KR20180110901A KR1020170040812A KR20170040812A KR20180110901A KR 20180110901 A KR20180110901 A KR 20180110901A KR 1020170040812 A KR1020170040812 A KR 1020170040812A KR 20170040812 A KR20170040812 A KR 20170040812A KR 20180110901 A KR20180110901 A KR 20180110901A
Authority
KR
South Korea
Prior art keywords
plate
coupled
pile
fixing part
main body
Prior art date
Application number
KR1020170040812A
Other languages
Korean (ko)
Other versions
KR101979895B1 (en
Inventor
구정민
Original Assignee
(주)동명기술공단종합건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)동명기술공단종합건축사사무소 filed Critical (주)동명기술공단종합건축사사무소
Priority to KR1020170040812A priority Critical patent/KR101979895B1/en
Publication of KR20180110901A publication Critical patent/KR20180110901A/en
Application granted granted Critical
Publication of KR101979895B1 publication Critical patent/KR101979895B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to a prefabricated soil retaining plate (A) capable of being installed and dismantled on the front surface of an excavation part (2) of the ground (1). According to the present invention, the prefabricated soil retaining plate (A) comprises: first and second fixing parts (200, 300) installed in a section between a pair of neighboring first and second H-piles (110, 120), and press-fit into inner groove parts (111, 121) of the first and second piles (110, 120), respectively; and a main body part (400) installed between the first and second fixing parts (200, 300). The first and second fixing parts (200, 300) are symmetrically formed with respect to the main body part (400). In this case, since the prefabricated soil retaining plate (A) is formed in a structure of coupling the first fixing part (200), the main body part (400), and the second fixing part (300) in one direction or the other direction, the prefabricated soil retaining plate (A) is installed and dismantled on the front surface of the excavation part (20). Accordingly, a construction time is reduced and an entire construction period is also reduced.

Description

조립식 토류판 및 이를 이용한 흙막이 가시설 시공방법{BUILD-ON RETAINING PANNEL AND CONSTRUCTION METHOD THEREOF}BACKGROUND OF THE INVENTION Field of the Invention [0001] The present invention relates to a prefabricated soil board,

본 발명은 건설분야에 관한 것으로서, 상세하게는 조립식 토류판 및 이를 이용한 흙막이 가시설 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction field, and more particularly, to a prefabricated soil board and a method for constructing a temporary earth retaining structure using the same.

일반적인 흙막이 가시설은 목재로 제작된 토류판을 사용한다. Typical earth retaining clay is made of wooden plate made of wood.

목재 토류판은 H-Pile에 상부에서 하부로 끼워넣는 방식으로 설치되고, 상부로 인발되어 해체되는데, 지반깊이가 깊어질수록 설치와 해체가 어렵고, 목재 토류판에 휨 변형이 발생하거나, 파단되는 문제가 발생한다.It is difficult to install and dismantle as the depth of the ground becomes deeper, and the warp deformation of the wooden soil plate is generated or the problem of the breaking occurs. Occurs.

또한, 가시설의 해체시 일부 토류판이 인발되지 않아, 지반에 묻히는 경우가 발생하고, 인발시 목재 토류판이 파손된다.In addition, when the dismantling of the hypothetical case, some soil boards are not pulled out, so that they are buried in the ground, and when they are pulled out, the wood board is broken.

아래 선행기술의 기술구성, 명칭 및 도면번호는 그 선행기술의 설명에 한정되어 사용한다.The technical structure, name and drawing number of the prior arts below are used only in the description of the prior art.

한국특허 제10-2006-0089313호 '폭 조절과 배수기능이 구비된 조립식 토류판'은 굴토된 지하 공간의 측벽에 작용하는 토압에 효과적으로 대처하기 위해 시공되는 토류판의 좌,우 폭 조절 및 배수기능을 크게 향상시키도록 된 조립식토류판을 제공함에 있는 것이다. 이를 위해서 본 발명은, 양쪽에 파일조립부(21)와 블록조립부(22)가 형성되어 서로 마주하는 H파일(10)의 대향면에 조립되는 한 쌍의 고무블록(20), 상기 고무블록(20)의 한쪽면에 체결구(33)로 조립되는 한 쌍의 지지블록(30), 인장스프링(41)의 양쪽에 고정판(42,43)이 용접되어 한쪽 고정판(42)이 상기 지지블록(30)의 가이드홈(34)에 조립되는 한 쌍의 탄성부재(40), 한쪽면에는 토목섬유조립부(51)로 물을 유입시키도록 무수히 많은 구멍(52)이 천공되어 토류판조립부(32)에 삽입되는 토류판(50), 상기 토류판조립부(32)에 조립되는 토목섬유(60), 지지블록(30)의 최상부측에 체결구(73)로 조립 체결되는 상면덮개(70), 외주면에 무수히 많은 구멍(81)이 천공되어 상기 토목섬유(60)의 조립공(61)으로 끼워지는 배수파이프(80)에 연결구(91)를 매개로 조립되는 배수펌프(90)로 구성되는 것을 특징으로 한다.Korean Patent No. 10-2006-0089313 'The prefabricated plate with width control and drainage function' is designed to effectively control the earth pressure acting on the sidewalls of the excavated underground space by adjusting the left and right width of the plate, So as to greatly improve the performance of the prefabricated soil board. To this end, the present invention comprises a pair of rubber blocks 20, each having a file assembly 21 and a block assembly 22 on both sides thereof and being assembled on opposite sides of H files 10 facing each other, A pair of support blocks 30 assembled with a fastening hole 33 on one side of the support block 20 and fixing plates 42 and 43 are welded to both sides of the tension spring 41, A large number of holes 52 are formed in one side of the ground weave assembly section 51 to allow water to flow into the geared fiber assembly section 51, A top cover 70 which is assembled with a fastening member 73 on the uppermost side of the support block 30, And a drain pump 90 that is assembled through a connection port 91 to a drain pipe 80 that is inserted into an assembly hole 61 of the geoscientific material 60 by drilling a large number of holes 81 on the outer circumferential surface And that is characterized.

한국실용신안 제20-2007-0021022호 '조립식 토류판'은 토류판을 폐플라스틱과 같은 재활용이 가능한 합성수지를 이용하여 제조하도록 하여 내구성 및 재사용이 용이하도록 하면서도 그 부피가 적고 무게가 가벼워 시공이 보다 용이하도록 하기 위하여 개발된 것으로, 일정 간격으로 입설되는 H빔 형태의 스페이셔와, 상기 인접한 스페이셔의 조림홈에 순차적으로 끼워져 적층되는 토류판에 있어서, 토류판은 일정 높이를 가지고 좌우측방향으로 길게 연장되는 직사각판의 형태를 가진 전면판과, 전면판 높이의 이등분점에 형성되어 좌우방향으로 일정간격 이격되어 다수 형성되며 입구부분은 넓고 후방으로 갈수록 좁아지면서 전면판의 후방으로 돌출 연장되어 그 끝단에는 그 내경이 축소되어 단턱진 관통홀이 형성되는 장착리브와, 장착리브에서 전면판과 수직이 되도록 일체로 연장되는 적어도 2개 이상의 보강리브와, 전면판의 상단에서 후방으로 전면판의 두께만큼 절곡되었다가 다시 상부로 소폭 돌출되도록 절곡되어 형성되는 걸림턱과, 전면판의 하단에는 인접한 하부에 위치한 토류판의 걸림턱에 상응하여 밀착되는 삽입절곡부로 구성되는 제1 조립판과 제1 조립판과 동일한 전면판, 관통홀, 장착리브, 보강리브, 걸림턱 및 삽입절곡부로 구성되어 대칭구조를 가지고 제1 조립판과 조립되는 제2 조립판과 제1 조립판과 제2 조립판의 관통홀에 삽입되어 조여줌으로 조립하는 다수의 볼트 및 너트로 구성됨을 특징으로 한다.The Korean Utility Model No. 20-2007-0021022 '' Prefabricated soil plate '' makes it possible to manufacture the soil plate by using recyclable synthetic resin such as waste plastics, thereby making it easy to durability and reuse, but its volume is small and its weight is light, The H-beam type spacer is installed at regular intervals and is sandwiched and stacked sequentially in the grooved grooves of the adjacent spacer. The soil plate is a rectangular plate having a predetermined height and extending in the left- The front plate is formed at a bisector of the height of the front plate and is formed in a large number spaced apart from the left and right by a predetermined distance. The inlet portion is wide and narrowed toward the rear and extended to the rear of the front plate. A mounting rib on which a stepped through hole is formed by being reduced, And at least two reinforcing ribs integrally extending to be perpendicular to each other, a latching jaw bent by a thickness of the front plate from the upper end of the front plate to a width slightly protruding from the upper plate, A through hole, a mounting rib, a reinforcing rib, a latching jaw, and an insertion bending portion, which are the same as the first and second assembling plates, And a plurality of bolts and nuts which are inserted into the through holes of the first and second assembling plates and assembled by tightening the bolts and the nuts.

한국특허 제10-2007-0084782호 '조립식 강재 토류판'은 강판의 양단이 H형강의 플랜지 사이에 삽입되도록 'ㄱ'자로 절곡시킨 체결부를 형성하며, 체결부에는 볼트체결을 위해 소정의 체결공이 형성되고, 강판의 상부 및 하부에 보강용 'L'자형 앵글이 결합되어 있는 강재 토류판에 있어서, 강재 토류판의 하부에 설치된 앵글에는 하나 또는 하나 이상의 수평장홀이 형성되고, 강재 토류판의 상부에 설치된 앵글에는 수평장홀과 동일선상에 위치하도록 돌출편이 형성되며, 다수개의 강재 토류판 적층 시 하부에 위치한 강재 토류판의 돌출편이 다른 강재 토류판의 수평장홀에 일체로 삽입되면서 다단으로 적층됨을 특징으로 한다.In Korean Patent No. 10-2007-0084782, a 'prefabricated steel plate plate' is formed with a fastening portion formed by bending both ends of a steel sheet to be inserted between flanges of an H-shaped steel, and a fastening hole is formed in the fastening portion And a reinforcing 'L' -shaped angle is coupled to the upper and lower portions of the steel plate. In the steel material plate, one or more horizontal elongated holes are formed in the lower portion of the steel material plate, and the angle formed at the upper portion of the steel material plate is The protruding pieces are formed so as to be positioned on the same line as the horizontal elongated holes and the projecting pieces of the steel material guide plate located at the lower part when stacking a plurality of steel guide plates are integrally inserted into the horizontal elongated holes of the other steel guide plates.

한국특허 제10-2006-0089313호Korean Patent No. 10-2006-0089313 한국특허 제10-2007-0084782호Korean Patent No. 10-2007-0084782

한국실용신안 제20-2007-0021022호Korean Utility Model No. 20-2007-0021022

본 발명은 상기와 같은 문제점을 해결하기 위해 도출된 것으로서, 토류판의 설치와 해체가 용이하고, 토압에 의한 변형이 적고, 설치와 해체시 파손되지 않는 조립식 토류판 및 이를 이용한 흙막이 가시설 시공방법을 제시하는 것을 목적으로 한다. Disclosure of Invention Technical Problem [8] Accordingly, the present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to provide a prefabricated soil board which is easy to install and disassemble soil plate, less deformed by earth pressure, .

상기 과제의 해결을 위하여 본 발명의 지반(1) 굴착부(2)의 전면에서 설치 및 해체할 수 있는 본원발명의 조립식 토류판(A)은 이웃하는 한 쌍의 H형 제1말뚝(110), 제2말뚝(120) 사이 구간에 설치되되, 상기 제1말뚝(110)의 내측 홈부(111)와 상기 제2말뚝(120)의 내측 홈부(121)에 각각 끼움 결합되는 제1고정부(200) 및 제2고정부(300); 상기 제1고정부(200) 및 상기 제2고정부(300) 사이 구간에 설치되는 본체부(400);를 포함하되, 상기 제1고정부(200)와 상기 제2고정부(300)는 상기 본체부(400)를 기준으로 대칭 구조로 형성된다.To solve the above-mentioned problems, the foundation type (A) of the present invention, which can be installed and disassembled from the front surface of the excavation portion (2) of the present invention, comprises a pair of adjacent H- And a first fixing part 200 which is installed in a section between the second piles 120 and is fitted into the inner groove part 111 of the first pile 110 and the inner groove part 121 of the second pile 120, And a second fixing part 300; And a body part 400 installed between the first fixing part 200 and the second fixing part 300. The first fixing part 200 and the second fixing part 300 And is formed symmetrically with respect to the main body 400.

상기 제1고정부(200)는 상기 홈부(111)에 끼움 결합되는 끼움부(210); 상기 끼움부(210)의 타측 단부에 결합되되, 상기 본체부(400)의 일측 단부와 결합되는 결합부(220);를 포함하는 것이 바람직하다.The first fixing part (200) includes a fitting part (210) fitted to the groove part (111). And an engaging part 220 coupled to the other end of the fitting part 210 and coupled to one end of the body part 400.

상기 제1말뚝(110)에 형성된 상기 홈부(111)는 전방플랜지의 후면(111a); 후방플랜지의 전면(111b); 및 복부의 내측면(111c);으로 형성되고, 상기 끼움부(210)는 상기 내측면(111c)에 일측면이 접촉되도록 설치되는 끼움플레이트(211); 상기 끼움플레이트(211)의 타측면 가장자리부에 결합되되, 상기 후면(111a)에 전면이 접촉하도록 형성된 제1연결플레이트(212); 상기 끼움플레이트(211)의 타측면 중앙 영역에 결합되되, 상기 제1연결플레이트(212)의 후방으로 이격되도록 형성된 제2연결플레이트(213);를 포함하는 것이 바람직하다.The groove 111 formed in the first pile 110 includes a rear surface 111a of the front flange 110a; A front surface 111b of the rear flange; And an inner side surface 111c of the abdomen; the fitting portion 210 has a fitting plate 211 installed to be in contact with the inner surface 111c at one side thereof; A first connection plate 212 coupled to the other side edge of the fitting plate 211 and having a front surface contacting the rear surface 111a; And a second connection plate 213 coupled to a center region of the other side of the fitting plate 211 and spaced apart from the rear of the first connection plate 212.

상기 결합부(220)는 전면이 개방된 중공형 박스구조로서, 상기 제1연결플레이트(212)와 상기 제2연결플레이트(213)의 타측 단부에 결합되되, 상기 전방플랜지의 전면(111b)과 전면이 나란하도록 상기 제1연결플레이트(212)와 상기 제2연결플레이트(213) 각각의 타측 단부에 결합된 일측플레이트(221); 상기 일측플레이트(221)의 상측 단부에 결합되되, 타측 방향으로 연장 형성된 상부플레이트(222); 상기 상부플레이트(222)의 타측 단부에 하측 방향으로 연장 형성된 타측플레이트(223); 상기 일측플레이트(221)와 상기 타측플레이트(223)의 하부에 일측 및 타측 단부가 각각 결합된 하부플레이트(224); 상기 일측플레이트(221), 상기 상부플레이트(222), 상기 타측플레이트(223), 상기 하부플레이트(224)의 후방 단부에 결합된 후면플레이트(225);를 포함하는 것이 바람직하다.The coupling part 220 is a hollow box structure having a front face and is coupled to the other end of the first connection plate 212 and the second connection plate 213. The front face 111b of the front flange, A side plate 221 coupled to the other end of each of the first connection plate 212 and the second connection plate 213 such that the front surface thereof is parallel to the first connection plate 212; An upper plate 222 coupled to an upper end of the one plate 221 and extending in the other direction; A second plate 223 extending downward from the other end of the upper plate 222; A lower plate 224 having one side and the other end connected to the lower side of the one side plate 221 and the other side plate 223; And a rear plate 225 coupled to a rear end of the one side plate 221, the upper plate 222, the other side plate 223, and the lower plate 224.

상기 본체부(400)는 전면이 개방된 중공형 박스구조로서, 상기 타측플레이트(223)의 타측면에 일측면이 접촉되는 구조로 결합되는 일측본체플레이트(410); 상기 일측본체플레이트(410)의 상측 단부에 결합되되, 타측 방향으로 연장 형성된 상부본체플레이트(420); 상기 상부본체플레이트(420)의 타측 단부에 하측 방향으로 연장 형성된 타측본체플레이트(430); 상기 일측본체플레이트(410)와 상기 타측본체플레이트(430) 하부에 일측 및 타측 단부가 각각 결합된 하부본체플레이트(440); 상기 일측본체플레이트(410), 상기 상부본체플레이트(420), 상기 타측본체플레이트(430), 상기 하부본체플레이트(440)의 후방 단부에 결합된 본체후면플레이트(450);을 포함하는 것이 바람직하다.The body portion 400 has a hollow box structure with a front surface opened, and has a side plate 410 coupled to one side surface of the other side surface of the other side plate 223 so as to be in contact with one side surface thereof. An upper body plate 420 coupled to an upper end of the one body plate 410 and extending in the other direction; A second body plate 430 extending downward from the other end of the upper body plate 420; A lower body plate 440 having one end and the other end coupled to the lower portion of the one body plate 410 and the other body plate 430; And a main body rear plate 450 coupled to the rear ends of the one body plate 410, the upper body plate 420, the other body plate 430, and the lower body plate 440 .

상기 본체부(400)는 측방을 따라 또 다른 복수의 상기 본체부(400)가 결합되는 것이 바람직하다.It is preferable that a plurality of the main body parts 400 are coupled along the side of the main body part 400.

상기 제1고정부(200)와 상기 본체부(400)는 상기 제1고정부(200)의 상기 타측플레이트(223) 타측면과 상기 본체부(400)의 상기 일측본체플레이트(410) 일측면이 접촉되고, 볼트에 의해 결합되는 것이 바람직하다.The first fixing part 200 and the main body part 400 are connected to the other side surface of the second side plate 223 of the first fixing part 200 and the other side surface of the one side body plate 410 of the main body part 400 And is preferably joined by bolts.

상기 조립식 토류판(A)은 상기 굴착부(2)의 깊이에 따라 복수의 조립식 토류판(A)이 적층되는 구조로 설치되고, 이웃하여 적층된 한 쌍의 상기 토류판(A)은 상부에 설치된 상기 토류판(A)의 상기 하부플레이트(224)와 상기 하부본체플레이트(440)가 하부에 설치된 또 다른 상기 토류판(A)의 상부플레이트(222) 및 상부본체플레이트(420)와 접촉되고, 볼트에 의해 결합되는 것이 바람직하다.The prefabricated soil board (A) has a structure in which a plurality of prefabricated soil boards (A) are stacked according to the depth of the excavated part (2), and a pair of the soil boards (A) The upper plate 222 and the upper body plate 420 of the current plate A where the lower plate 224 and the lower body plate 440 of the lower plate body A are installed at the lower part are brought into contact with each other, .

상기 조립식 토류판(A)은 강재, 목재, 강화플라스틱 중 어느 하나의 재질인 것이 바람직하다.The prefabricated soil board (A) is preferably made of any one of steel, wood, and reinforced plastic.

본 발명의 일 실시 예에 따른 조립식 토류판(A)을 이용한 흙막이 가시설 시공방법으로서, 상기 지반(1)에 상기 제1말뚝(110), 제2말뚝(120)을 삽입설치하는 말뚝설치단계; 상기 지반(1)을 굴착하여 상기 굴착부(2)를 형성하는 지반굴착단계; 상기 굴착부(2)에 상기 조립식 토류판(A)을 설치하되, 상기 제1말뚝(110), 제2말뚝(120)에 상기 제1고정부(200)와 상기 제2고정부(300)를 각각 측방으로 끼움 설치하는 고정부설치단계; 상기 제1고정부(200)와 상기 제2고정부(300)의 사이에 상기 본체부(400)를 전면에서 끼움 설치하는 본체부설치단계;를 포함한다.A method of constructing a temporary earth retaining structure using a prefabricated soil board (A) according to an embodiment of the present invention is characterized by comprising: a pile installing step of inserting the first pile 110 and the second pile 120 into the ground 1; A ground excavation step of excavating the ground 1 to form the excavation part 2; The assembled type soil board A is installed in the excavation part 2 and the first and second fixing parts 200 and 300 are fixed to the first pile 110 and the second pile 120, A step of installing a fixing part to be fitted to each side; And a main body part mounting step of inserting the main body part 400 between the first fixing part 200 and the second fixing part 300.

본 발명의 조립식 토류판은 지반(1) 굴착부(2)의 전면에서 설치 및 해체가 가능하고, 설치 및 조립시간을 단축하여 전체 공사기간을 단축할 수 있다.The prefabricated soil board of the present invention can be installed and disassembled from the front surface of the ground (1) excavation part (2), shortening the installation and assembly time and shortening the entire construction period.

또한, 설치 후 토압에 대한 변형이 적고, 설치와 해체시 토류판의 파손을 방지할 수 있다.Further, the deformation against the earth pressure after the installation is small, and it is possible to prevent breakage of the soil plate at the time of installation and disassembly.

도 1은 한국특허 제10-2006-0089313호의 토류판 분해 사시도.
도 2는 한국실용신안 제20-2007-0021022호의 토류판 결합 사시도.
도 3은 한국특허 제10-2007-0084782호의 토류판 결합 사시도.
도 4는 본 발명의 일 실시 예에 따른 조립식 토류판 평면도.
도 5는 본 발명의 일 실시 예에 따른 조립식 토류판 분해도.
도 6은 본 발명의 일 실시 예에 따른 조립식 토류판 결합도.
도 7은 본 발명의 일 실시 예에 따른 제1말뚝 단면도.
도 8은 본 발명의 일 실시 예에 따른 제1고정부 단면도.
도 9는 본 발명의 일 실시 예에 따른 제1말뚝에 결합된 제1고정부 결합도.
도 10은 본 발명의 일 실시 예에 따른 결합부 단면도.
도 11은 본 발명의 일 실시 예에 따른 제1고정부 사시도.
도 12는 본 발명의 일 실시 예에 따른 본체부 단면도.
도 13은 본 발명의 일 실시 예에 따른 본체부 사시도.
도 14는 본 발명의 일 실시 예에 따른 지반굴착 이전의 지반도.
도 15는 본 발명의 일 실시 예에 따른 말뚝설치단계 공정도.
도 16은 본 발명의 일 실시 예에 따른 지반굴착단계 공정도.
도 17은 본 발명의 일 실시 예에 따른 고정부설치단계 공정도.
도 18은 본 발명의 일 실시 예에 따른 본체부설치단계 공정도.
도 19는 본 발명의 일 실시 예에 따른 본체부설치단계가 설치된 굴착부 사시도.
도 20은 본 발명의 일 실시 예에 따른 띠장이 설치된 흙막이 가시설 단면도
도 21은 본 발명의 일 실시 예에 따른 두께조절플레이트가 결합되는 조립식 토류판 분해도.
1 is an exploded perspective view of a turntable of Korean Patent No. 10-2006-0089313.
FIG. 2 is a perspective view showing a connection plate of Korean Utility Model No. 20-2007-0021022.
FIG. 3 is a perspective view showing a connection plate of Korean Patent No. 10-2007-0084782.
4 is a plan view of the assembled type soil board according to one embodiment of the present invention.
5 is an exploded perspective view of an artificial turntable according to an embodiment of the present invention.
FIG. 6 is a perspective view of the assembly type soil board according to the embodiment of the present invention. FIG.
FIG. 7 is a first pile sectional view according to an embodiment of the present invention; FIG.
8 is a cross-sectional view of a first fixing part according to an embodiment of the present invention;
FIG. 9 is a first hinged coupling coupled to a first pile according to an embodiment of the present invention. FIG.
10 is a cross-sectional view of a coupling according to an embodiment of the present invention.
11 is a perspective view of a first fixing part according to an embodiment of the present invention;
12 is a cross-sectional view of the main body according to an embodiment of the present invention.
13 is a perspective view of a main body according to an embodiment of the present invention;
14 is a view of the ground before excavation according to an embodiment of the present invention.
15 is a process diagram of a pile installation process according to an embodiment of the present invention.
16 is a process diagram of a ground excavation step according to an embodiment of the present invention.
FIG. 17 is a process chart of a step of installing a fixing unit according to an embodiment of the present invention; FIG.
FIG. 18 is a process chart of a main body installation step according to an embodiment of the present invention; FIG.
FIG. 19 is a perspective view of an excavation unit having a body part installation step according to an embodiment of the present invention; FIG.
FIG. 20 is a cross-sectional view of a temporary retaining structure in which a belt is installed according to an embodiment of the present invention.
FIG. 21 is an exploded perspective view of an artificial soil plate to which a thickness adjusting plate according to an embodiment of the present invention is coupled. FIG.

본 발명에 따른 조립식 토류판 및 이를 이용한 흙막이 가시설 시공방법의 일 실시 예를 첨부도면을 참조하여 상세히 설명하기로 하며, 첨부 도면을 참조하여 설명함에 있어, 동일하거나 대응하는 구성 요소는 동일한 도면 번호를 부여하고 이에 대해 중복되는 설명은 생략하기로 한다.The present invention will now be described more fully hereinafter with reference to the accompanying drawings, in which exemplary embodiments of the present invention are shown. And redundant explanations thereof will be omitted.

또한, 이하 사용되는 제1, 제2 등과 같은 용어는 동일 또는 상응하는 구성 요소들을 구별하기 위한 식별 기호에 불과하며, 동일 또는 상응하는 구성 요소들이 제1, 제2 등의 용어에 의하여 한정되는 것은 아니다.It is also to be understood that the terms first, second, etc. used hereinafter are merely reference numerals for distinguishing between identical or corresponding components, and the same or corresponding components are defined by terms such as first, second, no.

또한, 결합이라 함은, 각 구성 요소 간의 접촉 관계에 있어, 각 구성 요소 간에 물리적으로 직접 접촉되는 경우만을 뜻하는 것이 아니라, 다른 구성이 각 구성 요소 사이에 개재되어, 그 다른 구성에 구성 요소가 각각 접촉되어 있는 경우까지 포괄하는 개념으로 사용하도록 한다.In addition, the term " coupled " is used not only in the case of direct physical contact between the respective constituent elements in the contact relation between the constituent elements, but also means that other constituent elements are interposed between the constituent elements, Use them as a concept to cover each contact.

이하, 첨부도면을 참조하여 본 발명의 일 실시 예에 따른 조립식 토류판 및 이를 이용한 흙막이 가시설 시공방법에 관하여 상세히 설명한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a granular soil board according to an embodiment of the present invention and a method of constructing an earth retaining structure using the same will be described in detail with reference to the accompanying drawings.

상기 과제의 해결을 위하여 지반(1) 굴착부(2)의 전면에서 설치 및 해체할 수 있는 본원발명의 조립식 토류판(A)은 이웃하는 한 쌍의 H형 제1말뚝(110), 제2말뚝(120) 사이 구간에 설치되되, 제1말뚝(110)의 내측 홈부(111)와 제2말뚝(120)의 내측 홈부(121)에 각각 끼움 결합되는 제1고정부(200) 및 제2고정부(300); 제1고정부(200) 및 제2고정부(300) 사이 구간에 설치되는 본체부(400);를 포함하되, 제1고정부(200)와 제2고정부(300)는 본체부(400)를 기준으로 대칭 구조로 형성된다.To solve the above problem, the prefabricated soil board (A) of the present invention, which can be installed and dismantled from the front surface of the ground (1) excavation part (2), comprises a pair of adjacent H- A first fixing part 200 and a second fixing part 200 which are installed between the inner groove 111 of the first pile 110 and the inner groove 121 of the second pile 120, (300); The first fixing part 200 and the second fixing part 300 are installed in the main body part 400 between the first fixing part 200 and the second fixing part 300, ) As a reference.

이 경우, 조립식 토류판(A)은 일측 또는 타측 방향으로 제1고정부(200), 본체부(400) 및 제2고정부(300)가 결합되는 구조로 형성되기 때문에 굴착부(2)의 전면에서 조립식 토류판(A)을 설치하고, 해체시킬 수 있다.In this case, since the prefabricated soil board A is formed in a structure in which the first fixing part 200, the main body part 400, and the second fixing part 300 are coupled to one side or the other, The assembled soil plate A can be installed and disassembled.

따라서 시공시간을 단축함은 물론 전체 공사기간을 단축할 수 있다.Thus, the construction time can be shortened and the entire construction period can be shortened.

제1고정부(200)는 홈부(111)에 끼움 결합되는 끼움부(210); 끼움부(210)의 타측 단부에 결합되되, 본체부(400)의 일측 단부와 결합되는 결합부(220);를 포함하는 것이 바람직하다.The first fixing part 200 includes a fitting part 210 to be fitted into the groove part 111; And an engaging part 220 coupled to the other end of the fitting part 210 and coupled to one end of the body part 400.

도 8과 도 9와 같이 본원발명의 제1고정부는 홈부(111)와의 결합을 용이하게 하기 위해 일측에 끼움부(210)가 형성되고, 타측에는 본체부(400)의 결합을 용이하게 하기위한 결합부(220)가 형성된다.8 and 9, the first fixing part of the present invention has a fitting part 210 formed on one side for facilitating the connection with the groove part 111 and a second fitting part 210 for facilitating the coupling of the body part 400 to the other side. The engaging portion 220 is formed.

제1말뚝(110)에 형성된 홈부(111)는 전방플랜지의 후면(111a); 후방플랜지의 전면(111b); 및 복부의 내측면(111c);으로 형성되고, 끼움부(210)는 내측면(111c)에 일측면이 접촉되도록 설치되는 끼움플레이트(211); 끼움플레이트(211)의 타측면 가장자리부에 결합되되, 후면(111a)에 전면이 접촉하도록 형성된 제1연결플레이트(212); 끼움플레이트(211)의 타측면 중앙 영역에 결합되되, 제1연결플레이트(212)의 후방으로 이격되도록 형성된 제2연결플레이트(213);를 포함하는 것이 바람직하다.The groove 111 formed in the first pile 110 includes a rear surface 111a of the front flange; A front surface 111b of the rear flange; And an inner side surface 111c of the abdomen; the fitting portion 210 includes a fitting plate 211 installed to be in contact with one side surface of the inner side surface 111c; A first connection plate 212 coupled to the other side edge portion of the fitting plate 211 and having a front surface contacting the rear surface 111a; And a second connection plate 213 coupled to the other central area of the other side of the fitting plate 211 and spaced apart from the rear of the first connection plate 212.

도 9와 같이, 별도의 결합장치 없이 홈부(111)에 끼움플레이트(211)와 제2연결플레이트(213)가 끼워지는 것만으로 제1말뚝(110)과 제1고정부(200)가 결합되기 때문에 전면에서의 설치와 해체가 용이하다.The first peg 110 and the first peg 200 are coupled with each other only by fitting the fitting plate 211 and the second connecting plate 213 into the groove 111 without a separate coupling device, Therefore, it is easy to install and dismantle from the front.

결합부(220)는 전면이 개방된 중공형 박스구조로서, 제1연결레이트(212) 와 제2연결플레이트(213)의 타측 단부에 결합되되, 전방플랜지의 전면(111b)과 전면이 나란하도록 제1연결플레이트(212)와 제2연결플레이트(213) 각각의 타측 단부에 결합된 일측플레이트(221); 일측플레이트(221)의 상측 단부에 결합되되, 타측 방향으로 연장 형성된 상부플레이트(222); 상부플레이트(222)의 타측 단부에 하측 방향으로 연장 형성된 타측플레이트(223); 일측플레이트(221)와 타측플레이트(223)의 하부에 일측 및 타측 단부가 각각 결합된 하부플레이트(224); 일측플레이트(221), 상부플레이트(222), 타측플레이트(223), 하부플레이트(224)의 후방 단부에 결합된 후면플레이트(225);를 포함하는 것이 바람직하다.The coupling portion 220 is a hollow box structure having a front face opened and connected to the first connection rate 212 and the other end of the second connection plate 213 so that the front face 111b and the front face of the front flange are aligned A side plate 221 coupled to the other end of each of the first connection plate 212 and the second connection plate 213; An upper plate 222 coupled to an upper end of the one plate 221 and extending in the other direction; An other plate 223 extending downward at the other end of the upper plate 222; A lower plate 224 having one end and the other end coupled to the lower portion of the one plate 221 and the other plate 223; And a rear plate 225 coupled to a rear end of the one plate 221, the top plate 222, the other plate 223, and the bottom plate 224.

도 9 및 도 10과 같이 결합부(220)는 제1말뚝(110)에 끼움부(210)가 설치되면 제1말뚝(110)의 전방플랜지 전면과 결합부(220)의 전면이 평평한 구조가 된다.9 and 10, when the fitting part 210 is installed in the first pile 110, the front flange front surface of the first pile 110 and the front surface of the coupling part 220 are flat do.

상기와 같은 구조는 도 22와 같이, 띠장(200)의 후면에 조립식 토류판(A) 전면이 밀착되도록 하여, 토압을 띠장에 직접적으로 전이할 수 있다.In such a structure, as shown in FIG. 22, the front surface of the assembled type soil board A is brought into close contact with the rear surface of the wristband 200, and the earth pressure can be directly transferred to the wrist band.

본체부(400)는 전면이 개방된 중공형 박스구조로서, 타측플레이트(223)의 타측면에 일측면이 접촉되는 구조로 결합되는 일측본체플레이트(410); 일측본체플레이트(410)의 단부에 결합되되, 타측 방향으로 연장 형성된 상부본체플레이트(420); 상부본체플레이트(420)의 타측 단부에 하측 방향으로 연장 형성된 타측본체플레이트(430); 일측본체플레이트(410)와 타측본체플레이트(430) 하부에 일측 및 타측 단부가 각각 결합된 하부본체플레이트(440); 일측본체플레이트(410), 상부본체플레이트(420), 타측본체플레이트(430), 하부본체플레이트(440)의 후방 단부에 결합된 본체후면플레이트(450);을 포함하는 것이 바람직하다.The body portion 400 has a hollow box structure with a front surface opened, and includes a body plate 410 coupled to one side surface of the other side surface of the other side plate 223. An upper body plate 420 coupled to an end of the one body plate 410 and extending in the other direction; A second side body plate 430 extending downward at the other end of the upper body plate 420; A lower body plate 440 having one end and the other end coupled to a lower portion of the one body plate 410 and the other body plate 430; And a body rear plate 450 coupled to a rear end of the one body plate 410, the upper body plate 420, the other body plate 430, and the lower body plate 440.

도 4와 같이 본체부(400)의 전면은 결합부(200)의 전면과 평평한 구조를 갖는다.As shown in FIG. 4, the front surface of the main body 400 has a flat structure with the front surface of the coupling portion 200.

또한, 도 13과 같이 본체부(400)는 전면이 개방된 주공형 박스구조물이기 때문에 결합부(200)와의 결합을 전면에서 실시하기 용이하다.Also, since the main body 400 is a main body type box structure with its front surface opened as shown in FIG. 13, it is easy to engage with the coupling part 200 from the front side.

본체부(400)와 결합부(200)는 볼트를 이용하여 결합하는데, 본체부(400)와 결합부(200) 사이에는 결합후 조립식 토류판(A)의 길이를 조절할 수 있는 두께조절플레이트(460)가 설치될 수도 있다.The main body part 400 and the engaging part 200 are coupled by using bolts and a thickness adjusting plate 460 which can adjust the length of the assembled type turntable A after the coupling is formed between the body part 400 and the engaging part 200 ) May be installed.

본체부(400)는 측방을 따라 또 다른 복수의 본체부(400)가 결합되는 것이 바람직하다.It is preferable that another plurality of body portions 400 are coupled along the side of the body portion 400.

본체부(400)는 제작 길이에 따라 복수의 본체부가 결합되어 사용될 수 있다.The main body part 400 may be used in combination with a plurality of main body parts depending on the production length.

제1고정부(200)와 본체부(400)는 제1고정부(200)의 타측플레이트(223) 타측면과 본체부(400)의 일측본체플레이트(410) 일측면이 접촉되고, 볼트에 의해 결합되는 것이 바람직하다.The first fixing part 200 and the main body 400 are in contact with the other side surface of the other plate 223 of the first fixing part 200 and one side surface of the body plate 410 on one side of the body part 400, .

조립식 토류판(A)은 굴착부(2)의 깊이에 따라 복수의 조립식 토류판(A)이 적층되는 구조로 설치되고, 이웃하여 적층된 한 쌍의 토류판(A)은 상부에 설치된 토류판(A)의 하부플레이트(224)와 하부본체플레이트(440)가 하부에 설치된 또 다른 토류판(A)의 상부플레이트(222) 및 상부본체플레이트(420)와 접촉되고, 볼트에 의해 결합되는 것이 바람직하다.The prefabricated soil board (A) has a structure in which a plurality of prefabricated soil boards (A) are stacked according to the depth of the excavating part (2), and a pair of soil boards (A) It is preferable that the lower plate 224 and the lower body plate 440 are brought into contact with and joined to the upper plate 222 and the upper body plate 420 of another soil plate A provided at the lower part thereof.

조립식 토류판(A)은 강재, 목재, 강화플라스틱 중 어느 하나의 재질인 것이 바람직하다.The prefabricated soil board (A) is preferably made of any one of steel, wood, and reinforced plastic.

이 경우, 본원발명의 조립식 토류판(A)은 굴착깊이에 따라 복수의 층으로 적층 되는데, 토압 및 작업 중 발생하는 여러가지 외력에 저항할 수 있는 강성이 우수한 재질로 제작된다. In this case, the prefabricated soil board (A) according to the present invention is stacked in a plurality of layers according to the depth of excavation, and is made of a material having superior rigidity to resist earth pressure and various external forces generated during operation.

본 발명의 일 실시 예에 따른 조립식 토류판(A)을 이용한 흙막이 가시설 시공방법으로서, 지반(1)에 제1말뚝(110), 제2말뚝(120)을 삽입설치하는 말뚝설치단계; 지반(1)을 굴착하여 굴착부(2)를 형성하는 지반굴착단계; 굴착부(2)에 조립식 토류판(A)을 설치하되, 제1말뚝(110), 제2말뚝(120)에 제1고정부(200)와 제2고정부(300)를 각각 측방으로 끼움 설치하는 고정부설치단계; 제1고정부(200)와 제2고정부(300)의 사이에 본체부(400)를 전면에서 끼움 설치하는 본체부설치단계;를 포함한다.A pile installation step of inserting a first pile 110 and a second pile 120 into the ground 1; A ground excavating step of excavating the ground 1 to form a digging unit 2; The assembled soil board A is installed on the excavation part 2 and the first and second fixing parts 200 and 300 are fitted to the first pile 110 and the second pile 120, A step of installing the fixed part; And a main body mounting step of inserting the main body part 400 between the first fixing part 200 and the second fixing part 300 at the front side.

도 17 내지 도 19와 같이 본원발명의 조립식 토류판(A)은 제1말뚝(110), 제2말뚝(120)에 끼움 결합되는 제1고정부(200)와 제2고정부(300) 그리고 제1고정부(200)와 제2고정부(300)의 사이에 결합되는 본체부(400)가 모두 굴착부(2)의 전면에서 결합설치되는 구조이기 때문에 설치와 해체가 용이하고, 작업속도를 향상시킬 수 있다.17 to 19, the assembled soil board A of the present invention comprises a first pile 110, a first fixing part 200 and a second fixing part 300 fitted to the second pile 120, Since the structure in which the body portion 400 coupled between the first fixing portion 200 and the second fixing portion 300 are all combined at the front surface of the excavating portion 2 is easy to install and disassemble, Can be improved.

A : 조립식 토류판 1 : 지반
2 : 굴착부 110 : 제1말뚝
111 : 홈부 111a : 후면
111b: 전면 111c : 내측면
120 : 제2말뚝 121 : 홈부
200 : 제1고정부 210 : 끼움부
211 : 끼움플레이트 212 : 제1연결플레이트
213 : 제2연결플레이트 220 : 결합부
221 : 일측플레이트 222 : 상부플레이트
223 : 타측플레이트 224 : 하부플레이트
225 : 후면플레이트 300 : 제2고정부
400 : 본체부 410 : 일측본체플레이트
420 : 상부본체플레이트 430 : 타측본체플레이트
440 : 하부본체플레이트 450 : 본체후면본체플레이트
460 : 두께조절용 플레이트 500 : 띠장
A: Prefabricated soil board 1: Ground
2: excavation part 110: first pile
111: groove portion 111a: rear surface
111b: front side 111c: inner side
120: second pile 121: groove
200: first fixing part 210:
211: fitting plate 212: first connecting plate
213: second connection plate 220:
221: one side plate 222: upper plate
223: the other plate 224: the lower plate
225: rear plate 300: second fixing portion
400: main body part 410: one side body plate
420: upper body plate 430: other body plate
440: Lower body plate 450: Body rear body plate
460: Plate for thickness adjustment 500: Welt

Claims (10)

지반(1) 굴착부(2)의 전면에서 설치 및 해체할 수 있는 조립식 토류판(A)으로서,
이웃하는 한 쌍의 H형 제1말뚝(110), 제2말뚝(120) 사이 구간에 설치되되, 상기 제1말뚝(110)의 내측 홈부(111)와 상기 제2말뚝(120)의 내측 홈부(121)에 각각 끼움 결합되는 제1고정부(200) 및 제2고정부(300);
상기 제1고정부(200) 및 상기 제2고정부(300) 사이 구간에 설치되는 본체부(400);를 포함하되,
상기 제1고정부(200)와 상기 제2고정부(300)는 상기 본체부(400)를 기준으로 대칭 구조로 형성된 것을 특징으로 하는 조립식 토류판.
(1) A prefabricated soil board (A) which can be installed and dismantled from the front surface of the excavating portion (2)
The first pile 110 and the second pile 120 are disposed between adjacent pair of H type first pile 110 and second pile 120. The inner pile 110 has an inner groove 111, A first fixing part 200 and a second fixing part 300 which are respectively fitted and fitted to the first fixing part 121;
And a body part 400 provided between the first fixing part 200 and the second fixing part 300,
Wherein the first fixing part (200) and the second fixing part (300) are formed symmetrically with respect to the main body part (400).
제1항에 있어서,
상기 제1고정부(200)는
상기 홈부(111)에 끼움 결합되는 끼움부(210);
상기 끼움부(210)의 타측 단부에 결합되되, 상기 본체부(400)의 일측 단부와 결합되는 결합부(220);를 포함하는 것을 특징으로 하는 조립식 토류판.
The method according to claim 1,
The first fixing part (200)
A fitting portion 210 to be fitted into the groove portion 111;
And an engaging part (220) coupled to the other end of the fitting part (210) and coupled with one end of the body part (400).
제2항에 있어서,
상기 제1말뚝(110)에 형성된 상기 홈부(111)는
전방플랜지의 후면(111a); 후방플랜지의 전면(111b); 및 복부의 내측면(111c);으로 형성되고,
상기 끼움부(210)는
상기 내측면(111c)에 일측면이 접촉되도록 설치되는 끼움플레이트(211);
상기 끼움플레이트(211)의 타측면 가장자리부에 결합되되, 상기 후면(111a)에 전면이 접촉하도록 형성된 제1연결플레이트(212);
상기 끼움플레이트(211)의 타측면 중앙 영역에 결합되되, 상기 제1연결플레이트(212)의 후방으로 이격되도록 형성된 제2연결플레이트(213);를 포함하는 것을 특징으로 하는 조립식 토류판.
3. The method of claim 2,
The grooves 111 formed in the first pile 110
A rear face 111a of the front flange; A front surface 111b of the rear flange; And an inner surface 111c of the abdomen,
The fitting portion 210
A fitting plate 211 installed to be in contact with one side surface of the inner side surface 111c;
A first connection plate 212 coupled to the other side edge of the fitting plate 211 and having a front surface contacting the rear surface 111a;
And a second connection plate (213) coupled to a center region of the other side of the fitting plate (211) and spaced apart from the rear of the first connection plate (212).
제3항에 있어서,
상기 결합부(220)는 전면이 개방된 중공형 박스구조로서, 상기 제1연결플레이트(212)와 상기 제2연결플레이트(213)의 타측 단부에 결합되되,
상기 전방플랜지의 전면(111b)과 전면이 나란하도록 상기 제1연결플레이트(212)와 상기 제2연결플레이트(213) 각각의 타측 단부에 결합된 일측플레이트(221);
상기 일측플레이트(221)의 상측 단부에 결합되되, 타측 방향으로 연장 형성된 상부플레이트(222);
상기 상부플레이트(222)의 타측 단부에 하측 방향으로 연장 형성된 타측플레이트(223);
상기 일측플레이트(221)와 상기 타측플레이트(223)의 하부에 일측 및 타측 단부가 각각 결합된 하부플레이트(224);
상기 일측플레이트(221), 상기 상부플레이트(222), 상기 타측플레이트(223), 상기 하부플레이트(224)의 후방 단부에 결합된 후면플레이트(225);를 포함하는 것을 특징으로 하는 조립식 토류판.
The method of claim 3,
The coupling part 220 is a hollow box structure having a front surface and is coupled to the other end of the first connection plate 212 and the second connection plate 213,
A side plate 221 coupled to the other end of each of the first connection plate 212 and the second connection plate 213 such that the front surface 111b of the front flange is flush with the front surface;
An upper plate 222 coupled to an upper end of the one plate 221 and extending in the other direction;
A second plate 223 extending downward from the other end of the upper plate 222;
A lower plate 224 having one side and the other end connected to the lower side of the one side plate 221 and the other side plate 223;
And a rear plate 225 coupled to a rear end of the one side plate 221, the upper plate 222, the other side plate 223, and the lower plate 224.
제4항에 있어서,
상기 본체부(400)는 전면이 개방된 중공형 박스구조로서,
상기 타측플레이트(223)의 타측면에 일측면이 접촉되는 구조로 결합되는 일측본체플레이트(410);
상기 일측본체플레이트(410)의 상측 단부에 결합되되, 타측 방향으로 연장 형성된 상부본체플레이트(420);
상기 상부본체플레이트(420)의 타측 단부에 하측 방향으로 연장 형성된 타측본체플레이트(430);
상기 일측본체플레이트(410)와 상기 타측본체플레이트(430) 하부에 일측 및 타측 단부가 각각 결합된 하부본체플레이트(440);
상기 일측본체플레이트(410), 상기 상부본체플레이트(420), 상기 타측본체플레이트(430), 상기 하부본체플레이트(440)의 후방 단부에 결합된 본체후면플레이트(450);을 포함하는 것을 특징으로 하는 조립식 토류판.
5. The method of claim 4,
The main body 400 has a hollow box structure with its front surface opened,
One side body plate (410) coupled to one side surface of the other side surface of the other side plate (223) so as to be in contact with one side surface;
An upper body plate 420 coupled to an upper end of the one body plate 410 and extending in the other direction;
A second body plate 430 extending downward from the other end of the upper body plate 420;
A lower body plate 440 having one end and the other end coupled to the lower portion of the one body plate 410 and the other body plate 430;
And a main body rear plate 450 coupled to the rear ends of the one side body plate 410, the upper body plate 420, the other side body plate 430, and the lower body plate 440. Prefabricated soil board.
제5항에 있어서,
상기 본체부(400)는 측방을 따라 또 다른 복수의 상기 본체부(400)가 결합되는 것을 특징으로 하는 조립식 토류판.
6. The method of claim 5,
Wherein a plurality of the body portions (400) are coupled along the side of the body portion (400).
제6항에 있어서,
상기 제1고정부(200)와 상기 본체부(400)는
상기 제1고정부(200)의 상기 타측플레이트(223) 타측면과 상기 본체부(400)의 상기 일측본체플레이트(410) 일측면이 접촉되고, 볼트에 의해 결합되는 것을 특징으로 하는 조립식 토류판.
The method according to claim 6,
The first fixing part 200 and the main body part 400
Wherein the other side surface of the other side plate (223) of the first fixing part (200) is in contact with one side surface of the one body plate (410) of the body part (400) and is coupled by bolts.
제7항에 있어서,
상기 조립식 토류판(A)은
상기 굴착부(2)의 깊이에 따라 복수의 조립식 토류판(A)이 적층되는 구조로 설치되고,
이웃하여 적층된 한 쌍의 상기 토류판(A)은
상부에 설치된 상기 토류판(A)의 상기 하부플레이트(224)와 상기 하부본체플레이트(440)가 하부에 설치된 또 다른 상기 토류판(A)의 상부플레이트(222) 및 상부본체플레이트(420)와 접촉되고, 볼트에 의해 결합되는 것을 특징으로 하는 조립식 토류판.
8. The method of claim 7,
The assembled soil board (A)
A plurality of prefabricated soil boards A are stacked according to the depth of the excavating unit 2,
The pair of soil plates (A) stacked adjacent to each other
The upper plate 222 and the upper body plate 420 of the current plate A where the lower plate 224 and the lower body plate 440 of the soil plate A installed at the upper portion are installed are brought into contact with each other , And are coupled by bolts.
제8항에 있어서,
상기 조립식 토류판(A)은
강재, 목재, 강화플라스틱 중 어느 하나의 재질인 것을 특징으로 하는 조립식 토류판.
9. The method of claim 8,
The assembled soil board (A)
Wherein the reinforcing plate is made of a material selected from the group consisting of steel, wood, and reinforced plastic.
제1항 내지 제9항 중 어느 한 항의 조립식 토류판(A)을 이용한 흙막이 가시설 시공방법으로서,
상기 지반(1)에 상기 제1말뚝(110), 제2말뚝(120)을 삽입설치하는 말뚝설치단계;
상기 지반(1)을 굴착하여 상기 굴착부(2)를 형성하는 지반굴착단계;
상기 굴착부(2)에 상기 조립식 토류판(A)을 설치하되,
상기 제1말뚝(110), 제2말뚝(120)에 상기 제1고정부(200)와 상기 제2고정부(300)를 각각 측방으로 끼움 설치하는 고정부설치단계;
상기 제1고정부(200)와 상기 제2고정부(300)의 사이에 상기 본체부(400)를 전면에서 끼움 설치하는 본체부설치단계;를 포함하는 것을 특징으로 하는 흙막이 가시설 시공방법.
A temporary earth retaining method using the granular soil board (A) according to any one of claims 1 to 9,
A pile installing step of inserting the first pile 110 and the second pile 120 into the ground 1;
A ground excavation step of excavating the ground 1 to form the excavation part 2;
(A) is installed on the excavating portion (2)
Installing the first fixing part (200) and the second fixing part (300) to the first pile (110) and the second pile (120) laterally;
And installing a main body part (400) between the first securing part (200) and the second securing part (300) by inserting the main body part (400) on the whole surface of the main securing part (300).
KR1020170040812A 2017-03-30 2017-03-30 Build-on retaining pannel and construction method thereof KR101979895B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170040812A KR101979895B1 (en) 2017-03-30 2017-03-30 Build-on retaining pannel and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170040812A KR101979895B1 (en) 2017-03-30 2017-03-30 Build-on retaining pannel and construction method thereof

Publications (2)

Publication Number Publication Date
KR20180110901A true KR20180110901A (en) 2018-10-11
KR101979895B1 KR101979895B1 (en) 2019-05-17

Family

ID=63865302

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170040812A KR101979895B1 (en) 2017-03-30 2017-03-30 Build-on retaining pannel and construction method thereof

Country Status (1)

Country Link
KR (1) KR101979895B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102514559B1 (en) * 2022-05-12 2023-03-24 최병관 Retaining temporary facility wall with displacement measuring device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0649812A (en) * 1992-07-29 1994-02-22 Sekisui Jushi Co Ltd Soundproof panel
KR200175225Y1 (en) * 1999-10-08 2000-03-15 주식회사의성실업 Bearing wall structure
KR20060089313A (en) 2005-02-03 2006-08-09 장응순 Locking device for the two-wheeled vehicle
KR20070084782A (en) 2006-02-22 2007-08-27 주식회사 하이닉스반도체 Sense amplifier circuit having a folded bit line structre in a semiconductor memory device and driving method there of
KR100882831B1 (en) * 2008-08-22 2009-02-10 문동춘 Reformed sheet plate and the method of installation of the same
KR101482585B1 (en) * 2013-06-22 2015-01-29 (주) 성우미래산업 Post foundation block structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0649812A (en) * 1992-07-29 1994-02-22 Sekisui Jushi Co Ltd Soundproof panel
KR200175225Y1 (en) * 1999-10-08 2000-03-15 주식회사의성실업 Bearing wall structure
KR20060089313A (en) 2005-02-03 2006-08-09 장응순 Locking device for the two-wheeled vehicle
KR20070084782A (en) 2006-02-22 2007-08-27 주식회사 하이닉스반도체 Sense amplifier circuit having a folded bit line structre in a semiconductor memory device and driving method there of
KR100882831B1 (en) * 2008-08-22 2009-02-10 문동춘 Reformed sheet plate and the method of installation of the same
KR101482585B1 (en) * 2013-06-22 2015-01-29 (주) 성우미래산업 Post foundation block structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
한국실용신안 제20-2007-0021022호

Also Published As

Publication number Publication date
KR101979895B1 (en) 2019-05-17

Similar Documents

Publication Publication Date Title
US7798748B2 (en) Double wall structure type mechanically stabilized earth wall system
KR101210721B1 (en) Retaining Wall Using PHC Pile
KR20220012525A (en) Slurry wall, construction method for the same and wire mesh assembly
US20050069389A1 (en) Interlocking and securable retaining wall block and system
KR101979895B1 (en) Build-on retaining pannel and construction method thereof
AU2003210567A1 (en) Interlocking and securable retaining wall block and system
KR20050005877A (en) Temporary wall for construction site and its installation method
KR100736393B1 (en) Panel fabrication structure used clamp
EP2530221A2 (en) Pool liner retaining system
KR100982819B1 (en) A prefabricated drain-road
KR100808483B1 (en) Structure of earthy plate for corner using architecture
KR100514155B1 (en) Mount method of temporary wall for building
KR101852083B1 (en) Arch assembly with outrigger, arch structure using the same, and construction method thereof
KR100671227B1 (en) Linear panel for retaining wall
KR101385090B1 (en) Foundation Structure and the method of wall and cut off wall
KR101102435B1 (en) Making of sheathing panel for earth retaining and this and construction technique
KR200253358Y1 (en) Apparatus for shoring of underground construction
KR200404658Y1 (en) Prefabricated Buttressed Retaining Wall
KR100712135B1 (en) Foundation panel being easy to assemble and install
KR101804342B1 (en) Pc pile structure and pc pile structure using the same
KR20070073313A (en) The tunnel constructin method and the tunnel using corrugated steel plates
CN213267919U (en) Combined steel sheet pile
KR102552442B1 (en) Hybrid waterway system using culvert and U-shaped plume and its construction method
KR102493993B1 (en) Earth wall for retaining safety construction through soil inflow prevention and installation method of the earth wall
KR20190142492A (en) PHC pile to facilitate soil guard and construction method of soil guard structure using the same

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant