SU138906A1 - The method of fastening the bottomhole zone of plug-forming wells - Google Patents

The method of fastening the bottomhole zone of plug-forming wells

Info

Publication number
SU138906A1
SU138906A1 SU674200A SU674200A SU138906A1 SU 138906 A1 SU138906 A1 SU 138906A1 SU 674200 A SU674200 A SU 674200A SU 674200 A SU674200 A SU 674200A SU 138906 A1 SU138906 A1 SU 138906A1
Authority
SU
USSR - Soviet Union
Prior art keywords
plug
fastening
bottomhole zone
forming wells
mixture
Prior art date
Application number
SU674200A
Other languages
Russian (ru)
Inventor
И.А. Назаров
Original Assignee
И.А. Назаров
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by И.А. Назаров filed Critical И.А. Назаров
Priority to SU674200A priority Critical patent/SU138906A1/en
Application granted granted Critical
Publication of SU138906A1 publication Critical patent/SU138906A1/en

Links

Landscapes

  • Solid-Sorbent Or Filter-Aiding Compositions (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Description

Известны способы креплени  призабойной зоны скважин с применением волокнистых веихеств в качестве аполнител  цементной смеси.Methods are known for securing the well bottom-hole zone using fibrous fibers as the cement inflator.

Предлагаемый способ состоит в том, что в ствол скважины нагнетают смесь целгента с древесными опилками в качестве наполнител .The proposed method consists of injecting a mixture of celgent with sawdust as a filler into the well bore.

Применение такой смеси позвол ет получить в призабойной зоне скважины экран, фильтрующий жидкость, но не пропускающий в ство.т скважины песчинкн из дренированной части продуктивного пласта.The use of such a mixture makes it possible to obtain in the wellbore zone a screen that filters the fluid, but does not allow sandcores from the drained part of the reservoir to pass into the wellbore.

Технологи  креплени  по данному способу заключаетс  в следующем . Древесные онилки дл  предварительного приготовлени  механлческой смеси в соотношени х - один объе.м цемента и два объема опилок должны быть предварительно высущены и пропущены через сито.The fastening technology for this method is as follows. Wood preservatives for the preliminary preparation of a mechano mixture in ratios of one volume of cement and two volumes of sawdust must be pre-dried and passed through a sieve.

Механическа  смесь цемент-опилки в пропорции I : 2 по объему изготовл етс  на-складах и доставл етс  на скважину в мешках. Смесь приготавливаетс  на морской воде. Вода беремс  в количестве 50% от объема механической смеси.Mechanical mixture of cement sawdust in proportion I: 2 by volume is produced in warehouses and delivered to the well in bags. The mixture is prepared in seawater. Water in the amount of 50% of the volume of the mechanical mixture.

После промывки песчаной пробки определ етс  поглотительна  способность пласта. Заливочные трубы устанавливаютс  на 5-6 м выше верхних отверстий фильтра. Затем, при открытом затрубном пространстве , в заливочные трубы закачиваетс  цементно-опилочный раствор, проталкиваемый расчетным количеством воды. После этого перекрываетс  затрубный кран, и раствор продавливаетс  за перфорированную колонну.After washing the sand plug, the absorption capacity of the formation is determined. The filling pipes are installed 5-6 m above the upper openings of the filter. Then, with an open annulus, cement-sawdust is pumped into the casting pipes, pushed by the calculated amount of water. Thereafter, the annular cock closes, and the solution is forced through the perforated column.

При хорощей поглотительной способности пласта за перфорированную колонну продавливаетс  весь раствор, закаченный в заливо-iные .трубы, и затем еще 0,5 м воды дл  лучшей промывки фильтра скважины.With a good absorption capacity of the reservoir, the entire solution pumped into the flood pipes and then another 0.5 m of water is forced through the perforated column and then another 0.5 m of water is used to flush the well filter better.

138906 138906

При слабой поглотительной способности пласта нагнетание раствора производитс  до момента, когда увеличение давлени  на насосе достигнет допустимой расчетной величины.With a weak absorptive capacity of the reservoir, the injection of the solution is carried out until the moment when the pressure increase at the pump reaches the allowable design value.

После окончани  процесса заливки, заливочные трубы приподнимаютс  на 30-50 м выше фильтра и через сутки провер етс  состо ние забо . Если фильтрова  часть колонны открыта, скважину пускают (2-3 дн ) плавным запуском через двое суток после заливки.After the completion of the pouring process, the pouring pipes rise 30-50 m above the filter and after a day the state of the slab is checked. If the filter part of the column is open, the well is started up (2-3 days) by smooth start two days after pouring.

Предмет изобретени Subject invention

Способ креплени  призабойной зоны пробкообразующих скважии, отличающийс  тем, что, с целью получени  в призабойной зоне з-крана, фильтрующего жидкость, но не пропускающего в ствол скважины песчинок из дренированной части продуктивного пласта, в призабойную зону нагнетают цементную смесь с древесными опилками R качестве наполнител .The method of attaching the bottomhole zone of the probokoobrazny wells, characterized in that, in order to obtain in the bottomhole zone of the s crane, filtering liquid, but not letting sand into the well bore from the drained part of the reservoir, the cement mixture with sawdust R is injected into the well bore .

SU674200A 1960-07-19 1960-07-19 The method of fastening the bottomhole zone of plug-forming wells SU138906A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU674200A SU138906A1 (en) 1960-07-19 1960-07-19 The method of fastening the bottomhole zone of plug-forming wells

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU674200A SU138906A1 (en) 1960-07-19 1960-07-19 The method of fastening the bottomhole zone of plug-forming wells

Publications (1)

Publication Number Publication Date
SU138906A1 true SU138906A1 (en) 1960-11-30

Family

ID=48295026

Family Applications (1)

Application Number Title Priority Date Filing Date
SU674200A SU138906A1 (en) 1960-07-19 1960-07-19 The method of fastening the bottomhole zone of plug-forming wells

Country Status (1)

Country Link
SU (1) SU138906A1 (en)

Similar Documents

Publication Publication Date Title
KR830009347A (en) Suction anchor and how to install it
RU2221130C1 (en) Technique limiting water inflow into production well
CN107575186A (en) One kind crosses screen casing sand-preventing process
CN106194105A (en) Profile control method is thrown in blocking agent deep
RU2315171C1 (en) Method for water influx zone isolation inside well
SU138906A1 (en) The method of fastening the bottomhole zone of plug-forming wells
CN107461182B (en) Layering fracturing sand control method
RU2183724C2 (en) Method of recovery of bottom-hole formation zone of gas well
SU1754880A1 (en) Method for solidifying bottom zone of wells with sand flow
SU467995A1 (en) The method of processing wellbore zone
RU2006139414A (en) METHOD FOR ISOLATING A PRODUCTIVE LAYER WHEN CEMENTING A CASE
RU1788148C (en) Construction of watertight screen in ground
SU672329A1 (en) Method of isolating waters
CN208106396U (en) A kind of low permeability oil and gas field increasing injection device
SU135059A1 (en) Method for reducing water and gas content in produced oil
RU2030552C1 (en) Cementing casing head
RU2059788C1 (en) Method for completion of oil wells
RU2054525C1 (en) Method for well completion
SU972145A1 (en) Method of hydraulic working of high-gas coal seam
RU2083813C1 (en) Compound for treating down-hole zone of oil beds
RU2145379C1 (en) Method of selective water shutoff in well
SU742578A1 (en) Formation isolation method
SU1121441A1 (en) Method of cementing large-diameter casings
RU2206731C1 (en) Method of treatment of well bottom-hole zone
RU2066733C1 (en) Method for shutoff of water inflow to producing well