SU1060760A1 - Method of making soil-concrete pile - Google Patents

Method of making soil-concrete pile Download PDF

Info

Publication number
SU1060760A1
SU1060760A1 SU823430233A SU3430233A SU1060760A1 SU 1060760 A1 SU1060760 A1 SU 1060760A1 SU 823430233 A SU823430233 A SU 823430233A SU 3430233 A SU3430233 A SU 3430233A SU 1060760 A1 SU1060760 A1 SU 1060760A1
Authority
SU
USSR - Soviet Union
Prior art keywords
fixing solution
soil
working body
ground
trunk
Prior art date
Application number
SU823430233A
Other languages
Russian (ru)
Inventor
Виктор Егорович Тяглик
Владимир Федорович Давыдов
Виталий Федорович Залого
Валерий Ефимович Сеськов
Валерий Павлович Блецко
Original Assignee
Институт Строительства И Архитектуры Госстроя Бсср
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт Строительства И Архитектуры Госстроя Бсср filed Critical Институт Строительства И Архитектуры Госстроя Бсср
Priority to SU823430233A priority Critical patent/SU1060760A1/en
Application granted granted Critical
Publication of SU1060760A1 publication Critical patent/SU1060760A1/en

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

СПОСОБ ИЗГОТОВЛЕНИЯ ГРУНТОБЕТОННОЙ СВАИ, включающий, формование ствола путем погружени  в грунт рабочего органа с подачей по мере его заглублени  закрепл ющего раствора с одновременным перемешиванием его с грунтом и последующее извлечение рабочего органа после формовани  ствола, отличающийс  тем, что, с целью снижени  материалоемкости без уменьшени  несущей способности изготавливаемой сваи, при подаче закрепл ющего раствора его расход уменьшают по мере заглублени  рабочего органа.A METHOD FOR MANUFACTURING GROUND CONCRETE PILES, including forming the trunk by immersing the working tool in the ground, feeding the fixing solution as it deepens, simultaneously mixing it with the ground, and then removing the working body after forming the trunk, which reduces bearing capacity of the pile being made; when applying a fixing solution, its consumption is reduced as the working body is deepened.

Description

о: Изобретение относитс  к строительству а именно к возведению фундаментов из вис чих свай в грунтах с повышенной деформативностью . Наиболее близким к предлагаемому по технической сущности и достигаемому результату  вл етс  способ изготовлени  грунтобетонной сваи, включающий формование ствола путем погружени  в грунт рабочего органа с подачей по мере его заглублени  закрепл ющего раствора, с одновременным перемешиванием его с грунтом и последующее извлечение рабочего органа после формовани  ствола.. Рабочий агент подают в грунт равномерно по мере заглублени  1 Недостаток известного способа - повыщенный расход материалов (цемента, химических добавок и других компонентов), вследствие того, что сваи имеют одинаковые прочностные характеристики (по материалу ) по всей длине. Равномерна  подача закрепл ющего раствора согласно известному способу приводит к тому, что прочность материала ствола полностью не используетс . Кроме того, снижаетс  прочность материала в оголовке, так как при изготовлении сваи в сторону подощвы уходит часть закрепл ющего раствора. Цель изобретени  - снижение материалоемкости без изменени  несущей способности изготавливаемой сваи. Поставленна  цель достигаетс  тем, что согласно способу изготовлени  грунтобетонной сваи, включающему формование ствола путем погружени  в грунт рабочего органа с подачей по мере его заглублени  закрепл ющего раствора с одновременным перемещиванием его с грунтом и последующее извлечение рабочего органа после формовани  ствола, при подаче закрепл ю760 щего раствора его расход уменьшают по мере заглублени  рабочего органа. Изготовление свай осуществл ют следующим образом. При погружении в грунт рабочего органа с помощью бурильного агрегата грунт размельчаетс  и одновременно перемещиваетс  с закрепл ющим раствором, который подаетс  в рабочую зону через полость в буровой щтанге и отверсти  в буросмесителе. Закрепл ющий раствор приготавливаетс  отдельным агрегатом, включающим дозировочные устройства, мешалку и растворонасос с плавкой регулировкой производительности , котора  осуществл етс  посредством безступенчатого уменьщени  числа оборотов его проводного электродвигател  по мере погружени  рабочего органа при помощи след щей системы, котора  в зависимости от хода буровой штанги измен ет подаваемое на электродвигатель напр жение питани  в сторону его уменьшев зависимости от грунтовых условий и требуемых прочностных характеристик материала, определ ющих несущую способность сваи, устанавливаетс  величина перепада расхода в жущего. Так, при изготовлении грунтобетонных свай диаметром 600 мм и длиной 7 м расход цемента на 1 м сваи снижаетс  от 160 до 100 кг от поверхности грунта до ее подошвы. В результате испытани  вы влена одинакова  несуща  способность такой сваи по сравнейию с изготовленной с равномерным расходом цемента по глубине, что позвол ет сократить расход в жущего и других компонентов до 35%. При этом несуща  способность изготавливаемой сваи не уменьщаетс .A: The invention relates to the construction namely the construction of foundations of new piles in soils with increased deformability. The closest to the proposed technical essence and the achieved result is a method of making a soil-concrete pile, which includes forming the trunk by immersing the working body in the ground with feeding as it deepens the fixing solution, while simultaneously mixing it with the ground and then removing the working body after forming the trunk .. The working agent is fed into the ground evenly as it deepens. 1 The disadvantage of this method is the increased consumption of materials (cement, chemical additives and others mponentov) because the piles have the same strength properties (the material) over the entire length. The uniform supply of the fixing solution according to a known method leads to the fact that the strength of the material of the barrel is not fully used. In addition, the strength of the material in the tip is reduced, since in the manufacture of the pile towards the base sheet, part of the fixing solution is removed. The purpose of the invention is to reduce material consumption without changing the bearing capacity of the pile being made. The goal is achieved by the fact that according to the method of manufacturing a soil-concrete pile, which includes the formation of the trunk by immersing the working body in the ground with the fixing solution being deepened while it is moving with the ground and subsequent removal of the working member after the trunk is formed, solution its consumption is reduced as the working body is buried. The manufacture of the piles is carried out as follows. When immersed in the working tool soil with the help of a drilling unit, the soil is crushed and simultaneously moves with a fixing solution, which is fed into the working zone through a cavity in the drill shank and holes in the drill mixer. The fixing solution is prepared by a separate unit, including metering devices, an agitator and a mortar pump with a fusible capacity control, which is performed by continuously adjusting the speed of its wired motor as the tool dives with a tracking system, which changes depending on the stroke of the drill rod voltage supplied to the motor in the direction of its diminution depending on the soil conditions and the required strength nature The source of the material determining the load bearing capacity of the pile is determined by the magnitude of the flow difference in the idle. Thus, in the manufacture of soil piles with a diameter of 600 mm and a length of 7 m, the consumption of cement per 1 m of pile decreases from 160 to 100 kg from the surface of the soil to its sole. As a result, the same bearing capacity of such a pile was found to be comparable to that produced with a uniform flow rate of cement in depth, which allows reducing the consumption of cement and other components by up to 35%. At the same time, the carrying capacity of the pile being made does not decrease.

Claims (1)

* СПОСОБ ИЗГОТОВЛЕНИЯ ГРУНТОБЕТОННОЙ СВАИ, включающий, формование ствола путем погружения в грунт рабочего органа с подачей по мере его заглубления закрепляющего раствора с одновременным перемешиванием его с грунтом и последующее извлечение рабочего органа после формования ствола, отличающийся тем, что, с целью снижения материалоемкости без уменьшения несущей способности изготавливаемой сваи, при подаче закрепляющего раствора его расход уменьшают по мере заглубления рабочего органа.* METHOD FOR MANUFACTURING A PRIMARY CONCRETE PILES, including forming a trunk by immersing the working body in soil with the filing of a fixing solution as it deepens, while mixing it with the soil and then removing the working body after forming the shaft, characterized in that, in order to reduce material consumption without reducing the bearing capacity of the manufactured piles, when the fixing solution is supplied, its consumption is reduced as the working body deepens.
SU823430233A 1982-04-28 1982-04-28 Method of making soil-concrete pile SU1060760A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823430233A SU1060760A1 (en) 1982-04-28 1982-04-28 Method of making soil-concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823430233A SU1060760A1 (en) 1982-04-28 1982-04-28 Method of making soil-concrete pile

Publications (1)

Publication Number Publication Date
SU1060760A1 true SU1060760A1 (en) 1983-12-15

Family

ID=21009115

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823430233A SU1060760A1 (en) 1982-04-28 1982-04-28 Method of making soil-concrete pile

Country Status (1)

Country Link
SU (1) SU1060760A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2467125C1 (en) * 2011-04-22 2012-11-20 Общество с ограниченной ответственностью "Научно-производственное предприятие "Геотек" (ООО "НПП "Геотек") Device for stabilisation of soils by binding materials

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Косоруков И. И. Сваййые работы. М., «Высша школа, 1974, с. 287-291, рис. 13.12, 13.13. ) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2467125C1 (en) * 2011-04-22 2012-11-20 Общество с ограниченной ответственностью "Научно-производственное предприятие "Геотек" (ООО "НПП "Геотек") Device for stabilisation of soils by binding materials

Similar Documents

Publication Publication Date Title
US6076997A (en) Deep mix soil stabilization method
SG81989G (en) Method and apparatus for forming piles of soil stabilised and compacted in situ
US4180350A (en) Method for forming foundation piers
SE427455B (en) CONCRETIVE MATERIALS CONTAINING HYDRAULIC CEMENT AND AN ACCELERATOR, SET TO MANUFACTURE THE MATERIAL AND USE OF THE MATERIAL
WO2004035938A2 (en) Forming in-situ pilings
SU1060760A1 (en) Method of making soil-concrete pile
PL355067A1 (en) Method of as well as tooling and apparatus for making in-situ cast concrete piles embedded in soil
NO138035B (en) PROCEDURES AND APPARATUS FOR IMPROVING BREEDING REASONS
KR101860093B1 (en) Reinforced structure underground for weak ground and construction method thereof
ATE460538T1 (en) METHOD FOR PRODUCING SELF-COMPACTING FILLING MATERIAL
RU2054502C1 (en) Method for making cement/soil piles in caved-in soils
RU2193625C2 (en) Method of cast-in-place pile making
RU93051923A (en) METHOD OF MANUFACTURE OF CEMENTO-GRUNT PILES
FI91984C (en) Method of reinforcing a structure to be formed in the soil
JPS6448926A (en) Construction of pile
RU2570583C1 (en) Method to erect screw pile in soil with detachable shoe
SU431281A1 (en) METHOD OF FORMING CONCRETE PILES IN GROUND12
SU1346718A1 (en) Method of constructing road paving
SU975897A1 (en) Method of constructing cement-soil piles
EP1805374B1 (en) Method for de-watering a slurry
GB2198765A (en) A tool for in-situ subsurface stabilisation of soil
JP2889853B2 (en) Continuous ground improvement method
JPS641823A (en) Consolidation of foundation
RU2169234C1 (en) Method for manufacturing built-in-place pile
ATE145570T1 (en) DEEP VIBRATION WITH THE ADD OF LIQUID NITROGEN