KR980002444A - Continuation Method of PSC Beam Using Point Rise and Fall - Google Patents

Continuation Method of PSC Beam Using Point Rise and Fall Download PDF

Info

Publication number
KR980002444A
KR980002444A KR1019980001799A KR19980001799A KR980002444A KR 980002444 A KR980002444 A KR 980002444A KR 1019980001799 A KR1019980001799 A KR 1019980001799A KR 19980001799 A KR19980001799 A KR 19980001799A KR 980002444 A KR980002444 A KR 980002444A
Authority
KR
South Korea
Prior art keywords
point
section
fall
parent
continuation method
Prior art date
Application number
KR1019980001799A
Other languages
Korean (ko)
Other versions
KR100283603B1 (en
Inventor
구민세
Original Assignee
구민세
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 구민세 filed Critical 구민세
Priority to KR1019980001799A priority Critical patent/KR100283603B1/en
Publication of KR980002444A publication Critical patent/KR980002444A/en
Application granted granted Critical
Publication of KR100283603B1 publication Critical patent/KR100283603B1/en

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

외측경간용 피에스씨 빔과 내측경간용 피에스씨 빔을 강선을 이용하여 정모멘트구간과 부모멘트구간에 압축프리스트레싱응력이 도입되도록 제작하여 다이아프램을 이용하여 빔과 빔을 일체화시킨 상태에서 내측지점부를 상승시켜 내측지점 부모멘트구간에 슬래브 콘크리트를 타설 및 양생시킨 후 내측지점부를 원상태로 하강시킨후 나머지 구간에 슬래브 콘크리트를 타설하여 설계하중이 작용시 발생되는 인장응력을 상쇄시킬 수 있는 압축 프리스트레싱 응력을 도입함을 핵심기술로 하는 지점 상승 및 하강을 이용한 피애스씨 빔의 연속화 공법.The outer point PS beam and the inner beam PS beam are manufactured so that compressive prestressing stress is introduced into the constant moment section and the parent section section using steel wires, and the inner point part is integrated with the beam using the diaphragm. The slab concrete is poured and cured in the parent point section of the inner point, and the inner point is lowered to the original state. Continuation method of PICES beam using point rise and fall with the core technology introduced.

Description

지점상승 및 하강을 이용한 피에스씨 빔(PSC Beam)의 연속화 공법Continuation Method of PSC Beam Using Point Rise and Fall

본 내용은 요부공개 건이므로 전문내용을 수록하지 않았음Since this is an open matter, no full text was included.

제2도는 본 발명에 의한 연속보형 구조물의 내측경간용 피에스씨 빔의 프리스트레싱 원리도.2 is a prestressing principle diagram of the PS beam for the inner span of the continuous beam structure according to the present invention.

제3도는 본 발명에 의한 연속보형 구조물의 내측경간용 피에스씨 빔의 프리스트레싱 원리도.3 is a prestressing principle diagram of the PS beam for the inner span of the continuous beam structure according to the present invention.

제4도는 본 발명에 의한 2경간 연속보 구조물의 시공에서 2개의 외측 경간용 피에스씨 빔을 중앙에서 다이아프램(Diaphragm)을 이용하여 일체화시킨후 내측지점을 상승시킨 상태에서 부모멘트 구간에 슬래브 콘크리트를 타설 및 양생후에 하강시킴으로써 압축 프리스트레싱을 도입하는 상태도.4 is a slab concrete in the parent cement section in the state of raising the inner point after integrating the two outer span PS beam in the center using a diaphragm (Diaphragm) in the construction of the two-span continuous beam structure according to the present invention The state which introduces compression prestressing by lowering after pouring and curing.

Claims (1)

피에스씨 빔(PSC Beam)을 연속빔 구조물로 시공함에 있어 내측경간 피에스씨 빔과 외측경간 피에스씨 빔을 연속구조물로 완성되었을시 발생되는 정모멘트와 부모멘트에 대응되도록 피에스(PS)강선을 이용하여 제작하여 빔과 빔을 다이아프램(Diaphragm)을 이용하여 종으로 일체화시킨 후 내부지점을 상승함으로써 내측지점부에 부모멘트를 발생시켜 부모멘트구간의 슬래브 콘크리트에 압축응력을 도입시키는 특징을 갖는 지점 상승 및 하강을 이용한 피에스씨 빔의 연속화공법.In constructing a PSC beam as a continuous beam structure, PS steel wire is used to correspond to the static moment and the parent moment generated when the inner span PS beam and the outer span PS beam are completed as a continuous structure. Point that has the characteristic of introducing compressive stress to the slab concrete of the parent section by raising the inner point and raising the inner point by integrating the beam and the beam into the bell by using the diaphragm. Continuous beam method of PS beam using rising and falling. ※ 참고사항 : 최초출원 내용에 의하여 공개하는 것임.※ Note: The disclosure is based on the initial application.
KR1019980001799A 1998-01-22 1998-01-22 Continuation Method of PSC Beam Using Point Rise and Fall KR100283603B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019980001799A KR100283603B1 (en) 1998-01-22 1998-01-22 Continuation Method of PSC Beam Using Point Rise and Fall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019980001799A KR100283603B1 (en) 1998-01-22 1998-01-22 Continuation Method of PSC Beam Using Point Rise and Fall

Publications (2)

Publication Number Publication Date
KR980002444A true KR980002444A (en) 1998-03-30
KR100283603B1 KR100283603B1 (en) 2001-03-02

Family

ID=65892741

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019980001799A KR100283603B1 (en) 1998-01-22 1998-01-22 Continuation Method of PSC Beam Using Point Rise and Fall

Country Status (1)

Country Link
KR (1) KR100283603B1 (en)

Also Published As

Publication number Publication date
KR100283603B1 (en) 2001-03-02

Similar Documents

Publication Publication Date Title
NO20093490L (en) Oil well drilling centering device
KR980002444A (en) Continuation Method of PSC Beam Using Point Rise and Fall
KR101146586B1 (en) UHPC Anchor Block for Prestressed Tendon and Prestressed Concrete Member having such UHPC Ancho Block
JP2001295469A (en) Method of constructing reinforced concrete column
ATE42785T1 (en) HEAT-INSULATING FORMWORK STONE.
AP1557A (en) Flat soffit, doubly prestressed, composite, roof-ceiling construction for large span industrial buildings
CH614006A5 (en) Method for producing fireproof concrete construction elements
KR200256791Y1 (en) prestressed composite beam made by using incrementally prestressing
KR100286614B1 (en) Continuous process of pcs beam by weight
KR19980019378A (en) Fabrication Method of Simple Beam Pre-Flex Composite Beam Using Branch Point
KR19990073455A (en) 2nd Prestressing Method of Simple Composite Beam Using PSC Steel Bar
KR20020023074A (en) The method of prestressed composite beam made by using the additional compressive materials
KR100328320B1 (en) The Construction and Repair Method of Continuous Girder Bridges by lifting and lowering the inner support.
DE60224946D1 (en) METHOD FOR REINFORCING A DOUBLE SHELL CONSTRUCTION
MA28165A1 (en) METHOD FOR PRODUCING A CONCRETE PIECE AND REINFORCING CAGE FOR A PART PRODUCED THEREBY
KR950032906A (en) Bridge construction method
KR19990073124A (en) 2nd Prestressing Method of Simple Prestressing Composite Beam Using PC Steel Bar
KR100537773B1 (en) Precasttype anchorage segment structures for building PSC(prestressed concrete) box girder bridge
UA32090A (en) VIBROPAD FOR FORMING PRODUCTS IN MOLD
KR970070372A (en) Manufacturing method of compressed slab member by putting steel wire in concrete
SU1399436A1 (en) Method of reinforcing metal column
CN104278876A (en) Splicing method of concrete tower pole
GB930111A (en) Method for the construction of a long-span bridge in pre-stressed concrete
FI906117A0 (en) FRAMSTAELLNINGSFOERFARANDE AV BETONGPELARE.
UA36558A (en) METHOD OF CONSTRUCTION OF ROAD FENCE

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
J204 Request for invalidation trial [patent]
J206 Request for trial to confirm the scope of a patent right
J206 Request for trial to confirm the scope of a patent right
J121 Written withdrawal of request for trial
J206 Request for trial to confirm the scope of a patent right
J301 Trial decision

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20050902

Effective date: 20060228

J121 Written withdrawal of request for trial
FPAY Annual fee payment

Payment date: 20121029

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20130926

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20140923

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20150918

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20161006

Year of fee payment: 17

EXPY Expiration of term