SU63656A1 - Device of reinforced concrete pile support - Google Patents

Device of reinforced concrete pile support

Info

Publication number
SU63656A1
SU63656A1 SU532A SU532A SU63656A1 SU 63656 A1 SU63656 A1 SU 63656A1 SU 532 A SU532 A SU 532A SU 532 A SU532 A SU 532A SU 63656 A1 SU63656 A1 SU 63656A1
Authority
SU
USSR - Soviet Union
Prior art keywords
pile
beams
reinforced concrete
nests
piles
Prior art date
Application number
SU532A
Other languages
Russian (ru)
Other versions
SU4325A1 (en
Inventor
А.М. Крюков
Original Assignee
А.М. Крюков
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application granted granted Critical
Publication of SU4325A1 publication Critical patent/SU4325A1/en
Application filed by А.М. Крюков filed Critical А.М. Крюков
Priority to SU532A priority Critical patent/SU63656A1/en
Publication of SU63656A1 publication Critical patent/SU63656A1/en

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

Сборные железобетонные свайные опоры не получили распространени  в силу того, что все примен вшиес  конструкции требовали большой точности выполнени  свайных работ как в отношении рассто ни  между сва ми в плане, так и в части расположени  голов забитых свай на одной высотной отметке. Поэтому, как правило, после бойки свай по вл лась необходимость в обработке их голов. Эта обработка заключаетс  либо в разрушении голов излишне длинных свай, либо в нарашивании коротких. Последн   операци   вл етс  чрезвычайно трудоёмкой, так как дл  нарашивани  сваи необходимо разбить её голову с тем, чтобы обнажить арматуру сваи, а затем установить арматуру и опалубку нарашиваемого участка; только после этого можно производить укладку бетона. Поскольку в строительной практике почти не бывает случаев, когда головы всех забитых железобетонных свай располагаютс  на одной отметке, то такие работы встречаютс  как правило. Это настолько снижает эффект, получаемый от применени  имеюшихс  конструкций сборных свайных опор из железобетона, чтоPrefabricated reinforced concrete pile supports did not become widespread due to the fact that all applied constructions required a high accuracy of the performance of pile works both in terms of the distance between the pile in the plan and in terms of the location of the heads of the driven piles at the same height. Therefore, as a rule, after the strikers of the piles, it was necessary to process their heads. This treatment consists either in breaking the heads of unnecessarily long piles, or in cutting short ones. The latter operation is extremely time-consuming, since in order to make a pile it is necessary to break its head in order to expose the pile reinforcement and then install the reinforcement and formwork of the overgrown area; only then can concrete be laid. Since there are almost no cases in the construction practice when the heads of all blocked reinforced concrete piles are located at the same mark, such works are usually encountered. This reduces the effect of the use of existing structures of precast reinforced concrete pile supports to such an extent that

изготовление насадки на месте считаетс  более целесообразным.making the attachment on site is considered more appropriate.

Изобретение имеет целью исключить выше отмеченные недостатки и заключаетс  в следуюшем.The invention aims to eliminate the above noted drawbacks and is as follows.

Б железобетонных балках (насадках ), соедин юших головы свай, сделаны гнёзда с заплечиками в верхней их части; этими гнёздами балки надеваютс  на головы свай, после чего гнёзда заливаютс  бетоном.In reinforced concrete beams (nozzles), connecting the heads of the piles, nests with shoulders in the upper part of them were made; With these nests, the beams are put on the heads of the piles, after which the nests are poured with concrete.

Таким образом предложенна  опора будет обладать достоинствами сборной конструкции, обе печива  в то же врем  монолитность, благодар  заливке гнёзд бетоном.Thus, the proposed support will have the advantages of a prefabricated structure, both furnaces being solid at the same time, thanks to the filling of nests with concrete.

На чертеже фиг. 1 изображает примерную форму выполнени  предложенного устройства применительно к промежуточным опорам мостов (внешний вид); фиг. 2 и 3 - разрез по I-I и II-II на фиг. 1; фиг. 4- продольный вертикальный разрез по опоре; фиг. 5 - балку (насадку) в аксонометрии; фиг. 6 - боковой вид балки с частичным разрезом; фиг. 7 - балку в плане.In FIG. 1 depicts an exemplary form of the implementation of the proposed device in relation to the intermediate supports of bridges (external appearance); FIG. 2 and 3 is a section along I-I and II-II in FIG. one; FIG. 4 is a longitudinal vertical section along the support; FIG. 5 - beam (nozzle) in axonometry; FIG. 6 is a side view of a beam with a partial cut; FIG. 7 - beam in the plan.

Свайна  опора, изображённа  на чертеже, состоит из свай 1 и коробчатой насадки 2. Железобетонные сваи дл  экономии материала , а также дл  облегчени  весаThe pile support shown in the drawing consists of piles 1 and a box-shaped attachment 2. Reinforced concrete piles to save material and also to lighten the weight

и удобства погружени  с помощью р.одмыва делаютс  трубчатыми. Их можно изготовл ть центробежным путём, что обусловливает большую прочность и даёт возможность изготовить сваи большого диаметра и малой толш,ины. Насадка по длине составл етс  из двух совершенно одинаковых по устройству коробчатых балок П-образного сечени . Разделение насадки на две пасти даёт возможность при установке её создать поперечный уклон путём соответствующего наклона каждой половины. В балках сделаны поперечные перегородки (диафрагмы) 3. Кажда  пара диафрагм вместе со стенками балки образует гнездо, в которое при установке насадок входит голова сиаи. Размеры гнезда в плане назначены с таким расчётом, чтобы сборка опоры была возможна при отклонении сваи от вертикали в любую сторону. Горизонтальна  полка балки в пределах гнёзд имеет отверсти  4 дл  подачи бетона, с помощью которого осуществл етс  заделка головы сваи. Размеры этого отверсти  прин ты несколько меньше размеров гнезда, благодар  чему в верхней части гнезда получаютс  заплечики, которыми балка может опиратьс  на голову сваи. В тех случа х, когда головы свай наход тс  на различных уровн х, касадка устанавливаетс  в проектное положение с помощью бетонных прокладок, устанавливаемых между головами сваи и заплечиками гнёзд. Прокладки выполн ютс  в виде колец 5 или брусков 6.and ease of immersion with the help of the rinsing pipe is made tubular. They can be manufactured by centrifugal means, which makes them more durable and makes it possible to manufacture piles of large diameter and small thickness, as well. The nozzle is made up of two absolutely identical in shape box-shaped girders with a U-shaped cross section. The division of the nozzle into two mouths makes it possible, when installed, to create a cross slope by appropriately tilting each half. In the beams, transverse partitions (diaphragms) are made 3. Each pair of diaphragms together with the walls of the beam forms a nest into which, when installing the nozzles, the head of a Siai enters. The dimensions of the nest in the plan are assigned in such a way that the support assembly would be possible if the pile is deviated from the vertical in any direction. The horizontal flange of the beam within the nests has openings 4 for supplying concrete, by means of which the pile head is embedded. The dimensions of this hole are slightly smaller than the dimensions of the socket, so that in the upper part of the socket there are shoulders with which the beam can rest on the pile head. In those cases when the heads of the piles are at different levels, the cascade is installed in the design position with the help of concrete pads installed between the heads of the pile and the shoulders of the sockets. The gaskets are made in the form of rings 5 or bars 6.

После выверки положени  насадок, оставшеес  снизу отверстие между сваей и стенками гнезда закрываетс  металлической инвентарной опалубкой и отсек сверху заполн етс  бетоном. Если не закрыть отверстие сваи сверху, то при бетонировании вс  сва  будет заполнена бетоном. Во избежание этого, отверстие в свае закрываетс  бетонным кружком 7, который опускаетс  на 40-50 см чиже насадки и поддерживаетс  ароволокой, имеющей на концах крючки, которые опираютс  наAfter aligning the position of the nozzles, the bottom of the hole between the pile and the walls of the nest is closed with metal inventory formwork and the compartment on top is filled with concrete. If you do not close the hole of the pile from above, then during concreting the whole pile will be filled with concrete. To avoid this, the hole in the pile is covered with a concrete circle 7, which is lowered 40-50 cm below the nozzle and supported by a long arm having hooks on the ends that rest on

торец сваи. До заполнени  внутренней части сваи бетоном, во избежание утечки цементного молока, на установленный бетонный кружок следует насыпать слой песка в 3- 5 см. Половинки насадок соедин ютс  на средней свае. Здесь дл  бо.чее прочного соединени  в стыкуемый отсек укладываетс  арматура.butt pile. Before filling the inside of the pile with concrete, in order to avoid cement milk leakage, a 3–5 cm layer of sand should be poured onto the mounted concrete circle. The halves of the nozzles are connected on the middle pile. Here, for a stronger connection, fittings are laid in the docked compartment.

Благодар  значительной высоте насадок и прин тому способу соединени  их со сва ми, при разнице в высоте голов свай до 50- 60 см, сборку опоры можно производить без каких-либо дополнительных работ. В тех случа х, когда разница превышает указанный предел, необходимы дополнительные работы по наращиванию или укорочению свай.Due to the considerable height of the nozzles and the method of joining them with their own, with the difference in height of pile heads up to 50-60 cm, the support can be assembled without any additional work. In cases where the difference exceeds the specified limit, additional work is needed to increase or shorten the piles.

Оба вида работ выполн ютс  до установки насадки. Наращивание свай производитс  путём установки на короткую сваю отрезка сваи необходимой длины и сращивани  его с новой сваей, путём устройства внутренней железобетонной пробки в месте их стыка.Both types of work are performed prior to installation of the nozzle. Pile buildup is carried out by installing a piece of pile of the required length on a short pile and splicing it with a new pile, by arranging an internal reinforced concrete plug in the place of their joint.

Укорачивание сваи производитс  путём разрушени  излишней высоты сваи. Следует отметить, что опасени  о повреждении нижних слоев бетона при разрушении головы сваи не  вл ютс  существенными, благодар  значительной длине заделки сваи в насадку.The shortening of the pile is done by destroying the excessive height of the pile. It should be noted that fears of damage to the lower layers of concrete during the destruction of the pile head are not significant, due to the considerable length of embedding the pile into the nozzle.

Предмет изобретени Subject invention

Claims (2)

1.Устройство железобетонных свайных опор с применением балок (насадок), св зывающих сваи, отличающеес  тем, что балки (насадки) имеют сквозные гнёзда с заплечиками в верхней части их, с целью жёсткого соединени  балок со сва ми, путём надевани  балок своими гнёздами на головы свай и последующей заливки гнёзд бетоном .1. A device of reinforced concrete pile supports with the use of beams (nozzles), connecting piles, characterized in that the beams (nozzles) have through nests with shoulders in the upper part of them, with the aim of rigid joining of beams with their own, by putting beams on their nests heads of piles and the subsequent filling of nests with concrete. 2.Форма выполнени  устройства по п. 1, отличающа с  тем, что балки (насадки) имеют П-образное поперечное сечение с поперечными перегородками 3, образующими гнёзда.2. The form of the device according to claim 1, characterized in that the beams (nozzles) have a U-shaped cross-section with transverse partitions 3 forming nests. Фиг. 1FIG. one III I I IIII I I I NJ4 1О-iwJNJ4 1O-iwJ Фиг. 4FIG. four jjlUt jjlUt г /g / Фиг. 2 Фиг. 3FIG. 2 FIG. 3 inin Фиг. 5FIG. five л/l /
SU532A 1941-03-31 1941-03-31 Device of reinforced concrete pile support SU63656A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU532A SU63656A1 (en) 1941-03-31 1941-03-31 Device of reinforced concrete pile support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU532A SU63656A1 (en) 1941-03-31 1941-03-31 Device of reinforced concrete pile support

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
SU43491 Addition

Publications (2)

Publication Number Publication Date
SU4325A1 SU4325A1 (en) 1928-01-31
SU63656A1 true SU63656A1 (en) 1943-11-30

Family

ID=48244555

Family Applications (1)

Application Number Title Priority Date Filing Date
SU532A SU63656A1 (en) 1941-03-31 1941-03-31 Device of reinforced concrete pile support

Country Status (1)

Country Link
SU (1) SU63656A1 (en)

Similar Documents

Publication Publication Date Title
US20200190799A1 (en) Prefabricated frame
US2618146A (en) Reinforced concrete column, bracket, and beam joint
CN108951869B (en) Low-rise fully-assembled concrete shear wall structure system
JPS6346820B2 (en)
CN106284655A (en) Precast concrete beam stud connects node and method of attachment in succession
US2556878A (en) Fireproofed flanged structural member and a precast shoe therefor
CN113529956A (en) Shear wall box type assembly type building structure and construction method thereof
US2295216A (en) Building construction
US3546830A (en) Prefabricated reinforced concrete flooring slabs and floors as thus formed
KR101541465B1 (en) The long-span slab system
KR101038945B1 (en) A filling structure of upper part of a tunnel and its procedure
SU63656A1 (en) Device of reinforced concrete pile support
US3341639A (en) Method for grouting girders supporting concrete slabs
CN207919848U (en) Top plate of underground parking garage is combined the unit with plastics diaphragm capsule
CN112832546B (en) Transformation method of existing structure replacement concrete system
JP6817589B1 (en) How to build pile support structure
KR101541454B1 (en) The long-span slab system
JP7079166B2 (en) Tunnel internal structure and its construction method
US1539033A (en) Method of and means for reenforcing wall foundations
US1959653A (en) Construction of self-supporting structures
KR100507729B1 (en) Process for setting up structures for excavation of underground
KR101684477B1 (en) Construction method of bridge using girder with integral coping
JPS58143020A (en) Slope protection work
CN219974512U (en) Rib plate type prefabricated tunnel main body structure and uplift pile connection structure
RU2243317C2 (en) Method of concrete dams erection in severe climate