SU1052674A2 - Guarding stopping for board-and-pillar mining - Google Patents

Guarding stopping for board-and-pillar mining Download PDF

Info

Publication number
SU1052674A2
SU1052674A2 SU823449178A SU3449178A SU1052674A2 SU 1052674 A2 SU1052674 A2 SU 1052674A2 SU 823449178 A SU823449178 A SU 823449178A SU 3449178 A SU3449178 A SU 3449178A SU 1052674 A2 SU1052674 A2 SU 1052674A2
Authority
SU
USSR - Soviet Union
Prior art keywords
elements
tension
roof
horizontal
guarding
Prior art date
Application number
SU823449178A
Other languages
Russian (ru)
Inventor
Филипп Иванович Бажанов
Вячеслав Васильевич Костюченко
Original Assignee
Джезказганский Научно-Исследовательский И Проектный Институт Цветной Металлургии
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Джезказганский Научно-Исследовательский И Проектный Институт Цветной Металлургии filed Critical Джезказганский Научно-Исследовательский И Проектный Институт Цветной Металлургии
Priority to SU823449178A priority Critical patent/SU1052674A2/en
Application granted granted Critical
Publication of SU1052674A2 publication Critical patent/SU1052674A2/en

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

ОГРАЖДАЮЩАЯ ПЕРЕМЫЧКА ДЛЯ КАМЕРНО-СТОЛБОВОЙ СИСТЕМЫ РАЗРАБОТКИ по авт. св. N° 973867. отличающа с  тем, что, с целью упрощени  монтажа ее подкровельной части в выработках переменного сечени , на первом от кровли горизонтальном элементе размешены промежуточные полосы, .снабженные проушинами и соединенные с ним узлами нат жени , при это.м проушины промежуточных полос соединены с канатными петл ми посредством т г с крючь ми.PROTECTIVE BAND FOR A CAMERA POSTS DEVELOPMENT SYSTEM by author. St. N ° 973867. characterized in that, in order to simplify the installation of its sub-roofing part in the workings of variable section, on the first horizontal element from the roof, intermediate strips are placed, fitted with eyelets and connected to it by tension nodes, with this, the eyelets of intermediate strips are connected to rope loops by means of m h with hooks.

Description

Изобретение относитс  к горной промышленности и может быть использовано при подземной добыче полезных ископаемых в качестве закладочной, вентид ционной и ограждающей перемычки.The invention relates to the mining industry and can be used in the underground mining of minerals as a filling, ventilation and enclosing lintel.

По основному авт. св. № 973867 известна ограждающа  перемычка дл  камерностолбовой системы разработки, содержаща  напр женную матрицу, состо щую из горизонтальных и вертикальных элементов нат жени , прикрепленных к анкерам, сетку и фильтрующий материал, при этом вертикальные элементы выполнены в виде т г с крючь ми, а горизонтальные - в виде разборных полос с проущинами, которые соединены между собой узлами нат жени  и снабжены узлами фиксации, напр жени  1.According to the main author. St. No. 973867 is a known bridging bridge for a chamber-like development system, containing a tension matrix consisting of horizontal and vertical tension elements attached to the anchors, a mesh and filter material, with vertical elements made in the form of hooked hooks, and horizontal - in the form of collapsible strips with strips, which are interconnected by tension nodes and are provided with fixation nodes, stresses 1.

Недостатками данной перемычки  вл ютс  узка - область применени  перемычки , обусловленна  несоверщенством устройства подкровельной части матрицы дл  выработок, имеющих непр молинейную форму кровли, так как непр молинейна  проектна  форма и всевозможные вывалы потребуют применени  переменной нестандартной длины анкеров, что приведет к осложнени м при сборке и излищним затратам на их подгонку непосредственно на месте сборки, а разрозненность усилий в каждой точке соединени  этих анкеров с горизонтальной полосой приведет к снижению, несущей способности матрицы перемычки, а также сложность монтажа подкровельной части матрицы из-за необходимости в самой высокой части выработки при минимальном зазоре между кровлей и горизонтальной полосой вести монтаж анкеров с канатными петл ми и соединение их с этой полосой.The disadvantages of this jumper are narrow - the area of the jumper, due to the inadequacy of the device under the roof of the matrix for openings with non-linear roofing, as non-linear design form and all kinds of dumps will require the use of variable non-standard length of anchors, which will lead to complications during assembly and due to the cost of fitting them directly at the assembly site, and the separation of efforts at each connection point of these anchors with a horizontal stripe will result in lower iju carrying capacity jumper matrix, and the complexity of mounting the underlay portion of the matrix due to the need for the highest generation part with a minimum gap between the roof and a horizontal strip lead anchor assembly with the cable loops and their connection to this strip.

Цель изобретени  - упрощение монтажа подкровельной части перемычки в выработках переменного сечени .The purpose of the invention is to simplify the installation of the under-roof part of the lintel in the workings of variable cross section.

Указанна  цель достигаетс  тем, что в ограждающей перемычке на первом от кровли горизонтальном элементе размещены промежуточные полосы, снабженные проущинами и соединенные с ним узлами нат жени , при этом проущины промежуточных полос соединены с канатными петл ми посредством т г с крючь ми.This goal is achieved by placing intermediate strips on the first horizontal element from the roof, fitted with webs and tension nodes connected to it, while the intermediate strips are connected to the rope loops with hooks.

На фиг. 1 изображена перемычка, общий вид; на фиг. 2 - соединительный узел А на фиг. 1; на фиг. 3 - разрез Ы на фиг. 2; на фиг. 4 - разрез II-II на фиг. 2.FIG. 1 shows a jumper, a general view; in fig. 2 shows the coupling assembly A in FIG. one; in fig. 3 shows a section L in FIG. 2; in fig. 4 shows section II-II in FIG. 2

Перемычка состоит из набора стандартной длины нижних вертикальных т г 1 и запроектированной длины вертикальных т г 2 с крючь ми на концах 3, горизонтальных разборных элементов 4 (не менее двух в одном р ду), промежуточных элементов 5, число которых определ етс  возможностью наибольшего количества подсоединени  к нему вертикальных т г 2 и весомThe jumper consists of a set of standard length bottom vertical tons 1 and projected length vertical tons 2 with hooks on the ends 3, horizontal folding elements 4 (at least two in one row), intermediate elements 5, the number of which is determined by the possibility of the greatest number connect to it vertical t g 2 and weight

этого элемента, удобным дл  монтажа, дерев нных щитов или других средств перекрыти  межр дного пространства 6. На каждом горизонтальном р де элементов в соответствующих местах размещаютс  проущины 7 дл  соединени  с вертикальными т гами, узлы 8 нат жени , узлы 9 фиксации нат жени  и крючь  10 дл  подсоединени  горизонтальных р дов элементов через канатные петли с анкерами 11 с помощью клиньев 12 в шпурах 13.this element, convenient for installation, wooden shields or other means of overlapping interdigital space 6. On each horizontal row of elements, there are places 7 for connection with vertical rods, tension assemblies 8, tension fixing assemblies 9 and hook 10 for connecting horizontal rows of elements through cable loops with anchors 11 using wedges 12 in bore holes 13.

Узел нат жени  состоит из металлических пластин, приваренных к горизонтальным элементам, при этом в пластинках имеютс  отверсти  дл  свободного размещени  в них ст жных болтов 14. Сборку перемычки ведут снизу вверх и начинают с бурени  шпуров 13 глубиной от 40 до 70 см, которые бур тс  по периметру выработки. Шпуры в боковых стенках выработки бур тс  с интервалом на 5-10 см больше рассто ни  между горизонтальными элементами дл  передачи первоначального нат жени  вертикальны.м т гам 1. Шпуры в кровле бур тс  против соответствующих проушин 7 элементов 5. После бурени  шпуров закрепл ют канатные петли с анкерами в щпурах так, чтобы концы петель были в одной вертикальной плоскости (свойства этого соединени  позвол ют компенсировать различные неровности за счет длины петли и глубины закреплени  этой петли в щпуре), соедин ют крайние элементы нижнего р да с канатной петлей через крючь  10, а сами элементы - на ст жные болты 14. Делают необходимое нат жение болтом 14 и фиксируют это нат жение клиновым замком. Ст жные болты снимают дл  последующего использовани  на других р дах, а смонтированную первую полосу через анкера с канатной петлей или без нее соедин ют с почвой выработки без зазора и нат жени . Следующие р ды горизонтальных элементов монтируют по данной аналогии только с зацепление.м вертикальных т г за соответствующие проущины до создани  напр жени .The tension assembly consists of metal plates welded to the horizontal elements, while the plates have openings for free placement of the clamping bolts 14 in them. The lintel is assembled from bottom to top and begins with drilling holes 13 to 40 to 70 cm deep that drill on the perimeter of production. The holes in the side walls of the excavation are drilled with an interval of 5-10 cm more than the distance between the horizontal elements in order to transfer the initial tension to the vertical lines. 1. The holes in the roof are drilled against the corresponding lugs of the 7 elements 5. After drilling the holes, the rope holes are fixed loops with anchors in shpurah so that the ends of the loops were in the same vertical plane (the properties of this compound can compensate for various irregularities due to the length of the loop and the depth of fixing of this loop in the pin), connect the extreme elements of the lower its series with the cable loops through the hooks 10 and the elements themselves - for the clamping bolts 14. Make the necessary tension bolt 14 and fixed tension is a wedge lock. The securing bolts are removed for later use on other rows, and the assembled first strip is connected through an anchor with or without a rope loop to the working soil without clearance and tension. The following rows of horizontal elements are mounted, by this analogy, only with hooking. Vertical tg for the corresponding holes before the creation of stress.

После монтажа горизонтальных р дов приступают к монтажу подкровельной части матрицы. Дл  этого в щпурах кровли закрепл ют анкера с канатными петл ми, концы которых наход тс  на проектной отметке кровли. Зацеплением проектной длины т г 2 за канатные петли и проущины элементов 5 и последующее соединение этих элементов через узлы нат жени  и фиксации этого нат жени  с ранее смонтированной верхней разборной полосой заканчивают сборку матрицы. Одинакова  величина зазора, оставл ема  между промежуточными элементами и разборной полосой, позволит передать равномерную нагрузку в вертикальной плоскости всем эле.мента.м матрицы, а увеличение зазора между кровлей и верхней разборной горизонтальной полосой на величину длины т г обеспечит хорошие услови  сборки подкровельной части матрицы при любой конфигурации кровли выработки.After mounting the horizontal rows proceed to the installation of the under-roof part of the matrix. For this purpose, anchors with rope loops, the ends of which are located at the design elevation of the roof, are secured in the cores of the roof. The engagement of the projected length t g 2 for the cable loops and the penetration of the elements 5 and the subsequent connection of these elements through the tension nodes and fixation of this tension with the previously mounted upper collapsible strip complete the assembly of the matrix. The same gap size, left between the intermediate elements and the collapsible strip, will allow to transfer a uniform load in the vertical plane to all elements of the matrix, and increasing the gap between the roof and the upper collapsible horizontal strip by the amount of length r will provide good conditions for assembling the under-roof part of the matrix in any configuration of roofing development.

В зависимости от назначени  перемычки , наличи  необходимых материалов перекрытие пространства между горизонтальными полосами производитс  дерев нными щитами или сеткой с фильтрующим материалом , или просто материалом необходимой прочности. Больщие зазоры между матрицей перемычки и стенками выработки заделывают досками. Крепление досок к канатным петл м осуществл ют с помощью болтов или в зальной проволоки. Малые зазоры между досками и стенками выработки заделывают торкретированием, обмазкой цементным раствором (штукатуркой) или другим известным средством.Depending on the purpose of the lintel, the availability of the necessary materials, the overlapping of the space between the horizontal stripes is produced by wooden shields or a mesh with filter material, or simply a material of necessary strength. Large gaps between the matrix lintels and the walls of the excavation close up boards. Fixing the boards to the cable loops is done with bolts or in a lead wire. Small gaps between the boards and the walls of the excavation are sealed by gunning, coating with cement mortar (plaster) or other known means.

Демонтаж перемычки производитс  рассоединением фиксирующего устройства, отсоединением вертикальных т г и всех других элементов перемычки дл  повторного их использовани .The jumper is disassembled by disconnecting the locking device, disconnecting the vertical links and all other elements of the jumper for reuse.

РR

фиг.Зfig.Z

5five

Фш.гFsh.g

I-II-I

77

Claims (1)

ОГРАЖДАЮЩАЯ ПЕРЕМЫЧКА ДЛЯ КАМЕРНО-СТОЛБОВОЙ СИСТЕМЫ РАЗРАБОТКИ по авт. св. № 973867, отличающаяся тем, что, с целью упрощения монтажа ее подкровельной части в выработках переменного сечения, на первом от кровли горизонтальном элементе размещены промежуточные полосы, снабженные проушинами и соединенные с ним узлами натяжения, при этом проушины промежуточных полос соединены с канатными лями посредством тяг с крючьями.THE FOUNDING JUMPER FOR THE CHAMBER AND POST SYSTEM DEVELOPMENT by ed. St. No. 973867, characterized in that, in order to simplify the installation of its subroofing part in the workings of variable cross-section, intermediate strips are provided on the first horizontal element from the roof, provided with eyes and connected to it by tension nodes, while the eyes of the intermediate strips are connected to the rope spruce by means of rods with hooks. пет21 F 15/02,1981.Pet21 F 15/02, 1981. то > >>then> >> (56) 1. Авторское свидетельство СССР № 973867, ’ V К νΙ Λ -то >(56) 1. USSR Copyright Certificate No. 973867, ’V K νΙ Λ -to> v/\ О v v/ΙλΙ v/IaL· , То То ТО-ТОv / \ О v v / ΙλΙ v / IaL ·, Then THAT Л ν' л ν' А Д V л ν' Λ то то >Л ν 'л ν' А Д V л ν 'Λ then то-то >that> V Λ ν Л л ν Л ν л V Λ ν L l ν L ν l А V Л V ДA V L V D SU .... 1052674 фиг.1SU .... 1052674 figure 1
SU823449178A 1982-06-04 1982-06-04 Guarding stopping for board-and-pillar mining SU1052674A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823449178A SU1052674A2 (en) 1982-06-04 1982-06-04 Guarding stopping for board-and-pillar mining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823449178A SU1052674A2 (en) 1982-06-04 1982-06-04 Guarding stopping for board-and-pillar mining

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
SU973867 Addition

Publications (1)

Publication Number Publication Date
SU1052674A2 true SU1052674A2 (en) 1983-11-07

Family

ID=21015421

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823449178A SU1052674A2 (en) 1982-06-04 1982-06-04 Guarding stopping for board-and-pillar mining

Country Status (1)

Country Link
SU (1) SU1052674A2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1985004444A1 (en) * 1984-03-26 1985-10-10 Gearhart Australia Limited Stoppings
AU749929B2 (en) * 1998-04-27 2002-07-04 Cervetto Courtice Solicitors Cable line stopping

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР .YO 973867, кл. Е 21 F 15/02,1981. сл СП 1чЭ 05 (54) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1985004444A1 (en) * 1984-03-26 1985-10-10 Gearhart Australia Limited Stoppings
AU749929B2 (en) * 1998-04-27 2002-07-04 Cervetto Courtice Solicitors Cable line stopping

Similar Documents

Publication Publication Date Title
US4564316A (en) Face panel system
US8434270B2 (en) Protective shelter
US4587684A (en) Precast concrete bridge
WO2009096725A2 (en) Precast temporary facility structure and a construction method for the same
CN107524149A (en) Assembled soil nailing wall and construction and dismantling method thereof
SU1052674A2 (en) Guarding stopping for board-and-pillar mining
US7124545B1 (en) Tilt-up panel and method
CN211081970U (en) Assembled reusable flexible filling retaining wall
US3971226A (en) Prestressed roof support system
RU2110689C1 (en) Lining of mine shaft
SU973867A1 (en) Fencing partition for chamber-pillar mining method
CN211228414U (en) Assembled reinforcing steel bar pipe sheet for rapid lining of U-shaped tunnel
SU929858A1 (en) Framework roof support erecting method
CN214303941U (en) Self-adaptive reusable filling retaining wall structure
CN219343246U (en) Prefabricated assembled slope protection device
SU1270349A1 (en) Maintenance-free metal support
CN212316945U (en) A no waist rail stake anchor supporting construction for handling landslide fast
SU1411374A1 (en) Anchorage foundation
RU1770579C (en) Shield-type support
SU1565963A1 (en) Lining for sinking vertical working
SU985224A1 (en) Form for making joints monolithic
SU1150370A1 (en) Method of supporting mine working with annular roof support
SU928024A1 (en) Prefabricated ferroconcrete tunnel lining
SU977808A1 (en) Method for determining cohesion between rock and anchour support
SU1296724A1 (en) Roof-bolt metal arch support