KR20230136576A - Combined guide unit for sheet pile construction and construction method of sheet pile using it. - Google Patents

Combined guide unit for sheet pile construction and construction method of sheet pile using it. Download PDF

Info

Publication number
KR20230136576A
KR20230136576A KR1020230119969A KR20230119969A KR20230136576A KR 20230136576 A KR20230136576 A KR 20230136576A KR 1020230119969 A KR1020230119969 A KR 1020230119969A KR 20230119969 A KR20230119969 A KR 20230119969A KR 20230136576 A KR20230136576 A KR 20230136576A
Authority
KR
South Korea
Prior art keywords
sheet pile
fastening
guide
construction
guide unit
Prior art date
Application number
KR1020230119969A
Other languages
Korean (ko)
Inventor
박정열
Original Assignee
(주) 대동이엔지
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 대동이엔지 filed Critical (주) 대동이엔지
Priority to KR1020230119969A priority Critical patent/KR20230136576A/en
Publication of KR20230136576A publication Critical patent/KR20230136576A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/02Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers specially adapted for placing or removing bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/16Auxiliary devices rigidly or detachably arranged on sheet piles for facilitating assembly
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

본 발명에 따른 시트파일 시공용 체결가이드유닛과 이용한 시트파일의 시공공법을 게시한다. 시트파일 시공용 체결가이드유닛은 가이드본체와, 상기 가이드본체에 시트파일의 단면의 형상으로 따라 배열 설치되며 시트파일의 단부에 삽입되는 삽입홈이 형성되는 고정부재들을 포함하며, 상기 가이드본체의 양측에 구비되는 것으로, 시공이 이루어진 시트파일의 체결부와 시공되는 시트파일의 체결부가 체결될 수 있도록 가이드하는 유도체결가이드부를 구비한다.The construction method of sheet piles using the fastening guide unit for sheet pile construction according to the present invention is posted. The fastening guide unit for sheet pile construction includes a guide main body and fixing members arranged in the guide main body according to the shape of the cross section of the sheet pile and forming an insertion groove inserted into the end of the sheet pile, on both sides of the guide main body. It is provided in and has an inductive fastening guide part that guides the fastening part of the installed sheet pile and the fastening part of the constructed sheet pile.

Description

시트파일 시공용 체결가이드유닛과 이를 이용한 시트파일의 시공공법. {Combined guide unit for sheet pile construction and construction method of sheet pile using it.} Fastening guide unit for sheet pile construction and sheet pile construction method using it. {Combined guide unit for sheet pile construction and construction method of sheet pile using it.}

본 발명은 시트파일을 시공에 관한 것으로, 더 상세하게는 시트파일의 시공과정에서 시트파일들을 작업자의 도움 없이 원활하게 결합 될 수 있도록 하는 시트파일 시공용 체결가이드유닛과 이를 이용한 시트파일의 시공공법에 관한 것이다. The present invention relates to the construction of sheet piles, and more specifically, to a fastening guide unit for sheet pile construction that allows sheet piles to be smoothly combined without operator assistance during the sheet pile construction process, and a sheet pile construction method using the same. It's about.

일반적으로 시트파일(sheet pile)은 각종 건축이나 토목공사를 위한 터파기 부지의 둘레를 따라 차수벽을 형성하거나 터파기 배후의 연약한 토양이 붕괴되는 것을 방지하는 흙막이 벽체로 이용되거나 하천 주위의 연약지반이 무너지는 것을 방지를 위한 벽체 또는 지중의 차수벽 등으로 사용될 수 있다.In general, sheet piles are used to form a cutoff wall along the perimeter of the excavation site for various construction or civil engineering works, or as an earth retaining wall to prevent the soft soil behind the excavation from collapsing, or to protect the soft ground around a river. It can be used as a wall to prevent collapse or as an underground water barrier.

이러한 시트파일에는 여러 종류가 있는데, 보통 단면의 형태에 따라서 U자형, Z자형, 모자형, 직선 웨브형 등으로 분류되며, 시트파일의 양단에는 구멍형 또는 요철형 등의 조인트가 형성되어 있어서 이웃하는 시트파일과 서로 끼워 맞출 수 있게 되어 있다. There are several types of sheet piles. Depending on the shape of the cross section, they are usually classified into U-shaped, Z-shaped, hat-shaped, straight web-shaped, etc. Joints such as holes or concave-convex are formed at both ends of the sheet pile, It can be fitted with the sheet pile.

이러한 시트파일은 지중에 설치하기 위해 크레인에 매달린 진동해머로 시트파일의 상단을 파지하고 진동을 가하면서 시트파일을 직접 지중에 압입하거나 지반이 불안정하거나 지중에 암석 등이 혼합되어 시트파일을 정위치에 수직으로 정밀하게 연이어 시공하기 어려운 경우에는 시트파일을 설치 할 부위에 스크류로 굴착공을 천공 후 시공하게 된다. To install these sheet piles in the ground, the top of the sheet pile is gripped with a vibrating hammer hung on a crane and vibration is applied to press the sheet pile directly into the ground, or the sheet pile is placed in the correct position due to unstable ground or rocks mixed in the ground. In cases where it is difficult to construct vertically and precisely in succession, construction is performed after drilling an excavation hole with a screw in the area where the sheet pile is to be installed.

이러한 점을 감안하여 대한민국 등록특허 제 10-2089857호에는 시트파일 가이드 장치가 게시되어 있다. 게시된 가이드 장치는 중앙부와 이 중앙부의 양단에 경사지게 확장되는 확장부와, 이 확장부의 단부에 형성되며 인접하는 시트파일과 결합되는 체결부를 구비한 시트파일을 지중에 하강시킬 때 시트파일을 안내하기 위한 것으로, 단면원형의 강관체와, 이 강관체의 외주면에 용접접합되며 그 외부둘레면이 상기 시트파일의 내부면에 정합되도록 중앙부와 확장부 및 이 확장부에서 상기 강관체로 연결되는 연결부를 포함하는 윤곽형태부와, 상기 윤곽형태부의 하단부에 형성되며 시트파일의 하단부가 걸려서 탑재되는 돌출부를 포함하고, 상기 돌출부의 상단면은 상부에서 하부로 갈수록 점진적으로 확장되는 구성을 가진다. Considering this, a sheet pile guide device is published in Korean Patent No. 10-2089857. The posted guide device guides the sheet pile when lowering it into the ground, including a central part, an extension that extends obliquely at both ends of the central part, and a fastening part formed at the end of this extension and coupled to an adjacent sheet pile. For this purpose, it includes a steel pipe body with a circular cross-section, a central portion and an extension portion that are welded to the outer peripheral surface of the steel pipe body and the outer circumferential surface is aligned with the inner surface of the sheet pile, and a connection portion connected from the expanded portion to the steel pipe body. It includes a contour-shaped portion and a protrusion formed at the lower end of the contour-shaped portion and on which the lower end of the sheet pile is hung and mounted, and the upper surface of the protrusion has a configuration that gradually expands from the top to the bottom.

그러나 이러한 가이드장치는 시트파일삽입공을 별도로 설치하여야 시트파일의 시공에 따른 많은 작업공수가 소요되는 문제점이 있다. However, this guide device has a problem in that it requires a separate installation of a sheet pile insertion hole, which requires a lot of man-hours for the construction of the sheet pile.

대한민국 특허등록 제 10-1694844호에는 안내케이싱을 이용한 시트파일 시공방법이 게시되어 있으며, 대한민국 공개특허 제 10-2021-0007374호에는 시트파일의 가이드장치가 게시되어 있다. 게시된 시트파일의 가이드 장치는 시트파일에 내접하는 단면원형의 강관체와 같이 시트파일을 시공하게 되므로 시공성이 떨어지는 문제점이 있다. Republic of Korea Patent Registration No. 10-1694844 discloses a sheet pile construction method using a guide casing, and Republic of Korea Patent Publication No. 10-2021-0007374 discloses a guide device for sheet piles. The posted guide device for sheet piles has the problem of poor constructability because the sheet piles are constructed like a steel pipe with a circular cross section inscribed in the sheet piles.

특히, 상술한 바와 같은 종래의 시트팡리 시공방법은 파일시공을 위한 장비를 운영하는 운영자와 시트파일들을 체결을 위한 보조작업자가 필요하게 되므로 파일의 시공작업 시 많은 작업공수가 소요되는 문제점이 있다. In particular, the conventional sheet pang-ri construction method as described above requires an operator to operate equipment for pile construction and an auxiliary worker to fasten the sheet piles, so there is a problem that a lot of man-hours are required during the pile construction work.

대한민국 등록특허 제 10-2089857호Republic of Korea Patent No. 10-2089857 대한민국 특허등록 제 10-1694844호Republic of Korea Patent Registration No. 10-1694844 대한민국 공개특허 제 10-2021-0007374호Republic of Korea Patent Publication No. 10-2021-0007374

본 발명은 상술한 바와 같은 문제점을 해결하기 위한 것으로, 시트파일의 시공 시 시트파일 장비를 운영하는 운영자가 보조작업자 없이 시트파일을 상호 연결하면서 시공할 수 있으므로 작업공수를 줄일 수 있으며, 시트파일의 작업효율을 대폭 향상시킬 수 있는 시트파일 시공용 체결가이드유닛과 이를 이용한 시트파일의 시공 공법을 제공함에 있다.The present invention is intended to solve the problems described above. When constructing sheet piles, the operator who operates the sheet pile equipment can construct the sheet piles by interconnecting them without an auxiliary worker, thereby reducing the number of working hours and reducing the number of work hours of the sheet piles. The aim is to provide a fastening guide unit for sheet pile construction that can significantly improve work efficiency and a sheet pile construction method using the same.

상기 목적을 달성하기 위한 본 발명의 시트파일 시공용 체결가이드유닛은 가이드본체와, 상기 가이드본체에 시트파일의 단면의 형상으로 따라 배열 설치되며 시트파일의 단부에 삽입되는 삽입홈이 형성되는 고정부재들을 포함하며,The fastening guide unit for sheet pile construction of the present invention for achieving the above object includes a guide body, and a fixing member arranged in the guide body according to the shape of the cross section of the sheet pile and having an insertion groove inserted into the end of the sheet pile. Includes,

상기 가이드본체의 양측에 구비되는 것으로, 시공이 이루어진 시트파일의 체결부와 시공되는 시트파일의 체결부가 체결될 수 있도록 가이드하는 유도체결가이드부를 구비한 것을 특징으로 한다. It is provided on both sides of the guide body and is characterized by an induction fastening guide part that guides the fastening part of the installed sheet pile and the fastening part of the constructed sheet pile.

본 발명에 있어서, 상기 가이드본체는 시트파일의 단면 형상과 동일한 형상으로 이루어진다. In the present invention, the guide main body has the same shape as the cross-sectional shape of the sheet pile.

상기 유도체결가이드부는 시공이 이루어진 제 1체결부와 시공이 이루어질 제 2시트파일의 제 2체결부가 결합을 위해 동축선 상에 위치될 수 있도록 가이드 하는 유도부를 구비하며, 이 유도부의 단부측의 외면측에는 제1시트파일의 상단면과 제2시트파일의 하단면이 일치될 수 있도록 기준을 받아주기 위한 위치정렬부재를 구비한다. The guided fastening guide part has a guiding part that guides the first fastening part on which construction has been performed and the second fastening part of the second sheet pile to be constructed so that they can be positioned on the same axis for coupling, and the outer surface of the end side of this guiding part The side is provided with a positioning member to receive a standard so that the upper surface of the first sheet pile and the lower surface of the second sheet pile coincide.

상기 고정부재들이 장착된 가이드본체는 상기 파지부재에 대칭적으로 설치될 수 있다. The guide body on which the fixing members are mounted may be symmetrically installed on the holding member.

사기 목적을 달성하기 위한 본 발명의 시트파일 시공용 체결가이드유닛을 이용한 시트파일의 시공공법은 가이드본체와, 상기 가이드본체에 시트파일의 단면의 형상으로 따라 배열 설치되며 시트파일의 단부에 삽입되는 삽입홈이 형성되는 고정부재들을 포함하며, The sheet pile construction method using the fastening guide unit for sheet pile construction of the present invention to achieve the purpose of the present invention includes a guide body, which is arranged and installed in the guide body according to the shape of the cross section of the sheet pile and inserted into the end of the sheet pile. It includes fixing members in which insertion grooves are formed,

상기 가이드본체의 양측에 구비되는 것으로, 시공이 이루어진 시트파일의 체결부와 시공되는 시트파일의 체결부가 체결될 수 있도록 가이드하는 유도체결가이드부 체결가이드유닛을 준비하는 준비단계와, A preparatory step of preparing an inductive fastening guide part fastening guide unit, which is provided on both sides of the guide main body and guides the fastening part of the installed sheet pile to be fastened to the fastening part of the constructed sheet pile;

준비된 체결가이드유닛의 고정부재의 삽입홈이 지반에 시공이 이루어진 제1시트파일의 단부에 삽입되도록 하여 체결가이드부와 제1시트파일의 제1체결부가 동축상에 위치될 수 있도록 하는 체결가이드유닛 장착단계와, A fastening guide unit that allows the fastening guide part and the first fastening part of the first sheet pile to be positioned on the same axis by inserting the insertion groove of the prepared fastening member of the fastening guide unit into the end of the first sheet pile constructed on the ground. Installation step,

파일시공장비를 이용하여 시공될 제2시트파일의 단부를 파지하여 제2시트파일의 제 2체결부가 상기 유도체결가이드부에 가이드되어 제 1시트파일의 제1체결부와 결합되도록 하는 지지단계와,A support step of holding the end of the second sheet pile to be constructed using pile construction equipment so that the second fastening part of the second sheet pile is guided to the inductive fastening guide and coupled to the first fastening part of the first sheet pile; ,

상기 제 2시트파일의 제 2체결부가 유도체결가이드부에 의해 제 1체결부와 체결된 상태에서 항타하는 항타단계와, A driving step of driving while the second fastening part of the second sheet pile is fastened to the first fastening part by the inductive fastening guide part;

상기 항타단계에 의해 항타가 이루어진 후 파일시공장비를 이용하여 제 1시트파일로부터 체결가이드유닛을 분리하여 제 2시트파일의 단부에 체결하는 체결가이드유닛이송단계를 포함한다. It includes a fastening guide unit transfer step of separating the fastening guide unit from the first sheet pile using pile construction equipment after the driving is performed by the driving step and fastening it to the end of the second sheet pile.

본 발명에 따른 시트파일 시공용 체결가이드유닛과 이를 이용한 쉬트파일의 시공공법은 시트파일을 시공하는 장비를 운영하는 운전자가 작업자의 도움없이 파일 시공작업을 수행할 수 작업공수를 줄이고, 시공효율을 향상시킬 수 있으며, 또한 장비의 운영효율을 높일 수 있다. The fastening guide unit for sheet pile construction according to the present invention and the sheet pile construction method using the same allow the driver operating the sheet pile construction equipment to perform pile construction work without the help of workers, reducing the number of workers and increasing construction efficiency. It can be improved and the operating efficiency of the equipment can also be increased.

도 1은 본 발명에 따른 시트파일 시공용 체결가이드유닛을 발췌하여 도시한 사시도,
도 2는 체결가이드유닛의 상태를 나타내 보인 사시도,
도 3은 본 발명에 따른 시트파일 시공용 체결가이드유닛의 평면도
도 4는 본 발명에 따른 체결가이드유닛의 다른 실시예를 나타내 보인 평면도.
도 5는 본 발명에 따른 시트파일 시공용 체결가이드유닛의 사용상태를 나타내 보인 사시도.
Figure 1 is a perspective view showing an excerpt of a fastening guide unit for sheet pile construction according to the present invention;
Figure 2 is a perspective view showing the state of the fastening guide unit;
Figure 3 is a plan view of the fastening guide unit for sheet pile construction according to the present invention.
Figure 4 is a plan view showing another embodiment of the fastening guide unit according to the present invention.
Figure 5 is a perspective view showing the use state of the fastening guide unit for sheet pile construction according to the present invention.

본 발명은 시트파일 시공용 체결가이드유닛과 이를 이용한 시공방법에 관한 것으로, 시트파일 시공용 체결 가이드유닛의 실시예를 도 1 내지 도 5에 나타내 보였다. The present invention relates to a fastening guide unit for sheet pile construction and a construction method using the same. Examples of the fastening guide unit for sheet pile construction are shown in Figures 1 to 5.

도면을 참조하면, 본 발명에 따른 시트파일 시공용 체결가이드유닛(10)은 시공이 이루어지며 양측에 제1체결부(101)가 형성된 제 1시트파일(100)과, 이 제1시트파일의 제1체결부(101)와 제 2시트파일(110)의 일측 제2체결부(111)의 결합 즉, 시공이 이루어진 제1시트파일(100)의 일측에 형성된 제1체결부(101)와 제 2시트파일(110)의 일측 제 2체결부(111)의 체결 시 작업자의 도움 없이 시트파일의 시공을 위한 장비의 운영 만으로 작업할 수 있도록 한다. Referring to the drawings, the fastening guide unit 10 for sheet pile construction according to the present invention includes a first sheet pile 100 on which construction is performed and first fastening parts 101 formed on both sides, and the first sheet pile 100. The combination of the first fastening part 101 and the second fastening part 111 on one side of the second sheet pile 110, that is, the first fastening part 101 formed on one side of the first sheet pile 100 on which construction was performed, and When fastening the second fastening portion 111 on one side of the second sheet pile 110, the work can be done simply by operating the equipment for constructing the sheet pile without the help of an operator.

상기 제 1체결부(101)는 제1시트파일(100)의 양측 단부가 외측방향으로 밴딩되어 제1시트파일(100)의 외주면과 이격되는 제1체결홈(102)이 형성되고, 제 2체결부(111)은 제2시트파일(110)의 양측 단부가 외측방향으로 밴딩되어 제2시트파일(110)의 외주면과 이격되는 제2체결홈(112)이 형성된다. 따라서 제1,2체결부(101)(111)의 제결 시 연속되는 시트파일벽체를 이루게 된다. The first fastening portion 101 is formed by bending both ends of the first sheet pile 100 in the outward direction to form a first fastening groove 102 spaced apart from the outer peripheral surface of the first sheet pile 100, and the second The fastening portion 111 is formed by bending both ends of the second sheet pile 110 in the outward direction to form a second fastening groove 112 spaced apart from the outer peripheral surface of the second sheet pile 110. Therefore, when the first and second fastening parts 101 and 111 are joined, a continuous sheet pile wall is formed.

이러한 시트파일 시공용 체결가이드유닛(10)은 시공이 완료된 제1시트파일(100)의 단부에 결합지지되는 고정부재(21)들이 하부에 소정의 간격으로 설치되는 가이드본체(20)를 구비한다. . This fastening guide unit 10 for sheet pile construction is provided with a guide body 20 in which fixing members 21 are coupled and supported to the end of the first sheet pile 100 on which construction has been completed and are installed at predetermined intervals at the bottom. . .

그리고 상기 가이드본체(20)의 양측에 구비되는 것으로, 시공이 이루어진 제1시트파일(100)의 제1체결부(110)와 시공되는 제 2시트파일(110)의 제2체결부(112)를 작업자의 가이드 없이 체결될 수 있도록 가이드 하는 유도체결가이드부 즉, 제 1,2유도체결가이드부(30)(40)를 구비한다. And, provided on both sides of the guide body 20, a first fastening portion 110 of the first sheet pile 100 to be constructed and a second fastening portion 112 of the second sheet pile 110 to be constructed. It is provided with inductive fastening guide parts, that is, first and second inductive fastening guide parts (30) and (40) that guide the fastener so that it can be fastened without the operator's guide.

이와 같이 구성된 체결가이드 유닛( 10)을 구성요소별로 보다 상세하게 설명하면, 상기 가이드본체(20)은 실질적으로 시공되는 제1, 2 시트파일(100)(110)의 단면과 동일한 단면 형상을 가지며, 가이드본체(20)의 두께는 제1,2시트파일(100)(110)의 두께와 동일한 두께를 가진다. The fastening guide unit configured as above ( 10) is described in more detail for each component, the guide main body 20 has a cross-sectional shape substantially identical to that of the first and second sheet piles 100 and 110 to be constructed, and the guide main body 20 The thickness has the same thickness as the thickness of the first and second sheet piles 100 and 110.

상기 가이드본체(20)의 하부측에 설치되는 고정부재(21)들에는 삽입홈(22)들이 형성되는데, 이 삽입홈(22)의 제1시트파일(100)(110)의 단부에 원활하게 삽입될 수 있는 폭을 가진다. 특히, 가이드본체(20)의 하부측에 설치되는 고정부재(21)들의 배열은 제1시트파일(100)의 형상을 따라 배열됨으로써 상기 제 1,2유도체결가이드부(30)(40)가 제 1시트파일(100)의 양측에 설치된 제 1체결부(101)와 각각 일치된다. 그리고 상기 가이드본체(20)에는 시트파일을 시공하기 위한 죠를 구비한 장비를 이용하여 파지할 수 있는 파지부(25)를 더 구비한다.Insertion grooves 22 are formed in the fixing members 21 installed on the lower side of the guide body 20, and the insertion grooves 22 are smoothly inserted into the ends of the first sheet piles 100 and 110. It has a width that can be inserted. In particular, the arrangement of the fixing members 21 installed on the lower side of the guide body 20 is arranged according to the shape of the first sheet pile 100, so that the first and second guided fastening guide parts 30 and 40 are Each corresponds to the first fastening portion 101 installed on both sides of the first sheet pile 100. In addition, the guide body 20 is further provided with a gripping part 25 that can be gripped using equipment equipped with jaws for constructing sheet piles.

상기 파지부(25)의 양측은 가이드본체(20)의 폭방향 양측의 단부와 체결되어 가이드본체(20)가 외력에 변형되는 것을 방지할 수 있도록 함이 바람직하다. It is preferable that both sides of the grip portion 25 are fastened to ends on both sides of the guide body 20 in the width direction to prevent the guide body 20 from being deformed by external force.

상기 고정부재(21)가 설치된 가이드본체(20)는 도 1 내지 도 3에 도시된 바와 같이 대칭적으로 파지부(25)를 중심을 대칭적으로 이루어질 수 있다. 대칭적으로 설치되는 경우, 가이드본체(20)는 수평방향으로의 단면이 육각형의 형상으로 이루어질 수도 있다. The guide body 20 on which the fixing member 21 is installed may be symmetrical about the grip portion 25 as shown in FIGS. 1 to 3. When installed symmetrically, the guide body 20 may have a hexagonal cross-section in the horizontal direction.

그러나 이에 한정되지 않고, 도 4에 도시된 바와 같이 가이드본체(20)와 이의 하부에 고정부재(21)들이 설치된 단일의 구조로 이루어질 수도 있다. However, it is not limited to this, and as shown in FIG. 4, it may be formed as a single structure in which the guide body 20 and fixing members 21 are installed at its lower portion.

한편, 상기 제1유도체결가이드부(30)는 시공이 이루어진 제 1체결부(101)와 시공이 이루어질 제 2시트파일(110)의 제 2체결부(111)가 결합을 위해 동축선 상에 위치될 수 있도록 가이드 하는 제1유도부(31)를 구비하며, 이 제1유도부(31)의 단부측의 외면측에는 제1시트파일(100)의 상단면과 제2시트파일(110)의 하단면이 일치될 수 있도록 기준을 받아주기 위한 제1위치정렬부재(35)가 설치된다. On the other hand, the first induction fastening guide part 30 is connected on the coaxial line for coupling the first fastening part 101 on which construction has been performed and the second fastening part 111 of the second sheet pile 110 to be constructed. It is provided with a first guide part 31 that guides it so that it can be positioned, and the upper surface of the first sheet pile 100 and the lower surface of the second sheet pile 110 are located on the outer surface of the end of the first guide part 31. A first position alignment member 35 is installed to receive the standard so that this can be matched.

상기 가이드 본체(20)의 타측에 형성된 2유도체결가이드부(40)는 실질적으로 제1유도체결가이드부(30)의 구성과 동일한 구조를 가진다. 즉, 제 2유도체결가이드부(40)는 가이드본체(20)의 타측에 형성된 제2유도부(41)가 구비되고, 이의 배면측에는 제1시트파일(100)의 상단면과 제2시트파일(110)의 하단면이 일치될 수 있도록 기준을 받아주기 위한 제2위치정렬부재(45)가 설치된다. 제1,2위치정열부재(35)(45)는 가이드본체(20)에 결합된 단일의 부재로 이루어질 수 있다. The second inductive fastening guide portion 40 formed on the other side of the guide body 20 has substantially the same structure as that of the first inductive fastening guide portion 30. That is, the second guiding fastening guide part 40 is provided with a second guiding part 41 formed on the other side of the guide main body 20, and the upper surface of the first sheet pile 100 and the second sheet pile ( A second position alignment member 45 is installed to receive a standard so that the lower surfaces of 110) are aligned. The first and second position alignment members 35 and 45 may be formed as a single member coupled to the guide body 20.

한편 대칭으로 이루어진 가이드본체(20)의 사이에는 도 2에 도시된 바와 같이 하부로 연장되어 시공이 이루어진 제1시트파일(100)의 배면을 지지하는 보조위치정열부재(36)를 더 구비한다. Meanwhile, between the symmetrical guide bodies 20, an auxiliary positioning member 36 is further provided, as shown in FIG. 2, extending downward to support the rear surface of the first sheet pile 100 on which construction was performed.

상술한 바와 같이 구성된 본 발명에 따른 시트파일 시공용 체결가이드유닛의 작용과 이를 통하여 상기 시트파일의 시공공법을 보다 상세하게 설명하면 다음과 같다.The operation of the fastening guide unit for sheet pile construction according to the present invention configured as described above and the construction method of the sheet pile through it will be described in more detail as follows.

시트파일을 시공, 즉, 제1,2시트파일(100)(110)들을 교번하여 시공하기 위해서는 먼저 제1시트파일(100)을 시공을 위한 위치에 장비를 이용하여 시공한다. 그리고 준비된 체결가이드유닛(10)을 바이브레이터와 파일파지부가 마련된 파일시공장비 예컨대, 진동리퍼, 항타기와 같은 파일 시공장비를 이용하여 파지부(25)를 파지하여 시공이 이루어진 제1시트파일(100)의 상단부에 체결하는 체결가이드유닛장착단계를 수행한다. In order to construct a sheet pile, that is, to construct the first and second sheet piles 100 and 110 alternately, the first sheet pile 100 is first constructed using equipment at the location for construction. Then, the first sheet pile (100) was constructed by gripping the prepared fastening guide unit (10) with the gripping part (25) using a vibrator and pile construction equipment such as a vibrating ripper or pile driver. Perform the fastening guide unit mounting step to fasten to the upper part of the.

이때에 제1시트파일(100)의 상단부측과 체결가이드유닛(10)의 결합은 가이드본체(20)의 하부측에 소정의 간격으로 설치되는 각 고정부재(20)의 삽입홈(22)이 제1시트파일(100)의 상단부 측에 삽입되도록 함으로써 이루어진다. At this time, the coupling between the upper end of the first sheet pile 100 and the fastening guide unit 10 is achieved through the insertion groove 22 of each fixing member 20 installed at a predetermined interval on the lower side of the guide main body 20. This is done by inserting it into the upper end of the first sheet pile (100).

이러한 과정에서 상기 가이드본체(20)의 수평방향으로의 단면형상은 제1시트파일(100)의 수평방향으로의 단면의 형상과 동일한 형상을 가지고 있으므로 가이드본체(20)의 하면이 상기 제1시트파일(100)의 상단면과 접촉하게 된다. In this process, the horizontal cross-sectional shape of the guide main body 20 has the same shape as the horizontal cross-sectional shape of the first sheet pile 100, so the lower surface of the guide main body 20 is the first sheet. It comes into contact with the top surface of the pile 100.

따라서 상기 체결가이드유닛(20)의 양측에 형성되는 제1,2체결유도가이드부(30)(40)가 시공된 제1시트파일(100)의 양측에 마련된 제 1체결부(101)들과 수직방향 즉, 제 1시트파일(100)의 길이 방향으로 정렬상태를 유지하게 된다. 이때에 상기 제1,2위치정력부재(35)(45)는 제1시트파일(100)의 양측 제 1체결부(101)의 배면에 밀착됨으로써 제1시트파일(100)에 대해 가이드본체(20)의 위치가 정열된다. 또한 보조위치정열부재는 제 1시트파일의 배면에 접촉되어 우치를 정열한다. Therefore, the first fastening parts 101 provided on both sides of the first sheet pile 100 on which the first and second fastening guide parts 30 and 40 formed on both sides of the fastening guide unit 20 are installed, and The alignment is maintained in the vertical direction, that is, in the longitudinal direction of the first sheet pile 100. At this time, the first and second position static members (35) (45) are in close contact with the rear surfaces of the first fastening portions (101) on both sides of the first sheet pile (100), thereby forming a guide body ( The positions of 20) are aligned. Additionally, the auxiliary positioning member is in contact with the back of the first sheet pile to align the stacks.

상술한 바와 같이 체결가이드유닛(10)의 장착이 완료되면, 파일시공장비를 이용하여 시공될 제2시트파일(110)의 단부를 파지하여 제2시트파일(110)의 제 2체결부(111)의 하단부 측이 제 1체결가이드부(30)에 가이드 될 수 있도록 지지시킨 후 하강시키는 지지단계를 수행한다. When the installation of the fastening guide unit 10 is completed as described above, the end of the second sheet pile 110 to be constructed is grasped using pile construction equipment and the second fastening portion 111 of the second sheet pile 110 is held. ) is supported so that the lower end can be guided to the first fastening guide part 30, and then a support step is performed to lower it.

상기 지지단계는 파일시공장비를 이용하여 시공을 위한 제 2시트파일(110)의 제 2체결부(112)의 하단부측을 제1체결유도가이드부(30)의 제1유도지지부(31)에 지지시키게 되면, 제 2시트파일(110)의 제 2체결부(111)의 하단부가 제 1시트파일의 제1체결부(101)의 상단부가 수직한 상태로 정렬된 상태에서 하강하게 됨으로써 제1체결부(101)와 제 2체결부가 결합된다. In the support step, the lower end of the second fastening part 112 of the second sheet pile 110 for construction is connected to the first guiding support part 31 of the first fastening guiding guide part 30 using pile construction equipment. When supported, the lower end of the second fastening part 111 of the second sheet pile 110 is lowered while the upper end of the first fastening part 101 of the first sheet pile is aligned in a vertical state, thereby causing the first The fastening part 101 and the second fastening part are coupled.

이러한 결합은 도 5에 도시된 바와 같이 제 1시트파일(100)의 제1체결부(101)의 단부측에 형성된 제 1체결홈(36)에 제 2시트파일(110)의 제 2체결부(111)가 삽입되고, 제 2체결부(111)의 제 2체결홈(46)에 제1시트파일의 제1체결부(101)가 결합됨으로써 이루어진다. As shown in FIG. 5, this coupling is achieved by connecting the second fastening part of the second sheet pile 110 to the first fastening groove 36 formed on the end side of the first fastening part 101 of the first sheet pile 100. (111) is inserted, and the first fastening part 101 of the first sheet pile is coupled to the second fastening groove 46 of the second fastening part 111.

이 상태에서 상기 파일시공장비를 이용하여 제 2시트파일(110)을 하강시킴과 아울러 시공을 위한 진동을 발생시켜 항타하는 항타단계를 수행한다. In this state, the second sheet pile 110 is lowered using the pile construction equipment, and a driving step is performed by generating vibration for construction.

이러한 항타작업은 굴착기의 붐에 설치되는 파일시공장비 즉, 리퍼나 항타기를 수직방향 즉, 제 1시트파일과 나란한 방향으로 진동시키면서 이루어진다. This driving operation is performed by vibrating the pile construction equipment, that is, the ripper or the pile driver installed on the boom of the excavator, in the vertical direction, that is, in the direction parallel to the first sheet pile.

상기와 같이 제 2시트파일(110)의 항타가 이루어진 후 파일시공장비를 이용하여 체결가이드유닛(20)의 파지부(25)를 파지하여 제 1시트파일(100)로부터 분리한 후, 회전시켜 시공이 이루어진 제 2시트파일(110)의 상단부에 상술한 바와 같은 방법으로 결함으로써 체결가이드유닛이송단계를 수행한다. After the second sheet pile 110 has been driven as described above, the grip part 25 of the fastening guide unit 20 is grasped using pile construction equipment, separated from the first sheet pile 100, and rotated. The fastening guide unit transfer step is performed by attaching to the upper end of the constructed second sheet pile 110 in the same manner as described above.

그리고 상술한 바와 같은 방법을 제 2시트파일에 체결을 위한 시트파일을 시공한다. Then, the sheet pile for fastening to the second sheet pile is constructed using the same method as described above.

이와 같이 본 발명에 따른 시트파일 시공용 결합가이드유닛과 이를 이용한 시트파일의 무인 시공공법은 시공된 시트파일과 시공을 위신 시트파일들을 체결하기 위하여 체결부위들을 결합하여 주기 위한 별도의 작업자 도움없이 파일시공장비를 운영하는 운전자가 시공을 위한 모든 작업을 수행할 수 있으므로 파일의 시공을 위한 작업공수를 줄일 수 있으며, 작업효율을 향상시킬 수 있다. In this way, the combination guide unit for sheet pile construction according to the present invention and the unmanned construction method of sheet piles using the same are used without the help of a separate worker to combine the fastening parts to fasten the constructed sheet piles and the sheet piles. Since the operator operating the construction equipment can perform all construction work, the number of workers required for pile construction can be reduced and work efficiency can be improved.

본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 사람이라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 것이다. 따라서 본 발명의 진정한 기술적 보호 범위는 첨부된 등록 청구 범위의 기술적 사상에 의해 정해져야 할 것이다.The present invention has been described with reference to the embodiments shown in the drawings, but these are merely exemplary, and those skilled in the art will understand that various modifications and other equivalent embodiments are possible therefrom. Therefore, the true technical protection scope of the present invention should be determined by the technical spirit of the attached registered claims.

Claims (5)

가이드본체와, 상기 가이드본체에 시트파일의 단면의 형상으로 따라 배열 설치되며 시트파일의 단부에 삽입되는 삽입홈이 형성되는 고정부재들을 포함하며,
상기 가이드본체의 양측에 구비되는 것으로, 시공이 이루어진 시트파일의 체결부와 시공되는 시트파일의 체결부가 체결될 수 있도록 가이드하는 유도체결가이드부를 구비한 것을 특징으로 하는 시트파일 시공용 체결가이드유닛.
It includes a guide body and fixing members arranged in the guide body according to the shape of the cross section of the sheet pile and forming an insertion groove inserted into the end of the sheet pile,
A fastening guide unit for sheet pile construction, which is provided on both sides of the guide main body and includes an inductive fastening guide part that guides the fastening part of the constructed sheet pile and the fastening part of the constructed sheet pile.
제 1항에 있어서, 상기 가이드본체는 시트파일의 단면 형상과 동일한 형상으로 이루어진 것을 특징으로 하는 시트파일 시공용 체결가이드유닛.The fastening guide unit for sheet pile construction according to claim 1, wherein the guide body has the same shape as the cross-sectional shape of the sheet pile. 제 1항에 있어서,
상기 유도체결가이드부는 시공이 이루어진 제 1체결부와 시공이 이루어질 제 2시트파일의 제 2체결부가 결합을 위해 동축선 상에 위치될 수 있도록 가이드 하는 유도부를 구비하며, 이 유도부의 단부측의 외면측에는 제1시트파일의 상단면과 제2시트파일의 하단면이 일치될 수 있도록 기준을 받아주기 위한 위치정렬부재를 구비한 것을 특징으로 하는 시트파일 시공용 체결가이드유닛.
According to clause 1,
The guided fastening guide part has a guiding part that guides the first fastening part on which construction has been performed and the second fastening part of the second sheet pile to be constructed so that they can be positioned on the same axis for coupling, and the outer surface of the end side of this guiding part A fastening guide unit for sheet pile construction, characterized in that the side is provided with a position alignment member to receive a standard so that the upper surface of the first sheet pile and the lower surface of the second sheet pile are aligned.
제 1항에 있어서,
상기 고정부재들이 장착된 가이드본체는 상기 파지부재에 대칭적으로 설치된 것을 특징으로 하는 시트파일 시공용 체결가이드유닛.
According to clause 1,
A fastening guide unit for sheet pile construction, characterized in that the guide body on which the fixing members are mounted is symmetrically installed on the holding member.
가이드본체와, 상기 가이드본체에 시트파일의 단면의 형상으로 따라 배열 설치되며 시트파일의 단부에 삽입되는 삽입홈이 형성되는 고정부재들을 포함하며,
상기 가이드본체의 양측에 구비되는 것으로, 시공이 이루어진 시트파일의 체결부와 시공되는 시트파일의 체결부가 체결될 수 있도록 가이드하는 유도체결가이드부 체결가이드유닛을 준비하는 준비단계와,
준비된 체결가이드유닛의 고정부재의 삽입홈이 지반에 시공이 이루어진 제1시트파일의 단부에 삽입되도록 하여 체결가이드부와 제1시트파일의 제1체결부가 동축상에 위치될 수 있도록 하는 체결가이드유닛 장착단계와,
파일시공장비를 이용하여 시공될 제2시트파일의 단부를 파지하여 제2시트파일의 제 2체결부가 상기 유도체결가이드부에 가이드되어 제 1시트파일의 제1체결부와 결합되도록 하는 지지단계와,
상기 제 2시트파일의 제 2체결부가 유도체결가이드부에 의해 제 1체결부와 체결된 상태에서 항타하는 항타단계와,
상기 항타단계에 의해 항타가 이루어진 후 파일시공장비를 이용하여 제 1시트파일로부터 체결가이드유닛을 분리하여 제 2시트파일의 단부에 체결하는 체결가이드유닛이송단계를 포함한 것을 특징으로 하는 시트파일 시공용 체결가이드유닛을 이용한 시트파일의 시공공법.


It includes a guide body and fixing members arranged in the guide body according to the shape of the cross section of the sheet pile and forming an insertion groove inserted into the end of the sheet pile,
A preparatory step of preparing an inductive fastening guide part fastening guide unit, which is provided on both sides of the guide main body and guides the fastening part of the installed sheet pile to be fastened to the fastening part of the constructed sheet pile;
A fastening guide unit that allows the fastening guide part and the first fastening part of the first sheet pile to be positioned on the same axis by inserting the insertion groove of the prepared fastening member of the fastening guide unit into the end of the first sheet pile constructed on the ground. Installation step,
A support step of holding the end of the second sheet pile to be constructed using pile construction equipment so that the second fastening part of the second sheet pile is guided to the inductive fastening guide and coupled to the first fastening part of the first sheet pile; ,
A driving step of driving while the second fastening part of the second sheet pile is fastened to the first fastening part by the inductive fastening guide part;
Sheet pile construction, characterized in that it includes a fastening guide unit transfer step of separating the fastening guide unit from the first sheet pile and fastening it to the end of the second sheet pile using pile construction equipment after the driving is achieved by the driving step. Sheet pile construction method using a fastening guide unit.


KR1020230119969A 2023-09-08 2023-09-08 Combined guide unit for sheet pile construction and construction method of sheet pile using it. KR20230136576A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020230119969A KR20230136576A (en) 2023-09-08 2023-09-08 Combined guide unit for sheet pile construction and construction method of sheet pile using it.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020230119969A KR20230136576A (en) 2023-09-08 2023-09-08 Combined guide unit for sheet pile construction and construction method of sheet pile using it.

Publications (1)

Publication Number Publication Date
KR20230136576A true KR20230136576A (en) 2023-09-26

Family

ID=88191328

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020230119969A KR20230136576A (en) 2023-09-08 2023-09-08 Combined guide unit for sheet pile construction and construction method of sheet pile using it.

Country Status (1)

Country Link
KR (1) KR20230136576A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101694844B1 (en) 2016-07-05 2017-01-10 차수익 Construction method of sheet pile using guide casing
KR102089857B1 (en) 2018-06-14 2020-03-16 홍성현 Guide device for sheet pile
KR20210007374A (en) 2019-07-11 2021-01-20 정훈식 Guide device for sheet pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101694844B1 (en) 2016-07-05 2017-01-10 차수익 Construction method of sheet pile using guide casing
KR102089857B1 (en) 2018-06-14 2020-03-16 홍성현 Guide device for sheet pile
KR20210007374A (en) 2019-07-11 2021-01-20 정훈식 Guide device for sheet pile

Similar Documents

Publication Publication Date Title
JP2005299202A (en) Steel sheet pile, earth retaining structure using the same, and construction method of earth retaining structure
JP6725313B2 (en) Base member for pile foundation
KR20230136576A (en) Combined guide unit for sheet pile construction and construction method of sheet pile using it.
KR20140015019A (en) Arch wall shoring structure
JP5976976B1 (en) Slide rail method built-in simple earth retaining method
JP2007107218A (en) Steel sheet pile gripping device and steel sheet pile driving device
JP5642988B2 (en) Detachable guide jig and steel pipe pile construction method using the same
JP6138192B2 (en) Steel pipe pile construction method
JP7102228B2 (en) How to build concrete sheet pile members, earth retaining walls and earth retaining walls
JP6871057B2 (en) Construction method and improvement method of steel pipe sheet pile
KR20110078445A (en) Device for connecting wales
JP2001279666A (en) Steel pipe erection and steel pipe erection/immersion method
JP5896082B2 (en) Steel sheet pile underground deformation prevention device, underground deformation prevention method, and continuous wall underground deformation prevention device
JP3227141B2 (en) Earth retaining plate
JP2015151796A (en) Joining structure and erection method of earth retaining h-shaped steel pile
JP2964406B1 (en) Driving protection device for protective fence post
KR20190127507A (en) lifting device for PHC pile and piling method of PHC pile using the same
JP2023147049A (en) Underground structure construction method
JPS6136587Y2 (en)
JP2019190096A (en) Earth retaining member, earth retaining member installation method
JP2002030881A (en) Casing for shaft
EP1405952A2 (en) Method of constructing a basement beneath an existing building
KR200339369Y1 (en) Form system for retaining concrete wall
JP3232196B2 (en) Drilling method and excavator for pile hole
JP3053270U (en) Support member receiving piece used for simple earth retaining method