |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU782636153A SU755569A1 (en) | 1978-06-21 | 1978-06-21 | Plant for producing reinforced concrete articles in cassette-type moulds |
Publications (1)
Publication Number | Publication Date |
---|---|
SU755569A1 true SU755569A1 (en) | 1980-08-15 |
Family
ID=20773383
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU782636153A SU755569A1 (en) | 1978-06-21 | 1978-06-21 | Plant for producing reinforced concrete articles in cassette-type moulds |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU755569A1 (en) |
-
1978
- 1978-06-21 SU SU782636153A patent/SU755569A1/en active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4252292A (en) | Apparatus and method for molding the exterior of building modules | |
SU755569A1 (en) | Plant for producing reinforced concrete articles in cassette-type moulds | |
US5569472A (en) | Continuously-operating chilling cabinet for treating a mass contained in molds | |
SU971081A3 (en) | Apparatus for producing prestressed reinforced concrete products | |
US4252291A (en) | Apparatus and method for molding building modules | |
SU727448A1 (en) | Multiple mould unit | |
SU1694375A2 (en) | Cassette line | |
US3465396A (en) | Plant for manufacturing large slabshaped constructional elements | |
SU1418049A1 (en) | Station for dismantling forms of conveyer line with multiple moulds for manufacturing ferroconcrete articles | |
SU1207775A1 (en) | Horizontal closed conveyer line for vertical moulding of concrete articles | |
CN221498651U (en) | Fresh packaging equipment for prefabricated vegetable lock | |
SU863363A1 (en) | Plant for making ferroconcrete articles in multiple moulds | |
SU1101352A1 (en) | Multiple mould for ferroconcrete articles | |
SU1673451A1 (en) | Rotary-table machine for manufacturing gypsum products | |
SU1214427A1 (en) | Installation for simultaneous manufacturing of several concrete articles | |
SU1219371A1 (en) | Arrangement for producing reinforced concrete articles in multiseat moulds | |
SU1756153A1 (en) | Installation for extruding building products | |
RU1808715C (en) | Moulding press for manufacture of products in large-sized remote moulds | |
SU921857A1 (en) | Apparatus for locking heat walls of magazine unit | |
SU1234310A1 (en) | Step motion conveyer | |
SU411992A1 (en) | ||
SU1438914A1 (en) | Arrangement for dispensing ingots from vertical machine of semi-continuous casting | |
SU916085A1 (en) | Automatic moulding unit | |
SU1646870A1 (en) | Rotary conveyor for production of concrete articles | |
SU614950A1 (en) | Conveyer production line for making reinforced-concrete articles |