layer
soil
filling
stone
ungraded
Prior art date
Application number
SU823426945A
Other languages
Russian (ru)
Inventor
Николай Алексеевич Перетрухин
Гавриил Павлович Минайлов
Игорь Дмитриевич Ткачевский
Николай Данилович Меренков
Иван Васильевич Буданов
Михаил Иванович Иванов
Сергей Константинович Матюгин
Original Assignee
Всесоюзный Научно-Исследовательский Институт Транспортного Строительства (Цниис)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный Научно-Исследовательский Институт Транспортного Строительства (Цниис) filed Critical Всесоюзный Научно-Исследовательский Институт Транспортного Строительства (Цниис)
Priority to SU823426945A priority Critical patent/SU1060761A1/en
Application granted granted Critical
Publication of SU1060761A1 publication Critical patent/SU1060761A1/en

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

СПОСОБ ВОЗВЕДЕНИЯ НАСЫПИ , включающий послойную отсыпку грунта с планировкой и уплотнением каждого сло  и обсыпку откосов каменным материалом , отличающийс  тем, что, с целью снижени  трудозатрат, насыпь .возвод т из несортировайного скальйого грунта, причем после отсыпки каждого сло  из него извлекают крупные камни, а обсыпку откосов осуществл ют после отсыпки каждого сло  путем перемещени  извлеченных из этого сло  крупных камней на его откосные части. О A METHOD OF BREAKING A BULK, including layered soil dumping with the layout and compaction of each layer and the filling of slopes with stone material, characterized in that, in order to reduce labor costs, embankment is removed from the non-graded skal soil, and after the filling of each layer, the stone is removed from ungraded skimy soil, and after the filling of each layer, the stone is removed from ungraded scaby soil, and after the filling of each layer, the stone is removed from ungraded scaby soil, and after the filling of each layer, the stone is removed from ungraded scaby soil, and after the filling of each layer, the stone is removed from ungraded scaby soil, and after the filling of each layer, the stone is removed from ungraded scaby soil, and after the filling of each layer, the stone is removed from ungraded scaby soil; and sprinkling of slopes is carried out after each layer is filled by transferring the large stones extracted from this layer to its slopes. ABOUT

Description

Изобретение относитс  к строительству и может быть использовано преимущественно при возведении насыпных земл ных сооружений. Известны способы возведени  дорожных насыпей с противодеформационными бермами ,- включающие возведение насыпи с последующей отсыпкой берм из каменного материала 1. Недостаки известных способов - мала  устойчивость берм и больщие трудозатраты, Наиболее близким к предлагаемому по технической сущности и достигаемому результату  вл етс  .способ возведени  насыпи , включающий послойную отсыпку грунта с планировкой и уплотнением каждого сло  и обсыпку откосов каменным материалом 2. Недостаток известного способа возведени  насыпей - большие трудозатраты. Цель изобретени  - снижение трудозатрат . Указанна  цель достигаетс  тем, что согласно способу возведени  насыпи, включающему послойную отсыпку грунта с планировкой и уплотнением каждого сло  и обсыпку откосов каменным материалом, насыпь возвод т из несортированного скального грунта, причем после отсыпки каждого сло  из него извлекают крупные камни, а обсыпку откосов осуществл ют после отсыпки каждого сло  путем перемещени  извлеченных из этого сло  крупных камней на его откосные части. На фиг. 1 схематично показано размещение машин и механизмов в пределах насыпи при ее возведении согласно предлагаемому способу; на фиг. 2 - поперечный разрез А-А на фиг. 1. Предлагаемый способ заключаетс  в следующем . Несортированный скальный грунт, из которого возвод т насыпь 1 с обсыпкой 2 из крупного камн , транспортируют к месту укладки автосамосвалами 3 из карьера или разрабатываемой дорожной выемки, разравнивают слоем требуемой толщины бульдозером 4, посредством землеройно-транспортной мащины 5 с вилообразным рабочим органом, например корчевателем пней, Затем выгребают из полученного сло  несортированного скального грунта камни заданного размера, перемещают их в сторону откосов и сдвигают на откосы в виде обсыпки 2 проектной щириной I. Землеройно-транспортна  мащина 5 выполн ет челночнообразное чередование рабочих 6 и холостых 7 ходов поперек земл ного полотна или под некоторым углом к его оси. После выгребани  крупных камней заданного размера и укладки их на откос оставщийс  в слое грунт планируют и уплотн ют катком 8 до требуемой нормы плотности. На уплотненный слой грунта . отсыпают следующий слой несортированного скального грунта и описанные выше операции повтор ют, Предлагаемый способ возведени  насыпи позвол ет-совмещать земл ные работы по возведению насыпи с работами по камней требуемого размера и обсыпке ими откосов возводимой насыпи. В результате применени  предлагаемого способа достигаетс  сокращение трудозатрат за счет операций по отсыпке насыпи и обсыпно ее откосов каменным материалом.The invention relates to construction and can be used primarily in the construction of bulk earth structures. There are known methods for erecting road embankments with antideformation berms, including the construction of an embankment with subsequent dumping of stone material berms 1. The disadvantages of the known methods are low berm resistance and high labor costs. The closest to the proposed technical essence and the achieved result is an embankment construction method including layer-by-layer dumping of soil with the layout and compaction of each layer and the sprinkling of slopes with stone material 2. The disadvantage of the known method of construction of embankments is large ie labor. The purpose of the invention is to reduce labor costs. This goal is achieved by the fact that, according to the method of erecting an embankment, which includes layering of soil with the layout and compaction of each layer and the filling of slopes with stone material, the embankment is erected from unsorted rocky soil, and after filling of each layer, large stones are removed from it, and the slopes are excavated after dumping each layer by moving the large stones extracted from this layer to its slopes. FIG. 1 schematically shows the placement of machines and mechanisms within the embankment during its construction in accordance with the proposed method; in fig. 2 is a cross section A-A in FIG. 1. The proposed method is as follows. Ungraded rocky soil, from which the embankment 1 with the sprinkling 2 of large stone is erected, is transported to the place of laying by dump trucks 3 from the quarry or the excavated roadway, is leveled with the required thickness using a bulldozer 4, using a earthmoving transport unit 5 with a fork-like working body, for example a roach stubs. Then, stones of a given size are removed from the resulting layer of unsorted rocky soil, move them to the side of the slopes and shift to the slopes in the form of dusting 2 project width I. Earth oyno-transport maschina 5 performs the job alternation chelnochnoobraznoe 6 and 7 moves across idle peanut web or at an angle to its axis. After digging up large stones of a given size and laying them on the slope, the soil remaining in the layer is planned and compacted by roller 8 to the required density standard. On compacted soil layer. the next layer of unsorted rocky soil is poured and the operations described above are repeated. The proposed embankment method makes it possible to combine earthworks for embankment construction with works on stones of the required size and sprinkling them with slopes of the embankment being built. As a result of the application of the proposed method, labor costs are reduced due to the operations of filling the embankment and sprinkling its slopes with stone material.

Х X

/ Щ / U

у/ /A )/j(, У Срие,2y / / A) / j (, Y Sree, 2

Claims (1)

СПОСОБ ВОЗВЕДЕНИЯ НАСЫПИ, включающий послойную отсыпку грунта с планировкой и уплотнением каждого слоя и обсыпку откосов каменным материалом, отличающийся тем, что, с целью снижения трудозатрат, насыпь возводят из несортированного скального грунта, причем после отсыпки каждого слоя из него извлекают крупные камни, а обсыпку откосов осуществляют после отсыпки каждого слоя путем перемещения извлеченных из этого слоя крупных камней на его откосные части.METHOD FOR BUILDING A BULK, including layering soil with the layout and compaction of each layer and sprinkling the slopes with stone material, characterized in that, in order to reduce labor costs, the embankment is erected from unsorted rocky soil, and after filling each layer, large stones are removed from it, and the sprinkling slopes are carried out after filling each layer by moving large stones extracted from this layer to its sloping parts.
SU823426945A 1982-04-19 1982-04-19 Method of erecting an embankement SU1060761A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823426945A SU1060761A1 (en) 1982-04-19 1982-04-19 Method of erecting an embankement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823426945A SU1060761A1 (en) 1982-04-19 1982-04-19 Method of erecting an embankement

Publications (1)

Publication Number Publication Date
SU1060761A1 true SU1060761A1 (en) 1983-12-15

Family

ID=21007915

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823426945A SU1060761A1 (en) 1982-04-19 1982-04-19 Method of erecting an embankement

Country Status (1)

Country Link
SU (1) SU1060761A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2469147C1 (en) * 2011-07-20 2012-12-10 Василий Петрович Ягин Dam of soil materials

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Справочник по земл ному полотну эксплуатируемых железных дорог. М., «Транспорт, 1978, с. 287. 2. Техйические указани по техйологии сооружейи железйодорожного земл ного полотна, вен 186-75, М., «Оргтрайсстрой, 1975, с. 278-279 (прототип). *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2469147C1 (en) * 2011-07-20 2012-12-10 Василий Петрович Ягин Dam of soil materials

Similar Documents

Publication Publication Date Title
CN109594442A (en) Garden path construction technology
SU1060761A1 (en) Method of erecting an embankement
Breitenbach Rockfill placement and compaction guidelines
RU2273687C1 (en) Roadbed and roadbed forming method
RU2325534C1 (en) Method for mined land reclamation
US3182460A (en) Apparatus for making permeable conduits in subterranean lines of drainage
US4072016A (en) Method of reconstructing and reclamation of river channels
US3191387A (en) Method for making permeable conduits in subterranean lines of drainage
RU2426832C1 (en) Method to build earth water-retaining construction in warm season (versions)
SU1724814A1 (en) Embankment filling method
JPH08177035A (en) Forming method of wing section of checkdam
CN115573354A (en) High-fill construction method
RU2791061C1 (en) Method for waterproofing a man-made container using loose overburden rocks in development of mineral deposits
RU2824540C1 (en) Method for erection of subgrade of cluster pad with geotextile cages
O'Flaherty Earthworks and unbound bases for pavements
RU2055118C1 (en) Method of building earth structure
SU1025898A1 (en) Method of burying waste in natural cavities
CN117926653A (en) Method for half-filling and half-digging roadbed at poor geological interface of soft rock
CN118547542A (en) Construction method of red mud rock crushed gravel soil waterproof roadbed
NL8403796A (en) Method of producing sub-soil water barrier - involves digging up to 15 m deep slot using tractor to move shuttering through slot whilst feeding screen material into it
SU1622517A1 (en) Embankment foundation
RU2145372C1 (en) Method of earth dam construction
Henry et al. THE CONSTRUCTION OF THE NEW HONG KONG AIRPORT.
Malhotra et al. Salient Construction Features of Beas Dam Embankment
CN114086538A (en) Method for replacing open pit bottom sludge by utilizing waste rock partition alternate extrusion