KR20170142671A - Method of and system for on-line construction management based on cloud - Google Patents

Method of and system for on-line construction management based on cloud Download PDF

Info

Publication number
KR20170142671A
KR20170142671A KR1020160076523A KR20160076523A KR20170142671A KR 20170142671 A KR20170142671 A KR 20170142671A KR 1020160076523 A KR1020160076523 A KR 1020160076523A KR 20160076523 A KR20160076523 A KR 20160076523A KR 20170142671 A KR20170142671 A KR 20170142671A
Authority
KR
South Korea
Prior art keywords
construction
adjustment
statement
server
construction site
Prior art date
Application number
KR1020160076523A
Other languages
Korean (ko)
Inventor
정찬주
Original Assignee
주식회사 이지큐
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 이지큐 filed Critical 주식회사 이지큐
Priority to KR1020160076523A priority Critical patent/KR20170142671A/en
Publication of KR20170142671A publication Critical patent/KR20170142671A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F15/00Digital computers in general; Data processing equipment in general
    • G06F15/16Combinations of two or more digital computers each having at least an arithmetic unit, a program unit and a register, e.g. for a simultaneous processing of several programs
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services

Abstract

The present invention relates to a method and a system for managing an online construction site, which enable workers, managers, enforcers, and supervising agencies to translucently efficiently manage a construction site regardless of time and place by being developed in an online web format based on a cloud from a current system of an offline method and sharing a lot of construction data information varied every moment in accordance with time. The method of the present invention comprises: a step of displaying a screen to enable a client member to select one function among a detail writing function, a detail management function of a construction site, and a cost search function for bidding or contracting of a construction work around the world; a step of enabling a client to select a construction site that the client desires when the client selects the detail management function, and displaying a comprehensive management screen for informing the overall state of a corresponding construction site and selecting management items when the client selects the construction site; a step of allowing a server to display various detail statements of a corresponding construction when the client selects expected establishment details, execution establishment details, ES application details, calculation of an ES index rate, calculation of an ES item rate, and resource management in the comprehensive management screen; a step of allowing the server to display various tabulations of the corresponding construction when the client selects various tabulations in the comprehensive management screen; and a step of allowing the server to display various cost accountings, an item rate, and an index rate of the corresponding construction when the client selects various cost accountings, calculation of the item rate, and calculation of the index rate in the comprehensive management screen.

Description

클라우드 기반 온라인 건설현장 관리 방법 및 시스템{ METHOD OF AND SYSTEM FOR ON-LINE CONSTRUCTION MANAGEMENT BASED ON CLOUD }TECHNICAL FIELD [0001] The present invention relates to a cloud-based online construction site management method and system,

본 발명은 건설 현장 관리 기술에 관한 것으로, 더욱 상세하게는 현재의 오프라인 방식인 건설공사의 현장관리 시스템을 클라우드를 기반으로 온라인 웹(On-line Web )방식으로 개발하여 시간에 따라 시시각각 변동되는 많은 건설 데이터 정보를 공유하여 작업자로부터 경영자, 시행자, 감독기관까지 장소나 시간에 관계없이 투명하고, 신속하게, 그리고 효율적으로 건설현장을 관리할 수 있는 클라우드 기반 온라인 건설현장 관리 방법 및 시스템에 관한 것이다.The present invention relates to a construction site management technology, and more particularly, to a construction site management system of a current off-line construction, which is developed based on an on-line web based on a cloud, The present invention relates to a cloud-based on-line construction site management method and system capable of transparently, promptly, and efficiently managing a construction site regardless of a place or time, from a worker to a manager,

일반적으로, 건설공사는 일반 제조업과는 달리 공사작업이 복잡하고 현장중심의 생산방식이며, 단일한 일품 생산형이다. 즉, 건설공사는 발주자의 요구조건과 현장의 위치 및 환경에 따라 고유의 특성이 존재하게 되고, 생산과정에 오랜 시일이 요구되며 반복 재생산이 어려운 특성을 가지고 있다. 이러한 건설공사를 시행하는 절차는 발주자의 성격과 공사의 성질에 따라 달리하고 있으나 직영공사와 도급공사로 구분되고, 도급공사의 경우에는 발주방법에 따라 경쟁입찰계약이나 수의계약방식 등으로 구분된다.Generally, unlike general manufacturing, construction work is complicated and work-oriented production method, and it is a single production type. In other words, the construction has inherent characteristics depending on the requirements of the client, the location of the site and the environment, and it requires a long time in the production process and it is difficult to reproduce it repeatedly. The procedure for carrying out the construction work is divided into the direct construction and the contract work, though it differs according to the nature of the client and the nature of the work. In case of the contract work, it is classified into the competitive bidding contract or the veterinary contract type according to the ordering method.

한편, 건설공사의 일반적인 순서는 발주자가 설계와 적산을 통해 예정가격을 결정한 후 입찰 공고하는 발주단계와, 수주자가 발주자의 요구조건을 검토하여 설계에 따라 적산한 후 견적하는 입찰단계, 낙찰되면 계약한 후 시공하는 시공단계로 이루어진다. On the other hand, the general order of the construction work is the ordering stage in which the buyer determines the planned price through design and integration and then announces the tender, and the bidding stage in which the buyer examines the requirements of the client, And a construction step of constructing after completion.

발주자는 공사계획을 수립한 후 현장실사를 거쳐 설계를 하고, 설계에 따라 공사비용(예정가격)을 산출하기 위한 적산을 하며, 입찰공고한다. 수주자는 수주계획에 따라 입찰공고를 본 후 현장설명과 설계도 및 발주자의 요구사항을 이해하고, 내역입찰의 경우에는 단가를 결정하여 입찰가격을 산정하고 총액입찰의 경우에는 입찰금액을 결정하여 입찰한다. 입찰 후 낙찰되면 발주자와 수주자 사이에는 계약이 체결된다. 내역입찰인 경우에는 입찰시에 제출한 내역입찰서를 계약내역서로 하며 총액입찰인 경우에는 입찰시의 총액금액과 일치하는 내역서를 작성하여 계약내역서로 한다. 수주자는 기성율에 따라 기성내역서에 의해 기성금액을 받고 공사설계변경이 있을 경우에는 내역서를 변경한다. 기간별 생산자물가지수의 변동이나 내역서 품목단가의 변동이 있을 경우는 물가연동제설계변경내역서를 제출한다. 수주자는 자원의 적기 투입을 위하여 자원을 관리하고, 발주자는 공정을 관리감독한다. 공사가 완료되면 각종 검사 후 목적물을 인도하고 계약금액을 정산한다.After establishing the construction plan, the client will make the design through on-site inspection, compile to calculate the construction cost (planned price) according to the design, and announce the tender. The buyer understands the site description, the design and the requirements of the client in view of the bidding announcement according to the order plan. In case of the detail bidding, the bid price is calculated by determining the unit price and in the case of the total bidding, the bid amount is determined and bidded . If the bid is won after the bid, a contract is concluded between the client and the buyer. In the case of a detailed bid, the details of the bid submitted at the time of bidding shall be the contract statement, and in the case of total bidding, the statement shall be made in accordance with the total amount at the time of bidding. The order recipient will receive a preliminary amount based on the preliminary statement according to the preliminary rate and change the statement if there is a change in the design of the construction. If there is a change in the producer price index by period or a change in the unit price of the statement item, submit the statement of change of the price inflation system. The contractor manages resources for timely input of resources, and the contractor manages the process. After the completion of the construction, it will deliver the object after various inspections and settle the contract amount.

이때, 입찰단계에서는 건설단가를 조사하여 내역작성프로그램에 의하여 입찰내역서를 작성하여 입찰을 하게 되고, 계약단계에서는 착공내역서, 공정관리계획서, 자원관리계획서를 제출하고, 시공단계에서는 건설공사의 공기와 품질, 안전 및 원가를 효과적으로 충족시키기 위하여 각종 건설현장의 공사관리가 요구된다. 즉, 건설공사는 시공주체로서의 노무자, 시공대상으로서 재료, 시공수단으로서 기계와 설비라는 3요소에 기술과 자금을 투입하여 수행되고, 이를 관리하기 위한 공사관리는 품질관리와 공정관리, 자원관리, 설계변경관리, 기성관리, 안전관리, 환경관리 등을 포함한다. At the bidding stage, the bidding statement is created by checking the construction unit price and the bidding statement is created by the detailing program. At the contracting stage, the construction schedule, the process control plan and the resource management plan are submitted. Construction management of various construction sites is required to effectively meet quality, safety and cost. In other words, construction work is carried out by inputting technology and funds to laborer as construction subject, material and construction equipment as machinery and equipment, and construction management for quality management, process management, resource management, Design change management, off-the-shelf management, safety management, and environmental management.

그런데 종래의 건설현장 관리는 주로 오프라인(Off-line)으로 관리분야별, 현장별, 업무단위별로 별도로 관리하고 있으므로, 첫째 한 현장의 시공이 완료된 후 건설 데이터(Data)의 온라인(On-line) 관리체계가 형성되어 있지 않아 현장 데이터가 폐기되거나 사장되어 재활용되지 못하는 문제점이 있고, 둘째 현장 내역서의 기성수량의 변경에 자동적으로 연동되는 프로그램이 개발되어 있지 않아 각종 관리를 위해서 관리분야별로 수작업으로 기성수량을 입력해야 하며, 셋째 관리분야별로 별도 프로그램들은 있으나 날짜별 시공수량 및 환율, 물가 지수율, 원가계산서의 간접비 요율, 계약단가의 변동 등의 도급액에 영향을 미치는 변동요소와 자동으로 연동되어 계산되는 통합관리 프로그램이 없고, 넷째 현장의 관리상황을 서류 또는 구두상의 보고체계에 의존하기 때문에 경영자, 감리자, 감독기관, 시행자가 현장관리상태에 대한 확인에 시간이 걸리고 투명성이 부족하며, 다섯째 국내.외의 건설자원 및 공사입찰, 건설공법의 정보가 부족하여 각종 국제입찰에 응찰하는 것이 어렵고 건설공법이나 건설내역서의 제품의 비교선택이 어렵고, 여섯째 공정관리에 의한 자원관리가 되지 않아 적기에 구입하지 못하거나 과다 구입 등의 문제가 생기고, 이로 인한 자원의 관리부실 및 관리비용이 증가하는 문제점이 있다. 그리고 시간과 지역에 따라 변동되는 방대한 수량의 건설단가의 검색을 위해서 검색율과 검색속도가 좋은 검색 프로그램이 필요하지만 현재 오프라인에서 제공되는 단가 데이터는 수량도 적을 뿐 아니라 검색율도 낮다.However, since the conventional construction site management is mainly managed off-line by management field, site, and business unit, after the construction of the first site is completed, on-line management of construction data There is a problem that the site data is discarded or is not recycled because the system is not formed, and second, there is not developed a program that is automatically linked to the change of the existing quantity of the field report, Third, there are separate programs for each management field, but they are automatically calculated and linked with the fluctuation factors affecting the contract amount such as the construction quantity and exchange rate, the price index, the indirect cost rate of the cost statement, Fourth, there is no integrated management program. Because there is a lack of information on domestic and overseas construction resources, construction bids, and construction methods, there is a lack of transparency on the part of management, supervisors, supervisors, It is difficult to select the products in the construction method or construction history, and 6) It is not possible to manage the resources by the process control. Therefore, it can not be purchased in a short period of time and problems such as over-purchase are caused. . In order to search a huge amount of construction cost that varies according to time and area, a search program with a good search rate and a high search speed is required. However, the unit price data provided at the present time is not only low in quantity but also low in search rate.

KRKR 10-2011-004929610-2011-0049296 AA

본 발명은 상기와 같은 문제점을 해결하기 위해 제안된 것으로, 본 발명의 목적은 건설현장 관리를 관리분야별로 별도로 운영하는 오프라인 방식이 아니라 건설현장에서 사용하는 모든 관리분야의 프로그램과 시간과 지역에 따라 변동되는 많은 건설 데이터 정보와 검색 프로그램을 통합하여 온라인으로 제공할 수 있는 클라우드 기반 온라인 건설현장 관리 방법 및 시스템을 제공하는 것이다.SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and an object of the present invention is to provide a method and system for managing construction site management in a management field, The present invention provides a cloud-based on-line construction site management method and system capable of integrating a plurality of varied construction data information and a search program on-line.

따라서 본 발명에 따르면, 건설현장을 운영자가 스스로 온라인(On-line)으로 운영할 수 있도록 하여 첫째, 건설 현장이 종료되면서 사장 또는 폐기되는 많은 건설 데이터 정보와 기술을 상호 공유할 수 있고, 둘째 고가의 관리프로그램이나 단가정보비용, 관리인원 및 관리시간을 절약할 수 있고, 셋째 경영자나 감독기관 또는 시행자가 자사의 관리하에 있는 현장을 현장 ID로 언제 어디서나 건설현장의 관리상황을 확인할 수 있어 투명하고 효율적으로 현장을 관리할 수 있으며, 넷째 국제화시대에 국내.외의 건설자원의 품질 또는 가격의 변동추세나 기술정보를 습득하게 하여 건설목적물의 품질을 높이고, 결과적으로 국가는 물론 모든 건설관련업체로 하여금 건설비용을 절감시켜 수익성을 높일 수 있다.Therefore, according to the present invention, it is possible for an operator to operate a construction site on-line by himself or herself. First, the construction company can share a lot of construction data information and technology, The third manager, supervisor, or enforcer can confirm the management status of the construction site anytime and anywhere with the field ID under his / her management. In the fourth internationalization era, it is possible to acquire the trends and technical information of the quality or price of construction resources in Korea and abroad to improve the quality of construction objects, and as a result, It can increase profitability by reducing construction cost.

상기와 같은 목적을 달성하기 위하여 본 발명의 방법은, 건설현장 데이터를 이용하여 데이터베이스를 구축한 후 건설현장관리를 위한 서버를 구현하여 업체회원이 자신의 단가를 관리하고, 고객회원들에게 웹을 통해 건설현장을 관리할 수 있도록 하는 건설현장관리 방법에 있어서, 상기 서버가 업체나 고객으로부터 회원가입을 요청받으면 소정의 절차에 따라 처리한 후 고객회원에게 입찰이나 도급을 위한 내역작성 기능과, 공사현장의 내역관리 기능, 단가검색기능 중 하나를 선택할 수 있도록 화면을 표시하는 단계; 고객이 상기 내역관리 기능을 선택하면, 고객이 원하는 공사현장을 선택할 수 있도록 하고, 고객이 공사현장을 선택하면, 해당 공사현장의 전체 상황을 알려주고 관리항목을 선택하기 위한 종합관리화면을 표시하는 단계; 고객이 상기 종합관리화면에서 e-작업수량관리를 선택하면, 상기 서버는 공사종류를 선택할 수 있는 기본화면을 표시하고, 고객이 임의의 공사를 선택하면, 상기 서버는 선택된 공사의 선택일에 작업수량과 작업수량 누계를 표시하는 단계; 고객이 상기 종합관리화면에서 예정/실행 기성내역을 선택하면, 상기 서버는 해당 공사의 예정/실행 기성내역을 표시해주는 단계; 고객이 상기 종합관리화면에서 예정/실행 기성집계표를 선택하면, 상기 서버는 해당 공사의 예정/실행 기성집계표를 표시해주는 단계; 및 고객이 상기 종합관리화면에서 예정/실행 기성원가계산서를 선택하면, 상기 서버는 해당 공사의 예정/실행 기성원가계산서를 표시해주는 단계를 구비한 것을 특징으로 한다.In order to achieve the above object, a method of the present invention is a method for constructing a database using construction site data and implementing a server for construction site management, wherein a company member manages his own unit price, The method comprising the steps of: (a) receiving a membership request from a company or a customer and processing the request according to a predetermined procedure; (b) Displaying the screen so that one of the history management function and the unit price search function of the field can be selected; When the customer selects the history management function, the customer is allowed to select a desired construction site, and when the customer selects the construction site, a comprehensive management screen for notifying the entire situation of the construction site and selecting a management item is displayed ; When the customer selects the e-work quantity management on the comprehensive management screen, the server displays a basic screen for selecting the construction type, and when the customer selects an arbitrary construction, Displaying a quantity and a work quantity accumulation; If the customer selects the scheduled / scheduled running history on the comprehensive management screen, the server displays the planned / scheduled running details of the corresponding work; When the customer selects the schedule / execution schedule table on the comprehensive management screen, the server displays a scheduled / execution schedule table of the schedule; And when the customer selects the scheduled / unplanned costing statement on the comprehensive management screen, the server displays the planned / enforced costing statement of the corresponding work.

또한 상기 온라인 건설현장 관리 방법은, 고객이 상기 종합관리화면에서 물가연동 조정내역서를 선택하면, 상기 서버는 해당 공사의 물가연동제(ES) 조정내역서를 표시해주는 단계; 고객이 상기 종합관리화면에서 물가연동제(ES) 조정집계표를 선택하면, 상기 서버는 해당 공사의 물가연동제(ES) 조정집계표를 표시하는 단계; 및 고객이 상기 종합관리화면에서 물가연동제(ES) 조정원가계산서를 선택하면, 상기 서버가 해당 공사의 물가연동제(ES) 조정원가계산서를 표시하는 단계를 더 구비할 수 있다.Further, in the online construction site management method, when a customer selects an inflation-linked adjustment statement in the comprehensive management screen, the server displays an ES adjustment statement of the construction site; When the customer selects an ES adjustment table in the comprehensive management screen, the server displays an ES adjustment table of the construction; And a step of the server displaying an ES adjustment cost statement of the construction when the customer selects the ES adjustment cost statement in the comprehensive management screen.

본 발명에 따르면, 첫째 현장의 건설정보(기술자료 및 건설단가 데이터)의 온라인(On-line) 관리프로그램에 의해 축적된 기술이나 정보를 공유할 수 있어 기술 및 품질향상이 가능하고, 둘째 건설현장의 온라인(On-line) 통합관리로 관리의 효율성을 높일 수 있으며, 셋째 경영자, 시행자 또는 감리감독기관이 현장ID로 건설현장의 현장관리 정보를 온라인(On-line)으로 공유할 수 있어 관리의 투명성을 높일 수 있으며, 현장의 문제점을 신속히 파악하여 대처할 수 있게 한다.According to the present invention, it is possible to share the technology or information accumulated by the on-line management program of the construction information (technical data and construction unit price data) of the first site, (3) On-line management of on-line management information can be shared by the manager, the enforcer, or the supervisory supervisory agency with the site ID. Transparency can be improved, and problems on the spot can be quickly identified and coped with.

또한, 본 발명에 따르면 온라인(On-line)에 의한 세계의 건설정보 공유로 값싸고 질 좋은 자재 또는 노동력에 대한 정보를 알 수 있고, 온라인(On-line) 자원관리 프로그램에 의해 공정관리에 따른 적기의 자원 투입으로 관리비용을 절약할 수 있고 자재 및 인력파동에 대비할 수 있으며, 온라인(On-line) 관리프로그램과 건설단가 정보에 의하여 온라인(On-line)으로 현장 담당자가 쉽게 스스로 운영할 수 있기 때문에 용역비용을 절감하고 관리인원을 절감할 수 있다.In addition, according to the present invention, it is possible to know information about cheap and high quality materials or labor force through on-line sharing of construction information of the world, It is possible to save management cost by inputting the bandit's resources and prepare for material and manpower fluctuation. It can easily operate itself on-line by on-line by on-line management program and construction unit price information. This reduces the cost of service and reduces staffing.

그리고 본 발명에 따르면, 적정 시기에 기성금액의 수령, 적정시기에 공사설계변경 및 물가변동설계변경의 시행을 통하여 자금의 사장을 방지할 수 있고, 모든 나라의 건설 시스템은 유사하므로 국가간, 지역간의 건설 데이터(Data) 정보를 공유할 수 있는 효과가 있다.According to the present invention, it is possible to prevent capital from being purchased through the receipt of a ready amount at a proper timing, a change in construction design and a change in price change design in a timely manner, and the construction systems of all countries are similar, It is possible to share the construction data (Data)

도 1은 본 발명에 따른 클라우드 기반 온라인 건설현장 관리시스템의 전체 구성을 도시한 개략도,
도 2는 도 1에 도시된 응용 서버의 기능 블럭도,
도 3은 본 발명에 따른 온라인 건설현장 관리절차를 도시한 전체 순서도,
도 4는 본 발명에 따른 온라인 입찰/도급 내역서 작성 절차의 순서도,
도 5는 본 발명에 따른 공사현장의 온라인 DB 구축 절차를 도시한 순서도,
도 6은 본 발명에 따른 온라인 내역관리 절차를 도시한 순서도,
도 7은 본 발명에 따른 작업일보 처리절차를 도시한 순서도,
도 8은 본 발명에 따른 단가검색 절차를 도시한 순서도,
도 9는 본 발명에 따른 건설현장의 종합관리화면의 예,
도 10은 본 발명에 따른 건설현장의 관리항목 선택화면의 예,
도 11은 본 발명에 따른 선택된 건설현장의 e-작업일보화면의 예,
도 12는 본 발명에 따른 건설현장의 기성내역서 화면의 예,
도 13은 본 발명에 따른 건설현장의 기성내역서 집계표화면의 예,
도 14는 본 발명에 따른 건설현장의 기성원가계산서 화면의 예,
도 15는 본 발명에 따른 건설현장의 ES조정내역서 화면의 예,
도 16은 본 발명에 따른 건설현장의 ES조정집계표 화면의 예,
도 17은 본 발명에 따른 건설현장의 ES조정원가계산서 화면의 예,
도 18 내지 도 32는 본 발명의 다른 실시예에 따른 화면들의 예.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic diagram showing the overall configuration of a cloud-based online construction site management system according to the present invention;
FIG. 2 is a functional block diagram of the application server shown in FIG. 1,
FIG. 3 is an overall flowchart showing an online construction site management procedure according to the present invention;
FIG. 4 is a flowchart of an online bidding /
5 is a flowchart showing an online DB establishment procedure of a construction site according to the present invention.
6 is a flowchart showing an online history management procedure according to the present invention;
FIG. 7 is a flowchart showing a job daily report process according to the present invention;
FIG. 8 is a flowchart illustrating a unit price search procedure according to the present invention.
9 shows an example of a comprehensive management screen of a construction site according to the present invention,
FIG. 10 is an example of a management item selection screen of a construction site according to the present invention,
11 is an example of an e-work daily report screen of a selected construction site according to the present invention,
FIG. 12 shows an example of a ready-made statement screen of a construction site according to the present invention,
FIG. 13 shows an example of a screen of an integrated schedule list of a construction site according to the present invention,
FIG. 14 is a view showing an example of a screen of a construction site preliminary cost statement according to the present invention,
FIG. 15 is a view showing an example of an ES adjustment statement screen of a construction site according to the present invention,
16 is an example of a screen of an ES adjustment table of a construction site according to the present invention,
17 shows an example of a screen for ES adjustment cost calculation at a construction site according to the present invention,
18 to 32 show examples of screens according to another embodiment of the present invention.

본 발명과 본 발명의 실시에 의해 달성되는 기술적 과제는 다음에서 설명하는 본 발명의 바람직한 실시예들에 의하여 보다 명확해질 것이다. 다음의 실시예들은 단지 본 발명을 설명하기 위하여 예시된 것에 불과하며, 본 발명의 범위를 제한하기 위한 것은 아니다. BRIEF DESCRIPTION OF THE DRAWINGS The above and other objects, features, and advantages of the present invention will become more apparent from the following detailed description of the present invention when taken in conjunction with the accompanying drawings. The following examples are merely illustrative of the present invention and are not intended to limit the scope of the present invention.

도 1은 본 발명에 따른 클라우드 기반 온라인 건설현장 관리시스템의 전체 구성을 도시한 개략도이고, 도 2는 도 1에 도시된 응용 서버의 기능 블럭도이다.FIG. 1 is a schematic diagram showing an overall configuration of a cloud-based on-line construction site management system according to the present invention, and FIG. 2 is a functional block diagram of the application server shown in FIG.

본 발명에 따른 온라인 건설현장 관리시스템은 도 1에 도시된 바와 같이 전세계적인 규모로 재료비, 노무비 등과 같은 건설 단일단가와 건설 일위대가 등과 같은 각종 건설관련 데이터들을 데이터베이스로 구축해 놓고 인터넷(20)을 통해 웹으로 본 발명에 따른 온라인 건설현장관리 서비스를 제공하는 건설현장 관리 서버(10)와, 인터넷(20)을 통해 건설현장 관리 서버(10)에 접속하여 본 발명에 따른 서비스를 이용하기 위한 고객 단말기(30)들과 건설공사에 필요한 각종 항목들의 제품이나 용역을 제공하는 업체단말기(40)들로 이루어진다.As shown in FIG. 1, the on-line construction site management system according to the present invention includes various construction-related data such as a construction single unit price such as material cost, labor cost, A construction site management server 10 for providing an on-line construction site management service according to the present invention through the web, and a client for accessing the construction site management server 10 via the Internet 20 to use the service according to the present invention And terminals 40 for providing products or services of terminals 30 and various items necessary for construction work.

도 1을 참조하면, 건설현장 관리 서버(10)는 세계적인 규모의 재료비, 노무비 등과 같은 건설 데이터를 기록 및 관리하기 위한 데이터 서버(11)와, 본 발명에 따른 건설관리를 위한 각종 절차들을 수행하는 응용 서버(12), 회원을 관리하고 고객과 웹 인터페이스를 담당하는 웹 서버(13), 관리자 터미널(14), 데이터 입력 터미널(15), 운영 터미널(16) 등으로 구성되어 데이터 터미널(15)을 통해 각종 데이터를 입력하고 운영자가 운영 터미널(16)을 통해 운영하며, 관리자가 관리 터미널(14)을 통해 관리할 수 있도록 되어 있다. 1, the construction site management server 10 includes a data server 11 for recording and managing construction data such as material costs and labor costs on a global scale, and a data server 11 for executing various procedures for construction management according to the present invention An application server 12, a web server 13, a manager terminal 14, a data input terminal 15, an operation terminal 16, And the operator can operate the terminal through the operation terminal 16 and manage the terminal through the management terminal 14.

본 발명에 따른 응용 서버(Application server;12)는 도 2에 도시된 바와 같이, 엑셀파일로 된 건설공사의 도급 내역서와 본 발명에 다른 데이터 베이스 상의 내역서를 상호 변환하는 파일 변환부(121)와, 도급 내역서의 세부항목별로 예정작업기간의 입력에 의한 내역서의 항목별, 날짜별로 예정작업의 누계수량의 계산 및 이로 인한 예정금액공정율이 산출되는 예정공정 관리부(122)와, 온라인(On-line) 상의 e-작업일보에 의한 내역 항목별 작업수량의 입력에 의해서 실행금액 공정율이 산출되는 실행공정 관리부(123)와, 월별 건설 데이터(단일단가, 일위대가단가 등 대략 110만 개) 및 내역서의 계산에 필요한 데이터(지수율, 환율 등)의 입력 및 자원 코드(Code) 부여를 처리하는 데이터 입력부(124)와, 데이터 및 환경 변동에 따라 날짜별로 지수조정율 또는 품목조정율이 산출되는 물가변동 설계변경부(125)와, 건설 데이터를 온라인(On-line) 상에서 검색할 수 있도록 하는 단가 검색부(126)와, 온라인 상에서 계산 및 검색속도를 증가시키기 위한 운영 및 관리부(127)와, 데이터 및 내역서 출력을 처리하는 데이터 및 내역서 출력부(128), 입찰내역서를 작성하기 위한 입찰내역작성부(129), 도급내역서를 작성하기 위한 도급내역작성부(130), 내역서의 항목과 단가검색을 이용하여 원가를 자동으로 계산하는 원가계산부(131), 각종 통계를 처리하는 통계처리부(132) 등으로 이루어진다.As shown in FIG. 2, the application server 12 according to the present invention includes a file conversion unit 121 for converting a contract description of construction work made up of an Excel file and a statement on a database according to the present invention, A scheduled process management unit 122 for calculating the cumulative quantity of scheduled work for each item and date of the statement by inputting the scheduled work period for each sub-item in the sub-contract, ), An execution process management unit 123 for calculating the execution amount process rate by inputting the number of work items per item by the e-work daily report on the monthly construction data, a monthly construction data (about 1.01 million units including single unit price, A data input unit 124 for inputting data (exponential rate, exchange rate, etc.) necessary for the calculation of the data and the assignment of a resource code to the data, and an exponent adjustment rate or item adjustment A unit price search unit 126 for enabling construction data to be searched on-line, an operation and management unit (for increasing on-line calculation and search speed) A data and annotator output unit 128 for processing the data and annotation output, a bid history creation unit 129 for creating a bid schedule, a subcontracting detail creating unit 130 for creating a subcontracting statement, A cost calculator 131 for automatically calculating the cost using the item and unit price search, and a statistical processor 132 for processing various statistics.

도 3은 본 발명에 따른 온라인 건설현장 관리절차를 도시한 전체 순서도이고, 도 4는 본 발명에 따른 온라인 입찰/도급 내역서 작성 절차의 순서도, 도 5는 본 발명에 따른 공사현장의 온라인 DB 구축 절차를 도시한 순서도, 도 6은 본 발명에 따른 온라인 내역관리 절차를 도시한 순서도, 도 7은 본 발명에 따른 작업일보 처리절차를 도시한 순서도, 도 8은 본 발명에 따른 단가검색 절차를 도시한 순서도이다.FIG. 3 is a flowchart showing an online construction site management procedure according to the present invention. FIG. 4 is a flowchart of an online bidding / contracting statement creation procedure according to the present invention, FIG. 5 is an online DB construction procedure 6 is a flowchart illustrating an online history management procedure according to the present invention, FIG. 7 is a flowchart illustrating a job daily report processing procedure according to the present invention, and FIG. 8 is a flowchart illustrating a unit price search procedure according to the present invention It is a flowchart.

먼저, 본 발명에 따른 건설현장 관리 프로그램은 공사의 진행에 따라 시공수량이 변동되고, 날짜의 변동에 따라 자원의 단가(가격), 각종 계산 요율, 물가지수율, 환율 등이 변동되므로 이 두 가지의 변동에 따라 공정관리, 기성관리, 자원관리, 공사 설계변경관리, 물가변동 설계변경관리 프로그램 등의 계산 결과가 변동된다. 이러한 현장 관리 프로그램들은 날짜와 시공량이라는 두 가지의 변동요소에 따라 통합되어 유기적으로 관리되어야 하고, 건설공사의 예산수립과 집행, 수익과 비용 계산의 기본이 되고, 소요 자원을 산출하는 데 기본이 되는 각종 내역서를 작성하기 위해서 시간과 지역에 따라 변동하는 건설 데이터(Data)의 가격정보가 구축되고 쉽게 검색할 수 있어야 한다. 이를 위하여 본 발명의 온라인 건설현장 관리시스템은 관리 프로그램의 운영과 건설단가의 관리방식을 현재와 같은 오프라인(Off-line)방식인 관리분야별로 별도로 운영되는 것이 아니라 온라인(On-line) 상에서 통합하여 현장 관리자가 스스로 운영할 수 있도록 개발되어 건설 데이터(Data) 입력관리, 외주입력자관리, 용역작업자관리, 영업관리, 영업자관리, 건설업체관리, 입찰공고관리, 회원관리, 회계관리 프로그램 개발 등을 관리할 수 있도록 된 것이다. 또한 본 발명의 건설현장 관리 시스템은 국제적인 건설단가 및 검색을 위한 해외 건설단가(일위대가단가 포함)의 입력 시스템(System)이 구축되어 있고, 건설용어의 번역을 처리하고, 각종 데이터(Data)와 내역서 출력을 위한 출력프로그램이 구현되어 있으며, 국내.외에서 본 발명에 따른 건설현장 관리시스템을 운영 및 이용할 수 있도록 웹 서버로 구현되어 있다.First, the construction site management program according to the present invention changes the construction quantity according to the progress of the construction, and the unit price (price) of the resources, the various calculation rates, the price index rate, , The calculation results of the process management, the construction management, the resource management, the construction design change management, the price change design change management program, etc. are changed. These site management programs should be integrated and managed organically in accordance with the two factors of change in date and construction quantity, basic budgeting and execution of construction works, calculation of profit and cost, The price information of construction data (Data) that varies according to time and area should be constructed and easily searchable. To this end, the on-line construction site management system of the present invention manages the management program and the management unit cost of the construction program on an on-line basis rather than being separately operated for off-line management fields It is developed to be able to operate by the field manager himself. It is designed to manage construction data (data) input, outsourcer management, service worker management, sales management, sales manager management, construction company management, bid notification management, membership management, It is possible to manage. In addition, the construction site management system of the present invention has an input system (system) for international construction cost and overseas construction cost (including one unit price) for the search, processes the translation of the construction term, And an output program for outputting a statement, and is implemented as a web server so that the construction site management system according to the present invention can be operated and utilized both at home and abroad.

이러한 본 발명의 건설현장 관리 시스템은 바람직하게 웹 운영팀과, 용역팀, 데이터 입력팀, 영업팀, 사용회원 들의 유기적인 협동에 의해 관리 및 운영될 수 있는데, 웹(Web) 운영팀은 공정관리프로그램, e-작업일보, 설계변경관리프로그램, 지수조정율계산프로그램, 품목조정율계산프로그램, 건설Data, 관리자프로그램(영업,용역,입력, 관리, 회계부면)등을 담당하고, 용역팀은 공정(항목별 공정일자 입력), 지수연동제(항목별 지수기호 입력, 항목별 계약일자, 설계변경일자), 품목연동제(항목별 단가 Code연결, 항목별 계약일자, 설계변경일자), 내역서작성(항목별 단가Code입력, 원가계산서 표준용율 입력)등을 담당하며, 데이터 입력팀은 매월 건설단가, 건설업체, 입찰공사정보, 건설현장정보, 건설법령기술자료, e-작업일보(F회원 입력용) 등을 담당한다. 그리고 영업팀은 상담사항, 계약사항, 영업활동상황입력, 지방정보입력을 담당하고, 사용자(회원)는 F회원(건설현장관리), B회원(입찰내역작성, 입찰내역Down), P회원(단가검색), 시공자, 시공감리자, 감독자, 시행자로 구분되며, 관리자는 용역팀(작업자), Data입력팀(입력자), 영업팀(지방영업자), 관리자(회계, 경영팀)로 구분된다.The construction site management system of the present invention can be managed and operated by the organic cooperation of the web operation team, the service team, the data input team, the sales team, and the user members. - It is responsible for job daily report, design change management program, index adjustment rate calculation program, item adjustment rate calculation program, construction data, manager program (sales, service, input, management, accounting) (Contract date, design change date), making a statement (entering unit price code for each item, inputting a unit price code for each item, The data input team is responsible for the construction unit price, construction company, bid construction information, construction site information, construction law technical data, e-job daily report (for F member input) and so on. In addition, the sales team is responsible for the consultation, the contract, the sales activity, and the input of local information. The user (member) is responsible for F member (construction site management), B member The manager is divided into a service team, a data input team, a sales team, and a manager. The manager is a manager, and the manager is a manager.

도 3을 참조하면, 먼저 기본적인 건설 데이터를 이용하여 데이터베이스를 구축하여 건설관리를 위한 서버를 구현한다(S301). 이와 같이 서버가 구축된 후 웹을 통해 건설현장 관리 서비스를 제공하면, 건설관련 제품이나 용역을 판매하는 업체는 업체단말기(40)를 통해 업체회원으로 가입하고, 입찰/도급/공사 내역서를 필요로 하는 공사업체는 고객단말기(30)를 통해 고객회원으로 가입한다(S302). 이때 회원은 사용할 수 있는 구체적인 서비스 내용에 따라 건설현장 관리를 이용할 수 있는 F회원, 입찰관련 서비스를 이용할 수 있는 B회원, 단가검색 서비스를 이용할 수 있는 P회원으로 구분하여 가입할 수 있다.Referring to FIG. 3, a database is constructed using basic construction data to implement a server for construction management (S301). After the server is constructed, if a construction site management service is provided through the web, a company that sells construction related products or services is required to subscribe as a business member through a company terminal 40 and to submit bids / contracts / The construction company joining the customer terminal 30 through the customer terminal 30 (S302). At this time, members can subscribe to F members who can use the construction site management, B members who can use bidding related services, and P members who can use the unit price search service according to the concrete service contents that can be used.

업체회원이 로그인하면, 서버는 업체회원 전용화면을 제공하고, 해당 업체는 관련된 품목의 단가를 등록 및 수정한다. 이에 따라 전 세계적인 규모로 실시간으로 단가를 업데이트할 수 있다(S303~S305). 고객회원이 로그인 하면, 서버는 고객회원 전용화면을 제공하여 원하는 기능을 선택하게 한다(S306~S308). 본 발명에 따르면 고객회원에게 내역서 작성, 현장내역관리, 단가검색 등의 서비스를 제공할 수 있다.When a member logs in, the server provides a screen dedicated to the members of the company, and the company registers and corrects the unit price of the related item. Accordingly, the unit price can be updated in real time on a global scale (S303 to S305). When the customer member logs in, the server provides a customer member exclusive screen to select a desired function (S306 to S308). According to the present invention, it is possible to provide a service such as a statement making, a field history management, and a unit price search to a customer member.

고객회원이 내역작성을 선택하면, 도 4에 도시된 바와 같이 입찰내역서나 도급내역서를 작성할 수 있게 한다. 도 4를 참조하면, 고객회원인 공사업체에서 엑셀파일로 된 기본 내역서를 업로드하면 데이터베이스에 맞는 파일 형태로 파일변환을 한 후 집계표를 생성한다(S401,S402). 이어 집계표와 단가검색을 통해 자동으로 원가계산을 수행한 후 입찰/도급 내역서를 출력하거나 경우에 따라 조정율이 입력되면 조정율에 따라 재계산을 한 후 입찰/도급 내역서를 출력한다(S403~S408).If the customer member selects to create the details, the bidding statement or the contract statement can be created as shown in FIG. Referring to FIG. 4, when a customer who is a customer member uploads a basic statement as an excel file, the system converts the file into a file format suitable for the database and generates an aggregate table (S401, S402). Subsequently, the system automatically performs cost calculation through an aggregate table and a unit price search, and outputs a bid / subliminal statement. If a correction rate is input as the case may be, the bid / sublimation statement is output after the recalculation is performed according to the adjustment rate (S403 to S408).

고객이 최초로 내역관리를 선택하면, 도 5에 도시된 바와 같이 해당 공사현장에 대한 예정공정 내역서를 작성할 수 있게 한다. 도 5를 참조하면, 고객회원인 공사업체에서 엑셀파일로 된 기본 내역서를 업로드하면 데이터베이스에 맞는 파일 형태로 파일변환을 한 후 집계표를 생성한다(S501~S503). 기준일이 입력되면 이어 기준일에 따른 원가계산이 이루어지고, 공사기간이 설정되면 공사기간별로 예정공정 내역서가 생성되어 데이터베이스에 저장된다(S504~S507). 이에 따라 공사현장 관리자나 발주자 등은 웹을 통해 공사현장을 관리할 수 있다.When the customer selects the history management for the first time, it enables to prepare a scheduled process statement for the construction site as shown in FIG. Referring to FIG. 5, when a customer who is a customer member uploads a basic statement as an excel file, the system converts the file into a file format suitable for the database and generates an aggregate table (S501 to S503). When the reference date is inputted, the cost calculation is performed according to the reference date. If the construction period is set, the predetermined process statement is generated for each construction period and stored in the database (S504 to S507). As a result, construction site managers and contractors can manage construction sites through the web.

공사현장이 구축된 후 고객이 내역관리를 선택하면, 도 6에 도시된 바와 같이 고객이 원하는 공사현장의 내역을 관리할 수 있게 하고, 고객이 단가검색을 선택하면 도 8에 도시된 바와 같이 고객이 원하는 품목의 단가를 검색할 수 있게 한다. 도 8을 참조하면, 고객이 품목을 입력한 후 검색을 클릭하면, 이미 입력된 건설 데이터베이스에서 해당 품목의 단가를 검색하여 지역별, 업체별 단가를 출력한다(S801~S804). 단가목록에서 특정업체를 선택하면, 해당 업체와 전자상거래를 할 수 있도록 해당 업체의 전자상거래 사이트로 이동시켜 준다(S805,S80). 이때 업체의 노출 순위(등급)는 업체회원의 등급에 따라 차등적으로 이루어질 수 있다.When the customer selects the history management after the construction site is established, the customer can manage the details of the construction site desired by the customer as shown in FIG. 6. When the customer selects the unit price search, This allows you to search for the unit price of the desired item. Referring to FIG. 8, if the customer clicks the search after inputting the item, the unit price of the item is retrieved from the construction database already input, and the price for each region and company is displayed (S801 to S804). When a specific company is selected from the unit price list, the electronic commerce site is moved to the e-commerce site of the company so that electronic commerce can be performed with the company (S805, S80). In this case, the exposure rank (grade) of the company can be differentiated according to the rating of the company member.

다시 도 6을 참조하면, 먼저 공사현장을 선택한다. 통상 공사현장은 여러 곳에 있을 수 있으므로 관리할 공사현장을 선택한다(S601). 공사현장을 선택하면, 도 9에 도시된 바와 같이 해당 공사현장의 전체 상황을 알려주는 종합관리화면이 나타난다(S902).Referring back to FIG. 6, first, a construction site is selected. Since a construction site may be located in various places, a construction site to be managed is selected (S601). When a construction site is selected, a comprehensive management screen for notifying the entire construction site is displayed as shown in FIG. 9 (S902).

도 9를 참조하면, 종합관리화면에는 기준일과, 공사명, 기준일까지의 예정공정률, 실행공정률, 차이, 지수조정률이 표시되고, e-작업일보, 기성내역, 집계표, 원가계산서, 조정내역서, 조정집계표, 조정원가계산서, 지수율 산정표, 등과 같은 관리항목의 아이콘이 표시된다. 이에 따라 고객은 종합관리화면에서 원하는 관리항목을 선택할 수 있다(S603).9, the comprehensive management screen displays the standard date, the name of the construction site, the planned construction rate up to the reference date, the execution rate, the difference, and the index adjustment ratio, and displays the e-operation daily report, the established report, the tally sheet, the cost statement, , An adjusted cost statement, an exponential rate chart, and the like. Accordingly, the customer can select a desired management item in the comprehensive management screen (S603).

고객이 e-작업일보를 선택하면, 도 10에 도시된 바와 같이 공사종류를 선택할 수 있는 공사현장 관리항목 선택화면을 표시한다(S604,S605). 공사현장 관리항목 선택화면에는 좌측에 건축공사와 토목공사, 설비공사로 분류된 각 공사의 구체적인 공사명이 표시되는데, 도 8의 절차에 따라 임의의 공사를 선택하면, 도 11에 도시된 바와 같이 선택된 공사의 선택일에 대한 e-작업일보를 화면에 표시한다(S501,S502). 도 11을 참조하면, 명칭과 규격, 단위, 수량, 예정금일수량, 예정누계, 실행금일수량, 실행누계 등과 같은 항목의 구체적인 내역이 표시되어 있다.When the customer selects the e-work daily report, a construction site management item selection screen for selecting the construction type as shown in Fig. 10 is displayed (S604, S605). On the construction site management item selection screen, a specific construction name of each construction classified into construction work, civil works, and facility construction is displayed on the left side. If a construction is selected according to the procedure of FIG. 8, The e-work daily report on the selection date of the construction is displayed on the screen (S501, S502). 11, specific details of items such as a name, a specification, a unit, a quantity, a scheduled day number, a scheduled total, a run day number, an execution total, and the like are displayed.

한편, 고객이 종합관리화면에서 기성내역을 선택하면, 도 12에 도시된 바와 같이 선택일에 대해서 명칭, 규격, 단위, 단가, 설계내역, 기성내역, 기성률 등을 표시하고, 기성집계표를 선택하면 도 13에 도시된 바와 같이 선택일에 대한 명칭, 규격, 단위, 설계, 기성, 미성의 집계표를 표시한다(S606~S609). 고객이 종합관리화면에서 기성원가계산서를 선택하면, 도 14에 도시된 바와 같이 선택일에 대해서 비목, 설계금액, 기성금액, 미성금액과 같은 기성원가계산서를 표시한다. 이러한 기성내역이나 기성집계표, 기성원가계산서의 표시화면 양식이나 구조는 하나의 예에 불과한 것이고 다양한 방식으로 표현할 수 있다.On the other hand, if the customer selects the default history in the comprehensive management screen, the name, standard, unit, unit price, design history, ready history, and default rate are displayed for the selection date as shown in FIG. 12, , The name, standard, unit, design, ready-made, and goodness of the selection date are displayed as shown in FIG. 13 (S606 to S609). When the customer selects the preliminary cost statement on the comprehensive management screen, the preliminary cost statement such as the designation amount, the ready amount, and the unspent amount is displayed for the selected date as shown in FIG. The display format or structure of such a ready-made report, the ready-made chart, and the ready-made cost statement is just an example and can be expressed in various ways.

한편, 내역과 집계표, 원가계산서 등은 수주시의 계약에 따라 물가연동제나 품목조정제 등에 따라 조정이 이루어질 수 있는데, 조정된 내역서나 집계표 및 원가계산서 화면의 예는 도 15 내지 도 17에 도시된 바와 같다, 구체적인 화면의 예는 채택된 방식 즉, 물가연동제나 품목조정제 등에 따라 달라질 수 있고, 적용을 위해 지수분류내역서, 물가지수조정율산정표, 품목조정단가산출계산서 등을 필요로한다.On the other hand, the details such as the details, the spreadsheet, and the cost statement can be adjusted according to the contracts at the time of ordering, according to the inflation-linked system or the item adjustment system. Examples of the adjusted statement, the spreadsheet and the cost statement screen are shown in FIGS. 15 to 17 For example, an example of a specific screen may vary depending on the adopted method, that is, the price leveling system or the item adjustment system. For the application, an index classification statement, a price index adjustment rate chart, and an item adjustment cost calculation sheet are required.

또한, 해당공사의 공사의 자원별/기간별투입수량산출을 표시할 수있고, 공사현장의 관리를 보다 용이하게 하기 위하여 건설현장의 예정/실행 기성율 그래프, 지수조정율변동 그래프, 품목조정율변동 그래프, 자원별/기간별투입 그래프, 건설단가의 자원별/기간별변동 그래프 등을 이용하여 각종 현황이나 변동상황을 그래프로 표시할 수 있다.In order to facilitate the management of the construction site, it is possible to display the input quantity calculation by the resource / period of the construction work of the construction site. In order to facilitate the management of the construction site, the schedule / Graphs of various statuses or fluctuations can be displayed using graphs of input by resource / period and graphs of fluctuation of resources / period by period of construction unit price.

이와 같이 본 발명에 따르면 고객이 원하는 공사현장의 각종 내역서를 웹을 통해 실시간으로 관리할 수 있다.As described above, according to the present invention, various statements of a construction site desired by a customer can be managed on the web in real time.

한편, 본 발명에 따른 온라인 건설현장 관리 방법이 적용된 웹 사이트는 다음 표1과 같이 화면들의 순서를 달리하여 제공할 수도 있다.On the other hand, the web sites to which the on-line construction site management method according to the present invention is applied may be provided in different order of the screens as shown in Table 1 below.

구분      division 세부내용   The details 비고         Remarks
업무관리

Business management
종합분석관리  Comprehensive analysis management 도 18  18
작업수량관리  Work Quantity Management 도 19  19 공시정보관리  Disclosure Information Management 도 20  20
예정기성관리

Planned Readiness Management
예정기성 내역서  Upcoming release 도 21  21
예정기성 집계표  Planned Readings 도 22  22 예정기성 원가계산서  Upcoming Costing Statement 도 23  23
실행기성관리

Launch management
실행기성 내역서  Launch Statement 도 24  24
실행기성 집계표  A run-time table 도 25  25 실행기성 원가계산서  Running cost sheet 도 26  26
ES적용관리

ES application management
ES적용 내역서  ES application statement 도 27  27
ES적용 내역 집계표  ES Application Details Sheet 도 28  28 ES적용 원가계산서  ES applied cost statement 도 29  29
지수ES관리

Index ES Management
지수분류 내역서  Index classification statement 도 30  30
지수분류 집계표  Index classification table 도 31  31 지수율산정표  Exponential rate table 도 32  32

상기 표1을 참조하면, 주요관리항목이 업무관리와 예정기성관리, 실행기성관리, ES적용관리, 지수ES관리, 품목ES관리, 건설자원관리로 구분되고, 각 관리항목은 다시 내역서, 집계표, 원가계산서 등으로 구분된다. 이러한 관리항목들은 앞서 설명한 실시예와 동일하나 필요에 따라 제공하는 화면 구성만을 달리한 것이므로 더 이상의 설명은 생략하기로 한다.Referring to Table 1, the main management items are classified into task management, scheduled maintenance, execution management, ES application management, index ES management, item ES management, and construction resource management. Cost accounts, and so on. These management items are the same as the above-described embodiments, but only the screen configuration provided according to the necessity is different, and the further description will be omitted.

이상에서 본 발명은 도면에 도시된 일 실시예를 참고로 설명되었으나, 본 기술분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 것이다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims.

10: 클라우드 기반 온라인 건설현장 관리시스템 11: DB 서버
12: 응용 서버 13: 웹 서버
14: 관리자 터미널 15: 데이터 입력 터미널
16: 운영 터미널 20: 인터넷
30: 고객단말기 40: 업체단말기
10: Cloud-based online construction site management system 11: DB server
12: Application server 13: Web server
14: Manager terminal 15: Data input terminal
16: Operational terminal 20: Internet
30: customer terminal 40: company terminal

Claims (7)

건설현장 데이터를 이용하여 데이터베이스를 구축한 후 건설현장관리를 위한 서버를 구현하여 업체회원이 자신의 단가를 관리하고, 고객회원들에게 웹을 통해 건설현장을 관리할 수 있도록 하는 건설현장관리 방법에 있어서,
상기 서버가 업체나 고객으로부터 회원가입을 요청받으면 소정의 절차에 따라 처리한 후 고객회원에게 입찰이나 도급을 위한 내역작성 기능과, 공사현장의 내역관리 기능, 단가검색기능 중 하나를 선택할 수 있도록 화면을 표시하는 단계;
고객이 상기 내역관리 기능을 선택하면, 고객이 원하는 공사현장을 선택할 수 있도록 하고, 고객이 공사현장을 선택하면, 해당 공사현장의 전체 상황을 알려주고 관리항목을 선택하기 위한 종합관리화면을 표시하는 단계;
고객이 상기 종합관리화면에서 e-작업수량관리를 선택하면, 상기 서버는 공사종류를 선택할 수 있는 기본화면을 표시하고, 고객이 임의의 공사를 선택하면, 상기 서버는 선택된 공사의 선택일에 작업수량과 작업수량 누계를 표시하는 단계;
고객이 상기 종합관리화면에서 예정/실행 기성내역을 선택하면, 상기 서버는 해당 공사의 예정/실행 기성내역을 표시해주는 단계;
고객이 상기 종합관리화면에서 예정/실행 기성집계표를 선택하면, 상기 서버는 해당 공사의 예정/실행 기성집계표를 표시해주는 단계; 및
고객이 상기 종합관리화면에서 예정/실행 기성원가계산서를 선택하면, 상기 서버는 해당 공사의 예정/실행 기성원가계산서를 표시해주는 단계를 구비한 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 방법.
We construct a database using construction site data and build a server for construction site management to manage the unit price of the company member and manage the construction site through the web to customer members. As a result,
When the server receives a request for member registration from a company or a customer, the server processes the request according to a predetermined procedure, and then displays a screen for selecting a function for creating a bidding or contract for the customer member, a history management function of the construction site, ;
When the customer selects the history management function, the customer is allowed to select a desired construction site, and when the customer selects the construction site, a comprehensive management screen for notifying the entire situation of the construction site and selecting a management item is displayed ;
When the customer selects the e-work quantity management on the comprehensive management screen, the server displays a basic screen for selecting the construction type, and when the customer selects an arbitrary construction, Displaying a quantity and a work quantity accumulation;
If the customer selects the scheduled / scheduled running history on the comprehensive management screen, the server displays the planned / scheduled running details of the corresponding work;
When the customer selects the schedule / execution schedule table on the comprehensive management screen, the server displays a scheduled / execution schedule table of the schedule; And
Wherein the server comprises a step of displaying a schedule / execution initial cost statement of the construction when the customer selects the schedule / execution initial cost statement on the comprehensive management screen.
제1항에 있어서, 상기 온라인 건설현장 관리 방법은,
고객이 상기 종합관리화면에서 물가연동 조정내역서를 선택하면, 상기 서버는 해당 공사의 물가연동제(ES) 조정내역서를 표시해주는 단계;
고객이 상기 종합관리화면에서 물가연동제(ES) 조정집계표를 선택하면, 상기 서버는 해당 공사의 물가연동제(ES) 조정집계표를 표시하는 단계; 및
고객이 상기 종합관리화면에서 물가연동제(ES) 조정원가계산서를 선택하면, 상기 서버가 해당 공사의 물가연동제(ES) 조정원가계산서를 표시하는 단계를 더 구비한 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 방법.
The on-line construction site management method according to claim 1,
When the customer selects an inflation-linked adjustment statement in the comprehensive management screen, the server displays an ES adjustment statement of the corresponding construction;
When the customer selects an ES adjustment table in the comprehensive management screen, the server displays an ES adjustment table of the construction; And
The method according to claim 1, further comprising the step of: when the customer selects an ES adjustment costing statement on the comprehensive management screen, the server displays an ES adjustment cost statement of the construction company How to manage.
제2항에 있어서, 상기 조정이 물가연동제(ES) 조정이면,
고객이 상기 종합관리화면에서 물가연동조정내역서를 선택하면, 상기 서버는 해당 공사의 조정된 물가연동조정내역서를 표시해주는 단계; 고객이 상기 종합관리화면에서 물가연동조정집계표를 선택하면, 상기 서버는 해당 공사의 조정된 물가연동조정집계표를 표시하는 단계; 고객이 상기 종합관리화면에서 물가연동조정원가계산서를 선택하면, 상기 서버가 해당 공사의 물가연동하여 조정된 원가계산서를 표시하는 단계; 고객이 상기 종합관리화면에서, 지수분류내역서를 선택하면, 상기 서버가 해당 공사의 지수분류내역서를 표시하는 단계; 고객이 상기 종합관리화면에서, 지수분류집계표를 선택하면, 상기 서버가 해당 공사의 조정된 지수분류집계표를 표시하는 단계; 고객이 상기 종합관리화면에서, 물가지수조정율산정표를 선택하면, 상기 서버가 해당 공사의 조정된 물가지수조정율산정표를 표시하는 단계를 구비한 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 방법.
3. The method according to claim 2, wherein if the adjustment is an adjustment of an inflation rate (ES)
If the customer selects an inflation linked adjustment statement on the comprehensive management screen, the server displays an adjusted inflation adjustment statement of the corresponding construction; If the customer selects an inflation-linked adjustment sheet in the comprehensive management screen, the server displays an adjusted inflation-adjustment sheet of the construction; When the customer selects an inflation-linked adjustment costing statement on the comprehensive management screen, the server displays the adjusted costing statement linked to the price of the construction concerned; When the customer selects an exponent classification statement on the comprehensive management screen, the server displays an exponential classification statement of the construction; When the customer selects an index classification table in the comprehensive management screen, the server displays an adjusted index classification table of the construction; Wherein the server displays an adjusted price index adjustment rate table of the construction when the customer selects the price index adjustment rate table on the comprehensive management screen.
제2항에 있어서, 상기 조정이 품목연동제 조정이면,
고객이 상기 종합관리화면에서 품목조정적용내역서를 선택하면, 상기 서버는 해당 공사의 품목조정내역서를 표시해주는 단계; 고객이 상기 종합관리화면에서 품목조정집계표를 선택하면, 상기 서버는 해당 공사의 품목조정집계표를 표시하는 단계; 고객이 상기 종합관리화면에서 품목조정원가계산서를 선택하면, 상기 서버가 해당 공사의 조정된 품목조정원가계산서를 표시하는 단계; 고객이 상기 종합관리화면에서, 품목조정단가산출계산서를 선택하면, 상기 서버가 해당 공사의 품목조정단가산출계산서를 표시하는 단계; 고객이 상기 종합관리화면에서, 품목조정산출내역서를 선택하면, 상기 서버가 해당 공사의 품목조정산출내역서를 표시하는 단계; 고객이 상기 종합관리화면에서, 품목조정산출내역집계표를 선택하면, 상기 서버가 해당 공사의 품목조정산출내역집계표를 표시하는 단계; 고객이 상기 종합관리화면에서, 품목조정산출원가계산서를 선택하면, 상기 서버가 해당 공사의 품목조정산출원가계산서를 표시하는 단계를 포함하는 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 방법.
3. The method according to claim 2,
When the customer selects the item adjustment application statement on the comprehensive management screen, the server displays the item adjustment statement of the corresponding construction; When the customer selects an item adjustment table on the comprehensive management screen, the server displays an item adjustment table of the corresponding construction; When the customer selects the item adjustment cost statement on the comprehensive management screen, the server displays the adjusted item adjustment cost statement of the corresponding construction; When the customer selects the item adjustment unit price calculation sheet on the comprehensive management screen, the server displays the item adjustment unit price calculation sheet of the corresponding construction; When the customer selects the item adjustment calculation statement on the comprehensive management screen, the server displays the item adjustment calculation statement of the corresponding construction; When the customer selects the item adjustment adjustment calculation list sheet on the comprehensive management screen, the server displays the item adjustment adjustment calculation table of the corresponding construction; Wherein the server displays an item adjustment calculation cost statement of the construction when the customer selects the item adjustment calculation cost statement on the comprehensive management screen.
제1항에 있어서, 상기 온라인 건설현장 관리 방법은,
고객이 상기 종합관리화면에서, 총자원산출서를 선택하면, 상기 서버가 해당 공사의 총자원산출서를 표시하는 단계와, 고객이 상기 종합관리화면에서, 자원별/기간별투입수량산출을 선택하면, 상기 서버가 해당 공사의 자원별/기간별투입수량산출을 표시하는 단계를 더 포함하는 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 방법.
The on-line construction site management method according to claim 1,
Displaying a total resource calculation sheet of the construction by the server when the customer selects the total resource calculation sheet from the comprehensive management screen; and if the customer selects the input quantity calculation by resource / period from the comprehensive management screen, Wherein the server further comprises the step of displaying the input quantity calculation for each resource / period of the construction work.
제1항에 있어서, 상기 온라인 건설현장 관리 방법은,
건설현장의 예정/실행 기성율 그래프, 지수조정율변동 그래프, 품목조정율변동 그래프, 자원별/기간별투입 그래프, 건설단가의 자원별/기간별변동 그래프를 표시하는 단계를 더 구비한 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 방법.
The on-line construction site management method according to claim 1,
The method according to any one of claims 1 to 3, further comprising the step of displaying a graph of a planned / executive rate graph of a construction site, an index adjustment rate fluctuation graph, an item adjustment rate fluctuation graph, an input graph by resource / How to manage an online construction site.
온라인 건설현장 관리시스템은 전세계적인 규모로 재료비, 노무비 등과 같은 건설 단일단가와 건설 일위대가 등과 같은 각종 건설관련 데이터들을 데이터베이스로 구축해 놓고 인터넷(20)을 통해 웹으로 온라인 건설현장관리 서비스를 제공하는 건설현장 관리 서버(10)와, 인터넷(20)을 통해 건설현장 관리 서버(10)에 접속하여 서비스를 이용하기 위한 고객 단말기(30)들과, 건설공사에 필요한 각종 항목들의 제품이나 용역을 제공하는 업체단말기(40)들로 이루어진 건설현장 관리 시스템에 있어서,
상기 건설현장 관리 서버(10)는 세계적인 규모의 재료비, 노무비 등과 같은 건설 데이터를 기록 및 관리하기 위한 데이터 서버(11)와, 본 발명에 따른 건설관리를 위한 각종 절차들을 수행하는 응용 서버(12)와, 회원을 관리하고 고객과 웹 인터페이스를 담당하는 웹 서버(13)로 구성되고,
상기 응용 서버(Application server;12)는 엑셀파일로 된 건설공사의 도급 내역서와 본 발명에 다른 데이터 베이스 상의 내역서를 상호 변환하는 파일 변환부(121)와, 도급 내역서의 세부항목별로 예정작업기간의 입력에 의한 내역서의 항목별, 날짜별로 예정작업의 누계수량의 계산 및 이로 인한 예정금액공정율이 산출되는 예정공정 관리부(122)와, 온라인(On-line) 상의 e-작업일보에 의한 내역 항목별 작업수량의 입력에 의해서 실행금액 공정율이 산출되는 실행공정 관리부(123)와, 월별 건설 데이터(단일단가, 일위대가단가 등 대략 110만 개) 및 내역서의 계산에 필요한 데이터(지수율, 환율 등)의 입력 및 자원 코드(Code) 부여를 처리하는 데이터 입력부(124)와, 데이터 및 환경 변동에 따라 날짜별로 지수조정율 또는 품목조정율이 산출되는 물가변동 설계변경부(125)와, 건설 데이터를 온라인(On-line) 상에서 검색할 수 있도록 하는 단가 검색부(126)와, 온라인 상에서 계산 및 검색속도를 증가시키기 위한 운영 및 관리부(127)와, 데이터 및 내역서 출력을 처리하는 데이터 및 내역서 출력부(128)와, 입찰내역서를 작성하기 위한 입찰내역작성부(129)와, 도급내역서를 작성하기 위한 도급내역작성부(130)와, 내역서의 항목과 단가검색을 이용하여 원가를 자동으로 계산하는 원가계산부(131)와, 각종 통계를 처리하는 통계처리부(132)를 포함하는 것을 특징으로 하는 클라우드 기반 온라인 건설현장 관리 시스템.
On-line construction site management system is constructed on the basis of a database of various construction related data such as construction cost, construction cost, construction cost, etc. such as material cost and labor cost, and provides on-line construction site management service through the Internet through the Internet (20) A construction site management server 10 and a customer terminal 30 connected to the construction site management server 10 via the Internet 20 for using the service and products and services of various items required for construction (40), the system comprising:
The construction site management server 10 includes a data server 11 for recording and managing construction data such as material costs and labor costs on a global scale, an application server 12 for performing various procedures for construction management according to the present invention, And a web server 13 that manages members and takes charge of a web interface with a customer,
The application server 12 includes a file conversion unit 121 for converting contracts of a construction work made up of an Excel file to a statement on a database according to the present invention, A scheduled process management unit 122 for calculating the cumulative quantity of the scheduled work for each item and date of the statement by input and calculating the planned amount of process rate by the calculation, (The number of units such as the unit price, the unit price, etc.) and the data necessary for the calculation of the statement (exponential rate, exchange rate, etc.) A data input unit 124 for inputting an input source code and a resource code and a price change design changing unit 12 for calculating an index adjustment rate or an item adjustment rate on a date- 5), a unit price search unit 126 for enabling construction data to be searched on-line, an operation and management unit 127 for increasing a calculation and a search speed on-line, A bid detail creating unit 129 for creating bid details, a contract detail creating unit 130 for creating a contract detail statement, A cost calculator 131 for automatically calculating a cost, and a statistical processor 132 for processing various statistics.
KR1020160076523A 2016-06-20 2016-06-20 Method of and system for on-line construction management based on cloud KR20170142671A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160076523A KR20170142671A (en) 2016-06-20 2016-06-20 Method of and system for on-line construction management based on cloud

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160076523A KR20170142671A (en) 2016-06-20 2016-06-20 Method of and system for on-line construction management based on cloud

Publications (1)

Publication Number Publication Date
KR20170142671A true KR20170142671A (en) 2017-12-28

Family

ID=60940050

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160076523A KR20170142671A (en) 2016-06-20 2016-06-20 Method of and system for on-line construction management based on cloud

Country Status (1)

Country Link
KR (1) KR20170142671A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101993279B1 (en) * 2018-12-31 2019-06-26 주식회사 나눔건설사업관리 Construction management system for personal housing owner
CN112990532A (en) * 2020-12-26 2021-06-18 广东电网有限责任公司 Power distribution network construction cost accounting system and method
KR102303357B1 (en) * 2020-11-17 2021-09-24 주식회사 퍼스트하우스 System for audit review based remote video chatting
KR20210115249A (en) * 2020-03-12 2021-09-27 주식회사 넥스트코어테크놀로지 3D modeling based worker location management system
CN113469840A (en) * 2021-06-16 2021-10-01 浙江华东建设工程有限公司 Intelligent management system for pile foundation construction
KR20230114390A (en) 2022-01-25 2023-08-01 김지훈 Integrated Management system for vehicles and materials
CN117236880A (en) * 2023-09-06 2023-12-15 河北建筑工程学院 Method and system for whole-process management of construction project contract

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101993279B1 (en) * 2018-12-31 2019-06-26 주식회사 나눔건설사업관리 Construction management system for personal housing owner
KR20210115249A (en) * 2020-03-12 2021-09-27 주식회사 넥스트코어테크놀로지 3D modeling based worker location management system
KR102303357B1 (en) * 2020-11-17 2021-09-24 주식회사 퍼스트하우스 System for audit review based remote video chatting
CN112990532A (en) * 2020-12-26 2021-06-18 广东电网有限责任公司 Power distribution network construction cost accounting system and method
CN113469840A (en) * 2021-06-16 2021-10-01 浙江华东建设工程有限公司 Intelligent management system for pile foundation construction
KR20230114390A (en) 2022-01-25 2023-08-01 김지훈 Integrated Management system for vehicles and materials
CN117236880A (en) * 2023-09-06 2023-12-15 河北建筑工程学院 Method and system for whole-process management of construction project contract

Similar Documents

Publication Publication Date Title
KR20170142671A (en) Method of and system for on-line construction management based on cloud
Safa et al. Supplier selection process in an integrated construction materials management model
Shan et al. Statistical analysis of the effectiveness of management programs in improving construction labor productivity on large industrial projects
CN101256647A (en) Item management system being suitable for garden engineering
Shan et al. The impact of management practices on mechanical construction productivity
AU2019100163A4 (en) Automated building construction project management system
CN113626914A (en) Engineering project management method, device and system based on digital twins
JP2016048543A (en) Project progress state management system and computer program
Ruwanpura et al. Evolution of the i-Booth© onsite information management kiosk
CN111353787A (en) Equipment comprehensive guarantee system based on cloud platform
KR100945523B1 (en) On-line construction management method
US20230245066A1 (en) Computer System and Method for Construction Project Prequalification and Management
Liu et al. A multi-agent-based mould due date setting approach in stochastic production
Dzhusoev et al. Selection of Software Products for the Development of a Calendar Plan for High-Rise Construction
US20230316197A1 (en) Collaborative, multi-user platform for data integration and digital content sharing
ESETOVA et al. Managing the information potential of a construction company in the transition to a digital economy
US20130205224A1 (en) Electronic data plate system for collaboration amongst multiple disparate parties
Wood et al. The effectiveness of the bills of quantities in Australia
JP2014016805A (en) Production plan adjustment support device, production plan adjustment support method, and production plan adjustment support program
US20150120369A1 (en) Chemical and natural resource supply chain advanced planning and forecasting through massively parallel processing of data using a distributed computing environment
Kazaryan et al. Aspects of assessment of the efficiency of using information modeling technology for transport infrastructure by BIM-modeling
Nakagawa Real time performance information system using mobile phone
Ershadi et al. Effective application of information technology tools for real-time project management
CN114066383B (en) Bid management system based on mobile internet technology
Ding et al. Supplier capacity analysis for a manufacturing firm with a case study