RU96111486A - METHOD FOR PRESERVING MINING - Google Patents

METHOD FOR PRESERVING MINING

Info

Publication number
RU96111486A
RU96111486A RU96111486/03A RU96111486A RU96111486A RU 96111486 A RU96111486 A RU 96111486A RU 96111486/03 A RU96111486/03 A RU 96111486/03A RU 96111486 A RU96111486 A RU 96111486A RU 96111486 A RU96111486 A RU 96111486A
Authority
RU
Russia
Prior art keywords
support
permanent
working
preserving
anchor
Prior art date
Application number
RU96111486/03A
Other languages
Russian (ru)
Other versions
RU2101501C1 (en
Inventor
Ю.М. Пирязев
Т.В. Петрова
Original Assignee
Сибирская государственная горно-металлургическая академия
Filing date
Publication date
Application filed by Сибирская государственная горно-металлургическая академия filed Critical Сибирская государственная горно-металлургическая академия
Priority to RU96111486A priority Critical patent/RU2101501C1/en
Priority claimed from RU96111486A external-priority patent/RU2101501C1/en
Application granted granted Critical
Publication of RU96111486A publication Critical patent/RU96111486A/en
Publication of RU2101501C1 publication Critical patent/RU2101501C1/en

Links

Claims (1)

Способ сохранения горной выработки, включающий формирование выработки на границе с отработанным пространством, возведение органного ряда, поддержание кровли выработки до начала очистных работ анкерной крепью, установку временной крепи и замену ее на постоянную податливую крепь, отличающийся тем, что возводят податливую постоянную крепь, состоящую из сегментов, дугообразной формы, а после возведения постоянной крепи убирают анкерную крепь, оставляя при этом один-два анкера у целика.A method of preserving a mine working, including forming a working on the border with the worked-out space, erecting an organ row, maintaining the working roof before starting treatment work with an anchor support, installing a temporary support, and replacing it with a permanent flexible support, characterized in that they build a compliant permanent support, consisting of segments, arcuate shape, and after the erection of a permanent lining removed anchor lining, while leaving one or two anchors in the pillar.
RU96111486A 1996-06-06 1996-06-06 Method of preservation of mine working RU2101501C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU96111486A RU2101501C1 (en) 1996-06-06 1996-06-06 Method of preservation of mine working

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU96111486A RU2101501C1 (en) 1996-06-06 1996-06-06 Method of preservation of mine working

Publications (2)

Publication Number Publication Date
RU96111486A true RU96111486A (en) 1998-01-10
RU2101501C1 RU2101501C1 (en) 1998-01-10

Family

ID=20181646

Family Applications (1)

Application Number Title Priority Date Filing Date
RU96111486A RU2101501C1 (en) 1996-06-06 1996-06-06 Method of preservation of mine working

Country Status (1)

Country Link
RU (1) RU2101501C1 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720498B (en) * 2012-06-20 2015-06-17 鄂托克前旗长城煤矿有限责任公司 Gob-side entry retaining mining process for coal face
CN107091091A (en) * 2017-07-03 2017-08-25 湖南科技大学 A kind of steeply-inclined seam mining gob-side entry retaining method of prefabricated arc support
CN107387084B (en) * 2017-09-15 2019-03-05 中国矿业大学 The construction method of top depth is cut in a kind of gob side entry retaining reduction
CN107461199A (en) * 2017-09-15 2017-12-12 山东东山新驿煤矿有限公司 The method that hilt formula fully-mechanized mining working carries out contracting face using connection roadway
CN108571340B (en) * 2018-04-10 2019-08-27 天地科技股份有限公司 Load evaluation method for gob side entry retaining obturation
CN110617071A (en) * 2019-10-25 2019-12-27 中国水利水电第七工程局成都水电建设工程有限公司 Tunnel expansion rock section arch-changing expanding excavation construction method
CN113622916B (en) * 2021-07-12 2024-04-09 山东黄金矿业(莱州)有限公司三山岛金矿 Stope point column supporting and reinforcing and recycling method
CN116717312B (en) * 2023-06-05 2023-12-08 安徽理工大学 Real-time monitoring system based on weak fiber bragg grating overlying strata stable sinking time

Similar Documents

Publication Publication Date Title
DE69804894D1 (en) expansion anchor
DE59812299D1 (en) expansion anchor
RU96111486A (en) METHOD FOR PRESERVING MINING
DK0758039T3 (en) Anchor rail for construction engineering
NO974546L (en) Method and apparatus for anchoring in soil
DE59801603D1 (en) Expansion anchor
RU2101501C1 (en) Method of preservation of mine working
HUT55881A (en) Method for anchoring clamps and sleeve member for carrying out the method
RU94012935A (en) NAIL
RU2624852C1 (en) Method of ensuring access to underground facility
SU1668686A1 (en) Anchor support for mine workings
DE59810570D1 (en) expansion anchor
RU2023881C1 (en) Tubular anchor and method for installation thereof
SU1671885A1 (en) Pliable anchor
SU1694916A1 (en) Support for development working
SU403860A1 (en) REINFORCED CONCRETE ANCHOR
RU93043675A (en) METHOD OF CONSTRUCTION OF METROPOLITENE STATION OF DEEP DEPOSIT
ATE218182T1 (en) TUNNEL LINING
SU1191587A1 (en) Sliding forms for constructing yielding concrete lining of vertical shafts
DE59805303D1 (en) expansion anchor
RU97110567A (en) METHOD FOR MANAGING ROOFING DAMAGING BLOCKS ON COMPLIANT SUPPORT AND MECHANISM OF ACTION OF THE METHOD
RU2083841C1 (en) Universal pliable framed support
SU1647148A1 (en) Roof bolt
SU1177500A1 (en) Method of protecting excavation workings
RU97113843A (en) METHOD FOR PROTECTING INTER-CHAMBER POSITIONS FROM DESTRUCTION