PL139088B1 - Method of manufacture of allyl chloride - Google Patents

Method of manufacture of allyl chloride Download PDF

Info

Publication number
PL139088B1
PL139088B1 PL24294083A PL24294083A PL139088B1 PL 139088 B1 PL139088 B1 PL 139088B1 PL 24294083 A PL24294083 A PL 24294083A PL 24294083 A PL24294083 A PL 24294083A PL 139088 B1 PL139088 B1 PL 139088B1
Authority
PL
Poland
Prior art keywords
column
hydrogen chloride
tank
amount
chlorine
Prior art date
Application number
PL24294083A
Other languages
Polish (pl)
Other versions
PL242940A1 (en
Inventor
Wladyslaw Madej
Marian Spadlo
Zofia Pokorska
Jerzy Wasilewski
Manfred Stajszczyk
Grzegorz Lewandowski
Tadeusz Wilusz
Andrzej Lauer
Original Assignee
Instytut Ciezkiej Syntezy Organicznej Blachownia
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Instytut Ciezkiej Syntezy Organicznej Blachownia filed Critical Instytut Ciezkiej Syntezy Organicznej Blachownia
Priority to PL24294083A priority Critical patent/PL139088B1/en
Priority to GB08414269A priority patent/GB2142626B/en
Priority to SU843754757A priority patent/SU1429933A3/en
Priority to BR8403228A priority patent/BR8403228A/en
Priority to IN471/CAL/84A priority patent/IN161697B/en
Priority to BG6614684A priority patent/BG45696A3/en
Publication of PL242940A1 publication Critical patent/PL242940A1/en
Publication of PL139088B1 publication Critical patent/PL139088B1/en

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C07ORGANIC CHEMISTRY
    • C07CACYCLIC OR CARBOCYCLIC COMPOUNDS
    • C07C17/00Preparation of halogenated hydrocarbons
    • C07C17/093Preparation of halogenated hydrocarbons by replacement by halogens
    • C07C17/10Preparation of halogenated hydrocarbons by replacement by halogens of hydrogen atoms

Landscapes

  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Organic Low-Molecular-Weight Compounds And Preparation Thereof (AREA)

Description

Przedmiotem wynalazku jest sposób wytwarzania chlorku allilu przez wysokotemperaturowe chlorowanie propylenu i rektyfikacyjne wydzielanie chlorowodoru z mieszaniny poreakcyjnej, W procesach wytwarzania chlorku allilu, w których wykorzystuje sie cieplo reakcji do podgrzewania propylenu, a chlorowodór wydziela sie z mieszaniny poreakcyjnej na drodze rek¬ tyfikacji, wystepuje bardzo silne wzajemne oddzialywanie zaklócen w pracy aparatów i urzadzen.Szczególne nasilenie zaklócen ma miejsce w czasie uruchamiania instalacji, kiedy sa jeszcze nieustabilizowane parametry pracy i sklady strumieni technologicznych. Duza wrazliwosc proce¬ su chlorowania na niewielkie zmiany w temperaturze, cisnieniu, wilgotnosci surowców i na zmia¬ ny innych parametrów jest glównym powodem trudnosci wystepujacych w czasie uruchamiania ins¬ talacji chlorku allilu. Wedlug danych termodynamicznych w warunkach chlorowania moze przebie¬ gac kilkanascie reakcji konkurencyjnych, w tym prowadzacych do gromadzenia sie wegla i chlo¬ rowodoru w produktach reakcji.W trakcie uruchamiania procesu bardzo latwo wytwarza sie sadza i koks. Przypuszcza sie, ze spowodowane to jest zmianami w cisnieniu i zalezy od stopnia wymieszania reagentów w ukla¬ dzie reaktorowym. W okresie uruchamiania instalacji bardzo trudno zachowac stale cisnienie i stala szybkosc przeplywu strumieni technologicznych. Wystarczy bowiem aby wzrosly opory w pom¬ pie, kolumnie lub innym urzadzeniu a zmieni sie cisnienie w ukladzie reaktorowym. Sadza powsta¬ la w ukladzie reaktorowym osadza sie w przeponowym wymienniku ciepla i zwieksza opory na linii odplywu gazów poreakcyjnych, co zwieksza wydzielanie sadzy, pogarsza wymiane ciepla i w efekcie zmusza do zatrzymania instalacji celem jej oczyszczenia. W literaturze technicznej, dotyczacej tematu brak jest informacji o tym, jak nalezy prowadzic proces a zwlaszcza, jak uruchamiac in¬ stalacje chlorku allilu, aby szybko ustabilizowac warunki pracy instalacji i lagodnie dojsc do zalozonych wielkosci produkcyjnych i w ten sposób zminimalizowac ujemne zjawiska i straty pro¬ dukcyjne.Istota wynalazku jest sposób wytwarzania chlorku allilu, na drodze chlorowania propylenu w temperaturze do 500°C z wstepnym wymieszaniem gazowych substratów w komorze mieszania i2 139 088 z wykorzystaniem w procesie chlorowania ciepla reakcji oraz przez rektyfikacyjne wydzielanie chlorowodoru z gazów poreakcyjnych. Przez komore mieszania i dalej przez reaktor, wymienniki ciepla, kolumne rektyfikacyjna do wydzielania chlorowodoru i przez zbiornik orosienia tej ko¬ lumny przepuszcza sie przy uruchamianiu procesu azot w ilosci stanowiacej co najmniej 20% wa¬ gowych wprowadzanego nastepnie do ukladu chloru i po uplywie 10-30 sekund rozpoczyna sie wpro¬ wadzac chlor najpierw w ilosci do 60# zalozonej ilosci a po przekroczeniu 66# tej ilosci prze¬ rywa sie doplyw azotu i azot wyprowadza z ukladu przez króciec odpowietrzajacy na zbiorniku orosienia kolumny rektyfikacyjnej chlorowodoru, przy czym w zbiorniku tym utrzymuje sie ciecz zawierajaca glównie propylen i chlorowodór, przez czas do 30 minut, a nastepnie cala zawartosc zbiornika orosienia kieruje na szczyt kolumny, po czym po osiagnieciu w oparach z kolumny za¬ wartosci 95% objetosciowych chlorowodoru napelnia sie zbiornik cieklym orosieniem i utrzymuje w zbiorniku stan cieczy zapewniajacy stabilna prace kolumny.W wyniku takiego uruchamiania procesu wytwarzania chlorku allilu uzyskuje sie w ciagu 2 godzin ustabilizowanie parametrów pracy ukladu reaktorowego i kolumny do rektyfikacyjnego wy¬ dzielania chlorowodoru a nastepnie zakladana zdolnosc produkcyjna. Przypuszcza sie, ze azot przeplywajacy przez uklad reaktorowy i przez kolumne rektyfikacyjna do wydzielania chlorowo¬ doru stabilizuje szybkosc przeplywu gazów i opory oraz wplywa na lepsze wymieszanie w pierw¬ szej fazie procesu, co zapobiega tworzeniu sie sadzy i koksu. Równiez odprowadzenie azotu z instalacji, we wskazanym wedlug wynalazku momencie procesu, wplywa na przerwanie reakcji pro¬ pylenu i chlorowodór do 2-chloropropanu, zachodzacej w ukladzie do wytwarzania orosienia przy kolumnie rektyfikacyjnej. Reakcja powstawania 2-chloropropanu katalizowana jest przez komple¬ ksy katalityczne zelaza i zwiazków chloroorganicznych. Opróznienie zbiornika orosienia przery¬ wa ten proces.Uruchomienie instalacji chlorku allilu wyposazonej w uklad rektyfikacyjnego wydzielania chlorowodoru z mieszaniny poreakcyjnej w inny sposób niz opisano w wynalazku prowadzi do szyb¬ kiego zatkania wezla reaktorowego weglem, sadza i zwiazkami smolistymi oraz utrudnia przerwa¬ nie reakcji propylenu z chlorowodorem do 2-chloropropanu. Prowadzi to do pogorszenia wskazników zuzycia surowców, a nawet uniemozliwia prace instalacji. Efektem wynalazku jest mozliwosc pro¬ dukcji chlorku allilu na instalacjach posiadajacych uklad do rektyfikacyjnego wydzielania chlorowodoru z selektywnoscia na poziomie 77% molowych i wyzej chlorku allilu w przeliczeniu na uzyty chlor nawet w przypadku czestych wylaczen i uruchomien instalacji.Przyklad. Aparature instalacji chlorku allilu przedstawiona na rysunku wypelniano przed uruchomieniem osuszonym propylenem o maksymalnej zawartosci wilgoci 5 ppm i regulujac ogrzewanie wyparki £-18 wymuszano obieg propylenu z natezeniem 10 500 kg/h. Temperature propy¬ lenu doplywajacego do reaktora R-3 utrzymywano na poziomie okolo 270°C przez reagulacje ogrze¬ wania w piecu F-1• W zbiornikach V-7, V-12 i V-17 oraz w kubach kolumn K-9 i K-15 utrzymywano poziom cieklego propylenu okolo 50# napelnienia. Wlasciwy rozruch instalacji rozpoczeto otwar¬ ciem doplywu azotu przez przewód B, a po uplywie 10-30 s otwarciem doplywu chloru do urzadze¬ nia mieszajacego M-2 przez przewód C z natezeniem przeplywu 2500 kg/h. Jednoczesny przeplyw azotu i chloru utrzymywano przez 10-20 s, po czym zamknieto doplyw azotu. Z chwila wprowadze¬ nia chloru do ukladu reaktorowego nastapil gwaltowny wzrost temperatury w reaktorze R3, tempe¬ ratury propylenu opuszczajacego wymiennik ciepla E-4 oraz temperatury propylenu opusczajacego piec F-1. Po uplywie 5 minut temperatura w reaktorze R-3 osiagnela 460°C, temperatura propyle¬ nu opuszczajacego wymiennik ciepla E-4 osiagnela 275°C a temperatura propylenu doprowadzanego do urzadzenia mieszajacego M-2 3^0°C.W tym czasie rozpoczeto podawanie przewodem A osuszonego propylenu w ilosci zapewniajacej utrzymanie natezenia przeplywu propylenu obiegowego na poziomie 10500 kg/h. Po uplywie 1-2 mi¬ nut od chwili wprowadzenia chloru rozpoczal sie spadek temperatury na szczycie kolumny K-9, co swiadczylo o pojawieniu sie chlorowodoru w oparach tej kolumny. Od tej chwili przez okolo 20 minut utrzymywano poziom cieczy w zbiorniku orosienia V-12 i odpuszczano gazy przewodem D z ta-139 088 3 kim natezeniem, aby na szczycie kolumny utrzymac stale cisnienie okolo 0,16 MPa* Fotem opróz¬ niono calkowicie zbiornik orosienia V-12 i napelniano go ponownie do poziomu umozliwiajacego stabilna regulacje pracy kolumny dopiero po osiagnieciu 95% obj* chlorowodoru w oparach z ko¬ lumny, co odpowiada temperaturze szczytu okolo -71 C* Regulujac ogrzewanie wyparki £-13 i wielkosc orosienia chlodzeniem skraplacza E-11 uzyskano w ciagu okolo 2 godzin od chwili wprowadzenia chloru do ukladu reaktorowego temperature -74°C do -76°C na szczycie kolumny K-9 i - 28°C w kubie tej kolumny.W tych warunkach w produkcie górnym kolumny zawartosc chlorowodoru wynosila powyzej 98,5% obj* a w produkcie dolnym ponizej 0,4% wagowych* Po kilku godzinach podniesiono stopniowo przeplyw chloru do optymalnej wielkosci 3100 kg/h osiagajac temperature w reaktorze na pozio¬ mie 485°C* V tych warunkach prowadzono synteze chlorku allilu doprowadzajac swiezy propylen przewodem A w ilosci okolo 1800 kg/h i odbierajac chlorowodór przeowdem D w ilosci okolo 1400 kg/h o zawartosci okolo 99% obj* HCl oraz chlorek allilu przewodem F w ilosci okolo 2600 kg/h o zawartosci okolo 98,5% CJtLCl. Zawartosc 2-chloropropanu w wywarze kolumny K-9 byla nizsza od 0,7% wag*, a w wywarze kolumny K-15 miescila sie w granicach 1,3 - 2,3% wagowych* W tabeli przedstawiono szereg zmian parametrów ukladu reaktorowego i kolumny wydzielania chlorowodoru w czasie rozruchu instalacji prowadzonego sposobem wedlug wynalazku* Tabela 1 Lp. 1 2 3 4 5 6 7l 8 9 10 11 12! 13 14 15 Czas od¬ prowa¬ dzenia chloru _ 0 5 min* 15 min. 30 min* 45 min. 1 h 1 h 15 mir 1 h30 " 1 h 45" 2 h 4 h 6 h 8 h 14 h Przeplyw chloru w kg/h 0 - 2500 2500 2500 -«- -*... -"- -W- -W. -"- 2800 3000 3100 3100 Temp* C3K6 do M-1 w°C 180 i 180 275 od 270 od 275 -*- -»• -W- -«- -«„ -*. od 275 do 280 -»« -«- Temp* C3H6 do M-2 w °C 270 270 340 od 338 od 342 -M- -K- -*- -"- —n- -K- -«- -*- -W- -*- Temp* w R-3 w°C 270 270 ¦ 460 od 460 od 342 -«- -tt- -w- -»- -»- -W- 475 480 od 483 do 486 Temp* w V-7 w°C -30 -30 -28 ! od -25 od -28 -W.-H- -«- -»- -«- -»« -W- —W- -N- -«- Tempera¬ tura szczytu K-9 w°C I -39 I -39 -42 -47 -55 -64 -68 -71 -75 -76 od -74 do -76 i -W- -M- -W_ Temp* Kuba K-9 w°C -30 -30 -30 od -28 do -30 -*- -W- -W— -"- -»- -«- -tl.-W- -K- -W- Stez.HCl na szczycie K-9 w % obj. 0 0 - - 72 I 93 95 98,5 od 98,5 do 99,5 -«- I -W- I m*H— I -tt- I Zastrzezenie patentowe Sposób wytwarzania chlorku allilu, na drodze chlorowania propylenu w temperaturze do 500°C z wstepnym wymieszaniem gazowych substratów w komorze mieszania i z wykorzystaniem w procesie chlorowania ciepla reakcji oraz przez rektyfikacyjne wydzielanie chlorowodoru z gazów poreak¬ cyjnych, znamienny tym, ze przez komore mieszania i dalej przez reaktor, wymienniki ciepla, kolumne rektyfikacyjna do wydzielania chlorowodoru i przez zbiornik orosienia tej kolum-4 139 088 ny przepaiszcza sie przy uruchamianiu procesu azot w ilosci stanowiacej co najmniej 20# wago¬ wych wprowadzanego nastepnie do ukladu chloru i po uplywie 10-30 sekund rozpoczyna sie wpro¬ wadzac chlor najpierw w ilosci do 60# zalozonej ilosci a po przekroczeniu 66% tej ilosci przerywa sie doplyw azotu i azot wyprowadza z ukladu przez króciec odpowietrzajacy na zbior¬ niku orosienia kolumny reaktyfIkacyjneJ chlorowodoru, przy czym w zbiorniku tym utrzymuje siS clSS* zawierajaca glównie propylen i chlorowodór przez czas do 30 minut, a nastepnie ca¬ la zawartosc zbiornika orosienia kieruje sie na szczyt kolumny, po czym po osiagnieciu w opa¬ rach z kolumny zawartosci 95# objetosciowych chlorowodoru napelnia sie zbiornik cieklym oro- sieniem i utrzymuje w zbiorniku stan cieczy zapewniajacy stabilna prace kolumny.£ PI M-2 R-3 E-4 E-5 E-6 Pracownia Poligraficzna UP PRL. Naklad 100 egz.Cena 130 zl PLThe subject of the invention is a process for the production of allyl chloride by high-temperature chlorination of propylene and rectification of hydrogen chloride from the reaction mixture. In the processes of producing allyl chloride, where the heat of reaction is used to heat propylene, and hydrogen chloride is separated from the reaction mixture by rectification, it is very present. strong interaction of disturbances in the operation of apparatuses and devices. Particular intensity of disturbances takes place during commissioning of the installation, when the operating parameters and composition of technological streams are still unstable. The high sensitivity of the chlorination process to slight changes in temperature, pressure, moisture of raw materials and changes in other parameters is the main reason for the difficulties encountered in starting the installation of allyl chloride. According to thermodynamic data, under the conditions of chlorination, several competitive reactions can take place, including those leading to the accumulation of carbon and hydrogen chloride in the reaction products. In the process of starting the process, soot and coke are very easily produced. This is presumed to be due to pressure variations and is dependent on the degree of mixing of the reactants in the reactor system. It is very difficult to maintain a constant pressure and constant flow rate of technological streams during the start-up of the installation. It is enough for the resistance in the pump, column or other device to increase and the pressure in the reactor system to change. The soot formed in the reactor system is deposited in the membrane heat exchanger and increases the resistance on the post-reaction gas outflow line, which increases the emission of soot, worsens heat transfer and, as a result, forces the installation to be stopped for cleaning. In the technical literature on the subject, there is no information on how to conduct the process and, in particular, how to start the allyl chloride installation, in order to quickly stabilize the operating conditions of the installation and smoothly reach the assumed production volumes and thus minimize the negative phenomena and loss of production. The essence of the invention is a method for the production of allyl chloride by chlorination of propylene at a temperature of up to 500 ° C with preliminary mixing of gaseous substrates in the i2 139 088 mixing chamber using the heat of reaction in the chlorination process and by rectifying hydrogen chloride release from post-reaction gases. Through the mixing chamber and further through the reactor, heat exchangers, rectification column for the separation of hydrogen chloride and through the reflux tank of this column, nitrogen is passed when the process is started in an amount of at least 20% by weight of chlorine then introduced into the system and after 10 30 seconds, chlorine begins to introduce up to 60% of the assumed amount, and after exceeding 66% of this amount, the nitrogen supply is interrupted and nitrogen is discharged from the system through the venting connector on the reflux tank of the hydrogen chloride rectification column, and it is kept in this tank. the liquid, containing mainly propylene and hydrogen chloride, for up to 30 minutes, then the entire contents of the reflux tank is directed to the top of the column, and then, after reaching 95% volumetric hydrogen chloride in the vapors from the column, the tank is filled with liquid reflux and the tank is kept in its condition. the liquid ensuring stable operation of the column. As a result of such starting the process In the production of allyl chloride, the operating parameters of the reactor system and the column for rectifying hydrogen chloride separation are stabilized within 2 hours, and then the assumed production capacity. It is presumed that the nitrogen flowing through the reactor system and through the rectification column for the evolution of hydrogen chloride stabilizes the gas flow rate and resistance, and contributes to better mixing in the first stage of the process, which prevents the formation of soot and coke. Also, the removal of nitrogen from the installation, at the point of the process indicated according to the invention, disrupts the reaction of propylene and hydrogen chloride to 2-chloropropane, taking place in the system for producing reflux at the rectification column. The formation of 2-chloropropane is catalyzed by the catalytic complexes of iron and organochlorine compounds. The emptying of the reflux tank interrupts this process. The start-up of the allyl chloride installation equipped with a system for rectifying hydrogen chloride from the reaction mixture in a manner different than described in the invention leads to rapid clogging of the reactor node with carbon, soot and tar compounds and hinders the interruption of the propylene reaction. with hydrogen chloride to 2-chloropropane. This leads to a deterioration in the consumption rates of raw materials and even prevents the installation from working. The result of the invention is the possibility of producing allyl chloride in installations having a rectification system for hydrogen chloride separation with a selectivity of 77 mol% and higher allyl chloride based on the chlorine used, even in the case of frequent shutdowns and plant start-ups. The equipment of the allyl chloride plant shown in the drawing was filled before start-up with dried propylene with a maximum moisture content of 5 ppm and by controlling the heating of the evaporator £ -18, propylene circulation was forced at the rate of 10 500 kg / h. The temperature of the propylene flowing to the R-3 reactor was kept at about 270 ° C by heating reactions in the F-1 furnace. In the V-7, V-12 and V-17 tanks and in the K-9 and K column cups Maintain the liquid propylene level at around 50% fill. The proper start-up of the installation was started by opening the nitrogen flow through line B, and after 10-30 seconds, opening of the supply of chlorine to the mixing device M-2 through line C with a flow rate of 2500 kg / h. The simultaneous flow of nitrogen and chlorine was maintained for 10-20 s, after which the nitrogen flow was shut off. As chlorine was introduced into the reactor system, there was a sharp increase in the temperature in reactor R3, the temperature of the propylene leaving the heat exchanger E-4, and the temperature of the propylene leaving the furnace F-1. After 5 minutes, the temperature in the R-3 reactor reached 460 ° C, the temperature of the propylene leaving the E-4 heat exchanger reached 275 ° C and the temperature of the propylene supplied to the M-2 mixing device at 3 ° C 0 ° C. of dried propylene in an amount that maintains the circulating propylene flow rate at 10,500 kg / h. 1-2 minutes after the introduction of chlorine, the temperature dropped at the top of column K-9, which indicated the appearance of hydrogen chloride in the vapors of this column. From then on, the liquid level in the reflux tank V-12 was maintained for about 20 minutes, and the gases were tempered through the line D with a constant flow rate to maintain a constant pressure of about 0.16 MPa at the top of the column. The reflux tank was completely emptied with a photo. V-12 and it was refilled to the level enabling stable regulation of the column operation only after reaching 95% vol * of hydrogen chloride in the vapors from the column, which corresponds to the top temperature of about -71 ° C. By regulating the heating of the evaporator £ -13 and the amount of reflux by cooling the condenser E -11, the temperature of -74 ° C to -76 ° C at the top of the K-9 column and -28 ° C in the barrel of this column was obtained within about 2 hours from the moment of introducing chlorine into the reactor system. was above 98.5% by volume and in the bottom product below 0.4% by weight * After a few hours, the chlorine flow was gradually increased to the optimum value of 3100 kg / h, reaching the temperature in the reactor at 485 ° C * In these conditions, the synthesis of allyl chloride was carried out by supplying fresh propylene through the A line in the amount of about 1800 kg / h and receiving hydrogen chloride through the D line in the amount of about 1400 kg / h with the content of about 99% vol * HCl and allyl chloride through the F line in the amount of about 2600 kg / h content of about 98.5% CJtLCl. The content of 2-chloropropane in the K-9 column stock was lower than 0.7% by weight *, and in the K-15 column stock 1.3 - 2.3% by weight * The table shows a number of changes in the parameters of the reactor system and the column hydrogen chloride evolution during the start-up of the installation carried out according to the invention * Table 1 No. 1 2 3 4 5 6 7l 8 9 10 11 12! 13 14 15 Chlorine discharge time - 0.5 min. * 15 min. 30 mins * 45 mins 1 h 1 h 15 mir 1 h30 "1 h 45" 2 h 4 h 6 h 8 h 14 h Chlorine flow in kg / h 0 - 2500 2500 2500 - «- - * ... -" - -W- -W . - "- 2800 3000 3100 3100 Temp * C3K6 to M-1 at ° C 180 and 180 275 from 270 from 275 - * - -» • -W- - «- -« "- *. from 275 to 280 - »« - «- Temp * C3H6 to M-2 in ° C 270 270 340 from 338 from 342 -M- -K- - * - -" - —n- -K- - «- - * - -W- - * - Temp * in R-3 in ° C 270 270 ¦ 460 from 460 from 342 - «- -tt- -w- -» - - »- -W- 475 480 from 483 to 486 Temp * in V-7 in ° C -30 -30 -28! from -25 from -28 -W.-H- - «- -» - - «- -» «-W- —W- -N- -« - Peak temperature K-9 in ° CI -39 I -39 -42 -47 -55 -64 -68 -71 -75 -76 -74 to -76 and -W- -M- -W_ Temp * Kuba K -9 at ° C -30 -30 -30 -28 to -30 - * - -W- -W— - "- -» - - «- -tl.-W- -K- -W- HCl concentration at the K-9 peak in% vol. 0 0 - - 72 I 93 95 98.5 from 98.5 to 99.5 - "- I -W- I m * H— I -tt- I Patent claim Process for the preparation of allyl chloride by chlorination of propylene at temperatures up to 500 ° C with preliminary mixing of the gaseous substrates in the mixing chamber and using the heat of reaction in the chlorination process and by rectifying hydrogen chloride separation from the post-reaction gases, characterized in that through the mixing chamber and further through the reactor, heat exchangers, rectification column for hydrogen chloride separation and through the reflux tank of this column, when the process is started, nitrogen in an amount of at least 20% by weight is then introduced into the chlorine system, and after 10-30 seconds, chlorine is first introduced in an amount of up to 60% of the assumed amount, until 66% of this amount is exceeded, the nitrogen flow is interrupted and the nitrogen is discharged from the system through a venting nozzle on the reflux tank of the hydrogen chloride reactivation column, where for this, the ClSS * containing mainly propylene and hydrogen chloride is maintained for up to 30 minutes, and then the entire contents of the reflux tank are directed to the top of the column, and then, after reaching 95% by volume of hydrogen chloride in the vapor, the tank is filled with liquid and maintains the liquid condition in the tank ensuring stable operation of the column. £ PI M-2 R-3 E-4 E-5 E-6 Printing Workshop UP PRL. Mintage 100 copies Price PLN 130 PL

Claims (1)

1. Zastrzezenie patentowe Sposób wytwarzania chlorku allilu, na drodze chlorowania propylenu w temperaturze do 500°C z wstepnym wymieszaniem gazowych substratów w komorze mieszania i z wykorzystaniem w procesie chlorowania ciepla reakcji oraz przez rektyfikacyjne wydzielanie chlorowodoru z gazów poreak¬ cyjnych, znamienny tym, ze przez komore mieszania i dalej przez reaktor, wymienniki ciepla, kolumne rektyfikacyjna do wydzielania chlorowodoru i przez zbiornik orosienia tej kolum-4 139 088 ny przepaiszcza sie przy uruchamianiu procesu azot w ilosci stanowiacej co najmniej 20# wago¬ wych wprowadzanego nastepnie do ukladu chloru i po uplywie 10-30 sekund rozpoczyna sie wpro¬ wadzac chlor najpierw w ilosci do 60# zalozonej ilosci a po przekroczeniu 66% tej ilosci przerywa sie doplyw azotu i azot wyprowadza z ukladu przez króciec odpowietrzajacy na zbior¬ niku orosienia kolumny reaktyfIkacyjneJ chlorowodoru, przy czym w zbiorniku tym utrzymuje siS clSS* zawierajaca glównie propylen i chlorowodór przez czas do 30 minut, a nastepnie ca¬ la zawartosc zbiornika orosienia kieruje sie na szczyt kolumny, po czym po osiagnieciu w opa¬ rach z kolumny zawartosci 95# objetosciowych chlorowodoru napelnia sie zbiornik cieklym oro- sieniem i utrzymuje w zbiorniku stan cieczy zapewniajacy stabilna prace kolumny. £ PI M-2 R-3 E-4 E-5 E-6 Pracownia Poligraficzna UP PRL. Naklad 100 egz. Cena 130 zl PLClaim 1. Process for the production of allyl chloride by chlorination of propylene at a temperature of up to 500 ° C with preliminary mixing of the gaseous substrates in the mixing chamber and using the heat of reaction in the chlorination process and by rectifying hydrogen chloride separation from the reaction gases, characterized by mixing chamber and further through the reactor, heat exchangers, rectification column for the separation of hydrogen chloride and through the reflux tank of this column, the nitrogen is passed through the process in an amount of at least 20% by weight of chlorine then introduced into the system and after elapsing 10-30 seconds, chlorine is first introduced in an amount of up to 60% of the assumed amount, and when 66% of this amount is exceeded, the nitrogen supply is interrupted and the nitrogen is discharged from the system through the venting port on the reflux tank of the hydrogen chloride reactivation column, while in the tank this keeps clSS *, which mainly consists of propylene and chlorine Hydrogen for up to 30 minutes, and then the entire contents of the reflux tank is directed to the top of the column, and then, after reaching 95% volumetric hydrogen chloride in the vapors from the column, the tank is filled with liquid hydration and the tank is kept in a liquid state that ensures stable work of the column. £ PI M-2 R-3 E-4 E-5 E-6 Printing workshop of the Polish People's Republic. Mintage 100 copies. Price PLN 130 PL
PL24294083A 1983-07-07 1983-07-07 Method of manufacture of allyl chloride PL139088B1 (en)

Priority Applications (6)

Application Number Priority Date Filing Date Title
PL24294083A PL139088B1 (en) 1983-07-07 1983-07-07 Method of manufacture of allyl chloride
GB08414269A GB2142626B (en) 1983-07-07 1984-06-05 Continuous method for the manufacture of allyl chloride
SU843754757A SU1429933A3 (en) 1983-07-07 1984-06-25 Method of producing allyl chloride
BR8403228A BR8403228A (en) 1983-07-07 1984-06-29 PROCESS FOR THE MANUFACTURE OF ALLYL CHLORIDE
IN471/CAL/84A IN161697B (en) 1983-07-07 1984-07-04
BG6614684A BG45696A3 (en) 1983-07-07 1984-07-06 Method for preparing of alylchloride

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL24294083A PL139088B1 (en) 1983-07-07 1983-07-07 Method of manufacture of allyl chloride

Publications (2)

Publication Number Publication Date
PL242940A1 PL242940A1 (en) 1985-01-16
PL139088B1 true PL139088B1 (en) 1986-12-31

Family

ID=20017845

Family Applications (1)

Application Number Title Priority Date Filing Date
PL24294083A PL139088B1 (en) 1983-07-07 1983-07-07 Method of manufacture of allyl chloride

Country Status (6)

Country Link
BG (1) BG45696A3 (en)
BR (1) BR8403228A (en)
GB (1) GB2142626B (en)
IN (1) IN161697B (en)
PL (1) PL139088B1 (en)
SU (1) SU1429933A3 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103724156B (en) * 2013-12-19 2015-06-24 山东海益化工科技有限公司 Chloropropene rectification process

Also Published As

Publication number Publication date
BG45696A3 (en) 1989-07-14
IN161697B (en) 1988-01-16
GB2142626A (en) 1985-01-23
SU1429933A3 (en) 1988-10-07
GB8414269D0 (en) 1984-07-11
PL242940A1 (en) 1985-01-16
BR8403228A (en) 1985-06-11
GB2142626B (en) 1987-06-10

Similar Documents

Publication Publication Date Title
JP5419350B2 (en) Method and apparatus for producing 1,2-dichloroethane by direct chlorination
US7144568B2 (en) Method and device for carrying out a reaction in liquid medium with gas evolution
US3535268A (en) Continuous process for manufacture of sols
PL139088B1 (en) Method of manufacture of allyl chloride
JP5590570B2 (en) Process for simultaneously producing different mixtures of diphenylmethane diisocyanate isomers
US2965455A (en) Apparatus for producing hydrogen sulfide
US7387770B2 (en) Method for ferric sulfate manufacturing
US5284630A (en) Apparatus for production of acetylene
CN107954827A (en) A kind of technique of hexachlorobutadiene conversion carbon trichloride
US3215503A (en) Apparatus for generating and storing inert gas
EP1657217A1 (en) Process for recovering calcium chloride from the purge of epichlorhydrine production
US3052518A (en) Process and apparatus for the manufacture of aluminum chloride
US4396593A (en) Process for the production of tin(IV) chloride
US3397206A (en) Production of chloroisocyanurates
US2735749A (en) The separate recovery of ammonia and hydrogen
US3222138A (en) Apparatus for the continuous manufacture of chlorinated cyanuric acid
NO329097B1 (en) Methods for preparing methyl formate
USH1697H (en) Continuous process for sodium methylate
CN1064253A (en) The commercial run of separation and recovery of chlorine
US6699455B2 (en) Process for preparing hydrogen fluoride in a rotary tube furnace
US5608124A (en) Process for continuous liquid phase reaction of hydrogen fluoride and 1,1,1-trichloroethane to provide 1,1-dichloro-1-fluoroethane and 1-chloro-1, 1-difluoroethane mixtures
US3330877A (en) Process for the chlorination of unsaturated hydrocarbons and unsaturated chlorohydrocarbons
RU2310666C2 (en) Method of governing butyl rubber production
EP0946261A1 (en) Process for removing chlorine from gas stream
US3431314A (en) Process for chlorinating hydrocarbons