LU502429B1 - A construction method for lifting steel structures in combustion and cleaning chambers of power plants - Google Patents

A construction method for lifting steel structures in combustion and cleaning chambers of power plants Download PDF

Info

Publication number
LU502429B1
LU502429B1 LU502429A LU502429A LU502429B1 LU 502429 B1 LU502429 B1 LU 502429B1 LU 502429 A LU502429 A LU 502429A LU 502429 A LU502429 A LU 502429A LU 502429 B1 LU502429 B1 LU 502429B1
Authority
LU
Luxembourg
Prior art keywords
zone
lifting
combustion
crane
construction
Prior art date
Application number
LU502429A
Other languages
German (de)
Inventor
Hancheng Wang
Jiaxiang Zhao
Yue Li
Yongpeng Huang
Haihui Xie
Lilan Deng
Xiao Yang
Xinqiang Shen
Zhi Zheng
Haiyong Jiang
Zhijie Lu
Wenzhao Liu
Shouxin Qi
Chenghui Jiang
Jing Tian
Yang Xiao
Weibin Qi
Bingheng Wen
Weiling Li
Li Ma
Shufan Zeng
Yuxin Zong
Zhitang Huang
Original Assignee
China Constr First Group Corp Ltd
China Construction First Group South China Corp Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Constr First Group Corp Ltd, China Construction First Group South China Corp Co Ltd filed Critical China Constr First Group Corp Ltd
Application granted granted Critical
Publication of LU502429B1 publication Critical patent/LU502429B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/285Plants therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B3/00General features in the manufacture of pig-iron
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/12Heat utilisation in combustion or incineration of waste

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Botany (AREA)
  • Manufacturing & Machinery (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Die vorliegende Erfindung offenbart ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken, das die folgenden Schritte umfasst: Schritt 1: Zoneneinteilung: Der Bereich des Verbrennungsraums westlich des Turmdrehkrans, der für das Heben von Ausrüstungen verwendet wird, wird als Zone 1 bezeichnet, der Bereich des Dekontaminationsraums nördlich des Verbrennungs-raums als Zone 2; der Bereich südlich des Turmdrehkrans wird als Zone 3 bezeichnet, der Bereich nördlich davon als Zone 4 und der Bereich des Turmdrehkrans als Zone 5; der Montageplatz für die Traversen wird an der West-, Nord- und Ostseite der Anlage errichtet; Schritt 2: Auswahl der Ausrüstung: Auswahl von Raupenkränen als Stahlhebegerät, Autokräne als Raupenkran Installation und Demontage, Stahlkonstruktion Montage Ausrüstung; Schritt 3: Bau: Verwenden Sie den Raupenkran, um zuerst die Hebekonstruktion von Zone 1 und Zone 2 durchzuführen; nachdem die Konstruktion von Zone 2 abgeschlossen ist, bewegen Sie den Raupenkran zu Zone 4 für die Hebekonstruktion; wenn die Stahlkonstruktion von Zone 1 und Zone 2 im Bau ist, führen Sie die Hebekonstruktion der Stahlkonstruktion von Zone 3 durch, wenn der Turmdrehkran frei ist; nachdem die Entfernung des Turmdrehkrans abgeschlossen ist, verwenden Sie den Fahrzeugkran, um die Hebekonstruktion der Stahlkonstruktion von Zone 5 durchzuführen. Die Anwendung hat die Vorteile einer kurzen Zykluszeit, geringer Baukosten und hoher Sicherheit.The present invention discloses a construction method for lifting steel structures in combustion and cleaning chambers of power plants, comprising the following steps: Step 1: Zoning: The area of the combustion chamber to the west of the tower crane used for lifting equipment is defined as Zone 1 designated, the area of the decontamination room north of the combustion room as Zone 2; the area south of the tower crane is designated as zone 3, the area to the north thereof as zone 4 and the area of the tower crane as zone 5; the assembly area for the trusses will be erected on the west, north and east side of the system; Step 2: Equipment selection: selection of crawler cranes as steel lifting equipment, truck-mounted cranes as crawler crane installation and disassembly, steel structure assembly equipment; Step 3: Construction: Use the crawler crane to do the lifting construction of zone 1 and zone 2 first; after zone 2 construction is completed, move the crawler crane to zone 4 for lifting construction; when the steel structure of zone 1 and zone 2 is under construction, carry out the lifting construction of the steel structure of zone 3 when the tower crane is free; after the tower crane removal is completed, use the mobile crane to carry out the lifting construction of the zone 5 steel structure. The application has the advantages of short cycle time, low construction cost and high security.

Description

Description LU502429 Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken Technischer Bereich Die vorliegende Erfindung bezieht sich auf das technische Gebiet des Stahlbaus, insbesondere auf ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. Technologie im Hintergrund Gegenwärtig ist Siedlungsabfall in China zu einem wichtigen Thema geworden, das die Entwicklung unserer Städte beeinflusst. Chinas Abfallproduktion ist riesig und wird jetzt hauptsächlich durch Müllverbrennung zur Energieerzeugung behandelt. Kessel ist eine Art von Energieumwandlung Ausrüstung. Die dem Kessel zugeführte Energie sind die chemische Energie in den Brennstoff, elektrische Energie. Der Kessel gibt Dampf, Hochtemperaturwasser oder organische Wärmeträger mit einer bestimmten Menge an thermischer Energie ab. Das im Kessel erzeugte Heißwasser oder der Dampf kann direkt für die industrielle Produktion und das Leben der Menschen genutzt werden, um die benötigte thermische Energie bereitzustellen, aber auch durch das Dampfkraftwerk in mechanische Energie umgewandelt werden, oder dann durch den Generator, um mechanische Energie ın elektrische Energie umzuwandeln. Die üblicherweise eingesetzten mechanischen Rostofen-Müllverbrennungskraftwerke bestehen hauptsächlich aus Abfall- verbrennungs- und Wärmerückgewinnungssystemen, Rauchgasreinigungssystemen, Hilfsprozessen und anderen Systemen, die alle im Wesentlichen in der Hauptanlage konzentriert sind.Description LU502429 A construction method for lifting steel structures in combustion and cleaning rooms of power plants Technical Field The present invention relates to the technical field of steel construction, more particularly to a construction method for lifting steel structures in combustion and cleaning rooms of power plants. Background Technology At present, municipal solid waste in China has become an important issue affecting the development of our cities. China's waste production is huge and is now mainly treated by incinerating waste to generate energy. Boiler is a kind of energy conversion equipment. The energy supplied to the boiler is the chemical energy in the fuel, electrical energy. The boiler emits steam, high-temperature water or organic heat carriers with a certain amount of thermal energy. The hot water or steam generated in the boiler can be directly used for industrial production and people's life to provide the required thermal energy, but also can be converted into mechanical energy through the steam power plant, or then through the generator to produce mechanical energy ın to convert electrical energy. The commonly used grate mechanical waste incineration power plants mainly consist of waste incineration and heat recovery systems, flue gas cleaning systems, auxiliary processes and other systems, all of which are essentially concentrated in the main plant.

11

Description LU502429 Die Hauptanlage ist meist eine Stahlkonstruktion Gebäude, die Stahlkonstruktion in den Prozess der Konstruktion, müssen die Stahlkonstruktion Heben Struktur mit dem Kran wird das Anheben der Stahlkonstruktion zu verwenden. Allerdings ist die aktuelle Stahlkonstruktion Bau und Verbrennung Ausrüstung Installation und Rauchgasreinigung Ausrüstung Installation Kessel in der Regel sukzessive Bau, Anlagen mit Turmdrehkräne für die Installation, die Stahlkonstruktion mit Raupenkränen für die Installation, aber für einige enge Zeitplan Anforderungen, die Verwendung von sukzessiven Bau der Art und Weise der Zyklus ist lang, und die Baukosten sind hoch, kann nicht den Anforderungen des Zeıtplans.Description LU502429 The main facility is mostly a steel structure building, the steel structure in the process of construction, need to use the steel structure lifting structure with the crane will be lifting the steel structure. However, the current steel structure construction and incineration equipment installation and flue gas cleaning equipment installation boiler is generally successive construction, equipment using tower cranes for installation, the steel structure using crawler cranes for installation, but for some tight schedule requirements, the use of successive construction type and way the cycle is long, and the construction cost is high, can not meet the schedule requirements.

Inhalt der Erfindung Die Erfindung stellt ein Konstruktionsverfahren von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken mit kurzer Taktzeit, geringen Baukosten und hoher Sicherheit bereit.SUMMARY OF THE INVENTION The invention provides a method of constructing steel structures in combustion and cleaning chambers of power plants with a short cycle time, low construction costs and high safety.

Das technische Problem gelöst ist: die aktuelle Stahlkonstruktion Bau und Verbrennung Ausrüstung Installation und Rauchgasreinigung Ausrüstung Installation Kessel in der Regel sukzessive Bau, Anlagen mit Turmdrehkräne für die Installation, Stahlkonstruktion mit Raupenkrine fiir die Installation, aber fiir einige enge Zeitplan Anforderungen, die Verwendung von aufeinanderfolgenden Bau der Art und Weise der Zyklus ist lang, und die Baukosten sind hoch, kann nicht den Anforderungen des Zeitplans.The technical problem is solved: the current steel structure construction and combustion equipment installation and flue gas cleaning equipment installation boiler generally successive construction, installations using tower cranes for installation, steel structure with crawler cranes for installation, but for some tight schedule requirements, the use of consecutive Construction of the way the cycle is long, and the construction cost is high, can not meet the schedule requirements.

Um die oben genannten technischen Probleme zu lösen, werden in der vorliegenden Erfindung die folgenden technischen Lösungen verwendet: -_———In order to solve the above technical problems, the following technical solutions are used in the present invention: -_———

Description LU502429Description LU502429

Die vorliegende Erfindung ist ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken, umfassend die folgenden Schritte:The present invention is a construction method for lifting steel structures in combustion and cleaning chambers of power plants, comprising the following steps:

Schritt 1: Zoneneinteilung: Der Bereich des Verbrennungsraums westlich des Turmdrehkrans, der für das Heben von Ausrüstungen verwendet wird, wird als Zone 1 bezeichnet, der Bereich des Dekontaminationsraums nördlich des Verbrennungs- raums als Zone 2; der Bereich südlich des Turmdrehkrans wird als Zone 3 bezeichnet, der Bereich nördlich davon als Zone 4 und der Bereich des Turmdrehkrans als Zone 5; der Montageplatz für die Traversen wird an der West-, Nord- und Ostseite der Anlage errichtet; Schritt 2: Auswahl der Ausrüstung: Auswahl von Raupenkränen als Stahlhebegerät, Autokräne als Raupenkran Installation und Demontage, Stahlkonstruktion Montage Ausrüstung, Raupenkräne nach dem Hubradius des Turmdrehkrans, seine eigene Hubradius, Hubleistung und die Höhe der Ausrüstung, wählen Sie die entsprechenden Spezifikationen des Hubgewichts und Auslegerlänge; Schritt 3: Bau: Die Fahrstrecke des Raupenkrans wird von der Zone 2 bis zur nordwestlichen Ecke der Zone 2 aus der Nordseite des Werks herausgefahren, dann durch die Nordseite von der nordöstlichen Ecke der Zone 4 in die Zone 4, die Fahrstrecke wird gehärtet, der Bindermontageplatz wird auf der Fahrstrecke des Raupenkrans in der Zone 2, der nordöstlichen Ecke des Werks, der nordwestlichen Ecke des Werks und der Ostseite des Werks errichtet; mit dem Raupenkran werden zunächst die Hebevorgänge in der ersten Zone durchgeführt, und nach Abschluss der Hebevorgänge in der ersten Zone werden die Hebevorgänge in der zweiten Zone durchgeführt, wobei die erste und die zweite Zone im Rückwärtsbauverfahren ————————Step 1: Zoning: The area of the combustion chamber west of the tower crane used for lifting equipment is designated Zone 1, the area of the decontamination chamber north of the combustion chamber is designated Zone 2; the area south of the tower crane is designated as zone 3, the area to the north thereof as zone 4 and the area of the tower crane as zone 5; the assembly area for the trusses will be erected on the west, north and east side of the system; Step 2: Equipment selection: selection of crawler cranes as steel lifting equipment, truck-mounted cranes as crawler crane installation and disassembly, steel structure assembly equipment, crawler cranes according to the lifting radius of the tower crane, its own lifting radius, lifting capacity and the height of the equipment, choose the appropriate specifications of the lifting weight and boom length; Step 3: Construction: The crawler crane travel route is driven out from the north side of the factory from zone 2 to the northwest corner of zone 2, then through the north side from the north-east corner of zone 4 to zone 4, the travel route is hardened, the Truss assembly site will be set up on the crawler crane travel route in zone 2, the northeast corner of the factory, the northwest corner of the factory and the east side of the factory; with the crawler crane, the first zone lifting operations are carried out first, and after the completion of the first zone lifting operations, the second zone lifting operations are carried out, with the first and second zones in reverse construction method ————————

Description LU502429 ausgeführt werden. Umsetzen des Raupenkrans in Zone vier zum Heben von Bauwerken nach Abschluss der Arbeiten in Zone zwei; bau von Stahlkonstruktionen in Zone 1 und Zone 2, unterbrochen durch das Heben von Stahlkonstruktionen in Zone 3 in Zeiten, in denen der Turmdrehkran keine Ausrüstung hebt; nachdem die Demontage des Turmdrehkrans abgeschlossen war, wurde die Stahlkonstruktion in Zone 5 mit einem Autokran angehoben.Description LU502429 run. moving the crawler crane to zone four to lift structures after completing work in zone two; construction of steel structures in Zone 1 and Zone 2 interrupted by lifting of steel structures in Zone 3 during periods when the tower crane is not lifting equipment; after the dismantling of the tower crane was completed, the steel structure in zone 5 was lifted with a truck-mounted crane.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. In Schritt 1 wird der Ort der Fachwerkmontage auf der Fahrstrecke des Raupenkrans für die Montage der Stahlkonstruktion von Zone 1 und Zone 2 verwendet , der Ort der Fachwerkmontage in der nordwestlichen Ecke der Anlage fiir die Montage der Stahlkonstruktion von Zone 2 verwendet wird, der Ort der Fachwerkmontage in der nordöstlichen Ecke der Anlage fiir die Montage der Stahlkonstruktion von Zone 4 verwendet wird, der Ort der Montage auf der Ostseite der Anlage in der Nähe des Turmdrehkrans fiir die Montage der Stahlkonstruktion von Zone 3 und Zone 5 verwendet wird.The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. In step 1, the truss assembly location on the crawler crane travel route is used for the steel structure assembly of Zone 1 and Zone 2, the truss assembly location in the northwest corner of the facility is used for the steel structure assembly of Zone 2, the location of Truss assembly in the northeast corner of the facility is used for assembling Zone 4 steel structure, the assembly location on the east side of the facility near the tower crane is used for assembling Zone 3 and Zone 5 steel structure.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. In Schritt 3 steht der Raupenkran auf der Westseite des Kessels, um die Gitterstiitzen, Wandbinder, Hauptbinder, Nebenbinder und Zugstangen nacheinander zu heben, der Raupenkran zum Heben in Bereichen verwendet wird, die nicht vom Raupenkran abgedeckt werden; nachdem die Installation in Zone 1 abgeschlossen ist, wird das Rückwärtsmontageverfahren zum Heben der Gitterstiitzen, Hauptbinder, ————————The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. In step 3, the crawler crane stands on the west side of the boiler to lift the lattice columns, wall trusses, main trusses, secondary trusses and tie rods one by one, the crawler crane is used for lifting in areas not covered by the crawler crane; after installation in zone 1 is completed, reverse assembly procedure for lifting lattice supports, main trusses, ————————

Description LU502429 Nebenbinder und Zugstangen nacheinander in Zone 2 verwendet.Description LU502429 Secondary truss and tie rods used in sequence in Zone 2.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. Zwei Bereich Stahlkonstruktion ist abgeschlossen, Raupenkran von der Nordseite der vier Bereich in den vier Bereich für Gitterstütze, Hauptbinder, Nebenbinder und Zugstangen heben.The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. Two area steel structure is completed, crawler crane from the north side of the four area into the four area for lattice support, main truss, secondary truss and tie rods lifting.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. Sekundäre Fachwerk und Pleuelstange Installation sind vor der Fertigstellung des Daches sekundären Fachwerk und Pleuelstange Installation auf der Anlage zu bestimmen, ob die Ausrüstung Installation beeinträchtigen wird. Wenn dies der Fall ist, wird zuerst das Gerät installiert und dann der sekundäre Balken und die Verbindungsstange eingebaut; wenn dies nicht der Fall ist, werden der sekundäre Balken und die Verbindungsstange eingebaut.The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. Secondary truss and connecting rod installation shall be prior to the completion of the roof secondary truss and connecting rod installation on the plant to determine whether the equipment will affect installation. If this is the case, the device is installed first, and then the secondary beam and tie rod are installed; if not, the secondary beam and tie rod are installed.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. Beim Heben der Haupt- und Nebenträger in einem Bereich durch den Turm, wenn der Schwerpunkt der Träger außerhalb des Erfassungsradius des Turmdrehkrans liegt, ein Wassertank an den Untergurt der Träger gesetzt wird, um den Schwerpunkt der Träger in den Erfassungsbereich des Turmdrehkrans zu bringen.The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. When lifting the main and secondary girders in an area through the tower, when the center of gravity of the girders is outside the detection radius of the tower crane, a water tank is placed on the bottom chord of the girders to bring the center of gravity of the girders into the detection range of the tower crane.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. Schweißen Sie I-Träger an die Untergurtstäbe des Fachwerks und den Wassertank —————————The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. Weld I-beams to the truss bottom chords and water tank —————————

Description LU502429 an die I-Träger.Description LU502429 to the I-beams.

Die vorliegende Erfindung betrifft ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. In der Stahlkonstruktion vor dem Schweißen, in der Fabrikation Werkszeichnungen Vertiefung des Knotens Design-Center-Koordinaten in die physische Oberfläche der dreidimensionalen Koordinaten, die Komponenten vor der Fabrik in der äußeren Oberfläche der Komponenten markiert Cross-Center-Position, und markiert mit auffälligen Farbe, zur gleichen Zeit in den Konstruktionszeichnungen, um den Punkt und Punkt-Koordinaten-Wert; bei der Positionierung der Stahlkonstruktion wird der Kreuzmittelpunkt als Positionierungspunkt verwendet.The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. In the steel structure before welding, in the fabrication shop drawings deepening of the node design center coordinates into the physical surface of the three-dimensional coordinates, the components in front of the factory in the outer surface of the components marked cross-center position, and marked with eye-catching color , at the same time in the design drawings to set the point and point coordinate value; when positioning the steel structure, the center of the cross is used as the positioning point.

Die vorliegende Erfindung betrifft eın Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken. Die Kreuzmittelpunkt-Markierungspunkte werden mindestens 300 mm einwärts von den Öffnungen der Armaturen gewählt , die Punkte nahe der Außenseite in der Nähe des Bodens angeordnet sind und nicht weniger als drei Markierungspunkte an jedem Knotenpunkt gewählt werden.The present invention relates to a construction method for lifting steel constructions in combustion and cleaning chambers of power plants. The cross center marking points shall be chosen at least 300 mm inwards from the openings of the fittings, the points shall be located near the outside near the bottom and not less than three marking points shall be chosen at each node.

Verglichen mit dem Stand der Technik hat die vorliegende Erfindung die folgenden vorteilhaften Wirkungen: I. Die vorliegende Anwendung kombiniert die Installation von Stahlkonstruktionen und die Installation von Ausrüstungen in der Anlage, nutzt Turmdrehkräne und Raupenkräne, die für das Heben von Ausrüstungen verwendet werden, um die Anlage sinnvoll aufzuteilen, und ermöglicht dann durch eine sinnvolle Planung der Baureihenfolge und des Bauprozesses jeder Aufteilung die —————————Compared with the prior art, the present invention has the following advantageous effects: I. The present application combines the installation of steel structures and the installation of equipments in the plant, utilizes tower cranes and crawler cranes used for equipment lifting to the subdivide the system in a sensible way, and then enables the ————————— through sensible planning of the construction sequence and the construction process of each division

Description LU502429 Kreuzkonstruktion von Stahlkonstruktionen und die Installation von Ausrüstungen, verkürzt den Bauzyklus, nutzt die Ausrüstungen sinnvoll und reduziert die Baukosten.Description LU502429 Cross construction of steel structures and the installation of equipment shortens the construction cycle, makes good use of the equipment and reduces construction costs.

2. Optimierung des Standorts von Fertig- und Halbfertigprodukten aus Stahl durch rationelle Planung der Baustraßen, um sekundären Umschlag auf der Baustelle zu vermeiden, Transportkosten zu senken und den Bauzyklus zu verkürzen.2. Optimizing the location of finished and semi-finished steel products through rational planning of the construction roads to avoid secondary transhipment at the construction site, reduce transportation costs and shorten the construction cycle.

3. Berücksichtigen Sie die Widersprüche, die sich aus der gleichzeitigen Errichtung der Stahlkonstruktion und der Installation der Ausrüstung während des Baus ergeben, und stellen Sie vor der Installation des sekundären Unterzugs und der Verbindungsstange fest, ob die Fertigstellung der Installation des sekundären Unterzugs und der Verbindungsstange auf dem Dach die Installation der Ausrüstung beeinträchtigt; wenn dies der Fall ist, installieren Sie zuerst die Ausrüstung und dann den sekundären Unterzug und die Verbindungsstange; wenn dies nicht der Fall ist, installieren Sie den sekundären Unterzug und die Verbindungsstange.3. Consider the contradictions arising from the simultaneous erection of the steel structure and the installation of equipment during construction, and before installing the secondary joist and tie rod, determine whether the completion of the installation of the secondary joist and tie rod on the roof affects the installation of equipment; if this is the case, install the equipment first, and then the secondary joist and tie rod; if not, install the secondary downstand and tie bar.

4. In Fällen, in denen der Turmkran und der Raupenkran unübersichtliche Bereiche im Hebebereich haben, die dazu führen, dass der Schwerpunkt des Trägers außerhalb des Abdeckungsradius des Turmkrans liegt, wird ein Wassertank am Untergurt des Trägers installiert, um den Schwerpunkt des Trägers innerhalb des Abdeckungsradius des Turmkrans auszurichten und die Sicherheit des Hebens zu gewährleisten.4. In cases where the tower crane and crawler crane have cluttered areas in the lifting area that cause the center of gravity of the girder to be outside the coverage radius of the tower crane, a water tank will be installed on the bottom chord of the girder to keep the center of gravity of the girder within the Aligning coverage radius of tower crane and ensure the safety of lifting.

5. Durch die Umwandlung der Konstruktionspunkte in dreidimensionale Koordinaten auf der Oberfläche der Bauteile und deren sichtbare Markierung ist es einfach, sie bei der späteren Montage der Stahlkonstruktion zu messen und zu ———————5. By converting the construction points into three-dimensional coordinates on the surface of the structural members and marking them visibly, it is easy to measure and to ——————— during later assembly of the steel structure.

Description LU502429 lokalisieren.Locate Description LU502429.

Die vorliegende Erfindung wird ım Folgenden ın Verbindung mit den beigefügten Zeichnungen näher beschrieben.The present invention is described in more detail below in connection with the accompanying drawings.

Beschreibung der beigefügten Zeichnungen Bild 1 zeigt eine schematische Darstellung der Zonenstruktur der vorliegenden Erfindung.Description of the accompanying drawings Figure 1 shows a schematic representation of the zone structure of the present invention.

Bild 2 zeigt eine schematische Darstellung der Konstruktionsstruktur der Zone I der vorliegenden Erfindung.Figure 2 shows a schematic representation of the Zone I construction structure of the present invention.

Bild 3 zeigt eine schematische Darstellung des Konstruktionsaufbaus der Zone 2 der vorliegenden Erfindung.Figure 3 shows a schematic representation of the structural layout of Zone 2 of the present invention.

Bild 4 zeigt eine schematische Darstellung der Konstruktionsstruktur von Zone 3 und Zone 4 der vorliegenden Erfindung.Figure 4 shows a schematic representation of the construction structure of Zone 3 and Zone 4 of the present invention.

Bild 5 zeigt eine schematische Darstellung der Konstruktionsstruktur von Zone der vorliegenden Erfindung.Figure 5 shows a schematic representation of the construction structure of zones of the present invention.

Bild 6 zeigt eine schematische Darstellung der Traversenhebevorrichtung der vorliegenden Erfindung.Figure 6 shows a schematic representation of the spreader hoist of the present invention.

Bild 7 zeigt eine schematische Darstellung der Befestigungsstruktur des Wassertanks im Sinne der vorliegenden Erfindung.Figure 7 shows a schematic representation of the mounting structure of the water tank according to the present invention.

Mit Kennzeichnungen:With markings:

1. Zone 1; 2. Zone 2; 3. Zone 3; 4. Zone 4; 5. Zone 5; 6. Raupenkran; 7. Turmdrehkran; 8. Fahrweg; 9. Bindermontageplatz; 10. Binder; 11. Wassertank; 12. I-Träger.1.Zone 1; 2.Zone 2; 3.Zone 3; 4.Zone 4; 5.Zone 5; 6. Crawler Crane; 7. Tower Crane; 8. driveway; 9. Truss assembly station; 10. Binder; 11. water tank; 12. I beam.

Detaillierte Beschreibung -_Detailed description -_

Description LU502429 Die Stahlkonstruktion des Verbrennungsraums und des Reinigungsraums des beantragten Kraftwerks besteht aus Gitterstützen, Wandbindern, Hauptbindern, Nebenbindern und Verbindungsstäben.Description LU502429 The steel structure of the combustion chamber and the cleaning chamber of the proposed power plant consists of lattice supports, wall trusses, main trusses, secondary trusses and connecting rods.

Die vorliegende Erfindung umfasst ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken, das die folgenden Schritte umfasst: Siehe Bild 1, Schritt 1: Einteilung in Zonen: Entsprechend der Hebeleistung der Kranmaschinen vor Ort, dem Heberadius, der Bauzeit der Ausrüstung und der Abbauzeit des Turmdrehkrans 7 wird der Bereich des Verbrennungsraums westlich des Turmdrehkrans 7 für das Heben der Ausrüstung des Verbrennungsraums und des Reinigungsraums als Zone 1 und der Bereich des Reinigungsraums nördlich des Verbrennungsraums als Zone 2 festgelegt; der Bereich südlich des Turmdrehkrans 7 wird als Zone 3 und der Bereich nördlich als Zone 4 und der Bereich des Turmdrehkrans 7 als Zone 5 festgelegt; die Gitterstützen und Fachwerkbinder 10 werden zusammengebaut und zum abschnittsweisen Andocken an die Baustelle im Werk geschickt.The present invention includes a construction method for lifting steel structures in combustion and cleaning rooms of power plants, which includes the following steps: See Figure 1, Step 1: Division into zones: According to the lifting capacity of the crane machines on site, the lifting radius, the construction time of the equipment and the dismantling time of the tower crane 7, the area of the incineration room west of the tower crane 7 for lifting the equipment of the incineration room and cleaning room is set as Zone 1, and the area of the cleaning room north of the incineration room is defined as Zone 2; the area south of tower crane 7 is defined as zone 3 and the area north as zone 4 and the area of tower crane 7 as zone 5; the lattice columns and trusses 10 are assembled and sent to the site at the factory for docking section by section.

Schritt 2: Auswahl der Ausrüstung: Der Raupenkran 6 wurde als Hebegerät für die Stahlkonstruktion ausgewählt, und der Autokran wurde für die Montage, Demontage und den Zusammenbau der Stahlkonstruktion verwendet. Der Raupenkran 6 wählte das geeignete Hubgewicht und die Auslegerlänge entsprechend dem Hubradius des Turmdrehkrans 7, seinem eigenen Hubradius, der Hohe und dem Gewicht der Stahlkonstruktion, der Hubleistung und der Ausrüstungshôhe des Raupenkrans 6 und des Turmdrehkrans 7, wobei sich die _—Step 2: Selection of equipment: Crawler crane 6 was selected as the lifting device for the steel structure, and the truck-mounted crane was used for the assembly, disassembly and assembly of the steel structure. The crawler crane 6 selected the appropriate lifting weight and boom length according to the lifting radius of the tower crane 7, its own lifting radius, the height and weight of the steel structure, the lifting capacity and the equipment height of the crawler crane 6 and the tower crane 7, with the _—

Description LU502429 Ausleger des Raupenkrans 6 und des Turmdrehkrans 7 nicht gegenseitig behindern dürfen.Description LU502429 Booms of the crawler crane 6 and the tower crane 7 must not interfere with each other.

Kombiniert mit Bild 2 - Bild 5, Schritt 3: Bau: Der Fahrweg 8 des Raupenkrans 6 fährt von der Nordseite der Anlage aus der Zone 2 zur Nordwestecke der Zone 2, und fährt dann von der Nordostecke der Zone 4 über die Nordseite ın die Zone 4 ein, der Fahrweg 8 wird gehärtet. Der Balkenmontageplatz 9 befindet sich auf der Fahrstrecke 8 des Raupenkrans 6 in Zone 2, in der Nordostecke des Werks, in der nordwestlichen Ecke des Werks und auf der Ostseite des Werks. Der Balkenmontageplatz 9 auf der Fahrstrecke 8 des Raupenkrans 6 wird für die Stahlbaumontage in Zone 1 und Zone 2 genutzt. Der Balkenmontageplatz 9 an der Nordwestecke des Werks ist für die Stahlbaumontage der Zone 2 vorgesehen, der Balkenmontageplatz 9 an der Nordostecke des Werks für die Stahlbaumontage der Zone 4 vorgesehen ist. Der Montagebereich auf der Ostseite des Werks in der Nähe des Hubbereichs von Turmkran 7 wird für die Montage der Stahlkonstruktion in Zone 3 und Zone 5 genutzt. Der Stahlbauhof ist mit einem Hebebereich in der Nähe des Turmdrehkrans 7 ausgestattet, um die Anforderungen an die Hebeleistung der Komponenten zu erfüllen. Optimieren Sie den Lagerort von fertigen und halbfertigen Stahlkonstruktionen, um sekundären Umschlag im Lager zu vermeiden und die Transportkosten zu senken.Combined with Picture 2 - Picture 5, Step 3: Construction: The track 8 of the crawler crane 6 runs from the north side of the plant from zone 2 to the northwest corner of zone 2, and then runs from the northeast corner of zone 4 via the north side ı into the zone 4 on, the route 8 is hardened. The beam assembly station 9 is located on the route 8 of the crawler crane 6 in zone 2, in the northeast corner of the factory, in the northwest corner of the factory and on the east side of the factory. Beam assembly area 9 on route 8 of crawler crane 6 is used for steel construction assembly in Zone 1 and Zone 2. Beam assembly yard 9 at the northwest corner of the plant is intended for zone 2 steel structure assembly, beam assembly yard 9 at the northeast corner of the plant is intended for zone 4 steel structure assembly. The assembly area on the east side of the plant near the lifting area of tower crane 7 is used for assembling the steel structure in Zone 3 and Zone 5. The steel construction yard is equipped with a lifting area near the 7 tower crane to meet the lifting capacity requirements of the components. Optimize the storage location of finished and semi-finished steel structures to eliminate secondary warehouse handling and reduce transportation costs.

Verwenden Sie den Raupenkran 6, um zuerst die Hebekonstruktion von Zone 1 durchzuführen; nachdem die Hebekonstruktion von Zone 1 abgeschlossen ist, führen Sie die Hebekonstruktion von Zone 2 durch, wobei Zone 1 und Zone 2 die Rückwärtsbauweise anwenden; nachdem die Konstruktion von Zone 2 1Use the Crawler Crane 6 to do the lifting construction of Zone 1 first; after zone 1 lift construction is completed, perform zone 2 lift construction, with zone 1 and zone 2 using reverse construction; after the construction of Zone 2 1

Description LU502429 abgeschlossen ist, bewegen Sie den Raupenkran 6 für die Hebekonstruktion nach Zone 4; wenn Sie die Stahlkonstruktion von Zone 1 und Zone 2 bauen, unterbrechen Sie die Hebekonstruktion der Stahlkonstruktion von Zone 3 während der nicht hebenden Ausrüstung des Turmdrehkrans 7; nachdem die Demontage des Turmdrehkrans 7 abgeschlossen ist, verwenden Sie den Autokran, um in Zone 5 zu gelangen, um die Stahlkonstruktion zu heben, und errichten Sie den Fachwerkmontageplatz 9 an der Stelle des ursprünglichen Turmdrehkrans 7 während der Konstruktion.Description LU502429 is completed, move the crawler crane 6 for the lifting structure to zone 4; when constructing the steel structure of Zone 1 and Zone 2, break the lifting structure of the steel structure of Zone 3 during the tower crane 7 non-lifting equipment; after tower crane 7 dismantling is completed, use truck crane to get into zone 5 to lift the steel structure and erect truss assembly yard 9 in place of original tower crane 7 during construction.

Konkret: Die Fahrstrecke 8 des Raupenkrans 6 fährt von der Nordseite des Werks aus der Zone 2 bis zur nordwestlichen Ecke der Zone 2 und fährt dann über die Nordseite von der nordöstlichen Ecke der Zone 4 in die Zone 4 ein. Die Fahrstrecke 8 wird gehärtet und auf der Fahrstrecke 8 des Raupenkrans 6 wird während des Baus der Stahlkonstruktion in Zone 1 und Zone 2 ein Bindermontageplatz 9 eingerichtet.Specifically, the route 8 of the crawler crane 6 runs from the north side of the factory from zone 2 to the northwest corner of zone 2, and then enters zone 4 via the north side from the northeast corner of zone 4. The route 8 is hardened and a truss assembly station 9 is set up on the route 8 of the crawler crane 6 during the construction of the steel structure in zone 1 and zone 2.

Während der Errichtung der Stahlkonstruktion in Zone 1 wurde der Raupenkran 6 von der Nordwestecke der Anlage in die Anlage gebracht und auf der Westseite des Kessels aufgestellt, um nacheinander die Gitterstützen, Wandbinder, Hauptbinder, Nebenbinder und Zugstangen mit dem Turmdrehkran 7 in den Bereichen anzuheben, die nicht vom Hubbereich des Raupenkrans 6 abgedeckt werden. Nach Abschluss der Montage der Stahlkonstruktion in Zone 1 werden nacheinander die Fachwerkstützen, die Hauptbinder, die Nebenbinder und die Zugstangen in Zone 2 im Rückwärtseinbauverfahren angehoben.During the erection of the steel structure in Zone 1, the Crawler Crane 6 was brought into the plant from the north-west corner of the plant and positioned on the west side of the boiler to successively raise the lattice columns, wall trusses, main trusses, secondary trusses and tie rods with the Tower Crane 7 in the areas, which are not covered by the lifting range of the crawler crane 6. After completing the assembly of the steel structure in Zone 1, the truss supports, the main trusses, the secondary trusses and the tie rods in Zone 2 are raised one after the other using the reverse installation method.

Bezug nehmend auf Bild 6 und Bild 7, wobei beim Bau der Stahlkonstruktion 1Referring to Figure 6 and Figure 7, when constructing the steel structure 1

Description LU502429 der Zone 1 eine Blindzone ım Hebebereich des Turmdrehkrans 7 und des Raupenkrans 6 vorhanden ist, was dazu führt, dass der Schwerpunkt des Trägers 10 außerhalb des Abdeckungsradius des Turmdrehkrans 7 liegt. Ein Wassertank 11 wird am Untergurt des Trägers 10 angebracht, um den Schwerpunkt des Trägers 10 vor dem anschließenden Heben innerhalb des Abdeckungsradius des Turmdrehkrans 7 einzustellen; insbesondere wird ein I-Träger 12 an den Untergurt des Trägers 10 geschweißt und der Wassertank 11 wird an den I-Träger 12 geschweißt und befestigt.Description LU502429 of zone 1 there is a blind zone in the lifting area of the tower crane 7 and the crawler crane 6, which causes the center of gravity of the girder 10 to be outside the coverage radius of the tower crane 7. A water tank 11 is attached to the bottom chord of the girder 10 to adjust the center of gravity of the girder 10 before subsequent lifting within the coverage radius of the tower crane 7; specifically, an I-beam 12 is welded to the bottom chord of the beam 10, and the water tank 11 is welded to the I-beam 12 and fixed.

Nach der Fertigstellung der Stahlkonstruktion in Zone 2 wurde der Raupenkran 6 von der Nordseite der Zone 4 aus in die Zone 4 gefahren, um die Gitterstützen, Haupt- und Nebenbinder sowie die Zugstangen einzuheben.After completion of the steel structure in Zone 2, crawler crane 6 was driven into Zone 4 from the north side of Zone 4 to lift the lattice supports, main and secondary trusses and tie rods.

Außerdem wird vor dem Einbau der Sekundärbinder und Zugstangen festgestellt, ob die Fertigstellung des Einbaus der Sekundärbinder und Zugstangen auf dem Dach den Einbau der Geräte beeinträchtigt; wenn ja, werden zuerst die Geräte eingebaut und dann die Sekundärbinder und Zugstangen installiert; wenn nicht, werden die Sekundärbinder und Zugstangen installiert.In addition, before installing the secondary trusses and tie rods, it is determined whether the completion of the installation of the secondary trusses and tie rods on the roof will affect the installation of the equipment; if so, the devices are installed first, and then the secondary trusses and tie rods are installed; if not, the secondary trusses and tie rods are installed.

Da derzeit die axialen Koordinaten der Knoten oft in den Konstruktionszeichnungen angegeben sind, sind diese Daten für die Konstruktion praktisch nicht brauchbar, das Reflexionsprisma der Totalstation kann nicht an der Position dieses Koordinatenpunktes stehen, noch kann das Infrarot den Stab durchdringen, um den Mittelpunkt zu erreichen, und es gibt keinen offensichtlichen Winkelmerkmalspunkt auf der Außenfläche, das Element der Messung und Positionierung ist der Punkt und der dreidimensionale Koordinatenwert des Punktes, die Position aller Knoten muss durch die dreidimensionalen Koordinaten bestimmt 1Since at present the axial coordinates of the nodes are often given in the design drawings, these data are practically useless for the design, the reflection prism of the total station cannot stand at the position of this coordinate point, nor can the infrared penetrate the rod to reach the center , and there is no obvious angle feature point on the outer surface, the element of measurement and positioning is the point and the three-dimensional coordinate value of the point, the position of all nodes must be determined by the three-dimensional coordinates 1

Description LU502429 werden, um ihre Position zu bestimmen, und die Konstruktion ist schwierig. Daher werden die Koordinaten des Knotenpunkts in der Entwurfszeichnung in 3D- Koordinaten der physischen Oberfläche umgewandelt, wenn die Zeichnungen in der Fertigungsanlage vertieft werden, und die Position des Kreuzmittelpunkts wird auf der Außenfläche des Bauteils markiert, bevor es das Werk verlässt, und mit auffälliger Farbe gekennzeichnet, während die Punktposition und der Punktkoordinatenwert auf der Entwurfszeichnung markiert werden; bei der Positionierung der Stahlkonstruktion wird die Position des Kreuzmittelpunkts als Positionierungspunkt entsprechend der Position des Kreuzmittelpunkts verwendet.Description LU502429 to determine their position, and the construction is difficult. Therefore, the coordinates of the nodal point in the design drawing are converted to 3D coordinates of the physical surface when the drawings are deepened in the factory, and the position of the cross center is marked on the outer surface of the part before it leaves the factory and with conspicuous color marked while marking the point position and point coordinate value on the design drawing; when positioning the steel structure, the position of the cross center is used as the positioning point corresponding to the position of the cross center.

Die Grundsätze für die Auswahl der Markierungspunkte sind: Der Markierungspunkt wird mindestens 300 mm von der Rohranschlussöffnung entfernt gewählt; die Position des Punktes ist nahe der Außenseite in der Nähe des Bodens, so weit wie möglich in der gleichen sichtbaren Ebene, und der Abstand zwischen den Punkten ist so groß wie möglich; nicht weniger als drei Punkte sollten an jedem Knoten ausgewählt werden. Wo die Punkte sind in den Knoten Port bis 300mm nach innen ausgewählt, ist es, in der Stahlkonstruktion Schweißen zu vermeiden, was zu markieren Punkt Positionsabweichung, wie Punkte in der Nähe des Hafens, Schweißen Metall schmelzen oder nach dem Schweißen Schleifen kann der Punkt Schaden zu entfernen, so dass die Abweichung nach dem Schweißen ist schwierig, den Vergleich zu bestimmen. Die Punkte befinden sich nahe der Außenseite in der Nähe des Bodens, so weit wie möglich in einer sichtbaren Ebene und der Abstand zwischen den Punkten ist so groß wie möglich. Die erste Überlegung ist die Einfachheit der Messung, da die Totalstation auf dem Boden aufgestellt wird und 1The principles for selecting the marking points are: the marking point is chosen at least 300 mm from the pipe connection opening; the position of the point is near the outside near the ground, as far as possible in the same visible plane, and the distance between the points is as large as possible; no fewer than three points should be selected at each node. Where the points are selected in the node port to 300mm inside, it is to avoid welding in the steel structure, resulting in marking point position deviation, such as points near the port, welding metal melt or grinding after welding may damage the point remove, so the deviation after welding is difficult to determine the comparison. The points are near the outside near the ground, as far as possible in a visible plane, and the distance between the points is as large as possible. The first consideration is the ease of measurement since the total station is placed on the ground and 1

Description LU502429 Punkte in der gleichen Sichtebene auf einmal beobachtet werden können, ansonsten muss die Station zweimal bewegt werden. Messungen aus einem anderen Winkel, von denen die zweite Messung zwischen wird auch ein gewisses Maß an Messfehler verursachen. Der Abstand zwischen den Punkten wird relativ zur maximalen Diagonale des Knotens umso größer, je größer der Abstand zwischen den Punkten und das Verhältnis der Diagonalenlänge ist, d.h. je höher die relative Fehlergenauigkeit ist, desto höher ist die korrekte Positionierung des Knotens. Jeder Knoten sollte nicht weniger als 3 Messmarken haben, die für die Positionierung ım 3D-Koordinatenraum benötigt werden. Wenn nur ein oder zwei Punkte ausgewählt werden, können sich die Knoten um die Achse drehen, was sich auf den Ausrichtungswinkel des Balkens auswirken kann.Description LU502429 Points in the same view plane can be observed at once, otherwise the station has to be moved twice. Measurements from a different angle from which the second measurement between will also cause a certain amount of measurement error. The distance between the points becomes larger relative to the maximum diagonal of the node, the larger the distance between the points and the ratio of the diagonal length, i.e. the higher the relative error accuracy, the higher the correct positioning of the node. Each node should have no less than 3 gage marks needed for positioning in 3D coordinate space. If only one or two points are selected, the nodes may rotate around the axis, which may affect the beam's orientation angle.

Die oben beschriebenen Ausführungsformen sind nur eine Beschreibung der bevorzugten Ausführungsform der vorliegenden Erfindung und sollen den Umfang der vorliegenden Erfindung nicht einschränken. Ohne vom Geist der vorliegenden Erfindung abzuweichen, fallen alle Arten von Variationen und Verbesserungen, die von Fachleuten an den technischen Lösungen der vorliegenden Erfindung vorgenommen werden, in den durch die Ansprüche der vorliegenden Erfindung bestimmten Schutzbereich.The embodiments described above are only a description of the preferred embodiment of the present invention and are not intended to limit the scope of the present invention. Without departing from the gist of the present invention, all kinds of variations and improvements made by those skilled in the art to the technical solutions of the present invention fall within the scope of protection determined by the claims of the present invention.

11

Claims (9)

Claims LU502429Claim LU502429 1. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken, dadurch gekennzeichnet, dass es die folgenden Schritte umfasst: Schritt 1: Zoneneinteilung: Der Bereich des Verbrennungsraums westlich des Turmdrehkrans, der für das Heben von Ausrüstungen verwendet wird, wird als Zone 1 bezeichnet, der Bereich des Dekontaminationsraums nördlich des Verbrennungs- raums als Zone 2; der Bereich südlich des Turmdrehkrans wird als Zone 3 bezeichnet, der Bereich nördlich davon als Zone 4 und der Bereich des Turmdrehkrans als Zone 5; Schritt 2: Auswahl der Ausrüstung: Auswahl von Raupenkränen als Stahlhebegerät, Autokräne als Raupenkran Installation und Demontage, Stahlkonstruktion Montage Ausrüstung, Raupenkräne nach dem Hubradius des Turmdrehkrans, seine eigene Hubradius, Hubleistung und die Höhe der Ausrüstung, wählen Sie die entsprechenden Spezifikationen des Hubgewichts und Auslegerlänge; Schritt 3: Bau: Die Fahrstrecke des Raupenkrans wird von der Zone 2 bis zur nordwestlichen Ecke der Zone 2 aus der Nordseite des Werks herausgefahren, dann durch die Nordseite von der nordöstlichen Ecke der Zone 4 in die Zone 4, die Fahrstrecke wird gehärtet, der Bindermontageplatz wird auf der Fahrstrecke des Raupenkrans in der Zone 2, der nordöstlichen Ecke des Werks, der nordwestlichen Ecke des Werks und der Ostseite des Werks errichtet; mit dem Raupenkran werden zunächst die Hebevorgänge in der ersten Zone durchgeführt, und nach Abschluss der Hebevorgänge in der ersten Zone werden die Hebevorgänge in der zweiten Zone durchgeführt, wobei die erste und die zweite Zone im Rückwärtsbauverfahren ausgeführt werden. Umsetzen des Raupenkrans in Zone vier zum Heben von —=<ËŒÆHË—1. A construction method for lifting steel structures in combustion and cleaning rooms of power plants, characterized in that it comprises the following steps: Step 1: Zoning: The area of the combustion room west of the tower crane, which is used for lifting equipment, is defined as Zone 1 denotes the area of the decontamination room north of the combustion chamber as Zone 2; the area south of the tower crane is designated as zone 3, the area to the north thereof as zone 4 and the area of the tower crane as zone 5; Step 2: Equipment selection: selection of crawler cranes as steel lifting equipment, truck-mounted cranes as crawler crane installation and disassembly, steel structure assembly equipment, crawler cranes according to the lifting radius of the tower crane, its own lifting radius, lifting capacity and the height of the equipment, choose the appropriate specifications of the lifting weight and boom length; Step 3: Construction: The crawler crane travel route is driven out from the north side of the factory from zone 2 to the northwest corner of zone 2, then through the north side from the north-east corner of zone 4 to zone 4, the travel route is hardened, the Truss assembly site will be set up on the crawler crane travel route in zone 2, the northeast corner of the factory, the northwest corner of the factory and the east side of the factory; with the crawler crane, the first zone lifting operations are performed first, and after the first zone lifting operations are completed, the second zone lifting operations are performed, with the first and second zones being reversed. Moving the crawler crane to zone four to lift —=<ËŒÆHË— Claims LU502429 Bauwerken nach Abschluss der Arbeiten in Zone zwei; bau von Stahlkonstruktionen in Zone 1 und Zone 2, unterbrochen durch das Heben von Stahlkonstruktionen in Zone 3 in Zeiten, in denen der Turmdrehkran keine Ausrüstung hebt; nachdem die Demontage des Turmdrehkrans abgeschlossen war, wurde die Stahlkonstruktion in Zone 5 mit einem Autokran angehoben.Claims LU502429 structures upon completion of work in zone two; construction of steel structures in Zone 1 and Zone 2 interrupted by lifting of steel structures in Zone 3 during periods when the tower crane is not lifting equipment; after the dismantling of the tower crane was completed, the steel structure in zone 5 was lifted with a truck-mounted crane. 2. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen ın Verbrennungs- und Reinigungsräumen von Kraftwerken nach Anspruch 1 , ist durch die folgenden Merkmale gekennzeichnet: In Schritt 1 der Ort der Fachwerkmontage wird auf der Fahrstrecke des Raupenkrans für die Montage der Stahlkonstruktion von Zone 1 und Zone 2 verwendet, der Ort der Fachwerkmontage ın der nordwestlichen Ecke der Anlage für die Montage der Stahlkonstruktion von Zone 2 verwendet wird, der Ort der Fachwerkmontage in der nordöstlichen Ecke der Anlage für die Montage der Stahlkonstruktion von Zone 4 verwendet wird, der Ort der Montage auf der Ostseite der Anlage in der Nähe des Turmdrehkrans für die Montage der Stahlkonstruktion von Zone 3 und Zone 5 verwendet wird.2. A construction method for lifting steel structures in combustion and cleaning rooms of power plants according to claim 1, is characterized by the following features: In step 1, the place of truss assembly is on the route of the crawler crane for assembling the steel structure of zone 1 and zone 2 truss assembly location in the north-west corner of the facility is used for assembling zone 2 steel structure, truss assembly location in the north-east corner of the facility is used for zone 4 steel structure assembly, truss assembly location on the East side of the facility near the tower crane used for assembling the steel structure of Zone 3 and Zone 5. 3. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken nach Anspruch 1, ist durch die folgenden Merkmale gekennzeichnet: In Schritt 3 steht der Raupenkran auf der Westseite des Kessels, um die Gitterstützen, Wandbinder, Hauptbinder, Nebenbinder und Zugstangen nacheinander zu heben, und der Raupenkran zum Heben ın Bereichen verwendet wird, die nicht vom Raupenkran abgedeckt werden; nachdem die Installation in Zone 1 abgeschlossen ist, wird das Rückwärtsmontageverfahren zum Heben der Gitterstützen, Hauptbinder, Nebenbinder und Zugstangen —=ËŒÆË—3. A construction method for lifting steel structures in combustion and cleaning rooms of power plants according to claim 1, is characterized by the following features: In step 3, the crawler crane stands on the west side of the boiler, around the lattice supports, wall trusses, main trusses, secondary trusses and tie rods one after the other lifting and the crawler crane is used for lifting in areas not covered by the crawler crane; after installation in zone 1 is completed, reverse assembly procedure for lifting lattice supports, main truss, secondary truss and tie rods —=ËŒÆË— Claims LU502429 nacheinander in Zone 2 verwendet.Claims LU502429 used consecutively in Zone 2. 4. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen ın Verbrennungs- und Reinigungsräumen von Kraftwerken nach Anspruch 3, ist durch die folgenden Merkmale gekennzeichnet: Zwei Bereich Stahlkonstruktion ist abgeschlossen, Raupenkran von der Nordseite der vier Bereich in den vier Bereich für Gitterstütze, Hauptbinder, Nebenbinder und Zugstangen heben.4. A construction method for lifting steel structures in combustion and cleaning rooms of power plants according to claim 3, is characterized by the following features: Two area steel structure is completed, crawler crane from the north side of the four areas into the four areas for lattice support, main truss, secondary truss and lift tie rods. 5. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken nach einem der Ansprüche 3-4, ist durch die folgenden Merkmale gekennzeichnet: Sekundäre Fachwerk und Pleuelstange Installation ist vor der Fertigstellung des Daches sekundären Fachwerk und Pleuelstange Installation auf der Anlage zu bestimmen, ob die Ausrüstung Installation beeinträchtigen wird. Wenn dies der Fall ist, wird zuerst das Gerät installiert und dann der sekundäre Balken und die Verbindungsstange eingebaut; wenn dies nicht der Fall ist, werden der sekundäre Balken und die Verbindungsstange eingebaut.5. A construction method for lifting steel structures in combustion and cleaning rooms of power plants according to any one of claims 3-4, is characterized by the following features: Secondary truss and connecting rod installation is prior to the completion of the roof secondary truss and connecting rod installation on the plant determine whether the equipment will affect installation. If this is the case, the device is installed first, and then the secondary beam and tie rod are installed; if not, the secondary beam and tie rod are installed. 6. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerkennach Anspruch 3, ist durch die folgenden Merkmale gekennzeichnet: Beim Heben der Haupt- und Nebenträger in einem Bereich durch den Turm, wenn der Schwerpunkt der Träger außerhalb des Erfassungsradius des Turmdrehkrans liegt, ein Wassertank an den Untergurt der Träger gesetzt wird, um den Schwerpunkt der Träger in den Erfassungsbereich des Turmdrehkrans zu bringen.6. A construction method for lifting steel structures in combustion and cleaning rooms of power plants according to claim 3, is characterized by the following features: When lifting the main and secondary beams in one area through the tower, when the center of gravity of the beams is outside the coverage radius of the tower crane , a water tank is placed on the lower chord of the girders in order to bring the center of gravity of the girders into the detection range of the tower crane. 7. Ein Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in m7. A construction method for lifting steel structures in m Claims LU502429 Verbrennungs- und Reinigungsräumen von Kraftwerken nach Anspruch 6, ist durch die folgenden Merkmale gekennzeichnet: In der Fachwerkuntergurt bar geschweißt I-Träger, Wassertank und I-Träger Schweißen.Claims LU502429 Combustion and cleaning rooms of power plants according to claim 6, is characterized by the following features: I-beam, water tank and I-beam welded in the truss lower chord bar. 8. Fin Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken nach Anspruch 1, ist durch die folgenden Merkmale gekennzeichnet: In der Stahlkonstruktion vor dem SchweiBen, in der Fabrikation Werkszeichnungen Vertiefung des Knotens Design- Center-Koordinaten in die physische Oberfläche der dreidimensionalen Koordinaten, die Komponenten vor der Fabrik in der äußeren Oberfläche der Komponenten markiert Cross-Center-Position, und markiert mit auffälligen Farbe, zur gleichen Zeit in den Konstruktionszeichnungen, um den Punkt und Punkt-Koordinaten-Wert. Bei der Positionierung der Stahlkonstruktion wird der Kreuzmittelpunkt als Positionierungspunkt verwendet.8. Fin construction method for lifting steel structures in combustion and cleaning rooms of power plants according to claim 1, is characterized by the following features: in the steel structure before welding, in the fabrication works drawings deepening of the node design center coordinates in the physical surface of three-dimensional coordinates, the components in front of the factory in the outer surface of the components marked cross-center position, and marked with eye-catching color, at the same time in the design drawings to show the point and point coordinate value. When positioning the steel structure, the center of the cross is used as the positioning point. 9. Fin Konstruktionsverfahren zum Anheben von Stahlkonstruktionen in Verbrennungs- und Reinigungsräumen von Kraftwerken nach Anspruch 8, ist durch die folgenden Merkmale gekennzeichnet: Die Kreuzmittelpunkt-Markierungs- punkte werden mindestens 300 mm einwärts von den Offnungen der Armaturen gewählt werden, die Punkte nahe der Außenseite in der Nähe des Bodens angeordnet sind und nicht weniger als drei Markierungspunkte an jedem Knotenpunkt gewählt werden. -_———9. Fin construction method for lifting steel structures in combustion and cleaning chambers of power plants according to claim 8, is characterized by the following features: The cross center marking points will be chosen at least 300 mm inwards from the openings of the fittings, the points close to the outside are located close to the ground and no fewer than three markers are chosen at each node. -_———
LU502429A 2022-01-20 2022-06-30 A construction method for lifting steel structures in combustion and cleaning chambers of power plants LU502429B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210065014.6A CN114562137B (en) 2022-01-20 2022-01-20 Steel structure hoisting construction method for power plant incineration room and purification room

Publications (1)

Publication Number Publication Date
LU502429B1 true LU502429B1 (en) 2023-01-12

Family

ID=81712309

Family Applications (1)

Application Number Title Priority Date Filing Date
LU502429A LU502429B1 (en) 2022-01-20 2022-06-30 A construction method for lifting steel structures in combustion and cleaning chambers of power plants

Country Status (2)

Country Link
CN (1) CN114562137B (en)
LU (1) LU502429B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117365121A (en) * 2023-08-31 2024-01-09 上海宝冶集团有限公司 Method for installing ultra-high special-shaped tower in limited space of large-sized garbage incineration power plant

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3749602B2 (en) * 1997-10-06 2006-03-01 宮地建設工業株式会社 Directly erected construction method of large roof
JP2007107785A (en) * 2005-10-12 2007-04-26 Babcock Hitachi Kk Installation method of boiler equipment
CN101899904B (en) * 2010-07-23 2011-06-29 中冶建工有限公司 Method for two-way hoisting construction of converter tower steel structure
CN106869319A (en) * 2017-01-22 2017-06-20 中国十七冶集团有限公司 Large span steel truss installation method
CN110356983A (en) * 2019-07-02 2019-10-22 山东核电设备制造有限公司 Nuclear power shields workshop suspender equipment and installation method
CN113863736B (en) * 2021-09-10 2023-02-28 上海二十冶建设有限公司 Construction process of continuous-span common-column C-shaped stock yard

Also Published As

Publication number Publication date
CN114562137B (en) 2024-04-16
CN114562137A (en) 2022-05-31

Similar Documents

Publication Publication Date Title
CN102345393B (en) High-altitude bulk process of bolt ball net frame
LU502429B1 (en) A construction method for lifting steel structures in combustion and cleaning chambers of power plants
CN108277882A (en) Super-huge steel structure canopy construction technology under mal-condition
CN110847375B (en) Large-span truss construction method and large-span truss structure
CN102296858A (en) Cement production line clinker storage warehouse roof steel structure and construction method thereof
CN209941511U (en) Supporting device for high-altitude folding of bridge steel box girder by section hoisting
CN111395623B (en) Steel arch-shaped roof structure of nuclear power station and assembling construction method thereof
CN108914963A (en) Assembled arcading barricade
CN117684700B (en) Tree-shaped column structure of station house main body and construction method thereof
CN114991483B (en) Construction method of large-span suspension ridge hyperbolic inverted arch skew single-layer grid structure
CN111042318A (en) Single-layer aluminum alloy latticed shell box type modular assembly joint and construction process thereof
JP2011052512A (en) Roof repair construction method and structure
CN108442598A (en) Rack and steel truss light composite board Combined roof construction
CN212337308U (en) Corrugated plate supporting structure and subway transverse passage
CN212077591U (en) Component hoisting walking foundation under complex environment of large railway station house
CN103470077A (en) Novel steel-structured plant
CN210421630U (en) Main workshop cylinder structure
CN110593081A (en) Component hoisting walking foundation for large railway station house under complex environment and construction method
Kollar Large reticulated steel cooling towers
GB2591785A (en) Modular structure for providing on-site protection
CN214329793U (en) Steel platform for repairing travelling crane
CN114215191B (en) Modular hoisting and two-stage integral synchronous lifting method for ultra-large span steel roof
CN217352141U (en) Construction system of large-section steel box girder
CN203129582U (en) Hydraulic lifting system
Yin et al. Research on the difficulties and countermeasures of super high-rise steel structure construction

Legal Events

Date Code Title Description
FG Patent granted

Effective date: 20230112