KR20240045647A - Pile construction method for underwater - Google Patents

Pile construction method for underwater Download PDF

Info

Publication number
KR20240045647A
KR20240045647A KR1020220125218A KR20220125218A KR20240045647A KR 20240045647 A KR20240045647 A KR 20240045647A KR 1020220125218 A KR1020220125218 A KR 1020220125218A KR 20220125218 A KR20220125218 A KR 20220125218A KR 20240045647 A KR20240045647 A KR 20240045647A
Authority
KR
South Korea
Prior art keywords
exterior
grouting
inner pipe
filler
gap
Prior art date
Application number
KR1020220125218A
Other languages
Korean (ko)
Inventor
한택희
구정민
정충열
김성환
Original Assignee
(주)동명기술공단종합건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)동명기술공단종합건축사사무소 filed Critical (주)동명기술공단종합건축사사무소
Priority to KR1020220125218A priority Critical patent/KR20240045647A/en
Publication of KR20240045647A publication Critical patent/KR20240045647A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 발명은 해상용 말뚝 시공방법에 관한 것으로, 더욱 상세하게는 외관을 굴착기에 케이싱시키는 외관케이싱단계, 외관이 케이싱된 상태에서 굴착기를 이용하여 수중 암반을 굴착하는 굴착단계, 수중 암반에 굴착이 완료된 후, 상기 외관이 위치된 상태에서 굴착기를 제거하는 굴착기제거단계, 굴착기가 제거된 상기 외관의 내부에 내관을 삽입시키는 내관 삽입단계, 및 상기 내관과 외관 내부, 외관과 암반 사이에 충진재를 충진시키는 그라우팅단계,를 포함한다.
상기와 같은 본 발명에 의하면, 종래 물막이 등을 이용하여 물을 막지 않고, 수중 암반에 말뚝을 견고하게 시공할 수 있어 작업시간과 비용을 절감시킬 수 있다.
The present invention relates to a method of constructing offshore piles, and more specifically, an exterior casing step of casing the exterior in an excavator, an excavation step of excavating underwater rock using an excavator with the exterior cased, and excavation completed in underwater rock. Afterwards, an excavator removal step of removing the excavator with the exterior in place, an inner pipe insertion step of inserting an inner pipe into the interior of the exterior from which the excavator has been removed, and filling a filler between the inner pipe and the exterior, and between the exterior and the rock. Includes grouting step.
According to the present invention as described above, it is possible to firmly construct piles in underwater rock without blocking water using conventional water barriers, etc., thereby reducing work time and costs.

Description

해상용 말뚝 시공방법{Pile construction method for underwater}Pile construction method for offshore {Pile construction method for underwater}

본 특허 출원은 국토교통부 "기후변화 적응형 다목적 국토확장 기술 개발(과제번호 22CTAP-C164018-02)" 사업의 연구비 지원으로 수행되었습니다.This patent application was carried out with the support of research funds from the Ministry of Land, Infrastructure and Transport's "Climate Change Adaptive Multipurpose Land Expansion Technology Development (Project No. 22CTAP-C164018-02)" project.

본 발명은 말뚝 시공방법에 관한 것으로, 더욱 상세하게는 종래 물막이 등을 이용하여 물을 막지 않고, 수중 암반에 말뚝을 견고하게 시공할 수 있어 작업시간과 비용을 절감시킬 수 있는 해상용 말뚝 시공방법에 관한 것이다.The present invention relates to a pile construction method, and more specifically, to a maritime pile construction method that can firmly construct piles in underwater rock without blocking water using conventional water barriers, etc., thereby reducing work time and costs. It's about.

일반적으로, 수중 교각을 시공하는 방법으로서, 우물통 공법이 있다. 이 기술은, 교각이 설치될 위치의 수면 위로 우물통 본체를 이송시킨 다음, 이송된 우물통 본체를 물속에 빠트려 해저 지반에 가라앉힌다.Generally, as a method of constructing an underwater pier, there is a well construction method. This technology transports the well body to the surface of the water at the location where the pier is to be installed, then drops the transported well body into the water and sinks it to the seafloor.

그리고 우물통 본체 내부의 지반을 암반층까지 굴착하여 우물통 본체를 해저 암반층에 침하시킨 후, 우물통 본체의 내부에 거푸집을 설치하고, 설치된 거푸집에 콘트리트를 타설 및 양생하여 교각을 시공하는 기술이다.It is a technology to construct a pier by excavating the ground inside the well body to the rock layer, sinking the well body into the seabed rock layer, then installing a form inside the well body, and pouring and curing concrete on the installed form.

그런데 이러한 종래의 우물통 공법은 등록특허 10-1154623호에 개진된 바와 같이, 중량체이고 길이가 긴 우물통 본체를 통째로 다루어야 하므로, 대규모의 중장비와 많은 작업인원이 필요하다는 단점이 있다.However, as disclosed in Registered Patent No. 10-1154623, this conventional well barrel construction method has the disadvantage of requiring large-scale heavy equipment and a large number of workers because the entire well body, which is heavy and long, must be handled.

특히, 이러한 단점 때문에 시공하기가 매우 어렵고 안전사고의 우려가 있으며, 많은 시공비용이 소요되고, 긴 시공기간이 필요하다는 문제점이 지적되고 있다.In particular, due to these disadvantages, problems have been pointed out that it is very difficult to construct, there is a risk of safety accidents, high construction costs are required, and a long construction period is required.

즉, 우물통 공법은, 중량체이고 길이가 긴 우물통 본체를 해상의 수면위로 통째로 옮겨야 하고, 이를 통째로 들어올려야 하므로, 작업하기가 매우 어렵고 힘들며 안전사고의 우려마저 있다는 단점이 있다.In other words, the well barrel method has the disadvantage of having to move the heavy and long body of the well to the surface of the sea and lift it as a whole, making it very difficult and difficult to work with, and even raising the risk of safety accidents.

특히, 무겁고 긴 길이의 우물통 본체를 다루기 위해 대형의 바지선, 대형의 해상 크레인 등이 필요하고, 이를 운용하기 위해서는 많은 작업인력이 필요하다는 단점이 있다. 따라서, 종래의 우물통 공법은, 시공하기가 매 우 어렵고 힘들 뿐만 아니라, 많은 시공비용과 많은 노동력이 소요되며, 시공기간도 연장된다는 문제점이 지적되고 있다.In particular, there is a disadvantage that large barges and large offshore cranes are needed to handle the heavy and long well body, and that a large number of workers are required to operate them. Therefore, the conventional well construction method is not only very difficult and difficult to construct, but also requires a lot of construction cost and labor, and has the problem of extending the construction period.

이에 본 발명은 상기와 같은 문제점들을 해소하기 위해 안출된 것으로써, 외관을 굴착기에 케이싱시키는 외관케이싱단계, 외관이 케이싱된 상태에서 굴착기를 이용하여 수중 암반을 굴착하는 굴착단계, 수중 암반에 굴착이 완료된 후, 상기 외관이 위치된 상태에서 굴착기를 제거하는 굴착기제거단계, 굴착기가 제거된 상기 외관의 내부에 내관을 삽입시키는 내관 삽입단계, 및 상기 내관과 외관 내부, 외관과 암반 사이에 충진재를 충진시키는 그라우팅단계,를 포함하여 종래 물막이 등을 이용하여 물을 막지 않고, 수중 암반에 말뚝을 견고하게 시공할 수 있어 작업시간과 비용을 절감시킬 수 있는 해상용 말뚝 시공방법을 제공하는 것이 목적이다.Accordingly, the present invention was created to solve the above problems, including an exterior casing step of casing the exterior in an excavator, an excavation step of excavating underwater rock using an excavator while the exterior is cased, and excavation in underwater rock. After completion, an excavator removal step of removing the excavator with the exterior in place, an inner pipe insertion step of inserting an inner pipe into the interior of the exterior from which the excavator has been removed, and filling a filler between the inner pipe and the exterior, and between the exterior and the rock. The purpose is to provide a maritime pile construction method that can firmly construct piles in underwater rock without blocking water using conventional water barriers, including the grouting step, thereby reducing work time and costs.

상기 목적을 이루기 위한 본 발명은, 외관을 굴착기에 케이싱시키는 외관케이싱단계, 외관이 케이싱된 상태에서 굴착기를 이용하여 수중 암반을 굴착하는 굴착단계, 수중 암반에 굴착이 완료된 후, 상기 외관이 위치된 상태에서 굴착기를 제거하는 굴착기제거단계, 굴착기가 제거된 상기 외관의 내부에 내관을 삽입시키는 내관 삽입단계, 및 상기 내관과 외관 내부, 외관과 암반 사이에 충진재를 충진시키는 그라우팅단계,를 포함한다.The present invention for achieving the above object includes an exterior casing step of casing the exterior in an excavator, an excavation step of excavating underwater rock using an excavator while the exterior is cased, and after excavation in the underwater rock is completed, the exterior is located. It includes an excavator removal step of removing the excavator from the state, an inner pipe insertion step of inserting an inner pipe into the interior of the exterior from which the excavator has been removed, and a grouting step of filling a filler between the inner pipe and the exterior, and between the exterior and the rock.

바람직하게, 상기 굴착기는 소구경 헤머를 포함하며, 소구경 해머는 직경 450 ~ 1,500mm이다.Preferably, the excavator includes a small diameter hammer, and the small diameter hammer has a diameter of 450 to 1,500 mm.

그리고 상기 외관과 내관은 강관으로, 내관의 직경은 800 ~ 824mm이고, 외관의 직경은 1000 ~ 1026mm이다.And the outer and inner pipes are steel pipes, and the diameter of the inner pipe is 800 to 824 mm, and the diameter of the outer pipe is 1000 to 1026 mm.

또한, 상기 내관 삽입단계 전에, 외관과의 간격을 유지하기 위해 복수의 간격유지부를 내관에 일정 간격으로 설치하는 간격유지부 설치단계, 및 상기 내관의 전단파괴를 방지하도록 복수의 전단키를 내관 외면에 설치하는 전단키 설치단계,를 더 포함한다.In addition, before the step of inserting the inner tube, a gap maintenance part installation step of installing a plurality of gap maintenance parts at regular intervals on the inner tube to maintain the gap with the outer tube, and a plurality of shear keys are placed on the outer surface of the inner tube to prevent shear failure of the inner tube. It further includes a leaflet key installation step.

그리고 상기 내관의 외주면을 따라, 나사산이 형성되고, 상기 간격유지부 설치단계의 간격유지부는, 상기 나사산에 결합되는 하단몸체, 상기 하단몸체의 상측으로 일정간격 이격되어 상기 나사산에 결합되는 상단몸체, 탄성을 갖고, 상기 하단몸체와 상단몸체를 연결하며 하단몸체와 상단몸체의 간격이 좁아질 경우, 중앙부가 외측으로 돌출되어 상기 외관의 내면에 닿아 간격을 유지시키는 간격유지바, 및 탄성을 갖고, 상기 간격유지바의 내측에 구비되어 간격유지바의 중앙부가 외측으로 돌출될 경우, 반대로 중앙부가 내측으로 돌출되어 돌출된 간격유지바를 지지하기 위한 간격지지부,를 포함한다.And along the outer peripheral surface of the inner tube, a screw thread is formed, and the space maintaining part in the space maintaining part installation step includes a lower body coupled to the screw thread, an upper body spaced at a certain distance above the lower body and coupled to the screw thread, A gap maintenance bar that has elasticity, connects the lower body and the upper body, and when the gap between the lower body and the upper body narrows, the central part protrudes outward and touches the inner surface of the exterior to maintain the gap, and has elasticity, It is provided inside the gap maintenance bar, and when the central part of the gap maintenance bar protrudes outward, on the contrary, the central part protrudes inward and includes a gap support part for supporting the protruding gap maintenance bar.

또한, 상기 그라우팅단계는, 상기 굴착된 암반의 높이까지 충진재를 충진시키는 제1그라우팅단계, 및 상기 내관과 외관의 상단부까지 충진재를 충진시키는 제2그라우팅단계,를 포함한다.In addition, the grouting step includes a first grouting step of filling the filler to the height of the excavated bedrock, and a second grouting step of filling the filler to the top of the inner pipe and the outer pipe.

그리고 상기 내관의 내부에 구비되는 그라우팅주입관, 상기 내관과 외관의 각 내부 압력을 조절하기 위한 압력조절부, 상기 내관의 하단부를 따라 복수 형성된 제1그라우팅이송공, 및 상기 외관의 하단부를 따라 복수 형성된 제2그라우팅이송공,을 더 포함한다.And a grouting injection pipe provided inside the inner pipe, a pressure regulator for controlling each internal pressure of the inner pipe and the outer pipe, a plurality of first grouting transfer holes formed along the lower end of the inner pipe, and a plurality of first grouting transfer holes along the lower end of the outer pipe. It further includes a formed second grouting transfer hole.

또한, 상기 제1그라우팅단계는, 상기 그라우팅주입관을 통해 충진재를 내관 하단부로 충진시키는 제1충진재주입단계, 상기 제1충진재주입단계 시, 충진재가 상기 암반의 높이 이하로 유지되도록 상기 압력조절부에 의해 내관의 내부 압력을 일정 압력으로 유지함에 따라, 지속적으로 공급되는 충진재가 상기 제1그라우팅이송공을 통해 내관과 외관 사이로 충진시키는 내부압력유지단계, 및 상기 압력조절부에 의해 내관과 외관 사이 압력을 일정 압력으로 유지하여 내관과 외관 사이로 충진되는 높이를 암반의 높이 이하로 유지시키며, 지속적으로 공급되는 충진재가 상기 제2그라우팅이송공을 통해 외관과 암반 사이로 충진시키는 외부압력유지단계,를 포함한다.In addition, the first grouting step is a first filler injection step of filling the lower part of the inner pipe with the filler through the grouting injection pipe, and the pressure regulator so that the filler is maintained below the height of the bedrock during the first filler injection step. As the internal pressure of the inner tube is maintained at a constant pressure, the continuously supplied filler is filled between the inner tube and the outer tube through the first grouting transfer hole, and the pressure control unit maintains the internal pressure between the inner tube and the outer tube. Including an external pressure maintenance step in which the pressure is maintained at a constant pressure to maintain the filling height between the inner pipe and the exterior below the height of the rock, and the continuously supplied filler fills the space between the exterior and the rock through the second grouting transfer hole. do.

본 발명에 의한 해상용 말뚝 시공방법에 의하면, 종래 물막이 등을 이용하여 물을 막지 않고, 수중 암반에 말뚝을 견고하게 시공할 수 있어 작업시간과 비용을 절감시킬 수 있게 하는 매우 유용하고 효과적인 발명이다.According to the maritime pile construction method according to the present invention, it is a very useful and effective invention that allows the piles to be firmly constructed in the underwater rock without blocking water using conventional water barriers, etc., thereby reducing work time and costs. .

도 1은 본 발명에 따른 해상용 말뚝 시공방법을 도시한 도면이고,
도 2는 본 발명에 따른 수중 암반에 설치된 말뚝을 도시한 도면이며,
도 3은 본 발명에 따른 해상용 말뚝 시공방법의 다른 실시 예를 도시한 도면이고,
도 4는 본 발명에 따른 간격유지부를 도시한 도면이며,
도 5는 본 발명에 따른 그라우팅단계를 도시한 도면이고,
도 6은 본 발명에 따른 그라우팅단계의 충진재 주입위치를 도시한 도면이며,
도 7은 본 발명에 따른 제1그라우팅단계를 도시한 도면이다.
1 is a diagram showing a method of constructing a maritime pile according to the present invention;
Figure 2 is a diagram showing a pile installed in underwater rock according to the present invention,
Figure 3 is a diagram showing another embodiment of the maritime pile construction method according to the present invention,
Figure 4 is a diagram showing a gap maintenance part according to the present invention;
Figure 5 is a diagram showing the grouting step according to the present invention,
Figure 6 is a diagram showing the filler injection position in the grouting step according to the present invention;
Figure 7 is a diagram showing the first grouting step according to the present invention.

이하, 본 발명에 따른 바람직한 실시 형태를 첨부된 도면을 참조하여 상세하게 설명한다. 첨부된 도면과 함께 이하에 개시될 상세한 설명은 본 발명의 예시적인 실시형태를 설명하고자 하는 것이며, 본 발명이 실시될 수 있는 유일한 실시형태를 나타내고자 하는 것이 아니다. 이하의 상세한 설명은 본 발명의 완전한 이해를 제공하기 위해서 구체적 세부사항을 포함한다. 그러나, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자는 본 발명이 이러한 구체적 세부사항 없이도 실시될 수 있음을 안다.Hereinafter, preferred embodiments according to the present invention will be described in detail with reference to the attached drawings. The detailed description set forth below in conjunction with the accompanying drawings is intended to illustrate exemplary embodiments of the invention and is not intended to represent the only embodiments in which the invention may be practiced. The following detailed description includes specific details to provide a thorough understanding of the invention. However, those skilled in the art will recognize that the present invention may be practiced without these specific details.

몇몇 경우, 본 발명의 개념이 모호해지는 것을 피하기 위하여 공지의 구조 및 장치는 생략되거나, 각 구조 및 장치의 핵심기능을 중심으로 한 블록도 형식으로 도시될 수 있다.In some cases, in order to avoid ambiguity of the concept of the present invention, well-known structures and devices may be omitted or may be shown in block diagram form focusing on the core functions of each structure and device.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함(comprising 또는 including)"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다. 또한, 명세서에 기재된 "…부"의 용어는 적어도 하나의 기능이나 동작을 처리하는 단위를 의미한다. 또한, "일(a 또는 an)", "하나(one)", "그(the)" 및 유사 관련어는 본 발명을 기술하는 문맥에 있어서(특히, 이하의 청구항의 문맥에서) 본 명세서에 달리 지시되거나 문맥에 의해 분명하게 반박되지 않는 한, 단수 및 복수 모두를 포함하는 의미로 사용될 수 있다.Throughout the specification, when a part is said to “comprise or include” a certain element, this means that it does not exclude other elements but may further include other elements, unless specifically stated to the contrary. do. Additionally, the term “… unit” used in the specification refers to a unit that processes at least one function or operation. In addition, the terms "a or an", "one", "the", and similar related terms are used in the context of describing the invention (particularly in the context of the claims below) as used herein. It may be used in both singular and plural terms, unless indicated otherwise or clearly contradicted by context.

본 발명의 실시예들을 설명함에 있어서 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명을 생략할 것이다. 그리고 후술되는 용어들은 본 발명의 실시예에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In describing embodiments of the present invention, if a detailed description of a known function or configuration is judged to unnecessarily obscure the gist of the present invention, the detailed description will be omitted. The terms described below are terms defined in consideration of functions in the embodiments of the present invention, and may vary depending on the intention or custom of the user or operator. Therefore, the definition should be made based on the contents throughout this specification.

이하, 본 발명의 바람직한 실시 예를 첨부된 도면을 참조하여 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the attached drawings.

도 1은 본 발명에 따른 해상용 말뚝 시공방법을 도시한 도면이고, 도 2는 본 발명에 따른 수중 암반에 설치된 말뚝을 도시한 도면이며, 도 3은 본 발명에 따른 해상용 말뚝 시공방법의 다른 실시 예를 도시한 도면이고, 도 4는 본 발명에 따른 간격유지부를 도시한 도면이며, 도 5는 본 발명에 따른 그라우팅단계를 도시한 도면이고, 도 6은 본 발명에 따른 그라우팅단계의 충진재 주입위치를 도시한 도면이며, 도 7은 본 발명에 따른 제1그라우팅단계를 도시한 도면이다.Figure 1 is a diagram showing a maritime pile construction method according to the present invention, Figure 2 is a diagram showing a pile installed in underwater rock according to the present invention, and Figure 3 is another diagram of the maritime pile construction method according to the present invention. It is a drawing showing an embodiment, Figure 4 is a drawing showing a gap maintenance part according to the present invention, Figure 5 is a drawing showing a grouting step according to the present invention, and Figure 6 is a drawing showing filler injection in the grouting step according to the present invention. It is a drawing showing the location, and Figure 7 is a drawing showing the first grouting step according to the present invention.

도면에서 도시한 바와 같이, 해상용 말뚝 시공방법은 외관케이싱단계(S10)와 굴착단계(S20), 굴착기제거단계(S30), 내관 삽입단계(S40) 및 그라우팅단계(S50)를 포함한다.As shown in the drawing, the offshore pile construction method includes an exterior casing step (S10), an excavation step (S20), an excavator removal step (S30), an inner pipe insertion step (S40), and a grouting step (S50).

외관케이싱단계(S10)는 외관(100)을 굴착기에 케이싱시킨다.In the exterior casing step (S10), the exterior 100 is cased in an excavator.

그리고 굴착단계(S20)는 외관(100)이 케이싱된 상태에서 굴착기를 이용하여 수중 암반(2)을 굴착한다.And in the excavation step (S20), the underwater rock mass (2) is excavated using an excavator while the exterior (100) is cased.

이 굴착단계(S20) 시, 수중 암반을 굴착함과 동시에, 외관(100)을 암반의 굴착공에 삽입시킨다.In this excavation step (S20), the underwater rock is excavated and the outer shell 100 is inserted into the excavation hole of the rock.

굴착기제거단계(S30)는 수중 암반에 굴착이 완료된 후, 외관(100)이 위치된 상태에서 굴착기를 제거한다.In the excavator removal step (S30), after excavation in the underwater rock is completed, the excavator is removed with the exterior 100 in place.

또한 내관 삽입단계(S40)는 굴착기가 제거된 외관(100)의 내부에 내관(200)을 삽입시킨다.Additionally, in the inner tube insertion step (S40), the inner tube 200 is inserted into the exterior 100 from which the excavator has been removed.

그라우팅단계(S50)는 내관(200)과 외관(100) 내부, 외관(100)과 암반 사이에 충진재(300)를 충진시킨다.In the grouting step (S50), filler 300 is filled between the inner pipe 200 and the exterior 100, and between the exterior 100 and the rock.

이에, 도 2에서 도시한 바와 같이, 종래 물막이 등을 이용하여 물을 막지 않고, 수중 암반에 말뚝을 견고하게 시공할 수 있다.Accordingly, as shown in FIG. 2, piles can be firmly constructed in underwater rock without blocking water using conventional water barriers, etc.

여기서, 굴착기는 소구경 헤머를 포함하며, 소구경 해머는 직경 450 ~ 1,500mm를 사용한다.Here, the excavator includes a small diameter hammer, and the small diameter hammer uses a diameter of 450 to 1,500 mm.

외관(100)과 내관(200)은 강관으로 제작된다.The exterior 100 and the inner pipe 200 are made of steel pipe.

그리고 내관(200)의 직경은 800 ~ 824mm이며, 일 실시 예로 812mm로 제작되고, 외관(100)의 직경은 1000 ~ 1026mm이며, 일 실시 예로 1013mm로 제작된다.The diameter of the inner tube 200 is 800 to 824 mm, in one embodiment, 812 mm, and the outer tube 100 has a diameter of 1,000 to 1,026 mm, in one embodiment, 1013 mm.

또한 해상용 말뚝 시공방법은 도 3에서 도시한 바와 같이, 간격유지부 설치단계(S60)와 전단키 설치단계(S70)를 더 포함한다.In addition, as shown in FIG. 3, the offshore pile construction method further includes a gap maintenance part installation step (S60) and a shear key installation step (S70).

간격유지부 설치단계(S60)는 내관 삽입단계(S40) 전에, 외관(100)과의 간격을 유지하기 위해 복수의 간격유지부(400)를 내관(200)에 일정 간격으로 설치한다.In the gap maintenance unit installation step (S60), before the inner pipe insertion step (S40), a plurality of gap maintenance units (400) are installed on the inner pipe (200) at regular intervals in order to maintain the gap with the outer tube (100).

그리고 전단키 설치단계(S70)는 내관(200)의 전단파괴를 방지하도록 복수의 전단키(500)를 내관 외면에 설치한다.And in the shear key installation step (S70), a plurality of shear keys 500 are installed on the outer surface of the inner pipe 200 to prevent shear failure of the inner pipe 200.

이를 위한 내관(200)의 외주면을 따라 나사산(210)이 형성된다.For this purpose, a screw thread 210 is formed along the outer peripheral surface of the inner tube 200.

그리고 간격유지부(400)는 도 4에서 도시한 바와 같이, 하단몸체(410)와 상단몸체(420), 간격유지바(430) 및 간격지지부(440)를 포함한다.And, as shown in FIG. 4, the gap maintenance part 400 includes a lower body 410, an upper body 420, a gap maintenance bar 430, and a gap supporter 440.

하단몸체(410)는 나사산에 결합된다.The lower body 410 is coupled to the screw thread.

또한 상단몸체(420)은 하단몸체(410)의 상측으로 일정간격 이격되어 나사산에 결합된다.In addition, the upper body 420 is spaced apart from the upper side of the lower body 410 at regular intervals and is coupled to the screw thread.

간격유지바(430)는 탄성을 갖고, 하단몸체(410)와 상단몸체(420)를 연결하며 하단몸체(410)와 상단몸체(420)의 간격이 좁아질 경우, 중앙부가 외측으로 돌출되어 외관(100)의 내면에 닿아 간격을 유지시킨다.The gap maintenance bar 430 has elasticity and connects the lower body 410 and the upper body 420. When the gap between the lower body 410 and the upper body 420 narrows, the central part protrudes outward to give an external appearance. It touches the inner surface of (100) and maintains the gap.

그리고 간격지지부(440)는 탄성을 갖고, 간격유지바(430)의 내측에 구비되어 간격유지바(430)의 중앙부가 외측으로 돌출될 경우, 반대로 중앙부가 내측으로 돌출되어 돌출된 간격유지바(430)를 지지한다.And the gap support part 440 has elasticity and is provided on the inside of the gap maintenance bar 430, so that when the central part of the gap maintenance bar 430 protrudes outward, on the contrary, the central part protrudes inward and the protruding gap maintenance bar ( 430).

이에, 내관(200)과 외관(100)의 간격을 유지시킬 수 있다.Accordingly, the gap between the inner tube 200 and the outer tube 100 can be maintained.

또한 그라우팅단계(S50)는 도 5 내지 도 6에서 도시한 바와 같이, 제1그라우팅단계(S51)와 제2그라우팅단계(S52)를 포함한다.Additionally, the grouting step (S50) includes a first grouting step (S51) and a second grouting step (S52), as shown in FIGS. 5 and 6.

제1그라우팅단계(S51)는 굴착된 암반의 높이까지 충진재(300)를 충진시킨다.In the first grouting step (S51), the filler 300 is filled to the height of the excavated bedrock.

그리고 제2그라우팅단계(S52)는 내관(200)과 외관(100)의 상단부까지 충진재(300)를 충진시킨다.And in the second grouting step (S52), the filler 300 is filled to the top of the inner pipe 200 and the outer pipe 100.

이를 위해, 그라우팅주입관(600)과 압력조절부(610), 제1그라우팅이송공(620) 및 제2그라우팅이송공(630)을 더 포함한다.For this purpose, it further includes a grouting injection pipe 600, a pressure regulator 610, a first grouting transfer hole 620, and a second grouting transfer hole 630.

그라우팅주입관(600)은 내관(200)의 내부에 구비되는 것으로, 하단부가 내관(200)의 저면부에 인접하게 구비된다.The grouting injection pipe 600 is provided inside the inner pipe 200, and its lower end is provided adjacent to the bottom of the inner pipe 200.

그리고 압력조절부(610)는 내관(200)과 외관(100)의 각 내부 압력을 조절하기 위해 구비된다.And the pressure control unit 610 is provided to adjust the internal pressures of the inner tube 200 and the outer tube 100.

제1그라우팅이송공(620)은 내관(200)의 하단부를 따라 복수 형성된다.A plurality of first grouting transfer holes 620 are formed along the lower end of the inner pipe 200.

또한 제2그라우팅이송공(630)은 외관(100)의 하단부를 따라 복수 형성된다.In addition, a plurality of second grouting transfer holes 630 are formed along the lower end of the exterior 100.

여기서, 제1그라우팅단계(S51)는 도 7에서 도시한 바와 같이, 제1충진재주입단계(S511)와 내부압력유지단계(S512) 및 외부압력유지단계(S513)를 포함한다.Here, the first grouting step (S51) includes a first filling re-injection step (S511), an internal pressure maintaining step (S512), and an external pressure maintaining step (S513), as shown in FIG. 7.

제1충진재주입단계(S511)는 그라우팅주입관(600)을 통해 충진재(300)를 내관(200) 하단부로 충진시킨다.In the first filler injection step (S511), the filler 300 is filled into the lower part of the inner pipe 200 through the grouting injection pipe 600.

그리고 내부압력유지단계(S512)는 제1충진재주입단계(S511) 시, 충진재(300)가 암반(2)의 높이 이하로 유지되도록 압력조절부(610)에 의해 내관(200)의 내부 압력을 일정 압력으로 유지한다.And, in the internal pressure maintenance step (S512), the internal pressure of the inner pipe 200 is adjusted by the pressure regulator 610 so that the filler 300 is maintained below the height of the rock 2 during the first filler injection step (S511). Maintain at a constant pressure.

이에, 지속적으로 공급되는 충진재(300)가 제1그라우팅이송공(620)을 통해 내관(200)과 외관(100) 사이로 충진시킨다.Accordingly, the continuously supplied filler 300 is filled between the inner pipe 200 and the outer pipe 100 through the first grouting transfer hole 620.

외부압력유지단계(S513)는 압력조절부(610)에 의해 내관(200)과 외관(100) 사이 압력을 일정 압력으로 유지하여 내관(200)과 외관(100) 사이로 충진되는 높이를 암반(2)의 높이 이하로 유지시킨다.In the external pressure maintenance step (S513), the pressure between the inner tube 200 and the outer tube 100 is maintained at a constant pressure by the pressure regulator 610, and the height filled between the inner tube 200 and the outer tube 100 is adjusted to the rock mass (2). ) is maintained below the height.

그리고 지속적으로 공급되는 충진재(300)가 제2그라우팅이송공(630)을 통해 외관(100)과 암반(2) 사이로 충진시킨다.And the continuously supplied filler 300 fills the space between the exterior 100 and the bedrock 2 through the second grouting transfer hole 630.

이러한 제1그라우팅단계(S51)를 통해 충진된 충진재(300)가 응고된 후, 제2그라우팅단계(S52)를 통해 내관(200)과 외관(100)의 내부가 충진재로 완전히 충진되어 응고됨에 따라, 말뚝 설치가 마무리된다.After the filler 300 filled through this first grouting step (S51) is solidified, the interior of the inner pipe 200 and the exterior 100 is completely filled with the filler and solidified through the second grouting step (S52). , pile installation is completed.

이 제2그라우팅단계(S52)에서 채워지는 충진재의 높이는 외관(100)의 직경보다 5배 이상의 높이로 충진됨이 바람직하다.It is preferable that the height of the filler filled in this second grouting step (S52) is 5 times or more than the diameter of the exterior 100.

100 : 외관 200 : 내관
300 : 충진재 400 : 간격유지부
500 : 전단키 600: 그라우팅주입관
610 : 압력조절부 620 : 제1그라우팅이송공
630 : 제2그라우팅이송공
100: exterior 200: interior
300: Filler 400: Gap maintenance part
500: Shear key 600: Grouting injection pipe
610: Pressure regulator 620: First grouting transfer hole
630: 2nd grouting transfer hole

Claims (5)

외관을 굴착기에 케이싱시키는 외관케이싱단계;
외관이 케이싱된 상태에서 굴착기를 이용하여 수중 암반을 굴착하는 굴착단계;
수중 암반에 굴착이 완료된 후, 상기 외관이 위치된 상태에서 굴착기를 제거하는 굴착기제거단계;
굴착기가 제거된 상기 외관의 내부에 내관을 삽입시키는 내관 삽입단계; 및
상기 내관과 외관 내부, 외관과 암반 사이에 충진재를 충진시키는 그라우팅단계;를 포함하는 해상용 말뚝 시공방법.
An exterior casing step of casing the exterior to the excavator;
An excavation step of excavating underwater rock using an excavator while the exterior is cased;
After excavation in the underwater rock is completed, an excavator removal step of removing the excavator while the exterior is located;
An inner pipe insertion step of inserting an inner pipe into the interior of the exterior from which the excavator has been removed; and
A method of constructing offshore piles comprising a grouting step of filling a filler between the inner pipe and the outer pipe and the outer shell and the bedrock.
제1항에 있어서,
상기 내관 삽입단계 전에, 외관과의 간격을 유지하기 위해 복수의 간격유지부를 내관에 일정 간격으로 설치하는 간격유지부 설치단계; 및
상기 내관의 전단파괴를 방지하도록 복수의 전단키를 내관 외면에 설치하는 전단키 설치단계;를 더 포함하는 해상용 말뚝 시공방법.
According to paragraph 1,
Before the inner tube insertion step, a gap maintenance unit installation step of installing a plurality of gap maintenance units at regular intervals in the inner tube to maintain the gap with the outer tube; and
A maritime pile construction method further comprising a shear key installation step of installing a plurality of shear keys on the outer surface of the inner pipe to prevent shear failure of the inner pipe.
제2항에 있어서,
상기 내관의 외주면을 따라, 나사산이 형성되고,
상기 간격유지부 설치단계의 간격유지부는,
상기 나사산에 결합되는 하단몸체;
상기 하단몸체의 상측으로 일정간격 이격되어 상기 나사산에 결합되는 상단몸체;
탄성을 갖고, 상기 하단몸체와 상단몸체를 연결하며 하단몸체와 상단몸체의 간격이 좁아질 경우, 중앙부가 외측으로 돌출되어 상기 외관의 내면에 닿아 간격을 유지시키는 간격유지바; 및
탄성을 갖고, 상기 간격유지바의 내측에 구비되어 간격유지바의 중앙부가 외측으로 돌출될 경우, 반대로 중앙부가 내측으로 돌출되어 돌출된 간격유지바를 지지하기 위한 간격지지부;를 포함하는 해상용 말뚝 시공방법.
According to paragraph 2,
A thread is formed along the outer peripheral surface of the inner tube,
The gap maintenance part in the gap maintenance installation step is,
a lower body coupled to the screw thread;
an upper body spaced at a certain distance above the lower body and coupled to the screw thread;
A gap maintenance bar that has elasticity, connects the lower body and the upper body, and when the gap between the lower body and the upper body narrows, the central part protrudes outward and touches the inner surface of the exterior to maintain the gap; and
It has elasticity, and is provided on the inside of the gap maintenance bar, so that when the central part of the gap maintenance bar protrudes outward, on the contrary, the central part protrudes inward to support the protruding gap maintenance bar. Construction of offshore piles including a gap support part. method.
제1항에 있어서, 상기 그라우팅단계는,
상기 굴착된 암반의 높이까지 충진재를 충진시키는 제1그라우팅단계; 및
상기 내관과 외관의 상단부까지 충진재를 충진시키는 제2그라우팅단계;를 포함하는 해상용 말뚝 시공방법.
The method of claim 1, wherein the grouting step is:
A first grouting step of filling filler material to the height of the excavated bedrock; and
A maritime pile construction method comprising a second grouting step of filling the inner pipe and the upper part of the exterior with filler.
제4항에 있어서,
상기 내관의 내부에 구비되는 그라우팅주입관;
상기 내관과 외관의 각 내부 압력을 조절하기 위한 압력조절부;
상기 내관의 하단부를 따라 복수 형성된 제1그라우팅이송공; 및
상기 외관의 하단부를 따라 복수 형성된 제2그라우팅이송공;을 더 포함하고,
상기 제1그라우팅단계는,
상기 그라우팅주입관을 통해 충진재를 내관 하단부로 충진시키는 제1충진재주입단계;
상기 제1충진재주입단계 시, 충진재가 상기 암반의 높이 이하로 유지되도록 상기 압력조절부에 의해 내관의 내부 압력을 일정 압력으로 유지함에 따라, 지속적으로 공급되는 충진재가 상기 제1그라우팅이송공을 통해 내관과 외관 사이로 충진시키는 내부압력유지단계; 및
상기 압력조절부에 의해 내관과 외관 사이 압력을 일정 압력으로 유지하여 내관과 외관 사이로 충진되는 높이를 암반의 높이 이하로 유지시키며, 지속적으로 공급되는 충진재가 상기 제2그라우팅이송공을 통해 외관과 암반 사이로 충진시키는 외부압력유지단계;를 포함하는 해상용 말뚝 시공방법.
According to clause 4,
A grouting injection pipe provided inside the inner pipe;
A pressure control unit for controlling the internal pressure of the inner tube and the outer tube;
A plurality of first grouting transfer holes formed along the lower end of the inner pipe; and
It further includes; a plurality of second grouting transfer holes formed along the lower end of the exterior,
The first grouting step is,
A first filler injection step of filling the lower part of the inner pipe with the filler through the grouting injection pipe;
During the first filler injection step, the internal pressure of the inner pipe is maintained at a constant pressure by the pressure control unit so that the filler is maintained below the height of the rock, so that the filler continuously supplied is fed through the first grouting transfer hole. An internal pressure maintenance step of filling between the inner tube and the outer tube; and
The pressure between the inner pipe and the exterior is maintained at a constant pressure by the pressure control unit to maintain the filling height between the inner pipe and the exterior below the height of the rock, and the continuously supplied filler is connected to the exterior and the rock through the second grouting transfer hole. A maritime pile construction method including the step of maintaining external pressure by filling the gap.
KR1020220125218A 2022-09-30 2022-09-30 Pile construction method for underwater KR20240045647A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220125218A KR20240045647A (en) 2022-09-30 2022-09-30 Pile construction method for underwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220125218A KR20240045647A (en) 2022-09-30 2022-09-30 Pile construction method for underwater

Publications (1)

Publication Number Publication Date
KR20240045647A true KR20240045647A (en) 2024-04-08

Family

ID=90715434

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220125218A KR20240045647A (en) 2022-09-30 2022-09-30 Pile construction method for underwater

Country Status (1)

Country Link
KR (1) KR20240045647A (en)

Similar Documents

Publication Publication Date Title
US10138616B2 (en) Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
JP6830748B2 (en) Open caisson construction structure and its construction method
US9567720B2 (en) Offshore platform for a marine environment
CN104452829A (en) Piled raft foundation anti-floating structure and construction method
CN110735600A (en) mechanical hole-forming pile construction process for karst geology
CN104074197B (en) The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure
KR20100065521A (en) A shoring method using arch plate pile and h-pile
CN114482099A (en) Steel sheet pile cofferdam construction method
CN101392521A (en) Rock-socketed steel dock structure and construction method thereof
JP5204063B2 (en) Box foundation construction method in open shield method
CN101748735A (en) Foundation ditch excavation method for reducing pile deflection in soft soil area
KR20240045647A (en) Pile construction method for underwater
JP2010209645A (en) Foundation pile structure and construction method for the foundation pile
JP6384768B2 (en) Precast concrete product with displacement recovery structure
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
KR101745363B1 (en) complex Temporary utility and its construction Method
KR102337545B1 (en) Underground retaining wall using concrete pile and soil retaining plate
CN204326119U (en) A kind of pile-raft foundation float Structure
KR20130002797A (en) Reinforced concrete pile construction method for which steel pipe casing structure for steel pipe casing recovery this were used
JP4911242B2 (en) Reinforcement structure of existing gravity quay
JP2010059622A (en) Underground structure and method for constructing the same
KR101862761B1 (en) the method of constructing underground basic structure
CN205636749U (en) A excavation supporting system for sandy gravel boulder geological stratification
CN212714970U (en) Cast-in-situ bored pile steel protects a stabilising arrangement
JP2008184889A (en) Caisson construction method combined with guide hole method for constructing underground structure