NL2029776B1 - Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel. - Google Patents

Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel. Download PDF

Info

Publication number
NL2029776B1
NL2029776B1 NL2029776A NL2029776A NL2029776B1 NL 2029776 B1 NL2029776 B1 NL 2029776B1 NL 2029776 A NL2029776 A NL 2029776A NL 2029776 A NL2029776 A NL 2029776A NL 2029776 B1 NL2029776 B1 NL 2029776B1
Authority
NL
Netherlands
Prior art keywords
load distribution
jack
pinion
vessel
pinion group
Prior art date
Application number
NL2029776A
Other languages
Dutch (nl)
Inventor
Romeijn Eric
Martinus Van Veluw Cornelis
Original Assignee
Itrec Bv
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Itrec Bv filed Critical Itrec Bv
Priority to NL2029776A priority Critical patent/NL2029776B1/en
Priority to PCT/EP2022/082123 priority patent/WO2023088958A1/en
Application granted granted Critical
Publication of NL2029776B1 publication Critical patent/NL2029776B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/04Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction
    • E02B17/08Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction for raising or lowering
    • E02B17/0818Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction for raising or lowering with racks actuated by pinions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B79/00Monitoring properties or operating parameters of vessels in operation
    • B63B79/10Monitoring properties or operating parameters of vessels in operation using sensors, e.g. pressure sensors, strain gauges or accelerometers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B79/00Monitoring properties or operating parameters of vessels in operation
    • B63B79/30Monitoring properties or operating parameters of vessels in operation for diagnosing, testing or predicting the integrity or performance of vessels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/021Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto with relative movement between supporting construction and platform
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/003Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting very large loads, e.g. offshore structure modules

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • Wind Motors (AREA)

Abstract

Jack-up vessel for comprising a buoyant hull, a plurality ofjack-up legs comprising leg chords having racks, and jacking assemblies to relatively move the associated leg chord the buoyant hull vertically. Jacking assemblies comprise actuators and a pinion groups, comprising a plurality of pinions arranged vertically above each other. Jacking assemblies further comprise a sensor system for sensing the load distribution associated with a pinion group. The jack-up 10 vessel further comprises a control system configured for receiving information about an intended use and/or future environmental conditions and determining a pre-operation load distribution a pinion group, in which pre-operation load distribution the loads within this pinion group are unequally distributed, such that in the intended use and/or during the future environmental conditions the loads within this pinion group are equally distributed. A method 15 for operating a jack-up vessel and a control system for a jack-up vessel are also disclosed.

Description

P35215NLO0/IWO
Title: Jack-up vessel, method for operating a jack-up vessel and control system for a jack- up vessel.
Offshore operations, such as offshore wind turbine installation are generally performed using marine vessels comprising a buoyant hull used for travelling to the offshore location.
Depending on the requirements of offshore operations and characteristics of the offshore location, offshore operations may be performed with vessels which are of a type wherein the hull floats during operations or with vessels which are of a jack-up type, wherein the hull is raised above the water during operations.
This invention relates to a jack-up type vessel for use such as installing components of a wind turbine at a wind turbine installation site including hoisting said components, the jack-up vessel comprising: - a buoyant hull; - a plurality of jack-up legs, each jack-up leg comprising one or more leg chords having racks; - a plurality of jacking assemblies, each jacking assembly being associated with a leg chord, each jacking assembly being configured to relatively move the associated leg chord the buoyant hull vertically; wherein each jacking assembly comprises: o a pinion group, comprising a plurality of pinions arranged vertically above each other, each pinion engaging a rack and being configured for transferring load between the hull and the leg chord, resulting in a load distribution over the pinions within a pinion group; o actuators for actuating a pinion.
Jack-up type vessels as described so far are known to a person skilled in the art. The aim of the invention is to provide an improved version of such a jack-up vessel.
The aim is achieved according to the present invention in that: - jacking assemblies further comprise a sensor system configured for sensing the load distribution associated with a pinion group, and emitting sensor signals indicative of the sensed load distribution; and in that - the jack-up vessel further comprises a control system configured for o receiving information about an intended use and/or future environmental conditions; o determining, based on this information, a pre-operation load distribution for a pinion group, in which pre-operation load distribution the loads within this pinion group are unequally distributed, such that in the intended use and/or during the future environmental conditions the loads within this pinion group are equally distributed; o receiving the sensor signals indicative of the sensed load distribution, and determining! computing a difference between the pre-operation load distribution and the sensed load distribution; o emitting, in response to the difference, control signals to actuators, such that the sensed load distribution of the at least one pinion group corresponds to the pre- operation load distribution.
As will be elucidated later, the effect of the invention is to cause a lower wear on some pinions and/or allow the use of pinions with a lower maximum capacity.
Jack-up vessels generally are intended to be used for performing a certain operation. In the past, this was often e.g. for drilling for oil. Recently jack-up vessels are increasingly used for an operation of installing components of a wind turbine at a wind turbine installation site. In such a use, the jack-up vessel is e.g. used for hoisting said components, for instance from the location on a vessel and to the wind turbine installation site, such that they can be installed.
For example, a monopile may be hoisted which is fixed to a foundation on the sea bottom; subsequently, a nacelle may be hoisted to be attached to the monopile; and then wind turbine blades may be hoisted in order to complete the wind turbine assembly.
A jack-up vessel comprises a plurality of jack-up legs, generally 3, 4 or 8, which can be moved vertically relative to the buoyant hull. In a travelling configuration, these jack-up legs extend upward from the hull. Upon reaching the offshore location, before the intended operation is commenced, the jack-up vessel needs to be brought into an operational configuration. In this operational configuration, the jack-up legs are lowered with respect to the hull to engage with the seabed and further operating the jack-up legs to raise the hull of the vessel to a stationary position above the water level. Optionally, bringing the vessel in the operational configuration may further comprise a preloading operation of increasing the load on one leg at a time such that the load on the seabed exerted by that leg is temporarily higher, and repeating this for all legs. A so-called pre-drive operation may also be performed.
A jack-up leg comprises one or more leg chords. A jack-up leg is generally formed as a truss structure. For example, a triangular truss structure may comprise three leg chords in a jack- up leg and a rectangular truss structure four leg chords in a jack-up leg. The jack-up legs further comprise racks, usually two racks per leg chord. Operation of the jack-up legs is performed by jacking assemblies, each jacking assembly being associated with a leg chord.
Generally, one jacking assembly is associated with one leg chord. Each jacking assembly is configured to move the corresponding jack-up leg and the buoyant hull vertically relative with respect to each other.
A jacking assembly comprises a plurality of pinions and actuators, each actuator configured for actuating a respective pinion. The pinions are arranged vertically above each other, each pinion engaging a rack of its associated leg chord and being configured for transferring, in the operational configuration, a part of the load of the hull to the leg chord, resulting in each pinion having an actual transferred load associated with the pinion. The number of pinions per rack may for example be 1, 2, 3, 5, or 10 pinions per rack. The pinions which correspond to one rack are generally arranged vertically above each other and are referred to as a group of pinions. The jacking assemblies engage with the racks of a leg chord by means of the pinions to transfer loads from the jack-up assemblies to the legs and to move the jack-up legs with respect to the hull. A translational movement of the jack-up legs is achieved by means of a rotational movement of the pinions, which is achieved by operating the actuators. The operation of the actuators is stopped when the respective jack-up leg is in a desired position with respect to the hull or the seabed.
Once the jack-up legs are in the desired position, this position should be maintained, i.e. this position should be a stationary position. This may be achieved by using the actuators for braking. Alternatively, jack-up vessels may comprise brakes in jacking assemblies which may be applied such that the pinions maintain a reached configuration, such as the operational configuration, when operation of the actuators has ceased. Alternatively, locking parts may be applied to the pinions to cause them to maintain the reached configuration.
When a jack-up leg is in a stationary position, the pinions of this jack-up leg are generally maintained in a configuration corresponding to this stationary position, e.g. by applying brakes. In this stationary position, the configuration of the pinions in a pinion group is generally chosen such that the load distribution of these pinions is equal, as long as the load onthe jack-up leg is not changed. When the load on the jack-up leg changes, this load distribution between pinions in a pinion group may be unequal. For instance, when the load on a jack-up leg is increased due to a certain use, for instance a pre-loading operation or an operation of installing wind turbine components, this increase is not equally transferred to the lower pinions in the pinion group. This is especially the case if brakes are applied which brakes are situated between the pinion and the actuation mechanism; as long as the brakes are applied the load distribution cannot be, so to say, equalised. This causes that the lower pinions to need to transfer a higher load, while the upper pinions may see no increase or just a small increase in load. Consequently, the resulting load distribution is unequal.
Alternatively or in addition to the load on a jack-up leg increasing due to a certain use, this load may also increase due to environmental conditions. For instance, when a storm passes the offshore location, winds and/or swell may cause additional forces on the jack-up vessel.
These additional forces may not be equally distributed among all the legs. Consequently, the forces on some pinion groups may increase, causing (additional) unequal load distribution. In practice, the loads endured during a so-called storm holding operation may be one of the most influential on the requirements on the design of the jack-up legs and jacking-assemblies.
Unequal load distribution leads to a non-optimal loading of pinions, which may lead to higher wear on some pinions and/or the need for pinions with a higher capacity than if this unequal loading would not be the case.
According to the invention, the effect of unequal loading is reduced. This is achieved by the control system: - receiving information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operation load distribution for at least one pinion group, in which pre-operation load distribution the load within this pinion group is unequally distributed, such that in the intended use and/or during the future environmental conditions the load within this pinion group is equally distributed; - receiving the sensor signals indicative of the sensed load distribution, and determining/ computing a difference between the pre-operation load distribution and the sensed load distribution; - emitting, in response to the difference, control signals to actuators, such that the sensed load distribution of the at least one pinion group corresponds to the pre-operation load distribution.
In embodiments, the control system is configured to determine the pre-operation load distribution for each pinion group individually. For a jack-up vessel with 4 jack-up legs and 2 jacking assemblies per leg, 8 separate pre-operation load distributions are determined. It is conceivable that, for a certain operation, some or all of these pre-operation load distributions are the same.
In embodiments, the control system is configured to determine the pre-operation load 5 distribution for the pinion groups of a jack-up leg. In other words, in this embodiment the pre- operation load distribution is determined for all the pinion groups in a jack-up leg, i.e. the pre- operation load distribution may be different for each jack-up leg, but not between pinion groups of a jack-up leg. Of course, it is also possible to determine the pre-operation load distribution for a set of legs, such as the starboard jack-up legs or the portside jack-up legs; or for the front jack-up legs and the rear jack-up legs.
For example, when the pre-loading operation is initiated, the pre-operation load distribution may be set automatically such that when the maximum loads are reached, these are distributed equally over pinions in a pinion group.
In another example, when weather is forecast that exceeds a threshold, a storm hold mode may be selected and characteristics of the expected weather may be the basis for determining the pre-operation load distribution. These characteristics may be wind direction, wind speed, wind gusts, but they may also be characteristics of the sea such as swell height, swell direction, or other characteristics. These characteristics may be selected by an operator or retrieved automatically, e.g. from weather forecast data which can be accessed and interpreted by a computer.
The information about the intended use may be related to parameters of the installation location, such as parameters relating to the sea condition or the depth of the sea.
After receiving information about the intended use and/or future environmental conditions, the control system determines a pre-operation load distribution for at least one pinion group, in which pre-operation load distribution the load within this pinion group is unequally distributed, such that in the intended use and/or during the future environmental conditions the load within this pinion group is equally distributed.
It will be clear that the pre-operation load distribution thus depends on the intended operation, and possibly also on characteristics of this intended operation. This may be set by an operator or it may be determined automatically.
In embodiments, the jack-up vessel further comprises a user interface, and the control system is configured for receiving the information about an intended use and/or future environmental conditions from an operator.
So, in other words, by intentionally causing an un-equal loading distribution before an intended use and/or future environmental conditions, in the intended use and/or during the future environmental conditions the effect of an unequal load distribution — which would be present in absence of the invention — is (partially) ‘cancelled out’. The result is that during the intended operation, or at least during part of the intended operation, and/or during the future environmental conditions, the actual load distribution is close to an equal load distribution.
In embodiments, the jack-up vessel is configured for installing components of a wind turbine at a wind turbine installation site, wherein the jack-up vessel further comprises a crane configured for hoisting said components; wherein the pre-operation load distribution is such that during hoisting the loads within a pinion group are equally distributed. At a wind turbine installation site, the crane of the jack-up vessel is operated for hoisting one or more components of a wind turbine. These components may initially be positioned on or in the jack- up vessel. Alternatively, these components may initially be positioned on or in a separate vessel. In both cases, the crane is operated for hoisting these components between their initial position and a second position, generally the installation site. During operation of the crane, the loads transferred to the jack-up legs through the jacking assemblies varies. For example, when the crane hoists a wind turbine component from a separate vessel, at least the load of the weight of this component is transferred to one or more jack-up legs, increasing one or more transferred loads. During the hoisting of a wind turbine component from an initial position on or in the jack-up vessel, the loads on one or more legs may increase, while the loads on other one or more legs may decrease.
During a hoisting operation the loads transferred from a jacking assembly to a leg chord may not be evenly distributed between two or more pinions in a pinion group of a jacking assembly. For example, the load on the bottom-most pinion in a pinion group may be higher than the load on the top-most pinion this pinion group. It is desirable that the load on a pinion in a pinion group does not exceed a maximum allowable load corresponding to that pinion.
In embodiments, the pre-operation load distribution is calculated on the basis of a hoisting load of the crane. When the jack-up vessel is used to hoist a load, characteristics of this load may be the basis for determining the pre-operation load distribution. This may be set before the hoisting operation is commenced, for example based on initial location, intended location and total weight of the load to be hoisted. Alternatively or in addition, information obtained during the hoisting operation may be used to (re)determine the pre-operation load distribution.
For example, when first hoisting a first wind turbine component, and subsequently hoisting a second wind turbine component, wherein the second wind turbine component has a higher weight than the first wind turbine component, the pre-operation load distribution in a non- hoisting configuration may be different. Additionally, one or more leg chords may have different pre-operation load distributions associated with it. For example, if it is foreseen that during the operation of the jack-up vessel one leg will transfer higher loads than one or more other legs, it may be desired that the load distribution in the pre-hoisting configuration differs for different legs, such that the load distribution achieved at a point in time during hoisting is close to an equal distribution for one or more jack-up legs.
Avoiding exceeding the maximum allowable load may also or in addition be achieved by limiting the hoisting operation such that the highest load on a pinion in a pinion group is below the maximum allowable load for that pinion. When all pinions in a pinion group have a similar maximum allowable load, this means that other pinions in this pinion group are loaded below their maximum allowable load, which may not be considered efficient. Alternatively, a pinion group may comprise pinions with different maximum allowable loads, such that all pinions in a pinion group are loaded closer to their maximum allowable loads during the intended hoisting operation. This means that different pinions are required, which impacts maintainability and the number of spare parts to be retained.
It may be that the pre-operation load distribution in a pinion group is such that the load transferred by the uppermost pinion is a highest load, each subsequent lower pinion having a lower load than pinions above this subsequent lower pinion, the lowermost pinion having a lowest load. In this way, in the intended use, the uppermost pinion in a pinion group transfers a higher part of the load than the bottom-most pinion in this pinion group, and the amount per pinion may decrease from the uppermost pinion to the bottom-most pinion. For example, for a jacking assembly comprising five pinions in a pinion group, such a pre-operation load distribution may be that the relative amount of load transferred by the uppermost, second uppermost, middle, second-to-lowest, and lowest pinion, respectively, is 30%, 25%, 20%, 15%, and 10%.
The control system may compute a computed load distribution. Such a computed load distribution may for example be that the loads transferred in three pinions in a pinion group consisting of three pinions is 200 megatonnes (mt), 300 mt and 500 mt. Alternatively, such a computed load distribution may be that these pinions transfer 20%, 30% and 50%,
respectively, of the total load in this pinion group. This may be achieved by sensing the load transferred in each pinion in a pinion group, or by measuring the loads in all but one pinion and computing the load in the remaining pinion.
The control signals based on the difference may be emitted based on an acceptable margin.
For example, when the difference is zero, the control signal may be a zero value, indicating that no change is required. If the difference is nonzero, for example 0.5 mt, 1 mt, 20 mt or 100 mt, or 0.1% , 0.5%, 1%, 2%, 5% or 10%, the emitted control signal may reflect that change is required, and/or how much change is required. Alternatively, in the case of a nonzero acceptable margin, when a measure of the difference is smaller than this accepted margin the control system may emit a zero value for the control signal. This may be the case, for example, if the error in a pinion is 0.5% and the accepted margin if 1%; or when the error in a pinion is 10 mt and the accepted margin is 11 mt. The measure of the difference corresponding to the accepted margin may also be a combined measure, for instance that the sum of error values is lower than 100 mt or that the sum of the squared error values is below a number or that the average error value is less than 1%. Combinations of such measures may also be used.
The invention further relates to a method for operating a jack-up vessel, preferably a jack-up vessel according to one or more of the preceding claims, comprising the steps of: - lowering jack-up legs for engagement with the seabed and raising a buoyant hull to a distance above water level; - receiving information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operation load distribution for a pinion group, in which pre-operation load distribution the loads within this pinion group are unequally distributed, such that in the intended use and/or during the future environmental conditions the loads within this pinion group are equally distributed, - sensing the load distribution associated with a pinion group, and emitting sensor signals indicative of the sensed load distribution; - a control system receiving the sensor signals indicative of the sensed load distribution, and determining/computing a difference between the pre-operation load distribution and the sensed load distribution; - the control system emitting, in response to the difference, control signals to actuators such that the sensed load distribution of the pinion group corresponds to the pre- operation load distribution.
The invention further relates to a method for operating a jack-up vessel for use such as:
- installing components of a wind turbine at a wind turbine installation site including hoisting said components, - pre-drive operations, - pre-load operations; the jack-up vessel comprising: - a buoyant hull, - a plurality of jack-up legs, each jack-up leg comprising one or more leg chords having racks; - a plurality of jacking assemblies, each jacking assembly being associated with a leg chord, each jacking assembly being configured to relatively move the associated leg chord the buoyant hull vertically; wherein each jacking assembly comprises: o a pinion group, comprising a plurality of pinions arranged vertically above each other, each pinion engaging a rack and being configured for transferring load between the hull and the leg chord, resulting in a load distribution over the pinions within a pinion group; o actuators for actuating a pinion; o asensor system; wherein the jack-up vessel further comprises a control system configured for receiving sensor signals from the sensor system and emitting control signals for actuating the actuators; the method comprising the steps of: - receiving information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operation load distribution for a pinion group, in which pre-operation load distribution the loads within this pinion group are unequally distributed, such that in the intended use and/or during the future environmental conditions the loads within this pinion group are equally distributed; - sensing the load distribution associated with pinion group(s), and emitting sensor signals indicative of the sensed load distribution; - the control system receiving the sensor signals indicative of the sensed load distribution, and determining/computing a difference between the pre-operation load distribution and the sensed load distribution; - the control system emitting, in response to the difference, control signals to actuators such that the sensed load distribution of the pinion group corresponds to the pre- operation load distribution.
In embodiments, the step of receiving information about an intended use and/or future environmental conditions comprises an operator interacting with a user interface. For example, the user interface may allow an operator to input future wind speed and wind direction, to select a pre-load operation, to enter sea depth or sea bottom characteristics, or to select a pre-programmed operation.
In embodiments, the information about future environmental conditions is received using telecommunication means. For instance, weather predictions may be supplied to the control system via a mobile network, a satellite downlink, or a wired connection.
In embodiments, the jack-up vessel is configured for installing components of a wind turbine at a wind turbine installation site, wherein the jack-up vessel further comprises a crane configured for hoisting the components of a wind turbine; wherein the pre-operation load distribution is such that during hoisting the loads within a pinion group are equally distributed.
The invention further relates to a control system for a jack-up vessel, the jack-up vessel being intended for offshore operations, wherein the control system is configured for - receiving information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operation load distribution for a pinion group, in which pre-operation load distribution loads within this pinion group are unequally distributed, such that in the intended use and/or during the future environmental conditions the loads within this pinion group are equally distributed; - receiving a sensed load distribution associated with a pinion group, and determining/computing a difference between the pre-operation load distribution and the sensed load distribution; - emitting, in response to the difference, control signals to actuators such that the sensed load distribution of the pinion group corresponds to the pre-operation load distribution.
In embodiments, the control system further comprises a user interface to receive information about an intended use and/or future environmental conditions, e.g. from an operator.
In embodiments, the information about future environmental conditions is received using telecommunication means.
In embodiments, the pre-operation load distribution is calculated on the basis of a hoisting load of a crane.
Details of the invention described above in relation to the device also relate to the method / control device of the invention.
The invention will be further elucidated in relation to the drawings, in which:
Fig. 1is a side view of a jack-up vessel;
Fig. 2a is a side view of a jack-up vessel in an operational position;
Fig. 2b is a side view of a jack-up vessel in an operational position during a hoisting operation;
Fig. 3a is a perspective view of a jack-up leg showing jacking assemblies;
Fig. 3b is a perspective view showing a jacking assembly;
Fig. 4 is a schematic representation of a sensor system and control system;
Fig. 5a is an illustration of load distribution with ‘Christmas Tree Behaviour’;
Fig. 5b is an illustration of a pre-operation load distribution;
Fig. 6a shows a side view of a gearbox for a pinion which is mounted in a resilient way by using resilient parts;
Fig. 6b shows a cross section of Fig. 6a, taken along the line VIb-VIb in Fig. 6a;
Fig. 6c shows a side view of the gearbox of Fig. 8a,.
Although the drawings illustrate a jack-up vessel performing an operation of installing components of a wind turbine at a wind turbine installation site, this does not mean that the invention is limited to this operation. The invention may also be applied to jack-up vessels used far other operations, for example a jack-up vessel drilling for natural resources such as oil. In practice, most jack-up vessels perform a pre-loading step and may be required to withstand environmental conditions such as storms.
In fig. 1 a jack-up vessel 1 for installing one or more components of a wind turbine at a wind turbine installation site is shown. The jack-up vessel is not in an operational position, but in a condition where it can travel to or from a wind turbine installation site. The jack-up vessel 1 includes a buoyant hull 5 and a crane 14. In an operational position of crane 14, not shown in fig. 1, crane 14 is configured for hoisting one or more components 2, 3a, 3b, 4a, 4b of a wind turbine.
In this embodiment, wind turbine components 2, 3a, 3b, 4a and 4b are positioned on the buoyant hull 5 for transport to a wind turbine installation site. In other embodiments, some or all wind turbine components may be transported to the wind turbine installation site by other vessels.
The crane 14 is shown in a transport position. In embodiments, the vessel may include more than one crane, such as two, in which case both cranes are e.g. mounted on the same side of the buoyant hull 5.
Jack-up vessel 1 includes a plurality of jack-up legs 6, 8. In this embodiment, jack-up vessel 1 includes four jack-up legs and four jacking assemblies. Jack-up legs 6 and 8 are shown; not shown are two other legs which are positioned, in this side view, behind legs 6 and 8. In other embodiments, the number of legs may be different, e.g. six. The legs may also be positioned at other locations than shown in fig. 1. For example, one or more legs may be positioned in the middle of buoyant hull 5. Two legs may be positioned at one end of buoyant hull 5 and the other legs at the opposite end.
Each jack-up leg comprises one or more leg chords. In fig. 1, each jack-up leg comprises three leg chords. Jack-up leg 6 includes leg chords 20, 21 and a third leg chord which is not shown in this side view. Jack-up leg 6 is shown in detail in fig. 3a.
Jack-up vessel 1 comprises a plurality of jacking assemblies 10, 11, 12, 13, each jacking assembly being associated with a leg chord. In the embodiment shown in fig. 1, jacking assembly 10 is associated with leg chord 20, and jacking assembly 11 is associated with leg chord 21. Jacking assemblies 12 and 13 are associated with two chords of jack-up leg 8.
Jacking assemblies associated with the third chords of jack-up legs 6 and 8 is not shown in this side view.
In this embodiment, jacking assemblies 10 and 11 are positioned at the same vertical position relative to buoyant hull 5. In other embodiments, jacking assemblies may be positioned at different vertical positions.
Jacking assemblies 10, 11 are configured to move the corresponding jack-up leg 6 vertically relative to the buoyant hull. Jacking assemblies 12, 13 are configured to move the corresponding jack-up leg 8 vertically relative to the buoyant hull.
In fig. 2a, jack-up vessel 1 is in an operational configuration of the jack-up vessel. This operational configuration is achieved by lowering jack-up legs 6, 8 for engagement with the seabed 16 and raising buoyant hull 5 to a distance above water level 15.
In this figure, legs 6 and 8 extend relative above and below buoyant hull 5. Crane 14 is in an operational configuration, such that a hoisting operation can be performed. Crane 14 may hoist one or more components to and from a wind turbine installation site. In this figure, no wind turbine component is being hoisted. This may be the case when jack-up vessel 1 has not yet started operation at the current site; alternatively, this may be the case when jack-up vessel 1 has finished hoisting of a wind turbine component, such as wind turbine component 4a. In this embodiment, wind turbine components 2 and 3b are positioned on buoyant hull 5.
In other embodiments some or all wind turbine components may be positioned on other vessels. Wind turbine component 4a may also have been installed by a separate vessel, which may be a jack-up vessel or a different type of vessel, which is suitable for hoisting wind turbine component 4a.
In fig. 2b, jack-up vessel 1 is in the operational configuration and hoists wind turbine component 3b using crane 14, for example to an intended position 3b’ on wind turbine component 4a. This may be at the same wind turbine installation site as in fig. 2. Alternatively, this may be at a different wind turbine installation site. Wind turbine component 3b may have been hoisted from a position on buoyant hull 5, or from a different position, for example a position on a separate vessel.
Alternatively, the intended position of wind turbine component 3b may be a position on buoyant hull 5, or on a separate vessel. A wind turbine component 3b may have already been positioned on wind turbine component 4a, such as when wind turbine component 3b was incorrectly placed on wind turbine component 4a or when jack-up vessel 1 is used in a situation where for instance maintenance or decommissioning of a wind turbine requires hoisting wind a wind turbine component such as wind turbine component 3b.
Infig. 3a, leg 6 is shown in more detail. In this embodiment, leg 6 consists of three chords 20, 21 and 22, each chord having two racks. Rack 23 of chord 20 is visible, and rack 26 of chord 22 is visible. Both racks 24 and 25 arranged on chord 21 are visible. In this embodiment, chords 20, 21 and 22 are interconnected via a truss structure.
Also shown in fig. 3a are: jacking assembly 27, corresponding to leg chord 20, shown engaging with rack 23 and an opposed rack of corresponding leg chord 20; jacking assembly 28, corresponding to leg chord 21, shown engaging with racks 24 and 25 of corresponding leg chord 21; and jacking assembly 29, corresponding to leg chord 22, shown engaging with rack 26 and an opposed rack of corresponding leg chord 22.
In embodiments, these jacking assemblies are arranged on buoyant hull 5, but for illustrative purposes, hull 5 is omitted in fig. 4.
In this embodiment, jacking assemblies 27, 28 and 29 are configured in the same way, but in other embodiments, different jacking assemblies may be used for different chords, for different legs, or for both.
In fig. 3b, jacking assembly 28 is shown in more detail. Each jacking assembly comprises at least one pinion group. The number of pinion groups is generally equal to the number of racks. In this embodiment, jacking assembly 28 comprises two pinion groups, 34 and 35.
Each pinion group comprises a plurality of, in this figure five, pinions 40 arranged vertically above each other.
Each pinion 40 engages a rack 24, 25 of its associated leg chord 21 and is configured for transferring a part of the load of the buoyant hull 5 to the leg chord 21, resulting in each pinion 40 having a transferred load associated with the pinion.
In the shown embodiment, each pinion 40 is formed identical, but in other embodiments, different pinions may be comprised by jacking assemblies. In embodiments, pinions within a pinion group may be the same; alternatively, different pinions may be used within a pinion group, or for different pinion groups, or for different jacking assemblies, or for a combination thereof.
Jacking assembly 28 further comprises a plurality of actuators 30, each actuator configured for actuating a respective pinion 40. An actuator may actuate just one pinion, but it is also possible that an actuator actuates a plurality of pinions, e.g. 2 pinions at the same vertical position, or all pinions in one pinion group. In the shown embodiment, jacking assemblies also comprise a plurality of gearboxes 31, brakes 32 and parallel parts 33.
Actuator 30 may be a hydraulic motor or an electric motor. In the embodiment shown, actuator 30 is an electric motor. In the case of an electric motor, actuation of a pinion 40 may be done directly coupled to actuator 30, or there may be a gearbox to provide the transmission from actuator 30 to pinion 40, such as a planetary gearbox 31. A parallel part 33 may also be included in the transmission.
Braking may be achieved by actuating actuator 30, or by actuating brake 32. Alternatively, brake 32 may be a failsafe brake, to be used in cases where using actuator 30 for braking does not give a sufficient result, such as when actuator 30 fails. Brake 32 may be embodied as a brake which brakes in a neutral position and is kept in a non-braking configuration by means of electric power, such that in case of a power failure, rendering actuator 30 inoperable, brake 32 is activated. In embodiments, brake 32 acts on the same shaft as the shaft on which actuator 30 acts.
In embodiments, gearboxes 31 are of the same type to keep the amount of spares minimal. In embodiments, this also applies for actuators 30.
In Fig. 4, a sensor system 150 and a control system 152 are schematically represented.
Pinions 140a and 140b engage with rack 125 of associated leg chord 121.
Sensor system 150 is configured for sensing the load distribution associated with a pinion group, and emitting sensor signals indicative of the sensed load distribution.
In this figure, one sensor system is associated with a pinion group. It is conceivable that a jack-up vessel comprises one sensor system for the entire jack-up vessel. It is also conceivable that each pinion, each pinion group, each rack, each chord, each jacking assembly or each leg may have a sensor.
Sensor signals may be emitted to the control system 152 by a wire from a sensor to the control system, or there may be an intermediate component which combines one or more sensor signals and emits a signal to the control system. Such an intermediate component may also perform calculations.
Here, sensor system 150 comprises sensor 151a and 151b, sensing parameters representative of transferred loads associated with pinion 140a and pinion 140b, respectively.
Pinion loads associated with pinions may be measured in many different ways, e.g. by load cells on the pinions or the pinion shaft. In a preferable embodiment they may be measured by integrated sensors at the pre-stages of the gearboxes 131a and 131b. This is a more practical location than the actual pinion or pinion shaft, because the actual pinion is in a more harsh environment and more difficult to reach.
The jack-up vessel comprises a control system 152. Control system 152 receives the sensor signals indicative of the sensed load distribution from sensor system 150.
Control system 152 is configured for receiving information about an intended use and/or future environmental conditions. In embodiments, an operator may use user interface 154 to provide the control system with characteristics of the pre-load operation, the load to be hoisted, weather conditions, etc. Alternatively, this information may be received before the vessel is deployed and stored in the control system. Based on the received information, the control system determines a pre-operation load distribution, e.g. automatically. For example, in a hoisting operation, a characteristic of the load to be hoisted may be measured by a hoisting system in communication with the control system.
If during a pre-loading step the actual transferred loads are measured and a difference between one or more of these loads is determined to be higher than a desired amount, the pre-operation load distribution may be reactively determined such that the load distribution is more even across the pinions in a pinion group. In other words, after receiving information about the intended use and determining a pre-operation load distribution, feedback during the operation may be received after which the control system may determine a second pre- operation load distribution. This may be determined at any point before or during operation and subsequently stored in the control system. At any point after storing this pre-operation load distribution it may be replaced by a different pre-operation load distribution. It is also possible that the control system is configured for storing a plurality of pre-operation load distributions, e.g. each time that a new pre-operation load distribution is determined, the previous pre-operation load distribution is added to a memory of possible load distributions, such that a previous pre-operation load distribution may be selected at any later point, for instance by the operator or automatically based on a characteristic that the control system detects.
In embodiments, control system 152 receives information about future environmental conditions using telecommunication means 153.
User interface 154 may provide the operator with information on the load distribution, for example the current load distribution, or information about integrity of the sensor system, i.e. whether the system detects that sensors in sensor system 150 are working properly or malfunctioning.
Control system 152 determines a difference between the pre-operation load distribution and the actual transferred load. It emits, in response to the difference, control signals to one or more actuators 130a, 130b, such that the pre-operation load distribution corresponds to the actual transferred loads. In embodiments, the one or more actuators 130a, 130b actuate their associated pinion 140a, 140b by using the respective gearbox 131a, 131b. It may suffice for one pinion to be actuated: for example, if the load on pinion 140a is higher than desired, and the load on pinion 140b is higher than desired, after actuating either actuator 130a or actuator 30b, the actual transferred loads may correspond to the pre-operation load distribution.
Alternatively, it may be required or desired to actuate more than one actuator, for example all actuators in a pinion group. It is also possible to actuate a plurality of pinions at a certain vertical location, i.e. first actuating upper pinions, then middle pinions, etc.
Figs. 5a and 5b illustrate the effect of a load distribution for a leg chord with two racks and two pinion groups, each pinion group comprising three pinions. Both figures show next to the pinions loads associated with the pinions as two bars. Each highest bar represents the load associated with the pinion before load is increased, each lowest bar represents the load associated with the pinion after load is increased. The behaviour illustrated in fig. 5a may be called ‘Christmas Tree Behaviour’. If the load on the jack-up legs increases while brakes are applied (e.g. during a pre-loading step, during storm conditions or during a hoisting operation of crane 14), the lower pinions might take more load than the upper pinion.
This can be counteracted by adjusting the load distribution before increasing the load on a leg to a pattern that gives an even distribution when the high leg load is applied. This can be achieved by adjusting the settings of a (re-)torque system. The resulting load distribution is shown in fig. 5b. The pre-operation load distribution before increasing load may be called a ‘Reverse Christmas Tree’. When load is applied, the loads associated with the pinions are equal, illustrated by the lower bars in fig. 5b.
The lower pinions in a pinion group will generally have the largest increases in load from the pre-operation load distribution to the loads in the intended use and/or during the future environmental conditions. In certain pre-operation load distributions, these pinions transfer a low load or approximately no load and have a large increase in load in the intended use and/or during the future environmental conditions.
It may however be desirable to achieve an even larger increase in load. In this case, in the pre-operation load distribution the loads of these pinions can be thought of as having a desired load corresponding to a value below zero, a ‘negative pre-operation load’ so to say. In other words, the slanted dashed line in Fig. 5b, when extrapolated to lower pinions, would cross the vertical axis. This can be achieved by positioning these pinions with respect to the rack so that they do not engage the rack in the pre-operation load distribution. In other words, a certain backlash or play is introduced, i.e. a clearance that the rack and/or the pinion can move before they engage each other. In this way, below a certain load on the rack these pinions transfer essentially no load, and above a certain load on the rack, these pinions will engage the rack and transfer part of the load on this rack.
Itis also conceivable that a part, e.g. a respective pinion, its respective gearbox, a connection between the pinion and the gearbox, and/or a mounting part in the respective jacking assembly is provided as a resilient part. This resilience refers to the ability of this part to absorb energy when it is deformed elastically, and release this energy upon unloading. With a resilient part, when the load on the respective pinion is increased, a part of this load is absorbed by elastic deformation of the resilient part. This allows the total load that can be transferred by this pinion to be higher. Within a pinion group, one more pinions, such as the lowest pinion, may be provided as a resilient part. When more than one pinion are provided as a resilient part, it is conceivable that a lower pinion has a resilient part which can take more load than a higher pinion.
When a resilient part is provided for a pinion in a pinion group, the pre-operation load distribution is determined such that the combined effect of the pre-operation load distribution and the resilient part leads to the loads within this pinion group being equally distributed in the intended use and/or during the future environmental conditions. For example, the lowest pinion in a pinion group could be provided with a resilient part, such as a flexible mounting of the gearbox. The resilient part can absorb part of an increase in load. The pre-operation load for the lowest pinion would then be the load in the intended use and/or during the future environmental conditions, minus the part of the increase in load which is not absorbed by the resilient part.
In Fig. 6a, an actuator (not shown) actuates a pinion (not shown) through a gearbox 31, brake 32 and parallel part 33. Gearbox 31 is mounted to a housing 60. Also shown are axial mounting plates 61. In Fig. 6b a cross section of Fig. 6a is shown. Between the gearbox 31 and housing 80 a bearing 62 is provided, here comprising a bronze bushing. The bearing allows rotation of the gearbox 31 with respect to the housing 60. In Fig. 6c, axial mounting plates 61 have been omitted for clarity. Now multiple (8) flexible parts 63 of a flexible or resilient material are visible, e.g. rubber or a polymer, e.g. a fibre-reinforced polymer. These flexible parts are provided between the gearbox 31 and the housing 60. The presence of these flexible parts 83 provides resilience to and limits any rotation of the gearbox 31 with respect to the housing 60.

Claims (15)

CONCLUSIESCONCLUSIONS 1. Jack-up vaartuig voor gebruik zoals het installeren van componenten van een windturbine op een windturbine-installatieplaats inclusief het hijsen van genoemde componenten, waarbij het jack-up vaartuig omvat: - een drijvende romp; - meerdere opvijzelpoten (EN: jack-up legs), waarbij elke opvijzelpoot een of meer poot- koorden met tandheugels heeft; - meerdere opvijzelconstructies (EN: jacking assemblies), waarbij elke opvijzelconstructie hoort bij een pootkoorde, en elke opvijzelconstructie geconfigureerd is om de bijbehorende pootkoorde verticaal te bewegen ten opzichte van de drijvende romp; waarbij elke opvijzelconstructie omvat: o een rondselgroep, omvattende een aantal verticaal boven elkaar geplaatste rondsels, waarbij elk rondsel in een tandheugel grijpt en geconfigureerd is voor het overbrengen van belasting tussen de romp en de pootkoorde, resulterend in een pre-operationele belastingverdeling over de rondsels binnen een rondselgroep; o actuatoren voor het in werking stellen van een rondsel; o een sensorsysteem dat geconfigureerd is om de pre-operationele belastingverdeling over een rondselgroep waar te nemen, en sensorsignalen uit te zenden indicatief voor de waargenomen pre-operationele belastingverdeling; waarbij het jack-up vaartuig verder een besturingssysteem heeft dat geconfigureerd is voor: - het ontvangen van informatie over een beoogd gebruik en/of toekomstige omgevingsomstandigheden; - het bepalen, op basis van deze informatie, van een pre-operationele belastingverdeling van een rondselgroep, waarbij de pre-operationele belastingverdeling binnen deze rondselgroep ongelijk verdeeld is, zodat bij het beoogde gebruik en/of tijdens de toekomstige omgevingsomstandigheden de belastingen binnen deze rondselgroep gelijk verdeeld zijn; - ontvangen van de sensorsignalen indicatief voor de waargenomen belastingverdeling, en bepaling/berekening van een verschil tussen de pre-operationele belastingverdeling en de waargenomen belastingverdeling; - in antwoord op het verschil stuursignalen uitzenden naar actuatoren, zodat de waargenomen belastingverdeling van de ten minste ene rondselgroep overeenstemt met de pre-operationele belastingverdeling.A jack-up vessel for use such as installing components of a wind turbine at a wind turbine installation site including lifting said components, the jack-up vessel comprising: - a floating hull; - several jack-up legs, where each jack-up leg has one or more rack-and-pinion leg cords; multiple jacking assemblies, where each jacking assembly is associated with a leg chord, and each jacking assembly is configured to move its associated leg chord vertically relative to the floating hull; each jacking structure comprising: o a pinion group comprising a number of pinions arranged vertically one above the other, each pinion meshing with a gear rack and configured to transfer load between the hull and the leg chord, resulting in a pre-operational load distribution among the pinions within a pinion group; o actuators for operating a pinion; o a sensor system configured to sense the pre-operational load distribution across a pinion group, and transmit sensor signals indicative of the sensed pre-operational load distribution; the jack-up vessel further having a control system configured to: receive information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operational load distribution of a pinion group, whereby the pre-operational load distribution within this pinion group is unevenly distributed, so that under the intended use and/or during future environmental conditions, the loads within this pinion group be evenly distributed; - receiving the sensor signals indicative of the observed load distribution, and determination/calculation of a difference between the pre-operational load distribution and the observed load distribution; - send control signals to actuators in response to the difference, so that the observed load distribution of the at least one pinion group corresponds to the pre-operational load distribution. 2. Jack-up vaartuig volgens conclusie 1, waarbij het besturingssysteem is geconfigureerd om de pre-operationele belastingverdeling voor elke rondselgroep afzonderlijk te bepalen. A jack-up vessel according to claim 1, wherein the control system is configured to determine the pre-operational load distribution for each pinion group separately. 3 Jack-up vaartuig volgens conclusie 1, waarbij het besturingssysteem is geconfigureerd om de pre-operationele belastingverdeling te bepalen voor de rondselgroepen van een opvijzelpoot.A jack-up vessel according to claim 1, wherein the control system is configured to determine the pre-operational load distribution for the pinion groups of a jack-up leg. 4. Jack-up vaartuig volgens een van de voorgaande conclusies, waarbij het jack-up vaartuig is geconfigureerd voor het installeren van componenten van een windturbine op een windturbine-installatielocatie, waarbij het jack-up vaartuig verder een kraan heeft die is geconfigureerd voor het hijsen van genoemde componenten; waarbij de pre-operationele belastingverdeling zodanig is dat tijdens het hijsen de belastingen binnen een rondselgroep gelijkmatig zijn verdeeld.A jack-up vessel according to any one of the preceding claims, wherein the jack-up vessel is configured for installing components of a wind turbine at a wind turbine installation site, the jack-up vessel further having a crane configured for lifting said components; where the pre-operational load distribution is such that during hoisting the loads within a pinion group are evenly distributed. 5. Jack-up vaartuig volgens conclusie 5, waarbij de pre-operationele belastingverdeling wordt berekend op basis van een hijsbelasting van de kraan.A jack-up vessel according to claim 5, wherein the pre-operational load distribution is calculated based on a lifting load of the crane. 6. Jack-up vaartuig volgens een van de voorgaande conclusies, waarbij het besturingssysteem verder een gebruikersinterface omvat om informatie over een beoogd gebruik en/of toekomstige omgevingsomstandigheden van een operator te ontvangen.A jack-up vessel according to any one of the preceding claims, wherein the control system further comprises a user interface to receive information about intended use and/or future environmental conditions from an operator. 7. Werkwijze voor het bedienen van een jack-up vaartuig, bij voorkeur een jack-up vaartuig volgens een of meer van de voorgaande conclusies, omvattende de stappen van: - het neerlaten van de opvijzelpoten om aan te grijpen op de zeebodem en een drijvende romp op te heffen tot een afstand boven de waterspiegel; - het ontvangen van informatie over een beoogd gebruik en/of toekomstige omgevingsomstandigheden; - het bepalen, op basis van deze informatie, van een pre-operationele belastingverdeling voor een rondselgroep, waarbij de pre-operationele belastingverdeling binnen deze rondselgroep ongelijk verdeeld is, zodat bij het beoogde gebruik en/of tijdens de toekomstige omgevingsomstandigheden de belastingen binnen deze rondselgroep gelijk verdeeld zijn; - het detecteren van de belastingverdeling behorend bij een rondselgroep, en het afgeven van sensorsignalen die de waargenomen belastingverdeling aangeven; - het door een besturingssysteem ontvangen van sensorsignalen indicatief voor de waargenomen belastingverdeling, en een verschil bepalen/berekenen tussen de pre- operationele belastingverdeling en de waargenomen belastingverdeling;7. Method for operating a jack-up vessel, preferably a jack-up vessel according to one or more of the preceding claims, comprising the steps of: - lowering the jacking legs to engage the seabed and a floating raise hull to a distance above the waterline; - receiving information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operational load distribution for a pinion group, whereby the pre-operational load distribution within this pinion group is unevenly distributed, so that under the intended use and/or during future environmental conditions, the loads within this pinion group be evenly distributed; - detecting the load distribution associated with a pinion group, and outputting sensor signals indicating the detected load distribution; - receiving sensor signals indicative of the observed load distribution by a control system, and determining/computing a difference between the pre-operational load distribution and the observed load distribution; - het door het besturingssysteem uitzenden, in antwoord op het verschil, van stuursignalen naar actuatoren zodat de gemeten belastingverdeling van de rondselgroep overeenstemt met de pre-operationele belastingverdeling.- the control system transmitting, in response to the difference, control signals to actuators so that the measured load distribution of the pinion group corresponds to the pre-operational load distribution. 8. Werkwijze voor het bedienen van een jack-up vaartuig voor gebruik zoals: - het installeren van componenten van een windturbine op een windturbine- installatieplaats, inclusief het hijsen van genoemde componenten, - pre-drive operaties, - voorbelastingsoperaties; waarbij het jack-up vaartuig omvat: - een drijvende romp; - een veelvoud van opvijzelpoten, waarbij elke opvijzelpoot een of meer pootkoorden met tandheugels heeft; - meerdere opvijzelconstructies, waarbij elke opvijzelconstructie hoort bij een beenkoorde, en elke opvijzelconstructie geconfigureerd is om de bijbehorende beenkoorde relatief ten opzichte van de drijvende romp verticaal te bewegen; waarbij elke opvijzelconstructie omvat: o een rondselgroep, omvattende meerdere verticaal boven elkaar geplaatste rondsels, waarbij elk rondsel in een tandheugel grijpt en geconfigureerd is voor het overbrengen van belasting tussen de romp en de pootkoorde, resulterend in een belastingverdeling over de rondsels binnen een rondselgroep; o actuatoren voor de aandrijving van een rondsel; o een sensorsysteem; waarbij het jack-up vaartuig verder een besturingssysteem omvat dat geconfigureerd is om sensorsignalen van het sensorsysteem te ontvangen en stuursignalen uit te zenden voor het in werking stellen van de actuatoren; waarbij de werkwijze de stappen omvat van: - het ontvangen van informatie over een beoogd gebruik en/of toekomstige omgevingsomstandigheden; - het bepalen, op basis van deze informatie, van een pre-operationele belastingverdeling voor een rondselgroep, in welke pre-operationele belastingverdeling de belastingen binnen deze rondselgroep ongelijk verdeeld zijn, zodat bij het beoogde gebruik en/of tijdens de toekomstige omgevingsomstandigheden de belastingen binnen deze rondselgroep gelijk verdeeld zijn; - het detecteren van de belastingverdeling binnen de rondselgroep{en), en het uitzenden van sensorsignalen die de waargenomen belastingverdeling aangeven;A method of operating a jack-up vessel for use such as: - installing components of a wind turbine at a wind turbine installation site, including lifting said components, - pre-drive operations, - pre-loading operations; wherein the jack-up vessel comprises: - a floating hull; - a plurality of jacking legs, each jacking leg having one or more rack leg cords; - a plurality of jacking structures, each jacking structure associated with a leg chord, and each jacking structure configured to vertically move the associated leg chord relative to the buoyant hull; each jacking structure comprising: o a pinion group comprising a plurality of pinions arranged vertically one above the other, each pinion meshing with a gear rack and configured to transfer load between the hull and the leg chord, resulting in a load distribution among the pinions within a pinion group; o actuators for driving a pinion; o a sensor system; the jack-up vessel further comprising a control system configured to receive sensor signals from the sensor system and transmit control signals for actuating the actuators; the method comprising the steps of: - receiving information about an intended use and/or future environmental conditions; - determining, based on this information, of a pre-operational load distribution for a pinion group, in which pre-operational load distribution the loads within this pinion group are unevenly distributed, so that under the intended use and/or during the future environmental conditions the loads will be within this pinion group are evenly distributed; - detecting the load distribution within the pinion group(s), and transmitting sensor signals indicating the detected load distribution; - het door het besturingssysteem ontvangen van de sensorsignalen die de gemeten belastingverdeling aangeven, en een verschil berekenen! bepalen tussen de pre- operationele belastingverdeling en de gemeten belastingverdeling; - het door het besturingssysteem uitzenden, in antwoord op het verschil, van stuursignalen naar actuatoren zodat de gemeten belastingverdeling van de rondselgroep overeenstemt met de pre-operationele belastingverdeling.- the control system receiving the sensor signals indicating the measured load distribution and calculating a difference! determine between the pre-operational load distribution and the measured load distribution; - the control system transmitting, in response to the difference, control signals to actuators so that the measured load distribution of the pinion group corresponds to the pre-operational load distribution. 9. Werkwijze volgens conclusie 7 of 8, waarbij de stap van het ontvangen van informatie over een beoogd gebruik en/of toekomstige omgevingsomstandigheden een interactie van een operator met een gebruikersinterface omvat.A method according to claim 7 or 8, wherein the step of receiving information about an intended use and/or future environmental conditions comprises an operator interaction with a user interface. 10. Werkwijze volgens een van de conclusies 7 - 9, waarbij de informatie over toekomstige omgevingsomstandigheden wordt ontvangen via telecommunicatiemiddelen.A method according to any one of claims 7 to 9, wherein the information about future environmental conditions is received via telecommunication means. 11. Werkwijze volgens een van de conclusies 7 - 10, waarbij het jack-up vaartuig is geconfigureerd voor het installeren van componenten van een windturbine op een windturbine-installatielocatie, waarbij het jack-up vaartuig verder een kraan omvat die is geconfigureerd voor het hijsen van de componenten van een windturbine; waarbij de pre- operationele belastingverdeling zodanig is dat tijdens het hijsen de belastingen binnen een rondselgroep gelijk zijn verdeeld.A method according to any one of claims 7 to 10, wherein the jack-up vessel is configured for installing components of a wind turbine at a wind turbine installation site, the jack-up vessel further comprising a crane configured for lifting of the components of a wind turbine; where the pre-operational load distribution is such that during hoisting the loads within a pinion group are equally distributed. 12. Besturingssysteem voor een jack-up vaartuig, waarbij het jack-up vaartuig bedoeld is voor offshore-operaties, waarbij het besturingssysteem geconfigureerd is voor - het ontvangen van informatie over een beoogd gebruik en/of toekomstige omgevingsomstandigheden; - het bepalen, op basis van deze informatie, van een pre-operationele belastingverdeling voor een rondselgroep, waarbij pre-operationele belastingverdelingen binnen deze rondselgroep ongelijk verdeeld zijn, zodat bij het beoogde gebruik en/of tijdens de toekomstige omgevingsomstandigheden de belastingen binnen deze rondselgroep gelijk verdeeld zijn; - ontvangst van een waargenomen belastingverdeling behorend bij een rondselgroep, en bepaling/berekening van een verschil tussen de pre-operationele belastingverdeling en de waargenomen belastingverdeling; - in antwoord op het verschil stuursignalen uitzenden naar actuatoren zodat de waargenomen belastingverdeling van de rondselgroep overeenkomt met de pre- operationele belastingverdeling.12. Control system for a jack-up vessel, where the jack-up vessel is intended for offshore operations, where the control system is configured to - receive information about an intended use and/or future environmental conditions; - determining, based on this information, a pre-operational load distribution for a pinion group, whereby pre-operational load distributions within this pinion group are unequally distributed, so that under the intended use and/or during future environmental conditions, the loads within this pinion group are equal be divided; - receipt of an observed load distribution associated with a pinion group, and determination/calculation of a difference between the pre-operational load distribution and the observed load distribution; - send control signals to actuators in response to the difference so that the observed load distribution of the pinion group matches the pre-operational load distribution. 13. Besturingssysteem volgens conclusie 12, waarbij het besturingssysteem verder een gebruikersinterface omvat om informatie te ontvangen over een beoogd gebruik en/of toekomstige omgevingsomstandigheden, bijvoorbeeld van een operator.An operating system according to claim 12, wherein the operating system further comprises a user interface to receive information about an intended use and/or future environmental conditions, for example from an operator. 14. Besturingssysteem volgens conclusie 12 of 13, waarbij de informatie over toekomstige omgevingsomstandigheden wordt ontvangen via telecommunicatiemiddelen.An operating system according to claim 12 or 13, wherein the information about future environmental conditions is received via telecommunication means. 15. Besturingssysteem volgens een van de conclusies 12 - 14, waarbij de pre- operationele belastingverdeling wordt berekend op basis van een hijsbelasting van een kraan.Control system according to any one of claims 12 - 14, wherein the pre-operational load distribution is calculated based on a crane lifting load.
NL2029776A 2021-11-16 2021-11-16 Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel. NL2029776B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
NL2029776A NL2029776B1 (en) 2021-11-16 2021-11-16 Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel.
PCT/EP2022/082123 WO2023088958A1 (en) 2021-11-16 2022-11-16 A jack-up vessel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NL2029776A NL2029776B1 (en) 2021-11-16 2021-11-16 Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel.

Publications (1)

Publication Number Publication Date
NL2029776B1 true NL2029776B1 (en) 2023-06-12

Family

ID=80685535

Family Applications (1)

Application Number Title Priority Date Filing Date
NL2029776A NL2029776B1 (en) 2021-11-16 2021-11-16 Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel.

Country Status (1)

Country Link
NL (1) NL2029776B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090090191A1 (en) * 2007-10-05 2009-04-09 Bernardino Lenders Methods and structures for monitoring offshore platform supports
US20190040598A1 (en) * 2017-08-02 2019-02-07 Rowan Companies, Inc. Multi-stage coming off location technology

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090090191A1 (en) * 2007-10-05 2009-04-09 Bernardino Lenders Methods and structures for monitoring offshore platform supports
US20190040598A1 (en) * 2017-08-02 2019-02-07 Rowan Companies, Inc. Multi-stage coming off location technology

Similar Documents

Publication Publication Date Title
DK2628854T3 (en) Cash System to a leg of a jack-up platform
JP7355807B2 (en) Device and method for lifting objects from the deck of a ship subject to motion
KR20180067566A (en) Hoisting system for installing wind turbines
US20110129334A1 (en) Wind turbine holding and lifting system and movable operating platform above water
KR102606868B1 (en) A wind turbine system
KR20130113482A (en) A heave compensating system
NL2029776B1 (en) Jack-up vessel, method for operating a jack-up vessel and control system for a jack-up vessel.
WO2023088958A1 (en) A jack-up vessel
AU2020300343B2 (en) A floating foundation for an offshore wind turbine, a system for extracting energy from wind, and a method of installing a wind turbine
NL2021708B1 (en) Method for stabilizing a jack-up platform unit
NL2015623B1 (en) Jack-up platform; Leg for a jack-up platform; method for installing a jack-up platform.
EP3879096A1 (en) Operations vessel for the maintenance, installation and/or disassembly of offshore structures
EP3693513A1 (en) Structure and method for decommissioning an offshore platform
WO2022015170A9 (en) Electrical retrofit skidding system
KR20240004955A (en) Systems and methods for rack structures for transport vessels configured for use with offshore self-elevating vessels
NL2028741B1 (en) upend crane and installation vessel
US20230287869A1 (en) Offshore wind turbine systems and processes for installing same
TWI843736B (en) Device and method for lifting an object from a deck of a vessel subject to movements
CN117755451A (en) Self-elevating self-navigation transportation hoisting integrated wind power installation platform and construction method
GB2108452A (en) Upthrust stabiliser for a craft
Gudmestad et al. Marine operations for installation and intervention of offshore wind turbines
KR20230133635A (en) Floating structure
GB2612616A (en) Improved jack up barge
Cholley et al. New Multipurpose Vessel Concept
Rodenburg Additional lifting days for single