KR20230067228A - Optimization method of precast concrete slab stacks for transportation - Google Patents

Optimization method of precast concrete slab stacks for transportation Download PDF

Info

Publication number
KR20230067228A
KR20230067228A KR1020210153100A KR20210153100A KR20230067228A KR 20230067228 A KR20230067228 A KR 20230067228A KR 1020210153100 A KR1020210153100 A KR 1020210153100A KR 20210153100 A KR20210153100 A KR 20210153100A KR 20230067228 A KR20230067228 A KR 20230067228A
Authority
KR
South Korea
Prior art keywords
stack
slab
final
stacks
slabs
Prior art date
Application number
KR1020210153100A
Other languages
Korean (ko)
Inventor
김태완
이강호
Original Assignee
인천대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 인천대학교 산학협력단 filed Critical 인천대학교 산학협력단
Priority to KR1020210153100A priority Critical patent/KR20230067228A/en
Publication of KR20230067228A publication Critical patent/KR20230067228A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • G06Q10/043Optimisation of two dimensional placement, e.g. cutting of clothes or wood
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Warehouses Or Storage Devices (AREA)

Abstract

A method for optimizing cargo loading of precast concrete slab stacks is disclosed. The method for optimizing cargo loading of precast concrete slab stacks of the present invention includes: a generation step of generating a temporary stack from PC slabs which satisfy reference area information among a plurality of PC slabs; a slab sorting step of sorting PC slabs with matching dunnage information among the PC slabs belonging to the temporary stack in installation order; a division step of generating one or more final stacks by dividing the temporary stack so that the number of stages is less than or equal to the maximum; and a confirmation step of generating loading area information of the one or more final stacks and comparing the information with luggage compartment area information.

Description

프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법{OPTIMIZATION METHOD OF PRECAST CONCRETE SLAB STACKS FOR TRANSPORTATION}Cargo load optimization method of precast concrete slab stack {OPTIMIZATION METHOD OF PRECAST CONCRETE SLAB STACKS FOR TRANSPORTATION}

본 발명은 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법에 관한 것으로, 보다 상세하게는, 화물적재에 최적화된 프리캐스트 콘크리트 슬래브 스택을 생성하도록 이루어지는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법에 관한 것이다.The present invention relates to a method for optimizing the cargo load of a precast concrete slab stack, and more particularly, to a method for optimizing the cargo load of a precast concrete slab stack configured to generate a precast concrete slab stack optimized for cargo load.

생산성 향상을 목적으로 Off-Site Construction (OSC)는 건설산업에서 점점 증가하는 추세이다. OSC는 공장에서 부재를 생산, 트레일러를 통해 운반하고, 현장에서 조립하여 건축물을 생산하는 방식이다. Off-Site Construction (OSC) is a growing trend in the construction industry for the purpose of improving productivity. OSC is a method of producing buildings by producing members in factories, transporting them through trailers, and assembling them on site.

이렇게 부재를 생산하는 위치(공장)와 설치하는 위치(건설현장)가 다르므로 부재를 어떻게 운반하는지가 OSC 프로젝트 Performance에 큰 영향을 줄 수 있다. Precast Concrete(PC)는 OSC에서 주로 다뤄지는 부재인데, 특히 PC slab의 경우 운반할 부재의 개수가 많고 넓이에 비해 무게가 가볍기 때문에 PC 공장에서 스택(stack)을 만들어 트레일러에 실어 운반하는 경우가 많다. Since the location where members are produced (factory) and the location where they are installed (construction site) are different, how the members are transported can have a great impact on OSC project performance. Precast Concrete (PC) is a member mainly handled by OSC. In particular, in the case of PC slab, since the number of members to be transported is large and the weight is light compared to the width, it is often transported by making a stack at the PC factory and loading it on a trailer. .

PC 슬래브 스택(PC Slab Stack)은 OSC 프로젝트의 주요 관리자들(공장의 제작 관리자, 운반의 운전수, 건설현장의 설치 관리자)의 목적을 만족시킬 수 있어야 한다. 주요 관리자들이 원하는 PC 슬래브 스택은 다음과 같다. The PC Slab Stack should be able to satisfy the objectives of the main managers of the OSC project (manufacturer in the factory, driver in the transport, and installer in the construction site). The PC slab stack that key managers want is:

공장의 제작 관리자(Production Manager)는 운반될 PC 슬래브 스택이 파손과 운반 사고 없이 안정하게 보내는 것을 원한다. 파손, 운반 사고로 인해 추가적인 PC 생산 작업으로 인한 추가 비용 발생을 원하지 않기 때문이다. 따라서, 공장의 제작 관리자는 안정된 PC 슬래브 스택을 목표로 계획한다. The production manager of the factory wants the PC slab stack to be transported safely without damage or transport accidents. This is because they do not want to incur additional costs due to additional PC production work due to damage or transportation accidents. Therefore, the plant's fabrication manager plans to target a stable PC slab stack.

운반의 운전수는 운반하기 위한 법적 준수와 트레일러의 공간(size)를 초과하지 않고, PC 슬래브 스택 자체의 안정한 적재를 원한다. 운전수는 운반 일정의 시간과 안전사고에 대해서만 책임이 있기 때문이다. 따라서, 운반의 운전수는 에러 없는 운반에 대해 중점적으로 고려한다. Transport drivers want stable loading of the PC slab stack itself, without exceeding the legal compliance and trailer size for transport. This is because the driver is only responsible for the time and safety of the delivery schedule. Therefore, the driver of the transport focuses on error-free transport.

건설현장의 설치 관리자는 설치 공정을 만족시킬 수 있는 PC 슬래브 스택을 원하고, 이를 통해서 빠른 설치 작업을 수행하길 원한다. 설치 순서가 뒤섞여 있는 PC 슬래브 스택을 인수받을 때, 건설현장의 설치 대기 공간을 추가적으로 필요로 하고, 이에 따른 재작업(reshuffling work)에 들어가는 작업시간이 추가되어 프로젝트 일정에 차질을 주기 때문이다. 따라서, 건설현장의 설치관리자는 재작업을 최소화 하는 것을 목표로 PC 슬래브 스택을 계획한다. The installation manager at the construction site wants a PC slab stack that can satisfy the installation process, and wants to perform the installation work quickly through this. This is because when receiving a PC slab stack with a mixed installation order, an additional installation waiting space is required at the construction site, which adds to the work time required for reshuffling work, which hinders the project schedule. Therefore, installers on construction sites plan PC slab stacks with the goal of minimizing rework.

하지만, 현재 OSC의 PC 슬래브 스택은 제작 관리자에 의해 수작업으로 계획되기 때문에, 주요한 관리자들의 관점(high stable, minimal reshuffling work, none error)들을 모두 고려하여 효과적인 슬래브 스택(effective slab stack)을 만드는 것은 매우 어렵다. However, since the current OSC PC slab stack is manually planned by the production manager, it is very difficult to create an effective slab stack by considering all the main manager's points of view (high stable, minimal reshuffling work, none error). difficult.

주요한 관리자들의 관점들을 사전에 고려되지 못하면, 다음과 같은 문제가 발생할 수 있다. 첫째, 건설현장에서는 설치 순서가 뒤섞인 슬래브 스택으로 인한 재작업(reshuffling work), 슬래브 스택의 던니지(dunnage) 위치불량으로 인해 파손(균열)이 발생한 슬래브의 보수작업 등 추가 작업 이슈가 발생할 수 있다. 둘째, 공장의 제작 관리자와 운전자 관점에서는 안정성이 낮은 운반으로 인한 사고, 또는 심각한 파손이 발생하는 경우 공장 측에 재생산 및 재운반 이슈가 발생할 수 있다. If the views of key managers are not considered in advance, problems may arise: First, at a construction site, additional work issues such as reshuffling work due to slab stacks in a mixed installation order and repair work for damaged slabs due to poor dunnage positioning of slab stacks may occur. . Second, from the point of view of the production manager and operator of the factory, if an accident or serious damage occurs due to transportation with low stability, issues of reproduction and re-transportation may occur on the factory side.

효과적인 슬래브 스택을 구성하지 못한다면 추가적인 비용, 일정 지연이 발생할 수 있다. OSC의 물류 문제를 해결하지 못한다면, OSC 장점인 효과적인 생산성은 발휘될 수 없다. Failure to construct an effective slab stack may result in additional costs and schedule delays. If OSC's logistical problems are not solved, the effective productivity that is the strength of OSC cannot be demonstrated.

이와 관련하여 중국 특허공개공보 제111445180호(이하 '선행문헌')는 화물 운송 차량 및 전자 장비의 화물 배치 모드를 위한 최적화 기법 및 장치를 개시하고 있다. In this regard, Chinese Patent Publication No. 111445180 (hereinafter referred to as 'Prior Document') discloses an optimization technique and apparatus for a cargo arrangement mode of a cargo transport vehicle and electronic equipment.

선행문헌의 최적화 기법 및 장치는, 운송할 물품의 매개변수 및 화물 차량의 화물칸 너비를 통해 운송할 물품의 수량을 계산하고, 최적의 배치 방법으로 가장 짧은 배치 길이의 배치 방법을 선택하여 제한된 길이의 화물창에 운송할 상품의 최대량을 배치할 수 있는 최적화 기법 및 장치를 개시한다. Optimization techniques and devices in the prior literature calculate the quantity of items to be transported through the parameters of the items to be transported and the width of the cargo compartment of the cargo vehicle, and select the arrangement method with the shortest batch length as the optimal arrangement method to reduce the length of the limited length. An optimization technique and device capable of placing the maximum amount of goods to be transported in a cargo hold are disclosed.

선행문헌의 최적화 기법 및 장치는 운송할 상품의 크기, 모양 및 총 수량 등에 따라 운송할 상품의 배치 방법을 찾음으로써, 화물창 공간활용도를 향상시켜 화물운송비를 절감하는 점에 이점이 있다. Optimization techniques and devices in the prior literature have an advantage in reducing freight transportation costs by improving cargo space utilization by finding a method of arranging goods to be transported according to the size, shape, and total quantity of goods to be transported.

그러나 선행문헌의 최적화 기법 및 장치는 일반 화물의 최적화 적재에 관한 것이므로 주요 관리자들이 원하는 PC 슬래브 스택의 화물 적재 특성을 제대로 반영할 수 없다. 따라서, PC 슬래브 스택의 특성을 고려하여 운반될 수 있도록 계획하고, OSC 프로젝트에 특화된 적재 최적화방법에 대한 개발이 요구된다. However, since the optimization techniques and devices in the prior literature relate to the optimized loading of general cargo, they cannot properly reflect the cargo loading characteristics of the PC slab stack desired by key managers. Therefore, it is required to plan to be transported considering the characteristics of the PC slab stack and to develop a loading optimization method specific to the OSC project.

중국 공개특허공보 제111445180호 (공개일: 2020.07.24)Chinese Laid-Open Patent Publication No. 111445180 (published date: 2020.07.24)

본 발명의 목적은, 주요 관리자들이 원하는 PC 슬래브 스택의 화물 적재 특성을 모두 반영하고, PC 슬래브 스택의 특성을 고려하여 운반될 수 있도록 계획하며, OSC 프로젝트에 특화된 적재 최적화를 달성하도록 이루어지는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법을 제공하는 것이다.The purpose of the present invention is to reflect all the cargo loading characteristics of the PC slab stack desired by key managers, plan to be transported in consideration of the characteristics of the PC slab stack, and achieve loading optimization specific to the OSC project. It is to provide a method for optimizing the cargo loading of a slab stack.

상기 목적은, 본 발명에 따라, 복수의 PC 슬래브 중 기준면적정보를 만족하는 상기 PC 슬래브들로 임시스택을 생성하는 생성단계; 상기 임시스택에 속한 상기 PC 슬래브들 중 던니지정보가 일치하는 상기 PC 슬래브들을 설치순서대로 정렬하는 슬래브정렬단계; 상기 임시스택을 최대단수 이하가 되도록 분할하여 하나 이상의 최종스택을 생성하는 분할단계; 및 상기 하나 이상의 최종스택의 적재면적정보를 생성하여 짐칸면적정보와 비교하는 확인단계를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법에 의하여 달성된다.According to the present invention, the above object is, according to the present invention, a generation step of generating a temporary stack with the PC slabs satisfying reference area information among a plurality of PC slabs; a slab sorting step of arranging the PC slabs having the same Dunnage information among the PC slabs belonging to the temporary stack in an installation order; a division step of generating one or more final stacks by dividing the temporary stack to be less than or equal to the maximum number of stages; and a confirmation step of generating loading area information of the one or more final stacks and comparing them with luggage area information.

상기 정렬단계에서, 상기 던니지정보가 일치하는 상기 PC 슬래브들을 설치순서대로 정렬한 후 상기 임시스택에 속하지 않은 상기 PC 슬래브의 존재 여부를 판단하고, 상기 임시스택에 속하지 않은 상기 PC 슬래브의 존재가 확인되면, 상기 생성단계에서 상기 기준면적정보를 변경하여 상기 임시스택을 더 생성하도록 이루어질 수 있다.In the sorting step, after arranging the PC slabs matching the Dunnage information in the order of installation, it is determined whether or not the PC slab does not belong to the temporary stack exists, and if the PC slab does not belong to the temporary stack exists, If confirmed, the temporary stack may be further created by changing the reference area information in the generating step.

상기 기준면적정보는 아래 수식을 만족하고, The reference area information satisfies the following formula,

Figure pat00001
Figure pat00001

여기서, AREAPICKED는 복수의 PC 슬래브 중 최대면적의 PC 슬래브의 면적이고, AREAREMAIN은 복수의 PC 슬래브 중 임시그룹에 속하지 않은 PC 슬래브의 면적이고, Tolerance는 0~1의 사용자 입력값일 수 있다.Here, AREA PICKED is the area of the PC slab with the maximum area among the plurality of PC slabs, AREA REMAIN is the area of the PC slab that does not belong to the temporary group among the plurality of PC slabs, and Tolerance can be a user input value of 0 to 1.

상기 정렬단계에서, 상기 던니지정보가 불일치하는 상기 PC 슬래브는 상기 임시스택 생성 이전으로 되돌려지도록 이루어질 수 있다.In the sorting step, the PC slab for which the dunnage information is inconsistent may be returned to a state prior to the creation of the temporary stack.

상기 분할단계에서 상기 최대단수가 상기 임시스택의 단수보다 크면, 상기 임시스택을 분할하지 않고 1개의 최종스택을 생성하도록 이루어질 수 있다.In the dividing step, if the maximum number of stages is greater than the number of stages of the temporary stack, one final stack may be generated without dividing the temporary stack.

상기 분할단계에서 상기 임시스택의 단수를 상기 최대단수로 나눈 값이 1을 초과하면, 상기 임시스택을 상기 최대단수로 분할하여 복수의 최종스택을 생성하도록 이루어질 수 있다.In the dividing step, if a value obtained by dividing the number of temporary stacks by the maximum number of stages exceeds 1, the temporary stack may be divided by the maximum number of stages to generate a plurality of final stacks.

상기 분할단계에서 상기 임시스택의 단수를 상기 최대단수로 나눈 나머지가 1이면, 상기 임시스택을 상기 최대단수-1로 분할하여 2개의 최종스택을 생성하도록 이루어질 수 있다.In the dividing step, if the remainder obtained by dividing the number of stages of the temporary stack by the maximum stage is 1, the temporary stack may be divided by the maximum stage - 1 to generate two final stacks.

상기 적재면적정보는 평면상에 배치된 상기 하나 이상의 최종스택의 총 폭 및 총 길이를 포함하고, 상기 짐칸면적정보는 짐칸의 폭 및 길이를 포함하여 이루어질 수 있다.The loading area information may include a total width and a total length of one or more final stacks disposed on a plane, and the luggage compartment area information may include a width and a length of a luggage compartment.

상기 확인단계는, 상기 하나 이상의 최종스택을 상기 PC 슬래브의 최대폭을 기준으로 오름차순으로 정렬하는 스택정렬단계; 상기 하나 이상의 최종스택의 총 폭이 상기 짐칸의 폭을 초과하지 않는 조건에서, 정렬된 상기 하나 이상의 최종스택을 차례대로 상기 평면상에 열과 행 순으로 배치하는 배치단계; 및 상기 하나 이상의 최종스택의 총 폭 및 총 길이가 짐칸의 폭 및 길이 이하인지 판단하는 판단단계를 포함하여 이루어질 수 있다.The checking step may include a stack sorting step of arranging the one or more final stacks in ascending order based on the maximum width of the PC slab; a arranging step of sequentially arranging the one or more final stacks in order of columns and rows on the plane under the condition that the total width of the one or more final stacks does not exceed the width of the luggage compartment; and determining whether the total width and total length of the one or more final stacks are less than or equal to the width and length of the luggage compartment.

상기 하나 이상의 최종스택에 대해 재작업(reshuffling work) 횟수를 아래 수식에 의해 계산하는 계산단계를 포함하고, A calculation step of calculating the number of reshuffling work for the one or more final stacks by the formula below,

Figure pat00002
Figure pat00002

여기서, Reshuffling Work는 재작업 횟수이고, Total number of movements는 최종스택이 설치순서대로 작업하기 위해 발생할 수 있는 이동횟수이고, Optimal number of movements는 최종스택이 설치순서대로 정렬되었을 때 발생하는 이동횟수일 수 있다.Here, Reshuffling Work is the number of reworks, Total number of movements is the number of movements that can occur for the final stack to work in the installation order, and Optimal number of movements is the number of movements that occur when the final stack is arranged in the installation order. can

상기 하나 이상의 최종스택에 대해 안정성(stability)을 아래 수식에 의해 계산하는 계산단계를 포함하고, A calculation step of calculating stability for the one or more final stacks by the formula below,

Figure pat00003
Figure pat00003

여기서, Stability of the ith Slab(%)는 최종스택에 있는 PC 슬래브 각각의 안정성이고, Area of the ith Slab는 최종스택에 있는 어느 하나의 PC 슬래브의 면적이고, Overlapping area of under Slab(s) and ith Slab는 최종스택에 있는 어느 하나의 PC 슬래브와 그 아래에 있는 PC 슬래브(들)의 겹친 면적일 수 있다.Here, Stability of the i th Slab (%) is the stability of each PC slab in the final stack, Area of the i th Slab is the area of any one PC slab in the final stack, and Overlapping area of under Slab (s ) and i th Slab may be the overlapping area of any one PC slab in the final stack and the PC slab(s) below it.

본 발명에 의하면, 생성단계, 슬래브정렬단계, 분할단계, 확인단계 및 계산단계를 수행함으로써, 주요 관리자들이 원하는 PC 슬래브 스택의 화물 적재 특성을 모두 반영하고, PC 슬래브 스택의 특성을 고려하여 운반될 수 있도록 계획하며, OSC 프로젝트에 특화된 적재 최적화를 달성하도록 이루어지는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법을 제공할 수 있게 된다.According to the present invention, by performing the generation step, slab alignment step, division step, confirmation step, and calculation step, all cargo loading characteristics of the PC slab stack desired by key managers are reflected, and transported in consideration of the characteristics of the PC slab stack It is possible to provide a method for optimizing the loading of precast concrete slab stacks to achieve load optimization specific to the OSC project.

도 1 및 도 2는 PC 슬래브 스택의 다양한 예를 나타내는 도면이다.
도 3A 및 도 3B는 본 발명의 일 실시예에 따른 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 순서도이다.
도 4는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 3 즉, 슬래브정렬단계에서 계산된 IBD 및 OBD를 나타내는 도면이다.
도 5는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 3 즉, 슬래브정렬단계에서 판단되는 던니지의 허용위치를 나타내는 도면이다.
도 6 및 도 7은 도 3B의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 4 즉, 스택정렬단계를 나타내는 도면이다.
도 8(a)는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 1의 일 예를 나타내는 도면이다.
도 8(b)는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 2 즉, 생성단계의 일 예를 나타내는 도면이다.
도 9는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 3 즉, 슬래브정렬단계의 일 예를 나타내는 도면이다.
도 10은 도 3B의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법의 Phase 5 즉, 확인단계의 일 예를 나타내는 도면이다.
1 and 2 are diagrams showing various examples of PC slab stacks.
3A and 3B are flowcharts of a method for optimizing cargo loading of a precast concrete slab stack according to an embodiment of the present invention.
FIG. 4 is a diagram showing IBD and OBD calculated in Phase 3, that is, the slab alignment step, of the method for optimizing the loading of a precast concrete slab stack of FIG. 3A.
FIG. 5 is a view showing the allowable position of dunage determined in Phase 3, that is, the slab alignment step, of the method of optimizing the cargo loading of the precast concrete slab stack of FIG. 3A.
6 and 7 are views showing Phase 4, that is, a stack alignment step, of the method for optimizing the loading of a precast concrete slab stack of FIG. 3B.
Figure 8 (a) is a diagram showing an example of Phase 1 of the method of optimizing the cargo loading of the precast concrete slab stack of Figure 3A.
Figure 8 (b) is a view showing an example of Phase 2, that is, the generation phase of the method of optimizing the cargo loading of the precast concrete slab stack of Figure 3A.
9 is a view showing an example of Phase 3, that is, a slab alignment step, of the method for optimizing the loading of a precast concrete slab stack of FIG. 3A.
FIG. 10 is a view showing an example of Phase 5, that is, a confirmation step, of the method for optimizing the loading of a precast concrete slab stack of FIG. 3B.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예들을 상세하게 설명하면 다음과 같다. 다만, 본 발명을 설명함에 있어서, 이미 공지된 기능 혹은 구성에 대한 설명은, 본 발명의 요지를 명료하게 하기 위하여 생략하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. However, in describing the present invention, descriptions of already known functions or configurations will be omitted to clarify the gist of the present invention.

본 발명의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)은, 주요 관리자들이 원하는 PC 슬래브 스택(100)의 화물 적재 특성을 모두 반영하고, PC 슬래브 스택(100)의 특성을 고려하여 운반될 수 있도록 계획하며, OSC 프로젝트에 특화된 적재 최적화를 달성하도록 이루어진다.The cargo loading optimization method (S100) of the precast concrete slab stack of the present invention reflects all the cargo loading characteristics of the PC slab stack 100 desired by key managers, and considers the characteristics of the PC slab stack 100 to be transported. This is done to achieve loading optimization specific to the OSC project.

공장의 생산 관리 책임자(production manager)가 PC 슬래브(101)를 쌓을(Stacking) 때 고려하는 6가지 고려사항은 아래 [표 1]과 같다. Six considerations that the production manager of the factory considers when stacking the PC slab 101 are shown in [Table 1] below.

ConsiderationConsideration TypeType DescriptionDescription Degree of ConsiderationDegree of Consideration FactoryFactory TransportTransport sitesite (C1) Stack stability(C1) Stack stability GoalGoal 피라미드 형태처럼 전체 하중을 안정하게 유지할 수 있는 형태가 바람직하다.A shape that can stably hold the entire load, such as a pyramid shape, is desirable. (C2) Installation Sequence of Slabs(C2) Installation Sequence of Slabs GoalGoal PC Slab Stack을 구성할 때, 설치 순서와 일치시키는 것이 바람직하다.When configuring the PC Slab Stack, it is desirable to match the installation order. ×× ×× (C3) Vertical Location of Dunnage(C3) Vertical Location of Dunnage ConstraintConstraint Dunnage의 상, 하 동일 좌표에 위치시킨다.Place it at the same coordinates above and below Dunnage. ×× (C4) Horizontal Location of Dunnage(C4) Horizontal Location of Dunnage ConstraintConstraint Dunnage는 최소 2개를 사용하며, PC의 양 끝에서 L/4~L/5지점에 위치시킨다.Dunnage uses at least two, and places them at L/4 ~ L/5 points at both ends of the PC. ×× (C5) Maximum number of PC Slab(C5) Maximum number of PC Slabs ConstraintConstraint 트레일러에 적재하기 위해서 PC Slab Stack의 적재 단수는 x단을 유지한다To load on the trailer, the number of loading stages of the PC Slab Stack is maintained at x stages. (C6) Dimension of PC Slab Stacks(C6) Dimension of PC Slab Stacks ConstraintConstraint 트레일러의 적재 규격(길이)을 넘어서 적재할 수 없다.It is not possible to load beyond the loading standard (length) of the trailer.

공장의 생산 관리 책임자가 PC 슬래브 스택(100)을 만들다 보면 C2와 C5, C6 등은 상대적으로 무시될 수 있어 OSC 프로젝트의 성공적 수행을 위한 효과적인 PC 슬래브 스택(100)을 만들기 어렵다. 또한, C1와 C2는 좋은 스택인지 평가하는데 활용될 수 있는 목표이고 C3~C6는 부재의 파손 방지와 법규 준수를 위해 PC 슬래브 스택(100)을 만들 때 반드시 지켜야 하는 제약(constraint)이다. 도 1 및 도 2는 PC 슬래브 스택(100)의 다양한 예를 나타내는 도면이다. 도 1에 도시된 바와 같이, 패널(Panel) 부재와 다르게 PC 슬래브 스택(100)은 던니지(200;dunnage)가 각각의 PC 슬래브(101) 사이에 포함되어야 한다. PC 슬래브(101)마다 기재된 번호(1,2,3,4,5)는 PC 슬래브(101)들을 구분하기 위한 임의의 숫자이다. When the production manager of the factory makes the PC slab stack 100, it is difficult to make an effective PC slab stack 100 for the successful execution of the OSC project because C2, C5, and C6 can be relatively ignored. In addition, C1 and C2 are targets that can be used to evaluate whether the stack is good, and C3 to C6 are constraints that must be observed when making the PC slab stack 100 to prevent damage to members and comply with laws. 1 and 2 are views showing various examples of the PC slab stack 100. As shown in FIG. 1, unlike a panel member, in the PC slab stack 100, a dunnage 200 must be included between each PC slab 101. The numbers 1, 2, 3, 4, and 5 written for each PC slab 101 are arbitrary numbers for distinguishing the PC slabs 101.

경화된 콘크리트는 운반 도중 충격으로 손상이 발생할 수 있으며, 손상이 심각한 경우 건설현장에서 사용할 수 없기 때문에 PC 슬래브 스택(100)을 생성할 때 완충 역할을 하는 던니지(200)가 필요하다. 도 1(b)에 도시된 바와 같이, 던니지(200)가 완충 역할을 효과적으로 발휘하기 위해서는 동일한 수직 선상과 수평 선상에 던니지(200)를 위치시켜야 한다. Hardened concrete may be damaged by impact during transportation, and if the damage is serious, it cannot be used at a construction site, so a dunage 200 that serves as a buffer when creating the PC slab stack 100 is required. As shown in FIG. 1(b), in order for the dunage 200 to effectively act as a buffer, the dunage 200 must be placed on the same vertical and horizontal lines.

도 1에 도시된 바와 같이, 던니지(200)의 관련 제약조건이 지켜지지 않는다면 PC 슬래브(101)는 운반 과정에서 심각한 손상을 입을 수 있기 때문에, PC 슬래브 스택(100)을 구성하는 부재들의 크기에 따라 PC 슬래브 스택(100)을 분할해야 하는 경우가 발생할 수 있다. 6가지 고려사항에 대한 구체적인 내용은 다음과 같다. As shown in FIG. 1, since the PC slab 101 can be seriously damaged during transportation if the related constraints of the Dunnage 200 are not observed, the size of the members constituting the PC slab stack 100 Depending on the case, the PC slab stack 100 needs to be divided. The details of the six considerations are as follows.

Stability of PC Slab Stack (C1)Stability of PC Slab Stack (C1)

도 2(a)에 도시된 바와 같이, 피라미드 형태나 박스 형태처럼 전체 하중을 안정하게 유지할 수 있는 형태가 바람직하다. 도 2(b)에 도시된 바와 같이, 역 피라미드 형태는 재작업(reshuffling)에서 좋은 성과를 보일 수 있지만 안정성 측면에서는 불리하다. PC 슬래브 스택(100)의 안정성(stability)이 70% 이상이면 안정하다고 간주할 수 있다. As shown in FIG. 2 (a), a shape capable of stably maintaining the entire load is preferable, such as a pyramid shape or a box shape. As shown in FIG. 2(b), the inverted pyramid shape can show good performance in reshuffling, but is disadvantageous in terms of stability. If the stability (stability) of the PC slab stack 100 is 70% or more, it can be considered stable.

Installation Sequence of Slabs (C2)Installation Sequence of Slabs (C2)

건설현장의 관리자가 PC 슬래브 스택(100)을 인수받아 설치 작업을 진행할 때 재작업(Reshuffling Work)이 최소로 발생할 수 있도록 PC 슬래브(101)의 설치 순서를 고려하여 PC 슬래브 스택(100)을 생성해야 한다. 도 2(a)에 도시된 바와 같이, 건설현장의 작업자는 PC 슬래브 스택(100)의 가장 맨 위의 3번 부재와 2번 부재를 지면에 내려놓고 1번 부재를 설치해야 하므로 재작업 2회를 겪게 된다. 도 2(b)에 도시된 바와 같이, 최적의 경우는 모두 한 번씩 설치하는 것이므로(3회), 재작업은 0회가 된다. 재작업 관점에서 도 2(b)를 더 좋은 PC 슬래브 스택(100)으로 볼 수 있다. When a construction site manager receives the PC slab stack 100 and proceeds with installation work, the PC slab stack 100 is created by considering the installation order of the PC slab 101 so that reshuffling work can occur to a minimum. Should be. As shown in FIG. 2 (a), the worker at the construction site must put down the topmost member 3 and member 2 of the PC slab stack 100 on the ground and install member 1, so rework is performed twice will experience As shown in FIG. 2(b), since the optimal case is to install all once (three times), rework becomes zero. From a rework perspective, Figure 2(b) can be viewed as a better PC slab stack 100.

Vertical Location of Dunnage (C3)Vertical Location of Dunnage (C3)

하나의 PC 슬래브 스택(100)에서 던니지(200)는 동일하게 수직으로 위치 되어야한다. 도 1(a)에 도시된 바와 같이, 던니지(200)의 상하 위치가 동일하지 않으면 운반 중 PC 슬래브(101)의 파손이 발생하기 때문이다. In one PC slab stack 100, the dunage 200 must be equally vertically positioned. As shown in FIG. 1(a), if the top and bottom positions of the dunage 200 are not the same, this is because the PC slab 101 is damaged during transportation.

Horizontal Location of Dunnage (C4)Horizontal Location of Dunnage (C4)

1개의 PC 슬래브(101)에 던니지(200)를 위치시킬 때, 던니지(200)의 위치는 PC 슬래브(101)의 양쪽 끝에서 L/4~L/5 지점에 있어야 한다. PC 슬래브(101)의 양쪽 끝 단 L/4~L/5의 던니지(200)가 위치했을 때 휨 모멘트에 대해서 가장 안정하기 때문이다. When placing the dunage 200 on one PC slab 101, the position of the dunage 200 should be at L/4 to L/5 points from both ends of the PC slab 101. This is because it is most stable against the bending moment when the dunnage 200 at both ends of L/4 to L/5 of the PC slab 101 is located.

Maximum number of PC Slab (C5)Maximum number of PC Slabs (C5)

트레일러(Flat-Trailer)에 PC 슬래브 스택(100)이 운반되기 위해서 최대단수를 초과하지 않아야 한다. PC 슬래브 스택(100)이 트레일러의 짐칸(TA)에 적재될 때, 적층 단수에 따라 운송효율을 유지할 수 있기 때문이다. In order for the PC slab stack 100 to be transported on a flat-trailer, the maximum number of stages must not be exceeded. This is because when the PC slab stack 100 is loaded in the luggage compartment TA of the trailer, transportation efficiency can be maintained according to the number of stacking stages.

Dimension of PC Slab Stacks (C6)Dimension of PC Slab Stacks (C6)

트레일러(Flat-Trailer)에 운반되기 위해서 PC 슬래브 스택(100)이 트레일러 규격에 대해 검토되어야 한다. 도로법에 의해 트레일러의 규격을 넘는 적재는 다른 차량과의 교통사고 위험이 있기 때문이다. In order to be transported on a trailer (Flat-Trailer), the PC slab stack 100 must be reviewed for trailer specifications. This is because there is a risk of traffic accidents with other vehicles if the load exceeds the trailer's specifications according to the Road Act.

도 3A 및 도 3B는 본 발명의 일 실시예에 따른 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 순서도이다. 3A and 3B are flowcharts of a method (S100) for optimizing the cargo loading of a precast concrete slab stack according to an embodiment of the present invention.

도 3A 및 도 3B에 도시된 바와 같이, 본 발명의 일 실시예에 따른 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)은 화물적재에 최적화된 프리캐스트 콘크리트 슬래브 스택을 생성하도록 이루어지며, 생성단계(S110), 슬래브정렬단계(S120), 분할단계(S130), 확인단계(S140) 및 계산단계(S150)를 포함한다. As shown in FIGS. 3A and 3B, the method for optimizing the cargo loading of a precast concrete slab stack according to an embodiment of the present invention (S100) is made to create a precast concrete slab stack optimized for cargo loading, It includes step S110, slab alignment step S120, division step S130, confirmation step S140 and calculation step S150.

도 3에 기재된 Phase 1은 생성단계(S110) 이전에 사용자가 입력값을 입력하는 단계이다. Phase 2는 생성단계(S110)를 의미한다. Phase 3는 슬래브정렬단계(S120)를 의미한다. Phase 4는 분할단계(S130)를 의미한다. Phase 5는 확인단계(S140)를 의미한다. Phase 6는 계산단계(S150)를 의미한다. 각 단계의 input, output, 그리고 related considerations는 아래 [표 2]와 같다. Phase 1 described in FIG. 3 is a step in which the user inputs an input value before the generating step (S110). Phase 2 means the generation step (S110). Phase 3 means the slab alignment step (S120). Phase 4 means the division step (S130). Phase 5 means a confirmation step (S140). Phase 6 means the calculation step (S150). The input, output, and related considerations of each stage are shown in [Table 2] below.

PhasePhase FunctionFunction InputInput OutputOutput ConsiderationConsideration 1One Input data and parametersInput data and parameters Project context, Expert judgmentProject context, expert judgment Slab dimension, trailer dimension, installation sequence, tolerance, max layer, offset between stacksSlab dimension, trailer dimension, installation sequence, tolerance, max layer, offset between stacks -- 22 Make a preliminary stack by toleranceMake a preliminary stack by tolerance Slab dimension, toleranceSlab dimension, tolerance Preliminary stackPreliminary stack C1C1 33 Develop a stack with stackability and installation sequenceDevelop a stack with stackability and installation sequence Preliminary stack, Slab dimension, installation sequencePreliminary stack, slab dimension, installation sequence Developed stackDeveloped stack C2, C3, C4C2, C3, C4 44 Divide stacks by maximum layerDivide stacks by maximum layer Developed stacks, maximum layerDeveloped stacks, maximum layer Finalized stacksFinalized stacks C5C5 55 Check loaderability of stacksCheck loaderability of stacks Finalized stacks, Trailer dimension, Finalized stacks, trailer dimensions, Loaderability for trailerLoaderability for trailers C6C6 66 Calculate and report metricsCalculate and report metrics Finalized stacks, loaderability for trailerFinalized stacks, loaderability for trailer Stability and reshuffling work for each stackStability and reshuffling work for each stack --

도 3A에 도시된 바와 같이, Phase 1에서 공장의 생산 관리 책임자는 운반할 PC 슬래브(101) 정보와 Tolerance, Maximum layer, Offset 값을 입력한다. 입력된 정보들 중 PC 슬래브(101) 정보는 Phase 2로 전달된다. PC 슬래브(101) 정보는 길이(length), 폭(width), 높이(height)와 같은 치수(dimension)와 설치순서를 포함한다. As shown in FIG. 3A, in Phase 1, the person in charge of production management of the factory inputs information on the PC slab 101 to be transported and Tolerance, Maximum layer, and Offset values. Among the input information, the PC slab 101 information is delivered to Phase 2. The PC slab 101 information includes dimensions such as length, width, and height, and an installation order.

Tolerance는 같은 PC 슬래브 스택(100)으로 묶일 수 있는 PC 슬래브(101)들의 허용되는 최대 면적 차이를 결정하며, PC 슬래브 스택(100)의 안정성(stability)을 일정 수준 이상으로 유지시키는 것과 동시에 생산 관리 책임자에게 여러 대안을 보여주기 위해 필요하다. Tolerance determines the allowable maximum area difference between PC slabs 101 that can be bundled into the same PC slab stack 100, maintains the stability of the PC slab stack 100 at a certain level or more, and simultaneously manages production. It is necessary to show the manager several alternatives.

Tolerance는 0~1, 0~100% 등의 단위로 입력될 수 있다. 일 예로, 생산 관리 책임자가 Tolerance를 30%로 설정하면 컴퓨터는 면적의 차이가 30% 이내인 PC 슬래브(101)들을 하나의 PC 슬래브 스택(100)으로 묶을 수 있다. Tolerance can be input in units of 0 to 1, 0 to 100%, and the like. For example, if the production manager sets Tolerance to 30%, the computer may group PC slabs 101 having a difference in area within 30% into one PC slab stack 100.

또한, 생산 관리 책임자는 부재 운반 과정에서의 전복 방지와 운송 법규 준수를 위해 하나의 PC 슬래브 스택(100)이 가질 수 있는 PC 슬래브(101)의 최대단수(maximum layer)를 결정한다. 일 예로, 최대단수가 3일 때, 1개의 PC 슬래브 스택(100)은 PC 슬래브(101)를 최대 3단까지 구성할 수 있다. In addition, the person in charge of production management determines the maximum number of PC slabs 101 that one PC slab stack 100 can have in order to prevent overturning in the member transportation process and to comply with transportation laws. For example, when the maximum number of stages is 3, one PC slab stack 100 can configure up to three stages of PC slabs 101.

Offset 값(Offset between stacks)은 상차, 운송 및 설치시 부재 파손을 방지하기 위해 PC 슬래브 스택(100) 간 띄어야 하는 거리를 의미하며, 생산 관리 책임자가 임의로 설정할 수 있도록 한다. Offset 값은 트레일러(Trailer)의 짐칸(TA) 위에 PC 슬래브 스택(100)이 상차될 때, PC 슬래브 스택(100) 간의 거리를 의미한다. Offset value (Offset between stacks) means a distance that must be separated between PC slab stacks 100 to prevent damage to members during loading, transportation and installation, and allows the production manager to arbitrarily set. The offset value means the distance between the PC slab stacks 100 when the PC slab stacks 100 are loaded on the luggage compartment TA of the trailer.

도 3A에 도시된 바와 같이, Phase 2 즉, 생성단계(S110)는 C1을 반영하며, 복수의 PC 슬래브(101) 중 기준면적정보를 만족하는 PC 슬래브(101)들로 PC 슬래브(101)들의 묶음 즉, 임시스택(100A;preliminary stack)을 생성한다. 기준면적정보는 아래 [수학식 1]을 만족한다. As shown in FIG. 3A, Phase 2, that is, the generation step (S110) reflects C1, and among the plurality of PC slabs 101, the PC slabs 101 that satisfy the reference area information are the number of PC slabs 101. A bundle, that is, a temporary stack (100A; preliminary stack) is created. The reference area information satisfies the following [Equation 1].

Figure pat00004
Figure pat00004

여기서, AREAPICKED는 복수의 PC 슬래브(101) 중 최대면적의 PC 슬래브(101)의 면적이고, AREAREMAIN은 복수의 PC 슬래브(101) 중 임시그룹에 속하지 않은 PC 슬래브(101)의 면적이고, Tolerance는 0~1의 사용자 입력값이다. Here, AREA PICKED is the area of the PC slab 101 of the maximum area among the plurality of PC slabs 101, and AREA REMAIN is the area of the PC slab 101 that does not belong to the temporary group among the plurality of PC slabs 101, Tolerance is a user input value between 0 and 1.

Tolerance는 0~100%의 사용자 입력값일 수도 있다. 이 경우 [수학식 1]은 아래와 같을 수 있다. Tolerance can also be a user input value from 0 to 100%. In this case, [Equation 1] may be as follows.

Figure pat00005
Figure pat00005

Tolerance가 0~100%의 사용자 입력값인 경우, Tolerance가 100이라면 이는 모든 PC 슬래브(101)는 하나의 PC 슬래브 스택(100)에 담길 수 있다는 의미이다. 이 경우, 설치 순서에 맞게 PC 슬래브(101)를 쌓을 수 있으므로 재작업(reshuffling) 측면에서 매우 유리하다. 그러나 안정성(stability) 측면에서는 불안정한 임시스택(100A)을 생성할 수 있으므로 매우 불리하다. When Tolerance is a user input value of 0 to 100%, if Tolerance is 100, it means that all PC slabs 101 can be contained in one PC slab stack 100. In this case, since the PC slabs 101 can be stacked according to the installation order, it is very advantageous in terms of reshuffling. However, in terms of stability, it is very disadvantageous because an unstable temporary stack 100A can be created.

반면, Tolerance가 0이면 PC 슬래브(101)의 면적을 기준으로 PC 슬래브(101)를 쌓을 수밖에 없으므로 임시스택(100A)은 가장 안정한 형태인 피라미드(Pyramid)와 동일한 박스(Box) 형태로 구성된다. 이 경우 안정성(stability) 측면에서는 유리하지만, 재작업(reshuffling) 측면에서 매우 불리하다. 따라서 생산 관리 책임자는 0과 100 사이의 tolerance 값을 입력하게 된다. On the other hand, if the Tolerance is 0, the PC slab 101 is inevitably stacked based on the area of the PC slab 101, so the temporary stack 100A is configured in the same box shape as the pyramid, which is the most stable shape. In this case, it is advantageous in terms of stability, but very disadvantageous in terms of reshuffling. Therefore, the production manager inputs a tolerance value between 0 and 100.

컴퓨터가 PC 슬래브(101)를 임시스택(100A)으로 생성하는 방법은 다음과 같다. 컴퓨터는 먼저 Phase 1을 통해 입력받은 정보를 이용해 각 PC 슬래브(101)의 면적을 아래 수식과 같이 계산하고, PC 슬래브(101)들을 내림차순으로 정렬(S111)한다. The method by which the computer creates the PC slab 101 as the temporary stack 100A is as follows. The computer first calculates the area of each PC slab 101 using the information received through Phase 1 as in the formula below, and arranges the PC slabs 101 in descending order (S111).

PC 슬래브(101)의 면적(Area) = 길이(length) × 폭(width)Area of PC slab 101 = Length × Width

이때 길이(length)는 PC 슬래브(101)의 장방향 길이이고, 폭(width)은 PC 슬래브(101)의 단방향 길이이다. 그 다음 컴퓨터는 모든 PC 슬래브(101)를 unstacked list에 포함시키고, 이들 중 가장 큰 면적을 가지는 PC 슬래브(101)(이하 '최대 슬래브')를 선택(S112)한다. At this time, the length (length) is the length of the PC slab 101 in the long direction, and the width (width) is the length of the PC slab 101 in one direction. Then, the computer includes all the PC slabs 101 in the unstacked list, and selects the PC slab 101 (hereinafter 'maximum slab') having the largest area among them (S112).

그리고 나서 unstacked list에 포함된 PC 슬래브(101) 중 아래 수식을 만족하는 PC 슬래브(101)들을 모두 찾고(S113), 최대 슬래브와 같이 묶어 임시스택(100A)으로 구성(S114)한다. Then, among the PC slabs 101 included in the unstacked list, all of the PC slabs 101 that satisfy the formula below are found (S113), and the temporary stack 100A is configured (S114) by grouping them together with the largest slab.

Area of a slab > Area of the picked slab × (1 - tolerance)Area of a slab > Area of the picked slab × (1 - tolerance)

도 3A에 도시된 바와 같이, 슬래브정렬단계(S120)는 임시스택(100A)에 속한 PC 슬래브(101)들 중 던니지(200)정보가 일치하는 PC 슬래브(101)들을 설치순서대로 정렬하는 단계이다. As shown in FIG. 3A, the slab sorting step (S120) is a step of arranging the PC slabs 101 whose Dunnage 200 information matches among the PC slabs 101 belonging to the temporary stack 100A in the order of installation am.

Phase 3에서 컴퓨터는 임시스택(100A)을 입력받아서 dunnage boundary(inner boundary for dunnage; IBD, outer boundary for dunnage; OBD), 그리고 설치순서(installation sequence)를 고려하여(C2, C3, C4 반영) 물리적으로 쌓을 수 있는 PC 슬래브 스택(100)을 생성한다. In Phase 3, the computer receives the temporary stack (100A) and considers the dunnage boundary (inner boundary for dunnage; IBD, outer boundary for dunnage; OBD) and the installation sequence (reflecting C2, C3, and C4). Create a PC slab stack 100 that can be stacked with

던니지(200)는 슬래브의 양쪽 끝에서 L/4~L/5 지점에 놓아야 하므로, 컴퓨터는 PC 슬래브(101)를 놓을 수 있는 PC 슬래브(101) 중앙에서 가장 가까운 위치(Inner bound)와 가장 먼 위치(Outer bound)를 아래 수식들에 의해 계산(S121)하고, 임시스택(100A)에 속한 모든 PC 슬래브(101)들의 던니지(200)정보가 일치하는지 판단(S122)한다. Since the Dunnage 200 must be placed at the L/4 to L/5 point at both ends of the slab, the computer is the closest position (Inner bound) to the center of the PC slab 101 where the PC slab 101 can be placed. The outer bound is calculated by the following formulas (S121), and it is determined whether the dunage 200 information of all PC slabs 101 belonging to the temporary stack 100A is identical (S122).

Figure pat00006
Figure pat00006

PC 슬래브(101) 아래의 던니지(200)는 반드시 inner bound와 outer bound 사이 즉, allowed position of dunnage에 위치해야 한다. The dunnage 200 under the PC slab 101 must be located between the inner bound and the outer bound, that is, in the allowed position of dunnage.

도 4는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 3 즉, 슬래브정렬단계(S120)에서 계산된 IBD 및 OBD를 나타내는 도면이다. 4 is a diagram showing IBD and OBD calculated in Phase 3, that is, the slab alignment step (S120) of the method for optimizing the cargo load of the precast concrete slab stack (S100) of FIG. 3A.

도 4에 도시된 바와 같이, PC 슬래브(101)의 면적(Area)은 4,000(=100×40), Inner bound는 25(=100/4), Outer bound는 30 (=(3×100)/10)이므로 던니지(200)는 길이(length) 방향으로 PC 슬래브(101)의 중심으로부터 25에서 30 사이에 떨어진 위치에 놓을 수 있다. As shown in FIG. 4, the area of the PC slab 101 is 4,000 (= 100 × 40), the inner bound is 25 (= 100/4), and the outer bound is 30 (= (3 × 100)/ 10), the dunage 200 can be placed at a distance between 25 and 30 from the center of the PC slab 101 in the length direction.

도 5는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 3 즉, 슬래브정렬단계(S120)에서 판단되는 던니지(200)의 허용위치를 나타내는 도면이다. FIG. 5 is a view showing the allowable position of the dunnage 200 determined in Phase 3 of the method for optimizing the loading of precast concrete slab stacks (S100) of FIG. 3A, that is, in the slab alignment step (S120).

도 5(a)에 도시된 바와 같이, 임시스택(100A) 안의 모든 던니지(200)가 허용위치(allowed position)가 겹쳐진다면, 이 임시스택(100A)은 어떤 방식으로 정렬되어도 쌓을 수 있다. 따라서 설치순서(installation sequence)대로 정렬(S124)하여 재작업 횟수(reshuffling work)를 최소화한다. As shown in FIG. 5(a), if all the dunnages 200 in the temporary stack 100A overlap in their allowed positions, the temporary stacks 100A can be stacked in any arrangement. Therefore, the number of reshuffling work is minimized by arranging in the installation sequence (S124).

도 5(b)에 도시된 바와 같이, 임시스택(100A)의 특정 PC 슬래브(101)의 던니지(200)를 다른 PC 슬래브(101)의 던니지(200)와 동일한 수평 위치에 놓을 수 없다면, 해당 PC 슬래브(101)는 임시스택(100A)에서 삭제되고 unstacked 슬래브 list로 반환(S123)되어 남은 다른 PC 슬래브(101)들과 함께 새로운 임시스택(100A)을 구성하는데 사용된다. 즉, 정렬단계에서, 던니지(200)정보가 불일치하는 PC 슬래브(101)는 임시스택(100A) 생성 이전으로 되돌려진다. As shown in FIG. 5(b), if the Dunnage 200 of a specific PC slab 101 of the temporary stack 100A cannot be placed in the same horizontal position as the Dunnage 200 of another PC slab 101 , the corresponding PC slab 101 is deleted from the temporary stack 100A, returned to the unstacked slab list (S123), and used to construct a new temporary stack 100A together with the remaining PC slabs 101. That is, in the sorting step, the PC slab 101 whose dunnage 200 information is inconsistent is returned to the state before the temporary stack 100A was created.

컴퓨터는 unstacked slab list에 있는 PC 슬래브(101)들이 모두 임시스택(100A)을 구성하고 설치순서대로 정렬될 때까지 Phase 2와 3의 과정을 반복한다. The computer repeats the processes of Phases 2 and 3 until all PC slabs 101 in the unstacked slab list form the temporary stack 100A and are aligned in the installation order.

즉, 정렬단계에서, 던니지(200)정보가 일치하는 PC 슬래브(101)들을 설치순서대로 정렬한 후 임시스택(100A)에 속하지 않은 PC 슬래브(101)의 존재 여부를 판단(S125)하고, 임시스택(100A)에 속하지 않은 PC 슬래브(101)의 존재가 확인되면, 생성단계(S110)에서 기준면적정보를 변경하여 임시스택(100A)을 더 생성하게 된다. 기준면적정보는 S113에서 자동으로 변경된다. That is, in the sorting step, after arranging the PC slabs 101 having matching Dunnage 200 information in the order of installation, it is determined whether there is a PC slab 101 that does not belong to the temporary stack 100A (S125), When the existence of the PC slab 101 that does not belong to the temporary stack 100A is confirmed, the temporary stack 100A is further created by changing the reference area information in the creation step S110. The reference area information is automatically changed in S113.

도 3B에 도시된 바와 같이, 분할단계(S130)는 임시스택(100A)을 최대단수 이하가 되도록 분할하여 하나 이상의 최종스택(100F)을 생성하는 단계이다. As shown in FIG. 3B, the division step (S130) is a step of generating one or more final stacks 100F by dividing the temporary stack 100A to be less than or equal to the maximum number of stages.

즉, 분할단계(S130)에서 컴퓨터는 임시스택(100A)들을 Phase 1에서 설정한 최대단수(maximum layer)를 고려하여 나눔으로써 운송을 위한 최종스택(100F;Finalized Stack)들을 생성한다. Phase 4는 C5을 반영한다. 임시스택(100A)은 Phase 1에서 입력한 최대단수(maximum layer) 이하가 되도록 나누어진다. That is, in the division step (S130), the computer divides the temporary stacks 100A in consideration of the maximum layer set in Phase 1 to generate finalized stacks 100F for transportation. Phase 4 mirrors C5. The temporary stack 100A is divided to be less than the maximum layer input in Phase 1.

분할단계(S130)에서 최대단수가 임시스택(100A)의 단수보다 크면, 임시스택(100A)을 분할하지 않고 1개의 최종스택(100F)을 생성한다. 일 예로, 최대단수가 4이고, 임시스택(100A)의 단수가 3이면, 임시스택(100A)이 최종스택(100F)으로 변환된다. In the dividing step S130, if the maximum number of stages is greater than the number of stages of the temporary stack 100A, one final stack 100F is created without dividing the temporary stack 100A. For example, if the maximum number of stages is 4 and the number of stages of the temporary stack 100A is 3, the temporary stack 100A is converted into the final stack 100F.

분할단계(S130)에서 임시스택(100A)의 단수를 최대단수로 나눈 값이 1을 초과하거나 0이면, 임시스택(100A)을 최대단수로 분할하여 복수의 최종스택(100F)을 생성한다. 일 예로, 최대단수가 4이고, 임시스택(100A)의 단수가 6이면, 4단의 최종스택(100F)과 2단의 최종스택(100F)이 생성된다. In the dividing step S130, if the value obtained by dividing the number of stages of the temporary stack 100A by the maximum number of stages exceeds 1 or is 0, the temporary stack 100A is divided into the maximum number of stages to generate a plurality of final stacks 100F. For example, if the maximum number of stages is 4 and the number of stages of the temporary stack 100A is 6, a 4-stage final stack 100F and a 2-stage final stack 100F are generated.

분할단계(S130)에서 임시스택(100A)의 단수를 최대단수로 나눈 나머지가 1이면, 임시스택(100A)을 최대단수-1로 분할하여 2개의 최종스택(100F)을 생성한다. 일 예로, 최대단수가 4이고, 임시스택(100A)의 단수가 5이면, 3단의 최종스택(100F)과 2단의 최종스택(100F)이 생성된다. In the division step S130, if the remainder obtained by dividing the number of stages of the temporary stack 100A by the maximum number of stages is 1, the temporary stack 100A is divided by the number of stages minus 1 to generate two final stacks 100F. For example, if the maximum number of stages is 4 and the number of stages of the temporary stack 100A is 5, a 3-stage final stack 100F and a 2-stage final stack 100F are generated.

도 3B에 도시된 바와 같이, 확인단계(S140)는 하나 이상의 최종스택(100F)의 적재면적정보를 생성하여 짐칸면적정보와 비교하는 단계이다. 즉, Phase 5는 모든 최종스택(100F)이 실제 트레일러(trailer)의 짐칸(TA)에 실릴 수 있는지 확인하기 위한 단계이다(C6 반영). As shown in FIG. 3B, the confirmation step (S140) is a step of generating loading area information of one or more final stacks 100F and comparing it with luggage compartment area information. That is, Phase 5 is a step for checking whether all the final stacks 100F can actually be loaded in the TA of the trailer (reflecting C6).

모든 최종스택(100F)이 트레일러의 짐칸(TA)에 실릴 수 없다면 생산 관리 책임자는 최대단수(maximum layer) 또는 tolerance를 조정하여 다른 스택 구성(stack configuration)을 테스트하거나 해당 트레일러의 짐칸(TA)에 싣는 PC 슬래브(101)들의 양을 줄여야 한다. If all of the final stacks (100F) cannot fit in the trailer's TA, the production manager can adjust the maximum layer or tolerance to test different stack configurations or load the trailer's TA. The amount of loaded PC slabs 101 should be reduced.

Phase 5는 트레일러에 싣는 최종스택(100F)의 정확한 위치를 지정하는 것이 아니라, 트레일러의 짐칸 면적(dimensions)을 파악하여 생성된 최종스택(100F)들이 트레일러의 짐칸(TA)에 실리는지 여부를 판단하는 단계이다. Phase 5 does not specify the exact location of the final stack (100F) loaded on the trailer, but determines whether the final stack (100F) created by figuring out the dimensions of the trailer is loaded on the TA of the trailer It is a step to

도 3B에 도시된 바와 같이, 확인단계(S140)는 스택정렬단계(S141), 배치단계(S142) 및 판단단계(S143)를 포함한다. As shown in FIG. 3B, the confirmation step (S140) includes a stack alignment step (S141), an arrangement step (S142), and a determination step (S143).

도 6 및 도 7은 도 3B의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 4 즉, 스택정렬단계(S141)를 나타내는 도면이다. 6 and 7 are diagrams showing Phase 4, that is, the stack alignment step (S141) of the method (S100) for optimizing the cargo loading of the precast concrete slab stack of FIG. 3B.

도 6(a)에 도시된 바와 같이, 스택정렬단계(S141)에서 컴퓨터는 우선 폭(width)을 기준으로 최종스택(100F)들을 오름차순으로 정렬한다. 이때 최종스택(100F)의 width는 최종스택(100F)에 포함된 PC 슬래브(101)들의 폭(width)의 최대값이다. As shown in FIG. 6(a), in the stack sorting step (S141), the computer first sorts the final stacks 100F in ascending order based on width. At this time, the width of the final stack 100F is the maximum of the widths of the PC slabs 101 included in the final stack 100F.

도 6(b), 도 6(c) 및 도 6(d)에 도시된 바와 같이, 배치단계(S142~S146)는 하나 이상의 최종스택(100F)의 총 폭이 짐칸(TA)의 폭을 초과하지 않는 조건(S143)에서, 정렬된 하나 이상의 최종스택(100F)을 차례대로 평면상에 열과 행 순으로 배치(S144)하는 단계이다. As shown in FIGS. 6(b), 6(c), and 6(d), in the arrangement step (S142 to S146), the total width of one or more final stacks 100F exceeds the width of the luggage compartment TA. Under the condition (S143) not to do so, it is a step of arranging one or more sorted final stacks 100F in order of columns and rows on a plane (S144).

어느 하나의 최종스택(100F)이 배치되면, 남은 최종스택(100F)이 존재하는지 여부를 판단(S146)하고 남은 최종스택(100F) 중 다음 최종스택(100F)을 순서대로 선택(S142)하여 트레일러 짐칸(TA)의 상단 좌측(upper left)에 배치하게 된다. When one final stack (100F) is arranged, it is determined whether the remaining final stacks (100F) exist (S146), and the next final stack (100F) among the remaining final stacks (100F) is selected in order (S142) to trailer the trailer. It is placed in the upper left of the luggage compartment (TA).

도 6(b)에 도시된 바와 같이, 컴퓨터는 첫 번째 최종스택(S1) 즉, 가장 작은 폭(width)를 가진 최종스택(S1)부터 순서대로 선택(S142)하여 트레일러 짐칸(TA)의 상단 좌측(upper left)에 최종스택(S1)을 배치한다. As shown in FIG. 6(b), the computer sequentially selects (S142) the first final stack (S1), that is, the final stack (S1 with the smallest width), and places the top of the trailer luggage compartment (TA). Arrange the final stack (S1) on the upper left.

도 7(c)에 도시된 바와 같이, 최종스택(S1)이 배치되고 남은 트레일러의 짐칸 폭(width)이 배치할 최종스택(S2)의 폭(width)보다 작다면, 도 7(d)에 도시된 바와 같이, 이미 배치된 최종스택(S1) 오른쪽 공간(A1)은 사용 불가능한 것으로 지정(S135)하고, 배치된 최종스택(S1) 아래 공간에 그 다음 최종스택(S2)을 배치한다. 이와 마찬가지로 배치된 최종스택(S2) 아래 공간에 그 다음 최종스택(S3)을 배치한다. As shown in FIG. 7(c), if the width of the luggage compartment of the remaining trailer after the final stack S1 is disposed is smaller than the width of the final stack S2 to be disposed, in FIG. 7(d) As shown, the space A1 to the right of the previously arranged final stack S1 is designated as unusable (S135), and the next final stack S2 is disposed in the space below the arranged final stack S1. Likewise, the next final stack S3 is disposed in the space below the final stack S2 arranged in the same manner.

도 6(d) 및 도 7(d)에 도시된 바와 같이, 판단단계(S147)는 하나 이상의 최종스택(100F)의 총 폭 및 총 길이가 짐칸(TA)의 폭 및 길이 이하인지 판단하는 단계이다. As shown in FIGS. 6(d) and 7(d), the determination step (S147) is a step of determining whether the total width and total length of one or more final stacks 100F are less than or equal to the width and length of the luggage compartment TA. am.

모든 최종스택(100F)들의 배치가 끝나면 트레일러 짐칸(TA)의 짐칸면적정보와 배치된 최종스택(100F)들의 적재면적정보를 비교하여, 최종스택(100F)들을 트레일러의 짐칸(TA)에 적재할 수 있는 지의 여부(loaderability)를 판단한다. After all the final stacks (100F) are arranged, the cargo area information of the trailer luggage compartment (TA) and the loading area information of the final stacks (100F) are compared to load the final stacks (100F) into the luggage compartment (TA) of the trailer. Determine whether it is possible (loaderability).

적재면적정보는 평면상에 배치된 하나 이상의 최종스택(100F)의 총 폭 및 총 길이를 포함하고, 짐칸면적정보는 짐칸(TA)의 폭 및 길이를 포함한다. 도 7(d)에 도시된 바와 같이, 하나 이상의 최종스택(100F)의 총 폭 및 총 길이가 짐칸(TA)의 규격을 초과한 경우, 생산 관리 책임자에게 추가적인 트레일러가 필요할 수 있음을 출력한다. The loading area information includes the total width and total length of one or more final stacks 100F disposed on a plane, and the luggage compartment area information includes the width and length of the luggage compartment TA. As shown in FIG. 7(d), when the total width and total length of one or more final stacks 100F exceed the specifications of the luggage compartment TA, it is output that an additional trailer may be needed to the person in charge of production management.

도 3B에 도시된 바와 같이, 계산단계(S150)는 하나 이상의 최종스택(100F)에 대해 재작업(reshuffling work) 횟수 및 안정성(stability)을 계산(S151)하고 리포트(S152)하는 단계이다. As shown in FIG. 3B, the calculation step (S150) is a step of calculating (S151) and reporting (S152) the number of reshuffling work and stability for one or more final stacks 100F.

하나 이상의 최종스택(100F)에 대해 재작업(reshuffling work) 횟수를 아래 [수학식 2]에 의해 계산한다. The number of reshuffling work for one or more final stacks (100F) is calculated by [Equation 2] below.

Figure pat00007
Figure pat00007

여기서, Reshuffling Work는 재작업 횟수이고, Total number of movements는 최종스택(100F)이 설치순서대로 작업하기 위해 발생할 수 있는 이동횟수이고, Optimal number of movements는 최종스택(100F)이 설치순서대로 정렬되었을 때 발생하는 이동횟수이다. Here, Reshuffling Work is the number of reworks, Total number of movements is the number of movements that can occur for the final stack (100F) to work in the order of installation, and Optimal number of movements is the number of times the final stack (100F) is arranged in the order of installation. is the number of moves that occur when

하나 이상의 최종스택(100F)에 대해 안정성(stability)을 아래 [수학식 3]에 의해 계산한다. The stability of one or more final stacks 100F is calculated by [Equation 3] below.

Figure pat00008
Figure pat00008

여기서, Stability of the ith Slab(%)는 최종스택(100F)에 있는 PC 슬래브(101) 각각의 안정성이고, Area of the ith Slab는 최종스택(100F)에 있는 어느 하나의 PC 슬래브(101)의 면적이고, Overlapping area of under Slab(s) and ith Slab는 최종스택(100F)에 있는 어느 하나의 PC 슬래브(101)와 그 아래에 있는 PC 슬래브(101)들의 겹친 면적이다. Here, Stability of the i th Slab (%) is the stability of each PC slab 101 in the final stack (100F), and Area of the i th Slab is any one PC slab 101 in the final stack (100F) ), and the overlapping area of under slab(s) and i th slab is the overlapping area of one PC slab 101 in the final stack 100F and the PC slabs 101 below it.

생산 관리 책임자는 리포트 결과에 따라 PC 슬래브(101) 정보와 parameter들을 조절(S153)할 수 있다. 본 발명의 일 실시예에 따른 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)은 조건에 맞는 PC 슬래브 스택(100)들을 빠르게 생성하고 이를 출력함으로써 생산 관리 책임자의 스택 쌓기(stacking) 의사결정을 지원할 수 있다. The person in charge of production management may adjust PC slab 101 information and parameters according to the report result (S153). The method for optimizing the loading of precast concrete slab stacks (S100) according to an embodiment of the present invention quickly creates PC slab stacks 100 that meet conditions and outputs them, thereby enabling the production manager to make stacking decisions. can support

도 8(a)는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 1의 일 예를 나타내는 도면이다. 도 8(b)는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 2 즉, 생성단계(S110)의 일 예를 나타내는 도면이다. Figure 8 (a) is a diagram showing an example of Phase 1 of the method (S100) of optimizing the cargo loading of the precast concrete slab stack of Figure 3A. 8(b) is a view showing an example of Phase 2, that is, the generation step (S110) of the method (S100) for optimizing the cargo loading of the precast concrete slab stack of FIG. 3A.

도 9는 도 3A의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 3 즉, 슬래브정렬단계(S120)의 일 예를 나타내는 도면이다. 도 10B은 도 3의 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 Phase 5 즉, 확인단계(S140)의 일 예를 나타내는 도면이다. 9 is a diagram showing an example of Phase 3, that is, a slab alignment step (S120) of the method (S100) for optimizing the loading of a precast concrete slab stack of FIG. 3A. 10B is a view showing an example of Phase 5, that is, the confirmation step (S140) of the method (S100) for optimizing the cargo loading of the precast concrete slab stack of FIG.

도 8 및 도 9에 도시된 바와 같이, Tolerence는 30, 최대단수(Maximum layer)는 4로 입력하였을 때, phase 2와 phase 3을 3회 정도 반복하여 임시스택(100A)을 생성한다. 8 and 9, when tolerance is 30 and maximum layer is 4, phase 2 and phase 3 are repeated about three times to create a temporary stack (100A).

도 10에 도시된 바와 같이, 3개의 임시스택(100A)은 트레일러(trailer)의 짐칸(TA)에 적재 가능한지 체크하고, 지표인 안정성(stability)과 재작업(Reshuffling work) 횟수를 출력한다. As shown in FIG. 10, the three temporary stacks 100A check whether the trailer can be loaded into the TA, and output stability and the number of reshuffling work as indicators.

도 8 내지 도 10에 도시된 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)의 결과는 PC 슬래브 스택(100) 3개, 트레일러에 적재 가능, 안정성은 PC 슬래브 스택1(S1)이 81%, PC 슬래브 스택2(S2)가 92%, PC 슬래브 스택3(S3)는 100%를 나타내며, 재작업 횟수는 0회, Error는 0개를 나타낸다. The result of the cargo loading optimization method (S100) of the precast concrete slab stack shown in FIGS. 8 to 10 is that three PC slab stacks (100) can be loaded on a trailer, and the stability is 81% for PC slab stack 1 (S1). , PC slab stack 2 (S2) represents 92%, PC slab stack 3 (S3) represents 100%, the number of reworks is 0, and the number of errors is 0.

본 발명에 의하면, 생성단계(S110), 슬래브정렬단계(S120), 분할단계(S130), 확인단계(S140) 및 계산단계(S150)를 수행함으로써, 주요 관리자들이 원하는 PC 슬래브 스택(100)의 화물 적재 특성을 모두 반영하고, PC 슬래브 스택(100)의 특성을 고려하여 운반될 수 있도록 계획하며, OSC 프로젝트에 특화된 적재 최적화를 달성하도록 이루어지는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법(S100)을 제공할 수 있게 된다.According to the present invention, by performing the generation step (S110), slab alignment step (S120), division step (S130), confirmation step (S140), and calculation step (S150), the PC slab stack 100 desired by the main managers The cargo loading optimization method (S100) of the precast concrete slab stack, which reflects all cargo loading characteristics, plans to be transported in consideration of the characteristics of the PC slab stack 100, and achieves loading optimization specific to the OSC project be able to provide

앞에서, 본 발명의 특정한 실시예가 설명되고 도시되었지만 본 발명은 기재된 실시예에 한정되는 것이 아니고, 본 발명의 사상 및 범위를 벗어나지 않고 다양하게 수정 및 변형할 수 있음은 이 기술의 분야에서 통상의 지식을 가진 자에게 자명한 일이다. 따라서, 그러한 수정예 또는 변형예들은 본 발명의 기술적 사상이나 관점으로부터 개별적으로 이해되어서는 안되며, 변형된 실시예들은 본 발명의 특허청구범위에 속한다 하여야 할 것이다.In the foregoing, although specific embodiments of the present invention have been described and shown, the present invention is not limited to the described embodiments, and it is common knowledge in the art that various modifications and variations can be made without departing from the spirit and scope of the present invention. It is self-evident to those who have Therefore, such modifications or variations should not be individually understood from the technical spirit or viewpoint of the present invention, and modified embodiments should fall within the scope of the claims of the present invention.

S100 : 화물적재 최적화 방법
S110 : 생성단계
S120 : 슬래브정렬단계
S130 : 분할단계
S140 : 확인단계
S141 : 스택정렬단계
S142 : 배치단계
S143 : 판단단계
S150 : 계산단계
100 : PC 슬래브 스택
100A : 임시스택
100F : 최종스택
101 : PC 슬래브
200 : 던니지
S100: How to optimize cargo loading
S110: Generation step
S120: slab alignment step
S130: division step
S140: Confirmation step
S141: stack alignment step
S142: arrangement step
S143: Judgment step
S150: Calculation step
100: PC slab stack
100A: temporary stack
100F: final stack
101: PC slab
200: Dunnage

Claims (11)

복수의 PC 슬래브 중 기준면적정보를 만족하는 상기 PC 슬래브들로 임시스택을 생성하는 생성단계;
상기 임시스택에 속한 상기 PC 슬래브들 중 던니지정보가 일치하는 상기 PC 슬래브들을 설치순서대로 정렬하는 슬래브정렬단계;
상기 임시스택을 최대단수 이하가 되도록 분할하여 하나 이상의 최종스택을 생성하는 분할단계; 및
상기 하나 이상의 최종스택의 적재면적정보를 생성하여 짐칸면적정보와 비교하는 확인단계를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
a creation step of generating a temporary stack with PC slabs that satisfy reference area information among a plurality of PC slabs;
a slab sorting step of arranging the PC slabs having the same Dunnage information among the PC slabs belonging to the temporary stack in an installation order;
a division step of generating one or more final stacks by dividing the temporary stack to be less than or equal to the maximum number of stages; and
The cargo loading optimization method of the precast concrete slab stack, characterized in that it comprises a confirmation step of generating the loading area information of the one or more final stacks and comparing them with the cargo area information.
제1항에 있어서,
상기 정렬단계에서, 상기 던니지정보가 일치하는 상기 PC 슬래브들을 설치순서대로 정렬한 후 상기 임시스택에 속하지 않은 상기 PC 슬래브의 존재 여부를 판단하고,
상기 임시스택에 속하지 않은 상기 PC 슬래브의 존재가 확인되면, 상기 생성단계에서 상기 기준면적정보를 변경하여 상기 임시스택을 더 생성하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
In the sorting step, after arranging the PC slabs matching the Dunnage information in the order of installation, determining whether the PC slabs that do not belong to the temporary stack exist;
When the presence of the PC slab that does not belong to the temporary stack is confirmed, the cargo loading optimization method of the precast concrete slab stack, characterized in that to further create the temporary stack by changing the reference area information in the generating step.
제1항에 있어서,
상기 기준면적정보는 아래 수식을 만족하고,
Figure pat00009

여기서, AREAPICKED는 복수의 PC 슬래브 중 최대면적의 PC 슬래브의 면적이고, AREAREMAIN은 복수의 PC 슬래브 중 임시그룹에 속하지 않은 PC 슬래브의 면적이고, Tolerance는 0~1의 사용자 입력값인 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
The reference area information satisfies the following formula,
Figure pat00009

Here, AREA PICKED is the area of the PC slab with the maximum area among the plurality of PC slabs, AREA REMAIN is the area of the PC slab that does not belong to the temporary group among the plurality of PC slabs, and Tolerance is a user input value of 0 to 1. A method for optimizing the loading of precast concrete slab stacks using
제1항에 있어서,
상기 정렬단계에서, 상기 던니지정보가 불일치하는 상기 PC 슬래브는 상기 임시스택 생성 이전으로 되돌려지는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
In the aligning step, the PC slab for which the dunnage information is inconsistent is returned to a state before the temporary stack is created.
제1항에 있어서,
상기 분할단계에서 상기 최대단수가 상기 임시스택의 단수보다 크면, 상기 임시스택을 분할하지 않고 1개의 최종스택을 생성하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
In the dividing step, if the maximum number of stages is greater than the number of stages of the temporary stack, one final stack is generated without dividing the temporary stack.
제1항에 있어서,
상기 분할단계에서 상기 임시스택의 단수를 상기 최대단수로 나눈 값이 1을 초과하면, 상기 임시스택을 상기 최대단수로 분할하여 복수의 최종스택을 생성하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
In the dividing step, if the value obtained by dividing the number of stages of the temporary stack by the maximum number of stages exceeds 1, the temporary stack is divided by the maximum number of stages to generate a plurality of final stacks. method.
제1항에 있어서,
상기 분할단계에서 상기 임시스택의 단수를 상기 최대단수로 나눈 나머지가 1이면, 상기 임시스택을 상기 최대단수-1로 분할하여 2개의 최종스택을 생성하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
In the dividing step, if the remainder of dividing the number of stages of the temporary stack by the maximum number of stages is 1, the temporary stack is divided by the maximum number of stages -1 to create two final stacks. optimization method.
제1항에 있어서,
상기 적재면적정보는 평면상에 배치된 상기 하나 이상의 최종스택의 총 폭 및 총 길이를 포함하고,
상기 짐칸면적정보는 짐칸의 폭 및 길이를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
The loading area information includes a total width and a total length of the one or more final stacks disposed on a plane,
The load optimization method of the precast concrete slab stack, characterized in that the luggage area information includes the width and length of the luggage compartment.
제1항에 있어서,
상기 확인단계는,
상기 하나 이상의 최종스택을 상기 PC 슬래브의 최대폭을 기준으로 오름차순으로 정렬하는 스택정렬단계;
상기 하나 이상의 최종스택의 총 폭이 상기 짐칸의 폭을 초과하지 않는 조건에서, 정렬된 상기 하나 이상의 최종스택을 차례대로 상기 평면상에 열과 행 순으로 배치하는 배치단계; 및
상기 하나 이상의 최종스택의 총 폭 및 총 길이가 짐칸의 폭 및 길이 이하인지 판단하는 판단단계를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
The verification step is
A stack sorting step of arranging the one or more final stacks in ascending order based on the maximum width of the PC slab;
a arranging step of sequentially arranging the one or more final stacks in order of columns and rows on the plane under the condition that the total width of the one or more final stacks does not exceed the width of the luggage compartment; and
A method for optimizing cargo loading of a precast concrete slab stack, characterized in that it comprises a determining step of determining whether the total width and total length of the at least one final stack are less than or equal to the width and length of the luggage compartment.
제1항에 있어서,
상기 하나 이상의 최종스택에 대해 재작업(reshuffling work) 횟수를 아래 수식에 의해 계산하는 계산단계를 포함하고,
Figure pat00010

여기서, Reshuffling Work는 재작업 횟수이고, Total number of movements는 최종스택이 설치순서대로 작업하기 위해 발생할 수 있는 이동횟수이고, Optimal number of movements는 최종스택이 설치순서대로 정렬되었을 때 발생하는 이동횟수인 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
A calculation step of calculating the number of reshuffling work for the one or more final stacks by the formula below,
Figure pat00010

Here, Reshuffling Work is the number of reworks, Total number of movements is the number of movements that can occur for the final stack to work in the installation order, and Optimal number of movements is the number of movements that occur when the final stack is arranged in the installation order. Method for optimizing cargo loading of a precast concrete slab stack, characterized in that.
제1항에 있어서,
상기 하나 이상의 최종스택에 대해 안정성(stability)을 아래 수식에 의해 계산하는 계산단계를 포함하고,
Figure pat00011

여기서, Stability of the ith Slab(%)는 최종스택에 있는 PC 슬래브 각각의 안정성이고, Area of the ith Slab는 최종스택에 있는 어느 하나의 PC 슬래브의 면적이고, Overlapping area of under Slab(s) and ith Slab는 최종스택에 있는 어느 하나의 PC 슬래브와 그 아래에 있는 PC 슬래브(들)의 겹친 면적인 것을 특징으로 하는 프리캐스트 콘크리트 슬래브 스택의 화물적재 최적화 방법.
According to claim 1,
A calculation step of calculating stability for the one or more final stacks by the formula below,
Figure pat00011

Here, Stability of the i th Slab (%) is the stability of each PC slab in the final stack, Area of the i th Slab is the area of any one PC slab in the final stack, and Overlapping area of under Slab (s ) and i th Slab is a method for optimizing cargo loading of a precast concrete slab stack, characterized in that the overlapped area of any one PC slab in the final stack and the PC slab (s) below it.
KR1020210153100A 2021-11-09 2021-11-09 Optimization method of precast concrete slab stacks for transportation KR20230067228A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210153100A KR20230067228A (en) 2021-11-09 2021-11-09 Optimization method of precast concrete slab stacks for transportation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210153100A KR20230067228A (en) 2021-11-09 2021-11-09 Optimization method of precast concrete slab stacks for transportation

Publications (1)

Publication Number Publication Date
KR20230067228A true KR20230067228A (en) 2023-05-16

Family

ID=86546049

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210153100A KR20230067228A (en) 2021-11-09 2021-11-09 Optimization method of precast concrete slab stacks for transportation

Country Status (1)

Country Link
KR (1) KR20230067228A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111445180A (en) 2020-03-23 2020-07-24 海南金盘智能科技股份有限公司 Method and device for optimizing goods placement mode in freight vehicle and electronic equipment

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111445180A (en) 2020-03-23 2020-07-24 海南金盘智能科技股份有限公司 Method and device for optimizing goods placement mode in freight vehicle and electronic equipment

Similar Documents

Publication Publication Date Title
US7835810B2 (en) Tools and methods for designing a structure using prefabricated panels
US7123988B2 (en) System and apparatus for materials transport and storage
KR20230067228A (en) Optimization method of precast concrete slab stacks for transportation
Park et al. Mathematical modeling and solving procedure of the planar storage location assignment problem
Lee et al. Automated generation of precast concrete slab stacks for transportation in offsite construction projects
JP2023524443A (en) Optimizing the operating capacity of container handling vehicles assigned to interact with the same ports for transferring storage containers to and from automated storage and retrieval systems. good use
JP5444622B2 (en) Yard operation planning apparatus and operation method
JP2006309610A (en) Construction work planning system for building
US6760642B2 (en) Parts placement calculation system
KR20020061293A (en) Method for dispatching a transporter of a port container terminal
KR20230087115A (en) Automatic method of precast concrete component allocation plan
Phan et al. Discrete-event simulation-based decision making of Just-In-Time strategies for precast concrete supply chain using batch delivery and offsite inventory level
JP2020046813A (en) Laminated body forming apparatus
KR101192486B1 (en) Panel Piling Management System
CN110728407A (en) Method and device for assembling goods
JP2019175215A (en) Production sequence creating method
JPH0259259A (en) Production indication system
CN116090220B (en) Logistics simulation load distribution method for automobile parts
US20230062204A1 (en) Cargo handling work creation device and cargo handling work creation method
JP3198082B2 (en) Panel production system
JP2000170307A (en) Manufacture of roof panel and designing device of roof panel
Wong et al. Weight management considerations for onshore modularized petrochemical facilities
JP2606906B2 (en) Method of rearranging the transfer order of workpieces on the line
JP2009166938A (en) Truck berth specification determination system, its program, and recording medium
CN114065441A (en) Simulation optimization method of hydraulic support part machining complete production line based on digital factory

Legal Events

Date Code Title Description
E902 Notification of reason for refusal