SU1165766A1 - Method of securing a well - Google Patents

Method of securing a well Download PDF

Info

Publication number
SU1165766A1
SU1165766A1 SU813234041A SU3234041A SU1165766A1 SU 1165766 A1 SU1165766 A1 SU 1165766A1 SU 813234041 A SU813234041 A SU 813234041A SU 3234041 A SU3234041 A SU 3234041A SU 1165766 A1 SU1165766 A1 SU 1165766A1
Authority
SU
USSR - Soviet Union
Prior art keywords
casing
well
corrosion
applying
coating
Prior art date
Application number
SU813234041A
Other languages
Russian (ru)
Inventor
Кульберды Оразклычев
Original Assignee
Туркменский государственный научно-исследовательский и проектный институт нефтяной промышленности
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Туркменский государственный научно-исследовательский и проектный институт нефтяной промышленности filed Critical Туркменский государственный научно-исследовательский и проектный институт нефтяной промышленности
Priority to SU813234041A priority Critical patent/SU1165766A1/en
Application granted granted Critical
Publication of SU1165766A1 publication Critical patent/SU1165766A1/en

Links

Abstract

1. СПОСОБ КРЕПЛЕНИЯ СКВАЖИНЫ , включающий нанесение антикоррозионного покрыти  на обсадную колонну, спуск ее в скважину, заполненную буровым раствором и последующее цементирование. отличающийс  тем, что, с целью повышени  эффективности креплени  скважины за счет уменьшени  коррозии обсадной колонны, уменьшени  затрат времени на нанесение антикоррозионного покрыти  и обеспечени  его равномерности по всей поверхности колонны, нанесение данного покрыти  на обсадную колонну осуш.ествл ют путем заполнени  верхней части скважины антикоррозионным твердеющим составом с адгезионными свойствами к металлу и спуска колонны через антикоррозионный состав, причем врем  твердени  последнего выбирают по меньшей мере равным времени спуска обсадной колонны. 2. Способ по п. 1, отличающийс  тем, § что в качестве антикоррозионного твердеющего состава примен ют эпоксидную смо- СЛ лу с отвердителем. о: СП 05 О51. METHOD OF FIXING A WELL, including applying an anti-corrosion coating on a casing, lowering it into a well filled with drilling mud and subsequent cementing. characterized in that, in order to increase the well casing efficiency by reducing casing corrosion, reducing the time spent on applying an anti-corrosion coating and ensuring its uniformity over the entire surface of the column, applying this coating to the casing is dried by filling the top of the well with anti-corrosion hardening composition with adhesive properties to the metal and descent of the column through the anticorrosive composition, and the time of hardening of the latter is chosen at least p an apparent casing running time. 2. A method according to claim 1, characterized in that § that an epoxy resin mixture with a hardener is used as an anticorrosive hardening composition. About: SP 05 O5

Description

Изобретение относитс  к способам креплени  скважин. Известен способ креплени  скважины, включающий спуск обсадной колонны и последующую прокачку буферной жидкости, очищающей йтенки обсадной колонны 1. Недостатком данного способа  вл етс  то, что он требует обильных объемов прокачки , а полной очистки поверхности обсадных колонн достичь не всегда удаетс . Известен способ креплени  скважин, включающий нанесение антикоррозионного покрыти  на обсадную колонну, спуск обсадной колонны в скважину, заполненную буровым раствором и последующее ее цементирование 2. Недостатком известного способа  вл етс  то, что внутренн   поверхность обсадной колонны, резьбова  часть трубы и муфта не покрываютс  антикоррозионным покрытием . Цель изобретени  - повыщение эффективности креплени  скважины за счет уменьщени  коррозии обсадной колонны, уменьщени  затрат времени на нанесение антикоррозионного покрыти  и обеспечени  его равномерности по всей поверхности колонны. Поставленна  цель достигаетс  тем, что согласно способу креплени  скважины, вклю. чающему нанесение антикоррозионного покрыти  на обсадную колонну, спуск ее в скважину , заполненную буровым раствором и последующее цементирование, нанесение данного покрыти  иа обсадную колонну осуществл ют путем заполнени  верхней части скважины антикоррозионным твердеющим составом с адгезионными свойствами к металлу и спуска колонны через антикоррозионный состав, причем врем  твердени  последнего выбирают по меньщей мере равным времени спуска обсадной колонны. При этом в качестве антикоррозионного твердеющего состава примен ют эпоксидную смолу с отвердителем. На фиг. 1 изображено положение обсадной колонны в процессе спуска; на фиг. 2 - положение обсадной колонны после цементировани . Перед спуском обсадной колонны в верхней части ствола скважины буровой раствор 1 замен ют антикоррозионным твердеющим составом 2 с адгезионными свойствами к металлу (например, эпоксидной смолой с отвердителем). Затем обсадную колонну 3 спускают через антикоррозионный состав . При этом врем  твердени  антикоррозионного состава выбирают по меньшей мере равным времени спуска обсадной колонны . При спуске колонны последн   покрываетс  молекул рным слоем 4 по всей поверхности , как наружной, так и внутренней. Обсадна  колонна изолируетс  от действи  бурового раствора и коррозионной жидкости . Затем обсадную колонну цементируют. По истечении времени цементный раствор затвердевает, образу  надежную изол цию колонны, на контактных поверхност х. Предлагаемый способ значительно уменьшает врем  на нанесение антикоррозионного покрыти  на колонну и обеспечивает равномерность покрыти  по всем боковым поверхност м.The invention relates to methods for well casing. There is a known method of mounting a well, including lowering the casing string and subsequent pumping of the buffer fluid, cleansing the tubing of the casing 1. The disadvantage of this method is that it requires copious pumping volumes, and it is not always possible to achieve complete cleaning of the casing surface. There is a known method of attaching wells, including applying an anticorrosive coating to the casing, lowering the casing into a well filled with drilling mud and its subsequent cementing 2. A disadvantage of the known method is that the inner surface of the casing, the threaded portion of the pipe and the coupling do not cover with an anticorrosive coating . The purpose of the invention is to increase the well casing efficiency by reducing casing corrosion, reducing the time spent on applying an anti-corrosion coating and ensuring its uniformity over the entire surface of the casing. This goal is achieved by the fact that according to the method of mounting a well, including. In order to apply the anticorrosion coating to the casing, lowering it into the well filled with drilling mud and subsequent cementing, applying this coating to the casing is performed by filling the upper part of the well with an anticorrosive hardening compound with adhesion to the metal and lowering the column through the anticorrosive composition, and the hardening of the latter is chosen at least equal to the casing run-off time. In this case, an epoxy resin with a hardener is used as an anticorrosive hardening composition. FIG. 1 shows the position of the casing in the process of descent; in fig. 2 shows the position of the casing after cementing. Before running the casing in the upper part of the borehole, the drilling fluid 1 is replaced with an anticorrosive hardening compound 2 with adhesive properties to the metal (for example, epoxy resin with a hardener). Then the casing 3 is lowered through the anti-corrosion composition. At the same time, the hardening time of the anticorrosive composition is chosen to be at least equal to the casing run-off time. During the descent of the column, the latter is covered with molecular layer 4 over the entire surface, both external and internal. The casing string is isolated from the action of the drilling fluid and corrosive fluid. Then the casing is cemented. After the time has elapsed, the cement slurry hardens, forming a reliable insulation of the column, on the contact surfaces. The proposed method significantly reduces the time it takes to apply an anticorrosive coating to the column and ensures uniform coating on all side surfaces.

Claims (2)

1. СПОСОБ КРЕПЛЕНИЯ СКВАЖИНЫ, включающий нанесение антикоррозионного покрытия на обсадную колонну, спуск ее в скважину, заполненную буровым раствором и последующее цементирование, отличающийся тем, что, с целью повышения эффективности крепления скважины за счет уменьшения коррозии обсадной колонны, уменьшения затрат времени на нанесение антикоррозионного покрытия и обеспечения его равномерности по всей поверхности колонны, нанесение данного покрытия на обсадную колонну осуществляют путем заполнения верхней части скважины антикоррозионным твердеющим составом с адгезионными свойствами к металлу и спуска колонны через антикоррозионный состав, причем время твердения последнего выбирают по меньшей мере равным времени спуска обсадной колонны.1. WAY OF FIXING A WELL, including applying an anti-corrosion coating to the casing, lowering it into a well filled with drilling fluid and subsequent cementing, characterized in that, in order to increase the efficiency of fixing the well by reducing corrosion of the casing, reducing the time required for applying an anti-corrosion coating and ensuring its uniformity over the entire surface of the casing, applying this coating to the casing is carried out by filling the upper part of the borehole anticorrosive hardening composition with adhesive properties to the metal and the descent of the column through the anticorrosive composition, and the hardening time of the latter is chosen at least equal to the time of descent of the casing. 2. Способ по π. 1, отличающийся тем, что в качестве антикоррозионного твердеющего состава применяют эпоксидную смолу с отвердителем.2. The method according to π. 1, characterized in that as an anti-corrosion hardening composition, an epoxy resin with a hardener is used. фиг. 1FIG. 1
SU813234041A 1981-01-12 1981-01-12 Method of securing a well SU1165766A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813234041A SU1165766A1 (en) 1981-01-12 1981-01-12 Method of securing a well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813234041A SU1165766A1 (en) 1981-01-12 1981-01-12 Method of securing a well

Publications (1)

Publication Number Publication Date
SU1165766A1 true SU1165766A1 (en) 1985-07-07

Family

ID=20937969

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813234041A SU1165766A1 (en) 1981-01-12 1981-01-12 Method of securing a well

Country Status (1)

Country Link
SU (1) SU1165766A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Барииов В. Н. и др. Вли ние рецептуры буферной жидкости на качество изол ции затрубного пространства. РНТС. «Бурение, М., ВНИИБТ, 1978, № 1. 2. Титков Н. И. и др. Применение обсадных труб со смоло-песчаным покрытием., «Нефт ное хоз йство, 1969, № 1 *

Similar Documents

Publication Publication Date Title
US3183971A (en) Prestressing a pipe string in a well cementing method
US4653587A (en) Method and apparatus for the sonic cementing of wells in porous formations
US3059697A (en) Method for locking of pipe sections
US3255819A (en) Method and apparatus for improving the bond between a well conduit and cement
SU1165766A1 (en) Method of securing a well
CN106704702B (en) A kind of method that easy built-in pipe is added
SU1134699A1 (en) Well-cementing process
SU1183673A1 (en) Method of locating the puncture of casing in well
SU1199906A1 (en) Method of securing wells
RU2200268C2 (en) Casing for strengthening walls of well
RU1828913C (en) Method for borehole strengthening
SU1670095A1 (en) Method of well cementing
RU2167267C1 (en) Polymer plugging composition
RU2057904C1 (en) Method of borehole fixing
RU2066735C1 (en) Method for well casing in flow rocks
SU1548454A1 (en) Method of milling cracks in metal hydraulic insulation of underground structures
SU810944A1 (en) Borehole-securing method
US3718184A (en) Insulation for a wellbore
CA1299999C (en) Method of cementing a casing in a wellbore
SU1640361A1 (en) Method of setting casing strings in drill holes
RU2161239C1 (en) Method of constructing well of multilayer oil field
SU1677257A1 (en) Method for isolation of lost-circulation high-permeable formation during drilling
RU1788210C (en) Method for isolation of lost-circulation formation in borehole
RU2219329C1 (en) Method fixing oil and gas wells
RU2182646C2 (en) Process of sealing of oil and gas wells