KR20220018267A - Bow beam structure - Google Patents

Bow beam structure Download PDF

Info

Publication number
KR20220018267A
KR20220018267A KR1020200098554A KR20200098554A KR20220018267A KR 20220018267 A KR20220018267 A KR 20220018267A KR 1020200098554 A KR1020200098554 A KR 1020200098554A KR 20200098554 A KR20200098554 A KR 20200098554A KR 20220018267 A KR20220018267 A KR 20220018267A
Authority
KR
South Korea
Prior art keywords
wale
facility
beam structure
present
retaining wall
Prior art date
Application number
KR1020200098554A
Other languages
Korean (ko)
Inventor
조광현
Original Assignee
조광현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 조광현 filed Critical 조광현
Priority to KR1020200098554A priority Critical patent/KR20220018267A/en
Publication of KR20220018267A publication Critical patent/KR20220018267A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Abstract

The present invention relates to a retaining wall temporary facility wale structure. A product is developed by inserting a hydraulic jack function into the structure. A preload is given to a retaining wall facility to greatly help in maintaining safe facilities. The present invention uses a method of calculating a design axial force for a temporary facility retaining wall in an earth anchor construction method to use a tensioner for each step to fix the temporary facility retaining wall after tensioning in accordance with the axial force to respond to rear soil pressure among present temporary facility construction methods. The method maintains sturdiness and uses the inserted hydraulic jack function in the waling structure to calculate the response axial force in accordance with the depth of each retaining wall facility step to assign a reverse load to the rear soil pressure to fix the structure. Also, the waling structure is maximally elongated to be constructed to greatly reduce loss in steel of a truss (strut) which is a problem at a site.

Description

띠장(보)빔 구조체{BOW BEAM STRUCTURE}STRUCTURE {BOW BEAM STRUCTURE}

본 발명은 흙막이 가시설 시공시 띠장(보)빔구조체에 관한 것으로, 더욱 상세하게는 맞춤 제작한 띠장빔에 역하중잭(jack) 기능을 삽입시켜 본 구조물을 통해 시공의 안전성과 편의성 및 효율성 갖게 하는 흙막이 가시설 시공시 적용 할 수있는 구조체 에 관한 것이다.The present invention relates to a wale (beam) beam structure when constructing temporary retaining facilities, and more particularly, by inserting a reverse load jack function into a custom-made wale beam to have safety, convenience and efficiency of construction through this structure It relates to a structure that can be applied when constructing a temporary retaining facility.

일반적으로 흙막이 가시설은 건축물 지하시설, 지하철, 하수관거 등과 같은 공사시 지반 터파기를 하게 되는데, 이때 흙의 붕괴를 막고 지하 구조물을 설치하기 위하여 가시설 설치를 하게 된다. In general, temporary earth retaining facilities are excavated during construction such as underground facilities of buildings, subways, sewage pipes, etc. At this time, temporary facilities are installed to prevent soil collapse and install underground structures.

이러한 흙막이 가시설은 토사붕괴등 안전성 확보가 중요하므로, 많은량 의 버팀보(트러스). 수직받침보. 수평 간격제등 으로 설치를 하고 있다.For these temporary retaining facilities, securing safety such as soil collapse is important, so a large amount of support (truss) is required. vertical support beam. It is installed with horizontal spacers.

그러나, 버팀보(트러스) 설치를 위한 강제와 경비등이 증가하며, 이는 장비의 지하 굴착시 시설 구조물에 간섭으로 인한 불편함으로 공사기간이 연장되며, 강제의 매립등 손실의 결과를 나타내게 된다.However, the force and cost for installing the brace (truss) increase, and this increases the construction period due to the inconvenience caused by interference with the facility structure during underground excavation of equipment, and results in losses such as forced landfill.

상기와 같이 문제점을 해결하기 위한 본 발명의 목적은 흙막이 가시설 공사시 벽체를 지지하기 위하여 버팀보(트러스)빔 과 세로받침보(매립)빔 설치를 생략함으로서, 자제의 손실과 목적하는 시공의 편의성을 확보할수 있는 흙막이 가시설 시공시 사용할수 있는 견고한 띠장(보)빔 구조체을 제공하는 데 있다.The purpose of the present invention to solve the above problems is to omit the installation of a beam (truss) beam and a vertical support beam (buried) beam to support the wall during the construction of temporary retaining facilities, thereby reducing the loss of self-restraint and the convenience of the desired construction. It is to provide a strong wale (beam) beam structure that can be used in the construction of temporary retaining facilities that can be secured.

상기와 같은 목적을 달성하기 위한 본 발명의 흙막이 가시설 구조체는 공사 순서에 맞추어 수직 천공 후 삽입하는 수직빔; 및 상기 수직빔의 일정간격의 터파기와 토류판 내지는 기타의 방법으로 흙막이 한후 일정 간격에 수직빔 전면에 보빔 (띠장빔)를 설치하게 된다. 이후 본 구조체를 설치, 역하중젝을 삽입 시킨 부재 로서 지하터파기시 단계별 배면토압에 대응하는 견고한 띠장(보)빔구조체를 설치하는 것을 특징으로 한다.Retaining temporary facility structure of the present invention for achieving the above object Vertical beams inserted after vertical drilling according to the construction order; And after digging the vertical beam at regular intervals and retaining the earth using earth plates or other methods, a beam is installed in front of the vertical beam at regular intervals. After this structure is installed, it is characterized by installing a solid wale beam structure corresponding to the back earth pressure in each stage when digging underground as a member with a reverse load project inserted.

상기 구조체를 부착하여 구조체 내부에 삽입되어 있는 유압젝(jack)에 기능으로 외력을 가하여, 시설에 공간을 차단할 수가 있으며 배면 토압에 대응하는 것을 특징으로 한다.By attaching the structure and applying an external force as a function to a hydraulic jack inserted into the structure, it is possible to block the space in the facility, and it is characterized in that it responds to the back earth pressure.

흙막이시설과 터파기시 심도와 넓이에 따라 단계별 배면토압이 다르게 계상되므로 단계별 현장여건에 맞추어 설계축력과 안전율을 고려한 정확한 선행 역하중을 부여하여, 예를들면 어스앵커공법시 단계별 설계축력에 따른 인장력을 부여하고 고정을 시킴으로써 배면토압에 대응하는 것과 같이 견고성을 가진 띠장(보)빔구조체에 유압젝 기능을 삽입함으로서 단계별 필요한 역하중을 부여하여, 고정시킴으로서 안전한 시공을 하게된다.Since the back earth pressure is calculated differently for each stage according to the depth and width of the retaining facility and digging site, an accurate preceding reverse load is given in consideration of the design axial force and safety factor according to the site conditions for each stage. By inserting the hydraulic eject function into the wale (beam) beam structure with rigidity as in response to the back earth pressure by applying and fixing it, the necessary reverse load for each stage is given and fixed, so that safe construction is carried out.

이상 과 같이, 본 발명은 흙막이 가시설 시공시 띠장빔구조체로 시공을 하게 되면 보다 안전하고 계산적 수치에 의한 시공을 할 수가 있으므로, 배면토압에 대응을 하며 그 결과 기존에 설치 되고 있는 버팀보(트러스)빔 설치를 최소화 또는 생략 할수 있으며 버팀보(트러스)빔을 받쳐주는 세로받침빔 설치를 생략할수 있으므로 지하 굴착공간 확보 및 강제 설치의 감소 강제손실(매립)을 막을수 있으며 시설에 대한 안전을 확보할 수 있다.As described above, in the present invention, when constructing a temporary retaining facility with a wale beam structure, it is safer and can be constructed by calculations, so it responds to the back earth pressure, and as a result, the existing brace (truss) beam Installation can be minimized or omitted, and the installation of a vertical support beam that supports the truss beam can be omitted, so it is possible to secure an underground excavation space and reduce forced installation.

도 1은 본 발명에 따른 흙막이시설 띠장(보)빔구조체의 사시도이다.
도 2는 본 발명에 따른 흙막이시설 띠장(보)빔구조체의 정면도이다.
도 3은 본 발명에 따른 흙막이시설 띠장(보)빔구조체 연결 연장 정면도이다.
도 4는 본 발명에 따른 흙막이시설 설치예 간략도 이다.
도 5는 본 발명에 따른 흙막이시설 중 보강방법 정면도 이다.
1 is a perspective view of a retaining facility wale (beam) beam structure according to the present invention.
Figure 2 is a front view of the retaining facility wale (beam) beam structure according to the present invention.
Figure 3 is a front view of the extension of the retaining facility wale (beam) beam structure connection according to the present invention.
Figure 4 is a simplified diagram of an installation example of a retaining facility according to the present invention.
Figure 5 is a front view of the reinforcement method of the retaining facility according to the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시 예를 상세히 설명한다. Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those of ordinary skill in the art can easily carry out the present invention.

본 발명의 실시예에 따른 흙막이 가시설 시공시 적용할수 있는 띠장(보)빔 구조체 에 대하여 설명하기로 한다.A wale (beam) beam structure that can be applied when constructing a temporary retaining facility according to an embodiment of the present invention will be described.

도 1 은 본 발명에 따른 구조체로 설치에 따른 흙막이시설 띠장(보)빔구조체 의 사시도 이며, 도2는 본발명에 따른 흙막이시설 띠장(보)빔구조체의 정면도 이다.1 is a perspective view of a retaining facility wale (beam) beam structure according to installation as a structure according to the present invention, and FIG. 2 is a front view of the retaining facility wale (beam) beam structure according to the present invention.

도3은 본발명 에 따른 흙막이시설 띠장(보)빔구조체의 연결 및 길이 연장체결 정면도이다.Figure 3 is a front view of the connection and length extension of the retaining facility wale (beam) beam structure according to the present invention.

도4는 본발명에 따른 흙맑이시설 에 일예로서 수직빔과 토류벽체와 기존띠장설치 등 설치예 간략도이며 여기에 띠장(보)빔구조체의 설치위치 및 시설의 구조형태를 나타내는 도면 이다.4 is a simplified diagram of an installation example such as a vertical beam, an earth wall, and an existing wale installation as an example in the earthenware facility according to the present invention.

도1에 띠장(보)빔구조체 의 사시도를 설명하면, 띠장(보)빔 구조체의 외형과 연결 연장선과 역하중젝(jack)에 위치 및 띠장(보)빔구조체에 삽입부위등 을 표시하는 사시도 이다.When explaining the perspective view of the wale (beam) beam structure in Fig. 1, it is a perspective view showing the outer shape of the wale (beam) beam structure, the connection extension line, the location on the reverse load jack, and the insertion site in the wale (beam) beam structure to be.

도2는 띠장(보)빔구조체에 정면도를 설명하면, 띠장(보)빔구조체의 좌측과 우측은 경계점(고정)을 나타내며, 도1에서의 역하중젝에 위치 및 외형을 보다 상세히 표시하는 도면이다.2 is a front view of the wale (beam) beam structure, the left and right sides of the wale (beam) beam structure indicate boundary points (fixed), and the position and appearance of the wale (beam) beam structure are shown in more detail in the reverse load project in FIG. to be.

도3은 띠장(보)빔구조체의 정면도를 설명하면, 도2에 띠장(보)빔구조체를 연장 및 연결하여 부제의 크기를 증대시켜 현장여건에 맞추어 대응할수 있는 띠장구조체의 정면도이다.3 is a front view of the wale (beam) beam structure, which is a front view of the wale (beam) beam structure, which can be adapted to the field conditions by extending and connecting the wale (beam) beam structure to increase the size of the subheading.

도4는 흙막이 가시설 전체적인 시설 구조로서 수직빔의 위치 토류벽 설치후 띠장의 설치와 이후 본 발명에 띠장(보)빔구조체 의 설치위치를 나타내는 간략도이다.4 is a simplified view showing the installation position of the wale (beam) beam structure in the present invention after the installation of the vertical beam and the installation of the wale after the earth wall is installed as the overall structure of the temporary retaining facility.

이와 같은 띠장(보)빔구조체를 흙막이벽체에 설치를 한다.Install such a wale (beam) beam structure on the retaining wall.

도 4 와 같이 설치도 를 참조하면, 본 발명의 흙막이시설 띠장(보)빔구조체 는 공사 순서에 맞추어 수직 천공하여 삽입하는 수직(말뚝)빔(10)과, 상기 수직빔(10)의 전면에 부착하는 띠장빔(보빔)(11)과 띠장(보)빔구조체(12)도3 과 역하중젝(13)을 포함하여 구성된다.Referring to the installation diagram as in FIG. 4 , the retaining facility wale (beam) beam structure of the present invention is a vertical (piling) beam 10 that is vertically perforated and inserted in accordance with the construction sequence, and the vertical beam 10 is on the front side of the The attached wale (beam) beam (11) and the wale (beam) beam structure (12) are configured to include 3 and a reverse load jek (13).

도5는 흙막이시설 중 설치위치 와 장소에 따라 토압하중의 값이 다르게 되므로 그에 따른 대응방법으로서 하중에 대한 보강 대응시설을 나타내는 정면도이다.Figure 5 is a front view showing the reinforcement response to the load as a countermeasure method according to the value of the earth pressure load varies depending on the installation location and place among the retaining facilities.

여기서, 도3 (12)띠장(보)빔구조체 에 삽입되어 있는 역하중젝 에 실린더를 이용하여 원하는 하중값 을 부여한 다음 고정을 시켜, 흙막이시설의 토압에 대응하는 과학적인 흙막이 시설을 할수 있게된다.Here, by using a cylinder to apply the desired load value to the reverse load project inserted into the wale (beam) beam structure in Fig. 3 (12), and then fix it, a scientific retaining facility corresponding to the earth pressure of the retaining facility can be made. .

상기 띠장(보)빔구조체 는 지하 굴착지별 토압에 대응할수 있는 역하중젝 에 기능으로 하여, 설치위치 및 설치장소에 따른 견고한 형태에 흙막이 가시설 공법이 생성되게 된다.The wale (beam) beam structure functions as a reverse load project that can respond to the earth pressure of each underground excavation site, and a temporary retaining facility construction method is created in a solid form according to the installation location and installation location.

이와 같이, 본 발명에서는 공사 진행 중 굴착 단계에서 장비의 이동 및 흙의 반출시 버팀보 간섭으로 인한 문제를 띠장(보)빔구조체 설치로 해결할 수 있다. 굴착면의 안전과 설치후 문제시 되는 버팀보(트러스)빔 의 미설치또는 최소설치가 가능케 하는 시공 방법이다.As described above, in the present invention, the problem due to the interference of the brace during the movement of equipment and the removal of soil in the excavation stage during construction can be solved by installing the wale (beam) beam structure. This is a construction method that allows the safety of the excavation surface and the non-installation or minimum installation of the truss beam, which is a problem after installation.

이상에서 본 발명의 실시예에 대하여 상세하게 설명하였지만 본 발명의 권리범위는 이에 한정되는 것은 아니고 다음의 청구범위에서 정의하고 있는 본 발명의 기본 개념을 이용한 당업자의 여러 변형 및 개량 형태 또한 본 발명의 권리범위에 속하는 것이다.Although the embodiments of the present invention have been described in detail above, the scope of the present invention is not limited thereto, and various modifications and improvements by those skilled in the art using the basic concept of the present invention as defined in the following claims are also provided. is within the scope of the right.

10 : 수직빔(말뚝빔) 13: 역하중젝(jack)
11 : 띠장빔(보빔)
10: vertical beam (pile beam) 13: reverse load jack (jack)
11: Band-jang-beam (bo-beam)

Claims (3)

띠장(보)빔구조체 에 젝(jack)기능을 삽입시켜 제작한 띠장(보)빔구조체. 지하의 심도와토질에 따른 배면토압에 대응할수 있는 특징으로 하는 흙막이시설 띠장(보)빔구조체.A wale (beam) beam structure manufactured by inserting a jack function into the wale (beam) beam structure. A retaining facility wale (beam) beam structure, characterized in that it can cope with the back earth pressure according to the depth of the basement and the soil quality. 제1항에 있어서,
상기 띠장(보)빔구조체에 삽입되어 있는 역하중젝(jack). 설치위치와 장소에 따라설계축력 에 맞추어 유압실린더를 이용해 젝의 상당부를 밀어오려서 하중젝을 고정시킴으로서 하중에 대한 선행(역)하중으로 대응할수 있는 기능을 특징으로하는 역하중젝(jack).
The method of claim 1,
A reverse load jack inserted into the wale (beam) beam structure. A reverse load jack is characterized by a function that can respond to a preceding (reverse) load to a load by fixing the load jack by pushing up a substantial part of the jack using a hydraulic cylinder according to the design axial force according to the installation location and place.
제1항에 있어서,
상기 띠장(보)빔구조체 에 설치시, 설치장소 및 위치에 따라 토압에 변화가 발생하게 되어 띠장(보)빔구조체의 1단의 설치로 토압에 대한 대응이 불가할시 추가보강 방법으로서 띠장(보)빔구조체 를 2단으로 겹처 시설하는 것을 특징으로 하는 흙막이시설 띠장(보)빔구조체.
The method of claim 1,
When installing on the wale (beam) beam structure, the earth pressure changes depending on the installation location and location. Retaining facility wale (beam) beam structure, characterized in that the beam structure is stacked in two stages.
KR1020200098554A 2020-08-06 2020-08-06 Bow beam structure KR20220018267A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200098554A KR20220018267A (en) 2020-08-06 2020-08-06 Bow beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200098554A KR20220018267A (en) 2020-08-06 2020-08-06 Bow beam structure

Publications (1)

Publication Number Publication Date
KR20220018267A true KR20220018267A (en) 2022-02-15

Family

ID=80325554

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200098554A KR20220018267A (en) 2020-08-06 2020-08-06 Bow beam structure

Country Status (1)

Country Link
KR (1) KR20220018267A (en)

Similar Documents

Publication Publication Date Title
KR100915099B1 (en) Structure for supporting retaining wall of earth with arch material and method constructing the arch structure
KR102162467B1 (en) Thrust pile with prestress and self-supporting type pile construction using it
CN102720201A (en) Support change construction building method implemented by using main structure of building
KR102071225B1 (en) Construction method of sheathing temporary facility using steel sheet pile
CN210459228U (en) Building foundation pit supporting device
KR20070118828A (en) Soil retaining apparatus for digging trench
KR100648409B1 (en) A method of construction for temporary retaining wall
KR101069702B1 (en) Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel
KR20120109418A (en) Inclined earth retaining structure method
JP2012092601A (en) Open shield machine start method of open shield method
JP2022026691A (en) Press bar for open shield construction method
KR20220018267A (en) Bow beam structure
KR100476842B1 (en) soldier beam installed according to axial force in excavating work
KR101221084B1 (en) Temporary pile using bending restoring force and temporary structure construction method therewith
KR20190142547A (en) Improved earth soil pre-stress method
KR20130042099A (en) The construction method of shield tunneling
KR20090067339A (en) A tight connection between steel pipe strut and center pile
KR101952669B1 (en) Temporary facility circular retaining wall method using arched steel plate and guide structure
KR20200137297A (en) Construction method of sheathing temporary facility
JP7309026B1 (en) Earth retaining device for shallow excavated trenches
JP7301203B1 (en) Earth retaining device for shallow excavated trenches
CN216405469U (en) U type tunnel and utility tunnel sharing structure
KR102503383B1 (en) Earth retaining wall
JP7397933B1 (en) Earth retaining device for shallow excavation trenches
JP3673921B2 (en) Preload panel retaining ring