RU2715214C1 - Transformer testing facility - Google Patents

Transformer testing facility Download PDF

Info

Publication number
RU2715214C1
RU2715214C1 RU2019139063A RU2019139063A RU2715214C1 RU 2715214 C1 RU2715214 C1 RU 2715214C1 RU 2019139063 A RU2019139063 A RU 2019139063A RU 2019139063 A RU2019139063 A RU 2019139063A RU 2715214 C1 RU2715214 C1 RU 2715214C1
Authority
RU
Russia
Prior art keywords
converter
output
transformer
threshold element
current
Prior art date
Application number
RU2019139063A
Other languages
Russian (ru)
Inventor
Илья Николаевич Джус
Original Assignee
Илья Николаевич Джус
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Илья Николаевич Джус filed Critical Илья Николаевич Джус
Priority to RU2019139063A priority Critical patent/RU2715214C1/en
Application granted granted Critical
Publication of RU2715214C1 publication Critical patent/RU2715214C1/en

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/01Subjecting similar articles in turn to test, e.g. "go/no-go" tests in mass production; Testing objects at points as they pass through a testing station

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Ac-Ac Conversion (AREA)

Abstract

FIELD: electrical engineering.
SUBSTANCE: invention relates to electrical engineering and is used in transformer plants and comprises converter (2) of three-phase mains voltage into alternating three-phase voltage, frequency-controlled in value, made based on voltage inverter, is equipped with current sensor (7), which output is connected to threshold element (8), which output is connected to converter (2) closing input; output transformer connected by primary winding (3) to output of converter (2), and by secondary winding - to resonant load; tested transformer (5), capacitor (6). At overcurrents through threshold element (8) key 10 is started, shunting circuit of elements (5, 6) and taking current to itself. Also, control pulses of converter (2) are removed. After reduction of current, key (10) is switched off and with delay time delay unit (9) converter (2) comes into operation.
EFFECT: increasing reliability.
1 cl, 1 dwg

Description

Предложение относится к электротехнике и используется на трансформаторных заводах. Широко известная [патент на полезную модель РФ №142928] установка для испытания трансформаторов /далее УИТ/, содержащего преобразователь частоты, выходом соединенный с выходным трехфазным трансформатором, Недостаток такого устройства состоит в большой сложности, обусловленной необходимостью использования шестифазного преобразователя. Кроме того в однофазном режиме снижается выходная мощность на 2/3. Наиболее близким по технической сути и достигаемым результатам к первому варианту является УИТ / патент на полезную модель РФ №119544/ содержащая преобразователь трехфазного сетевого напряжения в переменное трехфазное напряжение, регулируемое по частоте и величине, снабженный датчиком тока, который выходом присоединен к пороговому элементу, выход которого связан с управляющим входом преобразователя, выходной трансформатор, подключенный первичной обмоткой к выходу преобразователя, а вторичной обмоткой трансформатор предназначен для подключения к резонансной нагрузке. Недостаток таких устройств состоит в относительно низких функциональных возможностях, так как подобная схема адаптирована только для одного режима испытаний - без использования резонанса. Технический результат предложения- повышение надежности и упрощение. Технический результат достигается за счет того, что УИТ содержит тиристорный ключ, подключенный к вторичной обмотке трансформатора, вход открытия связан с выходом порогового элемента, а между выходом порогового элемента и запирающим входом преобразователя включен блок задержки на исчезновение сигнала.The proposal relates to electrical engineering and is used in transformer plants. The well-known [patent for utility model of the Russian Federation No. 142928] installation for testing transformers (hereinafter referred to as UIT), comprising a frequency converter, connected to an output three-phase transformer by the output. The disadvantage of such a device is its great complexity due to the need to use a six-phase converter. In addition, in single-phase mode, the output power is reduced by 2/3. The closest in technical essence and the achieved results to the first option is UIT / patent for utility model of the Russian Federation No. 119544 / containing a converter of a three-phase mains voltage to an alternating three-phase voltage, adjustable in frequency and magnitude, equipped with a current sensor, which is connected to a threshold element by the output, the output which is connected to the control input of the converter, the output transformer connected by the primary winding to the output of the converter, and the secondary winding of the transformer is designed to connections to the resonant load. The disadvantage of such devices is the relatively low functionality, since such a circuit is adapted for only one test mode - without the use of resonance. The technical result of the proposal is to increase reliability and simplification. The technical result is achieved due to the fact that the UIT contains a thyristor switch connected to the secondary winding of the transformer, the opening input is connected to the output of the threshold element, and a delay block for signal disappearance is connected between the output of the threshold element and the locking input of the transformer.

На чертеже представлена однолинейная схема УИТ. Она содержит сетевой выключатель 1 и преобразователь 2 преобразования трехфазного сетевого напряжения в напряжение, регулируемое по частоте и амплитуде, выполненного по схеме инвертора напряжения. Преобразователь 2 выходами подключен к трансформатору с обмотками 3 и 4. К вторичной обмотке 4 присоединен испытуемый трансформатор 5 и регулируемая конденсаторная батарея 6. Имеется датчик тока 7, пороговый элемент 8, блок задержки 9, битиристорный ключ 10 (или симисторный). УИТ функционирует так. Она используется для резонансных испытаний, т.е для случая когда индуктивное сопротивление испытуемого трансформатора (реактора) 5 равно емкостному сопротивлению батареи 6 на испытываемой частоте. В таком режиме от преобразователя 2 через трансформатор 3 протекает небольшой ток, который компенсирует потери в контуре 5-6. Т.е. преобразователь 2 является возбудителем колебаний тока в контуре 5-6 и ток в этом контуре может в десятки раз превышать ток преобразователя 2. В установившемся режиме резонанс в контуре 5-6 может исчезнуть, например, вследствие отключения части конденсаторов в батарее 6 (перегорание встроенных предохранителей) и т.п. В этом случае большой ток из контура 5-6 направляется в преобразователь 2, что может привести к его повреждению. Однако это не происходит из-за того, что при превышении током, измеряемым датчиком 7, уставки срабатывает пороговый элемент 8 и подает сигнал на закрытие преобразователя 2 путем запрета управляющих импульсов. Так как снятие импульсов преобразователя 2 не ведет к прекращению тока через него, в случае поступления его со стороны нагрузки (контура 5-6), то запускается битиристорный ключ 10, который шунтирует нагрузку (5-6), не пропуская ток в преобразователь 2, исключая таким образом его перегрузку. При наличии в составе преобразователя 2 регулятора тока указанный сигнал может воздействовать на него, снижая ток до небольшой величины (например 5-15%).Спадание тока до нормального уровня приводит к возврату порогового элемента 8 в нулевое состояние, что вызывает отключение ключа 10. С выдержкой времен на исчезновение сигнала, обусловленной блоком 9 на время большее полупериода сети преобразователь 2 вступает в работу, так как переходный процесс в контуре 5-6 закончился. Таким образом, снижается перегрузка преобразователя 2, чем повышается надежность.The drawing shows a single-line diagram of the UIT. It contains a network switch 1 and a converter 2 for converting a three-phase mains voltage to voltage, adjustable in frequency and amplitude, made according to the voltage inverter circuit. The converter 2 is connected with outputs to a transformer with windings 3 and 4. A test transformer 5 and an adjustable capacitor bank 6 are connected to the secondary winding 4. There is a current sensor 7, a threshold element 8, a delay unit 9, a bitistor switch 10 (or triac). WIT operates like this. It is used for resonance tests, that is, for the case when the inductive resistance of the transformer (reactor) 5 under test is equal to the capacitive resistance of the battery 6 at the tested frequency. In this mode, a small current flows from transformer 2 through transformer 3, which compensates for losses in circuit 5-6. Those. converter 2 is the causative agent of current oscillations in circuit 5-6 and the current in this circuit can be tens of times higher than the current of converter 2. In the steady state, the resonance in circuit 5-6 can disappear, for example, due to disconnection of part of the capacitors in battery 6 (blown internal fuses ) etc. In this case, a large current from circuit 5-6 is sent to the converter 2, which can lead to damage. However, this does not happen due to the fact that when the current measured by the sensor 7 exceeds the setting, the threshold element 8 is triggered and sends a signal to close the converter 2 by inhibiting the control pulses. Since the removal of the pulses of the converter 2 does not lead to the cessation of current through it, if it is received from the load side (circuit 5-6), then the bistyristor switch 10 is started, which shunts the load (5-6), without passing current to the converter 2, thus excluding its overload. If there is a current regulator in the converter 2, this signal can act on it, reducing the current to a small value (for example, 5-15%). When the current drops to a normal level, threshold element 8 returns to zero, which causes key 10 to turn off. the endurance of the time for the disappearance of the signal due to block 9 for a period longer than the half-period of the network, the converter 2 enters into operation, since the transient in circuit 5-6 has ended. Thus, the overload of the converter 2 is reduced, which increases the reliability.

Claims (1)

Установка для испытания трансформаторов, содержащая преобразователь трехфазного сетевого напряжения в переменное трехфазное напряжение, регулируемое по частоте и величине, снабженный датчиком тока, который выходом присоединен к пороговому элементу, выход которого связан с управляющим входом указанного преобразователя, выходной трансформатор, подключенный первичной обмоткой к выходу преобразователя, а вторичная обмотка выходного трансформатора предназначена для подключения к резонансной нагрузке, отличающаяся тем, что содержит тиристорный ключ, подключенный к вторичной обмотке выходного трансформатора, вход управления тиристорного ключа связан с выходом порогового элемента, а между выходом порогового элемента и управляющим входом преобразователя включен блок задержки на исчезновение сигнала.Installation for testing transformers, comprising a converter of a three-phase mains voltage to an alternating three-phase voltage, adjustable in frequency and magnitude, equipped with a current sensor, which is connected by an output to a threshold element, the output of which is connected to the control input of the specified converter, an output transformer connected by a primary winding to the output of the converter and the secondary winding of the output transformer is designed to be connected to a resonant load, characterized in that it contains a transistor key connected to the secondary winding of the output transformer, the thyristor key control input is connected to the output of the threshold element, and a delay block for the disappearance of the signal is connected between the output of the threshold element and the control input of the converter.
RU2019139063A 2019-12-02 2019-12-02 Transformer testing facility RU2715214C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2019139063A RU2715214C1 (en) 2019-12-02 2019-12-02 Transformer testing facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2019139063A RU2715214C1 (en) 2019-12-02 2019-12-02 Transformer testing facility

Publications (1)

Publication Number Publication Date
RU2715214C1 true RU2715214C1 (en) 2020-02-26

Family

ID=69630866

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2019139063A RU2715214C1 (en) 2019-12-02 2019-12-02 Transformer testing facility

Country Status (1)

Country Link
RU (1) RU2715214C1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117424350A (en) * 2023-12-18 2024-01-19 安徽凯川电力保护设备有限公司 Ground connection pulse selection dynamic monitoring controller

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6809525B1 (en) * 2002-12-31 2004-10-26 Abb Technology Ag Method and system for estimating conductor losses in a transformer
RU2282862C1 (en) * 2005-02-21 2006-08-27 Георгий Михайлович Михеев Device for measuring current and open-circuit loss of power transformers at low voltage
DE202009017938U1 (en) * 2009-06-03 2010-10-28 Pcs Power Converter Solutions Verwaltungs Ag Device for testing high voltage equipment
RU119544U1 (en) * 2012-04-04 2012-08-20 Открытое Акционерное Общество Холдинговая Компания "Электрозавод" (Оао "Электрозавод") STATIC FREQUENCY CONVERTER FOR TESTING TRANSFORMER AND REACTOR EQUIPMENT
RU142928U1 (en) * 2013-06-17 2014-07-10 Федеральное государственное унитарное предприятие "Всероссийский электротехнический институт им. В.И. Ленина" DEVICE FOR ELECTRIC TESTS OF SINGLE-PHASE AND THREE-PHASE POWER TRANSFORMERS

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6809525B1 (en) * 2002-12-31 2004-10-26 Abb Technology Ag Method and system for estimating conductor losses in a transformer
RU2282862C1 (en) * 2005-02-21 2006-08-27 Георгий Михайлович Михеев Device for measuring current and open-circuit loss of power transformers at low voltage
DE202009017938U1 (en) * 2009-06-03 2010-10-28 Pcs Power Converter Solutions Verwaltungs Ag Device for testing high voltage equipment
RU119544U1 (en) * 2012-04-04 2012-08-20 Открытое Акционерное Общество Холдинговая Компания "Электрозавод" (Оао "Электрозавод") STATIC FREQUENCY CONVERTER FOR TESTING TRANSFORMER AND REACTOR EQUIPMENT
RU142928U1 (en) * 2013-06-17 2014-07-10 Федеральное государственное унитарное предприятие "Всероссийский электротехнический институт им. В.И. Ленина" DEVICE FOR ELECTRIC TESTS OF SINGLE-PHASE AND THREE-PHASE POWER TRANSFORMERS

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117424350A (en) * 2023-12-18 2024-01-19 安徽凯川电力保护设备有限公司 Ground connection pulse selection dynamic monitoring controller
CN117424350B (en) * 2023-12-18 2024-04-16 安徽凯川电力保护设备有限公司 Ground connection pulse selection dynamic monitoring controller

Similar Documents

Publication Publication Date Title
US8995097B2 (en) High voltage DC breaker apparatus
Hajian et al. Evaluation of semiconductor based methods for fault isolation on high voltage DC grids
RU2263925C2 (en) Method and device for detecting short-circuit ground and calculating its resistance
US7969755B2 (en) Apparatus for electrical power transmission
US10171023B2 (en) Motor starter apparatus with start-up fault detection capability
CN109188278B (en) Three-phase unbalance detection circuit and system
Heidary et al. Series transformer based diode-bridge-type solid state fault current limiter
RU2715214C1 (en) Transformer testing facility
RU2647706C2 (en) Method of converting alternating current into direct current and related device
RU2652087C1 (en) Frequency converter for testing transformers (options)
US5995394A (en) Device for connecting a VSC converter to a source of alternating voltage
Dimova Investigation of digital protection relay for three-phase induction motor
RU2659588C1 (en) Transformer inverter tester
CN106291295B (en) Chain-end withstand voltage test method for chained STATCOM converter chain
Kumar et al. Elimination of DC component and identification of inrush current using harmonic analysis for power transformer protection
RU2739702C1 (en) Transformer testing facility
Bottrell et al. An impedance-based method for the detection of over-load and network faults in inverter interfaced distributed generation
RU121403U1 (en) DEVICE FOR AUTOMATIC CONTROL OF SUBMOTOR PUMP MOTOR
RU2244992C1 (en) Device for detecting single-phase ground faults in insulated-neutral networks
JPH028516Y2 (en)
SU1599815A1 (en) Method and apparatus for electrodynamic tests of power transformers
RU2763033C1 (en) Method for testing transformers and reactors
CN112335163A (en) Determination of the capacitor function of a passive filter circuit
RU145566U1 (en) STABILIZING CONVERTER OF AC THREE-PHASE VOLTAGE TO DC
RU2706709C1 (en) Apparatus for testing transformers and reactors