SU1765333A1 - Blast furnace revamping method - Google Patents

Blast furnace revamping method Download PDF

Info

Publication number
SU1765333A1
SU1765333A1 SU894671943A SU4671943A SU1765333A1 SU 1765333 A1 SU1765333 A1 SU 1765333A1 SU 894671943 A SU894671943 A SU 894671943A SU 4671943 A SU4671943 A SU 4671943A SU 1765333 A1 SU1765333 A1 SU 1765333A1
Authority
SU
USSR - Soviet Union
Prior art keywords
casing
columns
furnace
morator
dismantling
Prior art date
Application number
SU894671943A
Other languages
Russian (ru)
Inventor
Сергей Алексеевич Свободин
Борис Никитич Силантьев
Владислав Викторович Стефанович
Original Assignee
С.А.Свободин, В.Н.Силантьев и В.В.Стефанович
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by С.А.Свободин, В.Н.Силантьев и В.В.Стефанович filed Critical С.А.Свободин, В.Н.Силантьев и В.В.Стефанович
Priority to SU894671943A priority Critical patent/SU1765333A1/en
Application granted granted Critical
Publication of SU1765333A1 publication Critical patent/SU1765333A1/en

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

Использование: согласно изобретению способ реконструкции доменной печи включает в себ  установку колонн опорной системы между фундаментом и колошниковой площадкой, после этого производ т демонтаж существующих колонн, а также демонтаж и монтаж кожуха печи с моратором. При демонтаже кожуха из колонн горна, морато- ра и части распара образуют переходный элемент, опира сь на который производ т монтаж кожуха шахты, одновременно монтируют кожух низа печи, причем после его соединени  с кожухом шахты производ т демонтаж переходного элемента. 4 ил.Use: According to the invention, a method for reconstructing a blast furnace involves installing columns of a support system between the foundation and the top site, then dismantling existing columns, as well as dismantling and mounting the furnace shell with a morator. When dismounting the casing from the pillars of the hearth, the morator, and the parts of the split, they form a transitional element, on which the casing of the shaft is mounted, simultaneously assemble the casing of the furnace bottom, and after connecting it to the casing of the shaft dismantling the transition element. 4 il.

Description

Предлагаемое техническое решение относитс  к строительству и может быть использовано в черной металлургии при реконструкции существующих доменных печей.The proposed solution relates to the construction and can be used in ferrous metallurgy in the reconstruction of existing blast furnaces.

Известен способ реконструкции доменных печей, по которому с целью уменьшени  объемов работ по установке опорной системы и сокращени  сроков проведени  работ по реконструкции и ремонту опорную систему выполн ют из колонн, установленных в створе с колоннами кольцевой крановой эстакады от нулевой отметки до верхней кольцевой площадки шахты печи, на которых устанавливают подкосы с закреплением одних их концов к верху колонны, а других к кожуху печи, причем узлы креплени  подкосов к колоннам и кожуху соедин ют с кольцевыми площадками шахты печи, затем прикрепл ют посредством св зей верх кожуха печи к рамам литейного двора и производ т замену кожуха печи ниже уровн  креплени  подкосов по всему периметру.A known method for the reconstruction of blast furnaces, in order to reduce the amount of work required to install the support system and reduce the time needed for reconstruction and repair, the support system is made of columns installed in the alignment of the annular crane racks from the zero mark to the upper annular platform of the furnace shaft on which they install struts with fastening one of their ends to the top of the column, and others to the furnace casing, with the attachment points of the struts to the columns and the casing being connected to the annular platforms hty furnace, and then attached by bonding to the top of the furnace shell casthouse frames t and making replacement furnace housing below the level of the attachment struts around the circumference.

Данный способ обеспечивает сокращение сроков реконструкции и ремонта, ноThis method provides a reduction in the time of reconstruction and repair, but

может быть использован лишь дл  доменных печей, имеющих кольцевую крановую эстакаду и литейный двор, и приемлем лишь дл  частичной замены кожуха.can only be used for blast furnaces with an annular crane overpass and a foundry yard, and is only acceptable for partial replacement of the casing.

Ремонт доменных печей с полной заменой кожуха и с обычным литейным двором по данному способу исключаетс .Repair of blast furnaces with complete replacement of the casing and with a conventional casting yard is eliminated by this method.

Кроме того, монтаж кожуха доменной печи производитс  обычным способом укрупненными блоками снизу вверх, при этом исключаетс  совмещение операций монтажа низа и верха печи.In addition, the installation of the blast furnace casing is carried out in the usual way by enlarged blocks from bottom to top, thus eliminating the combination of the mounting operations of the bottom and top of the furnace.

Целью предлагаемого технического решени   вл етс  сокращение сроков ремонта доменных печей.The aim of the proposed technical solution is to reduce the time needed for the repair of blast furnaces.

Поставленна  цель достигаетс  тем, что согласно предлагаемому способу реконструкции доменной печи, включающему установку колонн опорной системы между фундаментом и колошниковой площадкой, демонтаж существующих колонн, а также демонтаж и монтаж кожуха печи с моратором , при демонтаже кожуха из колонн горна , моратора и части распара образуют переходный элемент, с опорой на которыйThe goal is achieved in that according to the proposed method of reconstruction of a blast furnace, including the installation of columns of the support system between the foundation and the top site, the dismantling of existing columns, as well as the dismantling and installation of the furnace shell with a morator, when dismantling the case from the hearth columns, the morator and the decoupling part transition element, based on which

сгsg

иand

VI о елVi o ate

GJGj

СА)SA)

GOGO

производ т монтаж кожуха шахты, одновременно монтиру  кожух низа печи, причем после соединени  его с кожухом шахты производ т демонтаж переходного элемента.the shaft housing is mounted, at the same time, the furnace bottom housing is mounted to the assembler, and after connecting it to the mine housing, the transition element is dismantled.

Существо предлагаемого технического решени  по сн етс  чертежами, где на фиг 1 изображена доменна  печь до реконструкции; на фиг. 2 - доменна  печь в процессе реконструкции; на фиг. 3 - то же, монтаж кожуха шахты и низа печи закончен, переходный элемент не демонтирован; на фиг. 4 - доменна  печь после реконструкции.The essence of the proposed technical solution is explained in the drawings, where Fig. 1 shows a blast furnace before reconstruction; in fig. 2 - blast furnace in the reconstruction process; in fig. 3 - the same, installation of the casing of the shaft and the bottom of the furnace is completed, the transition element is not dismantled; in fig. 4 - blast furnace after reconstruction.

Реконструкцию доменной печи 1 начинают с установки сквозных колонн 2 опорной системы (до начала ремонта) между фундаментом и колошниковой площадкой, выполненных в створе с существующими колоннами 3 горна и колоннами 4 шахты.Reconstruction of the blast furnace 1 begins with the installation of through columns 2 of the support system (before the start of repair) between the foundation and the top plate, made in alignment with existing columns 3 of the hearth and columns 4 of the mine.

После остановки печи демонтируют ко- лйнны 4 шахТы, кожух шахты 5 и горна б (фиг. 1), сохран   старые колонны горна 3, моратор 7 и часть распара 8 и образу  тем самым временный переходный элемент (фиг. 2).After stopping the furnace, the mines of the 4 mines, the casing of the shaft 5 and the forge b (Fig. 1) are dismantled, preserving the old columns of the forge 3, the morator 7 and part of the pair 8 and thereby forming a temporary transition element (Fig. 2).

Восстановительные работы начинают с монтажа моратора 9 и кожуха распара 10.Restoration work begins with the installation of the morator 9 and the split housing 10.

В качестве базы используют переходный элемент, состо щий из старых колонн 3 горна, моратора 7 и части распара 8As a base, a transitional element is used, consisting of old columns 3 of the forge, a morator 7 and a part of the pair 8

Блиндажное перекрытие 11 устанавливаетс  на старом мораторе 7 и на нем монтируют кольцевой монорельс 12 с электротельфером 13 дл  монтажа карт 14 кожуха горна.The dugout slab 11 is mounted on the old morator 7 and a ring monorail 12 is mounted on it with an electric hoist 13 for mounting the hearth shroud cards 14.

Монтаж карт 16 кожуха шахты производитс  при помощи грузоподъемного средства 17 (фиг. 2).The installation of the cards 16 of the casing of the shaft is made by means of a lifting means 17 (Fig. 2).

После окончани  монтажа кожуха фурменной зоны 18 и заплечиков 19, соединени  при помощи сварки с кожухом шахты производитс  демонтаж переходного элемента .After the installation of the casing of the tuyere zone 18 and the shoulders 19 is completed, the transition element is dismantled by welding with the casing of the mine.

Таким образом, предлагаемый способThus, the proposed method

реконструкции доменной печи, по которому демонтаж кожуха шахты осуществл етс  с образованием переходного элемента из старых колонн горна, моратора и части распара , позвол ет вести монтаж кожуха шахтыreconstruction of the blast furnace, in which the dismantling of the mine casing is carried out with the formation of a transitional element from old columns of the hearth, morator and part of the joint, allows mounting of the mine casing

одновременно (или с опережением) с монтажом кожуха горна и сократить сроки проведени  ремонта в среднем на 5-7 сут.at the same time (or ahead of time) with the installation of the horn housing and reduce the time for repairs by an average of 5-7 days.

Claims (1)

Формула изобретени Invention Formula Способ реконструкции доменной печи, включающий установку между фундаментом и колошниковой площадкой колонн опорной системы, демонтаж существующих колонн, а также демонтаж и монтаж кожуха печи с моратором, отличающийс  тем, что, с целью сокращени  сроков ремонта, при демонтаже кожуха из колонн горна, моратора и части распара образуют переходный элемент, с опорой на который производ т монтаж кожуха шахты, одновременно монтиру  кожух низа печи, причем после соединени  его с кожухом шахты производ т демонтаж переходного элемента.A method of reconstruction of a blast furnace, including installation between the foundation and the top plate of the columns of the support system, dismantling of the existing columns, and dismantling and mounting the furnace shell with a morator, characterized in that, in order to reduce the repair time, during the removal of the shell from the columns of the forge, the morator and The parts of the split form a transition element, with the support on which the shaft casing is mounted, while simultaneously mounting the bottom furnace shell, and after connecting it to the shaft casing, the transition element is dismantled. Фиг. 2FIG. 2 фиг.Зfig.Z фиг. ftFIG. ft
SU894671943A 1989-04-04 1989-04-04 Blast furnace revamping method SU1765333A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU894671943A SU1765333A1 (en) 1989-04-04 1989-04-04 Blast furnace revamping method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU894671943A SU1765333A1 (en) 1989-04-04 1989-04-04 Blast furnace revamping method

Publications (1)

Publication Number Publication Date
SU1765333A1 true SU1765333A1 (en) 1992-09-30

Family

ID=21438583

Family Applications (1)

Application Number Title Priority Date Filing Date
SU894671943A SU1765333A1 (en) 1989-04-04 1989-04-04 Blast furnace revamping method

Country Status (1)

Country Link
SU (1) SU1765333A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 1032149, кл. С 21 В 7/00, 1982. , *

Similar Documents

Publication Publication Date Title
US6513789B2 (en) Method and apparatus for short-term relining or construction of blast furnace
CA1052080A (en) Method for constructing a blast furnace
SU1765333A1 (en) Blast furnace revamping method
FI85505B (en) ANALYTICAL FORM OF THE GLIDRAINE IN SCHAKTUGNAR.
US4183305A (en) Furnace seal
RU2171849C1 (en) Method of repairing blast furnace
SU1032149A1 (en) Blast furnace reconstruction and repair method
SU885502A1 (en) Method of reconstructing and repairing a blast furnace
SU1028822A1 (en) Method and apparatus for restructing a blast furnace
SU1444350A1 (en) Method of blast furnace reconstruction and repairs
SU1353880A1 (en) Method of reconstructing a blast furnace
SU1067335A1 (en) Soaking pit cover
US4003558A (en) Supporting structure for blast furnaces
SU1262015A1 (en) Method of retrofitting a blast furnace
SU1463763A1 (en) Method of reconstructing a blast furnace
SU1186384A1 (en) Template for lining metallurgical tanks
JPH0196308A (en) Method for operating blow-down in blast furnace
SU1167288A1 (en) Method of reconstruction and repairs of blast furnace
SU1267147A1 (en) Heating furnace
CN106624125A (en) Energy saving blast furnace billet steel shearing machine
SU1523571A1 (en) Blast-furnace cast-iron tap hole
SU1663156A1 (en) Method of reconstruction of blast-furnace plant building
JPS585920Y2 (en) Refractory injection equipment for repair
SU1515016A1 (en) Upper platform of three-electrode electric furnace
SU985036A1 (en) Spout for casting products of blast-furnace melting