RU184322U1 - Rostverk for suspended support of pipelines of underground laying, compensating deviations of piles at installation - Google Patents
Rostverk for suspended support of pipelines of underground laying, compensating deviations of piles at installation Download PDFInfo
- Publication number
- RU184322U1 RU184322U1 RU2017137018U RU2017137018U RU184322U1 RU 184322 U1 RU184322 U1 RU 184322U1 RU 2017137018 U RU2017137018 U RU 2017137018U RU 2017137018 U RU2017137018 U RU 2017137018U RU 184322 U1 RU184322 U1 RU 184322U1
- Authority
- RU
- Russia
- Prior art keywords
- grillage
- longitudinal grooves
- piles
- pipeline
- axis
- Prior art date
Links
- 238000009434 installation Methods 0.000 title claims abstract description 8
- 239000000725 suspension Substances 0.000 abstract description 18
- 238000010276 construction Methods 0.000 abstract description 3
- 239000002689 soil Substances 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 4
- 238000006073 displacement reaction Methods 0.000 description 3
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 101150096674 C20L gene Proteins 0.000 description 1
- 102220543923 Protocadherin-10_F16L_mutation Human genes 0.000 description 1
- 101100445889 Vaccinia virus (strain Copenhagen) F16L gene Proteins 0.000 description 1
- 101100445891 Vaccinia virus (strain Western Reserve) VACWR055 gene Proteins 0.000 description 1
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/14—Hangers in the form of bands or chains
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Supports For Pipes And Cables (AREA)
Abstract
Полезная модель относится к области строительства, эксплуатации и ремонту трубопроводов, транспортирующих газ, нефть и другие продукты, и может быть использована в качестве подвески опоры подземного трубопровода на участке с просадочными грунтами, в т.ч. в условиях обводненных участков и многолетнемерзлых грунтов.The utility model relates to the field of construction, operation and repair of pipelines transporting gas, oil and other products, and can be used as a suspension support for an underground pipeline in a section with subsiding soils, including in conditions of watering areas and permafrost.
Ростверк для подвесных опор трубопроводов подземной прокладки, компенсирующий отклонения свай при монтаже, выполненный в виде двух взаимосопряженных балок, жестко соединенных между собой в одной плоскости, с расположенными сверху опорными плитами, при этом на концах ростверка выполнены ряды продольных пазов под болтовое соединение, при этом ростверк выполнен удлиненным с одной стороны от оси трубопровода, при этом на удлиненной части ростверка выполнен дополнительный ряд продольных пазов под болтовое соединение, а с противоположной стороны ростверка ближе к оси трубопровода выполнен дополнительный ряд продольных пазов под болтовое соединение.A grillage for overhead supports for underground pipelines, compensating for deviations of piles during installation, made in the form of two interconnected beams rigidly interconnected in the same plane with the supporting plates located on top, with rows of longitudinal grooves for the bolted connection at the ends, while the grillage is made elongated on one side of the axis of the pipeline, while on the elongated part of the grillage an additional row of longitudinal grooves for bolting is made, and on the opposite side with The corners of the grillage closer to the axis of the pipeline are made an additional row of longitudinal grooves for bolting.
Технический результат - повышение технологичности сборки опоры подвесной за счет обеспечения монтажа ростверка на сваи, имеющие повышенные (сверхнормативные) отклонения, и сокращение времени на проведение монтажных работ. 2 з.п. ф-лы, 7 ил. The technical result is an increase in the manufacturability of the assembly of the suspension bearing by providing installation of the grillage on the piles with increased (above-standard) deviations, and reducing the time for installation works. 2 hp f-ly, 7 ill.
Description
Полезная модель относится к области строительства, эксплуатации и ремонту трубопроводов, транспортирующих газ, нефть и другие продукты, и может быть использована в качестве ростверка опоры подвесной трубопровода на участке с просадочными грунтами, в т.ч. в условиях обводненных участков и многолетнемерзлых грунтов.The utility model relates to the field of construction, operation and repair of pipelines transporting gas, oil and other products, and can be used as a grillage of a suspension pipeline support on a site with subsiding soils, including in conditions of watering areas and permafrost.
Известна опора подвесная для участков подземной прокладки трубопроводов, содержащая несущий элемент (ростверк), расположенный надземно в верхней части, и объединяющий сваи в одну устойчивую систему. Ростверк предназначен для принятия вертикальной нагрузки 110 тс от веса подземного трубопровода с грунтом через гибкую цепную подвеску и передачи нагрузки на сваи. Ростверк выполнен одноуровневым в виде взаимосопряженных двух балок, жестко соединенных между собой в одной плоскости и усиленных вертикально ориентированными ребрами жесткости и перемычками, с расположенными сверху опорными плитами. Ростверк закреплен на свайном фундаменте через по меньшей мере два опорных узла шарнирного типа [патент RU 2601651 С1, дата публикации 10.11.2016, МПК F16L 3/14].Known suspension suspended for sections of the underground pipeline, containing a supporting element (grillage), located above the ground in the upper part, and combining piles into one stable system. The rostver is designed to take a vertical load of 110 ton-force on the weight of the underground pipeline with soil through a flexible chain suspension and transfer the load to the piles. Rostverk is made single-level in the form of interconnected two beams, rigidly interconnected in the same plane and reinforced with vertically oriented stiffening ribs and bridges, with supporting plates located above. The rostver is fixed on the pile foundation through at least two hinge-type support assemblies [patent RU 2601651 С1, published 10.11.2016, IPC F16L 3/14].
Недостатком ростверка является то, что допускаемые конструкцией ростверка отклонения головы свай в плане незначительны и составляют до ± 67 мм.The disadvantage of the grillage is that the deviations of the head of the piles in the plan allowed by the construction of the grillage in the plan are insignificant and amount to ± 67 mm.
Техническая проблема, на решение которой направлена заявляемая полезная модель, заключается в обеспечении возможности сборки опоры подвесной на сваях, имеющих отклонение от симметричности свай относительно оси подземного трубопровода до 400 мм, а так же при отклонениях головы свай в плане ± 150 мм и отклонение межсвайного расстояния ± 300 мм.The technical problem addressed by the claimed utility model is to provide the possibility of assembling a suspended support on piles deviating from the symmetry of the piles relative to the axis of the underground pipeline up to 400 mm, as well as deviations of the pile head in terms of ± 150 mm and the deviation of intersite distance ± 300 mm.
Технический результат, достигаемый при реализации полезной модели, заключается в повышении технологичности сборки опоры подвесной и сокращении времени на проведение монтажных работ за счет компенсации отклонений головы свай в плане, возникающие при бурении скважин, имеющих отклонение от симметричности свай относительно оси трубопровода до 400 мм, а так же при отклонениях головы свай в плане ± 150 мм и отклонение межсвайного расстояния ± 300 мм непосредственно в процессе сборки опоры подвесной.The technical result achieved during the implementation of the utility model is to improve the manufacturability of the assembly of the suspension support and reduce the time for installation work by compensating for deviations of the pile head in the plan arising from drilling wells deviating from the symmetry of the piles relative to the pipeline axis to 400 mm, and also with deviations of the pile head in terms of ± 150 mm and deviation of the intersweet distance of ± 300 mm directly in the process of assembling the suspension support.
Заявляемый технический результат достигается за счет того, что ростверк для подвесных опор трубопроводов подземной прокладки, компенсирующий отклонения свай при монтаже, выполненный в виде двух взаимосопряженных балок, жестко соединенных между собой в одной плоскости, с расположенными сверху опорными плитами, при этом на концах ростверка выполнены ряды продольных пазов под болтовое соединение, при этом ростверк выполнен удлиненным с одной стороны от оси трубопровода, причем на удлиненной части ростверка выполнен дополнительный ряд продольных пазов под болтовое соединение, а с противоположной стороны ростверка ближе к оси трубопровода выполнен дополнительный ряд продольных пазов под болтовое соединение.The claimed technical result is achieved due to the fact that the grillage for overhead supports of pipelines of the underground installation, compensating for deviations of piles during installation, made in the form of two interconnected beams rigidly interconnected in the same plane, with the support plates located above, while at the ends of the grillage are made rows of longitudinal grooves for bolting, with the grillage made elongated on one side of the axis of the pipeline, with an additional row of odolnyh recesses for bolt connection, and on the opposite side grillage closer to the axis of the conduit adapted additional series of longitudinal grooves for bolt connection.
Выполнение ростверка нессиметричным, т.е. удлиненным с одного конца относительно оси трубопровода и выполнение на удлиненной части дополнительных рядов продольных пазов под болтовые соединения обеспечивает возможность компенсации отклонений головы свай в плане, возникающие при бурении скважин, имеющих отклонение от симметричности свай относительно оси трубопровода до 400 мм, при котором образуется наклон цепей, повышающий боковую нагрузку на сваи, а так же при отклонениях головы свай в плане ± 150 мм и отклонение межсвайного расстояния ± 300 мм непосредственно в процессе сборки опоры подвесной.Performing a grillage asymmetric, i.e. elongated from one end about the axis of the pipeline and making additional rows of longitudinal grooves for bolted joints on the elongated part makes it possible to compensate for deviations of the head of the piles in the plan arising during the drilling of wells that deviate from the symmetry of the piles relative to the axis of the pipeline to 400 mm at which the slope of the chains is formed , which increases the lateral load on the piles, as well as with deviations of the pile head in terms of ± 150 mm and the deviation of the intersite distance of ± 300 mm directly during the assembly process Ora suspended.
Кроме того, в частном случае реализации полезной модели длина продольных пазов под болтовое соединение составляет не менее 245 мм.In addition, in the particular case of the implementation of the utility model, the length of the longitudinal grooves for the bolted connection is at least 245 mm.
Кроме того, в частном случае реализации полезной модели расстояние между центральной осью соседних продольных пазов под болтовое соединение (шаг пазов) составляет не менее 400 мм.In addition, in the particular case of implementing a utility model, the distance between the central axis of adjacent longitudinal grooves for bolting (pitch grooves) is at least 400 mm.
Полезная модель поясняется чертежами: на фиг. 1 - показан ростверк (вид сверху); на фиг. 2 - показана схема компенсации отклонений свай в плане и наклона цепей, образованного несимметричностью свай относительно оси подземного трубопровода при максимальном межсвайном расстоянии; на фиг. 3 -показано положение продольных пазов ростверка при схеме компенсации отклонений (разрез А-А и Б-Б на фиг. 2); на фиг. 4 - показана схема компенсации отклонений свай в плане и наклона цепей, образованного несимметричностью свай относительно оси подземного трубопровода при номинальном межсвайном расстоянии; на фиг. 5 - показано положение продольных пазов ростверка при схеме компенсации отклонений (разрез М-М и Н-Н на фиг. 4); на фиг. 6 - показана схема компенсации отклонений свай в плане и наклона цепей, образованного несимметричностью свай относительно оси подземного трубопровода при минимальном межсвайном расстоянии; на фиг. 7 - показано положение продольных пазов ростверка при схеме компенсации отклонений (разрез Д-Д и Е-Е на фиг. 6). На чертежах позиции имеют следующие обозначения:The utility model is illustrated by drawings: in FIG. 1 - the grillage is shown (top view); in fig. 2 shows a diagram of compensation for deviations of the piles in the plan and the inclination of the chains formed by the asymmetry of the piles relative to the axis of the underground pipeline at the maximum in-welder distance; in fig. 3 shows the position of the longitudinal grooves of the grillage with the deviation compensation scheme (section A-A and B-B in Fig. 2); in fig. 4 shows a diagram of the compensation of deviations of the piles in the plan and the inclination of the chains formed by the asymmetry of the piles relative to the axis of the underground pipeline at the nominal intersway distance; in fig. 5 shows the position of the longitudinal grooves of the grillage with a deviation compensation scheme (section M-M and H-H in FIG. 4); in fig. 6 shows a diagram of the compensation of deviations of the piles in the plan and the inclination of the chains formed by the asymmetry of the piles relative to the axis of the underground pipeline at the minimum intersway distance; in fig. 7 shows the position of the longitudinal grooves of the grillage with a deviation compensation scheme (the section D-D and E-E in Fig. 6). In the drawings, the positions have the following designations:
1 - ростверк;1 - grillage;
2 - опорные плиты;2 - base plates;
3 - дополнительный ряд продольных пазов;3 - an additional row of longitudinal grooves;
4 - продольные пазы (поперечные оси трубопровода);4 - longitudinal grooves (transverse axis of the pipeline);
5 - опорная муфта;5 - bearing clutch;
6 - полукольца;6 - half rings;
7 - свая;7 - pile;
8 - гибкая цепная подвеска;8 - flexible chain suspension;
9 - ложемент;9 - lodgement;
10 - трубопровод;10 - pipeline;
L - межсвайное расстояние;L is the intersway distance;
L1, L2 - расстояние от сваи до оси трубопровода;L 1 , L 2 - distance from the pile to the axis of the pipeline;
L3 - расстояние от края ростверка до оси цепной подвески со стороны удлиненной части ростверка;L 3 - the distance from the edge of the grillage to the axis of the chain suspension from the side of the elongated part of the grillage;
L4 - расстояние от края ростверка до оси цепной подвески со стороны не удлиненной части ростверка;L 4 - the distance from the edge of the grillage to the axis of the chain suspension from the side of the non-elongated part of the grillage;
L5 - несимметричность свай относительно оси трубопровода;L 5 - asymmetry of the pile relative to the axis of the pipeline;
L6 - максимальное смещение ростверка путем его перестановки на муфтах опорных на дополнительные пазы и смещения по пазам;L 6 - the maximum displacement of the grillage by rearranging it on the sleeves supporting to the additional grooves and displacements along the grooves;
L7 - допускаемый по условию прочности свай остаточный наклон цепей не компенсируемый ростверком;L 7 - the residual tilt of chains allowed by the condition of strength of piles is not compensated by a grillage;
L8 - длина продольных пазов;L 8 - the length of the longitudinal grooves;
L9 - расстояние между центральной осью соседних продольных пазов.L 9 - the distance between the central axis of the adjacent longitudinal grooves.
Опора подвесная для участков подземной прокладки трубопроводов (фиг. 2, фиг. 4, фиг. 6) содержит взаимосопряженные подвижную и неподвижную части, взаимодействующие друг с другом за счет соединяющей их гибкой цепной подвески 8, обеспечивающей передачу вертикальной нагрузки от трубопровода 10 на надземный ростверк 1, закрепленный на сваях 7.Suspension support for sections of underground laying of pipelines (Fig. 2, Fig. 4, Fig. 6) contains interconnected moving and fixed parts that interact with each other by connecting them with a
Подвижная часть опоры сопряжена с неподвижной частью посредством гибкой цепной подвески 8, состоящей из двух ветвей. Гибкая цепная подвеска 8 выполнена в виде цепи, шарнирно соединенной с одного конца с ложементом 9 и с другого конца с регулировочным винтом, опирающимся через опорные шайбы, сферические шайбы и гайки на опорную плиту 2 (показана на фиг. 1) ростверка 1.The movable part of the support mates with a fixed part by means of a
Неподвижная часть опоры представляет собой ростверк 1 и узлы его крепления к свае 7.The fixed part of the support is a
Ростверк 1 для подвесных опор трубопроводов (фиг. 1) выполнен одноуровневым в виде двух взаимосопряженных балок, жестко соединенных между собой в одной плоскости и усиленных вертикально ориентированными ребрами жесткости и перемычками, с расположенными сверху опорными плитами 2. На концах ростверка 1 выполнены ряды продольных пазов 4 под болтовое соединение с опорной муфтой 5, устанавливаемой на полукольца 6, приваренные к свае 7. Ростверк 1 выполнен удлиненным с одной стороны от оси трубопровода, тем самым образуется несимметричная конструкция ростверка -расстояние от края ростверка 1 до оси цепной подвески 8 со стороны удлиненной части ростверка L3 больше расстояния от края ростверка 1 до оси цепной подвески 8 со стороны не удлиненной части ростверка L4. На удлиненной части ростверка 1 выполнен дополнительный ряд 3 продольных пазов 4, а с противоположной стороны ростверка 1 выполнен дополнительный ряд 3 продольный пазов 4 ближе к поперечной оси.Rostverk 1 for suspended supports of pipelines (Fig. 1) is single-level in the form of two interconnected beams rigidly interconnected in the same plane and reinforced with vertically oriented stiffening ribs and bridges with supporting
Длина L8 продольных пазов 4 под болтовое соединение составляет не менее 245 мм. Расстояние L9 между осью соседних продольных пазов 4 под болтовое соединение (шаг пазов) составляет не менее 400 мм.The length L 8 of the
Ростверк 1 устанавливается на сваи 7 при сборке подвесной опоры в соответствии со схемами, которые приведены на фиг. 2, 4, 6.The
На фиг. 2 показано, что при максимальном межсвайном расстоянии L равным 4500 мм компенсируются отклонения головы свай в плане и частично наклон цепей 400 мм, образованный несимметричностью L5 свай 7 относительно оси трубопровода 10 на величину максимально возможного смещения ростверка L6, обеспечивая минимально допустимый наклон L7 цепей цепной подвески 8, при этом ростверк 1 установлен на муфты 5 на крайние (внешние) пазы 4 и смещен по ним максимально вправо, т.е. болты расположены по левой стороне паза 4 (разрез А-А и Б-Б на фиг. 3).FIG. 2 shows that at a maximum intersink distance L equal to 4500 mm, deviations of the head of the piles in the plan and partially inclination of the chains of 400 mm formed by the asymmetry of L 5 piles 7 relative to the axis of the
На фиг. 4 показано, что при номинальном межсвайном расстоянии L равным 4200 мм компенсируются отклонения головы свай в плане и наклон цепей цепной подвески 8 400 мм, образованный несимметричностью L5 свай 7 относительно оси трубопровода 10, обеспечивая их вертикальное положение, при этом ростверк 1 установлен на муфты 5 на крайние (внешние) пазы 4, болты расположены по левой стороне паза 4 (разрез М-М на фиг. 5) и на внутренние пазы 4, болты расположены по правой стороне паза 4 (разрез Н-Н на фиг. 5).FIG. 4 shows that at a nominal intake distance of L equal to 4200 mm, deviations of the head of the piles in the plan and the inclination of the chains of the chain suspension of 8,400 mm formed by the asymmetry of L 5 piles 7 relative to the axis of the
На фиг. 6 показано, что при минимальном межсвайном расстоянии L равным 3900 мм компенсируются отклонения головы свай в плане и наклон цепей 400 мм, образованный несимметричностью L5 свай 7 относительно оси трубопровода 10, обеспечивая их вертикальное положение, при этом ростверк 1 установлен на муфты 5 на крайние (внешние) пазы 4, болты установлены по правой стороне паза 4 (разрез Д-Д на фиг. 7) и на внутренние пазы 4, при этом болты расположены по левой стороне паза 4 (разрез Е-Е фиг. 7).FIG. 6 shows that with a minimum intersite distance L equal to 3900 mm, deviations of the head of the piles in the plan and the inclination of the chains of 400 mm formed by the asymmetry of L 5 piles 7 relative to the axis of the
Таким образом, выполнение ростверка 1 подвесной опоры подземного трубопровода 10 несимметричным, т.е. удлиненным с одной стороны от оси трубопровода и наличие дополнительных рядов 3 продольных пазов 4 под болтовые соединения обеспечивает возможность сборки опоры подвесной на сваях, имеющих отклонение от симметричности свай относительно оси трубопровода до 400 мм, а так же при отклонениях головы свай в плане ± 150 мм и отклонение межсвайного расстояния ± 300 мм.Thus, the execution of the
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2017137018U RU184322U1 (en) | 2017-10-20 | 2017-10-20 | Rostverk for suspended support of pipelines of underground laying, compensating deviations of piles at installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2017137018U RU184322U1 (en) | 2017-10-20 | 2017-10-20 | Rostverk for suspended support of pipelines of underground laying, compensating deviations of piles at installation |
Publications (1)
Publication Number | Publication Date |
---|---|
RU184322U1 true RU184322U1 (en) | 2018-10-22 |
Family
ID=63923202
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
RU2017137018U RU184322U1 (en) | 2017-10-20 | 2017-10-20 | Rostverk for suspended support of pipelines of underground laying, compensating deviations of piles at installation |
Country Status (1)
Country | Link |
---|---|
RU (1) | RU184322U1 (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3767149A (en) * | 1972-03-17 | 1973-10-23 | J Hill | Support trestle for permafrost areas |
SU614280A1 (en) * | 1976-04-28 | 1978-07-05 | Ленинградское Отделение Всесоюзного Государственного Ордена Ленина И Ордена Октябрьской Революции Проектного Института "Теплоэлектропроект" | Pipeline suspension member |
SU646130A1 (en) * | 1977-04-11 | 1979-02-05 | Luksha Valentin O | Suspended support for suspended pipeline |
SU916865A1 (en) * | 1980-07-29 | 1982-03-30 | Северо-Кавказский Зональный Научно-Исследовательский И Проектный Институт "Севкавзнииэпсельстрой" | Overhead pipeline support assembly |
UA7160A (en) * | 1994-08-05 | 1995-06-30 | Дніпропетровський Державний Проектно-Вишукувальний Інститут Дніпродіпротранс | Support for pipeline |
RU2286920C1 (en) * | 2005-04-07 | 2006-11-10 | Открытое акционерное общество "Уральский завод гражданской авиации" | Helicopter suspension unit |
RU2525992C1 (en) * | 2013-01-31 | 2014-08-20 | Андрей Михайлович Усков | Device to suspend underground pipeline at subsiding soils |
RU161900U1 (en) * | 2015-04-15 | 2016-05-10 | Открытое акционерное общество "Акционерная компания по транспорту нефти "Транснефть" (ОАО "АК "Транснефть") | CHAIN SUSPENSION ADJUSTABLE FOR PIPELINE SUPPORTS |
RU2601651C1 (en) * | 2015-04-15 | 2016-11-10 | Открытое акционерное общество "Акционерная компания по транспорту нефти "Транснефть" (ОАО "АК "Транснефть") | Suspension support for sections of underground pipeline routing |
-
2017
- 2017-10-20 RU RU2017137018U patent/RU184322U1/en active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3767149A (en) * | 1972-03-17 | 1973-10-23 | J Hill | Support trestle for permafrost areas |
SU614280A1 (en) * | 1976-04-28 | 1978-07-05 | Ленинградское Отделение Всесоюзного Государственного Ордена Ленина И Ордена Октябрьской Революции Проектного Института "Теплоэлектропроект" | Pipeline suspension member |
SU646130A1 (en) * | 1977-04-11 | 1979-02-05 | Luksha Valentin O | Suspended support for suspended pipeline |
SU916865A1 (en) * | 1980-07-29 | 1982-03-30 | Северо-Кавказский Зональный Научно-Исследовательский И Проектный Институт "Севкавзнииэпсельстрой" | Overhead pipeline support assembly |
UA7160A (en) * | 1994-08-05 | 1995-06-30 | Дніпропетровський Державний Проектно-Вишукувальний Інститут Дніпродіпротранс | Support for pipeline |
RU2286920C1 (en) * | 2005-04-07 | 2006-11-10 | Открытое акционерное общество "Уральский завод гражданской авиации" | Helicopter suspension unit |
RU2525992C1 (en) * | 2013-01-31 | 2014-08-20 | Андрей Михайлович Усков | Device to suspend underground pipeline at subsiding soils |
RU161900U1 (en) * | 2015-04-15 | 2016-05-10 | Открытое акционерное общество "Акционерная компания по транспорту нефти "Транснефть" (ОАО "АК "Транснефть") | CHAIN SUSPENSION ADJUSTABLE FOR PIPELINE SUPPORTS |
RU2601651C1 (en) * | 2015-04-15 | 2016-11-10 | Открытое акционерное общество "Акционерная компания по транспорту нефти "Транснефть" (ОАО "АК "Транснефть") | Suspension support for sections of underground pipeline routing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
ES2784000T3 (en) | Foundation for a windmill | |
TWI673432B (en) | Offshore support structure | |
US8511940B2 (en) | Offshore support structure and associated method of installing | |
KR101385028B1 (en) | Earth retaining structure having beam | |
EP2252749A1 (en) | Tower element | |
CN114174675B (en) | Support structure, in particular for a land-based and/or sea-based wind energy installation | |
RU2601651C1 (en) | Suspension support for sections of underground pipeline routing | |
KR100995820B1 (en) | Temporary bridge construction methods absorbing longtidudinal displacement and live load impact | |
JP4864774B2 (en) | Reinforcement method for water structure | |
US11753789B2 (en) | Pumping unit bases with driven piles | |
RU184322U1 (en) | Rostverk for suspended support of pipelines of underground laying, compensating deviations of piles at installation | |
CN111795212B (en) | Suspension method and suspension structure for pipeline crossing foundation pit | |
CN112112666A (en) | Connecting and rapid positioning device and method for shield tunnel prefabricated box culvert structure | |
GB2480501A (en) | A tunnel support apparatus | |
CN108915768B (en) | Fixing force transmission support system for thermodynamic pipeline in thermodynamic shield tunnel | |
CN206036408U (en) | Span pipeline normal position of foundation ditch and suspend protection architecture in midair | |
CN106320365B (en) | Assembly type foundation combining cylindrical supporting body and base | |
CN212454442U (en) | Quick positioning device for connecting prefabricated box culvert structure of shield tunnel | |
CN204475150U (en) | Assembly type steel bridge pier column | |
CN108487040A (en) | A kind of steel corrugated plating assembling combination bridge | |
RU46769U1 (en) | SUPPORT FOR HIGH STABILITY FOR GROUND PIPELINES | |
CN207377582U (en) | A kind of 36U circular arc sheds for coal roadway support | |
CN216515077U (en) | Utilize overhanging type pier to increase the overhead pipeline structure of span | |
KR200425123Y1 (en) | Multipurpose prefabricated structure | |
CN216973156U (en) | High-position beam falling structure based on walking machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
QB9K | Licence granted or registered (utility model) |
Free format text: LICENCE FORMERLY AGREED ON 20190318 Effective date: 20190318 |