RU1803569C - Method for protection of mine working at great depths - Google Patents

Method for protection of mine working at great depths

Info

Publication number
RU1803569C
RU1803569C SU904853349A SU4853349A RU1803569C RU 1803569 C RU1803569 C RU 1803569C SU 904853349 A SU904853349 A SU 904853349A SU 4853349 A SU4853349 A SU 4853349A RU 1803569 C RU1803569 C RU 1803569C
Authority
RU
Russia
Prior art keywords
workings
auxiliary
zones
mine
rock
Prior art date
Application number
SU904853349A
Other languages
Russian (ru)
Inventor
Евгений Иванович Шемякин
Михаил Владимирович Курленя
Виктор Николаевич Опарин
Владимир Николаевич Рева
Федор Петрович Глушихин
Марк Абрамович Розенбаум
Original Assignee
Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела filed Critical Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела
Priority to SU904853349A priority Critical patent/RU1803569C/en
Application granted granted Critical
Publication of RU1803569C publication Critical patent/RU1803569C/en

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

Использование: Изобретение может быть использовано при добыче полезных ископаемых подземным способом на большой глубине, где имеет место  вление зональной дезинтеграции горных пород. Сущность: дл  повышени  устойчивости выработок путем сохранени  эффекта разгрузки пород, про вл ющегос  при возникновении этого  влени . Провод т охран емую и вспомогательную выработки, последние провод т в одной из зон разрушенных пород, горную массу из указанной зоны удал ют и образовавшуюс  полость в кровле вспомогательных выработок заполн ют сыпучим материалом и после восстановлени  напр жений в массиве вокруг охран емой выработки частично выпускают сыпучий материал во вспомогательных выработках . 3 ил.Usage: The invention can be used in the extraction of minerals by underground mining at great depths, where the phenomenon of zonal disintegration of rocks takes place. Essence: to increase the stability of mine workings by preserving the effect of rock unloading that manifests itself when this phenomenon occurs. Protected and auxiliary workings are carried out, the latter are carried out in one of the zones of destroyed rocks, the rock mass is removed from the specified zone, and the cavity formed in the roof of the auxiliary workings is filled with bulk material and, after restoration of the stresses in the array around the protected workings, loose bulk is released material in auxiliary workings. 3 ill.

Description

елate

сwith

Изобретение относитс  к горнодобыва-. ющей промышленности и может быть использовано при эксплуатации горных выработок на больших глубинах.The invention relates to mining. industry and can be used in mining operations at great depths.

Цель изобретени  - повышение устойчивости выработок, путем сохранени  эффекта разгрузки пород.The purpose of the invention is to increase the stability of mine workings by maintaining the effect of rock unloading.

На фиг. 1 показан поперечный разрез в плоскости проводимых выработок ; на фиг 2 - разрез по I-I фиг. 1; на фиг. 3 - поперечный разрез в плоскости вспомогательной выработки .In FIG. 1 shows a cross section in the plane of the workings; FIG. 2 is a section along I-I of FIG. 1; in FIG. 3 - transverse section in the plane of the auxiliary production.

Способ осуществл етс  следующим образом . Вначале провод т выработку 1, котора   вл етс  основной и должна находитьс  в эксплуатационном состо нии в течении всего срока службы. В стенку выработки бур т шпур и путем просмотра его стенок, например прибором РВП-451, определ ют размеры и местоположение зон дезинтеграции , зоны разрушенных пород -2 и зон не- разрушенных пород -3, после этого засекают параллельно выработке 1 вспомогательные выработки 4, которые располагают по обе стороны от охран емой вы работки в пределах зоны дезинтеграции таким образом , чтобы их сечени  частично совпали с зоной разрушенных пород. Затем из разрушенной зоны, захватывающей часть кровли вспомогательных выработок, удал ют разрушенную горную массу, а в образовавшуюс  полость 7 укладывают разделительные элементы 6, зат жкой перекрывают кровлю и заполн ют полость 7 сыпучим материаоэThe method is carried out as follows. First, mining 1 is carried out, which is the main one and must be in operational condition throughout the entire service life. Drill a hole into the wall of the mine, and by viewing its walls, for example with the RVP-451 device, determine the sizes and location of the disintegration zones, the zones of the destroyed rocks -2 and the zones of the undisturbed rocks -3, after which the auxiliary workings 4 are tracked parallel to the mine 1, which are located on both sides of the protected mining within the disintegration zone so that their cross sections partially coincide with the zone of destroyed rocks. Then, from the destroyed zone, which captures part of the roof of the auxiliary workings, the destroyed rock mass is removed, and the separation elements 6 are placed in the formed cavity 7, the roof is covered with a puff and the cavity 7 is filled with loose material

ОABOUT

СА)CA)

ел о юate about

лом. Спуст  некоторое врем , под вли нием сил гравитации сыпучий материал будет сжат в полости и давление, передаваемое на крепь охран емой выработки начнет расти. Тогда в кровле вспомогательных выработок вынимают часть зат жки и часть сыпучего материала выпускают из полости 7 до образовани  в ней свободного пространства 8, после чего зат жку восстанавливают. Сыпучий материал выпускают в вагонетки 9, в которых и транспортируют его к месту складировани . При дальнейшем увеличении давлени  операцию выпуска вновь осуществл ют в описанном пор дке.scrap. After some time, under the influence of gravitational forces, the bulk material will be compressed in the cavity and the pressure transmitted to the support of the guarded mine will begin to increase. Then, part of the puff is removed in the roof of the auxiliary workings and part of the bulk material is released from the cavity 7 until a free space 8 is formed in it, after which the puff is restored. Bulk material is released into trolleys 9, in which it is transported to the place of storage. With a further increase in pressure, the discharge operation is again carried out in the described order.

Использование предлагаемого способа позвол ет обеспечить безремонтное поддержание охран емой выработки в течении всего периода ее эксплуатации, направленно , в зависимости от геомеханической обстановки , измен ть нагрузки на крепь охран емой выработки; использовать дл  креплени  основных выработок на больших глубинах крепи нормального, не повышеи0Using the proposed method allows for the maintenance-free maintenance of the guarded mine during the entire period of its operation, directionally, depending on the geomechanical situation, change the load on the lining of the guarded mine; use for fixing the main workings at great depths of the normal support, not higher than 0

55

00

ного сопротивлени ; исключить опасность возникновени  горного удара при длительной эксплуатации выработок.resistance; eliminate the risk of rock impact during long-term operation of the workings.

Claims (1)

Формула изобретени  Способ охраны горных выработок на больших глубинах, включающий опережающее проведение охран емой выработки, определение положение вокруг нее чередующихс  зон разрушенных и неразрушенных горных пород, образующих зоны дезинтеграции , проведение вспомогательных выработок в пределах этих зон, отличающий- с   тем, что, с целью повышени  устойчивости выработки путем сохранени  эффекта разгрузки пород, вспомогательные выработки проход т в одной из зон разрушени  пород, горную массу из указанной зоны удал ют , образовавшуюс  полость в кровле вспомогательных выработок заполн ют сыпучим материалом, и после восстановлени  напр жени  в массиве вокруг охран емой выработки частично выпускают сыпучий материал во вспомогательных выработках.SUMMARY OF THE INVENTION A method for protecting mine workings at great depths, including anticipating guarded workings, determining the position around it of alternating zones of destroyed and undamaged rocks forming disintegration zones, conducting auxiliary workings within these zones, characterized in that, for the purpose of increase the stability of the mine by maintaining the effect of rock unloading, auxiliary mine workings take place in one of the zones of rock destruction, the rock mass is removed from this zone, forming the sagging cavity in the roof of the auxiliary workings is filled with bulk material, and after the voltage is restored in the array around the guarded workings, the bulk material in the auxiliary workings is partially released. Фыг.2Fig.2
SU904853349A 1990-06-11 1990-06-11 Method for protection of mine working at great depths RU1803569C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU904853349A RU1803569C (en) 1990-06-11 1990-06-11 Method for protection of mine working at great depths

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU904853349A RU1803569C (en) 1990-06-11 1990-06-11 Method for protection of mine working at great depths

Publications (1)

Publication Number Publication Date
RU1803569C true RU1803569C (en) 1993-03-23

Family

ID=21528815

Family Applications (1)

Application Number Title Priority Date Filing Date
SU904853349A RU1803569C (en) 1990-06-11 1990-06-11 Method for protection of mine working at great depths

Country Status (1)

Country Link
RU (1) RU1803569C (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР .№ 1461965, кл. Е 21 D 1,1/00, 1989. Авторское свидетельство СССР № 1458597, кл. Е 21 D 5/00, 1988. *

Similar Documents

Publication Publication Date Title
Bräuner Rockbursts in coal mines and their prevention
Szwedzicki Geotechnical precursors to large-scale ground collapse in mines
Morissette et al. The influence of change in mining and ground support practice on the frequency and severity of rockbursts
RU1803569C (en) Method for protection of mine working at great depths
Pan et al. A new theoretical view of rockburst and its engineering application
US2846205A (en) Mining method for supporting geological structures
Williams et al. Underhand cut and fill mining as practiced in three deep hard rock mines in the United States
Paetzold et al. Reopening and closure of a block cave
Chouhan Induced seismicity of Indian coal mines
Szwedzicki Pre-and post-failure ground behaviour: case studies of surface crown pillar collapse
RU2122116C1 (en) Method of safeguard of mine workings in beds
Villaescusa et al. Backfill for bench stoping operations
RU2755287C1 (en) Method for developing thin and low-powered steel-falling ore bodies
SU757740A1 (en) Ore protecting anchor-rod lining for underground ore chutes
SU1765458A1 (en) Method of controlling stress in rocks adjoining mine working
SU899989A2 (en) Power-roof support
Singh et al. Review of fill mining technology in Canada
SU1680994A1 (en) Method for working steep coal seams having tendency towards gas dynamic effects
SU1731949A1 (en) Method of protecting ore masses from rock pressure
RU2107165C1 (en) Method of bore-hole hydraulic recovery of minerals
SU987102A1 (en) Method of forming dumps on slopes
SU1247538A1 (en) Method of open-cast mining of minerals
White et al. Differential wall rock movements associated with rock bursts, Lucky Friday Mine, Coeur d'Alene Mining District, Idaho, USA
Yernaidu et al. A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
CN116428002A (en) Movable adjustable flexible disaster-isolation intelligent suspension device for ultra-long roadway and operation method