METHOD OF FASTENING EQUIPMENT ON READY-BASED FOUNDATIONSInfo
- Publication number
- SU209305A1 SU209305A1 SU1087748A SU1087748A SU209305A1 SU 209305 A1 SU209305 A1 SU 209305A1 SU 1087748 A SU1087748 A SU 1087748A SU 1087748 A SU1087748 A SU 1087748A SU 209305 A1 SU209305 A1 SU 209305A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- bolts
- equipment
- ready
- holes
- fastening equipment
- Prior art date
Links
- 239000004593 Epoxy Substances 0.000 claims description 2
- 239000000853 adhesive Substances 0.000 claims description 2
- 230000001070 adhesive Effects 0.000 claims description 2
- 238000004873 anchoring Methods 0.000 claims description 2
- 125000003700 epoxy group Chemical group 0.000 claims description 2
- 239000003292 glue Substances 0.000 claims description 2
- 238000009434 installation Methods 0.000 claims 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 238000005755 formation reaction Methods 0.000 claims 1
- 239000004020 conductor Substances 0.000 description 1
- 229920000647 polyepoxide Polymers 0.000 description 1
Description
Известен способ креплени оборудований йа готовых фундаментах с помощью болтов, заключающийс в том, что, установив смонтированное и окончательно выверенное оборудование , через отверсти в станине образуют в фундаменте сквозные отверсти , куда затем устанавливают анкерные болты и заливают их в жущим. Этот способ трудоемок и требует многократной выверки болтов.There is a known method of fixing equipments of finished foundations with the help of bolts, which means that after installing the assembled and finally adjusted equipment, through the holes in the frame, they form through holes in the foundation, where the anchor bolts are then installed and poured into the masses. This method is time consuming and requires repeated adjustment of bolts.
Предложенный способ отличаетс от известных тем, что дл упрощени производства работ , используютс болты без нижней головки или анкерующих приспособлений на конце. Болты креп т в скважинах клеем, заполн им зазор между каждым болтом и стенками скважины, равный 0,03-0,15 диаметра болта.The proposed method differs from the known ones in that in order to simplify the production work, bolts without a bottom head or anchoring devices at the end are used. The bolts are fixed in the wells with glue; they fill the gap between each bolt and the walls of the well, equal to 0.03-0.15 bolt diameter.
Клеем служит эпоксидна композици .The adhesive is the epoxy composition.
Предлагаемый чертеж по сн ет описываемый способ, который состоит в следующем.The proposed drawing illustrates the described method, which is as follows.
На возведенный фундамент устанавливают и вывер ют опорную часть оборудовани или оборудование целиком. Через отверсти в опорных конструкци х оборудовани , использу их в качестве своеобразных кондукторов, с помощью бура, электросверлилки и т. д..The base of the equipment or equipment as a whole is installed and turned onto the erected foundation. Through the holes in the supporting structures of the equipment, using them as peculiar conductors, with the help of a drill, electric drills, etc.
бур т скважину заданной глубины и диаметра .drill a well of a given depth and diameter.
В разбуренные, в бетоне отверсти ввод т затвердевающую массу, например, эпоксидный клей. Пе позднее чем через 1-2 час после ввода массы в отверсти ввод т гладкие стержни болтов. После отвердени производ т зат жку болтов.A hardened mass, such as epoxy glue, is introduced into holes drilled in concrete. Pe later than 1-2 hours after the mass is introduced, smooth bolt rods are inserted into the holes. After hardening, bolts are tightened.
Предмет изобретени Subject invention
Claims (2)
Publications (1)
Publication Number | Publication Date |
---|---|
SU209305A1 true SU209305A1 (en) |
Family
ID=
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5393263B2 (en) | Masonry wall reinforcement method and masonry structure. | |
CA2940801C (en) | Foundation for the support of a structure and method of installation | |
US20200308794A1 (en) | Adjustable cap for column foundation | |
JP2004108034A (en) | Foundation structure, construction method and steel-pipe-mounted precast concrete pile for steel-framed building | |
JP2018178646A (en) | Reinforcement structure and reinforcement method of masonry structure | |
US20070266659A1 (en) | Perimeter foundation panel, and method of use | |
US20230258006A1 (en) | Anchorage template for building walls and method | |
SU209305A1 (en) | METHOD OF FASTENING EQUIPMENT ON READY-BASED FOUNDATIONS | |
RU2319809C1 (en) | Method to reinforce existent building and building structure foundation | |
JP3843896B2 (en) | Structure and construction method of steel pipe column and steel pipe pile | |
JP2001295496A (en) | Structure and method of installing viscous seismic control wall onto existing src constructed beam | |
JP5534861B2 (en) | PC well and bridge construction method | |
JP2015081467A (en) | Base isolation structure | |
JPS61233131A (en) | Foundation structure of pole | |
US20200063457A1 (en) | Adjustable cap for column foundation | |
JP2002097818A (en) | Method of installing base isolating foundation frame for building | |
KR200224744Y1 (en) | Concrete base device for support | |
JP3861085B2 (en) | Support metal fittings, installation method of support metal fittings, height adjustment method of support metal fittings, and mortar leveling method. | |
KR20230130975A (en) | Concrete foundation | |
KR102646641B1 (en) | Anchor construction method for water proof sill of roof | |
RU1784715C (en) | Method of securing anchor bolt and anchor bolt | |
KR20060025971A (en) | Wire draw gear of casket anchor | |
RU2157441C2 (en) | Heat-insulating and fencing structures for skeleton- type building and method for their manufacture | |
KR102613254B1 (en) | Self-standing fixing type pile and construction method of earth retaining facilities including it | |
JPH10292393A (en) | Method for reinforcing foundation of existing structure |