KR20230059331A - project management system - Google Patents

project management system Download PDF

Info

Publication number
KR20230059331A
KR20230059331A KR1020210143411A KR20210143411A KR20230059331A KR 20230059331 A KR20230059331 A KR 20230059331A KR 1020210143411 A KR1020210143411 A KR 1020210143411A KR 20210143411 A KR20210143411 A KR 20210143411A KR 20230059331 A KR20230059331 A KR 20230059331A
Authority
KR
South Korea
Prior art keywords
project
information
unit
management
module
Prior art date
Application number
KR1020210143411A
Other languages
Korean (ko)
Inventor
이준호
최석준
Original Assignee
최석준
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최석준 filed Critical 최석준
Priority to KR1020210143411A priority Critical patent/KR20230059331A/en
Publication of KR20230059331A publication Critical patent/KR20230059331A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • G06Q10/1093Calendar-based scheduling for persons or groups

Abstract

본 발명은 프로젝트 관리 시스템에 있어서, 다수 개의 사용자단말기; 상기 사용자단말기를 통해 접근가능하며, 프로젝트의 정보를 제공하는 서버; 상기 서버에 저장된 상기 프로젝트의 정보를 관리할 수 있도록 상기 서버에 연결된 관리자단말기를 포함하며, 상기 서버는, 상기 프로젝트의 정보 관리를 위한 양식을 포함하는 기준정보모듈과, 상기 기준정보모듈을 통해 세분화된 상기 프로젝트의 과제 및 일정 현황을 확인가능한 프로젝트정보관리모듈과, 상기 프로젝트의 진행을 통해 각 과제에서 생성되는 실적을 관리하는 프로젝트실적관리모듈과, 상기 프로젝트의 현황을 표시하는 대시보드모듈과, 각각의 상기 사용자단말기에 적합하게 환경설정이 가능한 환경설정모듈을 포함하는 것을 기술적 요지로 한다. 이에 의해 프로젝트의 진행 현황 또는 프로젝트를 수행 중 발생된 문제점을 실시간으로 파악할 수 있으며, 이를 통해 프로젝트로 인한 제품의 생산성이 향상될 수 있는 효과를 얻을 수 있다.The present invention is a project management system comprising: a plurality of user terminals; A server accessible through the user terminal and providing project information; It includes a manager terminal connected to the server to manage information of the project stored in the server, wherein the server includes a standard information module including a form for managing information of the project, and subdivided through the standard information module. A project information management module capable of checking the status of tasks and schedules of the project, a project performance management module managing performance generated from each task through the progress of the project, and a dashboard module displaying the current status of the project; It is a technical point to include an environment setting module capable of environment setting suitable for each of the user terminals. As a result, it is possible to grasp the progress of the project or problems occurring during the execution of the project in real time, and through this, the effect of improving the productivity of the product due to the project can be obtained.

Description

프로젝트 관리 시스템{project management system}Project management system {project management system}

본 발명은 프로젝트 관리 시스템에 관한 것으로, 보다 상세하게는 프로젝트의 진행 현황 또는 프로젝트를 수행 중 발생된 문제점을 실시간으로 파악할 수 있으며, 이를 통해 프로젝트로 인한 제품의 생산성이 향상될 수 있는 프로젝트 관리 시스템에 관한 것이다.The present invention relates to a project management system, and more particularly, to a project management system capable of grasping the progress of a project or problems occurring during the project in real time, through which the productivity of products due to the project can be improved. it's about

산업 제조 환경에서 공정의 효율을 증대시키기 위하여, 예컨대 사이클 타임을 줄이고 처리량을 늘리며 장비 활용을 개선하기 위해 제조 프로세스의 정확한 제어가 중요하다. 비효율적인 프로세스 제어는 제품들의 제조 기한을 놓치도록 유도하거나 요구되는 수율과 품질 레벨들을 만족시키지 못할 수 있으며, 늘어난 원료 사용과 인건비 등으로 인해 비용들을 현저하게 증가시키게 된다는 문제점이 있다. 따라서 이러한 문제점을 해결하기 위해 제조업체는 제품 개발 및 제조에 대한 각 업무별 계획 대비 실적 등 전반적인 진도관리 대응과, 업무별로 작성되는 인적, 물적, 산출물, 이슈, 각종 현황 등이 입력되는 정보의 관리로 업무 간 신속한 처리를 위한 정보공유 대응이 필요한 실정이다.In an industrial manufacturing environment, accurate control of the manufacturing process is important to increase process efficiency, such as to reduce cycle times, increase throughput, and improve equipment utilization. Inefficient process control may lead to missed manufacturing deadlines or may not satisfy required yield and quality levels, and significantly increase costs due to increased use of raw materials and labor costs. Therefore, in order to solve these problems, manufacturers respond to overall progress management, such as plans and performances for each task for product development and manufacturing, and manage information written by task such as human, physical, output, issues, and various current status. It is necessary to respond to information sharing for prompt processing between tasks.

대부분의 기업들은 한정된 인적, 물적 자원으로 프로젝트를 추진하고 있으며, 프로젝트의 실용화, 일정 단축, 효율적 추진에 대한 개발이 필요한 실정이다. 프로젝트 관리를 위해 기업들은 기술개발 로드맵, 중장기 기술개발전략 등과 같은 기술개발 전략에 준하여 각 프로젝트의 자원 배분을 위해 인력, 투자비, 개발목표에 관한 기본적인 범위를 정하여 진행하여야 하는데, 자원 배분을 위해 기업 내부 인력의 보유역량 수준 파악 또는 기술 축적이 되지 않는다는 문제점이 있다.Most companies are promoting projects with limited human and material resources, and it is necessary to develop projects for commercialization, schedule reduction, and efficient promotion. For project management, companies must set and proceed with the basic scope of manpower, investment cost, and development goal for resource allocation of each project in accordance with technology development strategies such as technology development roadmap and mid- to long-term technology development strategy. There is a problem that it is not possible to grasp the level of manpower possessed or to accumulate skills.

따라서 프로젝트의 성공적인 완수를 위해 프로젝트와 관련된 작업자들은 프로젝트의 가시성 확보, 의사결정 지원, 효율성 향상이 가능한 기술이 필요한 실정으로, 프로젝트 진행현황을 실시간으로 적기에 확인하여 프로젝트 수행시 발생하는 문제에 대해 신속히 대응하고 의사결정을 할 수 있으며, 역할과 업무의 분담으로 프로젝트 진척의 투명성을 확보하고 산출물의 통합관리를 위한 프로젝트 관리 시스템의 구축이 필요한 실정이다.Therefore, for the successful completion of the project, project workers need technology to secure project visibility, support decision-making, and improve efficiency. It is necessary to respond and make decisions, secure transparency of project progress through division of roles and tasks, and establish a project management system for integrated management of outputs.

대한민국특허청 등록특허 제10-1837021호Korea Intellectual Property Office Registration Patent No. 10-1837021

본 발명은 상기와 같은 문제점을 해결하기 위해 안출된 것으로, 프로젝트의 진행 현황 또는 프로젝트를 수행 중 발생된 문제점을 실시간으로 파악할 수 있으며, 이를 통해 프로젝트로 인한 제품의 생산성이 향상될 수 있는 프로젝트 관리 시스템을 제공하는 것이다.The present invention has been made to solve the above problems, a project management system capable of grasping the progress of a project or problems occurring during the project in real time, through which the productivity of products due to the project can be improved. is to provide

상기한 목적은, 다수 개의 사용자단말기; 상기 사용자단말기를 통해 접근가능하며, 프로젝트의 정보를 제공하는 서버; 상기 서버에 저장된 상기 프로젝트의 정보를 관리할 수 있도록 상기 서버에 연결된 관리자단말기를 포함하며, 상기 서버는, 상기 프로젝트의 정보 관리를 위한 양식을 포함하는 기준정보모듈과, 상기 기준정보모듈을 통해 세분화된 상기 프로젝트의 과제 및 일정 현황을 확인가능한 프로젝트정보관리모듈과, 상기 프로젝트의 진행을 통해 각 과제에서 생성되는 실적을 관리하는 프로젝트실적관리모듈과, 상기 프로젝트의 현황을 표시하는 대시보드모듈과, 각각의 상기 사용자단말기에 적합하게 환경설정이 가능한 환경설정모듈을 포함하는 것을 특징으로 하는 프로젝트 관리 시스템에 의해서 달성된다.The above object, a plurality of user terminals; A server accessible through the user terminal and providing project information; It includes a manager terminal connected to the server to manage information of the project stored in the server, wherein the server includes a standard information module including a form for managing information of the project, and subdivided through the standard information module. A project information management module capable of checking the task and schedule status of the project, a project performance management module that manages performance generated from each task through the progress of the project, and a dashboard module that displays the current status of the project; It is achieved by a project management system comprising an environment setting module capable of environment setting suitable for each of the user terminals.

여기서, 상기 기준정보모듈은, 상기 프로젝트의 과제 및 일정을 세분화하기 위한 양식을 포함하는 템플릿부와, 상기 템플릿부를 통해 세분화된 상기 프로젝트의 과제 및 일정을 저장하고, 저장된 상기 프로젝트의 과제 및 일정에 맞는 상기 사용자단말기를 지정하는 산출물양식등록부를 더 포함하는 것이 바람직하다.Here, the reference information module stores a template unit including a form for subdividing tasks and schedules of the project, tasks and schedules of the project subdivided through the template unit, and stores tasks and schedules of the project stored therein. It is preferable to further include an output form registration unit for specifying the user terminal that is suitable.

또한, 상기 프로젝트정보관리모듈은, 각각의 상기 사용자단말기에 해당하는 상기 프로젝트의 과제 및 일정 현황을 확인할 수 있는 프로젝트현황부와, 상기 프로젝트에 대한 작업 일정이 표시되는 스케쥴관리부와, 수주된 상기 프로젝트의 정보를 입력 및 관리하는 수주정보관리부와, 상기 서버에 입력된 모든 상기 프로젝트를 조회 가능한 프로젝트조회부와, 상기 프로젝트의 일정을 분할 및 관리하는 일정관리부와, 상기 프로젝트의 과제별로 담당자를 선정하는 담당자관리부와, 상기 프로젝트의 진행을 통해 발생되는 산출물 및 기술문서가 등록되는 산출물등록부와, 상기 프로젝트를 진행하는 도중 발생하는 이슈가 입력되는 이슈입력부를 더 포함하는 것이 바람직하다.In addition, the project information management module includes a project status unit capable of checking the task and schedule status of the project corresponding to each user terminal, a schedule management unit displaying a work schedule for the project, and the ordered project An order information management unit for inputting and managing information of the server, a project inquiry unit capable of inquiring all the projects entered into the server, a schedule management unit for dividing and managing the schedule of the project, and selecting a person in charge for each project task. It is preferable to further include a manager in charge, a product registration unit in which products and technical documents generated through the progress of the project are registered, and an issue input unit in which issues generated during the project are input.

이 뿐만 아니라, 상기 프로젝트실적관리모듈은, 상기 프로젝트 및 상기 프로젝트에 해당하는 과제를 조회가능한 과제조회부와, 상기 프로젝트의 진행 중 산출물이 등록된 과제의 내용을 조회가능한 산출물조회부와, 상기 프로젝트의 이슈를 조회가능한 이슈조회부를 더 포함하는 것이 바람직하며, 상기 환경설정모듈은, 상기 사용자단말기를 등록하는 사용자관리부와, 상기 프로젝트의 과제별 전담부서 선정을 위해 전체 부서를 관리하는 부서관리부와, 상기 사용자단말기 또는 상기 관리자단말기에 사용되는 메뉴를 관리하는 메뉴관리부와, 상기 사용자단말기의 권한을 관리하는 권한관리부와, 상기 프로젝트 및 과제를 지칭하는 코드를 각각 부여하는 코드관리부와, 상기 프로젝트가 수행되는 회사의 고객, 법인정보, 사업장, 공장 및 제품을 관리하는 회사정보관리부를 더 포함하는 것이 바람직하다.In addition to this, the project performance management module includes a task inquiry unit capable of inquiring the project and the tasks corresponding to the project, an output inquiry unit capable of inquiring the contents of the task in which the output product is registered during the project, and the project It is preferable to further include an issue inquiry unit capable of querying issues of, and the environment setting module includes a user management unit registering the user terminal, a department management unit managing all departments to select a dedicated department for each task of the project, A menu management unit for managing menus used in the user terminal or the manager terminal, a authority management unit for managing authority of the user terminal, and a code management unit for assigning codes indicating the project and task, respectively, the project is performed It is preferable to further include a company information management unit that manages customers, corporate information, workplaces, factories, and products of the company to be.

상술한 바와 같이 본 발명에 따르면, 프로젝트의 진행 현황 또는 프로젝트를 수행 중 발생된 문제점을 실시간으로 파악할 수 있으며, 이를 통해 프로젝트로 인한 제품의 생산성이 향상될 수 있는 효과를 얻을 수 있다.As described above, according to the present invention, it is possible to grasp the progress of a project or a problem occurring during the project in real time, and through this, an effect of improving product productivity due to the project can be obtained.

도 1은 본 발명의 실시예에 따른 프로젝트 관리 시스템의 개념도이고,
도 2는 프로젝트 관리 시스템 중 서버의 상세 개념도이고,
도 3 은 서버의 기준정보모듈 중 템플릿부의 화면이고,
도 4는 프로젝트정보관리모듈 중 프로젝트현황부의 화면이고,
도 5는 수주정보관리부의 화면이고,
도 6은 프로젝트조회부의 화면이고,
도 7은 일정관리부의 화면이고,
도 8 및 도 9는 담당자관리부의 화면이고,
도 10은 산출물등록부의 화면이고,
도 11은 프로젝트실적관리모듈 중 과제조회부의 화면이고,
도 12는 산출물조회부의 화면이고,
도 13은 이슈조회부의 화면이고,
도 14는 대시보드모듈의 화면이고,
도 15는 환경설정모듈 중 사용자관리부의 화면이고,
도 16은 부서관리부의 화면이고,
도 17은 메뉴관리부의 화면이고,
도 18은 권한관리부의 화면이고,
도 19는 코드관리부의 화면이고,
도 20 내지 도 25는 회사정보관리부의 화면이다.
1 is a conceptual diagram of a project management system according to an embodiment of the present invention;
2 is a detailed conceptual diagram of a server in a project management system;
3 is a screen of a template part among reference information modules of a server;
4 is a screen of the project status unit of the project information management module,
5 is a screen of an order information management unit;
6 is a screen of a project inquiry unit,
7 is a screen of a schedule management unit;
8 and 9 are screens of a manager in charge,
10 is a screen of a product registration unit;
11 is a screen of a task inquiry unit in a project performance management module;
12 is a screen of a product inquiry unit;
13 is a screen of an issue inquiry unit,
14 is a screen of the dashboard module,
15 is a screen of a user management unit among environment setting modules;
16 is a screen of a department management unit;
17 is a screen of a menu management unit;
18 is a screen of the authority management unit,
19 is a screen of a code management unit;
20 to 25 are screens of a company information management unit.

이하, 본 발명의 기술적 사상을 첨부된 도면을 사용하여 더욱 구체적으로 설명한다. 첨부된 도면은 본 발명의 기술적 사상을 더욱 구체적으로 설명하기 위하여 도시한 일예에 불과하므로 본 발명의 기술적 사상이 첨부된 도면의 형태에 한정되는 것은 아니다.Hereinafter, the technical idea of the present invention will be described in more detail using the accompanying drawings. Since the accompanying drawings are only examples shown to explain the technical idea of the present invention in more detail, the technical idea of the present invention is not limited to the form of the accompanying drawings.

도 1은 본 발명의 실시예에 따른 프로젝트 관리 시스템의 개념도이고, 도 2는 프로젝트 관리 시스템 중 서버의 상세 개념도이고, 도 3 은 서버의 기준정보모듈 중 템플릿부의 화면이고, 도 4는 프로젝트정보관리모듈 중 프로젝트현황부의 화면이고, 도 5는 수주정보관리부의 화면이고, 도 6은 프로젝트조회부의 화면이고, 도 7은 일정관리부의 화면이고, 도 8 및 도 9는 담당자관리부의 화면이고, 도 10은 산출물등록부의 화면이고, 도 11은 프로젝트실적관리모듈 중 과제조회부의 화면이고, 도 12는 산출물조회부의 화면이고, 도 13은 이슈조회부의 화면이고, 도 14는 대시보드모듈의 화면이고, 도 15는 환경설정모듈 중 사용자관리부의 화면이고, 도 16은 부서관리부의 화면이고, 도 17은 메뉴관리부의 화면이고, 도 18은 권한관리부의 화면이고, 도 19는 코드관리부의 화면이고, 도 20 내지 도 25는 회사정보관리부의 화면이다.1 is a conceptual diagram of a project management system according to an embodiment of the present invention, FIG. 2 is a detailed conceptual diagram of a server in a project management system, FIG. 3 is a screen of a template unit among reference information modules of a server, and FIG. 4 is a project information management 5 is a screen of the order information management unit, FIG. 6 is a screen of the project inquiry unit, FIG. 7 is a screen of the schedule management unit, FIGS. 8 and 9 are screens of the manager management unit, and FIG. is a screen of the output registration unit, FIG. 11 is a screen of the task inquiry unit of the project performance management module, FIG. 12 is a screen of the output inquiry unit, FIG. 13 is a screen of the issue inquiry unit, FIG. 14 is a screen of the dashboard module, and FIG. 15 is a screen of the user management unit of the environment setting module, FIG. 16 is a screen of the department management unit, FIG. 17 is a screen of the menu management unit, FIG. 18 is a screen of the authority management unit, FIG. 19 is a screen of the code management unit, and FIG. 25 are screens of the company information management unit.

본 발명에 따른 프로젝트 관리 시스템(10)은, 사용자단말기(100), 서버(server, 200) 및 관리자단말기(300)를 포함한다. 사용자단말기(100)의 경우 다수의 사용자가 각각 개별적으로 구비할 수 있도록 다수 개로 이루어지며, 이는 서버(200)에 접근가능하도록 구성되지만 서버(200) 내의 프로젝트 정보를 등록, 수정 또는 삭제하는 데는 일부 권한이 제한된다. 즉, 사용자단말기(100)는 서버(200) 내의 구성에 따라 등록이나 수정가능한 구성이 있으며, 수정하지 못하고 단순히 확인만 할 수 있는 구성이 구분된다. 이러한 사용자단말기(100)의 설정은 관리자단말기(300)를 통해 변경 가능하다.The project management system 10 according to the present invention includes a user terminal 100 , a server 200 and a manager terminal 300 . In the case of the user terminal 100, it is made up of a plurality of pieces so that a plurality of users can each have them individually, and it is configured to be accessible to the server 200, but some of them are required to register, modify, or delete project information in the server 200. Authority is limited. That is, the user terminal 100 has a configuration that can be registered or modified according to the configuration in the server 200, and a configuration that cannot be modified and can only be confirmed is classified. Settings of the user terminal 100 can be changed through the manager terminal 300 .

이와 달리 관리자단말기(300)는, 서버(200)에 저장된 프로젝트 정보를 관리할 수 있도록 서버(200)에 연결된 구성으로, 서버(200)에 포함된 모든 프로젝트 정보를 등록, 수정 또는 삭제할 수 있을 뿐 아니라, 서버(200)에 포함된 구성들에 대해서도 관리가 가능하다. 즉, 사용자단말기(100)는 서버(200)의 구성들에 대한 접근 제한이 있지만 관리자단말기(300)는 서버(200)의 접근이 제한되지 않는다.Unlike this, the manager terminal 300 has a configuration connected to the server 200 so as to manage the project information stored in the server 200, and can only register, modify, or delete all project information included in the server 200. In addition, it is possible to manage configurations included in the server 200 as well. That is, the access of the user terminal 100 to components of the server 200 is restricted, but the access of the manager terminal 300 to the server 200 is not restricted.

서버(server, 200)는, 사용자단말기(100) 및 관리자단말기(300)를 통해 접근 가능하며, 프로젝트 정보가 저장되어 있는 구성에 해당한다. 이러한 서버(200)는 기준정보모듈(210), 프로젝트정보관리모듈(220), 프로젝트실적관리모듈(230), 대시보드모듈(240), 환경설정모듈(250)을 포함한다.The server (server, 200) is accessible through the user terminal 100 and the manager terminal 300, and corresponds to a configuration in which project information is stored. This server 200 includes a reference information module 210, a project information management module 220, a project performance management module 230, a dashboard module 240, and an environment setting module 250.

먼저 기준정보모듈(210)은, 프로젝트 정보 관리를 위한 양식을 포함하는 구성으로, 이러한 기준정보모듈(210)은 템플릿부(211), 산출물양식등록부(212)로 이루어진다.First, the reference information module 210 has a configuration including a form for managing project information, and the reference information module 210 includes a template unit 211 and a product form registration unit 212 .

템플릿부(211)는, 프로젝트 구성될 게이트별 작업분할구조도(work breakdown structure)의 견본에 해당하는 구성으로, 프로젝트 목표를 달성하기 위해 필요한 과제 및 일정을 템플릿부(211)를 참고하여 세분화할 수 있도록 구성된다. 이러한 템플릿부(211)는 도 3에 도시된 바와 같이 프로젝트 또는 프로젝트를 수행하는 팀에 따라서 최적화된 템플릿(template)이 복수 개가 구비된다. 즉, 관리자단말기(300)를 통해 프로젝트 과제 및 일정을 세분화할 때 템플릿부(211)를 참고하여 최적의 프로젝트 세분화가 이루어지도록 할 수 있다. 경우에 따라서 관리자단말기(300)를 이용하여 새로운 템플릿을 제조한 후 이를 템플릿부(211)에 등록할 수도 있으며, 기존의 템플릿을 수정할 수도 있다.The template unit 211 is a configuration corresponding to a sample of a work breakdown structure for each gate to be configured in the project, and tasks and schedules necessary to achieve project goals are subdivided with reference to the template unit 211. It is structured so that As shown in FIG. 3 , the template unit 211 includes a plurality of templates optimized according to a project or a team performing the project. That is, when project tasks and schedules are subdivided through the manager terminal 300, the optimal project subdivision may be achieved by referring to the template unit 211. In some cases, after manufacturing a new template using the manager terminal 300, it may be registered in the template unit 211, or an existing template may be modified.

산출물양식등록부(212)는, 템플릿부(211)를 통해 세분화된 프로젝트의 과제 및 일정을 저장하고, 저장된 프로젝트 과제 및 일정에 맞는 사용자단말기(100)를 지정하는 구성에 해당한다. 이와 같이 프로젝트 과제 및 일정은 지정된 사용자의 데이터베이스로 전송되고, 사용자는 사용자단말기(100)를 통해 데이터베이스에 접근하여 지정된 프로젝트 과제 및 일정을 확인할 수 있다.The product form registration unit 212 corresponds to a configuration for storing tasks and schedules of subdivided projects through the template unit 211 and designating a user terminal 100 suitable for the stored project tasks and schedules. In this way, the project assignment and schedule are transmitted to the database of the designated user, and the user can access the database through the user terminal 100 and check the designated project assignment and schedule.

프로젝트정보관리모듈(220)은, 기준정보모듈(210)을 통해 세분화된 프로젝트의 과제 및 일정 현황을 확인가능하도록 구비된 구성으로, 이러한 프로젝트정보관리모듈(220)은 프로젝트현황부(221), 스케쥴관리부(222), 수주정보관리부(223), 프로젝트조회부(224), 일정관리부(225), 담당자관리부(226), 산출물등록부(227) 및 이슈입력부(228)를 포함한다.The project information management module 220 is a configuration provided to check the status of tasks and schedules of subdivided projects through the reference information module 210. This project information management module 220 includes a project status unit 221, It includes a schedule management unit 222, an order information management unit 223, a project inquiry unit 224, a schedule management unit 225, a manager management unit 226, a product registration unit 227, and an issue input unit 228.

프로젝트현황부(221)는, 각각의 사용자단말기(100)에 해당하는 프로젝트의 과제 및 일정 현황을 확인할 수 있는 구성으로, 도 4에 도시된 바와 같이 개인 대시보드 뿐 아니라 산출물양식등록부(212)를 통해 전송받은 프로젝트 과제 및 일정을 토대로 참여 프로젝트의 리스트, 프로젝트의 금주/차주 일정, 프로젝트 산출물, 작업 진행상태 및 이슈현황 등을 확인할 수 있도록 구성된다.The project status unit 221 is a configuration capable of checking the task and schedule status of the project corresponding to each user terminal 100, and the output form registration unit 212 as well as the personal dashboard as shown in FIG. Based on the project tasks and schedules transmitted through the project, it is configured to check the list of participating projects, the current/borrowing schedule of the project, the project output, the work progress status, and the current status of issues.

스케쥴관리부(222)는, 프로젝트에 대한 작업 일정이 표시되는 구성으로, 사용자단말기(100)를 이용하여 스케쥴관리부(222)에 접근하게 되면 프로젝트의 일정이 캘린더 형상으로 사용자단말기(100)에 표시된다. 이때 프로젝트의 마감 일정이 얼마 남지 않은 경우 별도의 표시가 캘린더에 표시될 수도 있으며, 프로젝트 리스트에 따라 색깔을 달리하여 캘린더에 표시될 수도 있다.The schedule management unit 222 is configured to display the work schedule for the project, and when the schedule management unit 222 is accessed using the user terminal 100, the schedule of the project is displayed on the user terminal 100 in the form of a calendar. . In this case, when the deadline for the project is near, a separate mark may be displayed on the calendar, or a different color may be displayed on the calendar according to the project list.

수주정보관리부(223)는, 수주된 프로젝트의 정보를 입력 및 관리하는 구성으로, 수주 정보가 입력된 개발요청서를 조회 및 등록할 수 있다. 여기서 수주정보는 도 5에 도시된 바와 같이 요청일자, 요청부서, 요청자, 프로젝트명, 프로젝트 레벨, 고객사, 고객사 제품, 납품수량, 납품일을 포함하며, 이러한 정보를 사용자단말기(100)를 이용하여 입력하게 된다. 이와 같이 수주된 정보가 수주정보관리부(223)에 의해 입력되면, 해당 수주 정보는 수주정보 승인요청을 받은 후 프로젝트로 등록될 수 있다.The order information management unit 223 is a configuration for inputting and managing information of an order received project, and may inquire and register a development request in which order information is input. As shown in FIG. 5, the order information includes request date, requesting department, requester, project name, project level, customer company, customer product, delivery quantity, and delivery date. will be entered When the order information is input by the order information management unit 223, the order information may be registered as a project after receiving a request for order information approval.

프로젝트조회부(224)는, 서버(200)에 입력된 모든 프로젝트를 조회 가능한 구성으로, 본 발명의 프로젝트 관리 시스템(10)이 적용되는 사내에서 관리고 있는 모든 프로젝트를 사용자단말기(100) 또는 관리자단말기(300)를 이용하여 조회 및 등록할 수 있다. 프로젝트 조회의 경우 사업장, 부서, 상태, 프로젝트 명, 프로젝트 코드, 프로젝트 기간을 입력하여 조회할 수 있다. 이러한 프로젝트조회부(224)는 도 6에 도시된 바와 같이 새로운 프로젝트를 등록할 수 있는데, 프로젝트 등록의 경우 프로젝트 번호, 프로젝트 명, 고객사, 대표 품번, 대표 품명, 수행 부서, 프로젝트 시작 예정일, 프로젝트 종료 예정일을 입력한 후 등록이 가능하다.The project inquiry unit 224 is a configuration capable of querying all projects entered into the server 200, and all projects managed in the company to which the project management system 10 of the present invention is applied are displayed by the user terminal 100 or the manager. It can be inquired and registered using the terminal 300 . In the case of project inquiry, you can search by entering the business site, department, status, project name, project code, and project period. The project inquiry unit 224 may register a new project as shown in FIG. 6. In the case of project registration, project number, project name, customer company, representative part number, representative item name, performing department, project start date, project end You can register after entering the scheduled date.

일정관리부(225)는, 프로젝트의 일정을 분할 및 관리하는 구성으로, 프로젝트조회부(224)를 통해 새로 등록되는 프로젝트의 일정을 관리할 수 있다. 상세하게는 도 7에 도시된 바와 같이 관리자단말기(300)를 이용하여 일정관리부(225)에 포함된 불러오기 버튼을 통해 새로운 프로젝트를 불러오게 되고, 해당 프로젝트에 다양한 과제를 추가하게 된다. 이때 과제는 과제명, 과제 기간, 시작계획일, 종료계획일을 입력하게 되며, 이러한 과제는 복수 개가 입력되어 과제의 수행 순서도 설정할 수 있도록 구성된다.The schedule management unit 225 is configured to divide and manage project schedules, and may manage schedules of newly registered projects through the project inquiry unit 224 . In detail, as shown in FIG. 7, a new project is called through the call button included in the schedule management unit 225 using the manager terminal 300, and various tasks are added to the project. At this time, the task name, task period, start plan date, and end plan date are input, and a plurality of these tasks are input so that the order of task execution can be set.

담당자관리부(226)는, 프로젝트의 과제별로 담당자를 선정하는 구성으로, 도 8에 도시된 바와 같이 관리자단말기(300)를 통해 담당부서를 클릭하게 되면 해당 부서에 포함된 구성원들이 우측에 표시된다. 이 중 적절한 구성원을 선택하여 과제의 담당자로 선정하게 되며, 선정된 담당자의 데이터베이스로 해당 프로젝트 및 과제 정보가 전송되어 이를 사용자단말기(100)를 통해 확인 가능하다. The manager management unit 226 is configured to select a person in charge for each task of the project. As shown in FIG. 8, when a department in charge is clicked through the manager terminal 300, members included in the department are displayed on the right side. Among them, an appropriate member is selected and selected as the person in charge of the task, and the project and task information is transmitted to the database of the selected person in charge, and it can be confirmed through the user terminal 100.

또한 도 9에 도시된 바와 같이 담당자관리부(226)를 통해 해당 프로젝트의 결재자를 선택할 수 있으며, 선택된 결재자에게 과제의 검토, 승인, 기타 결재 요청을 할 수 있다. 이와 같이 결재자로부터 결재가 이루어지게 되면 해당 날짜가 작업시작일로 설정된다.In addition, as shown in FIG. 9 , it is possible to select an approver of the project through the manager in charge 226, and requests for review, approval, and other approval of the project can be made to the selected approver. In this way, when an approval is made from an approver, the corresponding date is set as the work start date.

산출물등록부(227)는, 프로젝트 진행을 통해 발생되는 산출물 및 기술문서가 등록되는 구성으로, 관리자단말기(300)를 이용하여 산출물 정보를 직접 입력하거나 또는 산출물 관련 양식을 다운 받은 후 내용을 기재한 기술문서를 산출물등록부(227)에 업로드할 수도 있다. 여기서 산출물 정보는 도 10에 도시된 바와 같이 프로젝트 코드, 프로젝트 명, 과제번호, 과제명, 과제기간, 과제상태, 산출물번호, 산출물명 등을 입력한 후 저장할 수 있다.The output registration unit 227 is a configuration in which outputs and technical documents generated through project progress are registered, and the output information is directly input using the manager terminal 300 or a form related to the output is downloaded and the contents are written. Documents can also be uploaded to the product registration unit 227 . Here, as shown in FIG. 10, the product information can be stored after entering the project code, project name, task number, task name, task period, task status, product number, product name, and the like.

이슈입력부(228)는, 프로젝트를 진행하는 도중 발생하는 이슈가 입력되는 구성에 해당한다. 이러한 이슈 입력은 사용자단말기(100)를 통해 과제 번호, 과제 상태, 평가유형, 이슈일, 담당자, 프로젝트 명, 제목, 내용, 완료계획일자, 작성자, 작성일 등이 입력되며, 이러한 이슈 정보를 관리자단말기(300)가 확인할 수 있다.The issue input unit 228 corresponds to a configuration in which issues that occur during the project are input. In this issue input, task number, task status, evaluation type, issue date, person in charge, project name, title, content, completion plan date, author, writing date, etc. are entered through the user terminal 100, and such issue information is sent to the manager terminal (300) can confirm.

프로젝트실적관리모듈(230)은, 프로젝트 진행을 통해 각 과제에서 생성되는 실적을 관리하는 구성으로, 이러한 프로젝트실적관리모듈(230)은 과제조회부(231), 산출물조회부(232), 이슈조회부(233)를 포함한다.The project performance management module 230 is a component that manages performance generated from each task through project progress. This project performance management module 230 includes a task inquiry unit 231, an output inquiry unit 232, and an issue inquiry. It includes section 233.

과제조회부(231)는, 프로젝트 및 프로젝트에 해당되는 과제를 조회하기 위한 구성으로, 도 11에 도시된 바와 같이 현재 사내에서 진행되고 있는 과제의 정보를 사용자단말기(100)가 조회하여 확인할 수 있도록 한다. 여기서 과제 조회의 경우 부서, 진행상태, 프로젝트 명, 프로젝트 코드, 과제명, 과제시작일, 담당자 등을 입력 후 검색할 수 있으며, 검색된 결과는 복수 개의 리스트로 조회된다. 이러한 과제 리스트는 번호, 제안번호, 부서, 제안상태, 프로젝트 코드, 프로젝트 명, 과제명, 진행상태, 작성자 등이 표시되며, 과제 리스트는 별도의 엑셀 파일로 저장 되어 사용자단말기(100)에 전송 가능하도록 이루어져 있다.The task inquiry unit 231 is a component for querying projects and tasks corresponding to the projects, and as shown in FIG. 11, the user terminal 100 can inquire and check information on tasks currently in progress in the company. do. Here, in the case of task inquiry, you can search after entering the department, progress status, project name, project code, task name, task start date, person in charge, etc., and the searched results are searched in a plurality of lists. This task list displays the number, proposal number, department, proposal status, project code, project name, task name, progress status, author, etc., and the task list is saved as a separate Excel file and can be transmitted to the user terminal 100. made to do

산출물조회부(232)는, 프로젝트 진행 중 산출물이 등록된 과제의 내용을 조회하기 위한 구성으로, 산출물등록부(227)를 통해 입력된 산출물을 조회할 수 있도록 구성된다. 이러한 산출물조회부(232)는 과제조회부(231)와 마찬가지로 사용자단말기(100)를 통해 도 12에 도시된 바와 같이 부서, 진행상태, 프로젝트 명, 프로젝트 코드, 과제명, 과제시작일, 담당자 등을 입력 후 검색할 수 있으며, 검색된 결과는 복수 개의 리스트로 조회된다. 리스트의 경우 산출물이 등록된 경우에만 조회될 수 있으며, 산출물 리스트에는 번호, 제안번호, 부서, 제안상태, 프로젝트 코드, 프로젝트 명, 과제명, 진행상태, 작성자 등이 표시되며, 산출물 리스트는 별도의 엑셀 파일로 저장 가능하도록 이루어져 있다.The product inquiry unit 232 is configured to query the contents of a task in which the product is registered during the project, and is configured to query the product input through the product registration unit 227 . Similar to the task inquiry unit 231, the product inquiry unit 232 retrieves department, progress status, project name, project code, task name, task start date, person in charge, etc. through the user terminal 100 as shown in FIG. You can search after inputting, and the searched results are searched in multiple lists. In the case of the list, it can be inquired only when the output is registered, and the output list displays the number, proposal number, department, proposal status, project code, project name, task name, progress status, author, etc. It can be saved as an Excel file.

이슈조회부(233)는, 이슈입력부(228)를 통해 입력된 프로젝트의 이슈를 조회할 수 있는 구성으로, 도 13에 도시된 바와 같이 과제 번호, 과제 상태, 평가유형, 이슈일, 담당자, 프로젝트 명, 제목, 내용, 완료계획일자, 작성자, 작성일 등이 입력될 수 있으며, 이슈 조회의 경우 이 중 하나 또는 그 이상의 정보를 입력하여 검색이 가능하다. 이와 같이 검색된 이슈는 리스트화되며, 이러한 이슈 리스트는 별도의 엑셀 파일로 저장 가능하다. 이 중 프로젝트의 중대한 문제가 발생할 경우 작업자가 빠른 확인이 가능하도록 사용자단말기(100)에 별도의 팝업창을 뜨게 하거나 또는 다른 이슈와 달리 별도의 색으로 표현되도록 설정할 수 있다.The issue inquiry unit 233 is a configuration capable of inquiring issues of the project input through the issue input unit 228, and as shown in FIG. 13, the task number, task status, evaluation type, issue date, person in charge, and project Name, title, content, planned completion date, author, date of creation, etc. can be entered, and in the case of issue inquiry, one or more of these information can be entered to search. Issues searched in this way are listed, and this issue list can be saved as a separate Excel file. Among them, when a serious problem occurs in the project, a separate pop-up window may be opened on the user terminal 100 so that a worker can quickly check, or it may be set to be expressed in a separate color unlike other issues.

대시보드모듈(240)은, 프로젝트의 현황을 표시하는 구성에 해당하며, 상세하게는 도 14에 도시된 바와 같이 주요프로젝트 현황, 프로젝트 진행현황, 프로젝트 현황, 이슈 현황, 부서별 과제 지연 현황을 확인할 수 있다. 이 중 주요프로젝트 현황 및 프로젝트 진행현황은 리스트 형태로 표시되며, 프로젝트 현황, 이슈 현황 및 부서별 과제 지연 현황은 다이어그램(diagram) 형식으로 표시되어 사용자의 가독성을 높일 수 있다.The dashboard module 240 corresponds to a configuration for displaying the project status, and in detail, as shown in FIG. 14, it is possible to check the major project status, project progress status, project status, issue status, and task delay status by department. there is. Among them, the main project status and project progress status are displayed in list form, and the project status, issue status, and task delay status by department are displayed in diagram form to enhance user readability.

환경설정모듈(250)은, 프로젝트 관리 시스템(10)을 사용하는 각각의 사용자단말기(100)에 적합하게 환경설정하는 구성으로, 이러한 환경설정모듈(250)은 사용자관리부(251), 부서관리부(252), 메뉴관리부(253), 권한관리부(254), 제품관리부(255), 고객사제품관리부(256), 메뉴관리부(257) 및 회사정보관리부(258)를 포함한다.The environment setting module 250 is configured to set the environment appropriately for each user terminal 100 using the project management system 10, and this environment setting module 250 includes the user management unit 251, the department management unit ( 252), menu management unit 253, authority management unit 254, product management unit 255, customer product management unit 256, menu management unit 257, and company information management unit 258.

사용자관리부(251)는, 프로젝트 관리 시스템(10)을 사용할 수 있는 사용자단말기(100)를 등록하기 위한 구성으로, 관리자단말기(300)를 이용하여 사용자단말기(100)를 등록하게 되는데, 사용자관리부(251)를 통해 등록된 사용자단말기(100)만 본 발명의 프로젝트 관리 시스템(10)에 접근할 수 있도록 한다. 여기서 사용자단말기(100)의 등록은 도 15에 도시된 바와 같이 사용자의 아이디, 이름, 패스워드, 부서코드, 사업장, 공자, 직책, 직위, 보안등급, 메일, 전화번호, 언어, 역할 등을 입력할 수 있다.The user management unit 251 is a configuration for registering the user terminal 100 that can use the project management system 10, and registers the user terminal 100 using the manager terminal 300, the user management unit ( 251), only the registered user terminal 100 can access the project management system 10 of the present invention. As shown in FIG. 15, registration of the user terminal 100 involves inputting the user's ID, name, password, department code, business place, employee, title, position, security level, e-mail, phone number, language, role, etc. can

부서관리부(252)는, 프로젝트의 과제별 전담부서 선정을 위해 전체 부서를 관리하기 위한 구성으로, 프로젝트를 수행할 수 있는 사내의 부서를 등록 및 수정가능하도록 한다. 이러한 부서관리부(252)는 도 16에 도시된 바와 같이 부서를 등록 또는 수정할 때 사업장, 부서명, 부서코드, 인원수를 입력할 수 있으며, 등록된 부서는 사용자 리스트와 연결되어 사용자관리부(251)를 통해 등록된 사용자의 정보를 확인할 수 있다.The department management unit 252 is configured to manage all departments in order to select departments dedicated to each task of the project, and enables registration and modification of in-house departments capable of carrying out the project. As shown in FIG. 16, the department management unit 252 can input a business place, department name, department code, and number of employees when registering or modifying a department, and the registered department is linked to the user list through the user management unit 251. You can check the information of registered users.

메뉴관리부(253)는, 사용자단말기(100) 또는 관리자단말기(300)에 사용되는 메뉴를 관리하기 위한 구성으로, 각각의 사용자단말기(100) 또는 관리자단말기에 필요한 메뉴를 선별하여 프로젝트 관리 시스템(10) 내에 구성할 수 있도록 한다. 즉, 도 17에 도시된 바와 같이 필요한 메뉴를 등록, 수정 또는 삭제할 수 있다.The menu management unit 253 is a configuration for managing menus used in the user terminal 100 or the manager terminal 300, and selects menus required for each user terminal 100 or the manager terminal to project management system 10 ) to be configured within. That is, as shown in FIG. 17, necessary menus can be registered, modified, or deleted.

권한관리부(254)는, 사용자단말기(100)의 권한을 관리하는 구성에 해당한다. 이는 사용자단말기(100)가 프로젝트 관리 시스템(10)에 접근 또는 수정에 대한 권한을 관리하는 것으로, 사용자의 부서 또는 직책에 따라서 권한 부여를 할 수 있도록 한다. 상세하게는 도 18에 도시된 바와 같이 사용자단말기(100)를 각각 지정한 후, save, wiew, insert ,select 등과 같은 권한을 각각 체크하여 부여할 수 있도록 한다.The authority management unit 254 corresponds to a configuration that manages authority of the user terminal 100 . This allows the user terminal 100 to manage the authority for access or modification to the project management system 10, and to grant authority according to the user's department or position. In detail, as shown in FIG. 18, after designating each user terminal 100, the authority such as save, wiew, insert, select, etc. is checked and granted.

코드관리부(255)는, 프로젝트 및 과제를 지칭하는 코드를 각각 부여하는 구성에 해당하며, 관리자단말기(300)를 이용하여 코드를 등록, 수정 또는 삭제할 수 있도록 구성된다. 이때 코드를 등록 또는 수정하기 위해서는 도 19에 도시된 바와 같이 순번, 코드명, 코드값, 업무구분, 언어 등을 입력하게 된다.The code management unit 255 corresponds to a configuration for assigning codes indicating projects and tasks, respectively, and is configured to register, modify, or delete codes using the manager terminal 300 . At this time, in order to register or modify the code, as shown in FIG. 19, the order number, code name, code value, job classification, language, etc. are input.

회사정보관리부(258)는, 프로젝트가 수행되는 회사의 고객, 법인정보, 사업장, 공장 및 제품을 관리하기 위한 구성으로, 도 20 내지 도 25에 도시된 바와 같이 고객관리부, 법인정보관리부, 사업장관리부, 공장관리부 및 제품관리부를 포함한다.The company information management unit 258 is a component for managing customers, corporate information, workplaces, factories, and products of a company where a project is performed, and as shown in FIGS. 20 to 25, a customer management unit, a corporate information management unit, and a business site management unit. , including the factory management department and the product management department.

고객관리부는, 프로젝트를 요청하는 고객사 또는 협력사의 정보를 관리하는 구성으로, 도 20에 도시된 바와 같이 고객사 또는 협력사의 업체구분, 업종, 업체명, 사업자등록번호, 대표자명, 전화번호, 주소, 우편번호, 이메일, 국가구분 등을 관리자단말기(300)를 통해 입력한 후 입력된 정보를 관리하게 되며, 이러한 고객의 정보는 사용자단말기(100)를 통해 확인 가능하다.The customer management department is a component that manages the information of the customer or partner company requesting the project, and as shown in FIG. After inputting a number, e-mail, country classification, etc. through the manager terminal 300, the input information is managed, and such customer information can be checked through the user terminal 100.

법인정보관리부는, 자사, 고객사 또는 협력사의 법인정보를 관리하는 구성으로, 도 21에 도시된 바와 같이 법인명, 법인구분, 법인코드, 대표자명, 결산일, 기업구분, 법인등록번호, 사업자등록번호, 법인설립일자, 자본금 등을 관리자단말기(300)를 통해 입력할 수 있게 구성된다.The corporate information management department is a component that manages corporate information of the company, customers, or partners, and as shown in Figure 21, corporate name, corporate classification, corporate code, representative name, settlement date, corporate classification, corporate registration number, business registration number , the date of establishment of the corporation, the capital amount, etc. are configured to be input through the manager terminal 300.

사업장관리부는, 프로젝트가 수행되는 사내의 사업장을 관리하기 위한 구성으로, 관리자단말기(300)를 통해 사업장 정보를 등록 또는 수정할 수 있다. 이때 사업장 등록 또는 수정의 경우 도 22와 같이 법인코드, 사업자면, 대표자명, 사업장구분, 사업자등록번호, 업종, 업태, 본사여부, 주소, 이메일, 개업일자 등을 입력할 수 있도록 구성된다.The workplace management unit is a configuration for managing the in-house workplace where the project is performed, and can register or modify workplace information through the manager terminal 300 . At this time, in the case of registering or modifying a business place, as shown in FIG. 22, it is configured to enter a corporate code, business name, representative name, business place classification, business registration number, type of business, type of business, head office, address, email, business opening date, etc.

공장관리부는, 사내에서 관리되고 있는 공장 정보를 확인할 수 있는 구성으로, 도 23에 도시된 바와 같이 공장 정보 중 법인코드, 사업장코드, 공장명, 관리공장, 원가귀속공장, 발주관리공장, 자재관리부서, 생산관리부어, 설비보전부서, 등록자, 등록일 등을 관리자단말기(300)를 통해 입력한 후 관리가 이루어지게 된다.The factory management department is a configuration that can check factory information managed in-house. As shown in FIG. 23, among the factory information, corporate code, business site code, factory name, managed factory, cost-attached factory, order management factory, and material management After entering the department, production management department, facility maintenance department, registrant, registration date, etc. through the manager terminal 300, management is performed.

제품관리부는, 프로젝트를 통해 생산되는 생산품에 대한 정보를 관리하는 구성으로, 관리자단말기(300)를 통해 생산품을 등록 또는 수정할 수 있도록 구성된다. 이는 도 24와 같이 생산품의 품명, 제품타입명, 제품그룹명, 고객사명, 법인, 사업장, 공장, 모델명, 등록자, 등록일 등을 입력할 수 있으며, 이러한 생산품 정보는 리스트를 통해 관리된다. 경우에 따라서 제품관리부는 도 25에 도시된 바와 같이 고객사 제품정보 관리도 가능하다.The product management unit is configured to manage information on products produced through the project, and is configured to register or modify products through the manager terminal 300 . As shown in FIG. 24, product name, product type name, product group name, customer company name, corporation, workplace, factory, model name, registrant, registration date, etc. can be entered, and this product information is managed through a list. In some cases, the product management unit may also manage customer company product information as shown in FIG. 25 .

이와 같이 본 발명에 따른 프로젝트 관리 시스템(10)을 사내에 적용할 경우, 프로젝트의 진행 현황 또는 프로젝트를 수행 중 발생된 문제점을 실시간으로 파악할 수 있으며, 이를 통해 프로젝트로 인한 제품의 생산성이 향상될 수 있는 효과를 얻을 수 있다.In this way, when the project management system 10 according to the present invention is applied in-house, it is possible to grasp the progress of the project or problems occurring during the project in real time, and through this, the productivity of the product due to the project can be improved. effect can be obtained.

본 발명은 상기한 실시예에 한정되지 아니하며, 적용범위가 다양함은 물론이고, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 다양한 변형 실시가 가능한 것은 물론이다.The present invention is not limited to the above embodiments, and the scope of application is diverse, and various modifications and implementations are possible without departing from the gist of the present invention claimed in the claims.

10: 프로젝트 관리 시스템
100: 사용자단말기
200: 서버
210: 기준정보모듈
211: 템플릿부
212: 산출물양식등록부
220: 프로젝트정보관리모듈
221: 프로젝트현황부
222: 스케쥴관리부
223: 수주정보관리부
224: 프로젝트조회부
225: 일정관리부
226: 담당자관리부
227: 산출물등록부
228: 이슈입력부
230: 프로젝트실적관리모듈
231: 과제조회부
232: 산출물조회부
233: 이슈조회부
240: 대시보드모듈
250: 환경설정모듈
251: 사용자관리부
252: 부서관리부
253: 메뉴관리부
254: 권한관리부
255: 코드관리부
256: 회사정보관리부
300: 관리자단말기
10: Project management system
100: user terminal
200: server
210: reference information module
211: template part
212: output form registration
220: Project information management module
221: project status department
222: schedule management unit
223: Order information management department
224: Project inquiry unit
225: schedule management department
226: Person in charge management department
227: output register
228: issue input unit
230: Project performance management module
231: task inquiry unit
232: product inquiry unit
233: issue inquiry unit
240: dashboard module
250: environment setting module
251: user management unit
252: department management department
253: menu management unit
254: authority management unit
255: code management unit
256: Company information management department
300: manager terminal

Claims (5)

다수 개의 사용자단말기;
상기 사용자단말기를 통해 접근가능하며, 프로젝트의 정보를 제공하는 서버;
상기 서버에 저장된 상기 프로젝트의 정보를 관리할 수 있도록 상기 서버에 연결된 관리자단말기를 포함하며,
상기 서버는,
상기 프로젝트의 정보 관리를 위한 양식을 포함하는 기준정보모듈과, 상기 기준정보모듈을 통해 세분화된 상기 프로젝트의 과제 및 일정 현황을 확인가능한 프로젝트정보관리모듈과, 상기 프로젝트의 진행을 통해 각 과제에서 생성되는 실적을 관리하는 프로젝트실적관리모듈과, 상기 프로젝트의 현황을 표시하는 대시보드모듈과, 각각의 상기 사용자단말기에 적합하게 환경설정이 가능한 환경설정모듈을 포함하는 것을 특징으로 하는 프로젝트 관리 시스템.
a plurality of user terminals;
A server accessible through the user terminal and providing project information;
It includes a manager terminal connected to the server to manage the information of the project stored in the server,
The server,
A standard information module including a form for information management of the project, a project information management module capable of checking the task and schedule status of the project subdivided through the standard information module, and generated in each task through the progress of the project A project management system characterized in that it includes a project performance management module for managing performance, a dashboard module for displaying the status of the project, and an environment setting module capable of environment setting suitable for each of the user terminals.
제 1항에 있어서,
상기 기준정보모듈은,
상기 프로젝트의 과제 및 일정을 세분화하기 위한 양식을 포함하는 템플릿부와,
상기 템플릿부를 통해 세분화된 상기 프로젝트의 과제 및 일정을 저장하고, 저장된 상기 프로젝트의 과제 및 일정에 맞는 상기 사용자단말기를 지정하는 산출물양식등록부를 더 포함하는 것을 특징으로 하는 프로젝트 관리 시스템.
According to claim 1,
The reference information module,
A template unit including a form for subdividing tasks and schedules of the project;
The project management system further comprises a product form registration unit for storing tasks and schedules of the project subdivided through the template unit and designating the user terminal suitable for the stored tasks and schedules of the project.
제 1항에 있어서,
상기 프로젝트정보관리모듈은,
각각의 상기 사용자단말기에 해당하는 상기 프로젝트의 과제 및 일정 현황을 확인할 수 있는 프로젝트현황부와,
상기 프로젝트에 대한 작업 일정이 표시되는 스케쥴관리부와,
수주된 상기 프로젝트의 정보를 입력 및 관리하는 수주정보관리부와,
상기 서버에 입력된 모든 상기 프로젝트를 조회 가능한 프로젝트조회부와,
상기 프로젝트의 일정을 분할 및 관리하는 일정관리부와,
상기 프로젝트의 과제별로 담당자를 선정하는 담당자관리부와,
상기 프로젝트의 진행을 통해 발생되는 산출물 및 기술문서가 등록되는 산출물등록부와,
상기 프로젝트를 진행하는 도중 발생하는 이슈가 입력되는 이슈입력부를 더 포함하는 것을 특징으로 하는 프로젝트 관리 시스템.
According to claim 1,
The project information management module,
A project status unit capable of checking the task and schedule status of the project corresponding to each of the user terminals;
A schedule management unit for displaying a work schedule for the project;
An order information management unit that inputs and manages information on the received project;
A project inquiry unit capable of inquiring all the projects entered into the server;
A schedule management unit for dividing and managing the schedule of the project;
A manager in charge of selecting a person in charge for each task of the project;
An output registration unit in which outputs and technical documents generated through the progress of the project are registered;
The project management system further comprising an issue input unit for inputting issues occurring during the project.
제 1항에 있어서,
상기 프로젝트실적관리모듈은,
상기 프로젝트 및 상기 프로젝트에 해당하는 과제를 조회가능한 과제조회부와,
상기 프로젝트의 진행 중 산출물이 등록된 과제의 내용을 조회가능한 산출물조회부와,
상기 프로젝트의 이슈를 조회가능한 이슈조회부를 더 포함하는 것을 특징으로 하는 프로젝트 관리 시스템.
According to claim 1,
The project performance management module,
A task inquiry unit capable of querying the project and tasks corresponding to the project;
An output inquiry unit capable of inquiring the contents of the project in which the output is registered during the project;
The project management system further comprising an issue inquiry unit capable of querying issues of the project.
제 1항에 있어서,
상기 환경설정모듈은,
상기 사용자단말기를 등록하는 사용자관리부와,
상기 프로젝트의 과제별 전담부서 선정을 위해 전체 부서를 관리하는 부서관리부와,
상기 사용자단말기 또는 상기 관리자단말기에 사용되는 메뉴를 관리하는 메뉴관리부와,
상기 사용자단말기의 권한을 관리하는 권한관리부와,
상기 프로젝트 및 과제를 지칭하는 코드를 각각 부여하는 코드관리부와,
상기 프로젝트가 수행되는 회사의 고객, 법인정보, 사업장, 공장 및 제품을 관리하는 회사정보관리부를 더 포함하는 것을 특징으로 하는 프로젝트 관리 시스템.
According to claim 1,
The environment setting module,
A user management unit for registering the user terminal;
A department management department that manages all departments to select a dedicated department for each task of the project;
A menu management unit for managing menus used in the user terminal or the manager terminal;
An authority management unit for managing authority of the user terminal;
A code management unit that assigns codes indicating the projects and tasks, respectively;
The project management system further comprises a company information management unit for managing customers, corporate information, workplaces, factories and products of the company where the project is performed.
KR1020210143411A 2021-10-26 2021-10-26 project management system KR20230059331A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210143411A KR20230059331A (en) 2021-10-26 2021-10-26 project management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210143411A KR20230059331A (en) 2021-10-26 2021-10-26 project management system

Publications (1)

Publication Number Publication Date
KR20230059331A true KR20230059331A (en) 2023-05-03

Family

ID=86380764

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210143411A KR20230059331A (en) 2021-10-26 2021-10-26 project management system

Country Status (1)

Country Link
KR (1) KR20230059331A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117114269A (en) * 2023-07-11 2023-11-24 广东省科学院广州地理研究所 Strategic performance management system for implementing development strategy process in villages and towns

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101837021B1 (en) 2010-02-19 2018-03-09 어플라이드 머티어리얼스, 인코포레이티드 Prediction and scheduling server

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101837021B1 (en) 2010-02-19 2018-03-09 어플라이드 머티어리얼스, 인코포레이티드 Prediction and scheduling server

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117114269A (en) * 2023-07-11 2023-11-24 广东省科学院广州地理研究所 Strategic performance management system for implementing development strategy process in villages and towns

Similar Documents

Publication Publication Date Title
Heimerl et al. Work assignment to and qualification of multi-skilled human resources under knowledge depreciation and company skill level targets
Zhang et al. Manufacturing flexibility: defining and analyzing relationships among competence, capability, and customer satisfaction
Dai et al. Radio frequency identification-enabled real-time manufacturing execution system: a case study in an automotive part manufacturer
Tarantilis et al. A Web-based ERP system for business services and supply chain management: Application to real-world process scheduling
Lönngren et al. Aggregated construction supply chains: success factors in implementation of strategic partnerships
KR102064490B1 (en) System for managing manufacturing and production process
JP5651795B1 (en) Intellectual property information management system
US20060080326A1 (en) Method for reengineering of business processes
Rudberg et al. APS for tactical planning in a steel processing company
KR20230059331A (en) project management system
Medina-Serrano et al. Collaborative and sustainable supply chain practices: a case study
Liu et al. Dynamic co-ordinated scheduling in the supply chain considering flexible routes
Skobelev et al. Designing Distributed Multi-Agent System for Aggregate and Final Assembly of Complex Technical Objects on Ramp-up Stage.
Filip Modern methods and tools to improve the production processes from small series and unique production
Davis Management information systems (MIS)
JP2011022653A (en) Internet recruiting system
Belyakova et al. Formation of models of industrial cooperation management of machine-building enterprises in the transition to a digital manufacturing
Fähling et al. Managing an IT carve-out at a multi-national enterprise
Pinker et al. Can flexibility be constraining?
Choi A Knowledge Representation Model for Formalizing Subcontractors′ Scheduling Process
Engelbergs et al. How Zalando uses digital solutions to transform investment controlling
Thomas et al. Building a knowledge base for the knowledge worker system
Folgo Accelerating time-to-market in the global electronics industry
Rüttimann et al. Office Cell Design
Lewiński Visual Management as the Support in Building the Concept of Continuous Improvement in the Enterprise

Legal Events

Date Code Title Description
E902 Notification of reason for refusal