SU1500716A1 - Method of erecting earth-fill dam - Google Patents

Method of erecting earth-fill dam Download PDF

Info

Publication number
SU1500716A1
SU1500716A1 SU874242886A SU4242886A SU1500716A1 SU 1500716 A1 SU1500716 A1 SU 1500716A1 SU 874242886 A SU874242886 A SU 874242886A SU 4242886 A SU4242886 A SU 4242886A SU 1500716 A1 SU1500716 A1 SU 1500716A1
Authority
SU
USSR - Soviet Union
Prior art keywords
layer
dam
dumping
soil
ground
Prior art date
Application number
SU874242886A
Other languages
Russian (ru)
Inventor
Vladimir T Mankevich
Anatolij A Lengin
Original Assignee
Sib Vnii Gidrotekh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sib Vnii Gidrotekh filed Critical Sib Vnii Gidrotekh
Priority to SU874242886A priority Critical patent/SU1500716A1/en
Application granted granted Critical
Publication of SU1500716A1 publication Critical patent/SU1500716A1/en

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

Изобретение относится к гидротехническому строительству. Цель изобретения - повышение надежности работы плотины. В грунт противофильтрационного элемента при его отсыпке укладывают по длине элементаThe invention relates to hydraulic construction. The purpose of the invention is to increase the reliability of the dam. In the soil of the impervious element when it is dumped, it is laid along the length of the element.

Изобретение относится к строительству грунтовых гидротехнических сооружений, преимущественно в Сибири и районах Крайнего Севера.The invention relates to the construction of groundwater structures, mainly in Siberia and the Far North.

Цель изобретения - повышение надежности работы плотины.The purpose of the invention is to increase the reliability of the dam.

На фиг.1 изображена плотина после отсыпки первого яруса, поперечный разрез^ на фиг.2 - то же, после возведения полного профиля плотины.Figure 1 shows the dam after dumping the first tier, the cross section ^ in figure 2 - the same, after the construction of the full profile of the dam.

На подготовленное основание 1 укладывают грунты Переходных зон 2 и упорных призм 3, после чего отсыпа2On the prepared base 1, the soils of the Transition zones 2 and resistant prisms 3 are laid, after which the ground2

горизонтальные электроды. Электроды подключают посредством выводов к генераторам переменного и постоянного тока, которые размещают за пределами плотины. Электрообогрев мерзлого грунта осуществляют в следующей последовательности: вначале по достижении высоты отсыпаемого противофильтрационного элемента, равной мощности активного слоя, начинают его переменным током в зоне слоя, контактирующего с основанием. Заканчивают электрообогрев по достижении в обрабатывающем слое положительных температур. Затем начинают электрообогрев переменным током оhorizontal electrodes. The electrodes are connected via leads to alternating current and direct current generators, which are placed outside the dam. Electric heating of the frozen ground is carried out in the following sequence: first, upon reaching the height of pouring impervious element, equal to the power of the active layer, it is started with an alternating current in the zone of the layer in contact with the base. The electrical heating is completed upon reaching positive temperatures in the treatment layer. Then start heating with alternating current about

вышележащего слоя и одновременно осушают нижележащий слой, подвергая его воздействию постоянного тока до достижения грунтом минимальной влажности. Мощность активного слоя в процессе отсыпки до проектной высоты Поддерживают постоянной. 2 ил.overlying layer and at the same time dry the underlying layer, exposing it to direct current until the soil reaches the minimum moisture. The power of the active layer in the process of dumping to the design height Maintain a constant. 2 Il.

ют противофильтрационныи элемент 4 в который по длине укладывают горизонтальные электроды 5, подключаемые посредством выводов к электрогенераторам переменного и постоянного токов.There are impervious elements 4 into which horizontal electrodes 5 are placed along the length, connected by leads to alternators and alternating current generators.

При необходимости грунт, отсыпанный в противофильтрационныи элемент, обрабатывают электропроводными морозостойкими растворами, например ЦаС1 или СаС^ .If necessary, the soil, poured into an impervious element, is treated with electrically conductive frost-resistant solutions, for example, CacCl or CaCl2.

По достижении высоты иротивофильтрационного элемента, ранной мощности активного слоя, определяемой кон3 и „„ 1500716Upon reaching the height of the anti-filtering element, the early power of the active layer, determined by con3 and „„ 1500716

4four

3 15007163 1500716

кретными условиями строительства, начинают электропрогрев в зоне, контактирующей с основанием. Но достижении положительных температур в обрабатываемом слое его электропрогрев заканчивают и начинают электропрогрев вышележащего слоя, а нижний подвергают воздействию постоянного тока и с помощью электроосмоса обеспечивают осушение прогретого слоя. По истечении времени, требуемого для достижения минимальной влажности, определяемой опытным путем до производства работ, постоянный ток отключают. Параллельно с электрообработкой грунта продолжается его отсыпка, чем обеспечиваются как постоянная мощность активного слоя, так и его подъем, т.е. рост высоты сооружения в целом.specific conditions of construction, begin electric heating in the zone in contact with the base. But when the positive temperatures in the treated layer are reached, the electrical heating is completed and the electric heating of the overlying layer begins, and the lower one is exposed to direct current and with the help of electroosmosis they dry the heated layer. After the time required to achieve the minimum humidity, determined empirically before the work, the direct current is turned off. In parallel with the electrotreatment of soil, it continues to be dumped, which ensures both the constant thickness of the active layer and its rise, i.e. height increase of the structure as a whole.

Claims (1)

Формула изобретенияClaim Способ возведения грунтовой плотины, включающий укладку упорных призм и переходных зон и отсыпку противофильтрационного элемента изThe method of erection of a soil dam, including the laying of resistant prisms and transition zones and dumping impervious element from переувлажненного и (или) мерзлого грунта, о т л и ч а ю щ и й с я тем, что, с целью повышения надежности работы плотины, в грунт противофильтоационного элемента при его отсылке укладывают по длине элемента горизонтальные электроды, подключаемые посредством выводов к генераторам пе10 ременного и постоянного токов, размещаемым за пределами плотины, а электрообогрев осуществляют в следующей последовательности: вначале, при достижении высоты отсыпаемого противо15 фильтрационного элемента, равной мощности активного слоя, начинают его переменным током в зоне слоя, контактирующего с основанием, а заканчивают при достижении в обрабаты20 ваемом слое положительных температур, затем начинают электрообогрев переменным током вышележащего слоя и одновременно осушают нижележащий слой, подвергая его воздействию постоян25 ного тока до достижения грунтом минимальной влажности, при этом мощность активного слоя в процессе отсыпки до проектной высоты поддерживают постоянной.overmoistened and (or) frozen ground, so that, in order to increase the reliability of the dam, in the ground of the anti-filtering element, when it is sent, horizontal electrodes are placed along the element, connected via leads to the generators variable and direct currents placed outside the dam, and electrical heating is carried out in the following sequence: first, when the height of the sprinkled anti-filter element is equal to the power of the active layer, it begins to change current in the zone of the layer in contact with the base, and end when the heated layer reaches positive temperatures, then start heating the alternating current of the upper layer and at the same time dry the underlying layer, exposing it to direct current until the soil reaches the minimum moisture in the process of dumping to the design height support constant.
SU874242886A 1987-03-04 1987-03-04 Method of erecting earth-fill dam SU1500716A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU874242886A SU1500716A1 (en) 1987-03-04 1987-03-04 Method of erecting earth-fill dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU874242886A SU1500716A1 (en) 1987-03-04 1987-03-04 Method of erecting earth-fill dam

Publications (1)

Publication Number Publication Date
SU1500716A1 true SU1500716A1 (en) 1989-08-15

Family

ID=21303443

Family Applications (1)

Application Number Title Priority Date Filing Date
SU874242886A SU1500716A1 (en) 1987-03-04 1987-03-04 Method of erecting earth-fill dam

Country Status (1)

Country Link
SU (1) SU1500716A1 (en)

Similar Documents

Publication Publication Date Title
IS1577B (en) Electrochemical treatment of porous building materials, in particular to dry and recalibrate them
SU1500716A1 (en) Method of erecting earth-fill dam
ES2220981T3 (en) PROCEDURE FOR CIRCULATING A FLUID IN A POROUS MATERIAL.
US4180953A (en) Method and apparatus for countering an upward capillary flow of soil moisture in a foundation wall
SU1535926A1 (en) Method of constructing cohesive soil
SU1535929A1 (en) Method of constructing an earth dam
SU1271938A1 (en) Method of driving sinkable well into soil with use of thixotropic jacket
SU682482A1 (en) Device for electrically heating concrete mix
SU978786A1 (en) Soil desalination method
SU467968A1 (en) Foundation for technological equipment
RU2000122485A (en) METHOD FOR ESTABLISHING ROAD CLOTHES
EP1452654A2 (en) Method for effecting fluid flow in porous materials
SU706486A1 (en) Method of consolidating water-saturated clayey soil
SU184410A1 (en) METHOD OF ELECTROSOPHYSICAL DRAINAGE OF WALLS, FOUNDATIONS OF BUILDINGS OR CONSTRUCTIONS
SU1502694A1 (en) Drainage system
SU861594A1 (en) Method of loosening frozen loose materials
SU1504306A1 (en) Method of erecting earth structure at subzero temperatures
RU2206675C2 (en) Process of insulation of structures exposed to moisture
SU674338A1 (en) Method of placement of concrete of bulky monolithic structures
DK145633B (en) PLANT FOR PLANTING AND MAINTENANCE OF BUILDINGS
SU1157161A1 (en) Cathode for electro-osmotic drying of ground
SU316818A1 (en) METHOD FOR DETERMINING FROZEN GROUNDS
SU762913A1 (en) Method of electroosmotical dehydration
SU1535925A1 (en) Method of forming extension joints of central part of dam
SU724633A1 (en) Method of making built-in-soil pile