SU1176090A1 - Roof bolt - Google Patents

Roof bolt Download PDF

Info

Publication number
SU1176090A1
SU1176090A1 SU843710372A SU3710372A SU1176090A1 SU 1176090 A1 SU1176090 A1 SU 1176090A1 SU 843710372 A SU843710372 A SU 843710372A SU 3710372 A SU3710372 A SU 3710372A SU 1176090 A1 SU1176090 A1 SU 1176090A1
Authority
SU
USSR - Soviet Union
Prior art keywords
anchor
rod
tubular
split
cement
Prior art date
Application number
SU843710372A
Other languages
Russian (ru)
Inventor
Лев Сергеевич Гребенщиков
Кабды-Хаким Маулетбаевич Мейрембаев
Original Assignee
Grebenshchikov Lev S
Mejrembaev Kabdy Khakim M
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Grebenshchikov Lev S, Mejrembaev Kabdy Khakim M filed Critical Grebenshchikov Lev S
Priority to SU843710372A priority Critical patent/SU1176090A1/en
Application granted granted Critical
Publication of SU1176090A1 publication Critical patent/SU1176090A1/en

Links

Landscapes

  • Dowels (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

АНКЕР, включающий разрезную трубчатую штангу с упорным кольцом на выступающем конце, о т л и ч а ю- .щ и и с  - тем, что, с целью повышени  несущей .способности трубчатого анкера при работе в режиме податливости, полость трубчатой штанги заполнена расшир ющейс  при затвердевании смесью на цементной основе, при этом в устье штанги установлена запирающа  пробка. / S ч Од СО оANCHOR, including a split tubular rod with a stop ring at the protruding end, which means that, in order to increase the carrying capacity of the tubular anchor when operating in the compliance mode, the cavity of the tubular rod is expanded hardening with a cement-based mixture, with a locking plug installed at the mouth of the rod. / S h od s o o

Description

Изобретение относитс  к горной промышленности , а именно к креплению горных выработок- с помощью анкеров.The invention relates to the mining industry, namely to the fastening of mine workings with the help of anchors.

Целью изобретени   вл етс  повышение несущей способности трубчатого анкера при работе в режиме податливости .The aim of the invention is to increase the carrying capacity of the tubular anchor when operating in compliance mode.

На фиг. 1 изображен анкер в начальный момент установки его в шпур; на фиг.2 - анкерпосле расширени  затвер-, девшей смеси, размещенной в его полости .FIG. 1 shows the anchor at the initial moment of its installation into the hole; Fig. 2 shows the ankerpal after expansion of the hardened, virgin mixture placed in its cavity.

Анкер состоит из установленной в шпуре 1 разрезной -трубчатой штанги 2 с упорным кольцом на выступающем конце, расшир ющейс  при затвердевании смеси 3 на цементн9й основе и запирающей пробки 4.The anchor consists of a split-tube-shaped rod 2 installed in the hole 1, with a stop ring on the protruding end, which expands when the mixture 3 is solidified on a cement base and the stopper plug 4.

Анкер устанавливают следующим образом.Anchor set as follows.

В пробуренный шпур 1 ввод т разрезную трубчатую штангу 2. Затем заполн ют полость разрезной трубчатой штанги 2 расшир ющейс  при затвердевании смесью 3, например цементнопесчаньзм раствором с использованием напр гающего цемента. Причем,.дл  заполнени  разрезной трубчатой штангиA split tubular rod 2 is inserted into the drilled hole 1. Then the cavity of the split tubular rod 2 is filled, and the mixture 3 expands during solidification, for example, cement sand with a pressure cement. Moreover, for filling the split tubular bar

2,установленной в шпуре 1, расшир ющейс  смесью 3 примен ют то же оборудование , что и дл  заполнени  шпуров цементно-песчаным раствором при установке железобетонных анкеров, затем устанавливают запирающую пробку 4.2, installed in the hole 1, the expanding mixture 3, use the same equipment as for filling the holes with a cement-sand mortar when installing reinforced concrete anchors, then install the stopper plug 4.

. По мере отверждени  смеси 3 происходит увеличение ее в объеме. При этом под воздействием радиального давлени  расшир ющейс  смеси 3, стенки разрезной трубчатой штанги 3 деформируютс  и плотно прижимаютс  к ..стенкам шпура 1. Увеличение- площади контактировани  стенок разрезной тручатой штанги 2 со стенками шпура 1 повышает несущую способность анкера при работе его в режиме податливости в случае перегрузки (в зонах повьш1енного горного давлени ). Кроме того, при использовании расшир ющейс  смеси возможно изготовление трубчатых разрезных анкерных штанг из недорогой стали, так как снижение упругих свойств такой стали компенсируетс  радиальным давлением, создаваемым расшир ющейс  смесью в полости анкера.. As the mixture 3 solidifies, its volume increases. Under the influence of the radial pressure of the expanding mixture 3, the walls of the split tubular rod 3 are deformed and tightly pressed against the walls of the hole 1. Increasing the contact area of the walls of the split pipe rod 2 with the walls of the hole 1 increases the bearing capacity of the anchor during its operation in compliance in case of overload (in areas of increased rock pressure). In addition, when using an expanding mixture, it is possible to manufacture tubular split anchor rods from inexpensive steel, since the decrease in the elastic properties of such steel is compensated for by the radial pressure created by the expanding mixture in the cavity of the anchor.

Claims (1)

АНКЕР, включающий разрезную трубчатую штангу с упорным кольцом на выступающем конце, о т л и ч а ю— ,щ и й с я· тем, что, с целью повышения несущей способности трубчатого анкера при работе в режиме податливости, полость трубчатой штанги заполнена расширяющейся при затвердевании смесью на цементной основе, при этом в устье штанги установлена запирающая пробка.ANCHOR, which includes a split tubular rod with a thrust ring on the protruding end, with the exception of the fact that, in order to increase the bearing capacity of the tubular anchor when working in the compliance mode, the cavity of the tubular rod is filled with an expanding when hardening with a cement-based mixture, a locking plug is installed in the mouth of the rod. фигЛfigl 1 1176090 .21 1176090 .2
SU843710372A 1984-01-25 1984-01-25 Roof bolt SU1176090A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU843710372A SU1176090A1 (en) 1984-01-25 1984-01-25 Roof bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU843710372A SU1176090A1 (en) 1984-01-25 1984-01-25 Roof bolt

Publications (1)

Publication Number Publication Date
SU1176090A1 true SU1176090A1 (en) 1985-08-30

Family

ID=21107206

Family Applications (1)

Application Number Title Priority Date Filing Date
SU843710372A SU1176090A1 (en) 1984-01-25 1984-01-25 Roof bolt

Country Status (1)

Country Link
SU (1) SU1176090A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU172870U1 (en) * 2016-10-10 2017-07-28 Ильдар Мухаметович Кутлубаев Tubular anchor

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Широков А.П. Теори и практика применени анкерной крепи, М., Недра, 1981, с. 43-44. Скотт Д. Нова анкерна крепь, Глюкауф, 1980, № 3, с. 6-8 (прототип) . *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU172870U1 (en) * 2016-10-10 2017-07-28 Ильдар Мухаметович Кутлубаев Tubular anchor

Similar Documents

Publication Publication Date Title
SU651717A3 (en) Ground anchor and method of fitting same
US3139730A (en) Rock anchor
US4896416A (en) Anchoring method
GB1502476A (en) Construction of underground tunnels and rock chambers
CA2890020C (en) Device, method and system for loading fixatives for rock bolts
RU2344230C2 (en) Method of ground anchor installation and associated device
SU1176090A1 (en) Roof bolt
KR100439968B1 (en) A method of constrution method for tunnel of structure pipe
KR100667183B1 (en) Method of high grouting and that of packer
CN2289830Y (en) Sand consolidation anchor head prestressed rockbolt
SU1652588A1 (en) Method for installing tubular friction anchor
SU1551809A1 (en) Ferroconcrete yieldable roof bolt
SU901552A1 (en) Anchor roof support mounting method
SU1460312A1 (en) Method of setting a tubular roof bolt
JP7442387B2 (en) How to install rock bolts in tunnel construction
SU907266A1 (en) Ferroconcrete yielding anchor
CN218816467U (en) Small-aperture foot-locking anchor cable for extremely soft rock tunnel
SU1221375A1 (en) Roof bolt
JP7401391B2 (en) How to install rock bolts in tunnel construction
SU1731959A1 (en) Friction tubular anchor
SU1102974A1 (en) Ferroconcrete spacer roof bolting
SU1737130A1 (en) Anchor
SU1612089A1 (en) Method and apparatus for setting hole anchor
KR100386298B1 (en) Method and device for slope stabilize of using injection concrete
RU2081332C1 (en) Anchor