SU1094896A1 - Method of constructing ramp-type pier - Google Patents

Method of constructing ramp-type pier Download PDF

Info

Publication number
SU1094896A1
SU1094896A1 SU823557772A SU3557772A SU1094896A1 SU 1094896 A1 SU1094896 A1 SU 1094896A1 SU 823557772 A SU823557772 A SU 823557772A SU 3557772 A SU3557772 A SU 3557772A SU 1094896 A1 SU1094896 A1 SU 1094896A1
Authority
SU
USSR - Soviet Union
Prior art keywords
columns
pontoons
extreme
jacks
water
Prior art date
Application number
SU823557772A
Other languages
Russian (ru)
Inventor
Юрий Дмитриевич Кравчук
Борис Александрович Мялкин
Иван Семенович Ковалев
Original Assignee
Войсковая Часть 13073
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Войсковая Часть 13073 filed Critical Войсковая Часть 13073
Priority to SU823557772A priority Critical patent/SU1094896A1/en
Application granted granted Critical
Publication of SU1094896A1 publication Critical patent/SU1094896A1/en

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

СПОСОБ МОНТАЖА ПРИЧАЛА ЭСТАКАДНОГО ТИПА путем буксировки колонн и понтонов к месту монтажа, заглублени  в грунт крайних колонн,затем промежуточнбк колонн, подъем понтонов над водой с помощью домкратов и закрепление лонтонов на колоннах, отличающийс  тем, что, с целью снижени  стоимости и сокращени  сроков воздействи  причала, в качестве крайних колонн используют колонны с рейками и винтовыми домкратами , на которых поднимают понтоны над водой, затем заглубл ют промежуточные колонны в виде труб, а крайние колонны удал ют и вместо удаленных колонн с рейками устанавливают колонны в В1вде труб. (О о со СХ) ( О5 (Риг.1METHOD OF MOUNTING THE MOTTING OF THE MALE TYPE by towing columns and pontoons to the installation site, digging the extreme columns into the ground, then intermediate columns, raising the pontoons above the water with jacks and fixing the lantons on the columns, characterized in that in order to reduce the cost and reduce the time berths, as extreme columns, use columns with slats and screw jacks on which pontoons are raised above the water, then the intermediate columns are buried in the form of pipes, and the extreme columns are removed and instead of Alain columns with rails mounted in the column V1vde pipes. (About about with SH) (O5 (Rig.1

Description

110 Изобретение относитс  к гидротехническому строительству, а именно к воздействию причалов эстакадного типа. Известны способы возведени  стационарных причалов, основанные на использовании дл  погружени  свай (колонн-оболочек) плавучих кондукторов и последующем обустройстве свайного основани  верхним строением СтД Недостатком таких способов  вл етс  длительность и больша  трудоемкость монтажа верхнего строени ,что заметно удорожает стоимость причала и удлин ет сроки работ. Известен также способ монтажа при чала эстакадного типа путем ки колонны и понтонов к месту монтажа , заглублени  в грунт крайних, затем промежуточных колонн, подъем понтонов над водой с помощью домкратов и закреплени  понтонов на колоннах 12. Подьем понтонов в проектное положение осуществл етс  с помощью домкратов . Однако дл  монтажа причалов с помощью домкратов требуетс  большое их количество и специальных колонн, что усложн ет проведение монтажных работ и увеличивает их стоимость. При подъ еме не обеспечиваетс  равномерна  пере,п,ача нагрузки на колонны. Целью изобретени   вл етс  снижение стоимости и сокращение сроков возведени  пр1гчалов. Поставленна  цель достигаетс  тем что в качестве крайних колонн исполь зуют колонны с рейками и винтовыми домкратами, на которых поднимают понтоны над водой, затем заглубл ют промежуточные колонны в виде труб, а крайние колонны удал ют и вместо удаленных колонн с рейками устанавливают колонны в виде труб. На фиг. 1 показан подъем понтонамодул  над водой, общий вид; на фиг. 2 - понтон, план; на фиг. 3 схема погружени  промежуточных колонн-труб в грунт; на фиг. 4 - схема последовательного извлечени  колонн с рейками с помощью домкратов и кра™ на и замена их на обычные колоннытрубы; на фиг. 5 - смонтированный причал, общий вид. Понтон-модуль 1, заранее оборудованный по углам домкратами 2 и колоннами с рейками 3, буксируетс  к месту установки, выставл етс  в проектное положение и временно закрепл етс  на  кор х. Установка домкратов и специальных колонн может также производитьс  после раскреплени  понтона на  кор х. Затем понтон 1 с помощью винтовых домкратов 2 по колоннам поднимаетс  над водой (фиг. 1), в средние шахты опускаютс  промежуточные ° обычные колонны-трубы 4 и погружаютс  в грунт на расчетную глубину (фиг. 3), после чего понтоны жестко креп тс  к промежуточным колоннам . Далее с помощью домкратов и крана последовательно извлекаютс  колонны с рейками (фиг. 4), а на их место устанавливаютс  обычные колонны из прокатных труб, которые также заглубл ютс  в грунт на расчетную глубину, после чего жестко соедин ютс  с понтоном. Использование предлагаемого способа позвол ет на 10-15% снизить стоимость возведени  причала эстакадного типа и вдвое сократить едоки строительства по сравнению с базовьш объектом, в качестве которого прин т способ возведени  стационарных причалов с использованием дл  погружени  колонн (труб) плавучих кондукторов.110 The invention relates to hydraulic construction, in particular to the effects of pier type berths. Known methods of erection of stationary moorings are based on the use of floating conductors for immersing piles (column-shells) and subsequent construction of the pile foundation by the ST structure, the disadvantage of such methods is the length and complexity of the installation of the upper structure, which significantly increases the cost of the berth and lengthens the work time. . There is also known a method of mounting a tower-type primer by ki columns and pontoons to the installation site, digging extreme, then intermediate columns into the ground, raising pontoons above the water with jacks and securing the pontoons on the columns 12. Lifting the pontoons to the design position is carried out with the help of jacks . However, the installation of berths with jacks requires a large number of them and special columns, which complicates the installation work and increases their cost. When lifting, the load on the columns is not evenly transferred. The aim of the invention is to reduce the cost and reduce the time required for the construction of the facilities. The goal is achieved by using columns with rails and screw jacks on which the pontoons are lifted above the water, then the intermediate columns are buried in the form of pipes, and the extreme columns are removed and pipes are installed in the form of pipe columns . FIG. 1 shows the rise of a pontoon module above the water, a general view; in fig. 2 - pontoon, plan; in fig. 3 scheme of immersion of intermediate columns-pipes in the ground; in fig. 4 is a schematic diagram of sequential extraction of columns with rails using jacks and edges ™ and replacing them with conventional pipe columns; in fig. 5 - mounted berth, general view. The pontoon module 1, which is equipped in advance at the corners with jacks 2 and columns with rails 3, is towed to the installation site, set in the design position and temporarily fixed on the core. The installation of jacks and special columns can also be carried out after the pontoon has been fastened on the bark. Then the pontoon 1 is raised above the water by means of screw jacks 2 (Fig. 1), intermediate columns of ordinary pipe-pipes 4 are lowered into the middle shafts and immersed in the ground at the design depth (Fig. 3), after which the pontoons are rigidly fixed to intermediate columns. Then, with the help of jacks and a crane, columns with strips (Fig. 4) are successively removed, and in their place conventional columns are installed from rolled tubes, which are also buried in the ground to the calculated depth, after which they are rigidly connected to the pontoon. The use of the proposed method allows reducing the construction cost of a pier type pier by 10-15% and halving construction consumers as compared with the base object, which is a method of constructing stationary berths using floating conductors for immersion of columns (pipes).

(рцг.З(rtsg.Z

Claims (1)

СПОСОБ МОНТАЖА ПРИЧАЛА ЭСТАКАДНОГО ТИПА путем буксировки колонн и понтонов к месту монтажа, заглуб ления в грунт крайних колонн,затем промежуточных колонн, подъем понтонов над водой с помощью домкратов и закрепление понтонов на колоннах, отличающийся тем, что, с целью снижения стоимости и сокращения сроков воздействия причала, в качестве крайних колонн используют колонны с рейками и винтовыми домкратами, на которых поднимают понтоны над водой, затем заглубляют промежуточные колонны в виде труб, а крайние колонны удаляют и вместо удаленных колонн с рейками устанавливают колонны в виде труб.THE METHOD OF INSTALLATION ATTACHED THE TACKET TYPE by towing columns and pontoons to the installation site, deepening the extreme columns into the ground, then intermediate columns, lifting the pontoons above the water with jacks and securing the pontoons on the columns, characterized in that, in order to reduce cost and reduce time the impact of the berth, as the extreme columns use columns with slats and screw jacks, on which the pontoons are lifted above the water, then the intermediate columns are deepened in the form of pipes, and the extreme columns are removed and instead of removed x columns with racks mounted in a pipe string. фиг.1figure 1
SU823557772A 1982-12-24 1982-12-24 Method of constructing ramp-type pier SU1094896A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823557772A SU1094896A1 (en) 1982-12-24 1982-12-24 Method of constructing ramp-type pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823557772A SU1094896A1 (en) 1982-12-24 1982-12-24 Method of constructing ramp-type pier

Publications (1)

Publication Number Publication Date
SU1094896A1 true SU1094896A1 (en) 1984-05-30

Family

ID=21051498

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823557772A SU1094896A1 (en) 1982-12-24 1982-12-24 Method of constructing ramp-type pier

Country Status (1)

Country Link
SU (1) SU1094896A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5046897A (en) * 1989-09-29 1991-09-10 Ray Kenneth B Platform support system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР , 380825, кл. Е 21 В 15/02, 1971. 2. Авторское свидетельство СССР JP 132153, кл. Е 02 В 17/00, 1959 (прототип). / *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5046897A (en) * 1989-09-29 1991-09-10 Ray Kenneth B Platform support system

Similar Documents

Publication Publication Date Title
US5188484A (en) Jack-up type offshore oil and gas production platform and method
US3466878A (en) Rig for work at sea,in lakes,lagoons
EA002258B1 (en) Desk installation system for offshore structures
CA1039520A (en) Bridge beam tower erection method and apparatus
DE3751457T2 (en) Procedure for establishing a marine structure.
US4002038A (en) Method and apparatus for rapid erection of offshore towers
GB2218447A (en) Protective barrier for the protection of offshore marine works and method of installation of the same
JPS589206B2 (en) Land-based plant construction method
US3857247A (en) Offshore tower erection technique
SU1094896A1 (en) Method of constructing ramp-type pier
US2972234A (en) Method of constructing and setting a caisson for a bridge pier or like support
US4290716A (en) Platform resting on the bottom of a body of water, and method of manufacturing the same
US4114392A (en) Platform structure for maritime installations
RU2040638C1 (en) Sleetroof offshore platform
RU2441799C2 (en) Method for construction of floating structures
CN112160303A (en) Offshore wind power booster station platform based on self-installation concept and installation method thereof
RU2064553C1 (en) Immersed movable caisson provided with ice resistance for sea oil well drilling in arctic
US4662780A (en) Method for docking of a floating structure
SU1178838A1 (en) Support column of self-erecting floating installation
Cahay Full Year Drilling Season for MODU in Arctic Area
JP2953818B2 (en) Construction method for deep water structures
SU1276748A1 (en) Gravity-type ferroconcrete offshore foundation
SU1030489A1 (en) Method of installation of support pillars of self-lifting drilling sea platform
RU2085660C1 (en) Method of building seaborne platform
SU1142596A1 (en) Self-raising platform