KR20210064954A - Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore - Google Patents

Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore Download PDF

Info

Publication number
KR20210064954A
KR20210064954A KR1020190153757A KR20190153757A KR20210064954A KR 20210064954 A KR20210064954 A KR 20210064954A KR 1020190153757 A KR1020190153757 A KR 1020190153757A KR 20190153757 A KR20190153757 A KR 20190153757A KR 20210064954 A KR20210064954 A KR 20210064954A
Authority
KR
South Korea
Prior art keywords
statement
site
unit
modular building
information
Prior art date
Application number
KR1020190153757A
Other languages
Korean (ko)
Inventor
김지현
이명도
Original Assignee
주식회사 연우테크놀러지
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 연우테크놀러지 filed Critical 주식회사 연우테크놀러지
Priority to KR1020190153757A priority Critical patent/KR20210064954A/en
Publication of KR20210064954A publication Critical patent/KR20210064954A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Geometry (AREA)
  • Primary Health Care (AREA)
  • Computer Hardware Design (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Computational Mathematics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

An object of the present invention is to provide a system and method that can integrally manage construction support at a construction site based on BIM for the factory producing procedure of a modular building and the on-site construction procedure of the modular building. The system for managing the factory producing procedure of the modular building, the on-site construction procedure and on-site construction of the modular building according to the present invention comprises: a unit module extraction part (10); a statement classification part (20); a BIM and statement linkage part (30); a monitoring part (40); and an on-site construction linkage part (60).

Description

모듈러 건축물의 현장 시공 지원 시스템 및 그 제어 방법{Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore}Field construction support system of a modular building and its control method {Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore}

본 발명은 모듈러 건축물의 현장 시공 지원 시스템 및 그 방법에 관한 것으로서, 보다 상세하게는, 모듈러 건축물의 공장제작 수순 및 모듈러 건축물의 현장 시공 수순을 BIM 을 기반으로 하여 통합적으로 관리할 수 있는 모듈러 건축물의 현장 시공 지원 시스템 및 그 방법에 관한 것이다.The present invention relates to a system for supporting on-site construction of a modular building and a method therefor, and more particularly, to a modular building that can integrally manage the factory manufacturing procedure of the modular building and the on-site construction procedure of the modular building based on BIM. It relates to an on-site construction support system and a method therefor.

일반적으로, 건설 분야에 있어서 '비아이엠(BIM)'은, 건축 프로젝트의 전과정에서 요구되는 정보 혹은 활용할 수 있는 정보를 담은 3차원 모델을 구축함으로써 건축 프로젝트의 각 단계별 업무를 디지털 기반의 프로젝트 정보로 제공할 수 있는 도구 및 체계를 지칭하는 것으로서, 빌딩 정보 모델링(Building Information Modeling, 이하, 'BIM'으로 통칭)의 약칭이다.In general, in the field of construction, 'BIM' converts work at each stage of a construction project into digital-based project information by building a three-dimensional model containing information required or usable in the entire process of the construction project. It refers to tools and systems that can be provided, and is an abbreviation for Building Information Modeling (hereinafter, collectively referred to as 'BIM').

이러한 BIM 은 건축 설계에 있어서 시공, 유지 관리에 이르는 건축의 전 단계를 관리하기 위한 통합 데이터베이스에 대한 효용성과 필요성이 제기됨에 따라서 발생된 것으로서, 설계와 시공 프로세스를 관통하는 통합 데이터의 활용 가치를 인정받아 널리 활용되고 있다.This BIM was generated as the utility and need for an integrated database to manage all stages of construction from architectural design to construction and maintenance were raised, and the value of using integrated data that penetrates the design and construction process was recognized. received and widely used.

기존의 2차원 도면을 바탕으로 수행되는 건축 프로젝트는 수많은 분절된 정보의 수동적인 연계, 수작업, 반복적인 업무에서 오는 비효율성을 내재하고 있는 반면, 상기 BIM 은 디지털 정보를 활용할 수 있는 시스템 혹은 프로세스와 연계하여 업무를 수행할 수 있으므로, 기존의 2 차원 도면을 기반으로 수행되는 업무 방식과 비교하여 업무 생산성이 향상되고 결과의 정확성을 확보할 수 있다.Architectural projects based on existing two-dimensional drawings have inherent inefficiencies that come from the passive linkage of numerous fragmented information, manual work, and repetitive tasks, whereas BIM is a system or process that can utilize digital information. Since work can be performed in conjunction, work productivity is improved and the accuracy of results can be secured compared to the existing work method based on two-dimensional drawings.

아울러, 모듈러 건축물은 건축 공법 중에 하나로서 건축물의 벽체, 바닥, 지붕, 욕실, 화장실, 창호, 대문 등의 단위 모듈들을 미리 규격화시켜 제작하는 공장제작 수순과, 제작된 단위 모듈들을 현장에서 상호 결합시키는 현장제작 수순을 포함하는 건축 공법이다.In addition, the modular building is one of the construction methods, and the factory manufacturing procedure of standardizing and manufacturing unit modules such as walls, floors, roofs, bathrooms, toilets, windows, and doors of the building in advance, and combining the manufactured unit modules with each other in the field. It is a construction method that includes on-site manufacturing procedures.

이러한 모듈러 건축물의 건축 공법에 따르면, 건축물의 단위 구성요소들을 미리 제작하는 공장제작 수순이 전체 공정의 대략 70% 를 차지하고 있는데, 상술한 BIM 은 설계에만 적용되고 있어 공장제작 수순에서는 BIM 의 효용성이 매우 저하된다.According to the construction method of such a modular building, the factory manufacturing procedure of prefabricating the unit components of the building occupies approximately 70% of the total process. Since the above-mentioned BIM is applied only to design, the effectiveness of BIM is very high in the factory manufacturing procedure. is lowered

또한, 모듈러 건축물은 소규모의 산발적인 건축물 프로젝트가 많은데 이로 인하여 모듈러 건축물의 공정의 각 단계의 관리가 인력 중심이며 업무효율성 향상에 대한 방안이 부재하므로, 현재 공정이 어디까지 진행되고 있는지 비용, 인력, 장비가 얼마만큼 투입되고 있는지 파악하기 위해서는 각 공정을 수작업으로 직접 확인하여야만 하므로, 효율성 및 정확성이 저하되고 있는 실정으로 이를 개선하기 위한 방안이 요구되고 있다.In addition, there are many small-scale, sporadic building projects for modular buildings. As a result, the management of each stage of the modular building process is man-centered and there is no plan to improve work efficiency. In order to find out how much equipment is being put in, each process must be manually checked, so efficiency and accuracy are declining, and a method for improving this is required.

그러므로, 이러한 모듈러 건축물의 제작 공정의 대략 70% 를 차지하고 있는 공장제작 수순을 BIM 을 기반으로 통합적으로 관리할 수 있는 시스템 및 방법을 개발할 필요성이 상존하고 있다.Therefore, there is a constant need to develop a system and method that can manage the factory manufacturing procedure, which accounts for approximately 70% of the manufacturing process of such a modular building, in an integrated manner based on BIM.

한편, 상기의 BIM 에 관한 공지 기술로서 대한민국공개특허공보 제 10-2010-20060 호의 세견 기반의 BIM 정보 관리 시스템, 대한민국특허등록공보 제 976544 호의 BIM을 활용한 공간모델링 장치 및 대한민국특허등록공보 제 1224627 호의 구조 비아이엠을 이용한 건축 구조물의 설계 및 물량 산출 방법이 공지되어 있다.On the other hand, as a known technology related to the above BIM, the spatial modeling apparatus using the BIM information management system based on the Segyun of Korean Patent Application Laid-Open No. 10-2010-20060, the BIM of Korean Patent Registration No. 976544, and the Korean Patent Registration Publication No. 1224627 A method for designing a building structure and calculating a quantity using the arc structure BIM is known.

뿐만 아니라, 실제 설계된 건축물의 경우 현장에서의 물리적 제약으로, 시공되는 실제 현장에서 시공시 설계 당시의 설계안의 정확한 의도가 반영되지 못하여 정확한 시공 공정이 이루어지기 어렵고 관리에 제약이 따른다는 문제점이 수반된다. In addition, in the case of an actually designed building, due to physical constraints on the site, the exact intention of the design at the time of design is not reflected during construction at the actual site where it is being constructed, so it is difficult to perform the correct construction process and there are limitations in management. .

본 발명은 상기와 같은 종래의 제반 문제점들을 해소하기 위하여 창안된 것으로서, 모듈러 건축물의 공장제작 수순 및 모듈러 건축물의 현장 시공 수순을 BIM 을 기반으로 시공 현장에서의 시공 지원을 통합적으로 관리할 수 있는 시스템 및 방법을 제공한다. The present invention was created to solve the problems of the prior art as described above. A system that can manage the construction support at the construction site in an integrated manner based on the BIM for the factory manufacturing procedure of modular buildings and the on-site construction procedures of modular buildings and methods.

상기의 기술적 과제를 달성하기 위한 본 발명의 모듈러 건축물의 현장 시공 지원 시스템 및 그 방법은, 모듈러 건축물의 BIM 모델을 로드하고 로드된 BIM 모델을 각 단위 모듈별로 분개하고 분개된 각 단위 모듈을 타입별로 그룹핑하는 BIM 단위모듈 추출부와, 모듈러 건축물의 설계사로부터 제공된 모듈러 건출물의 내역서를 로드하고 로드된 내역서를 타입별로 구분하여 공장제작 수순과 현장제작 수순에 필요한 공장제작분 내역서와 현장제작분 내역서로 구분하는 내역서 분류부와, 상기 BIM 단위모듈 추출부로부터 타입별로 그룹핑된 BIM 단위모듈과 상기 내역서 분류부에서 분류된 공장제작분 내역서와 현장제작분 내역서를 전달받아 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 구성요소들의 수량과 내역 정보를 산출하고, 산출된 수량과 내역 정보에 따라서 각 공종별 작업시간정보, 투입인력정보, 장비정보를 포함하는 세부공종정보를 산출하는 BIM 및 내역서 연계부와, 상기 BIM 및 내역서 연계부에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고, 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 디스플레이수단에 표시하여 주는 모니터링부와, 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보를 산출하는 현장 시공 연계부(60)를를 포함하는 모듈러 건축물의 현장 시공 지원 시스템 및 그 방법으로 구성된다.The on-site construction support system and method of a modular building of the present invention for achieving the above technical task, load the BIM model of the modular building, journal the loaded BIM model for each unit module, and divide each journaled unit module by type The grouping BIM unit module extraction unit, and the detailed statement of the modular building provided by the designer of the modular building are loaded and the loaded statement is classified by type, and divided into the factory production and field production details required for the factory production procedure and the on-site production procedure BIM unit module grouped by type from the BIM unit module extracting unit and the factory production statement and field production statement classified by the statement classification unit are delivered to the factory production sequence and the on-site production sequence. BIM and statement linkage that calculates the quantity and detail information of unit components that make up the modular building and calculates detailed work type information including work time information, input manpower information, and equipment information for each work type according to the calculated quantity and detail information A monitoring unit that lists the quantity and detail information and detailed work type information calculated by the department and the BIM and statement linkage unit, and displays the real-time work status of the work type on the display means when the list is selected, and in the modular building The temporary facility BIM library and interference factor BIM library for Korea, the on-site construction schedule of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 Modular including a field construction linkage unit 60 for calculating on-site construction plan information including on-site construction temporary plans and on-site construction joint plans for constructing each unit module on-site using the factory production statement and on-site production statement It consists of a construction site support system for a building and its method.

상기 모듈러 건축물의 현장 시공 지원 시스템에 있어서, 상기 단위모듈 추출부(10)가 이용하는 BIM 모델은 BIM 을 설계하는 BIM 설계용 컴퓨터 프로그램에 의하여 작성될 수도 있다. In the on-site construction support system of the modular building, the BIM model used by the unit module extraction unit 10 may be created by a BIM design computer program for designing the BIM.

상기 모듈러 건축물의 현장 시공 지원 시스템에 있어서, 상기 내역서 분류부(20)가 이용하는 내역서 정보는, 모듈러 건축물의 설계사로부터 제공되어 데이터베이스(50)에 저장된 정보일 수도 있다. In the on-site construction support system of the modular building, the statement information used by the statement classification unit 20 may be information provided by a designer of the modular building and stored in the database 50 .

상기 모듈러 건축물의 현장 시공 지원 시스템에 있어서, 상기 BIM 및 내역서 연계부(30)가 산출하는 세부공종정보는, 작업시간정보, 투입인력정보, 장비정보를 포함할 수도 있다. In the on-site construction support system of the modular building, the detailed work type information calculated by the BIM and statement linkage unit 30 may include work time information, input manpower information, and equipment information.

상기 모듈러 건축물의 현장 시공 지원 시스템에 있어서, 상기 모니터링부(40)는, 실시간으로 모니터링되는 공종별 작업상황에 있어서 중요 사항을 캡쳐할 수 있으며, 이를 해당 작업의 작업자 및 공정별 작업 스테이션에 제공하여 품질 관리를 지원할 수도 있다. In the on-site construction support system of the modular building, the monitoring unit 40 can capture important matters in the work situation by work type monitored in real time, and provide it to the worker of the work and the work station for each process to provide quality You can also support management.

상기 모듈러 건축물의 현장 시공 지원 시스템에 있어서, 상기 모니터링부(40)는, 사용자인터페이스 화면을 제공하되, 상기 사용자인터페이스 화면의 좌측 영역(A)에 상기 BIM 및 내역서 연계부(30)에서 산출된 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보 및 각 공종별 세부공종정보가 표시되고, 상기 사용자인터페이스 화면의 중앙 영역(B)에 상기 모니터링부(40)가 제공하는 해당 공종의 실시간 작업상황이 표시되고, 상기 사용자인터페이스화면의 우측 영역(C)에 전체적인 공장제작 현황의 선택 메뉴가 표시되는 구성을 구비할 수도 있다. In the on-site construction support system of the modular building, the monitoring unit 40 provides a user interface screen, but the BIM and statement linkage unit 30 in the left area (A) of the user interface screen calculates the factory The quantity and detail information of the unit modules constituting the modular building required in the manufacturing procedure and the on-site manufacturing procedure and detailed work type information for each work type are displayed, and the monitoring unit 40 is provided in the central area (B) of the user interface screen It may be provided with a configuration in which the real-time work status of the corresponding work type is displayed, and a selection menu of the overall factory production status is displayed in the right area (C) of the user interface screen.

상기 모듈러 건축물의 현장 시공 지원 시스템에 있어서, 상기 현장 시공 연계부(60)는: 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여, 각 단위모듈을 현장에서 시공하는데 사용되는 현장 가설 시설물에 대한 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보를 산출하는 현장 시공 가설 계획 연계부(61)와, 각 단위모듈을 현장에서 시공하는 공정 순서에 대한 현장 시공 공졍 계획 정보를 산출하는 현장 시공 공정 가설 계획 연계부(63)를 구비할 수도 있다.In the on-site construction support system of the modular building, the on-site construction link unit 60 includes: a temporary facility BIM library and an interfering element BIM library for the modular building, a field construction schedule of a modular building provided by a designer of the modular building, and the Using the unit module grouped by type from the unit module extraction unit 10 and the factory-made statement and field-made statement classified by the statement classification unit 20, field hypothesis used to construct each unit module in the field The on-site construction temporary plan linking unit 61 for calculating on-site temporary facility type information and on-site temporary facility location information for the facility, and on-site construction for calculating on-site construction work plan information for the process sequence of constructing each unit module in the field A process hypothesis planning linkage unit 63 may be provided.

본 발명의 다른 일면에 따르면, 본 발명은, 모듈러 건축물의 공장제작 수순 및 모듈러 건축물의 현장 시공 수순을 관리하는 시스템에 의하여 수행되는 관리 방법에 있어서, 상기 모듈러 건축물의 BIM 모델을 로드하고(S11), 로드된 BIM 모델을 각 단위 모듈별로 분개하고(S12), 분개된 각 단위 모듈을 타입별로 그룹핑(S13)하는 단위모듈 추출단계(S1); 모듈러 건축물의 설계사로부터 제공된 모듈러 건출물의 내역서를 로드하고(S21), 로드된 내역서를 타입별로 구분하여 공장제작 수순과 현장제작 수순에 필요한 공장제작분 내역서와 현장제작분 내역서로 구분(S22)하는 내역서 분류단계(S2); 상기 단위모듈 추출단계(S1)에서 타입별로 그룹핑된 단위모듈과 상기 내역서 분류단계(S2)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 전달받고(S31), 전달받은 단위모듈 및 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보를 산출하고(S32), 산출된 수량과 내역 정보에 따라서 각 공종별 세부공종정보를 산출(S33)하는 BIM 및 내역서 연계단계(S3); 상기 BIM 및 내역서 연계단계(S3)에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고(S41), 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 디스플레이수단에 표시하여 주는(S42) 모니터링 단계(S4); 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보이 현장 시공 연계부(60)에서 산출되는 현장 시공 연계 단계(S5);를 포함하여 구성되는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템 제어 방법을 제공한다. According to another aspect of the present invention, in the management method performed by the system for managing the factory manufacturing procedure of the modular building and the field construction procedure of the modular building, the BIM model of the modular building is loaded (S11) , a unit module extraction step (S1) of journaling the loaded BIM model for each unit module (S12), and grouping each journaled unit module by type (S13); A statement of loading the statement of the modular building provided by the designer of the modular building (S21), classifying the loaded statement by type, and dividing it into a statement of factory production and a statement of on-site production required for the factory production procedure and on-site production procedure (S22) classification step (S2); In the unit module extraction step (S1), the unit module grouped by type and the factory production statement and field production statement classified in the statement classification step (S2) are delivered (S31), and the received unit module and factory production sequence BIM and statement linkage step of calculating the quantity and detail information of unit modules constituting the modular building required in the field production procedure (S32), and calculating detailed work type information for each work type according to the calculated quantity and detail information (S33) (S3); A monitoring step of listing the quantity, detail information, and detailed work type information calculated in the BIM and statement linkage step (S3) (S41), and displaying the real-time work status of the work type on the display means when the list is selected (S42) (S4); Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), the site construction plan information including the on-site construction temporary plan and on-site construction joint plan for constructing each unit module on-site using the factory production statement and on-site statement On-site construction linkage step (S5); provides a method for controlling the on-site construction support system of a modular building, characterized in that it is configured to include.

상기 모듈러 건축물의 현장 시공 지원 시스템 제어 방법에 있어서, 상기 모니터링 단계(S4)는, 실시간으로 모니터링되는 공종별 작업상황에 있어서 중요 사항을 캡쳐할 수 있으며, 이를 해당 작업의 작업자 및 공정별 작업 스테이션에 제공하여 품질 관리를 지원할 수도 있다. In the method for controlling the on-site construction support system of the modular building, the monitoring step (S4) may capture important matters in the real-time monitoring work situation for each work type, and provide it to the worker of the work and the work station for each process to support quality control.

상기 모듈러 건축물의 현장 시공 지원 시스템 제어 방법에 있어서, 상기 현장 시공 연계 단계(S5)는, 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여, 각 단위모듈을 현장에서 시공하는데 사용되는 현장 가설 시설물에 대한 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보가 현장 시공 가설 계획 연계부(61)에서 산출되는 현장 시공 가설 계획 연계 단계(S51)와, 각 단위모듈을 현장에서 시공하는 공정 순서에 대한 현장 시공 공졍 계획 정보가 현장 시공 공정 가설 계획 연계부(63)에서 산출될 수도 있다.In the method for controlling the on-site construction support system of the modular building, the on-site construction link step (S5) includes a temporary facility BIM library and an interfering element BIM library for the modular building, a field construction process table of a modular building provided by a designer of the modular building And by using the unit module grouped by type from the unit module extraction unit 10, and the factory-made statement and field-made statement classified in the statement classification unit 20, each unit module is used for construction in the field. The on-site temporary facility type information and the on-site temporary facility location information for the on-site temporary facility are calculated by the on-site construction temporary plan link unit 61, the on-site construction temporary plan connection step (S51), and the process sequence of constructing each unit module on-site On-site construction work plan information for the on-site construction process may be calculated by the hypothesis planning link unit 63 .

본 발명의 또 다른 일면에 따르면, 본 발명은 상기 모듈러 건축물의 현장 시공 지원 시스템 제어 방법을 수행하는 컴퓨터 프로그램이 수록된 컴퓨터에 의하여 판독가능한 저장매체를 제공할 수도 있다.According to another aspect of the present invention, the present invention may provide a computer-readable storage medium in which a computer program for performing the method for controlling the on-site construction support system of the modular building is recorded.

상기와 같은 본 발명의 모듈러 건축물의 현장 시공 지원 시스템 및 그 방법은, 모듈러 건축물의 전체 공정의 대략 70% 를 차지하는 공장제작 수순을 BIM 을 기반으로하여 통합적으로 관리할 수 있는 효과가 있다. The on-site construction support system and method of a modular building of the present invention as described above has the effect of being able to manage the factory manufacturing procedure, which occupies approximately 70% of the entire process of the modular building, in an integrated manner based on BIM.

또한, 모듈러 건축물의 투입 비용, 작업 인력, 장비 등이 내역서와 연계되어 표현되므로 공정과 비용이 통합적으로 관리할 수 있게 된다.In addition, since the input cost of the modular building, manpower, equipment, etc. are expressed in connection with the statement, the process and cost can be managed in an integrated manner.

또한, 각 공종별 중요사항을 즉각적으로 확인하여 공장제작 수순과 현장제작 수순을 수행하는 각 담당자에게 전달하여 줄 수 있어 모듈러 건축물의 건축물 품질관리를 지원할 수 있게 된다. In addition, it is possible to immediately check the important matters for each type of work and deliver it to each person in charge who performs the factory production procedure and the on-site production procedure, thereby supporting the building quality management of the modular building.

또한, 관리자가 BIM 모델과 실제 현장의 작업상황을 실시간 비교할 수 있어 공정 진행을 신속하고 정확하게 관리할 수 있게 된 효과를 수득하게 되었다.In addition, the manager can compare the BIM model with the actual work situation in real time, so that the process progress can be managed quickly and accurately.

도 1은 본 발명 모듈러 건축물의 현장 시공 지원 시스템의 구성도,
도 2는 본 발명의 모듈러 건축물의 현장 시공 지원 시스템의 모니터링부에서 제공되는 사용자인터페이스 화면의 일례,
도 3은 본 발명의 모듈러 건축물의 공장제작 관리 방법의 순서도,
도 4는 본 발명 모듈러 건축물의 현장 시공 지원 시스템의 변형 구성도,
도 5는 본 발명의 모듈러 건축물의 공장제작 관리 방법의 변형 순서도,
도 6은 본 발명 모듈러 건축물의 현장 시공 지원 시스템의 세부 구성의 변형 구성도,
도 7은 본 발명의 모듈러 건축물의 현장 시공 지원 시스템의 모니터링부에서 제공되는 사용자인터페이스 화면의 다른 일례이다.
1 is a block diagram of the on-site construction support system of the present invention modular building;
2 is an example of a user interface screen provided by the monitoring unit of the on-site construction support system of the modular building of the present invention;
3 is a flowchart of a factory production management method of a modular building of the present invention;
4 is a modified configuration diagram of the on-site construction support system of the present invention modular building;
5 is a modified flowchart of the factory production management method of the modular building of the present invention;
6 is a modified configuration diagram of the detailed configuration of the on-site construction support system of the present invention modular building;
7 is another example of the user interface screen provided by the monitoring unit of the on-site construction support system of the modular building of the present invention.

이하, 도면을 참조하여 본 발명의 BIM 기반의 모듈러 건축용 통합 운영 시스템 및 그 방법의 구성 및 작동을 상세하게 설명한다.Hereinafter, the configuration and operation of the BIM-based integrated operating system for modular construction of the present invention and the method thereof will be described in detail with reference to the drawings.

단, 개시된 도면들은 당업자에게 본 발명의 사상이 충분하게 전달될 수 있도록 하기 위한 예로서 제공되는 것이다. 따라서, 본 발명은 이하 제시되는 도면들에 한정되지 않고 다른 태양으로 구체화될 수도 있다.However, the disclosed drawings are provided as examples to sufficiently convey the spirit of the present invention to those skilled in the art. Accordingly, the present invention is not limited to the drawings presented below and may be embodied in other aspects.

또한, 본 발명 명세서에서 사용되는 용어에 있어서 다른 정의가 없다면, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 통상적으로 이해하고 있는 의미를 가지며, 하기의 설명 및 첨부 도면에서 본 발명의 요지를 불필요하게 흐릴 수 있는 공지 기능 및 구성에 대한 상세한 설명은 생략한다.In addition, unless there is another definition in the terms used in the present specification, those of ordinary skill in the art to which the present invention pertains have the meaning commonly understood, and the gist of the present invention in the following description and accompanying drawings Detailed descriptions of well-known functions and configurations that may be unnecessarily obscure will be omitted.

도 1 은 본 발명의 모듈러 건축물의 현장 시공 지원 시스템의 구성도이다.1 is a block diagram of the on-site construction support system of the modular building of the present invention.

본 발명의 모듈러 건축물의 현장 시공 지원 시스템(1)(이하, 공장제작 관리 시스템으로 약칭)은, 모듈러 건축물의 BIM 모델을 로드하고 로드된 BIM 모델을 각 단위 모듈별로 분개하고 분개된 각 단위 모듈을 타입별로 그룹핑하는 단위모듈 추출부(10)와, 모듈러 건축물의 설계사로부터 제공된 모듈러 건출물의 내역서를 로드하고 로드된 내역서를 타입별로 구분하여 공장제작 수순과 현장제작 수순에 필요한 공장제작분 내역서와 현장제작분 내역서로 구분하는 내역서 분류부(20)와, 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 전달받아 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보를 산출하고, 산출된 수량과 내역 정보에 따라서 각 공종별 작업시간정보, 투입인력정보, 장비정보를 포함하는 세부공종정보를 산출하는 BIM 및 내역서 연계부(30)와, 상기 BIM 및 내역서 연계부(30)에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고, 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 디스플레이수단에 표시하여 주는 모니터링부(40)를 포함한다. 또한, 경우에 따라 시공 현장에서의 현장 시공 계획 지원을 위한 구성요소로서, 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보를 산출하는 현장 시공 연계부(60)를 더 구비할 수도 있다. The on-site construction support system (1) of the modular building of the present invention (hereinafter, abbreviated as factory production management system) loads the BIM model of the modular building and journals the loaded BIM model for each unit module, The unit module extraction unit 10 for grouping by type, loading the statement of the modular building provided by the designer of the modular building, and classifying the loaded statement by type, the statement of factory production and on-site production necessary for the factory production procedure and the on-site production procedure The statement classification unit 20 divided into minute statements and the unit module grouped by type from the unit module extraction unit 10 and the factory production statement and field production statement classified by the statement classification unit 20 are delivered It calculates the quantity and detail information of the unit modules constituting the modular building required in the factory manufacturing procedure and the on-site manufacturing procedure, and includes work time information, input manpower information, and equipment information for each work type according to the calculated quantity and detailed information. BIM and statement linkage unit 30 that calculates detailed work type information, and lists the quantity and detail information and detailed work type information calculated by the BIM and statement linkage unit 30, and when the list is selected, real-time work of the work type It includes a monitoring unit 40 for displaying the situation on the display means. In addition, in some cases, as a component for supporting on-site construction planning at the construction site, the temporary facility BIM library and interfering element BIM library for the modular building, the on-site construction schedule of the modular building provided by the designer of the modular building, and the unit module On-site construction hypothesis planning and on-site construction in which each unit module is constructed in the field using the unit modules grouped by type from the extraction unit 10 and the factory production breakdown and field production breakdown classified by the statement classification unit 20 It may further include an on-site construction linkage unit 60 for calculating on-site construction plan information including a co-authorship plan.

상기 단위모듈 추출부(10)가 이용하는 BIM 모델은 건축물 전용 라이브러리 및 매뉴얼을 기반으로 하여 BIM 을 설계하는 공지의 BIM 설계용 컴퓨터 프로그램에 의하여 작성된 것으로서, 건축물을 물리적 단위인 공간 객체와 부위 객체로 분류시켜 목록(list)화 되어 있다.The BIM model used by the unit module extraction unit 10 is created by a known computer program for BIM design that designs BIM based on a library and manual dedicated to buildings, and classifies buildings into spatial objects and part objects, which are physical units. It is made into a list.

상기 공간 객체는 건축물의 층, 구역, 실 등 공간의 범위를 정의하는 객체이고, 상기 부위 객체는 건축물의 공간을 둘러싸고 공간의 기능을 지원하는 시설물의 구성 요소인 기둥, 벽, 문, 창 등과 같은 객체이며, 이러한 공간 객체와 부위 객체에 식별, 형상, 물성, 참고 등의 각 객체별 속성이 부여되어 있다.The space object is an object defining the scope of space such as a floor, a zone, a room, etc. of a building, and the part object surrounds the space of the building and supports the function of the space, such as columns, walls, doors, windows, etc. It is an object, and properties for each object such as identification, shape, physical properties, and reference are given to these spatial and part objects.

상기 단위모듈추출부(10)는 상술한 바와 같이 목록화된 공간 객체와 부위 객체로 이루어진 BIM 모델을 로드하고, BIM 모델에 기초하여 모듈러 건축물을 이루는 벽체, 바닥, 지붕, 욕실, 화장실, 창호, 대문, 계단, 승강기, 전기설비, 가스설비, 수도설비 등의 단위 모듈로 분개하고, 분개된 각 단위 모듈을 건축, 구조, 설비의 각 타입별로 그룹화시킨다.The unit module extraction unit 10 loads the BIM model consisting of the spatial objects and the part objects listed as described above, and based on the BIM model, the walls, floors, roofs, bathrooms, toilets, windows, It is divided into unit modules such as gates, stairs, elevators, electrical equipment, gas equipment, water equipment, etc., and each of the journalized unit modules is grouped by each type of architecture, structure, and equipment.

상기 내역서 분류부(20)는 모듈러 건축물의 설계사로부터 제공되어 데이터베이스(50)에 저장된 정보인 모듈러 건출물의 내역서 정보를 로드하고 로드된 내역서 정보에 따라서 공장제작 수순에 필요한 공장제작분 내역서와, 현장제작 수순에 필요한 현장제작분 내역서로 구분한다.The statement classification unit 20 loads the statement information of the modular building, which is information provided from the designer of the modular building and stored in the database 50, and according to the loaded statement information, the factory production statement necessary for the factory production procedure, and on-site production It is divided into the details of on-site production required for the procedure.

예를 들어, 상기 공장제작분 내역서로서 원자재 반입, 원자재 기본 가공, 가동된 원자재를 이용하여 벽체나 지붕과 같은 단위 모듈의 제작에 필요한 투입 자재, 제작시간, 투입인력 인원수, 제작에 필요한 장비 등의 내역 정보를 들 수 있다.For example, as the statement of factory production, the input materials required for the production of unit modules such as walls or roofs using raw materials, basic processing of raw materials, and operation of raw materials, production time, number of input personnel, equipment required for production, etc. historical information is available.

또한, 예를 들어, 상기 현장제작분 내역서로서, 제작된 단위 모듈의 운반, 단위 모듈 시공을 위한 기초 공사, 단위 모듈 시공에 필요한 투입 자재, 시공 시간, 투입 인력 인원수, 시공에 필요한 장비, 현장 지장물, 현장 특이사항 등의 내역 정보를 들 수 있다. In addition, for example, as the statement of field production, the transport of the manufactured unit module, the foundation work for the unit module construction, the input materials required for the unit module construction, the construction time, the number of input manpower, the equipment required for construction, the site disturbance Information on details such as water, site specifics, etc. may be mentioned.

상기 BIM 및 내역서 연계부(30)는 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈들과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서 정보와 현장제작분 내역서 정보를 전달받고, 전달받은 내역서 정보에 기초하여 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보를 산출하고, 산출된 수량과 내역 정보에 따라서 각 공종별 작업시간정보, 투입인력정보, 장비정보를 포함하는 세부공종정보를 산출한다.The BIM and statement link unit 30 transmits unit modules grouped by type from the unit module extraction unit 10 and factory-made statement information and field-made statement information classified by the statement classification unit 20 . Based on the received and received statement information, the quantity and detail information of the unit modules constituting the modular building required in the factory production procedure and the on-site production procedure are calculated, and according to the calculated quantity and detailed information, work time information and input for each work type Calculation of detailed work information including manpower information and equipment information.

상기 모니터링부(40)는 상기 BIM 및 내역서 연계부(30)에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고, 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 모니터와 같은 디스플레이수단에 표시하여 줌으로써 공장제작에 대한 전체 공정을 실시간으로 모니터링한다.The monitoring unit 40 lists the quantity and detail information and detailed work type information calculated by the BIM and statement linkage unit 30, and when the list is selected, the real-time work status of the work type is displayed on a display means such as a monitor. By doing this, the entire process of factory production is monitored in real time.

이때, 관리자는 모니터링부(40)에 표시되는 각 공종별 작업 상황을 실시간으로 모니터링하다가, 작업에 있어 중요한 사항을 BIM 모델에서 즉각적으로 텍스트 등을 입력하여 캡쳐하고, 이를 해당 작업의 작업자 및 공정별 작업 스테이션에 제공함으로써 공장제작 수순에서의 품질 관리를 지원할 수 있게 된다.At this time, the manager monitors the work status for each work type displayed on the monitoring unit 40 in real time, and captures important matters in the BIM model by immediately inputting text, etc. By providing it to the station, it is possible to support quality control in the factory production sequence.

한편, 상기의 단위모듈 추출부(10), 내역서 분류부(20), BIM 및 내역서 연계부(30) 및 모니터링부(40)에서 산출되거나 이용되는 데이터들은 이들과 연동된 데이터베이스(50)에 저장 및 갱신된다.On the other hand, the data calculated or used in the unit module extraction unit 10, the statement classification unit 20, the BIM and statement linkage unit 30 and the monitoring unit 40 are stored in the database 50 linked thereto. and updated.

또 한편, 본 발명의 모듈러 건축물의 현장 시공 지원 시스템은 현장 시공 연계부(60)를 더 구비할 수 있는데, 현장 시공 연계부(60)는 시공 현장에서의 현장 시공 계획 지원을 위한 구성요소로서, 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보를 산출할 수 있다. On the other hand, the on-site construction support system of the modular building of the present invention may further include an on-site construction linkage unit 60, which is a component for on-site construction planning support at the construction site, Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), it is possible to calculate on-site construction plan information including on-site construction temporary plans and on-site construction joint plans for constructing each unit module on-site by using the factory production statement and on-site production statement classified in ).

보다 구체적으로, 현장 시공 연계부(60)는 현장 시공 가설 계획 연계부(61)와, 현장 시공 공정 가설 계획 연계부(63)를 포함한다. 현장 시공 연계부(60)는 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여, 현장 시공 계획 정보를 산출한다. More specifically, the on-site construction linkage unit 60 includes an on-site construction temporary plan linkage unit 61 and an on-site construction process hypothesis plan linkage section 63 . The on-site construction link unit 60 is a temporary facility BIM library and interference element BIM library for a modular building, a field construction process table of a modular building provided by a designer of the modular building, and a unit module grouped by type from the unit module extraction unit 10 By using the detailed statement for factory production and the statement for on-site production classified by the statement classification unit 20, site construction plan information is calculated.

현장 시공 가설 계획 연계부(61)는 각 단위모듈을 현장에서 시공하는데 사용되는 현장 가설 시설물에 대한 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보 내지 간섭 정보 등을산출한다. 모듈러 건축의 경우 전체 제조부터 시공까지의 전체 프로세스를 고려할 때, 공장에서 진행되는 공장 제조 과정은 전체 공정의 약 50 내지 80%의 비중을 차지하고, 현장 시공이 나머지 공정 비중을 차지하는데, 결국 현장에서의 현장 시공 공사 기간을 단축하고 시공 품질을 관리하는 것이 공장에서의 공장 제조 과정의 중요도 못지 않다. 즉, 현장 시공 상태의 관리를 통하여 공사 기간을 단축하여 공정 원가를 최소화할 수 있고, 현장 시공 상태의 관리를 통하여 모듈러 건축의 공자 제조 과정 이후의 품질 손상 방지 및 품질 유지를 통하여 전체 공정의 품질 완성도를 급격하게 증진시킬 수도 있으며, 본 발명은 이와 같은 BIM을 통하여 모듈러 건축물의 현장 시공 계획을 지원하는 시스템 및 방법을 제공함으로써, 소정의 목적 달성 및 이에 따른 효과 수반을 이룰 수 있다. The on-site construction temporary planning linkage unit 61 calculates on-site temporary facility type information and on-site temporary facility location information or interference information for on-site temporary facilities used to construct each unit module in the field. In the case of modular architecture, when considering the entire process from manufacturing to construction, the factory manufacturing process in the factory accounts for about 50 to 80% of the total process, and on-site construction accounts for the rest of the process. Shortening the on-site construction period and managing construction quality are no less important than the factory manufacturing process in the factory. In other words, it is possible to minimize the process cost by shortening the construction period through the management of the on-site construction state, and through the management of the on-site construction state, the quality completeness of the entire process through the prevention of quality damage and quality maintenance after the Confucius manufacturing process of the modular building can be rapidly promoted, and the present invention can achieve a predetermined purpose and accompany the effect thereof by providing a system and method that support the on-site construction plan of a modular building through such BIM.

현장 가설 시설물 종류 정보는 현장에서 모듈러 건축물을 시공하는데 필요한 가설 시설물의 유형 및 개수 등에 대한 구체적인 정보를 포함한다. 예를 들어, 시공 현장에서 사용되는 현장 가설 시설물의 유형 정보로는 가설 펜스, 자재 야적장, 자재 가공소, 크레인, 리프트카 등의 유형 정보 및 이들의 개수 내지 대수에 대한 수량 정보를 포함할 수 있다. The on-site temporary facility type information includes specific information on the type and number of temporary facilities required to construct a modular building in the field. For example, type information of on-site temporary facilities used at the construction site may include type information of temporary fences, material yards, material processing plants, cranes, lift cars, etc., and quantity information about the number or number of them. .

또한, 현장 가설 시설물 위치 정보는 언급된 현장 가설 시설물이 배치되는 위치 등을 나타낸다. 경우에 따라 현장 가설 시설물 중 주요 시설물에 대하여는 IOT 등을 활용하여 실시간 위치 정보가 갱신되는 구성을 취할 수도 있다. 즉, 본 발명의 시스템(1)은 현장 가설 시설물에 배치되는 가설 시설물 통신 단말부(80)를 구비하고, 이의 정보는 현장에 설치되는 통신부(90)를 통하여 시스템(1)에 송신되고 시스템(1)은 시스템 통신부(70)를 통하여 이를 수신하여 현장 가설 시설물에 대한 현장 시설 가설물 위치 정보를 갱신하는 구성을 취하여 현장 시공 지원의 실시간적 지원 구조를 형성할 수도 있다. In addition, the site temporary facility location information indicates a location in which the mentioned on-site temporary facility is disposed. In some cases, a configuration in which real-time location information is updated by using IOT or the like for major facilities among temporary on-site facilities may be taken. That is, the system 1 of the present invention has a temporary facility communication terminal unit 80 disposed in the field temporary facility, and its information is transmitted to the system 1 through the communication unit 90 installed in the field, and the system ( 1) may form a real-time support structure of on-site construction support by receiving it through the system communication unit 70 and updating the on-site temporary facility location information for the on-site temporary facility.

현장 시공 공정 가설 계획 연계부(63)는 위와 같은 정보 들을 이용하여 각 단위모듈을 현장에서 시공하는 공정 순서에 대한 현장 시공 공졍 계획 정보를 산출한다. 이러한 현장 시공 공정 가설 계획 연계부(63)에서 산출된 현장 시공 공정 계획 정보는 단말을 통하여 설계자 측에 디스플레이되어 모니터링할 수도 있고, 실제 시공 현장 측으로 전송되어 시공 현장에 디스플레이되는 구성을 취할 수도 있는 등 다양한 구현이 가능하다. The on-site construction process hypothesis planning link unit 63 calculates on-site construction construction plan information for the process sequence of constructing each unit module on-site by using the above information. The on-site construction process plan information calculated by the on-site construction process hypothesis planning linkage unit 63 may be displayed and monitored on the designer side through the terminal, or may be transmitted to the actual construction site side and displayed on the construction site, etc. Various implementations are possible.

또한, 이러한 현장 시공 연계부(60)는 현장 시공 가설 계획 연계부(61)와, 현장 시공 공정 가설 계획 연계부(63)와 더불어, 현장 시공 계획 GUI부(65)를 더 구비할 수도 있다(도 6 참조). 현장 시공 계획 GUI부(65)는 현장 시공 가설 계획 연계부(61)와, 현장 시공 공정 가설 계획 연계부(63)에서 산출된 정보를 표시하고, 이들을 그래픽 유저 인터페이스 방식으로 선택 취합하여 소정의 현장 시공 정보를 연계시키는 시뮬레이션의 실행을 수행 가능하도록 할 수 있다. In addition, the on-site construction linkage unit 60 may further include a site construction plan GUI unit 65 along with the on-site construction temporary plan linkage unit 61 and the on-site construction process temporary plan linkage unit 63 ( see Fig. 6). The on-site construction planning GUI unit 65 displays the information calculated by the on-site construction temporary plan linking unit 61 and the on-site construction process temporary planning linking unit 63, and selects and aggregates them in a graphical user interface method to obtain a predetermined site It may be possible to perform execution of a simulation linking construction information.

도 7에 도시되는 바와 같이, 산출된 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보 내지 간섭 정보와, 산출된 현장 시공 공정 계획 정보는 단말을 통하여 설계자 측에 디스플레이되어 모니터링할 수도 있고, 실제 시공 현장 측으로 전송되어 시공 현장에 디스플레이되는 구성을 취할 수도 있는 등 다양한 구현이 가능하다. 즉, 디스플레이부(2)에 표시되는 분할 배치 구성이 배치될 수 있는데, 디스플레이 화면은 예시적으로 총 3개의 BIM 및 시공 연계 시뮬레이션 디스플레이 파트(Wa)와, 현장 시공 공정표 디스플레이 파트(Wb)와, 현장 가설 시설물 및 간섭 요소 검색 파트(Wc)로 구성되어, 각각 BIM 및 시공 연계 시뮬레이션 정보를 디스플레이하고, 현장 시공 공정표에 대한 정보를 표시하며, 현장 가설 시설물 및 간섭 요소의 검색을 실행하기 위한 검색창의 영역을 형성 제공할 수 있다. As shown in FIG. 7 , the calculated on-site temporary facility type information, on-site temporary facility location information or interference information, and the calculated on-site construction process plan information may be displayed and monitored on the designer side through the terminal, and the actual construction site Various implementations are possible, such as taking a configuration that is transmitted to the side and displayed on the construction site. That is, the divided arrangement configuration displayed on the display unit 2 may be arranged, and the display screen includes, for example, a total of three BIM and construction-related simulation display parts (Wa), an on-site construction schedule display part (Wb), It is composed of on-site temporary facility and interfering element search part (Wc), each of which displays BIM and construction-linked simulation information, displays information about on-site construction schedule, and is a search window for searching for on-site temporary facilities and interfering elements. A region can be provided.

현장 시공 관리자는 현장 가설 시설물 및 간섭 요소 검색 파트(Wc)에서 요소를 검색하고 선택하여 BIM 및 시공 연계 시뮬레이션 디스플레이 파트(Wa)에 드래그하여 소정의 시뮬레이션 작업을 수행하도록 할 수도 있다. 대형 크레인 등의 양중 장비 등과 같은 현장 가설 시설물은 위치 변경되어야 하는 정보를 일시에 따라 현장 시공 공정표 디스플레이 파트(Wb) 상에서 일정 체크하고 위치 변경을 계획하도록 설정할 수도 있다. 현장 시공 가설 계획 연계부(61) 및현장 시공 공정 가설 계획 연계부(63)에는 대형 크레인 등의 양중 장비의 현장 가설 시설물의 정보 및 BIM 정보를 통하여 작업 반경 및 위험 범위 정보도 함께 구비되어 각 구성의 위치 이동내지 시공 작업시 발생 가능한 간섭 등의 문제점등이 자동으로 체크 표시될 수도 있다. The on-site construction manager may search for and select an element from the on-site temporary facility and interfering element search part (Wc) and drag it to the BIM and construction-related simulation display part (Wa) to perform a predetermined simulation task. On-site temporary facilities, such as lifting equipment such as large cranes, may be set to schedule and plan location changes on the site construction process table display part (Wb) according to the date and time of information that needs to be changed. The on-site construction temporary planning linkage unit 61 and the on-site construction process temporary plan linkage unit 63 are provided with information on the working radius and risk range through the information and BIM information of on-site temporary facilities of lifting equipment such as large cranes. Problems such as possible interference during the location movement or construction work may be automatically checked and displayed.

BIM 및 시공 연계 시뮬레이션 디스플레이 파트(Wa)와, 현장 시공 공정표 디스플레이 파트(Wb)와, 현장 가설 시설물 및 간섭 요소 검색 파트(Wc) 중의 적어도 둘 이상은 연계되어 어느 하나의 데이터 변동시, 다른 하나에도 자동적으로 적용 변경되는 구조를 취할 수 있다. 즉, 현장 시공 공정표 디스플레이 파트(Wb)에서 변동 사항이 발생하는 경우, BIM 및 시공 연계 시뮬레이션 디스플레이 파트(Wa)에도 자동적으로 변경 사항이 적용되는 구성을 취한다.At least two or more of the BIM and construction link simulation display part (Wa), the on-site construction process table display part (Wb), and the on-site temporary facility and interference element search part (Wc) are linked, so that when any one data changes, the other You can take a structure that is automatically applied and changed. That is, when changes occur in the on-site construction process table display part (Wb), the change is automatically applied to the BIM and construction-linked simulation display part (Wa).

도 2 는 본 발명의 모듈러 건축물의 현장 시공 지원 시스템의 모니터링부(40)에서 제공되는 사용자인터페이스 화면의 일례를 나타내고 있다.2 shows an example of a user interface screen provided by the monitoring unit 40 of the on-site construction support system of the modular building of the present invention.

도면을 참조하면, 사용자인터페이스 화면의 좌측 영역(A)에는 상기 BIM 및 내역서 연계부(30)에서 산출된 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보 및 각 공종별 작업시간정보, 투입인력정보, 장비정보 등의 세부공종정보가 표시된다.Referring to the drawings, in the left area (A) of the user interface screen, the quantity and detail information of the unit modules constituting the modular building required in the factory manufacturing procedure and the field manufacturing procedure calculated by the BIM and statement linkage unit 30, and Detailed work type information such as work time information, input manpower information, and equipment information for each work type is displayed.

또한, 상기 사용자인터페이스 화면의 중앙 영역(B)에는 상기 모니터링부(40)가 제공하는 해당 공종의 실시간 작업상황이 표시된다.In addition, in the central area (B) of the user interface screen, the real-time work status of the corresponding work type provided by the monitoring unit 40 is displayed.

상기 사용자인터페이스화면의 우측 영역(C)에는 전체적인 공장제작 현황을 볼 수 있는 선택 메뉴(현재공정명, 현재제작률, 계획대비 제작률, 현재공정계획, 현재공정진행, 현재공정종료, 전체공정계획, 전체공정진행, 전체공정종료, 계획대비 진행률, 위치, 담당자)들이 표시된다.In the right area (C) of the user interface screen, a selection menu (current process name, current production rate, production rate versus plan, current process plan, current process progress, current process end, overall process plan) that can see the overall factory production status , overall process progress, overall process completion, progress compared to plan, location, person in charge) are displayed.

따라서, 관리자는 이와 같은 사용자인터페이스화면을 통하여 모듈러 건축물의 단위 모듈별 공정진행상황을 실시간으로 모니터링할 수 있게 된다.Accordingly, the administrator can monitor the progress of the process for each module of the modular building in real time through the user interface screen.

도 3 은 모듈러 건축물의 공장제작 관리 방법의 플로우챠트이다.3 is a flowchart of a factory manufacturing management method of a modular building.

도면을 참조하면, 본 발명의 모듈러 건축물의 공장제작 관리 방법은, 전술한 모듈러 건축물의 현장 시공 지원 시스템에 의하여 수행되는 것으로서, 모듈러 건축물의 BIM 모델과 모듈러 건축물의 내역서를 상호 연계시켜 모듈러 건출물의 공장제작상황을 실시간 모니터링할 수 있는 관리 방법이며, 앞서 기술된 단계와 더불어 하기와 같은 단계가 포함될 수도 있다. Referring to the drawings, the factory production management method of the modular building of the present invention is performed by the above-described on-site construction support system of the modular building, and the BIM model of the modular building and the statement of the modular building are interconnected to link the factory of the modular building It is a management method that can monitor the production status in real time, and may include the following steps in addition to the steps described above.

1) 단위모듈 추출 단계(S1)1) Unit module extraction step (S1)

상기 단위모듈 추출단계(S1)는, 모듈러 건축물의 BIM 모델을 로드하고(S11), 로드된 BIM 모델을 각 단위 모듈별로 분개하고(S12), 분개된 각 단위 모듈을 타입별로 그룹핑(S13)하는 단계이다.The unit module extraction step (S1), loading the BIM model of the modular building (S11), journaling the loaded BIM model for each unit module (S12), and grouping each journalized unit module by type (S13) is a step

2) 내역서 분류단계(S2)2) Statement classification step (S2)

상기 내역서 분류단계(S2)는, 모듈러 건축물의 설계사로부터 제공된 모듈러 건출물의 내역서를 로드하고(S21), 로드된 내역서를 타입별로 구분하여 공장제작 수순과 현장제작 수순에 필요한 공장제작분 내역서와 현장제작분 내역서로 구분(S22)하는 단계이다.In the statement classification step (S2), the statement of the modular building provided by the designer of the modular building is loaded (S21), and the loaded statement is classified by type, and the statement of factory production and on-site production necessary for the factory production procedure and the on-site production procedure It is a step of classifying into minute statements (S22).

상기 공장제작분 내역서로서 원자재 반입, 원자재 기본 가공, 가동된 원자재를 이용하여 벽체나 지붕과 같은 단위 모듈의 제작에 필요한 투입 자재, 제작시간, 투입인력 인원수, 제작에 필요한 장비 등의 내역 정보를 들 수 있다.As the above factory production statement, it contains information such as raw material import, basic processing of raw materials, input materials necessary for manufacturing unit modules such as walls and roofs using raw materials, production time, number of input personnel, equipment required for production, etc. can

상기 현장제작분 내역서로서, 제작된 단위 모듈의 운반, 단위 모듈 시공을 위한 기초 공사, 단위 모듈 시공에 필요한 투입 자재, 시공 시간, 투입 인력 인원수, 시공에 필요한 장비, 현장 지장물, 현장 특이사항 등의 내역 정보를 들 수 있다. As the statement of on-site production, transport of the manufactured unit module, foundation work for unit module construction, input materials required for unit module construction, construction time, number of input manpower, equipment required for construction, site obstacles, site specific matters, etc. history information can be found.

3) BIM 및 내역서 연계단계(S3)3) BIM and statement linkage step (S3)

상기 BIM 및 내역서 연계단계(S3)는, 상기 단위모듈 추출단계(S1)에서 타입별로 그룹핑된 단위모듈과 상기 내역서 분류단계(S2)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 전달받고(S31), 전달받은 단위모듈 및 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보를 산출하고(S32), 산출된 수량과 내역 정보에 따라서 각 공종별 작업시간정보, 투입인력정보, 장비정보를 포함하는 세부공종정보를 산출(S33)하는 단계이다.In the BIM and statement linking step (S3), the unit module grouped by type in the unit module extraction step (S1) and the factory production statement and field production statement classified in the statement classification step (S2) are delivered ( S31), calculate the quantity and detail information of the received unit module and the unit modules constituting the modular building required in the factory manufacturing procedure and on-site manufacturing procedure (S32), and according to the calculated quantity and detailed information, work time information for each work type , is a step of calculating (S33) detailed work type information including input manpower information and equipment information.

4) 모니터링 단계(S4)4) Monitoring step (S4)

상기 BIM 및 내역서 연계단계(S3)에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고(S41), 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 디스플레이수단에 표시하여 주는(S42) 단계이며, 상술한 도 2 에 도시된 바와 같은 사용자인터페이스 화면이 제공된다.Lists the quantity and detail information and detailed work type information calculated in the BIM and statement link step (S3) (S41), and when the list is selected, displays the real-time work status of the work type on the display means (S42). , a user interface screen as shown in FIG. 2 is provided.

이때, 관리자에 의하여 각 공종별 작업 상황이 실시간으로 모니터링되며, 작업에 있어 중요한 사항을 BIM 모델에서 즉각적으로 텍스트 등을 입력하여 캡쳐할 수 있으며, 이러한 캡쳐된 사항을 해당 작업의 작업자 및 공정별 작업 스테이션에 제공함으로써 공장제작 수순에서의 품질 관리를 지원할 수 있음은 전술한 바와 같다. At this time, the work situation for each work type is monitored in real time by the manager, and important matters can be captured by inputting text in the BIM model immediately in the BIM model. As described above, it is possible to support quality control in the process of factory production by providing

그러므로, 상기와 같이 구성되는 본 발명의 모듈러 건축물의 현장 시공 지원 시스템 및 그 방법에 따라서, 모듈러 건축물의 전체 공정의 대략 70% 를 차지하는 공장제작 수순을 BIM 을 기반으로하여 통합적으로 관리할 수 있게 된다.Therefore, according to the on-site construction support system and method for the modular building of the present invention configured as described above, it is possible to manage the factory manufacturing procedure, which occupies approximately 70% of the entire process of the modular building, integratedly based on BIM. .

한편, 본 발명의 다른 일예의 경우, 현장 시공 연계 단계(S5)가 더 구비될 수도 있다(도 5 참조). 여기서, 앞서 기술된 단계 S1 내지 S4에 대하여는 중복된 설명은 생략하고, 상기 기술로 대체한다. On the other hand, in the case of another example of the present invention, the on-site construction linkage step (S5) may be further provided (refer to FIG. 5). Here, redundant descriptions of steps S1 to S4 described above are omitted and replaced with the above description.

도 5는 모듈러 건축물의 공장제작 관리 방법의 플로우챠트의 변형예이다.5 is a modified example of a flowchart of a method for managing factory production of a modular building.

도면을 참조하면, 본 발명의 모듈러 건축물의 공장제작 관리 방법은, 전술한 모듈러 건축물의 현장 시공 지원 시스템에 의하여 수행되는 것으로서, 모듈러 건축물의 BIM 모델과 모듈러 건축물의 내역서를 상호 연계시켜 모듈러 건출물의 공장제작상황을 실시간 모니터링함과 더불어 현장 시공 계획을 수행하는데 필요한 지원 방법을 제공하는 것으로, 앞서 기술된 단계와 더불어 하기와 같은 단계가 포함될 수도 있다. Referring to the drawings, the factory production management method of the modular building of the present invention is performed by the above-described on-site construction support system of the modular building, and the BIM model of the modular building and the statement of the modular building are interconnected to link the factory of the modular building In addition to monitoring the production status in real time, it provides a support method necessary for performing on-site construction planning, and may include the following steps in addition to the steps described above.

5) 현장 시공 연계 단계(S5)5) On-site construction linkage step (S5)

상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보이 현장 시공 연계부(60)에서 산출되는 단계(S5)이다. Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), the site construction plan information including the on-site construction temporary plan and on-site construction joint plan for constructing each unit module on-site using the factory production statement and on-site statement Step S5.

보다 구체적으로, 현장 시공 연계 단계(S5)는, 상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 정보가 산출된다. More specifically, in the on-site construction link step (S5), the temporary facility BIM library and interference element BIM library for the modular building, the on-site construction process table of the modular building provided by the designer of the modular building, and the unit module extraction unit 10 from Information is calculated using the unit modules grouped by type and the factory-made statement and field-made statement classified by the statement classification unit 20 .

현장 시공 연계 단계(S5)는, 현장 시공 가설 계획 연계 단계(S51)와 현장 시공 공정 가설 계획 연계 단계(S53)를 포함한다. 현장 시공 가설 계획 연계 단계(S51)에서는, 각 단위모듈을 현장에서 시공하는데 사용되는 현장 가설 시설물에 대한 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보가 현장 시공 가설 계획 연계부(61)에서 산출되는 구성을 취한다. 현장 시공 공정 가설 계획 연계 단계(S53)에서는, 각 단위모듈을 현장에서 시공하는 공정 순서에 대한 현장 시공 공졍 계획 정보가 현장 시공 공정 가설 계획 연계부(63)에서 산출된다. The on-site construction linkage step (S5) includes an on-site construction temporary plan linkage step (S51) and an on-site construction process temporary plan linkage step linkage step (S53). In the on-site construction temporary plan link step (S51), on-site temporary facility type information and on-site temporary facility location information for on-site temporary facilities used to construct each unit module in the field are calculated by the on-site construction temporary plan linkage unit 61 take the configuration In the on-site construction process temporary plan link step S53, on-site construction work plan information for the process sequence of constructing each unit module on-site is calculated by the on-site construction process temporary plan linkage unit 63 .

* 도면의 주요 부분에 대한 부호의 설명 *
10; 단위모듈 추출부
20; 내역서 분류부
30; BIM 및 내역서 연계부
40; 모니터링부
50; 데이터베이스
60: 현장 시공 연계부
70: 시스템 통신부
80: 가설 시설물 통신 단말부
90: 현장 통신부
* Explanation of symbols for the main parts of the drawing *
10; unit module extraction unit
20; statement classification department
30; BIM and Statement Linkage Department
40; monitoring department
50; database
60: on-site construction linkage
70: system communication unit
80: temporary facility communication terminal unit
90: field communication department

Claims (11)

모듈러 건축물의 공장제작 수순 및 모듈러 건축물의 현장 시공 수순 및 현장 시공을 관리하는 시스템에 있어서,
상기 모듈러 건축물의 BIM 모델을 로드하고 로드된 BIM 모델을 각 단위 모듈별로 분개하고 분개된 각 단위 모듈을 타입별로 그룹핑하는 단위모듈 추출부(10);
모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 내역서를 로드하고,로드된 내역서를 타입별로 구분하여 공장제작 수순과 현장제작 수순에 필요한 공장제작분 내역서와 현장제작분 내역서로 구분하는 내역서 분류부(20);
상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 전달받아 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보를 산출하고, 산출된 수량과 내역 정보에 따라서 각 공종별 세부공종정보를 산출하는 BIM 및 내역서 연계부(30);
상기 BIM 및 내역서 연계부(30)에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고, 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 디스플레이수단에 표시하여 주는 모니터링부(40);
상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보를 산출하는 현장 시공 연계부(60)를
포함하여 구성되는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
In the system for managing the factory production procedure of modular buildings and on-site construction procedures and on-site construction of modular buildings,
a unit module extraction unit 10 for loading the BIM model of the modular building, journaling the loaded BIM model for each unit module, and grouping each journaled unit module by type;
A statement classification unit (20) that loads the statement of the modular building provided by the designer of the modular building, classifies the loaded statement by type, and divides it into a factory production statement and a field production statement necessary for the factory production procedure and the on-site production procedure;
The unit module grouped by type from the unit module extracting unit 10 and the factory production statement and field production statement classified by the statement classification unit 20 are delivered, and the modular required in the factory production procedure and the field production procedure BIM and statement linkage unit 30 for calculating the quantity and detail information of the unit modules constituting the building, and calculating detailed work type information for each work type according to the calculated quantity and detail information;
a monitoring unit 40 that lists the quantity and detail information and detailed work type information calculated by the BIM and statement link unit 30, and displays the real-time work status of the work type on the display means when the list is selected;
Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), the on-site construction linkage unit (60) that calculates on-site construction plan information including on-site construction temporary plans and on-site construction joint plans for constructing each unit module on-site using the factory production statement and on-site production portion statement (60) to
On-site construction support system of a modular building, characterized in that it comprises.
제 1 항에 있어서,
상기 단위모듈 추출부(10)가 이용하는 BIM 모델은 BIM 을 설계하는 BIM 설계용 컴퓨터 프로그램에 의하여 작성된 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
The method of claim 1,
The BIM model used by the unit module extraction unit 10 is a field construction support system of a modular building, characterized in that it is created by a computer program for BIM design that designs the BIM.
제 1 항에 있어서,
상기 내역서 분류부(20)가 이용하는 내역서 정보는, 모듈러 건축물의 설계사로부터 제공되어 데이터베이스(50)에 저장된 정보인 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
The method of claim 1,
The statement information used by the statement classification unit 20 is information stored in the database 50 provided by the designer of the modular structure.
제 1 항에 있어서,
상기 BIM 및 내역서 연계부(30)가 산출하는 세부공종정보는, 작업시간정보, 투입인력정보, 장비정보를 포함하는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
The method of claim 1,
The detailed work type information calculated by the BIM and statement linkage unit 30 is a field construction support system for a modular building, characterized in that it includes work time information, input manpower information, and equipment information.
제 1 항에 있어서,
상기 모니터링부(40)는,
실시간으로 모니터링되는 공종별 작업상황에 있어서 중요 사항을 캡쳐할 수 있으며, 이를 해당 작업의 작업자 및 공정별 작업 스테이션에 제공하여 품질 관리를 지원하는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
The method of claim 1,
The monitoring unit 40,
On-site construction support system for a modular building, characterized in that it is possible to capture important matters in the real-time monitoring work situation by work type, and provides it to the worker of the corresponding work and the work station for each process to support quality management.
제 1 항에 있어서,
상기 모니터링부(40)는,
사용자인터페이스 화면을 제공하되, 상기 사용자인터페이스 화면의 좌측 영역(A)에 상기 BIM 및 내역서 연계부(30)에서 산출된 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보 및 각 공종별 세부공종정보가 표시되고,
상기 사용자인터페이스 화면의 중앙 영역(B)에 상기 모니터링부(40)가 제공하는 해당 공종의 실시간 작업상황이 표시되고,
상기 사용자인터페이스화면의 우측 영역(C)에 전체적인 공장제작 현황의 선택 메뉴가 표시되는 구성을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
The method of claim 1,
The monitoring unit 40,
Provide a user interface screen, but in the left area (A) of the user interface screen, the quantity of unit modules constituting the modular building required in the factory production procedure and the field production procedure calculated by the BIM and statement linkage unit 30 and Details information and detailed work information for each work type are displayed,
In the central area (B) of the user interface screen, the real-time work situation of the corresponding work type provided by the monitoring unit 40 is displayed,
On-site construction support system of a modular building, characterized in that the selection menu of the overall factory production status is displayed in the right area (C) of the user interface screen.
제 1항에 있어서,
상기 현장 시공 연계부(60)는:
상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여,
각 단위모듈을 현장에서 시공하는데 사용되는 현장 가설 시설물에 대한 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보를 산출하는 현장 시공 가설 계획 연계부(61)와,
각 단위모듈을 현장에서 시공하는 공정 순서에 대한 현장 시공 공졍 계획 정보를 산출하는 현장 시공 공정 가설 계획 연계부(63)를 구비하는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템.
The method of claim 1,
The on-site construction linkage unit 60 includes:
Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), using the statement of factory production and the statement of on-site production,
A site construction temporary plan linking unit 61 for calculating site temporary facility type information and site temporary facility location information for on-site temporary facilities used to construct each unit module in the field;
On-site construction support system for a modular building, characterized in that it comprises a site construction process temporary plan link unit 63 for calculating on-site construction work plan information for the process sequence of constructing each unit module on-site.
모듈러 건축물의 공장제작 수순 및 모듈러 건축물의 현장 시공 수순을 관리하는 시스템에 의하여 수행되는 관리 방법에 있어서,
상기 모듈러 건축물의 BIM 모델을 로드하고(S11), 로드된 BIM 모델을 각 단위 모듈별로 분개하고(S12), 분개된 각 단위 모듈을 타입별로 그룹핑(S13)하는 단위모듈 추출단계(S1);
모듈러 건축물의 설계사로부터 제공된 모듈러 건출물의 내역서를 로드하고(S21), 로드된 내역서를 타입별로 구분하여 공장제작 수순과 현장제작 수순에 필요한 공장제작분 내역서와 현장제작분 내역서로 구분(S22)하는 내역서 분류단계(S2);
상기 단위모듈 추출단계(S1)에서 타입별로 그룹핑된 단위모듈과 상기 내역서 분류단계(S2)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 전달받고(S31), 전달받은 단위모듈 및 공장제작수순과 현장제작수순에서 필요로 되는 모듈러 건축물을 이루는 단위 모듈들의 수량과 내역 정보를 산출하고(S32), 산출된 수량과 내역 정보에 따라서 각 공종별 세부공종정보를 산출(S33)하는 BIM 및 내역서 연계단계(S3);
상기 BIM 및 내역서 연계단계(S3)에서 산출된 수량과 내역 정보 및 세부공종정보를 리스트하고(S41), 해당 리스트가 선택되면 해당 공종의 실시간 작업상황을 디스플레이수단에 표시하여 주는(S42) 모니터링 단계(S4);
상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여 각 단위모듈을 현장에서 시공하는 현장 시공 가설 계획 및 현장 시공 공저 계획을 포함하는 현장 시공 계획 정보이 현장 시공 연계부(60)에서 산출되는 현장 시공 연계 단계(S5)
를 포함하여 구성되는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템 제어 방법.
In the management method performed by the system for managing the factory production procedure of the modular building and the on-site construction procedure of the modular building,
A unit module extraction step (S1) of loading the BIM model of the modular building (S11), journaling the loaded BIM model for each unit module (S12), and grouping each journaled unit module by type (S13);
A statement of loading the statement of the modular building provided by the designer of the modular building (S21), classifying the loaded statement by type, and dividing it into a statement of factory production and a statement of on-site production required for the factory production procedure and on-site production procedure (S22) classification step (S2);
In the unit module extraction step (S1), the unit module grouped by type and the factory production statement and field production statement classified in the statement classification step (S2) are delivered (S31), and the received unit module and factory production sequence BIM and statement linkage step of calculating the quantity and detail information of unit modules constituting the modular building required in the field production procedure (S32), and calculating detailed work type information for each work type according to the calculated quantity and detail information (S33) (S3);
A monitoring step of listing the quantity, detail information, and detailed work type information calculated in the BIM and statement linkage step (S3) (S41), and displaying the real-time work status of the work type on the display means when the list is selected (S42) (S4);
Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), the site construction plan information including the on-site construction temporary plan and on-site construction joint plan for constructing each unit module on-site using the factory production statement and on-site statement On-site construction linkage step (S5)
On-site construction support system control method of a modular building, characterized in that it comprises a.
제 8 항에 있어서, 상기 모니터링 단계(S4)는,
실시간으로 모니터링되는 공종별 작업상황에 있어서 중요 사항을 캡쳐할 수 있으며, 이를 해당 작업의 작업자 및 공정별 작업 스테이션에 제공하여 품질 관리를 지원하는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템 제어 방법.
According to claim 8, wherein the monitoring step (S4),
An on-site construction support system control method for a modular building, characterized in that it is possible to capture important matters in the real-time monitoring work situation for each work type, and provides it to the worker of the corresponding work and the work station for each process to support quality management.
제 9 항에 있어서, 상기 현장 시공 연계 단계(S5)는,
상기 모듈러 건축물에 대한 가설 시설물 BIM 라이브러리 및 간섭요소 BIM 라이브러리, 모듈러 건축물의 설계사로부터 제공된 모듈러 건축물의 현장 시공 공정표 및 상기 단위모듈 추출부(10)로부터 타입별로 그룹핑된 단위모듈과 상기 내역서 분류부(20)에서 분류된 공장제작분 내역서와 현장제작분 내역서를 이용하여,
각 단위모듈을 현장에서 시공하는데 사용되는 현장 가설 시설물에 대한 현장 가설 시설물 종류 정보 및 현장 가설 시설물 위치 정보가 현장 시공 가설 계획 연계부(61)에서 산출되는 현장 시공 가설 계획 연계 단계(S51)와,
각 단위모듈을 현장에서 시공하는 공정 순서에 대한 현장 시공 공졍 계획 정보가 현장 시공 공정 가설 계획 연계부(63)에서 산출되는 것을 특징으로 하는 모듈러 건축물의 현장 시공 지원 시스템 제어 방법.
10. The method of claim 9, wherein the on-site construction link step (S5),
Temporary facility BIM library and interference element BIM library for the modular building, the field construction process table of the modular building provided by the designer of the modular building, and the unit module grouped by type from the unit module extraction unit 10 and the statement classification unit 20 ), using the statement of factory production and the statement of on-site production,
A site construction temporary plan link step (S51) in which on-site temporary facility type information and on-site temporary facility location information for the site temporary facility used to construct each unit module in the field are calculated by the site construction temporary plan link unit 61;
The on-site construction support system control method of a modular building, characterized in that the on-site construction work plan information for the process sequence of constructing each unit module on-site is calculated by the on-site construction process hypothesis planning link unit 63.
제 9 항 또는 제 10 항중 어느 한 항의 모듈러 건축물의 현장 시공 지원 시스템 제어 방법을 수행하는 컴퓨터 프로그램이 수록된 컴퓨터에 의하여 판독가능한 저장매체.
A storage medium readable by a computer in which a computer program for performing the control method of the on-site construction support system of the modular building of any one of claims 9 or 10 is recorded.
KR1020190153757A 2019-11-26 2019-11-26 Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore KR20210064954A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190153757A KR20210064954A (en) 2019-11-26 2019-11-26 Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190153757A KR20210064954A (en) 2019-11-26 2019-11-26 Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore

Publications (1)

Publication Number Publication Date
KR20210064954A true KR20210064954A (en) 2021-06-03

Family

ID=76396769

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190153757A KR20210064954A (en) 2019-11-26 2019-11-26 Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore

Country Status (1)

Country Link
KR (1) KR20210064954A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20240019990A (en) 2022-08-05 2024-02-14 서울대학교산학협력단 System and method for site management of modular construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20240019990A (en) 2022-08-05 2024-02-14 서울대학교산학협력단 System and method for site management of modular construction

Similar Documents

Publication Publication Date Title
KR20200061194A (en) Managing system for factory productiong the modular building and method therefore
US20200250354A1 (en) Building information modeling system with self-configuration
KR20190067329A (en) Intergrated managing system based on the BIM and method therefor
CN109933934B (en) Equipment maintenance management method and system and computer readable storage medium
CN104809591A (en) Electric power construction engineering supervision mechanism based on big data
CN105159239B (en) A kind of SPC strategies automatic update method and SPC Strategy Auto system
KR20210064953A (en) Total Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore
KR101674101B1 (en) Project management system based information and communication technology
KR20210064954A (en) Managing system for factory productiong the modular building and planning the modular building on construction site and and method therefore
Yuan et al. Review of the potential for a cyber-physical system approach to temporary structures monitoring
US20140058963A1 (en) Facility control system (fcs-c2) (introduction of traveler form) to manage assets planning, design, construction, fabrication, operating, maintence and products fabrication
JP4896832B2 (en) Process management system and method
Razavialavi et al. Estimating the size of temporary facilities in construction site layout planning using simulation
Peng et al. Decision support for mobile crane lifting plan with building information modelling (BIM)
KR101014798B1 (en) Method and system of setting lift equipment in high rising building and Program Recording Medium
JP2012256206A (en) Work progress state management system
Hamzah et al. A CMMS expert using BIM for IBS building maintenance
KR102112749B1 (en) Method for managing of the tower crane using construction management plan and computer readable media thereof
Kim et al. Sharing of temporary structures: Formalization and planning application
US8954369B1 (en) Method to build, analyze and manage a safety instrumented model in software of a safety instrumented system architecture for safety instrumented systems in a facility
KR101525003B1 (en) Estimating system for life cycle cost in construction
Cheung et al. Applying virtual reality to improve the construction logistics of high-rise modular integrated construction
Trani et al. BIM oriented equipment choice on construction site
Ji et al. Information representation schema for tower crane planning in building construction projects
Kazado et al. Construction progress visualisation for varied stages of the individual elements with BIM: A case study