SU1465556A1 - Percussive device - Google Patents

Percussive device Download PDF

Info

Publication number
SU1465556A1
SU1465556A1 SU874173042A SU4173042A SU1465556A1 SU 1465556 A1 SU1465556 A1 SU 1465556A1 SU 874173042 A SU874173042 A SU 874173042A SU 4173042 A SU4173042 A SU 4173042A SU 1465556 A1 SU1465556 A1 SU 1465556A1
Authority
SU
USSR - Soviet Union
Prior art keywords
striker
drain
spool
cavity
channel
Prior art date
Application number
SU874173042A
Other languages
Russian (ru)
Inventor
Сергей Васильевич Кравченко
Original Assignee
Карагандинский политехнический институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Карагандинский политехнический институт filed Critical Карагандинский политехнический институт
Priority to SU874173042A priority Critical patent/SU1465556A1/en
Application granted granted Critical
Publication of SU1465556A1 publication Critical patent/SU1465556A1/en

Links

Landscapes

  • Percussive Tools And Related Accessories (AREA)

Abstract

Изобретение относитс  к устройствам ударного действи  дл  разрушени  горных пород и искусственных материалов . Цель - повьшение экономичности устр-ва за счет уменьшени  утечек рабочей жидкости во внешнюю среду. Устр-во ударного действи  включает ударный механизм с бойком 1, имеющим два по ска 2 и 3, и корпусом (к) 4с напорным 5 и сливным 6 каналами. Последние расположены с возможностью совмещени  их наружных кромок с наружными кромками по сков ОА. ий ойшемаичю м рм с ых ов Tfr л 2,3 бойка I. Боек 1 образует с К 4 рабочую камеру 7 уштотнительного узла и полости: взвод щую 8, переливную 9, слива 10 и аккумул тора 11. Блок управлени  имеет золотник 12 и К 13. Каналы 14-18 золотника управлени  сообщены с рабочей камерой 7 и полост ми 8-10 ударного узла и напорной магистралью 19 трубопроводами 20-24. Длина сливного канала 6 К 4, сообщенного со сливной магистралью 29, выполнена равной по величине рабочему ходу бойка 1. Блок управлени  выполнен с возвратом золотника 12 пружиной 25. Золотник выполнен двухпо сковым с по сками 26 и 27. Боек 1 перемещаетс  влево при сообщении полостей 8 и 10 под действием давлени  сжатого газа в полости П. Происходит рабочий ход бойка 1 и удар бойка 1 по инструмен- ту. При зтом жидкость из напорной магистрали 19 через канал 5, полость 9, трубопровод 21 и канал 15 поступает в блок управлени  и перемещает золотник 12. 1 ил. а5/ - 7 (О 4ik. сл СП СП в W 11 го 29The invention relates to impact devices for the destruction of rocks and artificial materials. The goal is to increase the efficiency of the device by reducing the leakage of working fluid into the external environment. The percussion unit includes a percussion mechanism with striker 1 having two cca 2 and 3, and a casing (k) 4c with a pressure head 5 and a drain 6 channels. The latter are arranged with the possibility of combining their outer edges with the outer edges along the edges of the OA. Oishemaaicha m from the s of Tfr l 2,3 brisk I. Striker 1 forms with K 4 the working chamber 7 of the receptacle and the cavity: cocking 8, overflow 9, drain 10 and battery 11. The control unit has a spool 12 and K 13. Channels 14–18 of the control valve are in communication with the working chamber 7 and cavities 8–10 of the impact unit and the pressure line 19 by pipelines 20–24. The length of the drain channel 6 K 4, communicated with the drain line 29, is made equal to the size of the working stroke of the striker 1. The control unit is made with the return of the spool 12 by the spring 25. The spool is made two-way with steps 26 and 27. The striker 1 moves to the left when the cavities are communicated 8 and 10 under the action of pressure of compressed gas in the cavity P. There is a working stroke of the striker 1 and a strike of the striker 1 against the tool. In this case, the liquid from the pressure line 19 through the channel 5, the cavity 9, the pipeline 21 and the channel 15 enters the control unit and moves the valve 12. 1 sludge. a5 / - 7 (O 4ik. SL JV JV in W 11 th 29

Description

Изобретение относитс  к горной про№шшенности и может быть использовано в устройствах ударного действи  дл  разрушени  горных пород и искусственных материалов.The invention relates to rock formations and can be used in impact devices for the destruction of rocks and artificial materials.

Цель изобретени  - повышение экономичности устройства за счет уменьшени  утечек рабочей жидкости во .внешнюю среду,The purpose of the invention is to increase the efficiency of the device by reducing the leakage of the working fluid into the external environment.

На чертеже представлено устройств продольный разрез.The drawing shows the device longitudinal section.

Устройство ударного действи  содержит ударный механизм с бойком 1, имеющим два по ска 2 и 3, и корпусом А, имеюпдам напорный 5 и сливной 6 каналы, расположенные с возможностью совмещени  их наружных кромок с наружными кромками по сков 2. и 3 бойка 1, образугацего с корпусом 4 рабоThe percussion device contains a percussion mechanism with a striker 1 having two shots 2 and 3, and case A, having pressure 5 and drain 6 channels, arranged to align their outer edges with the outer edges along banks 2. and 3 striker 1, forming with body 4 slave

чую камеру 7 уплотнительного узла и полости: взвод щую 8, переливную 9, сливиую 10 и полость 11 аккумул тораI feel the chamber 7 of the sealing unit and the cavity: cocking 8, overflow 9, merging 10 and the cavity 11 of the battery

Блок управлени  имеет золотник 12 и корпус 13, переливной 14, управл ющий 15, рабочий 16, сливной 17 и напорный 18 каналы которого сообщены соответственно с рабочей камерой 7 уплотнительного узла, переливной 9, взвод щей 8 и сливной 10 полост ми ударного узла и напорной магистралью 19, трубопроводами 20 - 24.The control unit has a spool 12 and a housing 13, an overflow 14, a control 15, a worker 16, a drain 17 and a pressure 18 channels of which are communicated respectively with the working chamber 7 of the sealing assembly, the overflow 9, charging 8 and the drain 10 cavity of the shock assembly and the pressure line 19, pipelines 20-24.

Блок управлени  выполнен с пружинным возвратом золотника 12 пружиной 25, щж этом золотник выполнен двух- по сковым с по сками 26 и 27 и проточкой 28„The control unit is made with a spring return of the spool 12 by a spring 25, this time the spool is made double with ream 26 and 27 and a groove 28 "

Длина сливного канала 6 корпуса А, сообщенного со.сливной магистралью 29, выполнена равной рабочему ходу бойка 1,The length of the drain channel 6 of the housing And reported by the drainage line 29, is equal to the working stroke of the striker 1,

Ушютнительный узел имеет уплот- нительный элемент 30,The nodal assembly has a sealing element 30,

Полость П аккумул тора заполнена сжатым газом.The cavity P of the battery is filled with compressed gas.

Устройство работает следующим образом .The device works as follows.

В исходном положении под действием давлени  сжатого газа боек 1 находитс  в крайнем левом (по чертежу ) положении, при этом золотник 12 находитс  в крайнем правом пoJJOжeнии под действием усили  пружины 25. В это врем  переливна  полость 9 соедин ет трубопроводы 21 и 23, сливна  полость 10 каналом 6 сообщена со сливной магистралью 29, а задний то-,In the initial position under the pressure of the compressed gas, the hammer 1 is in the extreme left (according to the drawing) position, while the spool 12 is in the extreme right position under the force of the spring 25. At this time, the overflow cavity 9 connects the pipes 21 and 23, the drain cavity 10 channel 6 is connected to the drain line 29, and the back -

рец по ска канала 6,rec on ska channel 6,

3 бойка 1 совмещен3 striker 1 combined

с краемwith edge

с with

5 five

00

5five

00

5 five

0 0

5 five

oo

5five

При подаче рабочей жидкости в напорную магистраль 19 жидкость через трубопровод 24, канал 18, проточку 28, канал 16 и трубопровод 22 поступает в взвод щую полость 8, вследствие чего боек 1 перемещаетс  вправо ( по чертежу ), Газ в полости 1 1 дополнительно сжимаетс , жидкость из сливной полости 10 вытесн етс  в сливную магистраль 29 через каналы 6. Происходит взвод (холостой ход) бойка 1, в начале которого одновременно по сок 2 бойка 1 отсекает канал 5 от полости 9, а по сок 3 сообщает полость 9 со сливным каналом 6, Золотник 12 во врем  холостого хода бойка 1 удерживаетс  в крайнем правом положении усилием пружины 25, В конце холостого хода одновременно по сок 3 бойка I отсекает полость 10 от сливного канала 6, а по сок 2 сообщает взвод щую полость 8 через канал .5 напр мзто с напорной магистралью 19. При дальнейшем движении бойка 1 жидкость, замкнута  в сливной полости 10, воздействует на золотник 12, перемещал его влево и сжима  пружину 25, При перемещении золотника 12 1злево сначала канал 14 сооб- с проточкой 28, затем канал 16 отсекаетс  от проточки 28, а в конце пepeмeD eни  золотника 12 канал 16 сообщаетс  с каналом 17 ( при этом через каналы 16 и 17 и трубопроводы 22 и 23 взвод ща  полость 8 сообщаетс  с полостью 10), После сообщени  полостей 8 и Ю давлени  жидкости в них выравниваютс  и боек I под действием давлени  сжатого газа в полости 11 ускоренно перемеш;аетс  влево. Происходит рабочий ход бойка 1, во врем  которого сначала одновременно.-полость 10 сообщаетс  через канал 6 со сливной магистралью 29, а полость 8 по ском 2 бойка отсекаетс  от канала 5, затем одновременно полость 9 отсекаетс  от канала 6 и сообщаетс  через канал 5 с напорной Mai- стралью 19, Происходит удар бойка 1 по инструменту . Жидкость из напорной магистрали 9 через канал 5, полость 9, трубопровод 21 и канал 15 поступает в блок управлени  и перемещает золотник 12 в правое (по чертежу ) крайнее положенне . Далее цикл работы устройст повтор етс .When the working fluid is supplied to the pressure line 19, the fluid passes through the pipeline 24, the channel 18, the groove 28, the channel 16 and the pipeline 22 enters the charging cavity 8, as a result of which the striker 1 moves to the right (according to the drawing), the gas in the cavity 1 1 is further compressed the fluid from the drain cavity 10 is forced out into the drain line 29 through channels 6. A platoon (idle) of the striker 1 occurs, at the beginning of which simultaneously juice 2 of the striker 1 cuts off channel 5 from cavity 9, and juice 3 communicates cavity 9 with the drain channel 6, spool 12 during idle striker 1 is held in the extreme right position by the force of the spring 25. At the end of idling, juice 3 of the striker I simultaneously cuts the cavity 10 from the drain channel 6, and juice 2 informs a charging cavity 8 through the channel .5 for example with a pressure line 19. Further When the striker 1 moves, the fluid is closed in the drain cavity 10, acts on the spool 12, moved it to the left and compressed the spring 25. When moving the spool 12 1 to the left, first channel 14 is connected with the groove 28, then channel 16 is cut off from the groove 28, and at the end They spool 12 channel 16 is reported with to through the channels 16 and 17 and the pipes 22 and 23 of the charging cavity 8 communicates with the cavity 10). After the communication of the cavities 8 and 10 of the fluid pressure in them, the firing pin I is equalized by the pressure of the compressed gas in the cavity 11 and accelerated; It is left. The working stroke of the striker 1 takes place, during which at first simultaneously the cavity 10 communicates via channel 6 with the drain line 29, and the cavity 8 by means of the striker 2 is cut off from channel 5, then the cavity 9 is simultaneously cut off from channel 6 and communicated through channel 5 pressure valve 19, strikes the striker 1 on the tool. Fluid from the pressure line 9 through channel 5, cavity 9, pipe 21 and channel 15 enters the control unit and moves the spool 12 to the right (according to the drawing) extreme position. Further, the operation cycle of the device is repeated.

Уплотнительный узел бойка 1 работает таким образом.The sealing unit of the striker 1 works in this way.

Во врем  рабочего хода бойка 1 давление жидкости в рабочей камере 7 уплотнительного узла велико (т.к. в эту камеру поступает весь расход от насоса через трубопровод 24, ка- нал 18, проточку 28, канал 14 и трубопровод 20 ), что обеспечивает плотное прилегание уплотн ющего элемента 30 к поверхности бойка 1 и, следовательно , незначительный вынос жидко- сти во внешнюю среду.During the working stroke of the striker 1, the fluid pressure in the working chamber 7 of the sealing assembly is high (because all the flow from the pump through the pipeline 24, channel 18, groove 28, channel 14 and pipeline 20) flows into this chamber, which ensures tight the abutment of the sealing element 30 against the surface of the striker 1 and, consequently, a slight removal of fluid into the external environment.

Во врем  холостого хода давление жидкости в камере 7.равно давлению в сливной магистрали 29, т.к. золотник 12 удерживаетс .в крайнем правом положении усилием пружины 25, потому камера 7 сообщена с магистралью 29 (через трубопровод 20, каналы 14 и 15, трубопровод 21 и полость 9). При этом плотность прилегани  уплот- н ющего элемента 30 к поверхности бойка 1 резко уменьшаетс , что позвол ет бойку 1 внести вовнутрь ударного устройства значительную долю жидкости, вынесенной им при рабочем ходе.During idling, the pressure of the fluid in the chamber is 7. equal to the pressure in the discharge line 29, since the spool 12 is held. in the extreme right position by the force of the spring 25, because chamber 7 communicates with line 29 (through conduit 20, channels 14 and 15, conduit 21 and cavity 9). At the same time, the density of the abutment of the sealing element 30 against the surface of the striker 1 decreases sharply, which allows the striker 1 to introduce into the impact device a significant portion of the fluid it has carried during the working stroke.

ва wa

14655561465556

ФормулаFormula

изобретени the invention

Устройство ударного действи , включающее ударный механизм с двух- по сковым бойком и корпусом, имеющим напорный и сливной каналы, расположенные с возможностью совмещени  их наружных кромок с наружными кромками по сков бойка, образующего с корпусом рабочую камеру уплотнительного узла и полости взвод щую, переливную , сливную и аккумул тора, блок управлени , имеющий золотник и корпус , переливной, управл ющий, рабочий , сливной и напорньгй каналы которого сообщены соответственно с рабочей камерой уплотнительного узла, переливной, взвод щей и сливной полост ми ударного механизма и напорной магистралью, отличающее с   тем, что, с целью повышени  экономичности устройства за счет уменьшени  утечек рабочей жидкости во внешнюю среду, длина сливного канала корпуса выполнена равной по величине ходу бойка, причем блок управлени  выполнен с пружинным вовзратом золотника, при этом золотник выполнен двухпо сковым.The percussion device, which includes a percussion mechanism with a double-sided striker and a body having pressure and drain channels, arranged to align their outer edges with the outer edges of the striker, forming a working chamber of the sealing unit and cavity with the body, coaxing, overflow, drain and accumulator, control unit, having a spool and body, overflow, control, working, drain and pressure channels of which are communicated respectively with the working chamber of the sealing unit, overflow, platoon percussion mechanism and pressure line, characterized in that, in order to increase the efficiency of the device by reducing leakage of working fluid into the external environment, the length of the body drain channel is made equal to the striker stroke, and the control unit is spring-loaded the spool, while the spool is made double.

Claims (1)

Формула изобретенияClaim Устройство ударного действия, 5 включающее ударный механизм с двухпоясковым бойком и корпусом, имеющим напорный и сливной каналы, расположенные с возможностью совмещения их наружных кромок с наружными кромками 10 поясков бойка, образующего с корпусом рабочую камеру уплотнительного узла и полости взводящую, переливную, сливную и аккумулятора, блок управления, имеющий золотник и кор15 пус, переливной, управляющий, рабочий, сливной и напорный каналы которого сообщены соответственно с рабо- чей камерой уплотнительного узла, переливной, взводящей и сливной по20 лостями ударного механизма и напорной магистралью, отличающее с я тем, что, с целью повышения экономичности устройства за счет уменьшения утечек рабочей жидкости 25 во внешнюю среду, длина сливного канала корпуса выполнена равной по величине рабочему ходу бойка, причем блок управления выполнен с пружинным вовзратом золотника, при этом золотник выполнен двухпоясковым.Impact device 5 comprising a percussion mechanism with a double girder striker and a housing having pressure and drain channels arranged to combine their outer edges with the outer edges 10 of the striker belts forming a working chamber of the sealing assembly and cavity cocking, overflow, drain and battery , a control unit having a spool and housing 15, overflow, control, working, drain and pressure channels of which are in communication with the working chamber of the sealing unit, overflow, cocking a common and drain cavities of the percussion mechanism and a pressure line, characterized in that, in order to increase the efficiency of the device by reducing the leakage of the working fluid 25 into the external environment, the length of the drain channel of the body is equal to the working stroke of the striker, and the control unit is made with spring return of the spool, while the spool is made double-belt. ходе.course.
SU874173042A 1987-01-04 1987-01-04 Percussive device SU1465556A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU874173042A SU1465556A1 (en) 1987-01-04 1987-01-04 Percussive device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU874173042A SU1465556A1 (en) 1987-01-04 1987-01-04 Percussive device

Publications (1)

Publication Number Publication Date
SU1465556A1 true SU1465556A1 (en) 1989-03-15

Family

ID=21277290

Family Applications (1)

Application Number Title Priority Date Filing Date
SU874173042A SU1465556A1 (en) 1987-01-04 1987-01-04 Percussive device

Country Status (1)

Country Link
SU (1) SU1465556A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР 1252485, кл. Е 21 С 3/20, 1984. Авторское свидетельство СССР № 1298371, кл. Е 21 С 3/20, 1985. *

Similar Documents

Publication Publication Date Title
US4349075A (en) Hydraulically operated impact motor
SU776569A3 (en) Hydraulic shocking device
SU1465556A1 (en) Percussive device
SU860682A1 (en) Shocking device for cleaning industrial pipelines with washing liquid
SU1321811A1 (en) Percussive device
SU1373807A1 (en) Hydraulic percussive mechanism
SU1406363A1 (en) Percussive device
SU861577A1 (en) Immersion percussion device of drilling rig with hydrostatic drive
SU1298371A1 (en) Percussive device
RU2070247C1 (en) Impact-action device
SU1661399A1 (en) Percussive tool
SU1145129A1 (en) Hydraulic percussive device
SU831950A1 (en) Hydro-percussive earth-drilling machine
SU1608338A1 (en) Percussive hydraulic mechanism
SU1285146A1 (en) Hydropneumatic percussive device
SU853097A1 (en) Hydraulic percussive device
SU1506102A1 (en) Hydraulic percussive mechanism
SU1093801A1 (en) Hydropercussive apparatus
RU2055138C1 (en) Downhole air hammer for hole drilling
RU2030578C1 (en) Hydraulic percussive device
SU1263834A1 (en) Hydraulic percussive device
SU717313A1 (en) Hydraulic drilling machine
SU1627692A1 (en) Hydraulic percussion device
SU1229328A1 (en) Hydraulic percussive device
SU1647131A1 (en) Hydraulic percussive device