SU1101948A1 - Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle - Google Patents

Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle Download PDF

Info

Publication number
SU1101948A1
SU1101948A1 SU823523964A SU3523964A SU1101948A1 SU 1101948 A1 SU1101948 A1 SU 1101948A1 SU 823523964 A SU823523964 A SU 823523964A SU 3523964 A SU3523964 A SU 3523964A SU 1101948 A1 SU1101948 A1 SU 1101948A1
Authority
SU
USSR - Soviet Union
Prior art keywords
phase
section
substation
power transmission
high voltage
Prior art date
Application number
SU823523964A
Other languages
Russian (ru)
Inventor
Юрий Иосифович Лысков
Виктор Николаевич Подъячев
Original Assignee
Ордена Октябрьской Революции Всесоюзный Государственный Проектно-Изыскательский И Научно-Исследовательский Институт "Энергосетьпроект"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ордена Октябрьской Революции Всесоюзный Государственный Проектно-Изыскательский И Научно-Исследовательский Институт "Энергосетьпроект" filed Critical Ордена Октябрьской Революции Всесоюзный Государственный Проектно-Изыскательский И Научно-Исследовательский Институт "Энергосетьпроект"
Priority to SU823523964A priority Critical patent/SU1101948A1/en
Application granted granted Critical
Publication of SU1101948A1 publication Critical patent/SU1101948A1/en

Links

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

СПОСОБ ОТКЛЮЧЕНИЯ ЭЛЕКТРОПЕРЕДАЧИ СВЕРХВЫСОКОГО НАПРЯЖЕНИЯ В ПИКЛЕ ОДНОФАЗНОГО АВТОМАТИЧЕСКОГОПОВТОРНОГО ВКЛЮЧЕНИЯ, при котором релейной защитой контролируют состо ние электропередачи , состо щей из двух концевых подстанций , переключательного пункта и двух участков линии, определ ют поврежденный участок, выбирают фазу с коротким замыканием и по сигналу релейной защиты отключают ее выключател ми по концам этого участка, отличающийс  тем, что, с целью снижени  перенапр жений и подавлени  тока подпитки дуги при отсутствии на переключательном пункте источника питани  и потребител , задержиЕзают отключение выключател  поврежденного участка на переключате ,пьно.м пункте на врем , достаточное дл  передачи сигнала релейной защиты на концевую подстанцию неповрежденного участка и ()тключе И1  поврежденной фазы выключате;1ем это}} подстанции. СО 4 00METHOD OF DISCONNECTING ELECTRIC TRANSMISSION OF ULTRA-HIGH VOLTAGE IN THE SINGLE-PHASE AUTOMATIC-REPEATED PICTLE PICTLE, in which the switching over-off-off-off-off-off-off-off-off-off-off-off-off-order switching devices and from the two sections of the switching stations and the two sections of the line will be provided by the default switching units; its switches at the ends of this section, characterized in that, in order to reduce overvoltages and suppress the arc feed current in the absence of reklyuchatelnom paragraph power source and the consumer, zaderzhiEzayut switch off the damaged portion on swi, pno.m paragraph for a time sufficient for relaying the transmission signal at the terminal portion of intact and substation () tklyuche I1 faulty phase are switched off;}} 1em this substation. CO 4 00

Description

Изобретение относится к электротехнике и, в частности к защите электрических сетей сверхвысокого напряжения.The invention relates to electrical engineering and, in particular, to the protection of electrical networks of extra-high voltage.

Известен способ отключения однофазного повреждения в цикле автоматического повторного включения, при котором отключают три фазы линии [1].A known method of disabling single-phase damage in a cycle of automatic re-inclusion, in which disconnect the three phases of the line [1].

Наиболее близким техническим решением к изобретению является способ отключения однофазного повреждения в цикле однофазного автоматического повторного включения (ОАПВ), при котором контролируют состояние каждого участка линии, определяют поврежденный участок, выбирают фазу с коротким замыканием и по сигналу релейной защиты отключают ее но концам поврежденного участка [2].The closest technical solution to the invention is a method of disabling single-phase damage in a single-phase automatic re-enable (OAF) cycle, in which the condition of each section of the line is monitored, the damaged section is determined, the phase with a short circuit is selected and disconnected from the ends of the damaged section by the relay protection signal [ 2].

Однако при сооружении линии большой протяженности для повышения их надежности возникает необходимость в сооружении переключательного пункта. В этом случае применение известного способа отключения однофазного повреждения в цикле ОАПВ в ряде случаев приведет к перекрытию изоляции на неповрежденном участке линии, а отключение линии у концевых подстанций приведет к увеличению тока подпитки дуги (за счет электромагнитной составляющей), при этом самопогасание дуги в паузу ОАПВ не произойдет и ОАПВ будет неуспешным, т. е. значительно снижает ся надежность работы электропередачи.However, when constructing a long line to increase their reliability, there is a need for the construction of a switching point. In this case, the application of the known method of disconnecting single-phase damage in the OAPV cycle in some cases will lead to overlapping insulation on the undamaged section of the line, and disconnecting the line at the terminal substations will increase the arc feed current (due to the electromagnetic component), while the arc self-quenching during the OAPV pause will not happen and OAPV will be unsuccessful, i.e., the reliability of the power transmission is significantly reduced.

Цель изобретения — снижение перенапряжений на отключаемой фазе линии, а также.подавление тока подпитки дуги при отсутствии на переключатепьном пункте источника питания и потребителя.The purpose of the invention is to reduce overvoltages on the disconnected phase of the line, as well as suppress the arc feed current in the absence of a power source and consumer at the switching point.

Поставленная цель достигается тем, что согласно способу отключения электропередачи сверхвысокого напряжения в цикле однофазного автоматического повторного включения, при котором релейной защитой контролируют состояние электропередачи, состоящей из двух концевых подстанций, переключательного пункта и двух участков линии, соединенных выключателями на концевых подстанциях и переключательном пункте, определяют поврежденный участок, выбирают фазу с коротким замыканием и по сигналу релейной защиты отключают ее выключателями по концам этого участка, задерживают отключение выключателя поврежденного участка на переключательном пункте на время, достаточное для передачи сигнала релейной защиты на концевую подстанцию неповрежденного участка и отключения поврежденной фазы выключателем этой подстанции.This goal is achieved by the fact that according to the method of shutting off the extra-high voltage power transmission in a single-phase automatic restart cycle, in which the relay protection controls the state of the power transmission, consisting of two terminal substations, a switching point and two sections of the line connected by switches at the terminal substations and the switching point, determine damaged area, select the phase with a short circuit and, according to the relay protection signal, disconnect it with switches at the ends of this section, the circuit breaker of the damaged section at the switching point is delayed for a time sufficient to transmit the relay protection signal to the terminal substation of the undamaged section and the circuit breaker is turned off by the circuit breaker of this substation.

Способ реализуется в следующей последовательности, сначала контролируют состоя ние каждого участка электропередачи, затем определяют поврежденный участок, выбирают фазу с коротким замыканием, по сигналу релейной защиты отключают вы5 ключатели поврежденной фазы у концевых подстанций, и с выдержкой времени отключают выключатель на переключательном пункте.The method is implemented in the following sequence, first, the state of each power transmission section is monitored, then the damaged section is determined, the phase with a short circuit is selected, the relay of the damaged phase at the terminal substations is turned off by a relay signal, and the circuit breaker is turned off with a time delay.

На чертеже показана электропередача с промежуточной подстанцией, на котророй нагрузка н источники питания отключены. Устройство содержит электропередачу с участками 1 и 2. соединенных промежуточной подстанцией 3, на которой источники питания и нагрузка отключены. На концеJ вых подстанциях установлены выключатели 4 и 5. на промежуточной подстанции — выключатели 6 и 7. На участках 1 и 2 установлены соответственно блоки о и 9 релейной защиты, соединенные с блокамиThe drawing shows a power transmission with an intermediate substation, on which the load and power sources are disconnected. The device comprises a power transmission with sections 1 and 2. connected by an intermediate substation 3, on which the power sources and load are disconnected. Switches 4 and 5 are installed at the end of the J output substations. Switches 6 and 7 are installed at the intermediate substation. Relay protection blocks o and 9, connected to the blocks, are installed in sections 1 and 2, respectively.

ОАПВ И) и 11 на концевых подстанциях и блоки ОАПВ 12 и 13 - на промежуточной подстанции. Блоки ОАПВ Ю и II соединены соответственно с выключателями 4 и 5 на концевых подстанциях, блоки ОАГ1В И и 12 соединены с выключателями 6 и 7 25 па промежуточной подстанции 3 через блоки задержки 14 и 15 соответственно.OAPV I) and 11 at the terminal substations and blocks OAPV 12 and 13 - at the intermediate substation. Blocks OAPV Yu and II are connected respectively with switches 4 and 5 at the terminal substations, blocks OAG1V And 12 are connected with switches 6 and 7 25 pa of intermediate substation 3 through delay blocks 14 and 15, respectively.

При возникновении короткого замыкания на' участке 1 электропередачи срабатывает блок 8 релейной защиты контролирующий работу участка 1 электропередачи, и подает сигнал на блоки ОАПВ 10—13, определяющие поврежденную фазу. Блоки ОАПВ 10 и 11 передают команду на отключение поврежденной фазы на концевых подстанциях· выключателями 4 и 5.If a short circuit occurs in the power transmission section 1, the relay protection unit 8 controls the operation of the power transmission section 1, and sends a signal to the OAPV 10-13 blocks that determine the damaged phase. Blocks OAPV 10 and 11 transmit a command to turn off the damaged phase at the end substations · switches 4 and 5.

3<; Сигналы от блоков ОАПВ 12 и 13 через блоки 14 и 15 задержки вызывают отключение выключателей 6 и 7 на промежуточной подстанции с задержкой по времени, достаточной для отключения поврежденной фазы выключателями 4 и 5 на концевых подстан40 циях. 3 <; Signals from OAPV blocks 12 and 13 through delay blocks 14 and 15 cause the circuit breakers 6 and 7 to trip at the intermediate substation with a time delay sufficient to shut off the damaged phase by switches 4 and 5 at the terminal substations40.

Аналогично работает устройство при возникновении короткого замыкания на участке 2, при котором сначала срабатывает блок, контролирующий работу участка 2.The device works similarly when a short circuit occurs in section 2, in which the unit that first controls the operation of section 2 is triggered.

Предлагаемый способ по сравнению с известным позволяет снизить перенапряжения на неповрежденном участке линии электропередачи и пбдавить ток подпитки дуги. Так при отключении поврежденной фазы у концевых подстанций напряжение на ней 50 не превышает номинальное, а последующее отключение выключателя в промежуточной точке уменьшает длину поврежденного участка и, следовательно, уменьшает ток подпитки дуги пропорциональный этой длине.The proposed method, in comparison with the known method, allows to reduce overvoltages in the undamaged section of the power line and to suppress the arc recharge current. So when disconnecting the damaged phase at the terminal substations, the voltage on it 50 does not exceed the rated voltage, and the subsequent opening of the circuit breaker at the intermediate point reduces the length of the damaged section and, therefore, reduces the arc feed current proportional to this length.

ВНИИПИ Заказ 4688/39VNIIIPI Order 4688/39

Филиал ППП «Патент», гBranch of PPP "Patent", g

Тираж 614 ПодписноеCirculation 614 Subscription

Ужгород, ул. Проектная, 4Uzhhorod, st. Project, 4

Claims (1)

СПОСОБ ОТКЛЮЧЕНИЯ ЭЛЕКТРОПЕРЕДАЧИ СВЕРХВЫСОКОГО НАПРЯЖЕНИЯ В ЦИКЛЕ ОДНОФАЗНОГО АВТОМАТИЧЕСКОГО ПОВТОРНОГО ВКЛЮЧЕНИЯ, при котором релейной за- щитой контролируют состояние электропередачи. состоящей из двух концевых подстанций, переключательного пункта и двух участков линии, определяют поврежденный участок, выбирают фазу с коротким замыканием и по сигналу релейной защиты отключают ее выключателями по концам этого участка, отличающийся тем, что. с целью снижения перенапряжений и подавления тока подпитки дуги при отсутствии на переключательном пункте источника питания и потребителя, задерживают отключение выключателя поврежденного участка на переключательном пункте на время, достаточное для передачи сигнала релейной защиты на концевую подстанцию неповрежденного участка и отключения поврежденной выключателем этой подстанции.METHOD OF DISABLING ELECTRIC TRANSMISSION OF EXTRA HIGH VOLTAGE IN THE SINGLE-PHASE AUTOMATIC REPEATING CYCLE, in which relay protection monitors the state of power transmission. consisting of two terminal substations, a switching point and two sections of the line, the damaged section is determined, the phase with a short circuit is selected and, by the relay protection signal, it is turned off by switches at the ends of this section, characterized in that. in order to reduce overvoltages and suppress the arc feed current when there is no power source and consumer at the switching point, the circuit breaker of the damaged section at the switching point is delayed for a time sufficient to transmit the relay protection signal to the terminal substation of the undamaged section and shutting down this substation damaged by the switch. фазы iphase i
SU823523964A 1982-12-20 1982-12-20 Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle SU1101948A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823523964A SU1101948A1 (en) 1982-12-20 1982-12-20 Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823523964A SU1101948A1 (en) 1982-12-20 1982-12-20 Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle

Publications (1)

Publication Number Publication Date
SU1101948A1 true SU1101948A1 (en) 1984-07-07

Family

ID=21039880

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823523964A SU1101948A1 (en) 1982-12-20 1982-12-20 Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle

Country Status (1)

Country Link
SU (1) SU1101948A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Богорад А. М. Назаров Ю. Г. Автоматическое повторное включение и энергосистемах. М., «Энерги , 1969, с. 145. 2. Там же, с. 237-240 (прототип). *

Similar Documents

Publication Publication Date Title
EP3306766B1 (en) Direct current power transmission system, central server of same, and method for restoring direct current power transmission pathway after failure
SU1101948A1 (en) Method of de-energizing super-high voltage voltage power transmission in single-phase automatic reclosing cycle
US3388297A (en) Automatic sectionalizing of electric power distribution systems
US5689397A (en) Arrangement for disconnecting branches of a low voltage supply network under short circuit conditions
SU1236575A1 (en) Method of detecting faulted section of line
CN210941437U (en) Ground automatic neutral section passing processing device
RU190076U1 (en) DEVICE OF RELAY PROTECTION OF CABLES AND AIR LINES AGAINST SHORT CIRCUITS
RU2016453C1 (en) Equipment for protection of electric installations of three-phase network in case of fault of neutral wire
SU1030911A1 (en) Device for power transmission to three-phase loads in isolated neutral system
SU1192025A1 (en) Device for arcing short circuit protection in cells of factory-assembled siwtch-gear
SU964832A1 (en) Device for advancing sectionalizing in ac network
SU1686592A1 (en) Device for protection against damage of electromagnets for control over oil circuit breakers with groups of interlocking contacts
SU955348A1 (en) Device for reserving electric power line relay protection
RU1815725C (en) Device for protection of sectionalized mains with tapped transformers and short-circuiting switches
SU966806A1 (en) Method of phasewise automatic reconnection of generator-transformer-line block
SU748672A1 (en) Device for disconnection of electric equipment at short-circuiting in ac network
SU1081725A1 (en) Method of extinguishing single-phase short circuit arc in system with solidly earthed neutral,which allows operation with isolated neutral as well with neutral via compensating coil
SU803068A2 (en) Device for redundancy of switch failure
SU1485349A1 (en) Device for protection against single-phase partial ground in branched power transmission network
SU1670741A1 (en) Device for automatic switching-on of standby equipment
SU1203623A1 (en) Device for selecting faulted wire of electric power line with additional wire
SU904094A1 (en) Substation with switches of load
SU1100674A1 (en) Method of automatic phase de-energizing of high-voltage power line
SU1644287A1 (en) Device for centralized overcurrent protection of network
SU114366A1 (en) Device for automatically switching on high voltage distribution network sections